power system stability and control - · pdf filepower system stability and control editorial...
TRANSCRIPT
POWER SYSTEM STABILITY AND CONTROL
Editorial Board
Advisor:
Dr. R. Nagaraja
Editor:
M.M. Babu Narayanan
Members:
Faraz Zafar Khan
Poornima T.R.
Venkatesh H.R.
Maheedhar Patnala
Rajesh Kanchan
Thimmappa N.
Inside This Issue
From MD's Desk……………………………………………........…………………..…………......….…. 2
Detailed Case Study to Understand the Concepts of Transient Stability Analysis...……………………………………………………………..…………………………………… R. Nagaraja 4
Low Frequency Oscilla�ons in Power Systems and their Mi�ga�on …….. .......................................................................................................... K.R. Padiyar 13
Enhancing Power System Stability and Control Using Special Protec�on Systems………………………………………………….……..... Nitesh Kumar. D and Faraz Zafar Khan 16
Stability Studies for Industrial Power Systems ............................................................................................................ Maheedhar Patnala and T. Guru Charan Das 20
PRDC Provides LED Ligh�ng Solu�on for the Holy City of Puri ............................. 26
PRDC Annual Day - April 2015 ............................................................................... 27
Our Exper�se in Training ……………………………………………………………….………………... 28
Indian Power Sector Highlights …………………………………………………..…………….…….. 29
About the Authors ................................................................................................ 30
R.N.I No. KARENG/2013/51589
April - September, 2015April - September, 2015April - September, 2015Quarterly NewsletterQuarterly NewsletterQuarterly Newsletter Issues - 2&3Issues - 2&3Volume - 5Volume - 5Issues - 2&3Volume - 5
Page 2Power Research and Development Consultants
Newsletter
From MD's Desk
Dear Friends,
More o�en than not, the electric power
systems are subjected to faults of
various kinds, and hence it is
extremely important for power
engineers to be well-versed with the
stability condi�ons of the power
system. Through this column, I thought
of dwelling upon the various facets of
power system stability and control while
hopefully, readers would get a trea�se
on the specific aspects of transient
stability studies through the technical
ar�cles in this special issue.
An electrical power system comprising
synchronous generators, transmission
& distribu�on network and loads can be
analyzed for its steady state and transient
behaviour. The steady state behaviour of
the power system is fairly well
analyzed and understood as part of
short term and long term planning
studies and also through opera�onal
studies using the load flow program.
Most of the power systems would
perform well during steady state
condi�ons. However, its real behaviour
would be tested while performing
t rans ient stud ies where in the
disturbances are applied to the power
system, similar to subjec�ng oneself to
treadmill test to ascertain the human
heart behaviour.
The interconnected power system is
analogous to a spring - mass problem.
The generators are masses and the
transmission lines behave as springs.
When we excite the spring-mass system
with a disturbance, oscilla�ons are seen
everywhere. The generator which is
close to the disturbance would swing
more and the generator away
from the disturbance would swing less.
Here again, the machine with higher
mechanical iner�a will swing less, while
the machine with lesser iner�a will
swing more. However, all the generators
in the system will swing with respect to
one another.
These types of oscilla�ons in the
electrical system, wherein the electrical
system transients are coupled with the
machine mechanical system dynamics
are cal led e lectro-mechanical
transients. Power system transient
stability program is the tool to analyze
the behaviour of the power system
during large disturbances, wherein the
exc u rs i o n s o f ro t o r a n g l e s o f
synchronous machines are studied with
respect to each other. This type of
studies also reveals varia�ons in
frequency, voltage, line loading etc.
and the response of the associated
control systems like AVR, turbine-
governor, FACTS, HVDC etc. during and
post disturbance periods.
The first and foremost purpose of
transient stability study is to determine
the cri�cal clearing �me following a
three phase fault in the power system.
Cri�cal clearing �me is defined as the
�me within which the fault should be
detected and cleared so that the
associated synchronous machines do not
lose their synchronism. A power system
is said to be secure if the voltage,
frequency and the line loadings are
within the acceptable limits for the
credible system con�ngencies that are
most likely to occur. In line with this
concept, the sta�c system security
assessment is done using the
con�ngency analysis whereas the system
dynamic security assessment is
performed using the transient stability
studies. At �mes, con�ngency analysis
performed using the steady state load
flow analysis may give favourable results,
but a dynamic security assessment will
only reveal the cri�cality of the outage
/ con�ngency. While designing and
se�ng up of a new power plant,
transient stability studies are done to
finalize the combined iner�a constant of
the generator and the turbine, various
control parameters of the AVR and
turbine-governor control systems.
Sensi�vity analysis performed using the
transient stability study iden�fies the
Page 3Power Research and Development Consultants Newsletter
secure, reliable and stable power system.
I thank a l l those who have
contributed to this issue of PRDC
Newsle�er though their technical
ar�cles. I wish all the readers, their family
and friends a happy fes�ve season
ahead.
connected on the grid-side would get
affected. For grid connected CPPs,
transient stability studies are performed
to arrive at the proper se�ngs for the
islanding relays and also devise scheme
for under frequency load shedding or
generator tripping as the case may be,
in case of excess load or surplus
genera�on.
Finally, the importance of stability studies
is emphasized in the context of
protec�ve relay se�ng based on cri�cal
clearing �me for ensuring system
stability. Special protec�ons schemes are
best designed with the help of stability
studies. Also, as a measure of preven�ng
undesirable trippings during power
swings in transmission lines, it is the
general prac�ce to block the distance
relay tripping when the power swing
enters zone 3 or zone 2 and allow the
tripping only when the power swing
enters zone 1. However, the best
prac�ce is to block all the zones for
power swings, as a distance relay should
operate only during the fault condi�on.
A separate out-of-step protec�on
scheme has to be designed to safeguard
the system during unstable power
swings. Stability studies are performed
to determine the out-of-step relay
se�ngs in such cases as well. To
conclude, transient stability study is one
of the important aspects of the power
system studies and u�li�es, industries
and prac�cing engineers should give
adequate emphasis to conduct the
requisite studies to design and operate a
bandwidth of these control parameters
to give best system performance.
Another typical applica�on of the
transient stability study is the analysis
of the behaviour of a cap�ve power
plant (CPP) with its process load
connected through one or two lines to
the U�lity grid. Most of the CPPs are
synchronized with the grid mainly to
support their manufacturing processes
consis�ng of �me-varying or cyclic loads
wherein grid support is essen�al viz.,
arc furnace loads, rolling mills;
processes where no interrup�on of
power is envisaged and cases wherein
grid support provides enough system
strength for star�ng of large motors. In
case of certain grid disturbances or
even failure of grid, the process of
disconnec�ng the CPP from the U�lity
grid is called islanding of the CPP. Grid
islanding scheme consists of a single or
a set of protec�ve relays connected at
the point of islanding (also called point of
common coupling) which will sense the
disturbance in the grid and give a trip
command to the islanding breaker
whenever the set parameters exceeds
the limit. By opening the islanding
breaker, the CPP and CPP side loads are
isolated from the grid for secure
opera�on of CPP with its cri�cal loads.
The load on the grid side will survive if
the grid survives during the islanding.
However, if the U�lity grid collapses
following the disturbance, only part of
the plant load (o�en referred to as non-
cri�cal loads) that was originally
Dr. R. Nagaraja
Managing Director
PRDC, Bangalore
Page 4Power Research and Development Consultants
Newsletter
2. Sample System
To understand the various aspects of
transient stability study, typical steel plant
system shown in figure 1 is considered. The
sample system consists of an industrial plant
having its own cap�ve genera�on. The
industrial plant is connected to the 220 kV
grid though 220 kV double circuit line of
zebra conductor of 100 km length. Cap�ve
generators are of 2x120 MW capacity;
genera�on voltage being at 11 kV and the
genera�on is stepped up to 220 kV using
141.5 MVA genera�ng transformer (GT). Unit
auxiliary transformer (UAT) load at 6.6 kV is
fed by a 16 MVA transformer. UAT load
consists of 6 MW lumped load at 0.9 power
factor and a largest boiler feed pump (BFP)
motor of 3.6 MW ra�ng.
In the transient stability studies, one is
generally interested in the rotor angle swing
whereas in the dynamic stability study, the
performance of the various control func�ons
to bring down the oscilla�ons of different
state variables in the system is studied.
Reference [1] gives the elaborate concept of
the power system stability and control, being
wri�en by a prac�cing power system
engineer. Reference [2] gives the various
aspects of power system stability studies.
This paper is wri�en to help the prac�cing
system study engineers to understand the
concept of stability studies through a typical
case study. Emphasis is given to understand
the physical concept and interpreta�on of
results rather than detailed mathema�cal
analysis.
1. Introduc�on
Electrical power system is one of the most
dynamic and complex human made systems
on earth. Complexity is due to different
voltage levels, amount of power being
handled and the varie�es of equipment
being used. Dynamic is because of the �me
frame and response to system disturbances,
which is several days for energy resource
dynamics and of the order of micro seconds
to nano seconds during fast and very fast
transients in the power system. Power
system stability studies fall under electro-
mechanical oscilla�on studies. These studies
are further classified into transient stability
studies for large disturbances and small
signal stability study or dynamic stability
studies for small disturbances in the system.
Technical Article
Detailed Case Study to Understand the Concepts of Transient Stability AnalysisR. Nagaraja
Figure 1: Sample system to understand the aspects of stability study
Page 5Power Research and Development Consultants Newsletter
and line loadings are within the permissible
limits and about 100 MW of power is being
exported to grid.
