power plant sec
TRANSCRIPT
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 1/331
Signature of Bidder Signature of Purchaser1
FOR AUTHORISED USE ONLY
ÃÖŸµÖ´Öê¾Ö •ÖµÖŸÖê
GOVERNMENT OF MAHARASHTRAWATER RESOURCES DEPARTMENT
KAL HYDRO ELECTRIC PROJECT
(1 X 15 MW)
BIDDING DOCUMENT NO. SEGEMC/KAL/E&M/1
FOR
SUPPLY, ERECTION, TESTING AND COMMISSIONING OF TURBINE,GENERATOR AND ASSOCIATED EQUIPMENT .
VOLUME-I COMMERCIAL TERMS AND CONDITIONS OF CONTRACTVOLUME-II TECHNICAL SPECIFICATIONS OF TURBINE,
GENERATOR & ASSOCIATED EQUIPMENTS
VOLUME-II
OFFICE OF THE
CHIEF ENGINEER (ELECTRICAL)
HYDRO PROJECTS,
HSBC BANK BUILDING,
4TH
FLOOR, M.G.ROAD,
FORT, MUMBAI-400 001.
TEL. (022) 22670074, 22674867
FAX. (022) 22674996
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 2/331
Signature of Bidder Signature of Purchaser2
INDEX
Sr.No. Description Page No
SECTION – I INTENT OF SPECIFICATION 3-14
SECTION - II GENERAL REQUIREMENT 15-60
SECT ION II I SCHEDULE OF REQUIREMENT 61-76
SECTION IV MATERIAL OF MAJOR COMPONENT 77-82
SE CT IO N V TECHNICAL SPECIFICATION OF
TURBINE
83-162
SECTION VI TECHNICAL SPECIFICATION OF MAIN
INLET VALVES
163-183
SECTION VII TECHNICAL SPECIFICATIONS OF
STATION AUXILIARIES
184-208
SECTION VIII TECHNICAL SPECIFICATIONS OF
GENERATOR
209-291
SECTION IX TECHNICAL SPECIFICATIONS OF
SUPERVISORY CONTROL AND DATA
ACQUISITION SYSTEM
292-311
SECTIO N X TECHNICAL SPECIFICATION OF FORLAVT CUBICLE, NG CUBICLE, BUSDUCT,
AND ISOLATOR.
312-324
SECTION XI PROTECTIVE GEAR 325-3 31
SECTION XII DRAWINGS 332
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 3/331
Signature of Bidder Signature of Purchaser3
SECTION – I
INTENT OF SPECIFICATIONS
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 4/331
Signature of Bidder Signature of Purchaser4
SECTION – I
INTENT OF SPECIFICATION
INDEX
Sr.No. Description Page No
1.1
1.2
1.3
1.4
1.5
1.6
1.71.8
1.9
Scope of work
Hydraulic Data
Rating Requirements
Design Requirements
Layout Constraints
Design study/ calculation
Model test of TurbineData Sheets
Drawings and Data to be submitted with
Bid.
ANNEXURES-1-1
List of Drawings and Data to be submitted
with Bid.
5
6
7
7
9
10
1212
12
13
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 5/331
Signature of Bidder Signature of Purchaser5
SECTION- I
INTENT OF SPECIFICATION
1.1. SCOPE OF WORK:-
The scope of work comprise of the following:
To undertake the complete engineering, design, manufacture, assembly,
testing at manufacturer’s works before dispatch, proper packing, loading
at works, transport, delivery to site, unloading at site and stacking,
handling, loading at site store, transport at site of erection, onsite
erection, testing and commissioning and trial run of following plant and
equipment with spares, tools and tackles including composite insurance
upto taking over. The brief details of the plant equipment are as below:
Mechanical Lot :-
One number of Vertical shaft single stage turbine of Francis type.
Turbine shall be capable of developing Rated output of at least 15625
kW at 106m rated net head complete with governing equipment and all
auxiliaries.
One Number: Butterfly valve (2000 mm diameter approx) suitable for
connection with spiral inlet of turbine. Valve shall be designed for apressure of 175m of water column.
Penstock pipes. Matching pipes between penstock and Butterfly valve,
between Butterfly valve and spiral case of the turbine, between draft
tube liner and tail race joint. Further lot shall comprise of stiffeners,
supports and anchors for proper embedment.
Lot: Common auxiliary station equipment consisting of cooling watersystem, the power station drainage water system and draft tube/tail race
dewatering system.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 6/331
Signature of Bidder Signature of Purchaser6
Lot: Turbine junction boxes, switches etc. complete.
The above work shall be carried out on totality basis including the
incidental services mentioned in this document. Further the said work
shall be carried out in cooperation with the purchaser, and suppliers of
other equipment in a business like manner with utmost speed so as to
achieve overall economy and efficiency.
1.2. HYDRAULIC DATA
The hydraulic data and the other data regarding water conveyance
system is as follows:
A) LEVELS :
a) Minimum Draw Down level 140.50 mb) Full Reservoir water level 170.00 m
c) Maximum tail water level 35.00 m
d) Minimum tail water level 32.00 m
B) OPERATION HEADS
1. Maximum net head 117.00 m2. Minimum net head 84.00 m
3. Rated net head 106.00 m
4) Head variation 79.24 to 110.37%
5) Design Discharge 17.69 m3 /s
The turbine shall be designed based on the hydraulic data mentioned
above.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 7/331
Signature of Bidder Signature of Purchaser7
1.3. RATING REQUIREMENTS:
1) Output in turbine mode
The Turbine shall be so designed that Rated output of at least
15.625MW is developed at the coupling with generating under
the rated net head of 106 m
The bidder shall furnish information about maximum continuous
output at maximum net head of 117 m, at rated net head of 106 m
and at the minimum net head of 84.0 m in Annexure-V-5 and
data sheets of section V.
2) Turbine setting:
The Purchaser has tentatively chosen that the turbine setting
should be 0.63 m above the minimum tail water level. Further,the key dimensions / levels of the power house are tentatively
fixed based on the dimension of turbine and generator. For
example the levels such as the bottom of the draft tube, turbine
level, service bay level etc. The bidder shall examine this aspect
and give his recommendations about the precise requirements.
The proposed setting shall be such that adequate allowance is
provided under swing, shaft tube pressure pulsation,cavitationless performance, vibration and draft tube column
rupture etc.
3) Moment of inertia (GD2)
The moment of inertia shall be calculated and furnished. It shall
be by considering the maximum momentary speed rise, and
maximum momentary pressure rise
1.4 DESIGN REQUIREMENTS
i) The whole of the plant including all auxiliaries shall be
designed to give satisfactory service with designed
availability for a period of 50 years.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 8/331
Signature of Bidder Signature of Purchaser8
ii) Number of tripping :Ten (10) nos. per year
iii) Number of turbine : One (1) no. in five
runaway condition years life on an average.
iv) Closing of Butterfly : Every time the unit is
inlet valve stopped and brought to
standstill position.
v) The rotating parts of the unit shall be mechanically
designed so as to allow the continuous operation and the
stresses included in any part at maximum runway
condition shall not exceed 67% of the yield point of the
material of that part or 30% of the ultimate strength.
vi) The pressure containing parts of the unit for example theButterfly valve, the pipes and specials, the stay ring/spiral
case assembly and the guide vanes, shall be designed from
consideration of fatigue stresses induced due to cyclic
changes in pressure conditions. The guide vane regulating
mechanism shall be designed to have closing tendency and
minimum of lost motion and friction.
vii) The pulsation in power output in turbine operation shallnot exceed ±1.5% at full load output and ± 5% at partial
loads of actual rated power output.
viii) The maximum momentary speed rise as per IEC-41 clause
2.3.4.14 shall not exceed 1.5 times the rated speed.
ix) Maximum momentary pressure under most unfavorable
transient conditions accordingly to Clause 2.3.5.7 of IEC
4 1 shall not exceed permissible limit.
x) Whole of plant and equipment including the control and
protective equipment shall remain operative when
maximum credible earthquake occurs at site. Further, the
plant should trip and safely come to standstill when
earthquake of large magnitude occurs.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 9/331
Signature of Bidder Signature of Purchaser9
xi) The plant and auxiliaries shall be designed to operate
continuously for 12 months period without any offload
maintenance and to achieve high start-up reliability.
xii) The control scheme shall be so designed that in the event
of a collapse of the state grid system KAL HEP is
disconnected automatically.
xiii) When unit is in operation, the noise level in the turbine pit
liner 1 m away from shaft measured on any turbine floor
shall not exceed 90 dB (A) .
xiv) The generator and turbine bearing shall be so designed to
allow the unit to be frequently and quickly started.
Besides, the bearing shall be liberally designed such thatfull power output is available even if one of oil coolers of
any bearing is blocked continuously. In addition, the
volume of oil provided and circulating system shall be
such that none of the bearing would suffer any damage
during shutdown process in the event the unit is tripped
due to stoppage of cooling water / oil supply.
1.5 LAYOUT CONSTRAINTS :
The layout of power station is prepared with a view achieving over all
economy. The major dimensions and floor levels and the space provided
is given below
i) Width of the power station 15m
ii) Overall length of power station 32m
iii) Length of the service bay 10m
iv) Vertical distance between service bay
Level and the top of gantry rails. 11.6 m
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 10/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 11/331
Signature of Bidder Signature of Purchaser11
B. After award of Contract:-
The Successful bidder (Supplier) shall be required to undertake the
following studies and / or calculations:
1. Optimisation of the turbine runner and the hydraulic passages.
2. Review studies and/or calculation mentioned above on the basis of data
obtained on completion of detailed design and supply the result.
3. Conduct FEM study to determine the stresses induced and the pattern of
concentration of stresses in major components of the unit such as turbine
runner, guide vanes, head cover, generator stator frame and the bearing
brackets.
4.
Computations of forces on overhangs, generator lower bracketfoundations, stator foundations etc. under most unfavorable conditions.
5. Dynamic analysis:
Studies to determine the dynamic behavior of the unit rotating parts,
bearing brackets and the forces which would be induced and transferred
to civil foundations shall be undertaken by computer simulations. The
studies should demonstrate the unit and the foundations are capable of
withstanding without damage the abnormal conditions during trip outsand during runaway conditions.
Dynamic analysis by computer simulation of the unit vibratory
characteristics should be carried out to determine the amplitude and
frequency of the hydraulically and mechanically excited vibrations
originating within turbine, generator and entire water passage system.
The frequency of these vibrations should be compared with each other
and the natural frequency of related components to determine whether ornot there would be resonance. The comparison should include critical
speeds, major machinery components, draft tube pressure pulsations,
frequency and magnitude of vortex shedding from runner, stay vanes
and guide vanes, the unit dynamic imbalance, runner hydraulic
imbalance earthquake etc. All these natural frequencies shall be checked
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 12/331
Signature of Bidder Signature of Purchaser12
for adequate margin against predominant frequencies to avoid
resonance. Studies carried out in this regard shall be furnished.
The supplier shall duly analyse all cases of possible interferences of
different resonance frequencies and must ensure that abnormal vibration
shall not occur when the unit operating at any load from 60% to 100%
load turbine. Besides, such an operation shall not provoke power
pulsations at generator terminals.
1.7 Model Test of Turbine:-The performance guarantees i.e. output and
efficiency figures for turbine equipment being supplied under this
contract shall be on the basis of report of turbine model test already
carried out by the supplier for similar profile. The contractor shall
submit the test report along with calculations to prove the efficiency and
output of the turbine. If the calculation are agreeable to the purchaser the
model test will not be insisted and the turbine on the basis of data
furnish by the contractor will be accepted. If model test reports of
similar profile is not available with the supplier then model test shall be
carried out by supplier without extra cost to purchaser. In this case it is
assumed that price of mechanical lot is inclusive of price of model test.
1.8 DATA SHEETS
All data sheets appended to bidding documents must be completely
filled in by the bidder. The bidder shall specifically note incomplete
information or non supply of important information may result in
rejection of his bid.
1.9 DRAWINGS AND DATA TO BE SUBMITTED WITH BID
All drawings and data as per enclosed Annexure1.1 shall be submitted
alongwith the bid. The drawing and data shall be sufficient enough to
prove technical compatibility of the bid and shall not be limited to the
list of Annexure 1.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 13/331
Signature of Bidder Signature of Purchaser13
ANNEXURE 1-1
LIST OF DRAWING AND DATA TO BE SUBMITTED WITH BID
I- DRAWINGS
A) LAYOUT DRAWINGS PREFERRED SCALE
1. Plan and Cross section of Power house.
The drawing must show size of power
House required, the turbine Setting,
the excavation level below
the draft tube liner; turbine floor level
and generator floor level, Butterfly
Valve gallery level, the hook lift
requirement above the service bay
floor level and the required capacity
of the power station crane,
Drawing must indicate distance
between Butterfly valve center
and spiral case centre …….1: 100
2. Plan of the station at Butterfly
Valve gallery level showing the
equipment proposed and their
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 14/331
Signature of Bidder Signature of Purchaser14
location. …….1:100
3. Plan of power station at turbine
floor level …….1:100
4. Plan of power station at generator
floor level. …….1:100
5. Plan of power station at operating
Level. …….1:100
6. Power station Control room
Layout …….1:100
7. Draft tube
Hydraulic Design of the draft tube and
Elevation & plan of the Draft tube showing
the exact provision of steel liner ……..1:20
8. BAR CHART
The bidder shall furnish bar chart showing supply, erection
testing and commissioning activities of major equipments of
power plant. The overall schedule shall suite the completion
period of 22 months.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 15/331
Signature of Bidder Signature of Purchaser15
SECTION - II
GENERAL REQUIREMENT
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 16/331
Signature of Bidder Signature of Purchaser16
SECTION - II
GENERAL REQUIREMENT
INDEX
Clause
No.
Description Page No.
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.
2.11.
2.12.
2.13.
2.14.
2.15.
2.16.
2.17.
2.18.
2.19
General Requirements
Limits of contract
Interchangeabiltiy
Engineering data
Drawings
Supply of Oils, grease/lubricants and other
consumables.
Manufacturing schedule and the progress
reports.
Design improvements.
Erection - Tools and Tackles and Spanners
Foundations and fixtures
Materials and workmanship.
Electrical Equipment.
Earthing.
Units.
Protective Guards
Storage at site.
Rating Plates, name plates and labels
Tests
Applicable standards
17
17
17
17
18
20
20
20
21
21
21
39
47
48
48
48
48
49
56
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 17/331
Signature of Bidder Signature of Purchaser17
SECTION - II
2.1 GENERAL REQUIREMENTS:
The general requirements explained hereafter should be applicable to the
equipments to be supplied.
2.2 LIMITS OF CONTRACT:
Equipments furnished shall be complete in every respect with all
mountings, fittings, fixtures provided with such equipments and/or
needed for erection, completion and safe operation of the equipments
and are deemed to have been included. Further, these fittings, fixtures
and accessories shall be of the best standards and proven for use.
2.3 INTERCHANGEABILITY:
All parts shall be made to standard gauge in accordance with the normal
practice for the class of equipment concerned. All corresponding parts of
similar apparatus including spare parts shall be interchangeable.
2.4 ENGINEERING DATA:
The furnishing of engineering data by bidder shall be in accordance with
the provisions mentioned in the Technical specifications and the Data
Sheets annexed thereto. The review of these data by the purchaser and
his consultant will cover only general conformity of the data to the
specifications and documents interfaces with the equipments provided
under the specifications, external connections and of the dimensions
which might affect plant layout. This review by the purchaser shall not
be construed by the supplier, as limiting any of his responsibilities andliabilities for mistakes, omissions and deviations from the requirements,
specified under these specifications documents. All engineering data
submitted by the supplier after final design including review shall form
part of the contract documents and the entire work covered under these
specifications shall be performed in strict conformity.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 18/331
Signature of Bidder Signature of Purchaser18
2.5 DRAWINGS:
2.5.1 DRAWINGS AND DATA TO BE SUBMITTED WITH BID
Drawings and other data which is required to be submitted with the bid
is stated in the Annexure 1-1 of section I of this Volume.
These drawings shall include sufficient details to demonstrate fully that
the apparatus furnished shall conform to the provision and intent of
these specifications. Detail drawings or design data for the purpose of
checking the adequacy of the supplier’s design by calculations shall not
ordinarily be required but the purchaser reserves the right to call for
these in certain cases at his discretion. These drawing shall show
sufficient overall dimensions, clearance etc. required for assembling anddismantling and furnishing the space requirements of all apparatus to
enable the purchaser to determine the design and layout of the
installation and to decide the compatibility of the bid.
2.5.2 DRAWINGS AND DATA TO BE SUBMITTED AFTER AWARD
OF CONTRACT:
A) Drawings for approval:
The supplier shall furnish eight (8) copies of each of the
drawings, the list of which is given in respective specifications,
for approval of the purchaser. The methodology of submitting
these drawings to the officers of purchaser and/or to consultant
etc. shall be mutually agreed after award of contract.
The purchaser as far as possible will review the drawings
submitted by the supplier practicable within eight (8) weeks of their receipt. During the process the purchaser shall have the
right to call for additional clarification or to suggest changes,
which in the purchaser’s opinion, are required to conform the
equipment to the provision of the specification. The drawings
shall then be returned to the supplier along with comments and/or
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 19/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 20/331
Signature of Bidder Signature of Purchaser20
2.6 SUPPLY OF OIL, GREASE/LUBRICANTS AND OTHER
CONSUMABLE:
Sufficient quantity of oil, grease, lubricants and other consumable
required to put the whole of the plant including auxiliaries into
successful operation shall be supplied (i.e. deemed to be included in
scope) without extra charges.
The quality and the grade of the oil, grease and/or lubricants and other
consumable to be used shall be from the locally available suppliers.
2.7 MANUFACTURING SCHEDULE AND THE PROGRESS
REPORTS:
The supplier shall submit to the purchaser his confirmed manufacturingand delivery schedules for all equipments within thirty (30) days from
the date of notification of award of contract. This schedule will not
relieve the supplier of the delivery and work completion obligations as
offered by him with the bid. The schedule shall be such as to meet the
requirement of onsite construction. This schedule may be updated, if
required, and the changes, if any, must be informed to the purchaser
every quarter. The schedules shall also include the materials andequipments purchased from outside.
Every quarter a report highlighting the delays, if any, and the actual
progress achieved shall be submitted.
For substantiating the progress report, video films and copies of the
photographs (in duplicate) shall be supplied.
2.8 DESIGN IMPROVEMENTS:
The purchaser or the supplier may propose changes in the specifications
of the equipment or the quality thereof and if the parties agree upon any
such changes, the specification shall be modified accordingly.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 21/331
Signature of Bidder Signature of Purchaser21
2.9 ERECTION-TOOLS AND TACKLES AND SPANNERS:
A complete outfit of erection tools and tackles, gauges, slings, other
lifting devices, instruments and all other appliances required for the
assembly, erection, dismantling and maintenance of the plant should be
supplied. Spanners and wrenches shall fit the nuts and bolts used in the
plant.
