power system protection coordination studies at gas ...utpedia.utp.edu.my/7992/1/2009 - power system...

67
Power System Protection Coordination Studies at Gas Processing Plant B (GPPB), PETRONAS Gas Berhad (PGB), Paka By SITI FATHIMAH BT HARUN DISSERTATION REPORT Submitted to the Electrical & Electronics Engineering Programme in Partial Fulfillment of the Requirements for the Degree Bachelor of Engineering (Hons) (Electrical & Electronics Engineering) Universiti Teknologi Petronas Bandar Seri Iskandar 31750 Tronoh Perak Darul Ridzuan © Copyright 2009 by Siti Fathimah Harun, 2009

Upload: others

Post on 08-May-2020

23 views

Category:

Documents


4 download

TRANSCRIPT

Power System Protection Coordination Studies at Gas Processing Plant B (GPPB),

PETRONAS Gas Berhad (PGB), Paka

By

SITI FATHIMAH BT HARUN

DISSERTATION REPORT

Submitted to the Electrical & Electronics Engineering Programme

in Partial Fulfillment of the Requirements

for the Degree

Bachelor of Engineering (Hons)

(Electrical & Electronics Engineering)

Universiti Teknologi Petronas

Bandar Seri Iskandar

31750 Tronoh

Perak Darul Ridzuan

© Copyright 2009

by Siti Fathimah Harun, 2009

Approved:

CERTIFICATION OF APPROVAL

Power System Protection Coordination Studies at Gas Processing Plant B (GPPB),

PETRONAS Gas Berhad (PGB), Paka

by

Siti Fathimah Bt Harun

A project dissertation submitted to the

Electrical & Electronics Engineering Programme

Universiti Teknologi PE1RONAS

in partial fulfillment of the requirement for the

Bachelor of Engineering (Hons)

(Electrical & Electronics Engineering)

Ir. Mohd Faris Bin Abdullah

Project Supervisor

UNIVERSITI TEKNOLOGI PETRONAS

TRONOH, PERAK

December 2009

ii

CERTIFICATION OF ORIGINALITY

This is to certify that I am responsible for the work submitted in this project, that the

original work is my own except as specified in the references and

acknowledgements, and that the original work contained herein have not been

undertaken or done by unspecified sources or persons.

Siti Fathimah Bt Harun

iii

ABSTRACT

Power system protection coordination is a study on protection for power

system from any fault such as overcurrent, earthfaulth or any abnormal system

operating condition that can cause failure to the systems component for example

transformer, generator and transmission line. If any faults occur, the protection

devices will recognize faults and initiate action to clear the fault from the system. In

Gas Processing Plant B (GPPB), the protection system is an important part to take

care but sometimes for some reason, the protection system is not work as what we

want, therefore the studies on this project will be help the company to improve the

current protection systems. This study is based on some characteristics in power

system protection and develops the current power system protection coordination

for Gas Processing Plant B (GPPB). With this new protection system coordination,

the author hopes to help the company to improve the current protection systems.

iv

ACKNOWLEDGEMENT

The author would like to express her gratitude toward her supervisor, Ir

Mohd Faris B. Abdullah, Electrical and Electronics lecturer, Universiti Teknology

Petronas for the guidance throughout this project. A lot of new knowledge the

author learnt from him, and he always ready to answer all the questions regarding to

the project and share his experience before at TNB while doing the similar project

as the author did. There are a lot of tips that he gives and helped the author to finish

the project. Thank you for your help, support and motivation.

Also, thank you to the author friends that helped a lot and encouraged the

author not to give up at the first stage to start the project where at that stage it gives

the author a big challenges to understand the project requirement. Especially to the

author's group that work under the same supervisor as the author and have kind of

similarities in their project with the author. The author's group always discuss if

there is a misconception regarding the project. Thank you friends because be able to

be with the author even in critical period.

Last but not least, thank you to my family especially to the author's mother

and father also to other family members for their constant support and always

motivate to the author. With their support, the author becomes more motivated and

inspired to finish the project.

Lastly, thank you to Universiti Teknologi Petronas for assisting and

supporting in this project. UTP play an important role in the author project. UTP

provide the author with the main equipment that needs in order to complete the

project which is the ERACS software. Also UTP support this project by gives some

financial support to make sure this project completed successfully.

v

TABLE OF CONTENTS

ABSTRACT ................................................................................... iv

AC~OWLEDGEMENT ................................................................... v

LIST OF FIGURES ......................................................................... ix

LIST OJ? Ti\JEILES ..............................................................•........... Jti

CHAPTER I

INTRODUCTION

1.1 Project Background ...................................................................... 1

1.2 Problem Statement ........................................................................ 2

1.3 Objectives ................................................................................. 2

1. 4 Scope of study ............................................................................ 2

CHAPTER2

LITERATURE REVIEW

2.1 Basic Component in distribution Network ............................................ 3

2.1.1 Sensing Device ................................................................ 5

2.1.1.1 Current Transformer ............................................... 5

2.1.1.2 Voltage Transformer .............................................. 6

2.1.2 Relay ............................................................................ 6

2.1.3 Circuit Breaker ................................................................ 8

2.2 Types of Distribution Protection ....................................................... 9

2.2.1 Non-unit Protection ........................................................... 9

2.2.2 Unit Protection ................................................................. 9

2.2.3 Overcurrent and Earthfault Protection .................................... 10

vi

2.2.3.I Overcurrent Protection .......................................... 11

2.2.3 .2 Earthfault Protection ............................................. II

2.3 Protection Relay Coordination ........................................................ II

2.3.I Load Flow Analysis ......................................................... 11