4. Transient analysis for typical
case of single machine
connected to infinite bus
Transient stability concepts are be�er
understood through classical representa�on
of all the machines, i.e. constant voltage
behind the transient reactance xd'. The
analysis is similar to single machine
connected to infinite bus, grid being treated
as infinite bus having an equivalent machine
with fault level of about 4000 MVA and large
iner�a constant of 1000 MJ/MVA on 100
MVA base. A three phase to ground fault is
considered at the 220 kV grid bus occurring
at 1 second from the start of the simula�on.
Fault is cleared at 1.1 second (corresponding
to zone 1 fault clearing �me of 5 cycles).
Figure 2 shows the plot of machine terminal
voltage. When the fault occurs at 220 kV grid
bus, voltage at 220 kV grid bus is zero during
the fault and the plant generator terminal
voltage comes down to almost 55%, as the
machine feeds to the fault. Once the fault is
removed, the voltages restore to pre-fault
values.
governor system control blocks are
considered and all relevant data is furnished
in annexure. SVC control block considered is
taken from reference [1] and values are fine
tuned to minimize the oscilla�ons in the
system. SVC control block schema�c and the
transfer func�on parameters are also
furnished in annexure. All the simula�on
studies have been performed using the
MiPower™ so�ware package.
3. Steady state load flow results
For any transient study simula�on, it is
essen�al to define the steady state condi�on
and analyse the load flow problem to
establish the ini�al condi�on to solve the
differen�al equa�ons being used in the
transient problem. Figure 1 also depicts the
base case load flow results. Both the
generators are scheduled to generate 110
MW each, with machine terminal voltage set
at 1 pu. The GT taps are set at 105% to push
the required reac�ve power to the system.
For the load flow condi�on, the average
power of the varying load has been
considered. BFP motors are set to operate at
2% slip. SVC opera�on is not considered for
steady state simula�on. It is seen from the
load flow results, that all the bus voltages
The industrial process load consists of non-
varying power plant auxiliary load and other
clean and firm loads of steel plant and
varying rolling mill load. The fixed load is
distributed at 33 kV through a 220/33 kV,
100 MVA power transformer. The sta�on
auxiliary load is not explicitly shown in the
diagram, as lower voltage buses are not
explicitly depicted in the sample system and
all lower voltage loads are lumped at 33 kV.
The rolling mill load is cyclic in nature having
a cyclic period of 200 seconds. The varying
load is connected at 33 kV through a
dedicated 220/33 kV transformer. While
designing the industrial system, it is always
be�er to segregate the varying load and the
fixed process loads to different transformers,
so that the voltage varia�ons and harmonics
of the varying load do not affect the plant
auxiliary loads. In this case study, the average
power of varying load is 21.75 MW at 0.707
power factor. Figure 1 also shows the MVA
ra�ng of the transformer in the system along
with the percentage impedance value on
transformer MVA ra�ng.
One more important aspect of the industrial
system design is to iden�fy the islanding
breaker with a view to isolate the essen�al
plant load and genera�on from the rest of
the system for severe grid faults. In the
sample system considered, one of the
generators along with the varying load and
grid lines are connected onto the 220 kV grid
side bus. The second generator and the fixed
part of the plant load are connected onto the
220 kV plant side bus. Bus coupler breaker
connects both the 220 kV buses and gets
isolated for severe gird faults/disturbances.
Annexure gives the various data considered
in the sample system. Informa�on given in
the SLD and the data given in annexure is
adequate to re-produce the results using any
power system analysis tool. Sta�c Var
Compensator (SVC) of 100 MVAR is
considered at 33 kV bus of rolling mill load.
IEEE Type 1 excita�on system and turbine Figure 2: Classical representa�on - machine terminal voltage plot for three phase to
ground fault
Page 6Power Research and Development Consultants
Newsletter
ensuring the system stability. In figure 3, area
of the hatched por�on in red colour indicates
the energy available for the rotor angle to
accelerate and the area of the hatched
por�on in green colour indicates the energy
available for the rotor angle to decelerate. As
long as the decelera�ng area is more
compared to accelera�ng area, the system
angular stability is ensured. Cri�cal clearing
�me is defined as the maximum fault
clearing �me, at which the fault should be
isolated in order to ensure the system
angular stability. If the fault is isolated at the
cri�cal clearing �me, area under the
power Pe will suddenly increase and at this
instant it will be more than the mechanical
power Pm. Under this condi�on, machine
speed starts de-accelera�ng and rotor angle
decreases. As power system engineer, one
s h o u l d a p p re c i a t e t h i s b e a u �f u l
phenomenon in-built in our electro-
mechanical system. Fault has occurred
somewhere in the system and the protec�on
system si�ng in the vicinity of the fault has
operated and isolated the fault. At the
machine terminal, without any control
ac�on, the rotor angle which started
increasing automa�cally starts coming down,
It is quite interes�ng to observe as what
happens to machine electrical power output
during the fault. Electrical power output of
the machine is given by the expression,
Wherein, E and V are machine internal and
terminal voltages respec�vely, X is the
reactance of the machine and δ is the angle
between internal and terminal voltages. As
soon as the fault occurs, the terminal voltage
comes down. As the classical machine model
is considered in the study, the internal
voltage E remains the same. However, as
terminal voltage V comes down due to fault,
electrical power output of the machine also
decreases. Figure 3 shows the plot of
generator 1 mechanical power and electrical
power varia�on. Since no turbine governor
effect is considered in this case, the
mechanical power remains constant and
only electrical power varies.
Now, let us look at the machine swing
equa�on, given by the expression,
Wherein, H is the iner�al constant of the
rota�ng masses of the generator, Pm and Pe
are the mechanical and electrical power of
the generator, respec�vely.
During the fault, as electrical power output is
less compared to mechanical power output,
the rotor starts accelera�ng and rotor angle
increases. Figure 4 shows the plot of the
machine swing curve. At 1.1 second, the fault
is removed and hence terminal voltage
restores to its original value (Ref figure 2). By
this �me, the rotor angle δ would have
increased and since sinδ is more now
compared to pre-fault condi�on, electrical
Figure 3: Generator mechanical and electrical power for three phase to ground fault - Classical machine representa�on
Figure 4: Classical representa�on - swing curve plot for three phase to ground fault
Page 7Power Research and Development Consultants Newsletter
Even though the classical representa�on of
the machine with constant voltage behind
the transient reactance xd' is adequate to
understand the basics of power system
transient stability, detailed representa�on of
the machine including the damper winding
effect and field winding effect (sub-transient
model) is adopted to apply the transient
stability problem to prac�cal systems.
Further, if the transient stability simula�on
�me period is less than 1 second and one is
interested only in the first swing of the
machine to conclude on the system stability,
it is generally not required to model the AVR.
However, if the simula�on �me period is
more than 1 second, AVR should be
modelled. Besides, if the simula�on �me
period is more than 3 seconds, it is generally
advised to model the turbine-governor
control system as well. In the transient
stability study, it is assumed that the
abundant steam pressure or water head is
available and therefore, the boiler dynamics
are generally not modelled. In the
subsequent case studies, the sub transient
model of the plant machines is considered
including the AVR and turbine-governor
control system. Grid machine is con�nued to
be represented as classical model.
generator should not trip and to ensure the system stability and stable opera�on, the generator protec�on system should be properly co-ordinated for external faults and generator should be the last one to trip for the external system faults.
5. Sub transient modeling of machine with AVR and Turbine-Governor System
region is equal to the area under the decelera�ng region. This concept is called “Equal Area Criteria”, generally taught and answered in the power system stability class.
It is quite interes�ng to observe what happens to machine frequency, which is indica�ve of the rotor speed. Figure 5 shows the frequency of the generator 1 plo�ed along with the grid generator frequency. As the grid iner�a constant is very high, the generator 1 frequency oscillates with respect to the grid frequency. It is further observed from figure 1 that the generator 1 con�nues to oscillate with respect to the grid machine. The analogy is similar to a table top puppet as shown in figure 6, having ideal spring. The large base is equivalent to the infinite grid and the puppet head is analogous to generator 1. When the puppet head is pushed down and released, it con�nues to oscillate forever, as the spring is ideal. Similar to this, for the single machine connected to infinite bus case, as there is no field winding and damper winding effects as also without the AVR and governor control func�ons, there is no damping to this electro-mechanical system and oscilla�ons con�nue for ever. From figure 5, the �me period of oscilla�on is found to be 0.66 second resul�ng in the natural frequency of oscilla�on of this electro-mechanical system as 1.52 Hz.