2.10 FOUNDATION AND FIXTURES:
Foundations related to various equipments shall be prepared by the
purchaser on the basis of design data furnished by the supplier in line
with civil construction schedule. However, the supplier shall supply all
fixtures necessary for proper erection of embedded parts. If requested by
the purchaser, the supplier shall assist the purchaser in evolving special
designs and criteria for civil foundation works of the pump-turbine and
generator-motor unit. All supports, fixtures etc. needed for assembly,
erection, testing and commissioning including that for field tests shall be
prepared by supplier at his cost.
2.11 MATERIAL AND WORKMANSHIP:
2.11.1 GENERAL
All parts shall be manufactured true to drawing dimensions. All
tolerances shall be defined on the suppliers drawings for both
manufacturing and installation purposes. Holes shall be drilled full size
or under size and reamed during shop assembly. Punched holes will
only be permitted in plates 20 mm or less in thickness provided all such
holes are subsequently reamed full size during shop assembly.
The materials used in the construction of the plant shall be new of high
quality and selected particularly to meet the duties required of them.
The material specification shall be indicated in supplier’s detailed
drawings.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 22/331
Signature of Bidder Signature of Purchaser22
The use of materials liable to be attacked by termites or other insects
shall not be allowed. All workmanship shall be of the highest quality
throughout to ensure smooth running without vibration and noise under
all possible operating conditions. The design, dimensions and materials
of all parts, shall be so chosen that the stresses to which they may be
subjected shall not render them liable to distortion or damage under the
most severe conditions encountered in actual services.
Materials and workmanship shall conform to the latest editions of the
relevant standards.
2.11.2 PIPING:
All pipes and fittings (adequate number to be approved by thepurchaser), valves, drain plugs/cocks, test plugs, sight flow indicators,
meters etc. shall be provided so as to allow the operation and
maintenance of the system with ease.
All piping shall be clean inside and where ending in open connections
for other works, the piping shall have the ends capped for protection.
Valves shall be easily accessible and gauges and other operating or
indicating devices shall be located so that they can be convenientlyoperated or read from the floor walkways. Valves shall be suitable for
the services intended. Either a blind end flange or a pipe shall be
provided wherever necessary to protect valves.
Where piping systems must be disconnected for servicing, flanges or
unions shall be provided and the piping, valves and joints shall be
arranged for minimum disturbance or interference with other parts
during operation.As far as possible, the pipes shall not be embedded but shall run in
trenches or shall be suitably supported by hangers, brackets, hooks,
pedestals, or any other support suited to the requirements, care being
taken to avoid vibration at the supports. An adequate allowance for the
expansion of pipes under service conditions shall be made. Each drain
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 23/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 24/331
Signature of Bidder Signature of Purchaser24
removal in the course of operation, shall be made of corrosion resistant
steel or bronze.
Spring type washers will not be permitted where they may damage any
protective castings. Special tools, wrenches and devices found to be
necessary for the completion of the work should also be provided under
this contract.
2.11.4 FORGING:
All highly stressed forgings shall be subjected to examination internally
for the detection of flaw and heat treatment for the relief of residual
stresses. Particulars of the heat treatment proposed for all forging shall
be submitted to the purchaser.
2.11.5 CASTINGS:
The casting shall not contain damaging defects and shall be
satisfactorily cleared before use. The surfaces that are not machine
finished and which will be exposed after their final installation shall be
such that grinding at the site will not be required before painting. Thepresence of defective material shall be determined and it shall be
removed down to sound metal.
The cast parts shall be homogeneous and free from excessive non-
metallic inclusion. An excessive concentration of impurities or a
separation of the alloy elements in the critical points of a cast part shall
be sufficient reason for its rejection.
The casting of the main parts, including all those subject to hydraulicpressure and all castings which undergo a major repair, shall be tested
using radiographic, ultrasonic, dye-penetration, magnetic particle or any
other standard non-destructive test method. The expenses incurred on
such tests shall be to the suppliers account. In case of bus duct only
10% radiography of enclosure shall be done.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 25/331
Signature of Bidder Signature of Purchaser25
Minor defects or imperfections, which definitely do not affect the
strength or utilisation of the cast parts, may be repaired by welding,
according to the accepted practice for the repair of such parts.
Thickness and other dimensions of the cast parts shall agree
substantially with the dimensions shown on the drawing and shall not be
reduced by shop or casting practices to such extent that the effective
strength of the cast parts shall be less than the stresses allowed by these
specifications.
Use of cast iron for parts subjected to tension or impact shall not be
permitted without the approval of the purchaser.
2.11.6 WELDING
Supplier shall specify clearly on all relevant drawings, the amount and
type of material for each type of weld, supplier shall also provide
detailed drawings showing joint preparation required for each type of
welding to be carried out on site and at supplier’s works.
The parts to be joined by electric welding shall be cut precisely to the
correct size by methods suitable for the type of weld to be used and to
allow proper penetration and good fusion on the weld with the basemetal. The cut surface shall not have visible defects such as scales;
superficial defects caused by shearing or torch cutting operation or any
other damaging defects. The surfaces of the edge to be welded shall be
free from rust, oil, grease and other foreign matter. All welds exposed
to water flow shall be ground to a smooth and even surface flushed with
the adjacent plate.
Supplier shall indicate on the detailed drawings, the type, sizes andmaterial of electrodes he proposes to use for shop and/or field welding.
Unless otherwise stated, all non-destructive tests shall be carried out.
All major welding and all welding carried out on tanks and vessels,
which will contain liquid under pressure or compressed air shall be
subjected to 100% radiographic examination. In those cases where it is
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 26/331
Signature of Bidder Signature of Purchaser26
impossible to carryout radiographic inspection, or otherwise stated in
specifications, it may be replaced by ultrasonic examinations or any
other non-destructive test systems.
2.11.7 SURFACE TREATMENT AND PAINTING:
1. GENERAL
Where necessary the work shall be painted or treated with protective
coating to protect them from corrosion and to neat and pleasing
appearances. This work shall comprise the surface treatment, priming
and application of paint or metallic coatings in the supplier’s workshops
and at the site including all paint repair work becoming possibly
necessary.Every possible attempt shall be made that the design of the equipment is
such that all surfaces can be finish coated or recoated after erection at
the site.
Unless otherwise specified, the coating and painting shall be carried out
in accordance with the latest International Standard (Protective coatings
for steel structures, directions) or another equivalent approved standard.
All priming and painting material shall satisfactorily fulfil therequirements imposed by the site conditions (considering also possibility
of extended periods of storage at site) as well as the stresses to which the
respective equipment is subjected during operation of the works Shade
of the finishing coatings shall be as per the standard colour tables at the
choice of the purchaser.
Each coat of primer and paintings shall be compatible with the previous
and subsequent coats. All pigmented primers and paints, which will be
used for priming and painting at the site shall be delivered in original
and sealed containers packed by the supplier.
The supplier shall supply full details regarding the extent by which sand
blasting; priming will be carried out in his workshops (or his sub-
suppliers as the case may be), at the site and after erection.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 27/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 28/331
Signature of Bidder Signature of Purchaser28
All working of the material (e.g. welding, drilling, grinding) shall be
completed and surface defects (e.g. weld splatter, burns, cracks, surface
laminations and pitting), likely to be detrimental to the protective
coating shall be removed before surface preparation begins.
As regards welding joints, these shall be covered with one coat of
appropriate primer shortly after welding wherever possible. Otherwise
they must be cleaned with a steel brush before applying the first primer
coat.
3. PRIMER, FINISHER AND PAINT APPLICATION
Before the application of the primer all sand blasted or otherwisemechanically created surfaces shall be subject to thorough cleaning
process during which all dirt, dust, grease, moisture etc. is removed so
that the primer is applied on suitable surfaces. Clean cloth and pure
dissolvent shall be used for this process.
The primer may be applied by airless spray gun, roller or by brush.
All subsequent coats of paint shall be applied using airless spray
equipment, unless otherwise recommended by the paint supplier or
approved by the purchaser and or consultant.
Where the use of airless spray equipment is found impracticable, the
supplier must be prepared to use brush application at no additional cost
to the purchaser, such application being to the approval of the paint
supplier and the purchaser.
The paint supplier’s instructions shall be followed implicitly withrespect to the method of application of the paints, the drying time
between coats and the temperature of the material being painted, where
ambient temperature, relative humidity or dew point will affect the
drying or curing of paint, the manufacturer’s recommendations shall be
followed.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 29/331
Signature of Bidder Signature of Purchaser29
Unless specifically recommended otherwise by the paint supplier or
approved by the purchaser, not less than 24 hours, not more than five
days shall lapse between priming and successive coats of paint.
Each coat shall be free from runs, drops, pin holes, waves, lops, sag and
unnecessary brush marks.
Particular care shall be taken to provide adequate paint film cover on
corners and edges, nuts and bolt heads.
Equipment contained in cubicles, cabinets or similar enclosures shall be
painted as if it were exposed to view and the inside surface of the
enclosures shall be painted semi-gloss white. In sheet metal enclosures
where otherwise the surface would not be protected against corrosion(e.g. between the surfaces of spot welded joints and behind stiffening
channels), such surfaces shall be coated before assembly with an
approved spot welding primer after preparation of the surface in
accordance with the paint supplier’s instructions.
All paint shall be delivered to the point of use in unopened containers
bearing the manufacturer’s label which shall include, where appropriate
for special systems, date of manufacture, batch number and instructions.All paint shall be supplied in the ready-mixed condition and except to
comply with the supplier’s direction, mixing of paint by the supplier
shall not be permitted.
Machinery paint may be thinned, if necessary to permit satisfactory
application, but the amount of thinner shall be kept to a minimum.
Special attention has to be given to the two-pack coating. The
application of these materials is no problem if the specification is strictly
followed. For a perfect application the following important and
generally valid conditions apply:
The prime coating should be applied immediately after or at least on the
day of blasting (exception only in air conditioned rooms).
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 30/331
Signature of Bidder Signature of Purchaser30
After the mechanical treatment but before the top coating is applied, the
prime coating has to be cleaned (grease, oil and other impurities) with
solvents and/or hot stream.
- Application temperature for two-pack epoxy-resin coating at least
5°C
- Surface temperature minimum 5°C above dew point.
- Maximum atmospheric humidity: not higher than 75%
- The proportion of mixture for two component products is to be
strictly followed.
- Waiting times between coatings to be observed according to
specification.
- For multilayer it is advisable to change the shade of colour (forlater abrasion). Otherwise abrasions have to be checked by
measuring film thickness.
- Edges have to be pre coated.
- Not to prime a strip of 150 mm beside the planned site welds
(especially important for zinc rich primers.).
- Prior to the top coating, the prime coating has to be repaired
carefully.
4. GALVANISING:
All drilling, punching, tapping, cutting and bending of the parts shall be
completed and all burrs removed prior to galvanising.
Galvanising shall be applied by the hot dipped process and shall consist
of the smooth clean zinc coating free from defects and of uniform
thickness. Original blast furnace raw-zinc (minimum purity 98%) shallbe used. The zinc coating shall weigh not less than 600 g/m² of area
covered. Sheardizing or other alternative process shall not be used
without the approval of the purchaser and/or consultant.
Material on which galvanising has been damaged shall be re-dipped
unless, in the opinion of the purchaser, the damage is local and can be
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 31/331
Signature of Bidder Signature of Purchaser31
repaired by applying a coat of galvanising repair paint where such repair
is authorised the damaged area shall be cleaned by wiping with clean
rags saturated with mineral spirits or xylene followed by wire brushing.
After wire brushing, the area shall be re-cleaned with solvent to remove
residue and shall be given a minimum of two coats of zinc primer
containing not less than 98% (by weight) of metallic zinc in the dry film,
which shall have a total thickness of not less than 60 micrometers.
Galvanised surfaces should be kept apart in storage and transport. If this
is impossible, they should be treated by dipping in a 10 to 18% solution
of chromic acid, which should produce a coating of 12 micrometers.
This coating must be removed before any painting is attempted.
5. METAL SPRAYING:
Subject to the approval of the purchaser where an item is of a size or
shape to render hot-dip galvanising impracticable, zinc spraying or other
approved method of coating may be adopted.
Metal spraying of surfaces shall comply with the following procedure:
Surface preparation prior to spraying shall be dry grit blasting to a
standard approved by the purchaser and/or consultant.Immediately after grit blasting, the surface shall be cleaned of any traces
of blast products on the surface and in pockets, pits and corners by
brushing with clean brush, blowing with compressed air or vacuum
cleaning.
The surface shall be coated with the metal spray before discolouration
occurs. In the event of the surface becoming contaminated e.g. with
rust, oil or dirt between blast cleaning and applying the metal spray, it
shall be re-cleaned by repeating the above procedures. Care shall be
taken to have as little roughness as possible on the sprayed surface.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 32/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 33/331
Signature of Bidder Signature of Purchaser33
The material can only be applied with a special machine. Standard
application is one coat. Because of the lack of solvents in the painting
material, there is no danger of pores. Total film thickness: 360
micrometers.
REMARK: Condensation zones where the colour is not visible from
outside may be coated with epoxy coal tar.
8. NON-CORROSIVE MATERIALS
Normally highly alloyed stainless steels, Ni:Cr. 4:13 (can be corrosive if
soiled) and bronze e.g. red brass are not to be coated.
It is important, however, that the contact areas stainless steel/normal
steel are carefully protected by coating, also a stripe of the non-corrosivematerial, otherwise an amplified corrosion may occur (Contact
corrosion).
Machine with long rest periods (e.g. pumps) are exposed to increased
localised corrosion similar to ‘pitting’ (localised corrosion) usually on
the base materials when the coating is porous and damaged.
EXCEPTION: If a stainless steel part required a coating due to reasons
such as photographing or decoration, a water and oil resistant syntheticresin primer should be applied. Such coating has to be especially
required by the purchaser.
9. ZONES WETTED BY CONDENSATION:
The main strain for zones wetted by condensation is the permanent
rewetting, i.e. interchange: wetting - drying.
The visible surfaces are less stressed. However, surface quality and
appearance (shade of colour) require a high standard of material. Gloss
and semi gloss finishes facilities cleaning.
Due to practical reasons visible and invisible (dry) surfaces are not
differentiated. The same applies for visible surface of stainless
materials.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 34/331
Signature of Bidder Signature of Purchaser34
The coating system is set up as follows:
Prime coating:
One layer of two-pack zinc rich epoxy primer to avoid ‘under rusting’ if
the topcoat is damaged or porous. Film thickness 60 micrometers.
Intermediate Coating:
One layer of two-pack micaceous iron oxide epoxy paint (two coats if
exposed to condensation). The micaceous iron oxide in lamellar from
embedded in the epoxy oxide is a perfect pore protection and has
excellent adherence properties for the top coating. Film thickness: 60
micrometers,
Top coating:
One coat:Either polyurethane acrylpolyol micaceous iron oxide coat of 60
micrometers (recommended for outdoor coating providing a mat glossy
surface).
Or polyurethane top coating of 60 micrometers with a glossy surface,
usually applied for indoor coatings. The polyurethane based topcoats
have very good abrasion and mechanical resistance in addition to a
proven corrosion protection and excellent colour retention.Total film thickness: 180-240 micrometers.
REMARK: Parts covered with epoxy coal tar on the waterside should be
coated with the same material on the condensation waterside if the shade
of colour is not important.
10. OIL WETTED SURFACES:
For Oil tanks, bearing casings, servomotors etc. a standard coat as a one
pack synthetic resin primer is sufficient. This coat is oil and water
resistant up to 150°C. The first primer is applied before the tightness
test and the second coat is applied after assembly. The total film
thickness: 80 micrometers,
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 35/331
Signature of Bidder Signature of Purchaser35
11. COATING OF MACHINED SURFACES:
Machined surfaces require a two-pack epoxy resin zinc chromate or zinc
phosphate pigmented prime coat to improve adhesion to the base
material. A standard top coating may then be applied, depending on the
strain the parts are exposed to total film thickness: 120 - 160
micrometers.
REMARK: Generally sand blasting after machining (if possible) is
preferred because of the adhesion of the paint. Sand blast surfaces may
then be coated in the normal manner.
12. BLANK SURFACES
These surfaces are only to be protected for transportation and temporary
storage with a soluble lacquer.
13. PIPEWORK
WATER PIPES
All such pipes, except those of corrosion resistant material shall be blast
cleaned and be coated by dipping in acid free hot bituminous compoundto give an acceptable finished coating thickness.
Ends of pipes and tubes subject to weld joining at the site shall be left
uncoated over a distance of approx. 100 mm. After site welding the
erection welds shall be coated with 2 layers of zinc-rich primer
containing not less than 95%(by weight) of metallic zinc in the dry film,
which shall have a total thickness of not less than 60 micrometers.
Finishing of the ends of pipes and tubes interior shall be by a layer of zinc rich chlorinated rubber paint.
The exterior of small pipes shall be carefully cleaned and pickled and
coated with 2 layers of zinc-rich chlorinated rubber paint.
Exterior surfaces of pipes and tubes, except those of corrosion resistant
materials shall be primed with three layers of red lead paint on
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 36/331
Signature of Bidder Signature of Purchaser36
chlorinated rubber/synthetic resin basis (total minimum thickness of the
dry film: 100 micrometers). Un-insulated and unwrapped pipes and
tubes shall receive two subsequent layers of finishing paint on the same
basis (total minimum thickness of the dried finishing coats: 60
micrometers).
OIL PIPES
Both the interior and exterior shall be thoroughly cleaned and pickled
and rinsed very carefully to an approved method. The exterior surfaces
shall subsequently receive two layers each of oil resistant priming and
finishing varnish or enamel,
A corrosion prevention compound shall protect the interior of fuel
carrying pipes.
AIR PIPES
Same treatment and painting as for the water carrying pipes. The
purchaser will decide on the finishing shades at a later date.
AIR DUCTS
External surfaces shall be coated with 2 layers each of priming and
finishing paint.
14. CUBICLES AND CABINETS
FOR INDOOR INSTALLATION
After careful sand blasting all cubicles and cabinets shall be given two
priming and two finishing coats of varnish or enamel which in case of
those carrying oil or liable to oil vapour exposition shall be oil resisting.
A minimum dry film thickness shall be 100 micrometers in total.
The insides of cubicles and cabinets where condensation is liable to
occur shall be coated with four layers of an approved anti-condensation
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 37/331
Signature of Bidder Signature of Purchaser37
composition. Other inside surfaces shall be coated with at least two
layers of varnish of semi glass white.
External surfaces of cubicles and cabinets shall be given to supplier’s
standard primer and machinery enamel or appropriate enamel for
cubicles being used indoors for electrical equipment. All cubicles being
located in one row must be painted with the same shade.