2.3.2 Fault Calculation ............................................................ I2

2.3.3 Protection Coordination ..................................................... I2

2.3.3.I Grading Margin criteria .......................................... 12

2.3.3.2 Plug Setting (PS) ................................................. 13

2.3.3.3 Time Multiplier Setting (TMS) ................................. 13

2.3.3.4 Relay Calculation Steps .......................................... 14

CHAPTER3

MEmODOLOGY

3.1 Procedure Identification ............................................................... 15

3.2 Tools and Equipment Required ....................................................... 16

vii

CHAPTER4

RESULT AND DISCUSSION

4.1 Result ................................................................................... 17

4.2 Discussion ............................................................................... 20

4.2.1 Relay Coordination for Overcurrent Protection ......................... 20

4.2.1.1 Full Load Current at 132kV .................................... 20

4.2.1.2 Full Load Current at 33kV ...................................... 20

4.2.2 Grading Margin for Overcurrent Protection .............................. 22

4.2.2.1 IDMT l-2 .......................................................... 22

4.2.2.2 IDMT 1-3 .......................................................... 26

4.2.2.3 IDMTcable 1, IDMT cable 1-2 and IDMT .................. 30

4.2.2.4 IDMT 1 ............................................................ 34

4.2.2.5 IDMT 1-busbar, IDMT 1-motor and IDMT 2-motor ........ 35

4.2.3 Relay Coordination Earthfault Protection ................................ 37

4.2.3.1 Current at 132kV ................................................. 37

4.2.3.2 Current at 33kV ................................................... 37

4.2.4 Grading Margin for Earthfault Protection ................................ 39

4.2.4.1 IDMT 1-l, IDMT 1-2 ............................................ 39

4.2.4.2 IDMT 1-3, IDMT cable-!, IDMT cable-2 and IDMT ....... 41

4.2.4.3 IDMT 1 ............................................................ 44

4.2.4.4 IDMTI-busbar, IDMTI-motor and IDMT2-motor .......... 45

CHAPTERS

CONCLUSION AND RECOMMENDATION

5.1 Conclusion ................................................................................ 50

5.2 Recommendation ........................................................................ 51

REFERENCES ............................................................................. 52

APPENDIXES .............................................................................. 53

viii

LIST OF FIGURES

Figure I: Basic component of a protective system 3

Figure 2: Connection current transformer to the network 5

Figure 3: Connection of voltage transformer 6

Figure 4: Graph time-current characteristic for different relays 7

Figure 5: Vacuum circuit breaker use at high voltage 8

Figure 6: Non-unit Protection 9

Figure 7: Unit Protection I 0

Figure 8: Example connection ofOvercurrent and Earthfault (OCEF) relays to

the three phase network I 0

Figure 9: Flow chart of project 15

Figure I 0: Network of GPPB inside ERACs software 17

Figure 11: LocationofiDMT 1-1 andiDMT 1-2 22

Figure 12: Result of Coordination Protection IDMT 1-2 24

Figure 13: Graph for IDMT 1-1 and IDMT1-2 25

Figure 14: Location ofiDMT 1-3 26

Figure 15: Result of Coordination Protection IDMT 1-3 27

Figure 16: Graph for IDMTl-2 and IDMT 1-3 28

Figure 17: Result for IDMTl-2 and IDMT 1-3 29

Figure 18: Location ofiDMT cable 1, IDMT cable 1-2 and IDMT 30

Figure 19: Result of Protection coordination IDMT cable 1, and IDMT 1-3 31

Figure 20: Graph for IDMT 1-3 and IDMT-cablel 31

Figure 21: Result of Protection coordination IDMT 32

Figure 22: Graph for IDMT 1-3, IDMT cable 1, IDMT cable 1-2 and IDMT 33

Figure 23: Location ofiDMTl, IDMTl-busbar, IDMTl-motor,

and IDMT2-motor 34

Figure 24: Result of protection coordination for IDMT2-motor 35

Figure 25: Graph for IDMT 1-busbar, IDMT 1-motor and IDMT 2-motor 36

Figure 26: Location of relays 39

ix

Figure 27: Result ofEarthfault Protection Coordination for IDMT 1-2 40

Figure 28: Graph for Earthfault Protection for relay IDMT 1-1 and IDMT 1-2 41

Figure 29: Result for Earthfault Protection for relay IDMT 1-3 42

Figure 30: Earthfault current at Cable 1 43

Figure 31: Graph for Earthfault current IDMTl-cable 43

Figure 32: Result Earthfault current for IDMTl 44

Figure 33: Graph for Earthfault current IDMTl-cable 45

Figure 34: Result IDMTl-busbar for earthfault protection 46

Figure 35: Graph for IDMT 1 and IDMT 1-busbar 47

Figure 36: Result IDMTl-motor for Earthfault Protection 4 7

Figure 37: Graph for IDMT1-busbar and IDMTl-motor 48

Figure 38: Result IDMT2-motor for earthfault protection 48

Figure 39: Graph for IDMTl-busbar, IDMTI-motor and IDMT2-motor 49

X

LIST OF TABLES

Table 1: PS and TMS Overcurrent values for first path

Table 2: PS and TMS Earthfault values for first path

Table 3: List of Plug Setting for Overcurrent Protection

Table 4: Fault current and impedance for grid 1

Table 5: List of Plug Setting for Earthfault Protection

xi

18

19

21

23

38

1.1 Background of Study

CHAPTER I

INTRODUCTION

This study is intended to evaluate current power system protection

coordination at Gas Processing Plant B (GPPB), Power system protection is a

protection system used to protect important electrical component such as

transformer, generator, bus structures, transmission line and even the loads that

connected to the system from any fault, hazard such as short circuit or any abnormal

system operating condition that would eventually cause failure of one or more

system components. Therefore, the action is usually to isolate the portion of system

experiencing the hazard so that the rest of system can operate normally as fast as

possible. In doing so, the equipment will be safeguarded from further damage and

more importantly from endangering human life. Having this criteria set and adhered

to one can look at the second important objective that is to minimize interruptions.

There is number of protective device available which are fuses, relays and circuit

breakers.

The studies are basically on the characteristic of all protective devices and

find in the suitable coordination that can be the best way to protect all power system

components at Gas Processing Plant B (GPPB)

1

1.2 Problem Statement

Power system protection miscoordination had been observed to occur at

GPPB during the tripping of the upstream protection when there was a fault at the

downstream. A well coordinated protection system would allow the downstream

protection to clear the fault discriminatively, hence reducing the load loss.

1.3 Objeetive of Study

1. To study the power system protection at Gas Processing Plant B,

PETRONAS Gas Plant, Paka (GPPB, PGB).

2. To study on characteristic of each power system protection devices.

3. To improve current power system protection coordination at Gas

Processing Plant B, PETRONAS Gas Berhad (GPPB, PGB).

1.4 Scope of Study

The studies are based on the electrical power system protection,

characteristics of protection devices such as fuses, relays and circuit breaker,

overcurrent and earthfault relay coordination and setting. Also this project will

cover studies on coordination of overcurrent relays, differential relaying, and

restricted earth fault protection.

Other than that, this project is mostly deal with ERACS software to get the

best coordination of overcurrent setting and earthfault setting for power system

protection in Gas Processing Plant (GPPB). The author will be exposing to the

usage of the features in this new software through out this studies.

2

CHAPTER2

LITERATURE REVIEW

Main purpose of distribution protection and electrical protective devices is

to isolate the faulted component from the healthy parts as fast as possible. In doing

so, the equipment will be safeguarded from further damage and more importantly

from endangering human life. Also it is important to ensure that the distribution

network can operate with preset requirement for the safety of public, staff and

overall network including individual equipment. Having these criteria set then one

can look at the second important objective, that is, to minimize interruptions or the

cost of non-distributed energy.

2.1 Basic Component in Distribution Network

c "-

reaker SenllinaAdevice .

,. R•Jay

Trip

Ftgure 1: Baste component of a protective system

There are three basic components in distribution network as show in Figure 1 which

are:

a) Sensing device

b) Relay

c) Circuit Breaker

3

When the fault occur along the network, the nearest sensing device will

detect the fault in term of changes in measurement of basic electricity components

which are current, voltage, or frequency. The measured quantity then sent to other

basic component in distribution network which is relay. Relay act as decision maker

for the network whether to isolate the faulted network or not. The decision is

depending on the relay setting magnitude of the selected measured quantity. If

measured quantity exceed relay setting then the relay will make the circuit breaker

to trip therefore the faulted path will be isolated.

When designing, we have to make sure that the protection system 1s

selective, sensitive, stable, fast and reliable.

a) Selective - Relay systems should only trip as much of the system as

necessary to de-energize distressed components.[5]

b) Sensitive - Sensitive enough to operate under minimum fault

condition.(!]

c) Stable - Stable and remain inoperative under certain specified

conditions such as transmission system disturbance, through faults,

transients, etc. [I]

d) Fast- Fast operation in order to clear the fault from the system thns

to mininllze damage to the affected components.[ 1]

e) Reliable - The protective equipment should not fail to operate in the

events of faults in the protected zone. It may be necessary to provide

backup protection to cover the failure of the main protection.[!]

4

2.1.1 Sensing Device

First component in protection system is sensing device. Usually use as

sensing devices are current transformer and voltage transformer. Both use to

facilitate the changes in current or voltage within some range.

2.1.1.1 Current Transformer

A current transformer as shown in Figure 2 comprises of two

windings. The primary winding is connected in series with the main circuit.

In most cases, the primary winding is part of the main circuit. The secondary

winding comprises of several turns of wire wrap around an iron core. This

provides ampere-turns relationship:

• l '~

Prlm•fl'(Y', 1,.

'. ~ ·- M•ln olroul I, laoondlry

~ Trip O~--··y Figure 2: Connection current transformer to the network

Where Np and N, are the number of primary and secondary turns

respectively. The idea is to provide large number of turns on the secondary

to obtain small quantity of current that replicates the primary current.

Current transformer ratio is defined as Np/N; (example 300/5 A). [4]

5

2.1.1.2 Voltage Transformer

This device (Vn is use for measurement, directional protection

(conventional or reverse power relays) and undervoltage/overvoltage

protection. The primary of the VT is connected directly to the power circuit

between phase and ground as Figure 3. [4]

I • ;:!. ;:!.

Primary = = = -- -- .....

M aln olroult

Figure 3: Connection ofvoitage transformer

2.1.2 Relay

Second component in protection system is relay. It usually installed with

current transformers (CT) for current measurement. The current measured by the

CT is proportional to the circuit current. When the current exceed a preset value, the

relay will operate at a time depending on the characteristic of the relay. The basic

function of the relay is thus to sense the presence of signal (circuit current) and

activate an action that normally actuates the operation of switchgear if such a signal

surpassed a certain set value. [4]

6

IDMT·~-

Current (A)

Figure 4: Graph time-current characteristic for different relays

Relays are normally classified into the time/current characteristics as shown

in graph above:

• Instantaneous

• Defini~ Time

• Inverse Definite Minimum Time (IDMT)

Standard Inverse: t = 0.14

(f·02-1)

x time setting sees

Extremely Inverse: t= 0.14 x time setting sees

(!2-l)

Very Inverse: t = 0.14 x time setting sees

(1-1)

7

Throughout this project, the author use standard mverse IDMT relay

characteristic which have the equation:

0.14 X 1MS I =

( ~_UL_T __ C_URRE __ NT_ SETilNG CURRENT )

0 .02

- 1

2.1. 3 Circuit Breaker

Last component in protection system is circuit breaker. It is use to break the

connection between the faulted path and healthy path. There are many types of

circuit breaker, for example Molded Case Circuit Breaker (MCCB), Air circuit

Breaker (ACB), Gas Circuit Breaker (GCB). Selection of circuit breaker to use is

depending on the voltage that the system works with. For circuit breaker use at high

voltage, we can find it inside switchgear.

Figure 5: Vacuum circuit breaker use at high voltage

8

2.2 Types of distribution protection

There are various types of protection that can be considered m any

distribution network.

2.2.1 Non-unit Protection

Non-unit protection is a time/current graded system where protective

systems in successive zones are coordinated to operate at different times.

When a fault occurs, a number of relays will respond and only those closest

to the fault complete the tripping operation leaving the remaining relays

reset. [1]

SS1

~-s_e_c ________ ~

~ 0 sec

Figure 6: Non-unit Protection

2.2.2 Unit Protection

A unit protection is a protection system in which the protected zone

can be clearly identified by means of CT boundaries. Such protection does

not respond to through fault (out zone fault). It responds to only internal

faults or faults inside the protected zone. As shown in Figure 7. [1]

9

l--lli}··

Figure 7: UnitProtection

2.2.3 Overcurrent and Earthfault Protection

Overcurrent and Earthfault protection is used to protect feeders,

transformers, motors, capacitors and other equipment. The protection devices used

are either fuses or relays. Usually we used the combination connection between

overcurrent and earthfault (OCEF) relays like shows below. [4]

R (cT)·· .

~ .... ' .

y

,----..__ CT 8

C7 ~ ~~ II EARTH

Tl' BONOIN

Figure 8: Example connection of Overcurrent and Earthfault (OCEF)

relays to the three phase network

10

G

2.2.3.1 Overcurrent Protection

The objective for overcurrent protection is to detect fault affecting one or

two phase, Overcurrent protection involve inclusion of suitable device which is

overcurrent relay in each phase and is energized by current transformer

Magnitude of an interphase fault current depends on the impedances of the

system. Usually the phase fault current is larger. When calculating grading margin

for overcurrent relay, we use three phase fault current and the maximum load or

current carrying capacity of the cable/line/transformer will determine the setting

current.