It is general prac�ce to observe the machine electrical power output transients ge�ng recorded using the power plant digital control system (DCS), whenever major grid disturbance occurs and power plant trips or when damage occurs to the power plant equipment during the system disturbance. Power plant operators observe at �mes that a 700 MW generator delivers 1200 MW, 62 MW generator delivers 100 MW and perhaps even conclude as 'either DCS is faulty' or 'this high power delivery has resulted in the damage to the system'. However, from figure 3, it is clear that this phenomenon is quiet natural and as soon as the fault is cleared, the electrical power jumps and in the sample system considered, it has touched almost 200 MW, for a 120 MW generator. Further, for any of these momentary transients in the system, the
Figure 5: Generator frequency plot for three phase to ground fault - Classical representa�on
Figure 6: Analogy of single machine connected to
infinite bus
Page 8Power Research and Development Consultants
Newsletter
to slip. If the load torque at the star�ng is
more than the star�ng electrical torque,
motor will not start. Opera�ng point of the
motor is at that s l ip, wherein the
transformer with lower impedance, etc.
should be studied as alterna�ves to arrive at
a suitable op�on. Figure 9 shows the plots of
motor electrical and load torque with respect
Figure 7 shows the plot of the swing curves
when the fault at the grid 220 kV bus is
isolated at 0.l second and in another case, at
0.3 second. In both the cases the system is
stable, even though the angular excursion is
high at the la�er case. It can be found that
the cri�cal clearing �me for the sample
system for the fault at 220 kV grid bus is
around 0.36 second. Most of the grid codes
specify the maximum fault clearing �me, for
which the system should be stable. For
example, in the Indian gird code, it is
specified that for 220 kV faults, the system
should be stable for fault clearing �me of
0.16 second. While performing the transient
stability study for the interconnected system,
the system design should ensure stability for
the specified fault clearing �me. From figure
7, it is observed that even a�er 10 seconds,
the rotor angle con�nues to oscillate, with
low frequency oscilla�on of about 1.5 Hz.
This oscilla�on can be curtailed by judicious
deployment of power system stabilizer (PSS)
in the system. Discussion on the PSS, its
tuning and applica�on are beyond the scope
of this paper. Reference [1] gives the detailed
discussion on PSS.
6. Motor Star�ng
While designing the industrial system, one
should always conduct the motor star�ng
studies to ascertain the extent of voltage dip
while star�ng the largest motor within the
plant, while other motors and loads are s�ll
connected to the same bus at which the
largest sized motor is connected. Figure 8
shows the voltage dip at the 6.6 kV power
plant auxiliary bus, when the 3.6 MW BFP
motor is started. It is assumed that the motor
load torque varies as the square of the motor
speed. It is concluded that the voltage dips to
the extent of 0.91 pu on 6.6 kV base and the
motor star�ng �me is around 5 seconds. If
the voltage dips to less than 0.85 pu or as
specified in the industrial system design
standards, remedial measures like star-delta
star�ng, so� star�ng, resistance star�ng,
auto-transformer star�ng, series capacitor
star�ng, higher ra�ng of the incoming
Figure 7: Detailed model of plant machine - swing curve under stable opera�on
Figure 8: Voltage dip during motor star�ng
Figure 9: Motor electrical and load torques
Page 9Power Research and Development Consultants Newsletter
lines from the grid. The reac�ve power
varia�on is minimized by installing the
dynamic var compensa�ng devices like SVC.
U�lity should ascertain from the system
studies that the transient and steady state
voltage dip & voltage flicker level at the PCC
and current harmonic distor�on limits in the
grid lines are within the acceptable limits as
per the grid code. Even though the ac�ve
power is varying, within the demand block
period of say 15 minutes, industries are
required to maintain the scheduled demand
i.e., either import or export of ac�ve power.
It is quite un-fortunate that at �mes without
knowing the power system behaviour,
u�li�es insist on limi�ng the sudden ac�ve
power varia�on and also curtail the voltage
harmonic limits at PCC. Current harmonic
distor�on can be curtailed by the industry
and voltage harmonic distor�on needs to be
ascertained by the u�lity. As seen in figure 3,
even during system fault, there is sudden
varia�on in the ac�ve power and it cannot
be curtailed. Transient and steady state
voltage dip, frequency varia�on, current
harmonic distor�on limits and the flicker
level are the key parameters to be measured
and controlled, rather than the sudden ac�ve
power varia�on.
generator performance and also opera�on.
Too much frequency varia�on will cause
sha� vibra�on and damage. Most of the
manufactures prescribe that the transient
electrical power varia�on for con�nuous
opera�on should be less than 25% of the
machine ra�ng
4. To determine whether it is possible to
run the cap�ve power plant and the plant
varying load without the grid support
5. To study the requirement of the dynamic
Var compensators like SVC or STATCOM and
designing the ra�ng and control ranges for
the same and
6. To study the system performance
improvement with the installa�on of the SVC
and compute the flicker levels before and
a�er installing the SVC
Figure 10 shows the voltage plot at 33 kV
rolling mill load bus without and with SVC. It
can be seen that with the help of SVC, the
voltage dip is curtailed to a large extent.
Figure 11 gives the voltage plot at 220 kV
bus. It is concluded that with the help of the
SVC, the 220 kV bus voltage varia�on is
within the acceptable limits.
Most of the steel plant loads are �me-
varying in nature and it is not possible to limit
the ac�ve power varia�on on the incoming
electrical torque cuts the load torque. Data
required to model the motor for star�ng
studies are obtained from the no load and
short circuit tests of the motor. When the
mul�ple motors are started at the plant bus
simultaneously, the motor star�ng current
and the star�ng �me may cause the tripping
of the incomer feeder or transformer over
current relay. In such cases, instantaneous
and over current relay se�ngs should be
properly co-ordinated with the motor
star�ng current and the star�ng �me to
avoid the nuisance trippings.
7. Cyclic Load Varia�on
Using the transient/dynamic stability
analysis program, it is also possible to
ascertain the effect of the varying load on the
system performance. Varying loads can be
represented as cyclic loads in most of the
so�ware tools by defining the �me period
and ac�ve and reac�ve power load at
different �me intervals. Rolling mill load
considered in the present case study has the
�me period of 200 seconds. The cyclic load
data is given in annexure. The data pertains
to typical hot strip mill having 5 roughing
passes and 7 finishing stands. Equal �me
interval is considered for each pass and
stand, even though in reality, the �me
interval will vary. The cyclic load varia�on
study is required to ascertain the following:
1. To determine the transient voltage dip at
the point of common coupling (PCC) and
compare this with the acceptable values
prescribed in the u�lity grid code
2. To determine the voltage varia�on at the
plant 33 kV bus and ascertain the effect of
this voltage varia�on on the other loads
3. To determine the voltage, frequency and
power varia�on at the generator terminal to
determine the effect of these on the Figure 10: 33 kV rolling mill bus voltage without and with SVC
Page 10Power Research and Development Consultants
Newsletter
frequency protec�on would operate and
trip both the units, resul�ng in plant
total black out. On sensing the tripping
o f g r id l ines , i f the i s land ing
delay of 1 to 2 seconds and generator under
frequency protec�on limit is generally set at
47.5 Hz with a �me delay of 1 to 2 seconds.
Hence, it is quite certain that generator
6. Grid islanding
For major disturbances in the u�lity, cap�ve
power plant generator along with the
essen�al plant load should be disconnected
and their tripping should be minimized to
avoid total black out in the plant. Design of
the proper grid islanding scheme is done by
performing various transient simula�on
studies and arriving at the proper se�ngs for
the islanding relays and incorpora�ng the
required control func�ons. For the sample
system considered in this paper, whenever a
major grid disturbance occurs, the islanding
breaker trips. CPP unit 1 along with the
essen�al load is always protected from
tripping. If the grid survives, the CPP unit 2
along with the rolling mill load survives and if
grid dies, the CPP unit 2 collapses along with
the rolling mill load.
For the sample system considered, the
importance of segrega�ng one of the power
plants with the essen�al load from that of
the second unit and the varying load is
illustrated by considering a severe fault at the
grid (3 phase bus bar fault at grid bus). As a
consequence of the fault, it is assumed that
both the grid lines trip. Following cases are
simulated:
Case 1: No opera�on of the islanding breaker
and
Case 2: Tripping of the islanding breaker
within the plant Figure 12 shows the CPP
generator terminal voltage for both the
cases. It can be concluded that voltage
recovers and system is secure. However, it is
not just sufficient to look at the voltage plot,
but it is essen�al to observe the frequency
plot. Figure 13 shows the plot of generator 1
frequency for both the cases. In case 1,
machine frequency raises to almost 55 Hz
and in the reverse swing reaches to almost
46 Hz and then se�les at about 50.5 Hz.
Power system engineer without the
protec�on background may conclude that it
is stable opera�on as both voltage and
frequency are finally se�ling. However, it is
important to note that the turbine
mechanical over speed trip is at 55 Hz,
instantaneous and generator over frequency
protec�on is generally at 52.5 Hz with a �me
Figure 11: 220 kV plant bus voltage without and with SVC
Figure 12: Plant generator #1 terminal voltage for grid islanding cases
Figure 13: Frequency of plant generator #1 for grid islanding cases
Page 11Power Research and Development Consultants Newsletter
Turbine & Governor Control Block Data
IEEE Type 1
Droop: 5%, T : 0.1 s, T : 0.03 s, T : 0.4 s1 2 3
K : 0.276 pu, K : 0.324 pu, K : 0.4 pu, 1 3 5
K : 0 pu7
K : 0 pu, K : 0 pu, K : 0 pu, K : 0 pu2 4 6 8
T : 0.26 s, T : 10 s, T : 0.5shp rh ip
Gpup: 0.1, Gpdown: -1, P : 1.05 pu, m ax
P : 0 pumin
AVR Data
IEEE Type 1
Tr: 0.05 s
K : 100, K : -0.05, K : 0.05a e f
Ta: 0.1 s, Te: 0.5 s, Tf: 0.5
Vse1: 0.06, Vse2: 0.3
Vrmax: 1, Vrmin: -1
Efdmax: 2.7, Efdmin: 0
Annexure – System Data
Plant Generator Data – 120MW Rated MVA: 141.5 MVA
Terminal Voltage: 11 kV
Iner�a constant: 3.1 MJ/MVA
X : 1.95 pu, X : 1.84 pud q
X' : 0.22 pu, X' : 0.38 pud q
X" : 0.17 pu, X" : 0.18 pud q
T ': 7.15 s, T ': 2.5 sd0 q0
T ": 0.039 s, T ": 0.15 sd0 q0
Transmission Line L1&L2 Data
Voltage Level: 220 kV
Length: 100 km
Z: 0.0748746+j 0.3992516 ohm/km
B/2: j1.466942e-006mho/km
Grid Data
Voltage Level: 220 kV
Iner�a constant: 1000 MJ/MVA on 100 MVA base
Fault level: 4000 MVA
Source X/R Ra�o: 20
Motor Data
MVA ra�ng: 4.6875
MW ra�ng: 3.6
Voltage ra�ng: 6.6 kV
Stator resistance: 0.00591 pu
Stator reactance: 0.11111 pu
Rotor resistance: 0.02565 pu
Rotor reactance: 0.11111 pu
Magne�zing reactance: 3.98938 pu
Iner�a constant: 1.4881 second
Running slip: 0.02
Star�ng method: Direct On Line (DOL)
Load Torque characteris�c: Propor�onal to square of the speed
breaker also trips within a �me delay of
about 2-3 cycles, generator unit 1 along with
the essen�al plant load survives. From
frequency plot in figure 13, it is concluded
that the generator frequency excursions are
well within the generator over and under
frequency relay se�ngs. On the similar lines,
if there is import of power at the islanding
breaker during the islanding, part of the
loads can be tripped to mi�gate the
overloading of the generator. The under
frequency load shedding se�ng should be
co-ordinated with the generator under
frequency tripping se�ng, so that the load
shedding occurs before the generator
tripping takes place.
9. Conclusions
In this ar�cle, the concept of transient
stability study is explained through a typical
case study. The methodology explained
star�ng from the data requirement, studies
to be performed etc. to the analysis of results
can be used by the beginners of the system
stability studies to move forward from the
usual steady state analysis like load flow to
gain exper�se in power system stability
studies.
10. References
[1.] PrabhaKundur, “Power System Stability and Control”, (Book), Tata McGraw Hill Educa�on, 1994.
[2.] R. Nagaraja, “Power System Stability Studies”, PRDC Newsle�er special issue on 'Power system studies', vol. 2, issue 1-3, January-September 2012, pp 12.
Page 12Power Research and Development Consultants
Newsletter
Table 1:Rolling mill load varia�on data, power factor = 0.707
From -second
To - second Laod in MW Remarks
0 10 0
10 20 10 Roughing pass 1
20 30 0
30 40 15 Roughing pass 2
40 50 0
50 60 20 Roughing pass 3
60 70 0
70 80 25 Roughing pass 4
80 90 0
90 100 30 Roughing pass 5
100 120 0
120 130 35 Finishing stand 1
130 140 45 Finishing stand 2
140 150 55 Finishing stand 3
150 160 65 Finishing stand 4
160 170 55 Finishing stand 5
170 180 45 Finishing stand 6
180 190 35 Finishing stand 7 190 200 0
SVC control Block Schema�c
MiPower Free Programmable Block Realiza�on of SVC control
Page 13Power Research and Development Consultants Newsletter
examples.
2.. Review of PSS
While analog PSS with the input signal based
on the integral of accelera�ng power is
available since eigh�es, the digital PSS
(labelled as PSS 2B) was proposed in the
nine�es. Subsequently, PSS4B was
introduced based on the work carried out at
IREQ, Canada. The advantages are be�er
performance at low frequencies of
oscilla�ons (0.1 -0.8 Hz). Kamwaet al(2005)
claim that in spite of usage of PSS for a long
�me, “ it may s�ll be one of the most
misunderstood and misused pieces of
generator control equipment. Following the
western U.S. interconnec�on blackouts in
1996, was found that key PSS's were either
out of service or poorly tuned. Even today,
a�er these problems have been fixed, large
disturbances tend to induce 0.2 Hz low
frequency oscilla�ons in the grid. In Brazil,
the north-south interconnec�on has given
rise to a new low-frequency inter-area mode
between 0.17 and 0.25 Hz, necessita�ng a
retuning of PSSs throughout the system.
Inter-area oscilla�ons have also been
reported on the UCTE / CENTREL
interconnec�on in Europe, at 0.36, 0.26, and
even 0.19 Hz. The recent 2003 blackout in
eastern Canada and the U.S. was equally
accompanied by severe 0.4-Hz oscilla�ons in
several post-con�ngency stages.”
require special control measures for their
mi�ga�on. Normally, damper(amor�sseur)
windings provided on the generator rotor are
adequate.
Mi�ga�on of local and inter-area modes are
a�empted using Power System Stabilizers
(PSS). PSS using speed or frequency,
electrical power signals have been used.
With sa�sfactory design, they are useful in
damping local mode oscilla�ons. The block
diagram of a PSS is shown in Figure 1.The
input signal to PSS can be derived from
speed, frequency or electrical power.
However, speed and frequency signals can
destabilize the torsional modes of the
turbine generator sha�. The power signal
can cause excessive Var modula�on during
mechanical power changes. Thus, a
composite signal that represents the integral
of accelera�ng power is used in PSS.
The development and applica�on of FACTS
controllers in AC transmission lines has made
it feasible to apply damping controllers in
these power electronic devices. Both shunt
FACTS controllers (SVC and STATCOM) and
series FACTS controllers(TCSC) are being
widely used for control of voltage and power
flow. In addi�on, it is feasible to modulate
the voltage and power flow based on
varia�ons inthe signals derived from local
measurements of voltage and power flow.
The control law and the op�mum loca�on of
these damping controllers can be obtained
from energy concepts, The methodology for
the design of damping controllers based on
FACTS will be presented in the paper with
1. Introduc�on
During normal opera�on of power systems,
the voltages and currents in the transmission
lines remain steady and vary slowly as the
power outputs of generators vary depending
on the changes in the load. The load
varia�ons are assumed to be slow. However,
even in steady state opera�on, there are
small disturbances present due to small,
random changes in the load. If the system is
small signal stable (steady state stable),
the transients due to perturba�ons in the
system decay and do not pose any problem.
However, if the opera�ng point(equilibrium
point) is not stable, then even small
perturba�ons in the system can lead to
spontaneous oscilla�ons that can grow and
lead to loss of synchronism. These
oscilla�ons are normally caused by
oscilla�ons of the generator rotors that have
frequencies in the range of 0.1 to 2.5 Hz. If
there are N generators in the system, the
number of frequencies are (N-1). The
frequencies of oscilla�ons depend on the
loading of generators and system
configura�on. The modes of oscilla�on
having frequencies in the range of 0.8 to 1.8
Hz are labelled as local modes and typically,
small number of generators in a specified
area, par�cipate in these oscilla�ons. The
modes of oscilla�on having frequencies in
the range of 0.1 to 0.5 Hz are labelled as
inter-area modes and several generators,
spread over a large area par�cipate. In
general, it can be said that as the frequency is
reduced, more number of generators
par�cipate. Conversely, less number of
generatorspar�cipate in oscilla�on having
higher frequencies. When only generators in
a power plant par�cipate, the modes of
oscilla�on are called as intra-plant modes.
Typically, the intra-plant modes do not
Technical Article
Low Frequency Oscillationsin Power Systemsand their MitigationK.R. Padiyar
Figure 1: Block diagram of PSS
Page 14Power Research and Development Consultants
Newsletter
the two swing modes, with the controller are:
Th is c lear ly shows the ro le o f the controller in damping Mode 2.With mul�ple controllers there is a need for coordinated control, that is simultaneous tuning of all the control parameters.
5. Shunt FACTS Controller (STATCOM)The damping controller termed as SMC (Supplementary Modula�on Controller) associated with the STATCOM is designed to modulate the reac�ve current injected by the STATCOM. At bus j,
X�� = 0.0450, we get the closed loop e igenva lues for the swing modes , a�er installing the SMC at a STATCOM connected to bus 4 as,
and
The shunt FACTS controllers are not as effec�ve as series FACTS controllers as they are suscep�ble to the phenomenon of “Strong Resonance” or mode-coupling between the swing mode and an exciter mode. This is a generic phenomenon that is also observed in the tuning of PSS.
We have,
and
Figure 2 shows the damping controller for a series FACTS controller that includes a washout circuit. Tm can be chosen as 0.01s.