FOR OUTDOOR INSTALLATION
These cubicles and cabinets shall be given after careful sand blasting
and hot dip galvanising coat inside and outside. After etching these
should receive two layers each weather resisting varnish or enamel.
15. STEEL CONSTRUCTIONS
INDOOR
Same shall be thoroughly sand-blasted and provided with (two hours
later) three layers of red lead primer on chlorinated rubber/synthetic
resin basis (total minimum dry film thickness: 100 micrometers.)
Finishing shall be by 2 respective coatings on the same basis (totalminimum dry film thickness of finishers: 60 micrometers).
Areas subject to oil and grease shall receive four layers of oil resistant
priming and finishing (varnish or enamel). This shall apply in particular
to all transformers.
OUTDOOR
After careful blast cleaning with an approved method and cleaning of
the surface after this process, all steel structures shall be heavily hot dip
galvanised.
16. WORKSHOP EQUIPMENTS, PUMPS, COMPRESSORS ETC.
Treatment as per the supplier’s practice, and coating with the supplier’s
standard primer and machinery plant.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 38/331
Signature of Bidder Signature of Purchaser38
17. PLATFORMS, HANDRAILS, COVER PLATES, TRENCH
COVERS, ACCESS LADDERS ETC.
All gratings shall be heavily hot-dip galvanised. Aluminium alloy
chequered plates need no treatment and protection.
Ferrous chequered plates shall be heavily hot dip galvanized.
Handrails shall be heavily hot dip galvanized. These should after
etching receive 2 layers of oil resisting varnish or enamel.
18. PARTS IN CONCRETE
The surfaces shall be cleaned from mill scale, dirt, oil, grease and other
residues and shall be covered before leaving supplier’s premises with a
substantial coating of Portland cement wash or other proprietary coating.For parts in concrete, it is important that the zone between visible surface
and zone in concrete, a stripe of approx. 0.5 m of the concrete be coated,
along the visible surface.
Components under high pressure (penstocks or spiral cases) touching in
concrete should be sealed additionally.
2.11.8 BALANCINGFor small rotating machinery all rotating parts and assemblies shall be
well balanced both statically and dynamically at the supplier’s works.
The supplier shall rectify any out of balance that may occur during
erection at site. Over dimensioned and heavy rotating machinery shall
be statically and accurately balanced at the point of installation.
2.11.9 DOWELLING
At all stages of assembly, where accuracy of fit has to be assured
on-site, dowel holes shall be provided with dowels to assist
reassembly and load resting if needed.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 39/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 40/331
Signature of Bidder Signature of Purchaser40
The alternating current (A.C) motors of rating ≤120kW shall be
provided with direct on line starter at supply voltage of 400V and
those of rating > 120kW shall be provided with star/delta starter.
Rated power of motors shall be guaranteed at 85% rated voltage
and 95% of rated frequency with closed air cooling according to
IEC standard with interchangeable possibility.
The pump capacities and the rating of the driving motors shall
have liberal margin over the requirements. Motors shall be drip
proof.
All pumps shall be designed and constructed to ensure quiet and
satisfactory operation without undue noise or vibration under all
conditions of discharge and pressure. Centrifugal pump casings
shall be designed to produce smooth flow with gradual changes
in velocities. In addition, the pumps shall be easily removable
and replaceable. Suitable gaskets shall be provided for all pipe
joints to ensure that they are leak proof. If any strainers are
required with the pumps, these shall be included in the bid and be
duplex type or with by pass to enable periodic cleaning.
All pumps shall be complete with the necessary piping, both onthe suction and delivery sides and with all fittings suited to the
size and duty of the pump. Adequate number of valves as stated
earlier shall be furnished with each pumping unit to suit its
operation and maintenance. Wherever necessary, pumps shall be
provided with suitable flow meters or flow indicators and
pressure gauges to measure the discharge and the pressure
delivered by the pumps. Suitable eye bolts or lifting lugs shall beprovided on each pumping set to facilitate handling.
2.12.3 ELECTRIC MOTORS AND MOTOR CONTROL GEAR
All motors furnished by the supplier, for driving the unit
auxiliaries and other apparatus shall be directly coupled to the
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 41/331
Signature of Bidder Signature of Purchaser41
apparatus driven and shall be suitable for operation on purchasers
power supply. All motors to be supplied shall be energy efficient
motors.
The enclosure of each motor shall be of the type best suited to theservice conditions of the motor and shall be subject to the
approval of the purchaser in every case. The motor shall
generally conform to the relevant Indian or IEC or other
equivalent standards. The insulation shall be moisture, oil, oil
vapour, drip proof and the motors shall be entirely suitable for the
operation in the tropical climate conditions prevailing at site with
100% humidity (degree of protection IP 54 or as applicable).
Motor shall be provided with varnish cambric or glass insulation
class F and shall be used for connections from the windings to the
terminals. All motor terminals shall be of stud type and totally
enclosed.
The capacity, speed and torque characteristics of the motors shall
be suitable for the starting and operating requirements of theassociated apparatus. The supplier shall furnish necessary
starting, protective and control gear with each motor.
Instantaneous and thermal overload protection shall be provided
for the motors together with remote indication of the operation of
the protective gear, wherever necessary. In the case of essential
motors stoppage of which would result in serious damage the
thermal overload protection devices shall be arranged to givealarm only, without disconnecting the motors. Red and green
indicating lamps shall be furnished for indication of the closed
and open positions respectively of motor contacts. The control
and indication equipment shall be suitable for operation with 220
V DC supply.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 42/331
Signature of Bidder Signature of Purchaser42
Special type of motors, not adequately covered by the
specification may be offered for any special application, but these
shall be subject to the approval of the purchaser.
2.12.4 SMALL WIRING
All small electrical wiring of various equipments, panels, etc.
shall be completed at the supplier’s work as far as possible. All
small wiring shall be arranged neatly into flat or rectangular
groups and shall be adequately supported with cleats etc. The
small wiring shall be so arranged as to reduce the number of
bends or crossing to a minimum. There shall be no splices in the
wire and all connections shall be made at the terminal studs orterminal blocks. Similar circuit shall be arranged to terminate as
far as possible on adjacent terminals to facilitate grouping and to
minimise the number of interconnecting cables. Secondary or
control wiring including leads from the current transformers,
temperature detectors, alarm contacts, speed and pressure
switches etc, shall be enclosed in conduits and shall be carried to
dust and water proof and oil tight cabinets located convenientlyfor connection to the control cables.
Pressure circuits shall be suitably protected so that failure of one
circuit shall not cause the progressive failure of adjacent circuits.
Alternating current circuits, direct current circuits, shall be
grouped separately and the wiring of each of these groups shall
preferably be segregated.
For the purpose of easy identification, tracing and reconnectionthe wiring shall be colour coded according to relevant
international or IS standards and shall be fitted near the terminals
with ferrules or such other cap indelibly marked with the
identification number corresponding with that of the associated
terminal blocks. When an electrical circuit is extended to several
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 43/331
Signature of Bidder Signature of Purchaser43
pieces of equipment necessitating sectionalising of circuit wiring
at the terminal blocks of the corresponding equipments common
identification numbers shall be used for the designation of the
circuit at all the terminal blocks and connections. The terminals
and circuit designation for all wiring shall be subject to the
approval of the purchaser.
All small wiring shall be switchboard type, single conductor,
tinned annealed copper wire, PVC insulated cables as per
relevant Indian or International standards, insulated with
varnished cambric, which has proved its utility in tropical region
against hot damp and moist climatic conditions and wiring
complying with the relevant international standards. All small
wiring shall have oil and oil vapour proof insulation. The sizes
of the wiring for different circuits shall be so chosen as to provide
ample margin for the purposes intended and shall be subject to
the approval of the purchaser.
2.12.5 TERMINAL BLOCKS
Terminal blocks shall preferably be made of suitable moulded
plastic material and shall be provided with brass stud inserts for
terminating the outgoing end of the cubicle wiring and the
corresponding wiring of the incoming end. Provision shall be
made on each block for holding 15% extra connections.
Easily removable shrouds, moulded from transparent dielectric
material, shall shroud all blocks. The terminal block shall be of
disconnecting type and suitable for max. 1000 V service and
dielectric test of 2000V.
Sufficient space for receiving the control cables inside the
switchboard at the bottom of the switchboard cubicles and
mounting arrangements for the terminal glands shall be provided.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 44/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 45/331
Signature of Bidder Signature of Purchaser45
quantity or state under all conditions of operations and any error
due to change in the ambient temperature, over the entire range of
temperatures obtainable at site, shall be kept to a minimum. The
instruments shall be provided with all the auxiliary appliances
and any special tools required for their maintenance.
MKS (meter-kilogram-seconds) units shall be used for marking
the instrument dials. The range shall generally be such that the
normal operating values are indicated in the middle third of the
scale.
All electrical instrument coils shall be designed for continuous
operation on at least 120 percent of the full rated current and
voltage of the instruments. The instrument coil rating shall be co-ordinated with those of the associated instrument transformers.
The VA burden of instrument coils shall be as low as possible,
consistent with the best modern design.
Electrical indicating instruments shall comply generally with the
requirements of the Indian/IEC or any other International
Standards and shall be of the accuracy specified in relevant
sections.Recording instruments shall be of the strip chart type with chart
scales having a suitable width. The chart shall be gear driven by a
self-starting synchronous motor wound spring device having
ample torque even at reduced voltage and with at-least 8 hours
spring reserve under all normal conditions of operation. The
recording instruments shall be of withdrawal type for easy access
to maintenance work. Sufficient number of chart rolls, recording
ink for five years of operation and any special tools required for
the maintenance of the instruments shall be furnished with each
recorder.
Integrating watt and VAR hour meters shall comply generally
with the requirements of the international standards.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 46/331
Signature of Bidder Signature of Purchaser46
Instruments provided with contacts shall have contacts suitable
for 230V, A.C. or 220 V D.C. circuits.
All instruments shall have as high accuracy as possible consistent
with best modern design. The construction of instruments shall
be mechanically sound and shall ensure permanence in the
accuracy. The limits of error for different instruments shall be
stated in the bid and their accuracy classification, where
otherwise not specified, shall be subject to the approval of the
purchaser. All instruments shall be tested in accordance with the
requirements of the standard, wherever specified. In cases where
no specific standards are mentioned, the supplier shall submit the
list of the standards in accordance with which the instruments areproposed to be manufactured and tested and these shall be subject
to the approval of the purchaser in every case.
The instruments shall be capable of withstanding the following
tests viz., effect of shock, effect of vibration, effect of humidity
and dielectric tests of 2000 V to ground for one minute in
accordance with relevant standards.
2.12.7 FLOW RELAYS
Flow controllers, used throughout the works shall be equipped
with adjustable contacts suitable for 220V D.C.
System designed to change position on a decrease in flow below
predetermined value.
2.12.8 LIMIT SWITCHESAny limit switch shall be entirely suitable for its specific
application. Particular attention shall be paid to potentially
harmful environmental conditions, including water, oil, dust, dirt,
temperature variations and differential expansions, where
switches operate through linkages. Precautions shall be taken to
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 47/331
Signature of Bidder Signature of Purchaser47
eliminate variations of setting and incorrect operations resulting
from wear or tolerance. Operating voltage shall be 220V D.C.
2.12.9 CONSTRUCTIONAL REQUIREMENTS FOR CUBICLES
AND PANEL BOARDS
Switch boards, control, relay and metering panel shall be of
robust, industrial type design and manufacture, formed of a steel
frame and covered with smooth steel plate. The steel plate shall
be sufficiently thick and properly stiffened to prevent distortion.
If required, flush mounted hinged steel doors with latches shall be
provided; doors shall be of the lockable type by means of
approved key locks. The key lock shall be of the same type forall panels.
All cubicles shall be fully enclosed and protected according to the
protection class given in the specification. The lowest degree of
protection shall be IP 44.
The frames of the cubicles shall be designed to permit firm
anchoring on the floor.
The frames shall permit easy erection and allowance shall bemade for extension of the cubicles by additional similar ones.
Supplier’s supply shall include all necessary mounting brackets,
framing, foundation bolts and respective embedded metal to
permit proper installation of the cubicles.
2.13 EARTHING
The Supplier shall provide earthing terminals on all the equipmentssupplied under the contract and shall connect the earthing conductors to
these terminals as approved or directed by the purchaser.
The Supplier will provide the earthing conductors from the station
earthing bus to the equipment. Supplier shall do equipment earthing.
The Supplier shall provide suitable test terminals at convenient points
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 48/331
Signature of Bidder Signature of Purchaser48
of the equipments being supplied to enable periodic testing of the
receptivity and insulation level of the equipments. Purchaser will
provide earth mat and mild steel flats. Supplier shall provide suitable
earthing terminals with bimetal clamps, washers, nut bolts, lug etc.
suitable for both connections.
2.14 UNITS
According to the latest edition of the relevant Indian and/or IEC
publications shall be used for this contract. For the purpose of
design/calculations, SI Units shall be used.
2.15 PROTECTIVE GUARDS
Suitable guards shall be provided for protection of personnel on all
exposed rotating and/or moving machine parts. All such guards with
necessary spares and accessories shall be designed for easy installation
and removal for maintenance purpose.
2.16 STORAGE AT SITE
The supplier shall furnish complete instructions regarding the storage of
the equipment at site. If at any time after the receipt of equipment at
site, supplier or his representative desires to draw the attention of the
purchaser to the conditions of storage, which in his opinion might affect
the state of the equipment stored, he shall do so in writing to the
purchaser. Periodical inspection of stored items shall be the
responsibility of supplier.
2.17 RATING PLATES, NAME PLATES AND LABELS
A rating plate of non-corrodible material metal sheets shall be attached
to major and auxiliary item of equipment supplied. This plate shall be
permanently engraved with the designed full load ratings, serial number,
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 49/331
Signature of Bidder Signature of Purchaser49
type, number, date of manufacture and other identification deemed
necessary. Where necessary, diagram plates shall also be supplied.
A name plate shall be provided to identify the service of major items of
plant supplied. The purchaser shall approve the identifying description.
Devices shall be identified by name plate on both front and rear of all
desks, panels, cubicles etc.
Names plates or labels shall be manufactured of stainless steel or
aluminium alloy with engraving of contrasting colour or alternatively for
indoor use of transparent plastic material with lettering engraved on the
back and filled with enamel. These shall be in English language only.
2.18 TESTS
In accordance with stipulations of General Conditions of Contract and
Special Conditions of Contract the test shall be performed. Brief details
of tests are as follows but shall not be limited to the same.
2.18.1 GENERAL
Inspection and testing of the equipment shall include all
inspections, tests, checks, procedures etc. Whether mechanical,hydraulic or electrical as required to ensure that the equipment
supplied meets the requirements of the technical specifications.
The tests include, but are not limited to the following.
- Chemical analysis of materials
- Destructive and non-destructive tests of materials
- Check and examination of welds
- Check of fits and assemblies
- Dimensional checks
- Inspection of paints and coatings (thickness and porosity)
- Hydrostatic pressure and tightness tests
- Balancing tests
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 50/331
Signature of Bidder Signature of Purchaser50
- Shaft run-out tests
- Electrical tests
- Running tests (inclusive measurements of vibration and
noise levels).
- Functional tests
- Performance tests
- Load and overload tests
- Load rejection and load taking-up tests
- Acceptance tests (prototype output and efficiency tests)
- Type tests if specially required
The technique, equipment and instrumentation to be used for
these tests, checks, inspections, examinations etc. shall generally
be in accordance with the relevant internationally accepted
standards, rules or codes mentioned in except where specifically
mentioned in the technical specification.
If in the purchaser’s and/or consultants opinion instruments,
apparatus, devices etc. used by the supplier (or sub supplier) need
calibration or re-calibration then such instruments, apparatus,
devices etc. shall be calibrated at the supplier’s cost by anindependent authority or institute subject to approval by the
purchaser.
2.18.2 RANDOM SAMPLE TESTS
These tests are to be carried out on random samples from a lot of
equipment, parts or material. The purchaser and / or consultant
shall do the choosing of samples to be tested, parts etc. and thecomplete lot of equipment be presented for this purpose. The
number of samples taken will be either at the discretion of the
purchaser and/or consultant, particularly for small lots, or shall
conform to the generally accepted rules and standards of
statistical testing. The whole lot, of which the samples have been
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 51/331
Signature of Bidder Signature of Purchaser51
taken, shall be considered satisfactory if none of the sample
tested has failed. Should any one of the samples fail, even in any
one test, the following shall apply.
a) SMALL LOTS: All pieces shall be fully tested.
b) LARGE LOTS: A second set of samples, identical in
number to the first one, shall be chosen and tested. If the
set passes all tests satisfactorily, the lot shall be considered
to be accepted. If again one or more sample fails in the
tests, either the whole lot shall be rejected of all pieces of
the lot be fully tested individually. The decision as to
which of the two alternatives shall be adopted shall be
with the purchaser.Pieces of lots which have been declared non acceptable and
samples which have failed in test must be marked immediately
and must not be presented for test again.
2.18.3 TESTS AT SUPPLIER’S WORK
Before any material, equipment, aggregate, apparatus etc. is
packed or dispatched from the supplier or sub-supplier’s works,all tests, inspections, checks, examinations etc. required by the
relevant and international accepted standards, rules or codes shall
be carried out as far as practicable and agreed in the
specifications.
All equipment, materials, aggregates, apparatus and other parts of
components of the works to be tested, inspected, checked,
examined, etc. at the supplier’s or sub-supplier’s works shall beproperly accessible for testing and inspection work. There shall
be no interference or disturbance from other shop activities when
conducting the tests and inspections.
It shall be understood that all equipment materials, aggregates,
apparatus and other parts or components will be adequately
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 52/331
Signature of Bidder Signature of Purchaser52
shielded and protected against weather whilst being tested,
inspected, checked and examined.
Parts and components shall be assembled to the fairest possible
and agreed extent and dimensional checks shall be performed on
all major assemblies, sub-assemblies, parts and components
especially when close tolerance and fits are being involved
(tolerance of shafts, clearance between stationery and moving
parts, connecting dimensions for the assembly with other
elements and supplies, combined functioning of electrical
equipment etc.)
Components and parts to be weld assembled at the site, shall be
tag welded in the shops to permit visual and dimensional check of the fits and transmissions. All such components and parts shall be
match marked properly to ensure correct assembly and welding at
the site.
If dimensional checks show discrepancies in measurements,
which may affect the fit transition clearance, assembly or
dismantling of the respective part or component, immediate,
proper, and workman like correction or modification is a must.Such correction or modification shall, however, in no way lead to
sacrifice with respect to reliability of operation or inter-
changeability and shall be performed only after the agreement of
the purchaser and/or consultants has been obtained. If the
correction or modification cannot be carried out in accordance
with the terms mentioned above, the part or component
concerned may be subject to rejection.