2.2.3.2 Earthfault Protection

Earthfault protection is required to have a high sensitivity to earth faults.

Earthfault setting are often required to be lower than system rating. When

calculating grading margin for earthfault relay, we use single phase fuult current.

Normally a setting of 10%-20% from current transformer rating is used as earthfault

setting current.

2.3 Protection Relay Coordination

2.3.1 Load Flow Analysis

Load flow analysis must be done first before doing the grading

margin for protection relay coordination. Load flow analysis were run to

confirm that the busses, switchboard, Motor Control Centre (MCC),

transformer and feeder cables would operate within their ratings, and also to

determine the real and reactive power, bus voltage and load level at all

busses.

11

2.3.2 Fault Calculation

Next step we must know the current fault at every busses either three phase

current fault or single phase current fault. Fault calculation is fundamental to

protective relay setting and coordination. Knowledge of maximum 3-phase fault

MV A at any point in the system would enable one to initially set the operating time

of the relays to ensure that it is within the withstand capability of the equipment.

With knowing three phase fault, then coordination exercise can be

performed for overcurrent setting since 3-phase fault current is the highest fault

current in the system while single-phase to ground fault value is very important to

coordinate earthfault setting as this is the highest earthfault current in the system.

The criteria to choose 3-phase fault current for overcurrent setting and single-phase

to ground fault current for earthfault setting is based on normal Inverse Definite

Minimum Time (IDMT) relay characteristics.

2.3.3 Protection Coordination

2.3.3.1 Grading margin criteria

Grading margin between adjacent relays is determined by several factors:

Circuit Breaker Time

Relay overshoot

Instrument Errors

12

Two methods of determining grading margins:

• Fixed margin

Time margin is estimate as follows:

Circuit Breaker Time - O.lOsec

Relay Overshoot - 0.04sec

Relay Error - O.lOsec

Instrument Error - O.lOsec

Safety Margin - O.lOsec

Total Margin - 0.44sec

The margin could range between 0.3-0.5 sec. In practice for this

project, the author use margin 0.4 sec.

2.3.3.2 Plug Setting (PS)

Plug setting will set the minimum operating current. Usually it is in

electromechanical/electronic relay or in numerical relay.

2.3.3.3 Time Multiplier Setting (I'MS)

It gives operating time scale for maximum disc movement.

13

2.3.3.4 Relay Setting Calculation Steps

• For Transformer - the max operating time at LV side must considering

transformer damage curve. For this network, transformer damage curve

considered as 1.6 sec.

• No margin required within feeder and 0.4 sec margin between feeder

• For OC set PS =current carrying capacity and adjust TMS to get required

margin

• For EF set PS = 20% of ct ratio and adjust TMS to get required margin

For this project, all of the calculation mainly calculated by ERACS software

because it is much faster to perform calculation and without arithmetic error and

also the system that has been setup for computer calculation could be modified

easily and calculation can be repeated.

14

CHAPTER3

ME mODO LOGY

3.1 Procedure Identification

,r

"

,r

"

Understand the Project Requirement

L Data research and gathering information

Elements of studies involved in this stage include the study in power

system protection for GPPB, overcurrent and earthfault relay

coordination, characteristics of protective devices.

~ Analyse protective devices characteristic

Gather all information on fuses and relay charnctenstics and

simulate the protection system coordination.

L Designing using ERACS software

Using all information and characteristics done before, start

designing GPPB single line diagram using ERACS software and

find out the margin for the system.

~ Perform Loadflow Study

l Design Protection Coordination System

Figure 9: Flow chart or project

15

'

.I

I

3.2 Tools and Equipment

• ERACS software

ERACS software is a power system software used to calculate

the load flow study, fault analysis and calculate the protection

coordination of the network

Complete design the network for high voltage level.

Complete design the grading margin for one path of the network.

16

4.1 Result

CHAPTER4

RESULT AND DISCUSSION

The author design GPPB network for high voltage level up to llkV voltage

motor using ERACS software. The network as below:

(h

IDMTB :.' I .---0---, .. (

· lDMT 2·3

S86~0l

Figure 10: Network of GPPB inside ERACs software

17

Result simulation for the first path. It is including Grid 1 up to the 6.6kV

motor (PM5-0202A), the result for Plug Setting and Time Multiplier as the show in

Table l.

Table 1: PS and TMS Overcurrent values for first path

Relay Plug setting Time Multiplier Description .

IDMT 1-1 0.4 0.2 -

IDMT l-2 0.4 0.2 No margin

IDMT 1-3 0.75 0.25 Remaining time < 0.2 sec

IDMTcable l 0.75 0.175 Margin 0.4 sec

IDMTcable2 0.75 0.175 No margin

IDMT 0,75 0,175 No margin

IDMT1 0.70 0.25 Remaining time < 0.2 sec

IDMTBusbar 0.85 0.125 Margin0.4

IDMT 1 motor 0.85 0.05 Margin0.4

IDMT2motor 0.85 0.05 No margin

18

Table 2: PS and TMS Earthfault values for first path

Relay Plug setting Time Multiplier Descriptioo

IDMT 1-1 0.05 0.05 -

IDMT 1-2 0.05 0.05 No margin

IDMT 1-3 0.15 0.05 Remaining time< 0.2 sec

IDMTcable 1 0.15 0.10 Margin 0.4 sec

IDMTcable 2 0.15 0.10 No margin

IDMT 0.15 0,10 No margin

IDMT1 0.15 0.25 Remaining time < 0.2 sec

IDMTBusbar 0.20 0.20 Margin0.4

IDMT 1 motor 0.20 0.05 Margin0.4

IDMT2motor 0.20 0.05 No margin

19

4.2 Discussion

4.2.1 Relay Coordination for Overcurrent Protection

Start grading margin with calculation of the relay's CT ratio usage hence getting the

fix Plug setting (PS) of the relay that will be used through out the project.

4.2.1.1 Full load current at 132 kV

MVA I - -=-­FL - .,fi XVLL

SOMVA .,f3 X132kV 218.69A

MV A value is the maximum capacity transformer can carry. In this

case the maximum capacity is 50MV A for 132/6.6 kV transformer.

PS =Full load current 218.69 = 03645 CTratio 600

•:• Choose nearest PS available= 0.4

With PS at 0.4, the minimum available current that relay can carry is

IMin = 0.4 x CT Ratio = 0.4 x 600 = 240A

Therefore, minimum current that is allowable to flow through the

132kV relay is 240A.

4.2.1.2 Full load current at 33 kV

MVA I - -::::-­

FL - .,fi XVLL SOMVA

.,f3 X33kV 874.77A

PS =Full load current 874.77 = 0_729 CT ratio 1200

•:• Choose nearest PS available= 0.75

20

With PS at 0. 75, the minimum available current that relay can carry is

IMin = 0.75 x CT Ratio"" 0.75 x 1200 = 900A

Therefore, minimum current that is allowable to flow through the 33kV relay

is 900A.

The same steps use to calculate other equipments rating such as at the second

transformer 33/6.6 kV transformer and motor rating. The result for the first

path for overcurrent protection as table below:

table 3: List of Plug Setting for Overcurrent Protection

Relay CT Full load Plug Setting Allowable

Ratio currenl (PS) current

IDMT 1-1 600/1 218.69 0.4 240

IDMT 1-2 600/1 218.69 0.4 240

IDMT 1-3 120011 874.77 0.75 900

IDMTcable 1 600/1 437.39 0.75 450

IDMTcable2 600/1 437.39 0.75 45()

IDMT 600/1 437.39 0.75 450

IDMT1 300011 2091.85 0.70 2100

IDMTBusbar 1250/1 1049.73 0.85 1062.50

IDMT 1 motor 125011 1049.73 0.85 1062.50

IDMT2motor 1250/1 1049.73 0.85 1062.50

21

4.2.2 Grading Margin for Overcurrent Protection

4.2.2.1 /DMJ' 1-2

;; .'·

T '

Figure 11: LocationofiDMT 1-1 andiDMT 1-2

Start grading the network from grid 1 for IDMT 1-1 for overcurrent

relay protection. The grid 1 is from PAKA132_M1 substation which has the

characteristic as below:

22

Table 4: Fault current and impedance for grid 1

Characteristic Value

3-phase current fault (A) 22 010.10

1-phase current fault (A) 25 757.50

Positive impedance 0.254 + j3.453

Negative impedance 0.663 + j3.774

Zero impedance 0.146 + jl.585

Given value for TMS and PS for overcurrent IDMT 1-1 relay as:

Overcurrent setting: PS = 0.4

TMS=0.2

Using the value given, we grade IDMT l-2 relay which is the relay after

IDMT l-1. The purpose is to find its Time Multiplier Setting (TMS). There is no

margin required between this two relay because there is no other feeder connected

to relay IDMT 1-l and we can consider it as relay in the same feeder. Therefore we

get the same graph characteristic for relay IDMT l-1 and IDMT 1-2 as shown in

Figure l2.

23

u lit ~ .. .!. l!.l :!: 1111 'f v.. "'~ 13 •• (

tJ X: !a Y:ll1

~ ··:: ·.: . . . . .