4. ExampleConsider the 3 machine system shown in Figure 3. The data is essen�ally same as in [4] except for the following m o d i fic a �o n s . A l l g e n e ra t o rs a r e equipped with sta�c exciters with KE = 200, TE = 0.05. A shunt susceptance o f 0 . 5 p u i s p ro v i d e d a t b u s 5 fo r voltage support. The loads are assumed to be constant impedance type and mechanical damping is assumed to be zero.The eigenvalues for the swing modes at the opera�ng point are calculated as,
The tuning of the two parameters associated with a damping controller (G and x��) was done using Sequen�al Linear Programming (SLP) op�miza�on technique to maximize the damping of M o d e 2 s u b j e c t t o t h e f o l l o w i n g constraints: (a) the damping ra�o of all the eigenvalues is greater than 0.02 and (b) the real part of all eigenvalues is less than -0.65. The op�mal values of the
thcontroller parameters are x = 0.3391 and G = 0.2698 for the damping controller in line 5 – 4 of figure 3. The eigenvalues for
3. Energy Based Damping Controllers using FACTSThe low frequency oscilla�ons are due to exchange of the kine�c energy stored in the generator rotors and the magne�c energy stored in the transmission lines. The natural damping arises from the mechanical damping encountered by the rotors and frequency dependent load characteris�cs. By providing a series connected FACTS controller (say, TCSC) in s er ies w i t h a t ra n s mis s io n l in e ( t y p i c a l l y, a �e l i n e b e t we e n t wo coherent groups of generators), it is possible to provide damping of the low frequency oscilla�ons of power flow in the line by modula�ng the capaci�ve reactance injected by the TCSC. The control s ignal is obtained from the difference in frequencies of two buses, one of them is the terminal bus of the line (say, k) and the other, a fic��ous bus such that the reactance between two buses is the sum of the net line reactance and a Thevenin reactance (which can be viewed as a tunable parameter). The increment in the power flow in the line is given by,
Where,B = P / X .k ko k
If we propose a control law given by,
Where,G is the propor�onal gain.k
From the network analogy we have iden�fied the appropriate control signal as,
which can be synthesized from the locally measured quan��es. I f the voltage magnitudes V and V are assumed to be i j
equal to unity and
Figure 2: Damping controller for a series FACTS Controller
Page 15Power Research and Development Consultants Newsletter
6. References
[1] K.R.Padiyar, 'Power System Dynamics-Stability and Control', (Book), Second E d i �o n , B S P u b l i c a �o n s , 2 0 0 2 , Hyderabad
[2] I.Kamwa, R.Grondin and G.Trudel, 'IEEE PSS2B versus PSS4B: The limits of performance of modern power system stabilizers', IEEE Trans. on Power Systems, Vol. 20(2), 2005, pp.903-915
[3] K.R.Padiyar, 'FACTS Controllers in Power Transmission and Distribu�on' (Book) , New Age Interna�onal . Publishers, 2007, New Delhi
[4] P.M.Anderson and A.A. Fouad, 'Power System Control and Stability', (Book), Iowa State University Press, 1977, Ames, U.S.A.
[5] K . R . P a d i y a r a n d H . V . S a i Kumar, ' Inves�ga�ons of strong resonancein mul�-machine power s y s t e m s w i t h S T S T C O M s u p p l e m e n t a r y m o d u l a �o n c o n t r o l l e r ' , I E E E Tra n s . Po w e r Systems, Vol.21(2), 2006, pp.754-762.
Blood dona�on camp in PRDC Blood donors are special people!
Rotary Bangalore –TTK Blood Bank organized a Blood dona�on camp in PRDC on 16th April 2015. In all
there were 45 donors from PRDC, a great contribu�on for a social cause by any standard! Rotary
Bangalore were
so apprecia�ve of the event and even desired to have this as a biennial CSR ac�vity of
PRDC.
Figure 3: A three machine system (Anderson and Fouad)
Page 16Power Research and Development Consultants
Newsletter
3. Sample System
The system under considera�on represents two area systems as shown in Figure 1, with Area 1 being genera�on rich supplying power to Area 2. Area 1 has 2500 MW of genera�on and nearly 1400 MW of load. Area 2 has 2000 MW of genera�on and around 3000 MW of load. Area 2(a) is cri�cal industrial zone requiring high reliability. The addi�onal load in Area 2 is supplied by Area 1 over two 400 kV single circuit lines. In Area 1, the governors of Gen 1, Gen 5 and Gen 9 are considered to be opera�ng in droop mode. The other governors of area 1 are in constant power mode. In area 2, all the governors are considered to be opera�ng in droop mode. MiPowerTM so�ware is u�lized to build the sample system and carrying out transient stability simula�ons [4].
Under the situa�ons when any one of the 400 kV line i.e. Line 1/Line 2 is not available, the two areas become vulnerable to stability problems under the con�ngency of another line outage. The following con�ngencies can be envisaged under which ac�on of SPS will be required to safeguard the study system.
2. Design aspects of SPS
Designing SPS for any system can be divided into various major ac�vi�es such as [2]:
System Study for the considered system
Developing Logical Solu�on
Design and Implementa�on of SPS
Periodic Review and Records
There are many issues which can impact
reliable power system opera�on. However,
the most common issue is typically the
heavily loaded transmission system.
The tripping of heavily loaded line is
o�en seen as the root cause of system
instability [3]. The understanding of this
issue is cri�cal in power community, since it
can lead to poten�al blackout scenarios. This
ar�cle highlights one such scenario on a
sample two area system. It also suggests the
logic to implement SPS in order to safeguard
the system to the extent possible and avoid
system blackout.
1. Overview
Power system protec�on is o�en limited either to equipment protec�on or adjacent faulty equipment in vicinity. The size and complexity of the power system makes it vulnerable and subject to collapse under cri�cal situa�ons such as power conges�on, frequency and voltage viola�ons, power swings, etc. In order to secure wide area opera�ons, different class of protec�on schemes are proposed which are popularly known as Special Protec�on Systems (SPS). Most commonly used protec�on measures for such SPS are genera�on rejec�on, load rejec�on, under frequency load shedding, system separa�on and their combina�on [1]. It is important to note that the response �me and the quantum of load/ genera�on balancing required are key indices for the successful opera�on of SPS.
SPS is intended to safeguard the power grid during un-planned outage (con�ngency) or system opera�ng condi�ons where power demand cannot be met. Implementa�on of such schemes involves many factors such as [2]:
Understanding the need to implement Special Protec�on System
Complete knowledge of the system for which scheme is to be applied
Iden�fying undesired yet possible con�ngency condi�ons
I n fo r m a �o n o f o v e ra l l sy s te m performance and responses through system studies
Detailed design and implementa�on plan for opera�on and restora�on
Reliable communica�on system
Technical Article
Enhancing Power System Stability and Control Using Special Protection SystemsNitesh Kumar. D and Faraz Zafar Khan
Figure 1: Typically two area system considered for study
Page 17Power Research and Development Consultants Newsletter
system.
Further, in order to analyze whether
addi�onal load shedding in area 2 can help
safe guard the system, a case is studied by
tripping around 1500 MW of load in area 2
for case 2. The result of this case is shown in
Figure 6.
It can be inferred that for case 1, 1000 MW
of load shedding in Area 2 is sufficient to
maintain the frequency profile of the system.
However, for case 2 when the second outage
occurs before the system equilibrium is
a�ained following the fault and first outage,
the simple load shedding based approach
may not be adequate to safe guard the
Case 1 – One of the lines (Line 1 or Line 2) is
out of service due to fault or planned
maintenance, which results in complete
transfer of load on the other l ine.
Subsequently the system a�ains a new
steady state opera�on. A few minutes
later the other line is also tripped due to a
fault.
Case 2 - Both the lines i.e. Line 1 & Line 2
are lost in quick succession due some
disturbance. The outage of second line
happens before the system a�ains
new equilibrium point following first
disturbance. The typical disturbance
sequence can be, loss of first line due to
fau l t and the second due to load
encroachment occurring as a result of high
power swings.
The frequency profile of the two islands
for case 1 and case 2 without SPS are
shown in Figure 2 and Figure 3 respec�vely.
It can be observed from Figure 2 and Figure 3
that during either of the case, the system
cannot survive the disturbance and will result
in total blackout of the system. This suggests
the need for special protec�on system which
can act to restore the system to the
maximum extent possible. For this case, SPS
will facilitate taking intelligent decision so as
to maintain load genera�on balance. This
can be implemented in tradi�onal way by
having frequency based relays at selected
loca�ons or by using the modern day Wide
Area Measurement System (WAMS)
technology.
4. Implementa�on of
conven�onal frequency
based scheme
Frequency relays are placed in the Area 1 to
trip around 1000 MW of genera�on at
frequency of 52 Hz. In Area 2, the frequency
relays are placed such that around 100 MW
of load is shed at 48.5 Hz. The frequencies of
the two areas following islanding in the two
cases are shown in Figure 4 and Figure 5
respec�vely.
Figure 2: Frequency of Area 1 and Area 2 for case 1
Figure 3: Frequency of Area 1 and Area 2 for case 2
Figure 4: Frequency of Area 1 and Area 2 for case 1 with simple load shedding scheme
Page 18Power Research and Development Consultants
Newsletter
stability through the detailed analysis of the system for various worst case scenarios. This ar�cle demonstrates simple logic for SPS. However, complex SPS can also be derived for saving the power systems from cri�cal opera�ng condi�ons.
6. Conclusions
The selec�on of SPS is aimed at securing the system as top priority followed by recovery of sub-systems. While designing SPS, it is important to assess the performance of the steady state as well as dynamic/transient
For this case, it can be inferred that the frequency remains below 47 Hz for considerable �me dura�on which will result in tripping of all the generators in the area 2 on under frequency se�ng. Hence it can be observed that with system islanding occurring in case 2, simple frequency based load shedding may not be adequate.
5. Implementa�on of Special
Protec�on System (SPS)
The logic based SPS is designed as shown in
Figure 7. A�er isola�on of Area 1 and Area 2
due to tripping of Line 1 and Line 2, the SPS
scheme will try to save maximum possible
load in the cri�cal Area 2(a) by crea�ng a sub
island. The scheme takes the inputs from
breaker status of Line 1 and Line 2. When the
breaker status of both Line 1 and Line 2 is
high (tripped), a signal will be sent to the
relay of Line 3 to isolate Area 2(a). Also
Signal will be sent to enable the frequency
relay of Area 1, Area 2 and Area 2(a). When
the frequency relays are enabled, tripping of
concerned load or genera�on will occur
when the frequency se�ng of the relay is
crossed.