Doubtful, used, weak and faulty materials or products will also
become automatically liable for rejection.
Shop testing shall also cover the hydrostatic pressure testing of
equipment which can be finish assembled in the supplier’s or his
sub contractor’s premises.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 53/331
Signature of Bidder Signature of Purchaser53
Pumps, fans, compressors and apparatus shall be tested at the
manufacturer’s works. If two or more identical pumps, fans,
compressors and apparatus etc. are supplied a complete
performance test is to be carried out on the first unit only. Such
performance test shall comprise the verification of the discharge
capacity against discharge pressure, power input and efficiency
and other performance data requested in the specification. The
respective test diagrams shall be provided. Subsequent units
need to be tested only if test results obtained from the first unit
prove doubtful or unsatisfactory.
Evidence and diagrams of previous ‘type tests’ undertaken on
identical design of pumps, fans, compressors and apparatus may
be acceptable instead of further complete performance tests, but
the purchaser’s and or consultant’s approval must be sought in
each case. A test at the duty point will, however, in any event be
required. Particular requirements have also been set out in the
specifications.
As far as possible tests on pumps in the manufacturers works
shall be carried out with suction conditions as those after
installation at the site.
Cubicles, cabinets and control boards shall, prior to their
inspection and testing, be completely definitely assembled,
equipped and wired internally in the supplier’s or his sub
contractor’s shops.
Shop testing shall include functional tests as the case may be part
or complete assemblies to the extent practicable and agreed. Such
tests shall be performed under, as far as possible in operation like
conditions.
When requested by the purchaser the functional tests shall be
repeated or extended until proof has been obtained that the
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 54/331
Signature of Bidder Signature of Purchaser54
functioning of the assemblies will comply with the requirements
of the specification.
2.18.4 TESTS AT SITE
During erection and installation work at site, the equipment shall
be subject to tests which may include but not be limited to the
testing, checking, inspection and examination of all equipment
assembled/welded and set up at the site. The procedure may be
confirmed up to final acceptance of the works.
The supplier shall provide at his cost, all competent personnel
(including those from sub-supplier) as well as all equipment,
material and other services required for the proper and thecomplete testing and putting into commercial service of all
equipment. If in the opinion of the Purchaser not sufficient
competent personnel have been delegated, the Purchaser may
request the Supplier to send additional appropriate competent
personnel to the site.
Further to the tests, checks, examinations etc, stipulated in
technical specifications, the tests at the site shall comprise but notbe limited to:
- Checks and examination of welds
- Hydrostatic pressure tests
- Tightness tests
- Dielectric tests
- Dry rotation tests (with clearance and run out checks)
- Functional checks (on protective devices, automatic and
manual controls, monitoring, supervisory equipment etc.)
- Running tests
- Reliability tests
- Performance tests and determination of characteristic data
and tests in particulars of the turbine and generator.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 55/331
Signature of Bidder Signature of Purchaser55
- Turbine acceptance tests (in accordance with IEC-
Publication for “field acceptance tests to determine the
hydraulic performance of hydraulic turbines”)
- Regulator acceptance tests (in accordance with the IEC
Publication 308, 1970, “International Code for testing of
speed governing systems for hydraulic turbine”)
Stability tests of the unit when running in parallel with all such
tests and checks shall be performed in the presence of the
Purchaser and/or his Consultant. If not satisfied with the
performance or outcome of the tests and checks he shall have the
liberty to ask for additional tests or repetition of the same.
2.18.5 RELIABILITY TESTS
After the supplier has notified the purchaser and received his
agreement that the equipment is ready for commercial services,
the generating units may be operated continuously at rated speed
and maximum output for a maximum period compatible with site
conditions.
After successful completion of such tests, the unit shall beoperated under the various conditions envisaged within the limits
of maximum output either continuously or intermittently,
including mode changing operation for a period of ninety (90)
days with a view of obtaining useful information and to verify if
the interest of specifications are met or otherwise.
The purchaser’s staff will operate the equipment with the
assistance and as per the advice of the supplier’s staff during the
reliability test period. The supplier may request any minor
adjustments, which may be necessary provided that such
adjustments do not in any way, interfere with or prevent the use
of the equipment by the purchaser or result in reducing the output
or decreasing the efficiency.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 56/331
Signature of Bidder Signature of Purchaser56
If any failure or interruption occurs in any portion of the
equipment covered by the contract due to, or arising from faulty
design or materials, or workmanship (including construction at
site) sufficient to prevent full use of the equipment, all the
reliability tests shall be repeated after the supplier has remedied
the cause of failure or interruption.
2.19 APPLICABLE STANDARDS
Unless otherwise specifically stated, the applicable standards would be
the latest revisions of the relevant IEC standards/codes or other
standards, which are equivalent to IEC. In case the material and
equipment is manufactured in India, relevant Indian Standard, if available shall be applicable. The supplier is requested to get himself
acquainted with Indian Electricity Acts and Rules and follow those.
Generally applicable standards are as under but not limited to:
IEC standard for main pump turbine
IEC 193(1963) International code for model acceptance tests of
hydraulic turbines (code X) Amendment No.1
(1977) (code K)IEC 193A (1972) First supplement (code P)
IEC 308(1970) International code for testing of speed governing
system to hydraulic turbine (code X)
IEC 497(1976) International code for model acceptance tests of
storage pumps (code X B)
IEC 41(1991) Field acceptance test to determine the hydraulic
performance of hydraulic turbine storage pumps
and pump-turbines.(code XK)
IEC 545(1976) Guide for commissioning, operation and
maintenance of hydraulic turbines (Code S)
IEC 609(1978) Cavitations pitting & valuation in hydraulic
turbines, storage pumps & pump turbines (Code P)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 57/331
Signature of Bidder Signature of Purchaser57
IEC 994(1991) Guide for field measurement of vibration and
pulsation in hydraulic machines (turbine, storage
pumps and pump-turbines) (Code XB)
IEC 995(1991) Determination of prototype performance from
model acceptance tests of hydraulic machines with
consideration of scale effects. (Code V)
Note: IEC 198(1966) acceptance tests of pump turbines and IEC 609
(1978) Thermodynamic measurement are replaces to IEC 41 (1991)
IEC standard for accessories of pump turbine.
IEC 298(1990) A.C. metal enclosed switchgear and control gear for
rated voltage above 1 KV and up to and including
52 kV (code XA) Amendment No.1 (1994) (Code
K)
IEC 264 Packaging of winding wires 264.1, 264.2, 264.2.1,
264.2.2, 264.2.3, 264.3, 264.3.1, 264.3.2, 264.3.3,
264.3.4, 264.4, 264.4.1, 264.4.2.
IEC 502(1994) Extruded solid dielectric insulated power cables for
rated voltage from 1 kV up to 30 kV (code XA)
IEC 227 Polyvinyl chloride insulated cables of rated voltage
up to and including 450/750 V, 227.1(1993) (code
S), 227.2(1979)(code K), 227.3(1993) (code Q),
227.4(1992) (code H)-227.5(1979) (code P),
Amendment No.1 (1987) (code B), Amendment
No.2 (1994) (code D), 227-6(1985) (code L).
IEC 228(1978) Conductors of insulated cables (code M)
Amendment No. 1(1993) (code D)
IEC 228 A (1992) First supplement, Guide to the dimensional limits
of circular conductors (code E)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 58/331
Signature of Bidder Signature of Purchaser58
IEC 287(1982) Calculations of the continuous current rating of
cables (100% load factor) (code XB)
Amendment No. 1 (1988) (code G)
Amendment No.2 (1991) (code E)
Amendment No 3(1993) (code L)
IEC 287.1.2(1993) Part 1: Correct rating equations (100% load factor)
and calculations of losses - Section 2 Sheath eddy
current loss factor for two circuit in flat formation.
(Code U)
IEC 287.2-1(1994) Part 2: Thermal resistance section 1: and
calculation of thermal resistance.(Code V)
IEC 947-2(1989) Part 2: Circuit breaker (This publication SupersedsIEC 157-1 (Code XB)
Amendment No.1 (1992) (code U)
Amendment No.2 (1993) (code S)
IEC 947-4-1(1990) Part 4 contactors and motor starters Section 1
Electro mechanical contractors and motor - starter
(code XD) (This publication supersets IEC 158-
1(1970) and its Amendment (1983) and 158-1c.IEC 269 Low voltage fuses
269-1 (1966) Part 1 General requirements (code XB)
Amendments No.1 (1994) (code B)
269-2(1986) Part 2 Supplementary requirements for fuses for use
by authorized persons (fuses mainly for industrial
application) (code G)
269.2.1. (1987) Part2 Supplementary requirements for fuses for use
by authorised persons (code D)
Amendment No. 1 (1993) (code F)
Amendment No.2 (1994) (code B)
269-3 Part 3 Supplementary requirements for fuses for
uses by unskilled persons (code L)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 59/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 60/331
Signature of Bidder Signature of Purchaser60
34-1, 34-2A, 34-3, 34-4, 34-5, 34-6, 34-7, 34-8, 34-
9, 34-10, 34-11, 34-11-2, 34-11-3, 34-12, 34-13,
14-14, 14-15, 34-16-1, 34-16-2, 34-17, 34-18-1, 34-
18-2, 34-183.
IEC – 76 Power transformers 76-1 (1993) - 76-2 (1993), 76-3
(1980), 76-3-1 (1987), 76-5 (1976).
IEC 56(1987) High voltage alternating current circuit breakers
(code XH) Amendments No.1 (1992) (Code
M)831, 871
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 61/331
Signature of Bidder Signature of Purchaser61
SECTION - III
SCHEDULE OF REQUIREMENT
A) MECHANICAL LOT
B) ELECTRICAL LOT
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 62/331
Signature of Bidder Signature of Purchaser62
SECTION III
SCHEDULE OF REQUIREMENT
INDEX
Sr. No. Description Page No.
MECHANICAL LOT
3.1. Turbine 63
3.2 Butterfly Valve 65
3.3 Station Auxiliaries 66
3.4 Spares. . 67
ELECTRICAL LOT
3.5. Generator and Static Excitation 69
Equipment
3.4 Spares. . 72
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 63/331
Signature of Bidder Signature of Purchaser63
SECTION-III
SCHEDULE OF REQUIREMENTS
A MECHANICAL LOT
3.1 TURBINE
1 No. Vertical shaft Francis turbine.
Turbine shall consist of
1 No. Intake pipe of suitable length between main inlet valve and
spiral case.
1 Set. Expansion joint, air release valve and thrust collar
complete.
1 Set Penstock pipe piece between penstock and BFV of
required length with stiffeners, installation material, pipes,
valve etc. complete. Valve shall be suitable for operation
from inlet valve floor.
1 Set Guide Vanes, greaseless bearings (self-lubricated type),
regulating apparatus, servomotor double acting type etc.
complete with locking device, oil pipelines, valves,
pressure gauges, limit switches etc.
One Stay ring and spiral case.
One Runner in one piece or divided in minimum parts
One Head cover and upper wicket gate ring in one piece or
divided in minimum parts.
One Bottom ring, lower wicket gate ring and runner chamber in
one piece or divided in minimum parts.
One Elbow type Draft tube liner. Draft tube steel liner shall
extend up to the point where it is connected to tailrace.
The liner shall be complete with drain valve, drain piping,
manhole with door, pressure gauges, manometers, probes,
anchors, turn buckles etc.
One Shaft
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 64/331
Signature of Bidder Signature of Purchaser64
One Shaft seal with cooling water system complete including
pressure reducers, strainers, filters and plant to provide
clean water.
One Guide bearing with pads, oil coolers, Resistance
temperature detector (R.T.D.’s), Dial type thermometers
(D.T.T.’s) etc. with piping , valves etc.
One Pit liner provided with ribs, anchor hooks etc.
Lot Thermometers, thermal relays, all level gauges and relays,
water pressure gauges and relays etc. Gauges, temperature
indicators etc. for mounting on Gauge Panel.
1 Set Oil leakage system if needed (requirement shall be
justified at bidding stage) complete with tank, motor-pumpsets, pipes, valves, level switches, gauges etc.
1 Set Water level measuring devices.
1 Set mechanical over speed device
Lot Control and Power Cables :- Power cables for local
control centres to equipments, local control centres to unit
control boards and up to distribution centres provided by
Purchaser, shall be provided by the Supplier. Power cablesbetween two equipments which are in the scope of this
contract shall be supplied by the Supplier. All control
cables, racks, cleating, ferrule, glands etc. for entire
system of equipment covered under the scope of supply of
the supplier shall also be provided by the supplier. All
cables shall be of FRLS copper conductor.
Lot Oil, grease, lubricants sufficient for first filling and 25%
spare quantities.
Lot All accessories viz. sole plates, foundation and anchor
bolts, platforms, ladders, guards, hand rail, bolts, nuts, turn
buckles etc. complete including requirement during
installation and of permanent nature.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 65/331
Signature of Bidder Signature of Purchaser65
1 Set Turbine junction box.
1 Set Runner inspection & maintenance platform suitable for
fixing in the draft tube.
1 Set Necessary instrumentation, control, safety devices etc.
along with the spares and special tools and plants required
for erection, operation & maintenance including the
following.
- Runner removal tools complete.
- Hydraulic jacks for pre-stressing of the shaft
coupling bolts.
- Hydraulic jacks for pre-stressing of the head cover
and bottom ring.- Tools and Tackles required for handling of guide
and thrust bearing.
- All tools for assembling and dismantling guide
bearing, shaft seal, bottom ring, runner, guide vane,
guide vane link, turbine shaft support collar etc.
- Test equipment required for hydraulic pressure test
of spiral case and stay ring.1 Set All test kits, instruments, meters etc. for commissioning,
routine and special tests at site.
1 Set Slings for handling the bearing, runner, shaft head cover,
servomotor etc.
GOVERNOR
1 No. Turbine regulator of digital type.
3.2 MAIN INLET VALVE (MIV)
1 No. Butterfly valve about 2000 mm internal diameter provided
with service and maintenance seals complete with oil
hydraulic drive, main and stand-by pump-motor unit for
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 66/331
Signature of Bidder Signature of Purchaser66
servomotor closing/opening operations complete with air
valve, by pass valve, draining system all accessories
gauge, meter, indicators etc. complete.
1 Set Erection and maintenance tools for butterfly valve.
3.3 STATION AUXILIARIES
3.3.1 COMPRESSED AIR SYSTEM
Compressed air system for generator mechanical brakes and general
requirements comprising of adequate No. of power plant compressors,
pressure receivers, pressure switches, pressure gauges, temperature
detectors, pipe lines, valves, control panels etc shall be provided.
3.3.2 COOLING WATER SUPPLY SYSTEM
Cooling water system required for of unit is tapped from penstock
before butterfly valve and the water after circulation shall be discharge
in to Tail race.
Cooling water supply system shall include following
* Booster pump-motor units.* Control Switchgear.
* Valves strainer duplex filters and piping with control devices,
instruments etc. complete.
* The piping shall be complete from tap from penstock up to
discharge point.
3.3.3 DRAINAGE SYSTEM & DEWATERING SYSTEM
Comprising of adequate no. of submersible type, pump-motor units,
complete with control, protection and switch gear panels, level control
devices, piping, valves, check valves, clamps, supports, anchors etc.
The piping shall be complete from pump room up to discharge point.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 67/331
Signature of Bidder Signature of Purchaser67
3.4 SPARES
A) TURBINE
1/4 Set Guide Vanes.
1 Set Guide vane stem bearing.
1 Set Guide vane stem seal.
1 Set Guide bearing segments.
1 Set Piston rings for servomotor.
1 Set Shear pins for guide vane mechanism
1 set Necessary spares for shaft seal
1 Set Shaft seal water filter elements
1piece Removable protective bush of shaft
1 Set Solenoid coils per solenoid used.1 Set Flow relay of each type used.
1 Set Annunciator lamps of each type used.
1 Set Mercury thermometer of each type used.
1 Set Resistance thermometer of each type used.
1 Set Limit switch of each type used.
1 set Friction elements for guide vanes
Lot Necessary recording charts for one year operation.1 Set Consumables such as all packing, gasket and jointing
material used throughout the turbine assembly , including
those for the servomotors and for man doors.
1 Set Ten per cent(10%) of all bolts, screws, nuts and washers
used up to and including M30 size.
B) FOR GOVERNOR AND OIL PRESSURE SYSTEM
1 Set Oil Pump complete with motor.
1 set Hydraulic amplifier .
1 Set Pilot and control valve complete.
1 Set Transducers.
1 Set Equipment for changing turbine speed
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 68/331
Signature of Bidder Signature of Purchaser68
1 Set Equipment for limiting the opening of Guide vanes.
1 set Oil pump for pumping leakage oil.
1 Set Printed circuit boards used for speed and guide vanes limit
setting.
1 set Safety relief valve
1 Set Setting potentiometer of each type used.
1 Set Float switches, pressure, flow and temperature relays of
each type used.
1 Set Solenoids for each type of solenoid valve used.
1 Set Fuses of each type used.
1 Set Each kind of filter used.
1 Set Complete set of all packing, gasket and jointing materialused.
1 Set Ten percent(10%) of all bolts, screws, nuts and washers up
to and including M 30.
C) FOR BUTEERFLY VALVES.
1 Set Service seal with all fixing.
1 Set Maintenance seal with all fixing1 Set Servomotor piston rings and packings
1 Set Instrument and indicator of each type used.
1 Sets Control solenoid of each type used.
1 Set Flow relay and manostat of each type used.
1 Set Limit switch of each type used.
1 Set Valve of each type used.
1 Set Necessary recording charts for one year operation.
1 Set Complete set of all packing, gasket and jointing material
used throughout the regulator equipment.
1 Set Ten percent (10%) of all bolts, screws, nuts and washers
up to and including M 30.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 69/331
Signature of Bidder Signature of Purchaser69
D) FOR STATION AUXILIARIES DRAINAGE
AND DEWATERING EQUIPMENT
Completely assembled submersible
pump-motor set 1 No.
CONTROL AND SAFETY DEVICES
i) Limit Switches 1 Set
ii)Level Switches 1 Set
iii)Float Switches 1 Set
iv)Pressure Switch 1 Set
v)Flow Relays 1 Set
COMPRESSED AIR SYSTEM
i) Piston Rings 1 Set
ii)Unloader valves 1 Set
iii) Bolts 1 Set
iv) Gasket 1 Set
v) Oil filter elements 1 Set
vi)All types of valves 1 Set
B ELECTRICAL LOT
3.5 GENERATOR AND STATIC EXCITATION EQUIPMENTS.
Two Nos. Vertical shaft generator suitable for direct coupling with
Vertical shaft Francis turbine.
Generator shall comprise of:
One No. Closed circuit ventilation system air-cooled type
One No. Stator assembly complete with frame, core and winding.