/ I

I A4,t•

;v~- -1-3 Fault

..

oooo r111 e ' ~ldallllirl Nlllk iJj ~ J Dcralir£ 0.394r fnshfm 0.394c

Tie 111!1M7 led; tali! 1111 ile ~ ci ~ p!iedm deW:es ~ llic ~ If yw select n ~ lhe 1owt n lhe ~. deYi:et « lhe clolen 11m ¥oi be lijijtednlheneld~rdnre~. nlhenetd ovavilw.IJrNdedlhat ilabes!.,led~ -

ISialul I• DeW:ec I ll Nd~ftlrd nlhefa.tpalh. 33 ..... __

N~ ~~ W n h fa.t pelll 0 Olan!l.aa,rd~becaae~'lttageiklobll 0 ~ 0 Op«alrY;j!U~... 0 Abolt ID opnle. W rd n fa.t Plf/l

lo ~ IJiliJI! 2 11 tija

Opseia eairtllage. w rd ilfd pall Opere! at eairtllaga CllliJI! 2a h!ils. Opere! at llllirliage lllliJI! 1 ~~~ ""'-CT Ia waled o

IDMT2-3 lr: 22.121 kA ~· 22.121 kA

IDMT-cah!e~ lb .".: 121 kA w :;( tl-!·~ ~ ~~ !n

:;( SB05-B02 !n

Figure 12: Result of Coordination Protection IDMT 1-2

24

Re ~ fl'!llil raj:h 1 ID:IDMT 1-2 Tme(s) Reference Vobge:131 kV

DeW:e: IEC255-SI 10' 2P

T _I_ CT A~~~ 600.0 Phase PS {Jll~ 0.4 Phase TM {Jll~ 0.2 l Ofbet 1.0

101 - -t -

raph: 2

I ID IOMT 1-1 Devu IEC255-SI

I CTR~(AH.OOO Phase PS !Jlll 0 4 10: --- --1 Pha$e TM !Jllt 02 OftsetlO I

101 _J_

-----<

10° - l t ------<

,2P

10., -------~

10,:·~---~---~------+-------101 10- 10' 10' 10; 10'

1: 3.995 (M), T: 12.374 {s)

Figure 13: Graph for IDMT 1-1 and IDMT 1-2

After grading, value for IDMT 1-2 relay are:

Overcurrent setting: PS = 0.4

TMS=0.2

25

Cu-rert (A)

I I

I! Frish !I

4.2.2.2 IDMI 1-3

For the second grading which is IDMT 1-3 relay, this relay is located at low

voltage transformer.

MT1-2

IDMT -cable 1

Figure 14: Location ofiDMT 1-3

Note that, we have to considered transformer damage curve in order to

design this relay. There are two characteristics that we have looked for to set

Relay's TMS:

1. Relay operating time must not exceed 1.6 sec which means the TMS value

can be increase until its operating time for relay is 1.6 sec

2. The remaining time must be less than 0.2 sec (since we only consider circuit

breaker time and safety margin which total up given 0.2 sec)

26

But for this system, we use the second characteristic since the value for

operating time is too small so we have to consider its remaining time must not be

less than 0.2 sec.

Therefore, value for IDMT 1-3 relay is:

Overcurrent setting: PS = 0.75

TMS=0.25

~ ·. - .. •.. . . . -

D ~ I • 1 ill ~ ~ ~ ~~~~00 ?

" X 413 V: 417

f.- ,:. .· . . ,. ) . r

IDMT-ca! c

Fault

lr: 6256kA

0 0 00 tit. • • Stage lrltJH:rl ttrabec [1 ~ d s o~ o.ns.

The_, lesW l.tle iils lhe ILllla d 4 ~ dM:el alh 11age.

I JW select one d h 101¥111 h l.tle. dM:es a1 fle c:lmen till,. be tioJ61Ied n 111enetMit ~in! an~. n lhe l'ollllllllk ~~'~~Mew. ~~i ha3bmqln:!ed~.

IStab Ji'D-1 NU ~ inlrd n fle fd Pllh 32 Nm~bintheldPBil o ! Dildinllll!iw rd CICIArG becue poleisalir) ~ i bl kM 0 i OpllaliiJ. 0 : Opeqq lilt NdecJIIIe ftlilgl\ 2 1A~x~.C~o~.hin:~~nldPifh o

AlxU lo ~Ill !0'111 . Operal!da~Mier -..hi n:~~ nfd Pllh

I' Opsal Ill Mill llage Ill !0'112 II t.;e. Opsal al Mier llage 111 !0'111. ,R.IIholeCT llllllall.laled.

0

Figure 15: Result of Coordination Protection IDMT 1-3

27

2-3

SB05-Bot

IDMT~

Re Ell Gr~

1 ... 1 10: IDMT l2 Tille (a)

DM:e: IEC255-SI 10' -CT RalnJ ~~ 1m 0 PhasePS {rA!tO.• PhaseTt.I~0.2 Offset 1~ 10,

~r¢ 2

JD· IDMT1 ·3 Dew:e: IEC2SSI

Reference VobGe: 33 kV 2P

CT Ra1nJ~P200.0 10: ----+----r----f-J----+-----t Phase PS [pJJ: 0.15 Phase Tlol ~ 0.25 Off!e!:lO

- -

10° -----+-----+---

+ +

I: 20.943 (IrA), T: 25.456 (s)

Figure 16: Graph for IDMTI-2 and IDMT 1-3

I! Frith II

From the graph we can see that the graph for IDMT 1-3 cross the graph for

IDMT 1-2. We accept this criteria because in real practice both relay IDMT 1-2 and

IDMTI-3 is actually operating at the same time when fault occur at bus SB6-BOI

because we already consider the circuit breaker time and safety margin for the

breaker which is less than 0.2 sec. In this case it is around 0.166.

28

to'

to'

to'

to'

to·•

to"' tO I to'

)

tO ; to'

I ••• a••~••-••-•••-•••••-•

I

tc1DM~<t!e2

~~ ~IDMT ~)'-J

DM'Gen~'' f~oM1 0

-

IOMTI-3 IDMT IWI!Illl-3 TR5AIIm oo tub.Y sa~m

s~ F'ha!e 1\.g s~ w o. 75 Phase Tine J,l!J~ W 0.25 Ealh 1\.g s~ !PJ~ 0.1 Eadh Tinelol~fpJ~ 0.(5

Red Ph. 1\.gS~~ 6.~ Cu!n IliA~ 6.255 Cu!n I CT PN}I Rallv 5.2125 Operaliig Tine (s~ 1188526 RelllaiqTine(st 0.16616 P«ceetage Operated !%l 81 231 St.~u&: 4 ZnNI.IIk

Yehf'hale 1\.gS~M'* 6.~ CUTn IliA~ b.255 Cullri ICT PN}I R~ 5 2125 Operali-Q f~~~e (s~ 0.88526 Relllaiq Tine lsl 0.16016 P«ceetage Operated !%l 81 231 Slm: 4 ZnNII!ilef. 1

Bl.le Ph. 1\.g SdlilgMt.ti*; 6.~ CulertlliA~ 6.255 Cu!n/CT PN}IRallv 5.2125 Operali-9 Tine (sl 0.88526 Relllaiq Tine(sl 0.16016 PeJcerUoeOperDJI%]: 81 231 Stu 4 ZnNum: 1

Figure 17: Result for IDMTl-2 and IDMT 1-3

29

4.2.2.3 IDMT cable 1, IDMT cable 1-2 and IDMT

Margin for this IDMT -cable I with IDMT 1-3 is 0.4 sec since this relay is in

different feeder. But no margin required for next three relays which are IDMT cable

1, IDMT-cable2 and IDMT because these relays is in the same feeder.

I

~I DMT -cable2

¥ <t>i:JIDMT-1 .--------------- ':: = = = = = =:

~ IDMT -cable2 __ ..,._ sub-bus2

Figure 18: Location ofiDMT cable 1, IDMT cable 1-2 and IDMT

30

Fte Edt Gra!)h

Gtopr 1 10: IOMT1·3 Tme (a)

Device: IEC255-SI 10' CT AU>g lA~ 12000 Phase PS (pu~ 0.75 Phase TM (pu~ 0.25 Ofta11:10 10>

Gropr 2 10 IDMT -cablel Dew:e: IEC255-SI CT Ratrlg lA! 600.0 10> Phase PS IPul 0 75 Phase TM {pu~ 0 175 Offset 10

10°

Refetence Vollag<t: lJ kV 1P o=.o"

10"+-:-, -----:-. ----":"', ---!--:-------:-----~ 10 10- 10 10' 10' 104

Figure 20: Graph for IDMT 1-3 and IDMT-cablel

31

CUTert (A)

J II F"rioh II

The 0.4 margin required for IDMT 1-3 and IDMT-cablel result the graph

characteristic as Figure 20. The different at the fault current line for both of the

graph is 0.4 sec.

