Building Your Biogas System Workshop 10 th March 2009. Power Purchase and Grid Connection Procedures. Aidan Foss ANF Energy Solutions Inc. [email protected]. ANF Energy Solutions. DG grid connection specialists No project ownership Current projects. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Power Purchase and Grid Connection Procedures

Aidan FossANF Energy Solutions Inc.

[email protected]

Building Your Biogas System Building Your Biogas System WorkshopWorkshop1010thth March 2009 March 2009

Page 2: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

ANF Energy Solutions

• DG grid connection specialists• No project ownership• Current projects

Biogas 21

Landfill Gas 2

Wind 25

PV 5

Small Hydro 3

River Turbine 1

• Increasing involved in research due to new connection issues

Page 3: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

The Grid Connection

HV FUSE

INTER-TIE CIRCUIT-BREAKER

GENERATOR CIRCUIT-BREAKER

TO DIGESTER & POWERHOUSE LOADS

INTER-TIETRANSFORMER

M REVENUE METER

BIOGAS GENERATOR

UTILITY FEEDER

HV DISCONNECT

LV DISCONNECT

LV FUSE

M REVENUE METER

HV FUSE

GENERATOR CIRCUIT-BREAKER

TO OTHERLOADS

INTER-TIETRANSFORMER

M REVENUE METER

BIOGAS GENERATOR

LV DISCONNECT

POWER EXPORTER NET METERING

LV FUSE

HV EQUIPMENTOWNED BY

FARMER

Page 4: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Getting Connected

• Power Purchase Options

• Grid Access

• Grid Connection Costs

• Grid Connection Process

Page 5: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Power Purchase

Options:• Embedded Retail Generator – market price• Net Metering – to 500kW• RESOP – Renewable Energy incentive• CESOP – Clean Energy incentive - ??• Green Energy Act – will replace RESOP

Page 6: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Renewable Energy Standard Offer Program (RESOP)

• Launched in Nov 2006• 11c/kWh + 3.52c/kWh for peak• 20 year contract with OPA• Up to 10MW, 50kV• Requires a CIA• Green, Yellow & Orange zones• Driver for flood of projects• Suspended in May 2008• Biogas OK to 5MW• Will be superseded by Green Energy Act

Page 7: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Grid Access Rights

• No guaranteed access rights

• Distribution Code has limited capacity

• Until 12 February 2009, Distribution Code was ‘First-come First-served’ for all generation in 10kW-10MW range

Page 8: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Hydro One Queue

Substation Capacity = 20MW

Queue Position Project

1 111 (10 MW)

2 222 (10 MW)

CIA Pending 333 (10 MW)

CIA Pending 444 (500 kW)

• Capacity limits due to feeder, switchgear and transformers• Speculative projects ahead in the queue could delay your

application by 2-3 years per project

Page 9: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Hydro One Queue Analysis

Project Size Applications

<500kW 39

501kW - 8.99MW 184

9 - 10MW 971

Full Substations 117 of 151

• From Hydro One queue 31-Oct-08• Over 80% in 9-10 MW range• Blockages started in windy areas – Great Lakes• Blanket applications in Eastern Ontario Aug/Sept 07• Small biogas being shut out from many agricultural areas

Page 10: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Wind & Farm Biogas

Wind & PV Farm Biogas

Typically 9-10MW Generally <500kW

Multiple applications financed by large corporations

Individual applications financed by farmers

Flexible on location Tied to farms

30-35% capacity factor 70-100% capacity factor

Competition between generators Co-operation between farmers

Grid access is first step - companies forced to speculate

No speculation, but forced to rapidly submit Form Bs

Removes opportunity for small biogas

No significant impact on wind farm development

Page 11: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Distribution Code Modification

12th February 2009 Amendment• Up to 250kW: Queue exempt on feeders

below 15kV• Up to 500kW: Queue exempt on feeders

above 15kV

Page 12: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Grid Connection Costs

• All costs up-front – unlike load customer• Distribution Network designed for load

customers• Deep Entry – Watch out for $$$:

– Protection upgrades– Anti-islanding protection– Recloser replacement– Voltage regulators

Page 13: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

The Single-phase Hydraulic Recloser

• Extensively deployed across Ontario

• Restores load customers in 1-2 seconds

• Simple, reliable• Can be a big problem

for generation

Page 14: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Grid Connection Process

1. Initial Feasibility Assessment2. Connection Impact Assessment

– Gives queue position– 12 months to CCRA

3. Connection Cost Estimate4. Connection Cost Recovery Agreement5. Connection Agreement

Page 15: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Grid Connection Process

• Distribution Code timescales not met – Hydro One swamped

• Generator responsibility for connection design, equipment procurement and protection design

• No simplified process for small generation

Page 16: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Terryland Farm 180kW Biogas

• Form A submitted Sept 2006

• CIA issued May 2007

• Commissioned August 2007

• Major delay due to Anti-islanding Protection

Page 17: Power Purchase and Grid Connection Procedures

Biogas Workshop10th March 2009

ANF Energy Solutions IncPower Purchase& Connection

Fepro Farms 499kW Biogas

• July 2007 – 1st Form B and CIA

• Highlighted several areas of unclear connection policy

• Pilot for new Anti-islanding protection strategy

• Scheduled for March 2009