One No. Rotor assembly complete with spider rim, brake, jacks,
field winding etc.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 70/331
Signature of Bidder Signature of Purchaser70
One No. Shaft with coupling flanges and bolts etc. complete.
One No. Bottom bracket with lower guide bearing, complete with
supporting structure oil reservoir etc.
One No. Top bracket with combined thrust and upper guide bearing
complete with oil reservoir and supporting structure etc.
One No. Forced lubrication system for combined thrust and guide
bearing with externally mounted oil coolers complete with
all the oil and water piping with valves, flow relays.
One Set. High-pressure injection lubrication system for lubrication
of thrust bearing during starting and stopping of the unit.
One Set Air coolers (Air/Water heat exchangers) with valves,
connecting piping, flow meter, thermometers and otherfittings for generator cooling.
One Set. Sole plates, foundation bolts, dowels and other fittings
required for proper erection, levelling and alignment of
stator and bottom bracket and top bracket.
One Set. Air guide cum air seal assembly.
One Set. Brake and jack cylinders complete with all the necessary
internal and external pipe work, valves, electrical remoteswitches with contacts and with brake dust collector.
One No. Speed signal sensing device.Signal sensing device shall be
complete with casing suitable to cover over speed device
also.
One Set. Brush gear system with slip rings and brushes.
One Set Static excitation system complete with excitation
transformer, thyristor cubicles, field flashing system,battery field flashing provision, field suppression cubicle
with field breaker and discharge resistor, etc. complete.
One No. Digital voltage regulator.
One Set. All instruments and devices such as dial type
thermometers, pressure gauges, resistance temperature
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 71/331
Signature of Bidder Signature of Purchaser71
detectors, thermostats, flow relays, oil level switches etc.
complete shall be provided.
One Set. Turbine, generator gauge panel containing temperature
gauge both of turbine and generator.
One Set. Temperature scanners to be mounted on unit control board
for monitoring temperature of thrust and guide bearings,
stator and field windings, cold and hot air temperature of
generator cooling air with 3 sets of contracts. Each set
consisting of two potential free normal/open contacts
operating at two different levels of temperatures to be used
for external annunciation scheme. The scanner shall be
suitable to operate on the inputs from RTD (Resistance
Temperature Detectors).
One Lot Local control boards for equipment wherever necessary
for control indication and alarm of the system shall be
provided.
One Set Rotor lifting device if required.
One Set Complete erection tools required.
One Lot Testing equipment comprising the following
I) 5kV megger, mains operated. 1No.
II) 10kV megger, mains operated. 1No.
III) Lubricating oil filter (Centrifugal type) 1No.
IV) 10kV, tan-delta measuring kit 1No.
One lot Mulsifire system
One Set: Operation and maintenance tools
One Set Current transformers on Neutral side of generator.
One Set Current transformers in tap-off for excitation transformer.
One Set Shorting Links for dry out and short circuit test
In =1000 A.
One Set All special tools required for erection and maintenance.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 72/331
Signature of Bidder Signature of Purchaser72
One Set 12Nos. Single Phase Current transformers for Generator
protection
One set LAVT cubical with PTs, Lighting arrestor, Surge
capacitor, isolator cubicle
One Set Generator neutral
One set Neutral grounding cubicle with grounding transformer,
resistor and voltage transformer.
Lot Connectors, support structure hardware etc.
Lot Fittings, accessories.
One Set Special tools required for erection and maintenance.
One Set Microprocessor based supervisory control and Data
acquisition system
One Set Microprocessor based protection relays ( Main and Back-
up)
SPARES
1. GENERATOR1 Set Stator upper and lower bar with insulating material to form
1/3 stator winding.
2 Nos. Rotor field coils complete with insulation
1 Set Generator Guide bearing segment/pads
2 Nos. Brake assembly with shoes.
1 Set Brushes with Brush holders.
1 Set Brake liner
1 /2 set Generator air coolers
1 Set Oil coolers for combined bearing.
1 Set Dial type Thermometer
1 No Over speed device.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 73/331
Signature of Bidder Signature of Purchaser73
1 Set Thermostat for air circuit and bearing etc.
1 Set water flow relays for air coolers ,bearing etc.
1 Set Gaskets for brake cylinders
1 Set Gaskets . washers for air water coolers.
1 Set Speed device equipment.
½ Set Fans with driving electrical motors.
1 No Embedded detector for bearings.
2. EXCITATION AND DIGITAL VOLTAGE REGULATOR
EQUIPMENT
Parts of magnetic contactor1 Set Contactor
1 Set Operating coils
1 Set Printed circuit board for DVR(modules).
1 Set Uninterrupted Power supply in DVR
1 Set Converting measuring and supervision units for slips
stabilization
1 Set Rotor angle limiter1 Set Rotor Current limiter
1 Set Stator Current limiter
1 Set Pulse Comparison units
1 Set Digital Voltage Adjuster
1 Set Digital potentiometer
1 Set Feed back module
1 Set Grid control unit
1 Set Pulse Amplifier
1 Set Pulse Supervision unit
1 Set Voltage supervision unit
1No Over – current relay for excitation transformer
1 No Rotor earth fault relay
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 74/331
Signature of Bidder Signature of Purchaser74
1 No Network filter
3 Nos Thyristor element and fuse
1 No Thyristor ridge
1 No Field breaker
1 Set De-excitation discharge resistor
1 Set ripping coil
1 Set Closing Coil
1 No Field flashing rectifier
3Nos Blocking diodes for field
2Nos Ventilation fans
1 Set Grid control unit
1 Set Pulse Amplifier1 Set Pulse Supervision unit
1 Set Voltage supervision unit
1No Over – current relay for excitation transformer
1 No Rotor earth fault relay
1 No Network filter
3 Nos Thyristor element and fuse
1 No Thyristor ridge1 No Field breaker
1 Set De-excitation discharge resistor
1 Set Tripping coil
1 Set Closing Coil
1 No Field flashing rectifier
3Nos Blocking diodes for field
2Nos Ventilation fans
3 Supervisory Control and Data Acquisition System
1 Lot Copy of software
1 Set Interfacing cable each type
1 Set Report printing papers
1 Set Spares of computer
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 75/331
Signature of Bidder Signature of Purchaser75
1 Set Spares of printer
4. Protective Gear
1 Lot Copy of software
1 No. I/P module each type
1 No. O/P Relay module
1 No. Power supply module
1 Set Connecting cables
5 Panels
1 Set Indicating lamp each type used
1 Set Push button/ selector switches
1 Set Auxiliary relays
1 Set Meters each type used1 Set Fuse carrier and base
1 Set Fault, operation and symbol indicator assembly.
Five of Lens for symbols
Each kind.
1 Set Indicating LED & Lamp
1 Set Fuse of each size used
One of Transducer
Each kind
10% of Wrapping label and marketing strip
installed
Quantity
One pair Plug-in type connection accessories
Of each kind
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 76/331
Signature of Bidder Signature of Purchaser76
6 LAVT AND NG CUBICLE
1 No. PT
11kv/ 110v/ 110v
J3 J3 J3
Core-1, 100VA, CL. 0.2
Core-2, 200 VA, CL 3P.
1 No. LA
1 No. Surge capacitor
7 CURRENT TRANSFORMER ( CT)
1 Set CTs single phase as used in Generator Protection Circuit1 Set CTs single phase as used in Generator neutral circuit
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 77/331
Signature of Bidder Signature of Purchaser77
SECTION - IV
MATERIAL OF MAJOR COMPONENT
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 78/331
Signature of Bidder Signature of Purchaser78
SECTION NO. IV
MATERIAL OF MAJOR COMPONENT INDEX
Sr. No. Description PageNo.
1. Material of major component 79
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 79/331
Signature of Bidder Signature of Purchaser79
SECTION - IV
MATERIAL OF MAJOR COMPONENTS
The description of materials and the tables attached to this section shallbe deemed to form part of these specifications. The bidder shall note therequirements and shall state in his bid that the requirements are fullycomplied or otherwise. In any case, he must supply the informationabout the materials to be used in the construction of the plant andequipment in a tabular form.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 80/331
Signature of Bidder Signature of Purchaser80
KAL Hydro Electric Project ( 1X15 MW)
Material List of the turbine and its Auxiliary Equipment
No Name of parts
Type of material
Main materialIS or equiv.
Chemical composition of material Mechanical properties of the mate
C(%) P(%) S(%) Other
elements
contents
Ultimate
tensile
strength Us
Mpa
Yield
strength
Ys Mpa
Normal design
stress
(primary)
Mpa
Normal
safety
factor
A
de
(
1 Runner casting SCS6 0.06 0..40 0.030 750 550 150 1/5 Us
2 Turbine shaft forging SF540A 0.60 0.030 0.035 540 ~ 640 275 68.75 1/4 Ys
3 Head cover plates SM400B 0.22 0.035 0.035 400 ~510 215 100 1/4 Us
4 Stay ring plates SM490B 0.20 0.035 0.035 490~610 295 122.5 1/4 Us
5 Spiral case plates SM570 0.18 0.035 0.035 570~720 420 142.5 1/4 Us
6 Guide Vane casting SCS5 0.06 0.040 0.040 740 540 148 1/5 Us
7 Guide vane
stem
casting SCS5 0.06 0.040 0.040 740 540 148 1/5 Us
8 Wearing
plate
Plates SUS410 0.15 0.040 0.030 440 205 / /
9 Stationarywearing ring
castingplates
SCS1SUS410
0.150.15
0.0400.040
0.0400.030
540440
345205
/ /
/ /
10 Guide vane
operatingring
Plates SS400 / 0.050 0.050 400~510 215 107.5 1/2 Ys
11 Bottom ring Plates SM400B 0.22 0.035 0.035 400~510 215 100 1/4 Us
12 Draft tubeliner
Plates SS400 / 0.050 0.050 400~510 215 107.5 1/2 Ys
13 Guide vane
Servomotor
piston
casting FC250 / / / 250 / 50 1/5 Us
14 Guide vane
servomotor
cylinder
Plates SS400 / 0.050 0.050 400~510 215 100 1/4 Us
15 Turbine pitliner
Plates SS400 / 0.050 0.050 400~510 215 100 1/4 Us
16 Connecting
bolt betweenmain shaft
and runner/
Chromium
molybdenumsteel
SCM435 0.33~
0.38
0.030 0.030 930 785 523.3 2/3 Ys
17 Sealing plate
for main
shaft seal
Plates SS400
Stainless Steel
overlay
/ 0.050 0.050 400~510 215 / /
18 Inlet valveextension
pipes
Plates SM570 0.18 0.035 0.035 570~720 420 142.5 1/4 Us
19 Oil sump
tank
Plates SS400 / 0.050 0.050 400~510 215 107.5 1/2 Ys
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 81/331
Signature of Bidder Signature of Purchaser81
No Name of
parts
Type of
material
Main material
IS or equiv.
Chemical composition of material Mechanical properties of the mate
C(%) P(%) S(%) Otherelements
contents
Ultimatetensile
strength Us
Mpa
Yieldstrength
Ys Mpa
Normal designstress
(primary)
Mpa
Normalsafety
factor
Ade
(
20 Pressure oil
tank
Plates SB480 0.33 0.035 0.040 480~620 265 120 1/4 Us
21 Air receiver Plates SPV410 0.18 0.030 0.030 550~670 410 137.5 1/4 Us
22 Valve bodyfor main
distributing
valve of
governor
casting SC450 0.35 0.040 0.040 450 225 90 1/5 Us
23 Piston for
maindistributing
valve of governor
forging SF540A 0.60 0.030 0.035 540~690 295 196.6 2/3 Ys
24 Butterflyvalve body
Plates SM400B 0.22 0.035 0.035 400~510 215 100 1/4 Us
25 Butterflyvalve rotor Plates SM400B 0.22 0.035 0.035 400~510 215 100 1/4 Us
26 Butterfly
valve
extensionpipes
Plates SM400B 0.22 0.035 0.035 400~510 215 100 1/4 Us
27 Butterfly
valve shaft
forging SF490A
stainless steeloverlay
0.60 0..030 0.035 490~590 245 122.5 1/4 Us
28 Governor
pressure oil
pipes
Carbon steel
pipe
STPG370 0.25 0.040 0.040 370 215 92.5 1/4 Us
29 Oil pressuresystem pipes
Carbon steelpipe
STPG370 0.25 0.040 0.040 370 215 92.5 1/4 Us
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 82/331
Signature of Bidder Signature of Purchaser82
MATERIAL LIST OF THE GENERATOR AND ITS AUXILIARY EQUIPME
Chemical composition of materials Mechanical properties of the materials an
No. Name of
parts
Type of
material
Main material
IS or equiv
C(%) P(%) S(%) Other
elements
contents
Ultimate
tensile
strength
Us Mpa
Yield
strength
Ys Mpa
Normal design
stress(Primary)
Mpa
Normal
safety
factor
Abnorm
design
stress
(Primar
1 Stator
Frame
Plates SS400 - 0.050 0.050 400 ~ 510 215 100.0 1/4 Us 143.3
2 Stator
Core
Silicon
Steel
C2552 - - - - - - - -
3 Stator
Coil
Copper C3 104 No.3-4 - - - - - - - -
4 Field
Coil
Copper C3 104 No.2 - - - - - - - -
5 Main
Shaft
forging SF540A 0.60 0.030 0.035 540 ~ 640 275 68.8 1/4 Ys 183.3
6 Pole
Core
plates PCYH300 - - - 400 300 100.0 1/4 Us 200.0
7 Rotor
Rim
Massive
plates
SM570 0.18 0.035 0.035 570 ~ 720 450 142.5 1/4 Us 300.0
Laminate
plates
PCYH600 - - - - 700 600 175.0 1/4 Us 400.0
8 Thrust
Runner
forging SF590A 0.60 0.030 0.035 590 ~ 690 295 147.5 1/4 Us 196.7
9 Thrust
Block
forging SF540A 0.60 0.030 0.035 540 ~ 640 275 135.0 1/4 Us 183.3
10 Base-
metal
Bearing
plates SS400
- 0.050 0.050 400 ~ 510 215 100.0 1/4 Us 143.3
11 Bearing
metal
white
metal
WJ2 - - - - - - - -
12 Upper &
Lower
Bracket
plates SS400 - 0.050 0.050 400 ~ 510 215 100.0 1/4 Us 143.3
13 Miscella
neous
Cover
plates SS400 - 0.050 0.050 400 ~ 510 215 107.5 1/2 Ys 143.3
14 Sole
Plate
plates SS400 - 0.050 0.050 400 ~ 510 215 107.5 1/2 Ys 143.3
NOTE : Composit ion of materia l shal l be as per IS/ASTM
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 83/331
Signature of Bidder Signature of Purchaser83
SECTION – V
TECHNICAL SPECIFICATIONS OF TURBINE
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 84/331
Signature of Bidder Signature of Purchaser84
SECTION NO. V
TECHNICAL SPECIFICATION OF TURBINE
I N D E X
CLAUSE NO. Description PAGE
NO.
5.1.
5.2.
5.3.
5.4.
5.5
5.6
5.7
5.8
5.9
5.105.11
5.12
General
Type and rating
Guarantees vis-a-vis liquidated damages
Field test and acceptance test
Detailed Construction specifications of
component turbine.
Governing System
Electrical Equipment
Drawings and Manuals to be furnished
after award of contract.
Assembly and inspection at factory
Test Certificate and inspection reportsTests on site
Standards
ANNEXURES
Annexure V-1 to V-5
DATA SHEETS
85
85
86
89
90
112
123
126
127
127129
129
131
148
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 85/331
Signature of Bidder Signature of Purchaser 85
SECTION – V
TECHNICAL SPECIFICATIONS OF TURBINE
5.1 GENERAL
5.1.1 This section covers technical specification and requirements of Turbine
and associated auxiliaries.
5.1.2 The turbine and generator unit shall match in respect of speed, over-
pressure, over-speed and runaway speed, moment of inertia, outputs,
coupling and other requirements.
5.1.3 For operational and design requirements, relevant provisions of section Ishall be applicable.
5.2 TYPE AND RATING:
1) Number of units : 1 No.
2) Type : Vertical shaft single stage Francis type
turbine in a steel spiral case and suitable for
direct coupling with the generator.
3) The hydraulic data and the other data regarding water conveyance
system is as follows:
B) LEVELS :
a) Minimum Draw Down level 140.50 m
b) Full Reservoir water level 170.00 m
c) Maximum tail water level 35.00 m
d) Minimum tail water level 32.00 m
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 86/331
Signature of Bidder Signature of Purchaser 86
B) OPERATION HEADS
1. Maximum net head 117.00 m
2. Minimum net head 84.00 m
3. Rated net head 106.00 m
4) Head variation 79.24 to 110.37%
5) Design Discharge 17.69 m3 /s
The turbine shall be designed based on the hydraulic data mentioned
above.
5.3 GUARANTEES VIS-À-VIS LIQUIDATED DAMAGES:-
GENERAL:The supplier shall guarantee that the turbine in its entirety, including all
related equipment, material and structure furnished under this
specification will be free from defects in design, material and
workmanship. The Supplier shall warrant the successful operation of all
such equipment.
(i) EFFICIENCY GUARANTEE: - The weighted average efficiency of full
size turbine under rated net head of 106 m at rated speed shall beguaranteed as per formula given below.
Eav=1/3 (E100+E75+E50)
Where Eav = weighted average efficiency.
E100, E75, E50 are the efficiencies respectively at 100%, 75%, 50% of
rated turbine output. For Efficiency Guarantee, Bidder shall give values
of efficiencies at 100%,75% and 50% of rated turbine output in data
sheets and also in Annexure V-5 of this section.
The above guarantee shall be based either on field tests or on model tests
as per IEC test codes. If field test is opted, this shall be performed within
90 days of commissioning of turbine. For this purpose the provisions of
inspection and field repair of the machine before the test would be
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 87/331
Signature of Bidder Signature of Purchaser 87
applicable. The penalty on account of shortfall in efficiency is given in
Volume-I.
(ii) OUTPUT GURANTEE: - The supplier shall give guarantee in respect of
values of turbine output at rated net head of 106 m , maximum net head
of 117m and minimum net head of 84.0m. The supplier shall also give
guarantee for the maximum output (110%) from turbine. Penalty for
any short fall in output is given in Volume-I.
(iii) CAVITATION GUARANTEE: - The turbine runner shall be
guaranteed against excessive pitting due to cavitation for a period of
4000 Hrs of actual operation within a period of 24 months from the dateof commissioning but before expire of warranty period. The supplier
shall however, be entitled to make sure within six months after
commissioning that cavitation damage is not caused or aggravated by
local defects of turbine shape as well as to repair the damage that may
have been caused and take steps to prevent future cavitation damage.
Existence of excessive pitting is defined as the rate of metal removal
from the runner due to cavitation more than the rate given by formula.W=0.1 D² kg per 1000 hrs of operation.
