power point of checklist of ij and sj jointing of 230kv xlpe-lg
TRANSCRIPT
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
1/8
132PMJ-003
No.Item
Description
Project Name1
2 Feeder Name
3 Cable
4
Work period5
Workplace
6 Joint
7 Jointer
8 Remarks
20 . . . ~ 20 . . .
PMJ
Jointer Chief Engineer P M
/ / / /
Approved
PMJ(IJB) CHECK LIST
230kV 1C 2,000 SQMM
Paya Lebar I ~ Paya Lebar II (F2)
LS Cable Ltd
LS Cable Ltd (Power Cable Construction Team)
Spore NDC 38
Paya Lebar I S/S (J/B # 1 A /1)
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
2/8
132PMJ-003
PhaseHeated
TemperatureAnnealing Condition
RemarksStarting time Reached time Heated hour
R
Y
B
3. Cable Annealing
Note : Annealing Heating : 853 Hr
Cooling : above 5 Hr
Description
Measured
Phasing out
Neggering
1. Preparation
Above 10
2. Material CHECK
Lot No.
Rubber Sleeve Insulator PlateBox NoDescription
R Y B
R
Y
B
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
3/8
132PMJ-003
L1 = 380mm
L2 = 220mm
L1 = 870mm
SIDE-A SIDE-B
50 50 50 50
5 4321
50 50 50 50
1 2 3 45
4. Cable Stepping
L3 =
80mm
L3
SIDE
A
SIDE
B
Surface condition
of insulator
(Good or Bad)
Measured
Position
L1
L2
1
L3
2
3
4
5
L1
L2
1
L3
2
3
4
5
R Y B
Stepping
L2 = 220mm
105mm 105mm
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
4/8
132PMJ-003
5. Semi Conductive Painter
250 950 250
220 90
Description
Cable Cutting(From end of sheath)
Measured
SIDE A : 950 mm
SIDE B : 460 mm
Exposed Conductor
SIDE A : 80 mm
SIDE B : 80 mm
Remove of OuterSemi-conductive layer
SIDE A : 220 mm
SIDE B : 220 mm
Remove of outerSemi-ConductiveLayers slope
SIDE A : 80 mm
SIDE B : 80 mm
SIDE
SIDE B
R Y B
6. Insert parts
No.
1
2
3
4
5
6
SIDE A
Shrinkable tube
(No.1175 200A-450L)
Coffin Box
Shrinkable tube
(No.1175 200A-450L)
Protective casing (A)
O-Ring
Insulating flange
SIDE B Y
No.
9
Description
Rubber Sleeve
Checking of inserting parts
Confirm of direction of SIDE A,SIDE B
R BYR B
YR B
220 40 304058030
460
Shrinkable tube
(No.1175 200A-450L)
Coffin Box
Shrinkable tube
(No.1175 200A-450L)
Protective casing (B)
O-Ring
Shrinkable tube
(No.1175 350A-900L)
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
5/8
132PMJ-003
7.Insert of Rubber Sleeve
1
2 5
L3
L2
L1
3 4
6
X Y X Y X Y X Y X Y X Y
A
B
C
A
B
C
X Y X Y X Y
A
B
C
A
B
C
1
PhaseDescription2 6
Description Phase
L1 L2 L3
3 4 5
Before insert
Before insert
After insert
Remarks
After insert
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
6/8
132PMJ-003
8. Compression of Conductor
L1 L2
R
Y
B
R
Y
B
Before
compression
After
compression
L1 L2 L3 3 4
Note :Check the dimension, before compression of conductor
L3
Corona Shield
2
1
3
4
1 2
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
7/8
132PMJ-003
9. Rubber Sleeve Setting
R
Y
B
Drawing Measured Drawing Measured
D 1 D 2
Drawing Measured
L 1
L2
L1
D1 D2
Teflon tape Markin
Drawing Measured
L 2
10. Supplementary treatment
Phase
R
Y
B
Drawing Measured Drawing Measured
D 1 D 2
Drawing Measured
D 3
Side A Side B
25 25 10
D1 D2 D3
-
8/11/2019 Power Point of Checklist of Ij and Sj Jointing of 230kv Xlpe-lg
8/8
132PMJ-003
11. Earth Connection Check
Phase Measured meggaring Cross Bonding wire
R
Y
B
12. Coffin box check
Phase Sealing of coffin box Filling of compound
R
Y