5ub-busl

IOM"'Gen

• 1r 6039kA SB5-C ¥ 6039kA

*'{] IDMT -mlle2

IDMTl

SB05-801

Slage~

N\nber :;-~ d 5 Du.iDt 0.46 I

The 11.n15J reds ~ t:a lhe llab d al ptUc~Jon de¥11:4 U JOJ teled one d il1e 10M il lhe ta!M. dM:es atllle craent ~nlhe~cb}"". andii'IDie~, n O't'el'/n,pDYi:led INi l tee been~~

,N<t~nlrdiltefdpalh 29 N<t~lx.tiltefdpalh 0

' ------------- ' DiedloM!IIIilllrw:t~becaulepolftalion~iambw o

~ 10Mrubfe2 Ops~ 1 )( sub-busZ Ops.rglx.t~,.. 3

AtxU" ~·' lx.t rdil fd path. 1AIJcU !D qJel& on Zlll1e 2CI t.ja

Opelllled a~ a-., lx.trw:tnfd ~ i Opsaled ala ~tag~ on zaw 2 e1 ho,tllll Opsaled aiNi!r atage on Zlllle l , Rei!Mrl whole CT tee laluallld.

lb 6 039 kA -blsbs ¥ ~ <HJIOMTI-bus~ S85-002 (jr{]~ ~ .. -... -- .. --- .. -- .. -- ..... ------ ... --.. ------- .... -.. _;_-_-_ .. _-_-_-_-_-_-_-_-_-_-_-_._-_-_-_-_-_-_-_-_-_-_-_-_-_-

Figure 21 : Result of Protection coordination IDMT

32

~ n ~x

"-: ~ "' " • ~ ... ... ··-- """ .. ~--; " .. ' .. , . --:: <.. __.. -

Fie Edt Gr"!lh td< I 10: IOMTI·3 Tioe(s)

Device: JEC251S-SI 10' CT Rairig lA~ 1200.0 Phae PS (puJ 0.15 Phae T M !Put 0.25 OlfMt 1 0 10'

~,'(it 2 ID IOMT Oe.-.:e:IE~SI

CT Ra1r1g IAl mlO 10' 1'1>= PS Ill<* 0 15 Phase IM!Ix4 0115 Oftl!l. 10

r4j:h 3 10' - - - -10: IDMT .c«JJe2 Device: IE~SI CT Ralrlg IA1600.0 Pheae PS lllul 015 10• Phase HI lllul 0115 Oftlll.lO

'(it' I[) lot bl

De. EC2'i5-Sl CT Rairig lA 1iOO Phase PS ta4 'l"i PhaseiM(Illt 17'i Otic« I 0

10..: I

10 J

10 10° C11nd(A)

u Frail n

Figure 22: Graph for IDMT 1-3, IDMT cable 1, IDMT cable 1-2 and IDMT

From Figure 22, relay that has no margin will have the same characteristic,

therefore the graph is about the same for all there relays; IDMT-cablel , IDMT­

cable2 and IDMT. All three relays lay on the same graph as shown on the green

line.

same:

Therefore, value for all IDMT -cable 1, IDMT -cable2 and IDMT relay is

Overcurrent setting: PS = 0. 75

TMS = O.l75

33

4.2.2.4 IDMI' 1

IDMTGen

>K c:>-D IOMTl-bu~

I ----------

885,{)~

~1-motor IDMT2-motor I

motorbus2

IDMT2-motor2

Figure 23: Location ofiDMT 1, IDMTI-busbar, IDMTI-motor, and IDMT2-motor

For relay IDMT 1, the same step as use to grade IDMT 1-3 is apply to find

the TMS value.

• For low voltage transformer relay, need to consider either 2 things:

Maximum operating current is 1.6 sec

Maximum remaining time is 0.2 sec

Therefore, value for IDMT 1

Overcurrent setting: PS = 0. 70

TMS = 0.25

34

4.2.2.5 IDMI' 1-busbar, IDMI' 1-motor and IDMI' 2-motor

To grade lDMT 1-busbar, its needs margin 0.4 sec with IDMT 1. Same steps goes

to grade IDMT 1-motor, it is also needs 0.4 sec. But to grade IDMT 2-motor it does

not need any margin to IDMT 1-motor since it is in the same feeder.

Therefore, value for all IDMT 1-busbar

Overcurrent setting: PS = 0.85

TMS =0.15

Therefore, value for all IDMT 1-motor

Overcurrent setting: PS = 0.85

TMS=0.05

Therefore, value for all IDMT 2-motor

Overcurrent setting: PS = 0.85

TMS=0.05

. '

SB5-Dd~

. --------

, !~n-~oto< ~ IDMT2-<ne>t<><

moto~Ms moto~s2

Fault

lr: 19 979 kA ly: 1 9 _ 979 kA lb: 19.979 kA

10M T 2 -motor2

Figure 24: Result of protection coordination for IDMT2-motor

35

Fie fit Grllj)h

reph: 1 10: IOMT1-busbor Tlrl're(S) Refetente Vobge: U kV

Device: IEC2SSI 10' ~ ""''

CT Racilg !At 125110 I u !I Phaoe PS (pu~ 0.85 Frish Phaoe Tlol (put 0.125 i O"set 1.0 10'

I raph 2

l lD IOMTl·mo(a D~ IEC255-SI CT Rating IAl1251l 0 10' --- --+- - -- -- - -Phose PS !PJl 0.85 Phaoe TM (pul O.l!i Offl8l 1.0

'"""' 3 10

1 +

ID. IOMT2....m DoW:« IEC255-SI CT Rilling !At 125110 Phase PS (put 0.85 Phase TM (put 0.05

10° - --·+ -Off$1!1: 1.0

1P

10., -t I ~

I 10.,

' 10' ' • . 10 10 10 10 10

Ct.rrett (A)

Figure 25: Graph for IDMT 1-busbar, IDMT 1-motor and IDMT 2-motor

The same steps apply to the other path but basically if the three phase fault

current for the other path is same as the first path which have been discuss by the

author above, the result for the relay TMS and PS is the same. But if there is a

different in three phase fault current, than the author need to grade the relay again.

From this project, three phase fault current is the same at the same level of voltage,

therefore the author just need to grade the first path and can obtain the other

coordination of relays.

36

4.2.3 Relay Coordination for Earthfault Protection

As in literature review, to grade relay for earthfault protection, need to

consider earthfault condition. Since earthfault always occur and to prevent its trip

on unbalanced load, the earthfault must be set 20% of its current carrying therefore,

it will operate faster than overcurrent relay.

4.2.3.1 Current at 132 kV

I= 20% X IFL = 0.2 X 218.69A = 43.738A

PS = Full load. ~rrent = 43.738 = 0_073 CTratto 600

•!• Choose nearest PS available= 0.075

With PS at 0.075, the minimum available earthfault current that relay

can carry 1s

IMin = 0.075 x CT Ratio = 0.075 x 600 = 45A

Therefore, minimum current that is allowable to flow through the

132kV earthfault relay is 45A.

4.2.3.2 Current at 33 kV

Ioc = 20% x IFL = 0.2 x 874.77 = 174.77A

PS = Pull load ~rrent = 174.77 = O.l46 cr ratto 1200

•!• Choose nearest PS available = 0.15

37

With PS at 0.15, the minimum available earthfault current that relay can carry is

lMin = 0.15 x CT Ratio = 0.15 x 1200 = 180A

Therefore, minimum current that is allowable to flow through the 33kV earthfault

relay is 180A.

The same steps use to calculate other equipments rating such as at the second

transformer 33/6.6 kV transformer and motor rating. The result for the first path for

earthfault protection as table below:

Table 5: List of Plug Setting for Earthfault Protection

Relay CT 200/o of full Plug Setting Allowable

Ratio load current (PS) current

IDMT 1-1 600/1 43.74 0.075 45

IDMT 1-2 600/1 43.74 0.075 45

IDMT 1-3 120011 174.95 0.15 180

IDMTcable 1 600/1 87.48 0.15 90

IDMT cable 2 600/l 87.48 0.15 90

IDMT 600/1 87.48 0.15 90

IDMT1 3000/1 418.37 0.15 420

IDMTBusbar 125011 209.95 0.20 250

IDMT 1 motor 1250/1 209.95 0.20 250

IDMT2motor 1250/1 209.95 0.20 250

38

4. 2. 4 Grading Margin for Earthfault Protection

The available values for TMS and PS for incoming 33kV /6.6kV transformer

is given by the plant supervisor to help the author start grading margin for earthfault

protection. The values are:

Earthfault setting: PS = 0.10

TMS=O.IO

This value is for IDMT-cable 1, IDMT-cable2 and IDMT. But refer to the

Relay Coordination for EarthfauJt Protection calculation, PS is 0.15. Therefore the

author uses this value to start with.

4.2.4.1 IDMT 1-1, IDMT 1-2

~ IOMT-cable2

*~=~

]IDMT 1 1

AlJl

SBOS-801

~

~T1·3 l IOMT-ceble1 )K >K >K

(i)....fl c:>-0 IOIV IOMT-ca~l ----- - __ <j>-0

0 0 0 ' ------------ - -----------------=-=-=-=-=--=~

~ IOMT-cable2 --..,...- sub-bus2

L=l,_- sub-buc;3 •

Figure 26: Location of relays

Start grading the network from grid 1 for IDMT 1-1 for earthfault relay

protection. The grid 1 is from PAKA132 M1 substation which has the

characteristic as in Table 4 above

39

The same characteristic apply here as in overcurrent protection. Since both relays

are in the same feeder, therefore it does not need any margin. The author set the

IDMT 1-2 TMS same as IDMT 1-1.