Where W = loss of weight of metal due to cavitations in kg.
P = Runner discharge diameter in meter.
The guarantee does not cover the removal of metal by erosion,
corrosion, the presence of injurious foreign elements in the water, or the
removal of metal by chipping and grinding preparatory to repairing the
pitted area. The cavitations damage shall be evaluated by the sum of all
separate masses. The mass for each part damage shall be calculated as
half the product of its maximum depth, the area with a depth exceeding
0.5 mm and the density of the material.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 88/331
Signature of Bidder Signature of Purchaser 88
Should the runner show excessive pitting within the guarantee period
specified above, Supplier undertakes to repair the runner by welding,
chipping and grinding.
Cavititation damage is of spongy nature. The damage by erosion and
corrosion is distinct from cavitation and can be identified by visual
inspection.
(iv) MAXIMUM MOMENTARY OVERSPEED:
The supplier shall guarantee that the maximum momentary over speed
under most unfavourable transient conditions according to IEC
41(1991), sub-clause 2.3.4.14 will not exceed 1.50 times the rated
operating speed.
(v) MAXIMUM STEADY STATE RUNAWAY SPEED:
The Supplier shall guarantee that the maximum steady state runaway
speed according to IEC 41(1991), sub-clause 2.3.4.15 will not exceed
1.70 times rated speed.
(vi) MAXIMUM/MINIMUM MOMENTARY PRESSURE:The supplier shall guarantee that the maximum and the minimum
momentary pressure under most unfavourable transient conditions
according to IEC 41(1991), sub-clause 2.3.5.7 shall not exceed
guaranteed values of data sheets.
(vii) VIBRATION AMPLITUDE:
The amplitude (zero to peak) of vibration according to Rathbone chart
shall be less than 75 µm (microns).
Should for any reason the above limit exceed, the supplier shall take at
his own cost, all steps to remedy the situation and to reduce the vibration
to the above stated limits.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 89/331
Signature of Bidder Signature of Purchaser 89
(viii) NOISE LEVEL:
When units are in operation at most unfavourable conditions in any
mode, noise level measured in the turbine pit shall not exceed 90 dB(A).
Further, the maximum noise level, on the turbine and generator floor
levels at a point outside barrel shall not exceed 90 dB(A).
(ix) RESONANCE:
The supplier shall guarantee that turbine is capable of operating
continuously and smoothly without hunting in the entire operating
range.
The supplier shall confirm that the turbine design is such that the power
pulsation at generator terminal is within ±1.5% at full load and ± 5% atpartial load of actual rated output.
5.4 FIELD TESTS AND ACCEPTANCE TESTS
Only the tests regarding vibration, noise, temperature-rise, stable
operation, over speed and over pressure shall be conducted to verify the
guaranteed performances. The performance guarantees i.e. output and
efficiency figures for turbine equipment being supplied under thiscontract shall be on the basis of report of turbine model test already
carried out by the supplier for similar profile. The Supplier shall submit
the test reports along with calculations to prove the efficiency and output
of the turbine. If the calculations are agreeable to the purchaser the
model test will not be insisted and the turbine on the basis of data
furnish by the contractor will be accepted. If the model test reports of
similar profile is not available with the Supplier then model test shall be
carried out by supplier without extra cost to Purchaser. To ascertain
guaranteed performance values, the model test result form basis of
acceptance. The guarantee at the discretion of Purchaser shall be subject
to verification by field test. Charges for field test shall be shown
separately in price schedule. If the field tests are decided to be done for
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 90/331
Signature of Bidder Signature of Purchaser 90
final acceptance, for arriving at the liquidated damages for non-
conformity with guaranteed values, field tests will prevail, if the results
obtained during field tests differ from those guaranteed by the Supplier,
he shall pay the liquidated damages as per the provisions stipulated in
Volume-I.
Irrespective of whether the field efficiency & output test is conducted or
otherwise the supplier shall have to prove at site the guarantees of
energy generated and water released during turbine mode in one-week
operation cycle. The supplier will have to establish and prove the
relation of;
* Energy generated during operation cycle of one week.
No bonus will be given to supplier in case of better resultshowever Purchaser reserve the rights to reject the equipment in
case of failure to meet the guaranteed values with variation limit
specified in Annexure III-2 of Volume-I.
5.5 DETAILED CONSTRUCTION SPECIFICATIONS OF
COMPONENTS OF TURBINE
5.5.1 STAY RING AND SPIRAL CASE ASSEMBLY
i) CONSTRUCTION:
Stay ring and spiral cases shall be of welded construction. High
tensile, high strength steel plates confirming to material list
attached with Section IV shall be used. Intake pipe of suitable
length to connect Butterfly valve with spiral case shall also be of
similar material. The assembly shall be designed to account for
fatigue stresses induced due to increasing operational duties for
example frequent starting, stopping, and abnormal conditions.
Steel plate, which is used in the construction, shall be free from
defects such as harmful seams, laminations, blisters, snakes and
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 91/331
Signature of Bidder Signature of Purchaser 91
excessive scales and shall be tested for mechanical properties and
physical composition.
The assembly shall be manufactured at the factory into the
minimum number of segments ( not more than two) within
limitations suitable for transportation.
Further, the method of construction shall be such that the critical
welded joints, where the stress concentration occurs (Circular
joints between stay ring and spiral case segments) shall be
finished at factory and shall be stress relieved.
Special precautions shall be taken by the supplier to prevent
cracking in the spiral case plates adjacent to the stay ring bolting
flange faces due to the discontinuity in the stay ring acting as a‘stress raiser’.
The stay ring shall be of “Parallel plate” design. The stay vanes
shall be welded to the flat plates with full penetration welds. The
stay ring shall be designed and shaped to direct the water flow
with a minimum frictional loss and to eliminate vibrations. The
trailing edges of stay vanes shall be shaped so as to minimise
vortex formation.The surface of stay ring and the welded joints in contact with
water shall be ground to a smooth finish.
Holes not less than 100 mm and preferably 150 mm in diameter
shall be provided in the lower stay ring to facilitate the placing of
concrete. Suitable provision shall be made for closing the holes
after the concrete is placed. Suitable grout holes with plugs shall
be provided in the stay ring as required for concreting and
grouting. Air vent holes shall be provided through the webs in
isolated pockets.
The stay ring shall be designed to withstand all forces acting
upon it, hydraulic conditions during hydrostatic testing and
operation of the turbine including the loads due to the generator
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 92/331
Signature of Bidder Signature of Purchaser 92
and rotating turbine parts with the spiral case empty. The stay
ring shall also be designed to withstand the forces transmitted to
it from the spiral case under abnormal condition pressure. Under
these conditions, the maximum stresses induced shall not exceed
67% of yield point stress of the material used.
Welding of the stay ring shall be in accordance with requirements
of these specifications. The weld shall be ground smooth to 3.2
micron (roughness). All other areas of the stay ring in contact
with water shall be finished to roughness not exceeding 6.4
microns (roughness).The stay ring shall be stress relieved before
machining.
All butt welds and welds to spiral case plate shall be examined by100% Radiography Test and stay vane to shroud welds shall be
examined by Ultra sonic Test. All welds shall also be checked by
Penetration Test or Magnetic particle test. Any defects discovered
shall be repaired in accordance with relevant code.
The stay ring shall be painted. All paint applied for protection of
wetted surfaces during shipment shall be removed at site and
surfaces shall be prepared and painted according tospecifications.
It shall be possible to perform site welding of spiral plates
without pre-heating. Also, the quality of the steel shall be such
that post weld heat treatment is not required.
The circumferential joints shall be designed to give a strength
equivalent to that of the longitudinal joints of corresponding
sections.
For convenience in transportation and erection at site, each
divided segment of the assembly shall be provided with bases for
installation and lifting hooks.
Spiral case shall have a manhole of at least 600 mm. internal
diameters, for access to facilitate inspection. The manhole shall
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 93/331
Signature of Bidder Signature of Purchaser 93
be provided with door made of steel plate. It shall be fixed to
spiral by means of bolts. The manhole cover shall also withstand
maximum water pressure.
Spiral case shall be provided with pipes for the following
purposes (but not limited to) with necessary valves.
_________________________________________________
Sr. Description Quantity Nos.
_________________________________________________
I) Drain pipe for the spiral case. …1
ii) Piping for the by pass valve of the
Butterfly valve. …1
iii) Stainless steel piezometer taps for
the purpose of flow measurement
during operation : …4
iv) Any other piping & tapping
required to make the equipment
complete …Lot
The foundation items such as sole plates, packing, levelling
jacks/screws, tie rods and turn buckles etc. in sufficient quantity
shall be supplied along with spiral case.
Expansion joint, thrust collar, air release valve and such other
assemblies which are necessary shall be provided.
ii) HYDRAULIC PRESSURE TEST ON SITE
A hydraulic pressure test of the spiral case and stay ring assembly
shall be conducted before concreting. The suitable test pressure
(24Kg /cm²) shall be gradually increased in steps. The final
pressure shall be maintained for sufficiently long time (30
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 94/331
Signature of Bidder Signature of Purchaser 94
minutes) to allow inspection of field joints for leaks. The
pressure shall then be reduced. This pressure cycle shall be
repeated three (3) times. The rectification /repairs shall be
carried to stop the leakage notified. After completion of
repairs/rectifications, the assembly shall again be subject to
pressure cycles. The hydraulic pressure tests shall be treated as
successfully completed only if no leaks are notified and no
visible damage to spiral case and stay ring is seen.
The supplier shall provide one set of test equipment for
performing the hydraulic pressure tests on stay ring, spiral case
assembly.
The test equipment shall include the following:* One test cone for the spiral case inlet.
* One test ring for the inner diameter of the stay ring with
seals etc.
* One pump-motor set of adequate capacity and pressure
flow and pressure gauges, dial gauges, isolating valves,
relief valve etc., required to perform the pressure test and
all pressure test equipment shall become property of thepurchaser.
The supplier shall provide the services of experienced
personnel and all materials and tools necessary for taking
measurements and conducting the pressure tests.
Upon successful completion of hydraulic pressure test, the
supplier shall submit the copies of the pressure test report,
which should detail the following
* The time of commencing the preparation of the test and
completion of the major activities.
* Description of equipment.
* Test conditions.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 95/331
Signature of Bidder Signature of Purchaser 95
5.5.2 DISCHARGE RING
The discharge ring shall be of plate steel welded construction and
sectionalised as necessary to facilitate shipment and handling. It shall
be of heavy section and adequately ribbed externally to secure proper
anchorage to the concrete and to prevent distortion.
The discharge ring shall have a flange at the top for bolting to the
bottom ring or stay ring. The lower end shall have either a flange for
bolted connection or an extension for welded connection to the draft
tube cone. The necessary foundation bolts shall be supplied for
anchoring the foundation ring to the concrete and adjusting jacks with
steel bearing plates shall be furnished to facilitate levelling duringinstallation.
Suitable grout holes with plugs shall be provided in the discharge ring,
as required, for concreting and grouting.
The lower end of the discharge ring or alternatively the draft tube cone
flange shall be machined to form a ledge for support of the runner
during installation and also when disconnected from the generator.
5.5.3 GUIDE VANES AND REGULATING APPARATUS
The number of guide vanes and the number of runner blades shall be co-
ordinated in a manner to ensure that the turbine will operate without
objectionable pressure pulsation and vibration.
The guide vanes shall be of stainless steel casting having wear and
corrosion resistance properties. The vanes shall be uniform in shape and
their cross sections shall be such as to obtain a streamline flow of water
with a minimum of friction and hydraulic disturbances during operation
of the turbine. Each guide vane stem shall be provided with greaseless
self lubricated bearings and a water seal. All bolts and nuts for the seals
shall be of bronze or stainless steel. The system of bearings and water
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 96/331
Signature of Bidder Signature of Purchaser 96
seals provided including the construction details should be fully
described in the bid.
The turbine guide bearing shall be designed so that guide vanes will not
be lifted up by water pressure of leakage water from the lower portion.
The guide vanes shall be accurately machined and ground so smooth
that surface roughness shall not exceed 6.3 Ra. All vanes shall be
interchangeable.
The guide vane regulating apparatus shall be of ample strength to
withstand the maximum forces imposed on it under most severe
operating conditions. All parts having relative contact in motion shall
be provided with self-lubricating greaseless bearings. The whole
mechanism shall be designed to have “closing tendency” and minimumof lost motion and friction.
A suitable shear pin or breaking link shall be provided between each
vane stem and the regulating ring and shall be strong enough to
withstand the maximum operating forces, but which will break in the
event of excessive forces acting in either the opening or closing
direction and will protect the rest of the mechanism from damage in case
one or more of the vanes become blocked. Locking device, oil pipelines,valves, pressure gauges, limit switches etc shall be provided.
As a precaution against damage when a guide vane is free to rotate due
to breakage of a shear pin or link, the vane shall be restrained from
excessive movement by means of a friction device located on the vane
stem, which provides a restraining force between the levers. The
friction device shall be designed to resist independent movement of the
vane for the maximum hydraulic torque at any guide vane position. The
friction device mechanism on each vane shall be tested during
installation to ensure performance as designed.
A manually adjustable stop shall be incorporated, with which the motion
of the guide vanes in the opening direction can be positively limited.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 97/331
Signature of Bidder Signature of Purchaser 97
5.5.4 SERVOMOTORS
Turbine shall be provided with two (2) Nos. oil pressure operated double
acting hydraulic servomotors. The combined capacity of the
servomotors shall be sufficient to supply the maximum force necessary
to operate and hold the guide vanes at any desired position at the
minimum oil pressure.
Further, the servomotors shall be rigidly supported and shall be capable
of moving the guide vanes from a completely closed position to a fully
open position in one stroke and vice versa. Cushioning shall be
provided in the last ten percent (10%) of the stroke in each direction.
The servomotor cylinders shall be provided with flanges for connecting
oil piping. Connection for pressure gauges shall be provided at each endof each cylinder. An air vent and a drain cock shall be provided on each
servomotor for draining purpose.
The inner surface of the cylinder shall be bored accurately to a uniform
diameter. The surface finish shall be such that roughness shall be within
1.6 micron.
The piston fitting shall be such as to allow the piston to travel, freely and
smoothly but to reduce oil leakage past the piston to an absoluteminimum. Chevron type packing shall be used for this purpose. Each
piston shall be fitted with not less than three piston rings, suitably
shaped to give close contact and uniform pressure on the cylinder walls.
The servomotor piston rod shall be provided with lubricated bearings.
Lubrication shall be arranged to ensure that lubricant is admitted to high
pressure areas regardless of vane position. This piston rod shall be
arranged for adjustment of stroke. The connecting rod shall be of forged
steel and of uniform cross section. A specially designed and a strong
joint using accurately ground pin of hardened steel shall be provided
between piston rod and connecting rod. The joint shall be provided with
greaseless bearings of self-lubricating type.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 98/331
Signature of Bidder Signature of Purchaser 98
The servomotor cylinder shall be designed and so located that the force
for moving the turbine guide vanes shall be divided approximately
equally between the two cylinders and shall be applied in substantially
equal magnitude to opposite sides of the vane regulating ring and
tangentially to the ring.
Provision shall be made for adequate field alignment of the servomotors
using levelling or dutchmen (shim) plates supplied by manufacturer.
The servomotor flange shall be dowelled in the field to its mounting
flange.
A manual locking device of a simple construction to permit locking the
guide vanes in the fully open and closed positions and capable of
withstanding safely the full operating force of the servomotors shall beprovided at the servomotors. The device shall be such that it can be
easily engaged and disengaged by one man. Besides, limit switches
(with electrical contacts suitable for operating on 220 V D.C. system)
shall be provided, to indicate the fully open and fully closed positions of
the guide vanes and for using in the control circuit as interlocks for
starting the unit. All contacts shall be wired up to terminal box placed in
the turbine pit.By-pass connections, equipped with orifices and/or adjustable needle
valves, with a secure means of locking the adjustment, shall be provided
on the servomotors to retard connections shall be fitted with check
valves to prevent sluggish movement during opening the guide vanes
from the fully closed position.
A suitable pointer and graduated scale shall be provided to indicate the
stroke of the servomotor (i.e. % guide vane opening from the closed
position) in steps of 5 %. The scales shall be calibrated in the field and
marked “closed” at one end of the scale and “opened” at the other end.
The servomotor stroke must be capable of manual adjustment. Means
for positively locking the adjustment must be provided.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 99/331
Signature of Bidder Signature of Purchaser 99
Servomotor cylinders and all the oil piping and valves in the system
shall be shop tested to a pressure equal to 150% of the design pressure
of the oil system.
5.5.5 RUNNER
The turbine runner shall be integrally cast in one piece. The material
used shall be proven for erosion and corrosion resistant properties. The
contours of the runner vanes shall be accurate and shall be hand finished
so that the vane profile precisely conform to the model design within
the tolerances set out in IEC publication 193, Chapter - IV.
The runner vanes shall be evenly and symmetrically spaced.
The surface of the runner in contact with water shall be ground to asmooth finish so as to achieve surface without any humps or hollows.
The surface roughness shall be :
Entire blade high pressure side surface and low pressure side surface
except following……………………………3.2 Ra.
Blade low pressure side surface and band inner surface beyond outlet
width corresponding point …………… ….1.6 Ra.
Entire crown inner surface and band inner surface except above………………………………………………3.2Ra.
The runner band, the crown and shaft coupling surfaces shall be
accurately machined and ground. If required these records shall be made
available to purchaser on request.
To prevent seizure of runner during starting and stopping the vertical
running clearance between the runner band and the discharge ring shall
be zigzag.
Provision shall be made to permit aeration of the draft tube through the
runner crown.
Runner and turbine shaft shall be connected by coupling. To facilitate
replacement of runner in future and interchangeability, connecting parts
shall be accurately finished and use of template and keys shall be
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 100/331
Signature of Bidder Signature of Purchaser 100
provided. Connecting bolts shall be suitably covered to minimise
resistance when rotating in water.
The runner shall be designed to withstand safely the dynamic stresses at
maximum runaway speed.
The runner shall be designed to support its own weight and the height of
the turbine shaft when disconnected from the generator shaft with the
runner resting on a shoulder of the discharge ring or draft tube liner
flange.
The supplier shall provide complete arrangement of runner removal
through the generator stator.
5.5.6 HEAD COVER AND BOTTOM RINGHEAD COVER
It shall be of a heavy construction, adequately ribbed and so shaped as to
give rigid support to the guide bearing and the regulating ring.
All welds shall be fully penetrated and stress relieved. Only the radial
ribs, if used, may be fillet welded.