The results for case 1 and case 2 islanding
with suggested SPS is given in Figure 8 and
Figure 9. For case 1, use of logic based SPS
results in crea�on of sub-island and shedding
of addi�onal load. However, for case 2 the
cri�cal load in Area 2(a) is saved.
In the suggested SPS shown in Figure 7,
addi�onal logic can be included to decide if
the sub-islanding is actually necessary or not.
This can save the extra load shedding which
occurred in Case 1. In all the simula�ons, the
load shedding is carried out in single stage.
However, the load shedding can be divided
into different stages. This will result in
minimum loss of load. The stage wise load
shedding can also be incorporated in the
logic of SPS, which makes the scheme more
effec�ve.
Figure 5: Frequency of Area 1 and Area 2 for case 2 with simple load shedding scheme
Figure 6: Frequency of Area 1 and Area 2 for case 2 with increased load shedding in Area 2
Figure 7: Logic of SPS designed for sample two area system
Page 19Power Research and Development Consultants Newsletter
Protec�ve
Re l ay E n g i n e e rs , Te xa s A & M University, Mar 30 – Apr 1, 2004, pp.1-12.
[3] V.K. Agrawal, R.K. Porwal, Rajesh K u m a r, V i v e k P a n d e y a n d T. Muthukumar, “Deployment of System Protec�on Schemes for Enhancing Reliability of Power System”, Interna�onal Conference on Power System, IIT Madras, Dec 2011, pp. 1-6.
[4] User Manuals, MiPowerTM, 2012.
7. References
[1] P. M . A n d e r s o n a n d B . K . LeReverend, “Industry Experience with Special Protec�on Schemes”, I E E E Tr a n s a c �o n s o n P o w e r Systems, Vol. 11, No. 3, Aug 1996, pp.1166-1179.
[2] VahidMadani, Mark Adamiak and M a n i s h T h a ku r, “ D e s i g n a n d I m p l e m e n t a �o n o f W i d e AreaSpecial Protec�on Schemes”, 5 7 t h A n n u a l C o n fe r e n c e fo r
Also, it can be clearly observed that the damage to the system, in terms of load shed, depends on the response �me.
In fact there is exponen�al rela�onship of damage to the system with respect to the response �me. Design of fast ac�ng SPS could reduce the poten�al deteriora�on of the system in the cri�cal fault condi�ons.
PRDC received order from an interna�onal client “M/s. KhimjiRamdas LLC, Sultanate of Oman” for the supply of Distance relay lab set-up.
Distance Relay Lab-Setup for Oman
Figure 8: Frequency of Area 1 and Area 2 for case 1 with logic based SPS
Figure 9: Frequency of Area 1 and Area 2 for case 2 with logic based SPS
Page 20Power Research and Development Consultants
Newsletter
assessment, find protec�ve device se�ngs, and apply the necessary remedy or enhancement to improve the system stability.
2. Case Study
The stability study is carried out for a steel plant with a combined capacity of 860,000 TPA of Sponge Iron, 300,000 TPA of Steel, and 60,000 TPA of Ferro Alloys and power genera�on facility of 170MW and is interconnected to u�lity at 132 kV level.
A. Network model forconsidera�on
For stability studies, the en�re industrial network from High Voltage (HV) to either Medium Voltage (MV) or Low Voltage (LV) level needs to be modeled for base case load flow and short circuit analysis. Dynamic modeling (sub transient or transient model) of plant cap�ve generators along with automa�c voltage regulators (AVR) & turbine governors need to be carried out. It is not required to model complete grid network for the stability studies, only grid substa�on model with its equivalent short circuit
therefore it is not advisable. For sensing such a condi�on, careful selec�on of islanding relay se�ngs is required. Also a�er islanding, load genera�on balance need to be maintained in the island formed. Thus transient stability study plays a vital role in islanding studies by establishing the CCT for industrial plant generators for external faults.
M/s PRDC has carried out a number of projects rela�ng to stability studies for industrial power systems. The calcula�on of CCT for industrial plant generators for a three phase fault both in u�lity and industrial plant usingMiPower™ so�ware is briefly described in this technical ar�cle.
The MiPower™ transient stability analysis program inves�gates the stability limits of a power system before, during and a�er system changes or disturbances. The program models dynamic characteris�cs of a power system, implements the user-defined events and ac�ons, solves the system network equa�on and machine differen�al equa�ons interac�vely to find out system and machine responses in �me domain with a user defined reference. From these responses, users can determine the system transient behaviour, make stability
1. Introduc�on
Technical Ar�cle Stability Studies for Industrial Power Systems
Maheedhar Patnala and T. Guru Charan Das When an industrial plant with cap�ve power genera�on is connected to u�lity, it may result in stability problems to the cap�ve generators in the plant due to transient disturbances such as three phase faults, loss of genera�on or loss of a large load etc., both in grid and plant. For a given disturbance, the longest fault dura�on which does not result in instability of the generators is referred to as the Cri�cal Clearing Time (CCT). The CCT for the cap�ve generators need to be calculated by conduc�ng transient stability for various disturbances. The most onerous abrupt change is usually a three-phase fault; a three-phase fault causes the power transfer through the line to be reduced to zero from the working condi�on.
During transient disturbances in the industrial plant (internal faults), the faulty sec�on isola�on needs to be carried out by protec�ve relay within CCT so as to avoid instability of the cap�ve generators. Thus transient stability study plays a vital role in relay coordina�on by establishing the CCT for industrial plant generators so as to co-ordinate the relay se�ngs in such a way that the protec�on relay gives the trip signal before cap�ve generators trip or become unstable for internal faults.
During transient disturbances in u�lity (external faults), industrial plant generators have to withstand this major disturbance or should island from gird for a permanent fault. The challenge for islanding system is to island from the grid within the CCT to protect industrial plant generator from tripping or becoming unstable.
Moreover, it has to ensure that the islanding is absolutely necessary i.e. islanding should not take place for every temporary disturbance in the grid. Frequent islanding of the system will reduce the reliability and
Technical Article
Stability Studies for Industrial Power SystemsMaheedharPatnala and T. Guru Charan Das
Figure 1: Network model for simula�ons
Page 21Power Research and Development Consultants Newsletter
protec�ve system opera�ng �me is longer than the CCT of plant generators, system will become unstable.
Remedial Ac�on: The exis�ng protec�on
schemes are modified and a new unit protec�on schemes are recommended so as to isolate the faulty sec�on from the system within CCT of plant generators. Similar methodology is adopted and CCT at different loca�ons in the plant is calculated and is summarized in Table 2. For the corresponding loca�on of fault, the exis�ng protec�on system opera�ng �me is calculated by inspec�ng the exis�ng protec�on schemes and se�ngs. The maximum exis�ng protec�on system opera�ng �me for faults at different loca�ons is calculated and is summarized in Table 2.
bus is 700 ms.
Exis�ng protec�on system opera�ng �me calcula�on: For the corresponding loca�on of fault, exis�ng protec�on
system opera�ng �me is calculated by i n s p e c �n g t h e ex i s�n g p ro te c �o n
schemes and se�ngs.
In present case, the minimum IDMT opera�ng �me of the exis�ng protec�on system (i.e. overcurrent protec�on) for a fault at 33kV plant bus is 800 ms. As the
MVA shall be sufficient to carry out stability studies. For large induc�on machines (MV motors) the detailed dynamic representa�on is needed, however small induc�on machines (LV motors) are represented as a sta�c load (constant power).
B. Transient Stability Analysis
Various simula�on studies have to be conducted to determine the CCT for faults in industrial plant and u�lity. A case study for calcula�on of CCT is illustrated below.
S y s t e m c o n d i �o n : P l a n t c a p �v e generators are synchronized to grid. The plant load, genera�on and import from the grid are shown in the Table 1.
a. Internal Faults:
The transient disturbances with in the industrial plant at any voltage level in the plant are termed as internal faults to the industrial plant.
CCT Calcula�on for internal faults: The first s te p i s to s i m u l ate fo l l o w i n g sequence of the events in the transient stability program of MiPower™ so�ware.
Time t =1.0 s Se�ng a temporary
three phase fault at 33kV Plant Bus.
Time t =1.1 s Fault cleared.
The next step is to itera�vely change the
fault clearing �me and observe the swing curve of the plant generators. The Figures 2 and 3 illustrate the swing curve with different fault clearing �mes. It can be observed that the CCT of the plant generators for a three fault at 33kV plant
Figure 2: Swing curve for TG1, TG2 & TG3 - Fault clearing �me of 700ms
Figure 3: Swing curve for TG1, TG2 & TG3 - Fault clearing �me of 710ms
Page 22Power Research and Development Consultants
Newsletter
Unstable case(s) [i.e. here CASE C] is
iden�fied from the stability analysis and
recommenda�ons are suggested so as to
maintain the stability of plant generators for
internal faults in the plant.
b. External Faults:
The transient disturbances in the u�lity grid
at transmission voltage level termed as
external faults to the industrial plant.
CCT Calcula�on: The following sequences of
the events are simulated in the transient
stability program of MiPower so�ware.
Time t =1.0 s Se�ng a temporary
three phase fault at 132 kV grid bus.
Time t =1.1 s Fault cleared.