Earthfault setting IDMTl-1 and IDMTl-2: PS = 0.05

TMS=0.05

Fa.t ,, 32.511 kA tr nou lx QOirA

SEfU(ll -----.--_._,~~~·~

llMT~1)1: X ---······ ····· ................. m 10M~' ' ' I ' . -·------------.-,.,.-.----~---.~.-.-:.·· tollloll -atr2 ~ IDHI U:i1!2

~,~' ~~~ ~1 ~ t:

Figure 27: Result of Earthfault Protection Coordination for IDMT 1-2

40

Fte ~ (#~ ~·

10: IDMT 1-2 'lnll (l) Pdetence Volbge: 1J2 ~y

De-nee: IEOSSI 10' 2E

CTA~~600.0 E.v1h PS lpul 0.~ II frilh II E.v1h TM fplt 0.~ oqae~: 10 10' -- -- -Gr~2

ID:IDMT 1·1 Oew:e. IEOSSI CT~Io\!600.0 10: + E.v1hPS 1P4 0.~ E.v1h HIIPJl 0.05 Oftaet 1 0

10°

10°

., 10 2E

10·:

10 '

Figure 28: Graph for Earthfault Protection for relay IDMT 1-1 and IDMT 1-2

4.2.4.2 IDMT 1-3, IDMT cable-1, IDMT cable-2 and IDMT

The problem occurs to grade relay IDMT 1-3, IDMT cable-1 , IDMT cable-2

and IDMT. Note that earthfault protection for relay located at low voltage

transformer must be grade with overcurrent relay located at high voltage

transformer. For this project earthfault relay IDMT1-3 must be grade with

overcurrent relay IDMTI-2. Therefore the author uses this characteristic to grade

IDMT 1-3.

41

10'

10'

10°

10°

10.

10 .. 10° 10' 10° 10

s.wo "'-Pl.vS.VW 0.1'5 P~~Mr ... .....,..w a.2!5 E..,P\.vS.VW 0.1~ [..,T.,...,.._P¢ Q3 o oo o 11a • •

S~.,gti-N.....,. jl- :1 d 1 0........ O.Oo fnoltT- O.O o

Tho_J_.,Iobloloblho.....,ololpCiioclionciM;a"'u-Oo-lf)'CIU- ... ollho-illhoi.t>lo.-lllho--.. .... bo ~;, .... -.s.g-.rd-.~ ..... ---~lholthoo-~~.

5I.. I• o..c. r- 1Nal-.rQrdN:II•hfdpolf\ 32

~---......... ~ )( )( _ .-.... .. ,.,.~-~ ............... 0

- - - - ----- fd

¥3 IOMI ...tlo2

(!;.("1 <x...J • ~ 0 IDNf.~t , ·OpHrvw~- D

·-..·.·.···· '""':'- :-.ID-•.Wnclnlajpolf\ 0 , ........ _ ........ 2 .. hdw 0

to~' .. ......... _. ....... ,. 0 'Opor*<l .. -ologo.Wncl,fdl>lfl, 0

10por_ot_o~ogoan ... 2Gh:!#w 0

,lljool*<l .. - .......... 0 e Relo!:M _ cr hoi ... -. o

k D-i-Tol:lo l~

Figure 29: Result for Earthfault Protection for relay IDMT 1-3

Refer to the Figure 29, the single phase to ground fault current is too small.

The current is just 17 A and the IDMT 1-3 relay cannot detect such a small current.

This occurs because of transformer connection. Transformer 132kV/33kV

use star-delta connection with solid grounded at star side. The star side connected to

the supplier which is 1NB while the delta side is connected to the load. Other than

that, delta-star connection is use for transformer 33kV/6.6kV. The delta connection

is at high voltage side which is connected to the delta connection low voltage side

132kV/33kV transformer. Therefore the unbalanced current is circulating around

delta connection and not returns to ground. While this happen, the supplier which is

1NB cannot detect this unbalanced occur.

Therefore, relay at this path which is IDMT1-3, IDMT cable-1 , IDMT

cable-2 and IDMT only can detect if there is overcurrent occur not for earthfault.

This may risk the plant while operating this relays.

42

Fie fdt Graph

roph 1 10: 1Dt.H·cablo1 Device: 1EC25&51 cr Ra111g IAl 600.0 EorthPS!po.dll15 Earlh TM [pu~ D 1 0111et1.0

-c. C) &. •••

St..go lnformalion Number. r ::J ., , Durolion: 0.0 • Froilh Time. 0 0 s

The summary reaub t"bl" 5sts tho otatuo ol "I proteclion devices et thia otag10. If you select one ol tho row a in the table. devices et the chooen slat us wil be ~in lhe networl< ciagrarn. - """"conveniently. in the network overview. provided that l hoo been~ ..JfiCientlv

Staluo

Not operating - not in h faul pelh. Not operating. boA in lhe 1- pelh. 4 Directianal ,.,._not operating beoet.e ~ vo1t<v> ia too low. 0 Operating. 0 Operating boA inodequeto rnavri 0

SB05-B01 AboU to operate. boA not in, .... path. 0 --------t AboU to op«ale on""""' 2 or higher. 0

,,...,,, ...,... -"'"" Opereted et earlier at-. boA not in, .... path. Operated et....,... ol- on zone 2 or hrltler. Opereted et earlier at- on zone 1 Rele}(s) ..nose CT t- •at<aated.

Figure 30: Earthfault current at Cable 1

Time l•) 10• 'u.a • 1E

10'

102

10°

10°

10. ,

10 .. 1 I 10:

Figure 31: Graph for Earthfault current IDMTI-cable

43

i .. ~ 0 0 0 0

4.2.4.3 IDMI' 1

IDMT 1 relay located at low voltage transformer, therefore it must be grade with

overcurrent relay IDMT. The result that we have as Figure 32 and Figure 33.

We can see that from the graph, the earthfault line never cross the IDMT relay

graph. The author set the TMS value so that it meets the requirement for the next

relay to operate.

Earthfault setting: PS = 0.15

TMS=0.25

o,......., 1 07 a Frioh T"""' 1.07 a ···--·-----------------------

lr 2.2491<A iy OOkA

. ttr O.OkA

'

~~- ~IDMT2<nelol ~ ~

To ~10w•

The "'""""')' <edal..ble bts lhe al.otua d ol prcUcbon deo;ices II .ria ~~age. II )IOU .elect one d the lOWS n the table. deo;ices Ill the chooen ll.alua will be ~in the nol-k Oagllll. and mole~- in il'e nolwok .,.,._,provided thai in.'-"~ d ........

0

0 ---- .:__ 11 __ }

Operaled Ill ellier Que. boa not n ld polh.

Operaled Ill en. uoe on zone 2 ar hV>er Dperaled at e11ier Que an zone 1. A~a)......,_ CT hetlltlllled.

0 0 0 0

Figure 32: Result Earthfault current for IDMTl

44

596

Fie Edt Graph

raph: 1 10: IOMTl 1n (s)

Ofl'¥ica IEC2SSI 10' CT Rating IAl Dll.O Eslh PS (pu~ 0.15 Eslh TM (pu~ 025 Ofla«:10 10•

,.., 2

10 IOMT 0""""" IEC255-SI CT R*'!I!Al 6000 10' Pllase PS {pu) 0. 75 F'haoe TM (ilul 0 175 OHsol: 7171

10'

Refetence Volloge: '-' kV 1E a ••

r ---,---

1: 25.03i (IrA), T: 47.991 (s)

Figure 33: Graph for Earthfault current IDMTI-cable

4.2.4.4 IDMI'l-busbar, IDMI'l-motor and IDMI'2-motor

__j

u Frilh II

The same method use to grade this relays as overcurrent relays. Since IDMTl­

busbar and IDMTl-motor relays located at different feeder than the margin with the

previous relay must be 0.4 sec, but there is no margin required for IDMT2-motor

because it is in the same feeder.

Therefore, for IDMTI-busbar

Earthfault setting: PS = 0.20

TMS = 0.22

IDMTl-motor

Earthfault setting: PS = 0.20

TMS=0.05

45

IDMT2-motor

Earthfault setting: PS = 0.20

sub-bua1

SC5

Foult l r 2Z48kA ly: 0.0 kA It>- 0 OkA

TMS = 0.05

St-lnlonnatJOn N....,..,_, f1 - of 3 D uration: 0.&23 c Frioh Timec 0.&23 •

Tho ...........,y raaA• toble r.ata tho • t<ALU of ol protection dov;cee at this at-. II .I'(IU aolect one o f tho row• '" tho toble. dovices at tho chosen statu• will be highlighted n the nelwork diogram. and more conveniently. '" the n e twork ovennew. provided thai it na. been e>epanded sufficientlY.

Status Not operating and not in the foul path Not operatJng. but In the foul .,..._ _..;.a.;.._... Dnoctional rato&o not -aling becauee polenaotJon voltage ia too..__ 0

Oporellng but r-tequate ,_gin_

About to _at ... but not in fault path About to operate on zone 2 or 1-9-Aboulto -ate on zone 1 .

!--~~-~ Operated at_...--- but not in foul path.

Operated at eorlief • - on zone 2 or~­O porotod at ....,.,. •- on zone 1 A~al who- CT na. aaturoted.

0 0 0

0 0 0 0

Figure 34: Result IDMTI-busbar for Earthfault Protection

46

- ..... - )(' T: .. • • • • •• ~ •. - •• ' •. ·'

"" Edt Gl!>h laiiii1 IO:ID~Tl o....,.. IEC2S&SI CTR~~tlWlO Ed PS (pul 0.15 Ed TM (pul 0.25

1 o.-1o ,Gr<dl 2 I 10 IDI•Hl-lluoblr

Oeva: IEC2S&51 CT Ratng lA} 1250.0 EdPSW 0.2 EdTt.I(Jlul02 Offset 1 0

~1

Tme(a)

10' 2E 1f

II ..... II 10'

10:

10°

10°

10.1

10" 10° 10:

1: 962.'19 (A), T: 12163.1 (s)

Figure 35: Graph for IDMT 1 and IDMT 1-busbar

S tage lrlormalion

N...,.._ fl :i ol 3 o .. a~~on: O.lSSs

Tho ....,.,..,Y .-Ala table iota the atatua ol al protection r:lrwic:es 61 this atage If you ael!ocl one ollho rowa ., lhe table. devicM etlho c:no-. status will be hg~Wgtlled 1n the netwook ciagr-. and tn01e eonvenienlbl. in tho network OYeMew, provided that t hoa ~ expanded wffic:ient!y.