The head cover shall be designed to withstand safely and without
detrimental deflection the maximum water pressure and all other forcesacting upon it. The deflection of the head cover shall be small enough to
obviate the possibility of rubbing of the guide vanes and bending the
vane stems. The underside of the head cover shall be designed to
minimise friction and eddy losses between the head cover and the
runner. The space between shall be adequately drained to relieve water
pressure and to minimise hydraulic thrust. Head cover shall be in one
piece or divided in minimum possible number of parts. Construction of
head cover shall be such that the parts such as turbine bearing, shaft seal
etc. shall be easily accessible for easy maintenance without requiring the
head cover to be dismantled.
The head cover and bottom ring shall be provided with replaceable
stainless steel liners between them and runner.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 101/331
Signature of Bidder Signature of Purchaser 101
The head cover assembly shall be provided with machined sets for the
turbine guide bearing, guide vane regulating ring, shaft seal, guide vane
and any other equipment. The part of the head cover, which constitutes
the guide bearing support structure, shall be so designed as to provide a
rigid support. A retaining ring or pads shall be furnished to prevent any
lifting tendency of the guide vane-regulating ring.
The seat for the guide vane regulating ring shall be provided with a
renewable stainless steel liner accurately machined so as to ensure
minimum lost motion and friction in the operation of the guide vane
regulating ring.
At least four (4) Nos. opening for inspection shall be provided in thehead cover to allow entry and check clearance of the runner crown seals.
The opening shall be provided with doors which are bolted to the head
cover.
The lower surface of the head cover shall be machined to provide
smooth surface to the water passage at the entrance to the runner.
A renewable stainless steel seal ring or rings, accurately machined to
form a master seal with the runner crown and shaped to reduce leakage,
shall be secured to head cover. Any hydrostatic pressure built up behind
the seal rings shall be relieved through built-in pressure relief holes.
The seal rings (on head cover) may be of the same composition as the
sealing face on the runner provided it is at least 50 B(Brinnell) lower in
hardness. Leakage of water through the seal shall be directed to the
draft tube without building pressure under the head cover.
Renewable stainless steel facing plates shall be provided on the lower
face of the head cover between the stay ring and runner seal. The
surface finish of the facing plates shall be smooth.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 102/331
Signature of Bidder Signature of Purchaser 102
Supplier shall provide isolating valves, check valves and all necessary
piping and fitting within the turbine pit for air, leakage water, air
admission etc.
A minimum of three (3) Nos. piezometer connections shall be provided
on the head cover. These shall be connected to a common manifold and
equipped with suitable valves and a pressure gauge. These connections
shall be arranged so that fluctuations of water pressure under the head
cover can be measured. The pressure gauges shall be mounted in the
turbine pit.
Walkways around the head cover and turbine bearing shall be provided
with gratings or suitable opening to facilitate visual inspection of equipment located below the walkways.
For welding purposes, the head cover shall be considered as a pressure
vessel.
All butt welds shall be examined by 100% UT or RT. All other welds
shall be fully examined by PT or MT. Any weld defects shall be
repaired in accordance with these specifications.
An adequate number of eye bolts shall be supplied to lift the head cover.The head cover shall be designed to pass through the generator bore in
the place during erection and dismantling and with the runner and shaft
in place.
The supplier shall furnish an air valve piping within the turbine pit,
terminating in standard pipe flanges at the limits of the pit liner. All
components of the automatic air valves shall be made of non-corrosive
material.
Balance pipe shall be provided with a valve having adjustable opening at
suitable position between the head cover and upper draft tube liner.
Efficient draining arrangement for leakage water from guide vane shall
be provided and described by the supplier.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 103/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 104/331
Signature of Bidder Signature of Purchaser 104
Draft tube liner shall extend upto hydraulic profile with exit velocity of
less than 4m/s at maximum discharge.
The UDTL shall be of stainless steel and machined accurately for
connection to the discharge ring. It shall extend for sufficient distance
below the centre line of the distributor to protect the concrete around the
draft tube from scouring and pitting.
A watertight and airtight manhole door, having a clear opening not less
than 750 mm, complete with studs and nuts, shall be provided in the
draft tube liner.
A sufficient number of levelling screws, jacks, turn buckles and hold-
down bolts shall be provided to permit centring, levelling and securely
holding the liner, both vertically and laterally, during assembly andwhile concrete is being placed. Sufficiently large holes shall be
provided in the draft tube liner for placing of concrete, in difficult
position.
These holes shall be plugged and ground flush after the placement is
complete. Also, suitably spaced grout holes shall be provided to
facilitate final low pressure concrete. These grout holes shall be
plugged and ground flush after grouting is completed.Upper draft tube liner (UDTL) shall be provided with following piping
and necessary valves:
* Test cock for water level detection.
* Piping for mounting the balance pipe.
* Drain pipe for leakage water from guide vanes.
* Piping for water level detector.
* Piping for measuring the water pressure in the draft tube.
* A compound pressure gauge for measuring pressure in draft tube.
* Anchors, stiffeners, turn buckles, etc.
Drain pipe with water valves shall be provided for draft tube at the
lowest point. The drainage pipe shall be taken up to dewatering sump.
The drain valves shall be “gate type” and shall be provided with
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 105/331
Signature of Bidder Signature of Purchaser 105
sufficiently long stem and on hand wheel suitable for operation from the
valve floor.
The supplier shall provide a strong aluminium platform to be located in
the upper draft tube liner (UDTL) for access to the runner. Provision
shall be made in the liner for the support of this platform. The platform
shall be so constructed that the same can be installed and removed from
manhole.
Steel lined outlet of draft tube shall be connected to the tailrace. Steel
for this pipe shall be same as that of draft tube and suitable to withstand
maximum pressure during transient and steady state conditions. All
fixtures, stiffeners, anchors, supports, rail line for erection etc. shall be
provided for them.
5.5.8 TURBINE SHAFT:
It shall be provided with integrally forged coupling flanges for
connecting to the generator shaft and to the runner. It shall be of ample
size to operate at any speed up to the maximum runaway speed without
detrimental vibration or distortion and to transmit the maximum output.
The maximum stress induced under such abnormal condition shall notexceed 67% of the yield point stress. Besides, the shaft shall be
designed to withstand safely the shocks and abnormal stress induced
under conditions of line to line short circuit, faulty synchronising and
turbine trip-outs without harmful vibrations or distortions.
The shaft system shall be designed so that the first critical speed shall be
at least 1.25 times the maximum steady state runaway speed, which may
occur under most unfavourable transient conditions of turbine.
The shaft shall be accurately machined all over and polished smooth in
the portions where guide bearing and the shaft seal sleeve are fitted such
that surface finish is within 0.4 microns.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 106/331
Signature of Bidder Signature of Purchaser 106
The shaft shall be bored axially to a diameter of atleast 150mm
throughout its entire length to facilitate baroscopic inspection of the
shaft material.
The sleeve shall be made in two halves removable and renewable and
securely fastened to the shaft. After assembly on the shaft, the sleeve
shall be accurately machined and polished. The sleeve shall be made of
non-nickel bearing stainless steel. Effective means shall be adopted for
the prevention of corrosion of the shaft underneath the sleeve. Suitable
oil baffles and water detectors shall be provided between the main guide
bearing and the shaft seal.
The amount of shaft run out shall be checked by rotating the finished
turbine shaft in a lathe or lining device in factory. The amount of runoutshall not exceed the recommended values in NEMA standard No. MG-
5.1.-3.04 (R 1979) for vertical hydraulic turbine generator shaft run out
tolerances. Two bands shall be marked on the shaft for reference during
alignment. The bands shall be concentric with the shaft and polished to
a finish of 0.4 micron (roughness). The turbine - generator shaft
coupling shall be designed in accordance with ANSI B 49.1 The lower
shaft coupling to the runner shall be dimensioned so far as is practicablein accordance with ANSI Standards.
Immediately above the bearing housing a circumferential line shall be
inscribed on the shaft and an adjustable pointer shall be mounted on the
bearing housing opposite this line to indicate if any axial movement of
the shaft occurs, and to permit re-alignment after thrust bearing
dismantling.
The turbine supplier shall be responsible for the final reaming of the
coupling bolt holes, aligning of the turbine and generator shaft and
conducting the combined run-out to NEMA Standard No. MG-5.1-3.04
(R 1979).
The field alignment procedure for shaft and bearings shall be approved
by the Purchaser prior to the start of assembly. Under the conditions of
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 107/331
Signature of Bidder Signature of Purchaser 107
rotational test, the run outs at the turbine bearing shall not exceed 0.10
microns per meter length of shaft between the generator top guide
bearing and the turbine guide bearing.
Hydraulic jack for pre-stressing of shaft couplings bolts, head cover &
bottom ring shall be provided.
5.5.9. SHAFT SEAL
The axial movement type shaft seal shall be provided below the guide
bearing to prevent the leakage of water along the shaft. The sealing
shall be achieved by rings of tough fibre and metal carbon one rotating
with the shaft and other stationary. The seal components shall be
hydraulically designed to suit the worst operating conditions. Theloading of the seal faces may be regulated by springs. Any wear, which
may take place, shall be restricted to seal components and not the shaft.
All seal components including seal faces may be manufactured in
suitable number of parts to facilitate, both initial assembly and
maintenance. The rings shall be of self-compensating type and shall
automatically adjust for wear during its full operational life. The
wearing of the seal shall be minimum with a guaranteed life of at least20,000 operating hours. A wear indicator shall be provided to monitor
the wearing rate.
The shaft seal shall be so designed as to prevent the high pressure water
flowing out during turbine operation.
A secondary maintenance-sealing device shall be provided to allow the
carbon seal rings to be serviced. This secondary maintenance-sealing
device shall prevent leakages along the shaft when the turbine is
stationery and subject to tail water pressure and shall be compressed air
operated.
Suitable means, such as lifting bolts and backing out studs, shall be
provided to facilitate installation and removal of shaft seal parts.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 108/331
Signature of Bidder Signature of Purchaser 108
The shaft seal shall be arranged for water lubrications. Two or more
connections for water shall be provided. These shall be evenly spaced
on the periphery to admit supply of clean water at a sufficiently high
pressure to remove dirt and foreign matter from the seal. The supplier
shall be responsible and shall provide the necessary equipment to
maintain the quality and quantity of sealing water requirements.
The supplier shall provide the necessary water filtration equipment,
piping and valves, including pressure-reducing valves, if required. The
piping and fittings within the turbine pit terminated by unions or flanges
shall be continued outside the turbine pit. Piping shall be provided with
a sufficient number of unions to permit easy removal.
All bolts, nuts, screws and hardware used in connection with the shaftwater seal shall be of bronze or stainless steel.
The shaft seal housing shall be made of wear resistant material of high
durability and shall be sufficiently rigid.
5.5.10 GUIDE BEARING (SEGMENT TYPE)
The turbine guide bearing shall be “segment” type and shall be self-
lubricating i.e. lubrication shall be automatically achieved by means of centrifugal action of the rotating shaft. The use of any external electrical
pump for circulation of oil shall not be made.
The bearing design shall be such that no water shall enter the lubricating
system via the shaft seal and there shall be no appreciable loss of oil by
leakage or by overflow from any part of the oil system under any
condition of operation including starting, stopping and over speeding
during trip outs.
Further the bearing shall be designed to operate satisfactory (i.e. without
any damage) under following conditions:
i) Continuous operation at any speed between 30% and 110% of
rated speed at no load and maximum load.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 109/331
Signature of Bidder Signature of Purchaser 109
ii) For 15 minutes at maximum runaway speed.
iii) For 15 minutes, upon sudden rejection of maximum power and in
continuation thereafter till the unit comes to standstill as a result
of tripping and interruption of cooling water supply.
The bearing area and the bearing oil reservoir capacity shall be such that
temperature of the segments shall not exceed 70oC under worst
conditions of operations.
The lubricating oil shall be cooled by means of heat exchangers placed
outside oil reservoir. The heat exchanger shall be tested in the shop and
before assembling on site under a pressure equal to 200% of the
maximum operating pressure for a period of two hours.
The bearing shall be located as near to runner as possible consistent withthe distance assumed in shaft system analysis and keeping in view the
space required for accessibility and maintenance of the shaft seal. The
construction of the bearing and bearing oil reservoir shall be such that
inspection, adjustment or dismantling and removal of the bearing
segments shall be possible without requiring dismantling of the head
cover and/or disturbing the major parts of the turbine.
The mechanical design of the bearing shall take into account theabnormal radial forces during starting, stopping, trip-outs and running at
runaway speed of the unit and also provide axial movement of the shaft.
The bearing segments shall be truly cylindrical in shape, the cylinder
formed by assembly. The segments shall be concentric with the shaft,
the bearing segments shall be of heavy sections and shall be provided
with a continuous, strong and rigid supporting arrangement. The
method of construction shall be fully described in the bid.
The adjustment of the bearing segments by use of shims or radial studs
shall not be acceptable.
The bearing oil reservoir shall have sufficient capacity to supply the
required amount of oil to the turbine guide bearing and provide cool oil
to the bearing under all conditions of load. The bearing design shall
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 110/331
Signature of Bidder Signature of Purchaser 110
prevent the leakage of oil down along the shaft. Piping for filling oil in
the bearing and reservoir shall be separate from the drain piping.
The supplier shall supply and install the following indicating and
protection devices for guide bearing.
- One dial type thermometer to indicate the hottest part of the
bearing.
The thermometer shall have two (2) sets of separately adjustable
contact suitable for operating alarm and tripping circuits at 220 V
D.C. The thermometer indicator shall be mounted on Gauge
panel.
- The resistance temperature detectors R.T.D (Pt 100 Ohms at 0oC)
One for bearing segment and one for oil indication and recordingthe temperatures at unit control board.
- One direct reading water flow meter with two electrical contacts
(suitable for operation at 220 V D.C. for signalling low cooling
water supply / stoppage of cooling water supply.
- One oil level gauge properly graduated marked in litres and high
and low level adjustable alarm contacts with 220V.D.C. contact
rating.
5.5.11 PIT LINER, WALKWAYS, PLATFORMS AND STAIRWAYS
A pit liner of plate steel welded construction with servomotor pockets if
requested shall be provided for the full height up to generator lower
bracket. It shall be made in sections as necessary for shipment. The
internal diameter of the pit liner shall be such to allow the removal of
the head cover, the turbine runner and regulating ring easily.
The bottom of the pit liner shall be prepared for welding to the stay ring
with full penetration welds. The pit liner shall be provided with
sufficient number of stiffeners and anchors so that distortion of the liner
shall not occur during life time operation of the unit.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 111/331
Signature of Bidder Signature of Purchaser 111
If servomotor pockets are provided a suitable arrangement to transmit,
the servomotor reaction forces through the pit liner to the surroundings
concrete shall be made.
The section of the pit liner containing the servomotor pockets shall be
stress relieved and the surfaces of the servomotor support plates shall be
machined after stress relieving.
Working, operating and inspecting walkways and platforms complete
with floor plates and/or gratings, stairs and handrails shall be furnished
in the turbine pit to provide convenient and safe access to all operating
equipment and point of lubrications if any. The design of the floor
plates, gratings, stairs and handrails shall facilitate easy removal to
permit free access.Monorail and a electric hoist of adequate capacity shall be provided in
the turbine pit for easy handling of the guide vanes and other parts.
5.5.12 Tools and tackles required for handling guide bearing shall be provided
by Supplier.
5.5.13 Test equipments of all kinds, which are necessary for erection, testing &commissioning at site shall be provided.
5.5.14 Turbine junction boxes suitable for mounting on barrel wall outside
shall be provided.
5.5.15 Control and power cables:-
All power cables for local control centres to equipment, local control
centres to unit control boards and up to distribution centres provided by
the purchaser shall be provided by the supplier, all power cables
between two equipment covered under the scope of this contract shall be
provided by the supplier. All the control cables between equipments
covered under the scope of this contract shall be provided. Racks, cleats,
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 112/331
Signature of Bidder Signature of Purchaser 112
ferrule, glands etc for entire system of equipment covered under the
scope of supply of the supplier shall also be provided by the supplier.
All power and control cables shall be of FRLS copper conductor type.
5.5.16 Oil, grease, lubricants sufficient for first filling and 25% spare quantities
shall be supplied.
5.5.17 All accessories viz. sole plates, foundation & anchor bolts, platforms,
ladders, guards, handrail, bolts, nuts, turn buckles etc complete required
during installation shall be provided by the supplier.
5.5.18 Thermometers, thermal relays, oil level gauges and relays, waterpressure gauges and relays etc. to install near the equipment, on Gauge
panel and Unit control board shall be provided by the Supplier.
5.5.19 Oil leakage system if needed (requirement shall be justified at bidding
stage) complete with tank, motor-pump sets, pipes, valves, level
switches, gauges etc.
5.6 GOVERNING SYSTEM
Turbine shall be provided with electronic PID governor to control the
turbine during starting, stopping and operation at any load.
5.6.1 The governor system should have following qualities:
i) Fast acting
ii) Stable (No hunting).
iii) Reliable
iv) High sensitivity.
v) Easy control.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 113/331
Signature of Bidder Signature of Purchaser 113
The governing system shall be designed to perform the following
functions.
1) Unit start-up.
2) Idling and synchronisation
3) Normal stopping and emergency shut-down with necessary
monitoring and safety functions.
In addition the governing system must allow the operation of the unit
either in ‘frequency control’ (i.e. speed governing) function or in ‘output
control’ function. In ‘frequency control’ function, the frequency (and
therefore the operating speed) shall be maintained at set point, when the
unit is in isolated operation or in idling mode. In output controlfunction, the power output of the unit shall be maintained at set point.
Configuration
The governing system comprising of oil pressure system, the hydro
mechanical cabinet (HMC) i.e. actuator and the electronics shall divide
functionally so as to achieve, “Local” i.e. ‘Manual Control’ or remote
control of the unit.
The manual control shall be directly from the HMC i.e. actuator cabinet.The remote control shall be from Unit control board or from SCADA
system.
The speed governor shall have the following facilities and performance.
1) Speed adjusting range 85 - 105%
2) Adjusting range of permanent droop 0 - 6%
3) Adjusting range of incremental
momentary speed droop 0 - 50%
4) Adjusting range of time constant
of damping 0 - 15 sec
5) Governor dead band 0. 02%
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 114/331
Signature of Bidder Signature of Purchaser 114
6) Gate setting operation
The speed governor shall be capable of gate setting operation by
the load limiting device and will be capable of easily changing
over from automatic operation to gate setting operation or vice
versa.
7) Gate opening regulating device
This device shall be capable of the following control.
a) Starting gate opening control.
b) Control of maximum output gate opening.
8) Protective device:The protective device shall be capable of fully closing the guide
vane in case that a trouble occurs in the speed governor and shall
stop the turbine quickly.
5.6.2 Both the speed control governor and power output governor shall
actuate the same servo-positioner through the opening set point.
5.6.3 The electronic PID controller’s behaviour shall be enhanced by special
means such as disturbance super position and secondary variable super
position.
Speed sensing
The speed sensing for governor operation shall be taken from toothed
disc method or via transducers using residual remainance.