The fault clearing �me is itera�vely changed
and the swing curve of the plant generators
is observed for assessing stability of plant
generators. The Figures 4 and 5 illustrate the
swing curve with different fault clearing �me.
It can be observed that CCT of the plant
generators for a three phase fault at grid bus
is 220 ms.
Exis�ng protec�on system opera�ng �me
calcula�on: For the corresponding loca�on
of faults in the u�lity grid, the exis�ng
protec�on system opera�ng �me is
calculated by inspec�ng the exis�ng
protec�on schemes and se�ngs. The
exis�ng protec�on se�ngs of distance
protec�on which is meant to take care for
faults in the u�lity grid are given in below
Table 3.
In present case, the minimum opera�ng
�me of the exis�ng protec�ve system for a
fault at 132kV Grid is 400ms on zone2 of
distance relay. As the protec�ve system
opera�ng �me is longer than the CCT of
plant generators, system will become
unstable.
Remedial Ac�on: New protec�on scheme
with under voltage in conjunc�on with
direc�onal overcurrent (logic and se�ng) is
proposed in the islanding relay so as to
isolate from the fault in the u�lity within CCT
of plant generators. The proposed scheme
(logic & se�ngs) are given in below Table 4.
Table 2:Summary for CCT for internal faults
Case Fault
Loca�on
Bus
voltage
(kV)
Cri�cal Clearing Time (s)
Opera�ng �me of exis�ng
protec�on system (s)
System
stability
CASE A 132kV Power
Plant Bus132 0.21 0.10 Stable
CASE B Auxiliary
Bus 132 0.21 0.10 Stable
CASE C 33kV
Plant
Bus 33 0.70 1.0 Unstable
CASE D 6.6kV Plant Bus
6.6 1.5 1.0 Stable
132kV
Figure 4: Swing curve for TG1, TG2 & TG3 - Fault clearing �me of 220ms
Figure 5: Swing curve for TG1, TG2 & TG3 - Fault clearing �me of 230ms
Page 23Power Research and Development Consultants Newsletter
The above proposed scheme takes care of
islanding of the plant generators in case of
faults in the u�lity only. For disturbances in
the u�lity related to wide fluctua�ons in grid
frequency, frequency based islanding
scheme shall be used and its se�ngs need to
be coordinated with the plant generator
frequency protec�ons. The aspect of
frequency based islanding scheme is detailed
in the next sec�ons.
C. Disturbances in the u�lity
related to wide fluctua�ons in
grid frequency
Any wide fluctua�on in grid frequency for
higher dura�ons of �me will be treated as a
disturbance for which islanding of plant from
u�lity is necessary to avoid tripping of
generators on generator protec�on. The
exis�ng generator protec�on se�ngs are
given below in Table 5.
The frequency based islanding se�ngs are
to be coordinated with the generator
protec�ons and proposed islanding relay
se�ngs are given below in Table 6.
Under Frequency Case for Islanding:
For a frequency disturbance in u�lity where
grid frequency is falling with a rate of (-ve) 0.4
Hz/s, the islanding relay operated on
proposed under frequency scheme and
islanded the plant generators before the
generator under frequency protec�on
operates. The plant generator's frequency
response a�er islanding from u�lity is
illustrated in Figure 6.
Nega�ve dF/dT Case for Islanding: For a
frequency disturbance in u�lity where grid
frequency is falling with a rate of (-ve) 5 Hz/s,
the islanding relay operated on proposed
under frequency &dF/dT scheme and
islanded the plant generators before the
generator under frequency protec�on
operates. The plant generator's frequency
response a�er islanding from u�lity is
illustrated in Figure 7. Figure 6: Frequency response a�er islanding from u�lity on under frequency
Page 24Power Research and Development Consultants
Newsletter
Over Frequency Case for Islanding: For a
frequency disturbance in u�lity where grid
frequency is increasing with a rate of (+ve)
0.4 Hz/s, the islanding relay operated on
proposed over frequency scheme and
islanded the plant generators before the
generator over frequency protec�on
operates. The plant generator's frequency
response a�er islanding from u�lity is
illustrated in Figure 8.Posi�ve dF/dT Case for Islanding: For a
frequency disturbance in u�lity where grid
frequency is increasing at a rate of (+ve) 5
Hz/s, the islanding relay operated on
proposed over frequency & posi�ve dF/dT
scheme and islanded the plant generators
before the generator over frequency
protec�on operates. The plant generator's
frequency response a�er islanding from
u�lity is illustrated in Figure 9.For all the cases of islanding from u�lity
illustrated above, a�er islanding load
shedding is not required as the in-plant
genera�on is always more than the load. It
should be noted that a load shedding is
necessary in case the in-plant load is more
than the genera�on during islanding. In that
case, the islanding se�ngs are to be
coordinated with under frequency based
load shedding and generator under
frequency protec�on.
3. Conclusion For a given disturbance, the longest fault
dura�on which does not result in instability
of the generators is referred as the cri�cal
clearing �me (CCT).The stability studies for industrial power
system are different from stability studies
carried out for transmission system as the
la�er studies deal with only establishing CCT
and checking whether the calculated CCT's
are within the range s�pulated by the grid
standards. Transient stability plays a vital role
in understanding the stability problems of
cap�ve generators when connected to u�lity
grid. The CCT for the cap�ve generators need
to be calculated by conduc�ng transient
stability for various disturbances. The stability
study for industrial power system was
discussed in this ar�cle right from modeling
to the significance of the results.
Figure 7: Frequency response a�er islanding from u�lity on under frequency & nega�ve dF/dT
Figure 8: Frequency response a�er islanding from u�lity on over frequency
Figure 9: Frequency response a�er islanding from u�lity on over frequency & posi�ve dF/dT
Page 25Power Research and Development Consultants Newsletter
Events & AchievementsThe en�re industrial network from high
voltage (HV) to either Medium Voltage (MV)
or Low Voltage (LV) level needs to be
modeled and it is not required to model
complete grid network for the stability
studies; only grid substa�on model with its
equivalent short circuit MVA shall be
sufficient to carry out stability studies for
industrial power system.
It should be noted that a par�cular type of
solu�on suggested in one plant need not be
applicable for a different plant. Various
simula�on studies need to be conducted for
internal & external faults and CCT of the
cap�ve generators needs to be established
for faults at different loca�ons and
condi�ons. The complexity involves in
iden�fying unstable cases, and then in
revisi�ng the exis�ng protec�on schemes in
order to recommend new protec�on
schemes or modifica�on of exis�ng
protec�on scheme based on the outcome of
CCT based stability studies and the analysis
of lacunae in the exis�ng protec�on system.
4. References
[1] P ra b h a Ku n d u r, ' Po w e r Sy ste m Stabilityand Control' (Book), McGraw Hill Educa�on, 1994
[2] Central Electricity Authority, 'Manual On Transmission Planning Criteria', June 2013, New Delhi.
[3] Central Board of Irriga�on and Power, India, 'Manual On Protec�on Of Generators, Generator transformers And 220kV And 400 kV Networks', Publica�on No. 274, November 1999.
Page 26Power Research and Development Consultants
Newsletter
LED ligh�ng system at Alarnath Temple.
Replacement of exis�ng conven�onal
lights by LED fixtures along Grand Road
and Lord Jagannath temple surrounding.
Some of the important areas of Puri city
covered under the scheme are:
High Mast LED ligh�ng at Grand Road
where three chariots move all along
during RathYatra.
High mast and street ligh�ng system at
famous Sea Beach where almost
thousands of visitors gather every day.
Street Ligh�ng system along Puri - Konark
Marine drive.
PRDC has emerged as one of the major
u�lity consul�ng firms in India in providing
LED ligh�ng solu�ons using modern tools.
The company has provided LED ligh�ng
solu�on for six important areas of the Holy
city of Puri in Odisha. The responsibility of
PRDC included survey, design, prepara�on of
tender specifica�on, tender evalua�on, GTP
and drawings approval and supervision
during execu�on of work. Overall project
cost for LED ligh�ng scheme is Rs. 12 Crores.
PRDC being PMC for all the ligh�ng projects,
was responsible for ensuring quality job and
�mely comple�on.
LED ligh�ng is one of the revolu�onary
technologies over conven�onal ligh�ng
system in the recent years. It is widely
accepted due to its many advantages
such as long life �me, energy efficiency,
eco-friendliness, dimmability, instant ligh�ng
capability etc. Also, it has been proved that
LED ligh�ng is one of the best energy saving
drives accepted across the globe.
Apart from the LED Ligh�ng scheme, PRDC
was also entrusted by the Government of
Odisha to prepare the DPR for developing a
robust electrical distribu�on system to
provide uninterrupted power supply in Puri
city. During the world famous Nabakalebar
fes�val of Lord Jagannath, there is almost 30
lakhs foot fall of pilgrims in the holy city to
witness the grand event.
For the LED Ligh�ng scheme in Puri city,
more than 837 nos. of 80 wa�s, 300nos. of
160 wa�s and 340 nos. of 280 wa�s of LED
fixtures were used in 97 High mast towers as
well as street light poles. The ligh�ng designs
were carried out as per applicable IS and IEC
standards with the help of ligh�ng so�ware
tools. Fi�ngs and high mast poles were from
reputed suppliers.
PRDC Provides LED Lighting Solution for the Holy City of Puri
Figure 1: High mast LED lights at the Lord Jagannath Temple entrance
Figure 2: Puri Sea Beach LED Ligh�ng
Page 27Power Research and Development Consultants Newsletter
PRDC Annual Day - April 2015
Page 28Power Research and Development Consultants
Newsletter
At PRDC, we conduct various training
programmes throughout the year. The
dura�on of the training programme
varies from one to four weeks.