~talus II• OeW:ea 1 Not opera~ng and not in lho , ... pelh. 26

Drec:tional r~ not operebng .__..., poloriaalion ...,._ ia too low 0 I Not operatng. W in the ld path 6

OperaQno. 2 Operatng W inadequate mwgin. 0

585-0~

~10M T1 -bu:bar

sa sod.~

~ ' '

lr. 2.164 kA ly OOM lb: O.OM

'\..:Y

IDMT 2-motor

101>4 T 2<f110t012

!Abo<a to operate. w not in, ... pelh. 0 iAbo<a to operate on zone 2 or tV>er 0

Opereled et-"" ~- W not tn faA pelh. Opereled et-"" ataoe on zone 2 or tV>er Opereled el-"" stage on zone 1 R~s) whose CT hoa catu'eled.

0

0 0 0

a Hode,i""""*)' hble II Qose

Figure 36: Result IDMT1-motor for Earthfault Protection

47

~~ 9; ("\I l- • o1 ,.. "' "' ht"' -" 0\ ¥":. • HI • '-!.o't"' \(t • --

Roo Ell; Gtoph

rapk 1 10: IDMT1-bo.nbor Device: IEC255-SI CT Ramo~l12al0 E orlh PS (pu~ 0 2 Earth TM (pu~ 02 Ohoet 1 0

raplr 2 IO:IDMT1rnota Oevrco IEC255-SI CT R .. ing ~~ 12SO.O E.U. PS !Pul 02 Eortn TM ll>Ul 0 05 on~ 1 o

Tine (S)

10'

10'

10°

~ __..:~ (:!:"" ....

l l t

10'·+:------~------:-+-----:--------:-----~ 10° 10' 10

1 10' 10

1 10'

OlreR(A)

1: 33.118 (l<A), T: 13.961 (s)

Figure 37: Graph for IDMTl-busbar and IDMTl-motor

Stage lnlonnabon N.m-: r- : o/ 5 o ... otion: o. 159 • Fonosh TOne: 0.159 •

The summary redo table liato the atatuo of all poolecbon deviceo at !hit olage.

II you select """ olthe rowt i'l the l6blo. de~ at the chooen •letuo wl be higlllig,ted in lhe nelwotk diagram, and,.,.,... c:onvenienlllo. i'l the network o.......W.W. provided 1hat ~ has been eocpended sufficiently.

__ j _]

II Fnoh d

Statuo -------.....,.~-:---..

SS!:>-0~

~1-motor to IOMT2·""*'<

....,tc •• ~~.. ...~

T r~'~' Faul

lr. 2.1SolkA ly: O.OkA lb: 0.0 kA

Not ope<aling and not i'l the faul path. Not ope~oti'lg. but i'l the faul path.

- Diec:lionool rel<oy not _.aling becauoe pol..n.ation vall- ia too low 0 Ope~aling. 2 Operating but~· ma~gin. Abo<A to ate. but not in fault pa1h.

IAbo<A to ope<ata on zone 1 •

Ope~"'ed"'-·-·but not in fault palh. Opereted et -"" .._on zone 2 or higta'.

Opereted ot earliet ~~-on zone 1. Aelay(o) whole CT has -.eted.

d Hide£~ Table II

0

0 0 0

Figure 38: Result IDMT2-motor for earthfault protection

48

'f; I C""' ~ • • ~ '" ,. "t~ .,., -' • y:. " • ~·. ,.. y': •

Fte e.- Ciraph

r.P,: 1 ID: IDMT1-buobar Tme(s)

DIMeo: IEC255-SI 10' CT A '*'!liM 12&1.0 EllfthPS (put 02 Ellfth 1M (pul 0.2 OJJMI: 1.0 10'

r.P,: 2 ID IOMTl-rno!OI Davrce. IEC25'5·51 CT Flaln;IIAt 12&1. 0 10' E-'1-o PS (pu) 0.2 Elllh TM (put !l05 Ofttt't 10

r.P,: 3 10° ID: IDMT2-motar DIMeo: IEC255-SI CT Roq lA~ 12!i0.0 Earlh PS (pu~ 112 10° + Earth TM (pu~ 0.05 Offoet 1.0

10.1

10" 10

1

Reference Volto~: 1.1 •v ....

--+ - -

1: l0.613 (1<A), T: 196.19 (s)

!,'~ )(

Figure 39: Graph for IDMTl-busbar, IDMTl-motor and IDMT2-motor

The same steps apply to the other path but basically if the eart:hfault current

for the other path is same as the first path which have been discuss by the author

above, the result for the relay TMS and PS is the same. But if there is a different in

earthfault current, than the author need to grade the relay again. From this project,

eart:hfault current is the same at the same level of voltage, therefore the author just

need to grade the first path and can obtain the other coordination of relays.

49

CHAPTERS

CONCLUSIONS AND RECOMENDATIONS

5.1 Conclusions

This project, basically study on current protection coordination at GPPB.

Main objective of the project is to do grading margin for overcurrent and earthfault

protection from the source-TNB to the high voltage system is 6.6 kV motor so that

it meet all the requirements (stable, selective, sensitive, fast and reliable) to operate

safely to human life also to the other electrical component. For overcurrent it

related to 3-phase current fault and for earthfault it is related to the single phase to

ground fault. Both current faults needed in order to grade the relay. The best

coordination need to be find by getting the Plug setting (PS) and also Time

Multiplier setting (TMS) for the relay. These two components is a setting of the

relay to determine time for relay to operate. At the end, the coordination for

overcurrent and earthfault can be achieved

The author finished design the network inside ERACS software for high

voltage network and finished design the grading margin for the first path. While

doing the grading, the problem occur where the given Plug Setting (PS) and Time

Multiplier (TMS) value by the plant supervisor is too small and some consideration

such as:

1. Consider the maximum remaining time is 0.2 sec for relay at low voltage

transformer

2. Relay for bus that have only one feeder no need margin

From the result, the author cannot compare TMS and PS value with the real

value use at plant because the author cannot gets all TMS and PS setting values. But

50

still with the available value, there is different in PS value calculated and real use at

plant for earthfault protection relay.

A lot of lessons that the author learnt from this project which cannot be get

in class. The author learnt the steps taken to do grading margin, some characteristics

that need to be considered while grading, and learnt the usage of ERACS software

as one of the software use in Power system.

5.2 Recommendations

There are some recommendations that the author would suggest to be implemented

and corrected for this project:

I. Refer to the Relay Coordination for Earthfault Protection calculation, there

is a different in PS value for IDMT -cable!. The value should be 0.15 for PS

rather than 0.1 for PS use at plant.

2. The use of star-delta connection at 132kV/33kV is not suitable because the

earthfault current is too small at load side. The relay cannot detect if there is

earthfault occur and can only trip if the overcurrent or three phase fault

occur. The author suggests replacing the transformer with delta-star

connection

3. Value for NER use at plant is 100 at 33kV/6.6kV. But after calculation, the

author suggest to use NER = 1.820.

I _ MVA FL- ../3XVLL

25MVA ../3 X6.9kV = 2091.85A

NER =single phase voltage full load current

51

6.6kV f../3 l 820

2091.85 •

REFERENCES

[l] /EM Professional Interview Report, Protection Relay Coordination and

Protection Equipment Commissioning Testing of the 22KV Main Switch

Station (SSU) Satera Maju Project, Tenaga Nasional Berhad (TNB) Ipoh,

Perak.

[2] Hadi Saadat, Power System Analysis, Second Edition. McGRAW-HILL

INTERNATIONAL EDITION, Electrical Engineer Series.

[3] John J. Grainger and William D. Stevenson, Jr. Power System Analysis,

McGRAW-HILL INTERNATIONAL EDITION, Electrical Engineer

Series.

[4] A Guide book on Distribution Protection - Coordination of Protective

Device from Tenaga Nasional Berhad

[5) Distribution Protection System note by Unit Perlindungan (Kedah/Perlis)

Tenaga Nasional Berhad.

52

Appendixes

53

......,, 131<l.433 kV n~ SOkVA f -.::::~1 I -% -

=O!Jgoi'w

~ g

I

I SB5-AOII

i~~~l~ m-U-;Ut·" ]g'~jtn i"-'-ConlroiPIINI: II~ !~---~-! • - - - "J g,.~50A m> .... ..., ____________ :------·--: ___ :;_~:::,, _;_< ~

11L _ _., 1 ':,;.! .-' -"·' 1250A I I• •:$ I ~ToEICS

------::.1

To ElCS

EOOIIA ' J

FOR PROTECTION ANO"METERING SYSTEM, SEE INCOMNG CIVERtieAD UNEFEEOERNO,t

·•f--/d if~t"' .,

·•!--'""" ' ' J I SB5-A021 132 kV- 50 Hz.~1250A-31.5 kA3s ~---'/ l - \1

1b TR5-AB02

i -

SBS-E02

/ 1 125llA - ~'"OA I -= GCB L~ \ N.O olr-- · _I

7 12~A ~1250A

·•I-"

-""""-,---------] 1250A 1®88: ' GCB :!OJ88! ~-"·" l--:··-:----'

~

ToE!CS

)l'oEICS I j t

t

lbEICB (-

ToEICS

·:--

,~1 ToEICS

! ~ • ~-------, )121Xi'1A III'I"D< ~ ~ ~ ~! ~! u • ,,.. i =•v<J ;lAMP _______ j ~---~-i-i-~ ~i.

