power system protection - bau.edu.jo · power systems protection course department of electrical...
TRANSCRIPT
Power systems Protection
course
Department of Electrical Energy Engineering
Dr Audih alfaoury 1
Al-Balqa Applied University
Zones of protection
Is the place or the distance that the relay can protect
easily.Fig.1 shows an example of three protection zones for
three circuit breakers. It is to be noted that the protection
zones are overlapped.
3
Fig.1
Dr Audih alfaoury
Nota:-In power systems, all power system elements must be
covered by at least one zone
4
The important elements must
be included two zones or
more.
Zones must overlap to prevent
any element from unprotected.
The overlap must be finite or
limited, but small to minimize
the probability of outcome
fault from inside of this region.
A zone boundary is usually
defined by a CT and a CB.
The CT provides the ability
to detect a fault inside the
zone The CBs provide the ability to
isolate the fault.
The protection zone may be
open or close zone. Dr Audih alfaoury
6
Backup protection
It is an alternative protection that work when primary
protection fails to operate.
Primary and backup protection are independent ( relay,
breaker , CT,PT) .
Backup is slower time than primary.
Sometimes backup protection opens more circuit
breakers (that net necessary) to clear the fault.
backup protection become primary protection when usual
primary equipment out of service.
Back up relaying may be installed locally, in the same
substation (local), or remote in other substations(Clears
fault on station away from where the failure has
occurred).
Dr Audih alfaoury
7
Primary and Back up
protection at the same
location ( Local Backup)
Dr Audih alfaoury
Local backup
protection at
different locations
VT
CT CB
VT
CT
CB
8
Remote back up protection
Selectivity and zones of protection
Selectivity is defined in terms of regions of a power
system (zones of protection) for which a given relay is
responsible.
The relay will be considered secure if it responds only to
faults within its zone of protection. Dr Audih alfaoury
CT
VT VT
CT
CB CB
Primary Back up
10
Example 2
The tie circuit breaker (T) is assumed to work normally closed.
For a fault at CD, Line Breakers 5 and 6 should operate as the
primary protection. If Protection 5 fails to operate, with existing
technology, we have two possibilities for cutting the fault current
contribution from A, B, and F: open Breakers 1, 3 and 8; or open
Breakers 2 and T. In any case, backup protection needs time
delay. The primary protection needs to be given an opportunity to
operate before using the decision of a backup operation Dr Audih alfaoury
11
Local Backup( in same substation) Breakers 2 and T represent local backup protection, which is located in the same substation as the primary protection. Local backup protection is more expensive than remote backup because additional equipment is needed. Advantages of local backup over remote backup are greater sensitivity, greater selectivity, and faster operation speed.
Dr Audih alfaoury
12
Remote Backup ( in same substation)
Breakers 1, 3 and 8 are located in a remote substation. This is the remote
backup protection. An advantage of remote backup protection is low cost:
the remote backup protection comes from protection equipment that is
needed for primary protection functions of adjacent system elements.
Therefore, there is no need for additional investment.
Dr Audih alfaoury
13
Example 2: Consider the following simple power system:
Discuss the local and remote backup protection for two fault locations as follows:
Dr Audih alfaoury
14
Case 1: Local Backup
For fault at F1: Suppose that breaker J operate and breaker H failed to operate. Therefore: G and I must operate as local backup protection
Dr Audih alfaoury
15
For fault at F2: Suppose that breakers P and Q operate and breaker M failed
to operate. Therefore:
L must operate as local backup protection and it should tripped by
communication signal (Transfer Trip).
Case 2: Local Backup
Dr Audih alfaoury
16
Case 3: Remote Backup
For fault at F1: Suppose that breaker J operate and breaker H failed to
operate. Therefore:
E, F, L and M must operate as Remot backup protection
Dr Audih alfaoury
17
Case 4: Remote Backup
For fault at F1: Suppose that breakers P & Q operate and breaker M failed to
operate. Therefore:
I, B, and C must operate as Remot backup protection Dr Audih alfaoury