One Week Training
W e c o n d u c t o n e w e e k t r a i n i n g
p ro g ra m m e o n M i Po w e r ™ . I t i s a
standard course.
MiPower Training Level 1
Level 1 is a training programme on basic
theory & simple problems (hands - on).
Level 1 Batch:
16thNovember to 20thNovember 2015
MiPower Training Level 2
Level 2 is a training programme which
consists of only hands-on and solving
own system problems, sor�ng out issues
and clarifica�ons.+
Level 2 Batch:
14thDecember to 18thDecember 2015
Short Term Training /Workshop
In addi�on to the above said programme
PRDC is also conduc�ng short term
training program and workshops to
i m p a r t k n o w l e d g e a n d p r a c �c a l
approach on specific topics, which are of
relevance to power engineers in day-to-
day works . Such t ra in ing not on ly
enhances their knowledge but also helps
to implement these techniques in their
rou�ne works. For short term and special
training programme, please contact our
marke�ng team at the following address:
marke�[email protected]
Our Expertise in Training
Upcoming Events
Page 29Power Research and Development Consultants Newsletter
supply business) in the power sector by introducing mul�ple supply licensees so as to bring in further compe��on and efficiency in the distribu�on sector by giving choice to the consumers.
Source: pib.nic.in
Na�onal Smart Grid Mission
Government has approved the Na�onal Smart Grid Mission (NSGM) -an ins�tu�onal mechanism for planning, monitoring and implementa�on of policies and programs related to Smart Grid ac�vi�es. The total outlay for NSGM ac�vi�es for 12th Plan is Rs 980 crore with a budgetary support of Rs 338 crore. The major ac�vi�es envisaged under NSGM are development of smart grid, development of micro grids, consumer engagements and training & capacity building etc. NSGM entails implementa�on of a smart electrical grid based on state-of-the art technology in the fields of automa�on, communica�on and IT systems that can monitor and control power flows from points of genera�on to points of consump�on.
Source: pib.nic.in
India's solar installa�ons set to quadruple in two years
According to the Ministry of New and Renewable Energy (MNRE), India has installed solar capacity of 4,262 MW, of which 518 MW were built in the current financial year. MNRE expects 4,345 MW of fresh capacity to come up in 2015-16 (including the 518 MW achieved so far.) Further, going by the bids on the anvil, the government expects to add 10,859 MW in 2016-17 alone. The numbers add up to close to 19,000 MW by March 2017 compared with the previous target of 20,000 MW by 2022.
Source: Business line
Amendments to the Electricity Act
The Union Cabinet has approved the proposals for amendment in Electricity Act, 2003 on 10th December, 2014 as contained in the Electricity (Amendment) Bill 2014. The Electricity (Amendment) Bill, 2014 was introduced in the Lok Sabha on 19th December, 2014. This was referred to Parliamentary Standing Commi�ee on Energy and the commi�ee has submi�ed its report to the Parliament on 7th May, 2015. The amendments proposed in Electricity (Amendment) Bill, 2014 seeks to end the monopoly of power distribu�on companies by segrega�ng the carriage (distribu�on sector/network) from the content (electricity
Power Policy
The Government has revised the Na�onal Solar Mission target of Grid Connected Solar Power projects from 20,000 MW to 1,00,000 MW by 2022. The revised Na�onal Solar Mission is under implementa�on.
The Union Ministerof State (IC) forPower, Coal, New & Renewable Energy stated that the it is planned to achieve the revised target of 1,00,000 MW by se�ng up Distributed Roo�op Solar Projects and Medium & Large Scale Solar Projects, the break-up of which is is given in the Table.
Source: pib.nic.in
Na�onal Clean Energy Fund
In the year 2014-15, an amount of Rs 16,388.81 crore has been collected as coal cess for Na�onal Clean Energy Fund (NCEF). As per the budget es�mates, during 2015-16 an amount of Rs 13,118.04 crore will be collected as coal cess for NCEF. Na�onal Clean Energy Fund (NCEF) is created for funding research and innova�ve projects in clean energy technologies. Out of 44 projects recommended for NCEF support in renewable energy, 30 projects are awai�ng alloca�on of fund.
Source: pib.nic.in
Indian Power Sector Highlights
Page 30Power Research and Development Consultants
Newsletter
Dr. R. Nagaraja is the founder and Managing
Director of M/s. Power Research &
Development Consultants Pvt. Ltd.,
Bangalore- one of the reputed Power System
Consultants in the country.
R. Nagaraja has done his B.E. in Electrical and
Electronics Engineering from Mysore
University (India) in 1986. He obtained his
M.E in 1988, specialized in Computer
Applica�ons to Power System and Drives
and Ph.D. Degree in the field of Energy
Management System from Indian Ins�tute of
Science (IISc). His specializa�ons are Power
System Analysis, Simula�on, Power
Engineering Educa�on and Power System
Protec�on. Dr. Nagaraja has authored several
technical papers and conducted a number of
workshops / conferences / seminars
throughout the country.
Dr. Nagaraja is the brain behind the
architecture, design and development of the
MiPower™ – Power system analysis so�ware
package widely used by Electric u�li�es,
Industries, Consultants and Engineering
colleges. Dr. Nagaraja has been involved in
the planning studies of State U�li�es and
Industries in India and abroad.
Prof K.R. Padiyar is associated with Indian
Ins�tute of Science, Bangalore since 1987,
where he is currently an Honorary Professor
in the Department of Electrical Engineering.
Prior to joining IISc, he was with Indian
Ins�tute of Technology, Kanpur. He obtained
M.E degree in 1964 from IISc and Ph.D
degree from University of Waterloo, Canada
in 1972. He has taught and lectured at
various Universi�es in Canada and USA.
He has authored over 200 papers and 4
Books including 'Power system dynamics,
stability and control'. His research interest are
in the areas of HVDC and FACTS, power
system stability and control. He was a
member of the Review commi�ee on the
Na�onal HVDC project. He is the recipient
of 1999 Prof. Rustom Choksi award for
excellence in research. He was ABB chair
professor (2001-03). He is fellow of Indian
na�onal academy of Engineering.
Faraz Zafar Khan is presently working as
Senior Engineer in Power Research and
Development Consultants Pvt. Ltd. He is also
pursuing his PhD under VTU in the research
area of “Advanced Protec�on and Analysis
Schemes for Transmission System”. He
completed M-Tech in Power system from
VNIT, Nagpur.
About the Authors
Dr. R. Nagaraja Prof K. R. Padiyar Faraz Zafar Khan
Nitesh Kumar D is presently working
as Engineer in Power Research and
Development Consultants Pvt. Ltd. He
completed BE in Electrical and Electronics
Engineering from VTU and is presently
pursuing M.Sc (Engg.) by research under VTU
in the research area of generator protec�on
enhancement. His area of interest includes
power system stability, automa�on &
control, Power system protec�on and PMU
applica�on.
Nitesh Kumar D
Page 31Power Research and Development Consultants Newsletter
T. Guru Charan Das obtained his
gradua�on in Electrical Engineering from
Dayalbagh University in 1997. Therea�er, he
began his career as GET in DCM Shriram
group of Industries. His ini�al role was in
power plant opera�on and maintenance.
During this associa�on for 9 years he has
gained insights into power genera�on,
distribu�on and u�liza�on in Cement plants,
Fer�lizer plants, PVC plants, Tex�le plants,
Sugar plants, Dis�lleries and other chemical
processes and industries.
He then joined Bajaj group of industries in
2006 to look a�er Power plant projects and
BoP Engineering. He has successfully
contributed in adding 450 MW power
genera�ons to the group. His role involved
technical, commercial and project
management aspects of the Power projects.
His associa�on with PRDC began in 2010 and
is presently working as DGM-Power System
Consul�ng. He has 19 years of experience
and his area of interest is in Power Plant
engineering, Energy management, Industrial
plants and their related issues with Electrical
Power Systems' applica�on and opera�on
Maheedhar Patnala obtained B.Tech
(Electrical & Electronics) in 2003 and M.Tech
(Power Systems) in 2006 from Kaka�ya
University, Kothagudem and NIT, Warangal
respec�vely. His areas of interest include
power system simula�on studies especially
transient stability studies for industrial plant.
He joined in ABB Limited in 2006 as
Engineer-Consul�ng Department and then
joined in PRDC in 2012 as Team Lead-PSS
department. From 2006, he executed various
projects in the field of power system
Studies for industrial plant involving Load
flow & Short circuit analysis, Transient
stability analysis, Harmonic analysis, Islanding
and load shedding and relay coordina�on
studies.
T. Guru Charan Das Maheedhar Patnala
R.N.I No. KARENG/2013/51589
Printed & Published by : Dr. R. Nagaraja on behalf of Power Research & Development Consultants Pvt. Ltd.Printed at : M/s. Art Print, Dr. Modi Hospital Main, WOC Road, Bengaluru - 560 086. Cell : 98452 33516. Editor : M.M. Babu Narayanan
Power Research & Development Consultants Pvt. Ltd.# 5, 11th Cross, 2nd Stage, West of Chord Road,
Bengaluru - 560086. INDIA. Phone : (080) 4245 5555 / 2319 2209Website : www.prdcinfotech.com
[email protected] feedback and subscription, please reach us at