GCB N.C

TR5-AB02· ~ 13:2134.2 w 1 40150MVA Orum/Onaf Uec=:12.5%

[;;~]::::: :~1;::::

To EICS

FOR PROTECTION AND METERING SYSTEM, SEE 'fRS.ABO'I TRANSFORMER

"'"''

., ----- --) TR-BE02

~ ·--[o;;;J Deoo:llllrtet.:l<Rt

G;] ........ ,.,. -[':ji] IDMTO.....C~m..t

~ IOMT&thRdR

6iJ --"-'· ... ~ ,_,_..., B DirectlanoiO..Cu

G] Trip~Rt

l5lJ ·--15'1 """"-ll<'iJ Jlao~R~

[.;.;J ~&thF• /.LVSdo

~ .... ,_., Mlllfn!UBor1

~ a.. Bor PI<Ucim MillnS..8ar2

~ Buollllr~Zonl

® -@ -8 , w•t.~~ter

9 ... ._ ;;;] ' Seleclor91rich-(\ol

[\jJ 'SeloclorSIMII:h-l,k

e '~o.n.rtrl

9 -Fa ... -1""~;;""-:"'!i• ;.;,;.;~ ____ . _rr;,;-,:;~;~ '¥!'

1 ,-;: u~ [ ;··--- -~~~~~~~--------:--~/

:::r:::f=~=l=s~B=5=-B=0~l=l~~:•:v:-oo:~~-=,2:oo:AF·2:•~~:•·:'-:--:-:--:--~~===t~~=l· ---F::==~·==-~~~:I::~:::i~~-~~-~~==+===~l~s~B~5§-B~0~2~1:: ....... ...........

Equipped ..... '

TOGPPS Feeder 1 To EICS

As GPP 6 Feeder 1

~

ToEICS

ToGPPB Feeder1

As GPP 6 Feeder 1

*V : V~stgnaJa. fnHn Incoming vr. via elrcult bmlaker auxBiary switches to. identify switching cenflgunttlon

SINGLE UNE DIAGRAM 132 KV MAIN SUBSTATION PROTECTION & METERING GPP 5&6, TOK ARUN DRAWINGNO: 02

S8ssd Or! D"aMng No 05d120061-09

15-DOI I

50kW 'lrterpump

<750kW

ENGINE PANEL

~===1=:.n ~i SYNCHRONIZING

SECTION

I' b~l"·'' ~I "1110000 CD CD fl. 1+>1--"'l.....-~ = ~

® ® 88

®[l§]i)(l _ro.;;l.,

~

I

TR&-BD-01 3316.9 kV 20125MVA OnanfOoof Ucc=8% Taps +I· 2.5% ,5%

I VobQO-"""' f---a.-vro .... ~ l """"'-""' l I,

L~"' I -I' GENERATINO SET CONTROL PANEL

' ToEICS

6.6 kV, 50 Hz·2500 A

:::_: ToEICS

400A

1250A VCB

vcs 630A - ..-----,

e s kV 2;::L )I SBs-oos I

750 kW ·3'.5 MW

i i To EICS To EICS

! i i

From 33 kV SB5-B07

BusbarA

,,, ~·· ~

ToElCS

~

L-====r=l~F,Jl-, ' 'il' I~ ,, •

lf VCB '

,,

.. j. ' ···ToEICS I i

··­'""'""""'""'~~'·

t,fT~ il ~ ' ~ ~~ F!~ AT8-001 Typical

~""""' Feeders to (OPCU3)

TR5-DE-21

I ATS-051 '

TR5-DE-31 (GPP516 Utility) '

TRS..DE-418 TR5-DE-61

Spare (GPP5/6 Utility)

TR5-DE-91 (ACS)

(REfER TO TRS-DE-11}

2500A VCB 52AB N.O

" ;11{;1250A

VCB

•I' r:····•\

:-.-' To EICS

[S8s.OO. I Outgoing CircuitS

From

TR5-B0-02 am.ekv 20J25 MVA OnanJOnaf Uoo<8%

33 kV sa5-B06 -· Taps +I· 2.5% ,5%

'1 c®

-·· ,,c-,--t-1 ~

' lr Typical

Feeders to -:l -~ TR5-DE-32 (GPP516 Utllty) TR5-DE-42B TRS..OE-62

I (GPP516 Ub>ty) ..... (REFER TO TRI-DE-11}

~

,_ ,. I For Protection And Met8f!ng System, see TR5-B0-01

I SB5-D02 I

A 1250A \. VCB

"-----ll

0 ToEICS

. 1<'""1 -~ • E3J -·· ~

,_, -[5;] IDMTOWrCu'rlll

~ IOMI" Ellth FU

G;l --"""""""' GJ T~~R 81 T~Relay

~ ...... _.

l"il LJXt< out Relay Fe _ ... ~

,_,.. -~ --· ~ ......., ...

~/LV.olo

r;;;] ,_ EariiiFIUIR*i

~ T .... l!:tmo"DIJII -[::;;;] -----B FiefljFai>ftR'*

['];] OvliriUmrF~UqJ -~ Nogotiva~S

''" ["';;] ,.._,_ L:J ObfeFIIilnRW

Q --~ , __

[::;;;] ,:r"QhldTn

~ .......... ~ -~tmrlzi

® -· @ v•-Q --" SeloclcrSWtd>·f

'" --~ Gl ---Gl l<ioWaiiHol.o"""' --As Switch Board 885-005

[ SBS-004 I Outgoing Circuits

As Switch Board 585-003 il ,..,

TOEICS INTERFACE PANEL

r :sBS::iiii 1

SINGLE LINE DIAGRAM PR01ECTION AND ME1ERING GPP5 SUBSTATION GPP 5&6, TOK ARUN DRAWINGNO: 04

Ball8d On Orswlng No 06&'15120110f..06

·1901 KV tiNA =9.7%

B6-DOI I

ISOkW ..,.,_

ENGINE PANEL

TR&-B0-01 33.15.9kV 20125 WA OnaniOnBf

""""% r··--···----------------1

i-----0 I """"'"""" Taps +/-2.5% ,5%

l ·~~·"""" .. . . I '.. . • I l I

I ~==--a.i~ ... I <'IW!a._ ....

I __ , ,--;;;;--,1

; <:) o 1 c._::::'_j J ; \: GEHERATUG BET CONTROL PAHB.

ToE!CS

,-,

'"' To EICS

6.8 kV, 50 Hz~2500 A

1250A VCB

I I

'""" 33 kY SB$-903 BusbarA

~----

"~- - l .• I

T

, _ _I ____ 1 -~ f __ 'o'"' f - -1 I

~J­is :::l h d ~FROM

1

! ' VTBUSIIARS Typl~ Feeders to

TR6-DE-21l ri-;AT"-s-os="t------~ 1 ATS-001 (DPCU3)

p,;:oo,- I

<750kW 750kW-3.SMW

f8B6-liill

To EICS To EICS

l i i

TPR

TR6-D&. 31 II (GPP516 Utility) TR6-0E-41 I TR6-DE-61

Spare I (GPP6 Utility) TRS-DE-92 (ACS) TRS...OE-41 (ATS.D41)

(REFER TO TR&-OE.11)

'""" INTERFACE PANEL • ::r;.u ~ ~~~I I .... i I cr::J I 'o""

4!5V I SB6-EI2 I

'0""" ~

TRIS-B0-02 3319.lilkV 20/25 MVA OflaniOnal' u-.. Taps +I· 2.5% ,5%

'""" 33kVSS~ ..... ,.

,_ ,

I ~ f''"~ S~Ct.l

I"3J --Q] ·--~ -['=i] ICMTO...C..,..,.

[:;;_) IOMTEorlt\FdR

[5;,1 --0\oii"Curen!Rrta)

[;] Tr10~RI

81 , __

~ LcckllutRSI)Itt-... For ProtecUon And Metering System, See TR6-BD-01

l"il l.OI:IcO.. Relayf'Qr

,-, ,,., ToEICS

~I OUtgoing Circuits

Typtcal

r-------·-~~~,-·-·-------11 TR6-0E-22 I' ATS-052

I TR6-0E-32 I (GPP516 Utility)

I ATS-042

(GPPS Subs)) TR6-DE-52

Spare

(REFER lO TRI-DE-11)

L=l ·--- -·· ,-, ,,.,

To EICS

1250A vcs

I 886-004 I Outgotng Circuits

-·d ~ -~' -GJ ---· ~

,.. __ Ftl.llt/LVIIido

t;;;] ,_ ""'""'-

~ ,.......,_,_ -[;;;] ----~ __ ...,

['],] Ol'oriU'*F""''I' -~ __ .. -· ~ ---[::::;] Db:loF.._Riolr,

0 ....,, .... 0 --[;;;] ~IWITrar ..... ~ ........ ["Zl

... _ ® ....... GiJ -G --[jj] SelopU &Midi· f:J ~ ---(N !;;] ~Arrlpftlioo

!;] ICiid.rllalllil>ll'r.IU

Rslllti\o>TOII1'JPfl"'ll< As SWiktl Board SBS-005 As SWtch Board SB6-003 R ....

SINGLE LINE DIAGRAM PROTECTION AND METERING GPP6 SUBSTATION GPP 5&6, TOK ARUN DRAWINGNO: 11