5.6.4 CHARACTERISTIC PARAMETERS OF PID- CONTROLLERS.
(Definitions as per IEC 308/1970)
i) Permanent Droop (bp)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 115/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 116/331
Signature of Bidder Signature of Purchaser 116
vii) Time setting range.
a) Speed setting -between 20 and 100 s
b) Power output -between 20 and 80 s
setting for full travel of
servomotor
c) Limiter. - between 20 and 80s
for full travel of
servomotor
viii) Control Inaccuracy(ix/2)
speed control ix/2<2 x 10-4
Power output control ix/2 <1 x 10-2
ix) Parameters of servo positioner.
Input :Electrical signal or position of pilot servomotor.
Output: Relative position of the main servomotors
For servo positions, the following applies:-
a) Minimum servomotor opening and closing times Tg and Tf shallbe separately determined to satisfy water hammer and over speed
limitations. The limiting orifices shall be so dimensioned that the
actual stroke times in the presence of the highest supply pressure
and lowest required regulating capacity is not lower than the
allowable stroke time.
b) Time constant (Ty) of the main servo positioner to be introduced
in digital stimulation system shall lie between 0.1s and 0.25s.
Near the zero displacement, higher values of Ty shall prevail due
to overlap and grooves.
c) Servo positioner inaccuracy in follow up arrangement (ia/2)
which has a major influence on dead band shall be kept small i.e.
< 0.2% for the complete servo positioning system.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 117/331
Signature of Bidder Signature of Purchaser 117
d) Control system dead time constant (Tq) shall be less than 0.25s.
e) Dynamic response of servo positioner.
Setting of servo positioner shall be so chosen that the dynamic
response of servo positioner corresponding to a damping ratio (D)
between 0.8 and 1.1 is achieved.
5.6.5 MANUAL CONTROL
Manual control of setting of turbine power directly via the actuators by-
passing the governor control loop shall be provided. In that case, the
safety of unit shall rest with over speed protection.
5.6.6 FOLLOW - UP CONTROLSFollowing follow-up controls shall be provided:
i) The power output governor command signal shall follow the
actual power output signal in the speed control mode.
ii) The speed command signal shall follow the actual frequency-
signal in the power output control mode or during the start up
phase (speed command signal pre-adjustment).iii) The manual control set point shall follow the actual actuator
position in the various control modes.
iv) In case of remote control, respective local control shall follow the
respective command signals.
v) It shall be possible to adjust the pre-opening of varying heads to
minimise start up times.
5.6.7 OPTIMISATION CONTROL
Special control configuration shall be provided to optimise the system
with respect to overall plant efficiency, smooth running or other criteria.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 118/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 119/331
Signature of Bidder Signature of Purchaser 119
i) Purpose
Oil pressure unit system shall be used for operation of the guide
vane.
ii) System
a) The pressure oil supply system shall comprise of 2 sets of
pressure oil pumps directly coupled with the 400V A.C.
motors (1 set for normal operation and 1 set for stand-by).
1 set of sump tank, 1 set of pressure tank and other
accessories.
b) Compressed air required shall be taken from one of the
two Air receivers. Necessary valves pipes etc. required
shall be provided by supplier.c) Operation method of the pressure oil pump shall be of the
continuous operation type using unloader valves. When
the normal oil pump stops during operation of turbine or in
case of the first stage of oil pressure drops, stand-by pump
shall start automatically.
d) Changeover between the main and stand-by pumps shall
be carried out through the changeover switch provided onthe motor control panel and shall operate automatically. In
case of drastic depression of oil level, both pumps shall
operate simultaneously. Besides, starting and stopping
shall be carried out not only automatically but also
manually from the motor control panel and from unit
control board. Operating mechanism shall be oil/water or
alternatively oil/oil will be considered.
iii) Composition and Design
One set of the oil pressure unit system shall comprise of the
following items.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 120/331
Signature of Bidder Signature of Purchaser 120
Pressure oil pumps . . . 2 sets
(one for normal and one for stand-by)
a) Each pressure oil pump shall be vertical shaft screw pump.
The oil flow rate per pump at the maximum delivery
pressure shall be sufficient for operating the guide vanes
from the fully opened state to the fully closed state without
supply of pressure oil from the pressure tank. Each of
these pumps shall be of capacity sufficient to cover
leakage losses with a safety margin in excess of 2. Design
of pressure tank shall be according to draft TC4/WG
14.4(Sec.102 of Feb.88)
b) The normal operating oil pressure shall be adequate.System shall have sufficient oil under pressure to operate
servomotor in close-open-close or open-close-open cycles
(three operations) of guide vanes without requiring
charging of system.
c) Each set of normal and stand-by pumps set shall be
provided with following accessories.
i) Unloader valve 1 setii) Safety valve 1 set
iii) Non return valve 1 set
iv) Strainer 1 set
v) Induction motors 2 sets
(One for normal and one for stand-by)
Each motor shall be vertical shaft, 400V, 50 Hz., 3
phase AC induction motor and shall be used for
driving the pressure oil pump.
vi) Motor control panel
for oil pressure system 1 set
iv) Pressure tank/air oil accumulator 1 No.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 121/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 122/331
Signature of Bidder Signature of Purchaser 122
i) Automatic oil level control device 1 set
ii) Oil level gauge (with stop valve
with check valve) 1pce.
iii) Oil pressure gauge (with stop valve) 1pec.
iv) Safety valve (if any) 1 pec
v) Solenoid valve for air supply 1pec.
vi) Oil supply valve and oil drain valve 1pec
vii) Oil pressure relays 1 set
v) Sump tank
a) Total capacity of the sump tank shall be 120% of
oil volume in the pressure oil system. The sump
tank shall be designed to allow drainage of complete hydraulic system into the tank. It shall
also be designed to allow a complete emptying for
maintenance purposes and to remove the dew point
of water, e.g. by providing a slightly inclined
bottom.
Cooling/heating of the system oil shall be provided
to limit oil viscosity variations. Separate oil vapourexhaust equipment shall be provided.
b) Sump tank shall be provided with a cooler so that
oil temperature will not become too high. Oil/water
cooling coils of cooler shall be made of seamless
steel pipes and shall be free from water leakage.
c) A manhole shall be provided for inspection.
d) The following accessories shall be supplied.
i) Dial type oil level gauge with
alarm contact 1 pec.
ii) Oil level relays (for low oil level
warning and for high oil level warning) 1 pec.
each
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 123/331
Signature of Bidder Signature of Purchaser 123
iii) Dial type thermometer. 1pec
vi) Pipes and valves.
Pipes and valves necessary for all pressure supply system,
and also a complete set of flange couplings, bolts, nuts and
packing required shall be supplied.
5.7 ELECTRICAL EQUIPMENT
CONTROL AND MONITORING DEVICES.
These shall be provided as per the Annexure V-2 through V-5 appended
to this section. The control and monitoring devices shall include but not
limited to following:
1. Automatic operation control devicesa) Solenoid valves.
i) For opening and closing of the
inlet valve 1 pec.
ii) For starting and stopping of unit 1 pec.
iv) For the brake of the generator 1 pec
The solenoids shall be so arranged that they do notremain continuously energised in whichever case
the unit is running or in standstill.
b) All necessary limit switches 1 set.
c) All necessary auxiliary relays 1 set.
d) All necessary relay valves 1 set.
e) All necessary piping and valves 1 set.
2) Turbine control board (Gauge Panel)
The turbine control board shall be of cubicle type of steel
plates and shall be arranged in line with the speed
governor cabinet. In front of the turbine control board, a
name plate shall be mounted.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 124/331
Signature of Bidder Signature of Purchaser 124
The turbine control board shall be capable of manual
operation of the turbine and auxiliaries such as flowing of
cooling water, opening and closing of the inlet valve of the
turbine, starting, stopping, and operation of the brake, etc.
Manual operation shall be of such type as to actuate the
solenoid by operation of the switches on the turbine
control board individually. The control board shall house
the solenoid valves etc., shall be provided with the
measuring instruments, operation indicators, on the front
surface and shall keep sufficient space so that inspection
and adjustment can be carried out easily. The turbine
control board shall comprise the following.a) Control switch change-over switch 1 No.
(local-remote)
b) Manual operation switches for :
i) Solenoid valves for opening and
closing of the butterfly valve. 1 No.
ii) Solenoid valve for starting andstopping of turbine. 1 No.
iv) Solenoid valve for the brake of the
generator 1 No
v) Other solenoid valves housed in
turbine unit control board 1 set
vi) Limit switches 1 set.
vii) Auxiliary relay. 1 set.
viii) Piping and valves. 1 set.
ix) Indicating lamps. 1 set.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 125/331
Signature of Bidder Signature of Purchaser 125
Oil pressure relays :
i) For starting condition of turbine.
(operates when oil pressure for
guide vane operation is same
as or higher than the specified
value.) 1 No.
ii) For alarm at oil pressure drop 1 No.
iii) For quick stop at operating oil
pressure drop 1 No.
iv) For start and stop of the stand by
oil pump 1 No.
v) For oil level control 1 No.vi) For Actuator pressure. 1 No.
vii) Water pressure relay for spiral
case pressure. 1 No.
Instruments :
i) Water pressure gauge for steel
lined shaft 1 No.ii) Water pressure gauge for spiral
case. 1 No.
iii) Pressure gauge for oil pressure
tank. 1 No.
iv) Dial thermometer for turbine
bearing 1 No.
v) Dial thermometer for upper guide
bearing of generator 1 No.
vi) Dial thermometer for lower guide
bearing of generator. 1 No.
vii) Dial thermometer for thrust
bearing of generator. 1 No.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 126/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 127/331
Signature of Bidder Signature of Purchaser 127
5.9 ASSEMBLY AND INSPECTION AT FACTORY.
1. Distributor assembly -in the presence
- Head cover, bottom ring, and of Purchaser’s
guide vanes regulating representative
mechanism (excluding runner
and shaft) shall be assembled
by using assembly stand and
following shall be checked.
Side and bedding face
clearances of guide vanes.
- Stroke of servomotor and its
relation to guide vane opening.- Match marking and doweling
shall be done.
2. Draft tube liner and cone Manufacturer’s
assembly and match marking -inspection
certificate
3. Runner and shaft assembly
and dowelling -----’’-------4. Pressure oil system comprising - in the presence
Sump tank air/oil accumulator, of Purchaser’s
actuator, servomotor and representatives
connected piping
5.10 TEST CERTIFICATE AND INSPECTION REPORTS:
LEGEND :
1) Composition and physical properties of the material in the
following components shall be supplied.
2) For welded joints. The welded joints of the following
assemblies/components shall be examined by ultrasonic and/or
radiographic methods
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 128/331
Signature of Bidder Signature of Purchaser 128
3) For hydraulic pressure test and leakage test.
4) Dimensional accuracy.
5) For surface finish.
Sr. No Particulars of Assembly 1 2 3 4 5
1 Runner - Runner rim, runner blades √ √ √
2 Shaft - Main shaft √ √ √
3 Spiral case, ring and stay vanes: Spiralcase, stay ring, Parallel plates, Stayvanes, Steel plates, draft tube liner,Support cone.
√ √ √
4 Head cover and regulating apparatus:
Head cover, Wearing rings (rotating),Facing plates, Coupling bolts, Bottomring.
√ √ √
5 Draft tube Liners √
6 Stay ring / spiral assembly √ √ √
7 Head Covers √
8 B.F. valve. √ √ √
9 Bottom ring and / discharge ring. √
10 Sump tanks air/oil accumulators,Servomotor/cylinders. √
11 Penstock and Specials. √
12 Oil sump tank. √
13 Oil pressure tank. √
14 Oil coolers. √
15 Guide vane servomotor cylinders. √
16 All the components of the turbine √
17 Runner vanes crown and blanksurfaces.
√
18 Stay ring upper & lower surfaces. √
19 Stay vanes. √
20 Guide vanes. √
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 129/331
Signature of Bidder Signature of Purchaser 129
21 Bearing pads. √
22 Head cover facing plates. √
5.11 TESTS ON SITE.
After completion of erection each of the sub system shall be individually
operated and tested to verify if the specified performance/functional
requirements are achieved.
The following are illustrative list.
i) Pressure oil system.
ii) Compressed air system.
iii) Cooling water system,
iv) Governing system according to IEC 308.
v) Dewatering and drainage system.
vi) B.F. valve.etc.
5.12 STANDARDS.
Turbine and governing system shall be designed, manufactured and
commissioned to the latest I.E.C standard accepted standard practices. A
few of the standards are listed below but not limited to.
IEC-41/1991 Field acceptance tests.
IEC- 545 Commissioning procedure.
IEC-607 Thermodynamic method measuring.
IEC-609 Cavitations pitting evaluation.
IEC-193/1965,193-A/1972
and 995/1991 Scale model testing.IEC-994/1991 Guide for field measurement.
ASME Tank and hydraulic cylinders.
IEC- 308 Governor testing.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 130/331
Signature of Bidder Signature of Purchaser 130
ASME VIII,
ASME V
ASTMA 435
ASTMA 609, welding materials
ASTMA 709 .
ASTMA A 388 and
IEC 404
ASME Boiler and pressure vessel code section VIII, Dim 2 Low cycle
fatigue.
IEC- 34.9 Noise limits for electrical machines.ISO- 1996 Noise measuring.
VDI-2056 Vibration limit.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 131/331
Signature of Bidder Signature of Purchaser 131
ANNEXURE V-1
LIST OF DRAWINGS, DESIGNS AND MANUALS TO BE SUBMITTED BY THESUPPLIER AFTER THE AWARD OF CONTRACT
Sr.
No.
Brief Description To be submitted
within monthsfrom the awardof contract
Remark
1 2 3 4I1
DRAWINGSGeneral plans and sections showing allessential details of turbine assembly,setting and water passages
3 For approval
2 Plans and cross sections of powerhouse showing layout of equipment
listed below, floor arrangement,principle dimensions and scope of works
- Penstock pipes to be provided at bothsides of the Inlet valve to connectpenstock and spiral casing.
- Inlet Valve.- Turbine components- Governing system- Pressure pumping systems for
governing
- Stay ring and spiral case- Draft tube and draft tube liner- Generator outline- Generator barrel- Speed signal device, excitation
equipment- Line and neutral end cubicles- Unit control board- All unit auxiliaries
- All station auxiliaries viz. coolingwater system,drainage& dewatering
system, compressed air systems. etc.
3 For approval
3. Cross Section through Turbine andlongitudinal section of turbine inmachine hall
3 For approval
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 132/331
Signature of Bidder Signature of Purchaser 132
4. Installation drawings of:- Draft tube liner, elbow and cone- Spiral case/stay ring assembly- Guide apparatus, regulation and
operating mechanism- Runner and housing- Shaft and shaft seal- Head cover, lower and upper coverings- Guide vanes and sealing- Turbine bearing, lubrication and
cooling- Test equipment for pressure testing of
spiral case- Turbine platform in Turbine pit.
666
66888
6
8
For approval
5. Governor, governing scheme and
connection diagram, hydromechanical and electrical cabinets
12 For approval
6. Control diagram for Turbine 8 For approval
7. Runner removal arrangement. 3 For approval
8. Schematic diagram for auto control of Turbine
8 For approval
9. Drawings of tools, tackles and erection
devices
3 For reference
10. Leaking piping 8 For reference
11. Embedment in:- DT liner and cone concreting- Stay ring and spiral case concreting
- Generator barrel concreting
366
For approvalFor approvalFor approval
12. Area velocity curve for draft tube 3 For reference
13. Layout plan and cross-sections showing
details of floor openings (for piping,cables etc.)
- Trenches- Block-outs/cut outs- Openings in concrete
8 For approval
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 133/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 134/331
Signature of Bidder Signature of Purchaser 134
ANNEXURE – V2
SCHEDULE OF INDICATING AND RECORDING INSTRUMENTS FOR TURBINE AND EQUIPMENT ASSOCIATED W
Number Provided Total Sr.No
.
Item Type of
instrument
deviceOn or near
the
equipmentor locally
At Generator-
gauge
panel
At Governor
Cabinet
At Unit
Control
Board
1 2 3 4 5 6 7 8
1 TEMPERATURE OF
i. Guide bearing segment
ii. Guide bearing oil 24 point
indicator
(Provided by
Gen-Motor
manufacturer)
- 1 - - 1
iii. Cooling water at
Outlet of guide
bearing
iv. Guide bearing segment. DTT - 1 - 1 2 v. Guide bearing Oil. DTT - 1 - - 1
vi. Cooling water at outlet of
guide bearing.
DTT - 1 - - 1
vii. Governor sump oil. DTT - 1 - - 1
2 PRESSURE AT
i. Inlet to Butterfly valve i.e.
penstock.
PG +RL 1 1 - - 2
ii. Draft Tube. PVG 1 - - - 1
iii. Inlet & outlet of cooling
water to the guide bearing.
PG+RL 2 - - - 2
iv. Guide vane servomotor. PG+RL 2 - - - 2
v. Governor oil pressure receiver PG+RL 1 1 - - 2
vi. Spiral pressure near Butterflyvalve PG+RL 1 1 - - 2
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 135/331
Signature of Bidder Signature of Purchaser 135
1 2 3 4 5 6 7 8
vii. BFV oil Pressure PG+RL 1 - - - 1
3 LEVELS OF.
i. Oil in governor sump tank Sight gauge + relay 1 - - - 1
ii. Oil in Air/Oil pressure
receiver
-do- 2 - - - 2
iii. Oil in leakage oil tank -do- 1 - - - 1iv. Oil in guide bearing reservoir -do- 1 - - - 1
4 FLOW OF.
i. Cooling water inlet to guide
bearing
Flow indicator 1 - - - 1
ii. Cooling water inlet to shaft
seal.
-do- 1 - - - 1
Iii Discharge through spiral case
.
- do- - 1 -- - 1
5. STATUS INDICATION FOR
i. Governor Oil
pump No.1
running/standstill/fault
Lamp Set - - Se
ii. Governor Oil
pump No.2 running/standstill
-do- Set - - Se
iii. Leakage Oil pump for
governor running/standstill/fault
-do- Set - - - Se
iv. Head cover drain pump
running/standstill/fault
-do- Set - - - Se
v. Guide vane remained open
after close
-do- - - - 1 1
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 136/331
Signature of Bidder Signature of Purchaser 136
1 2 3 4 5 6 7 9
vi. Guide vane lock in/out -do- - - - 2 2
vii. Dome light -do- 1 - - - 1
ix. Main inlet Butterfly valve
open/transit/close
-do- Set - - Set Set
6 OTHER ITEMS
i. Setting of guide vane limiterand gate position
Gate limiter andgate position
indicator
- 1 1 1 2
ii. Turbine speed Tachometer - - 1 1 2
iii. Governor speed droop setting -do- - - 1 - 1
iv. Governor balance meter
indication
Governor
balance meter
- - 1 1 2
v. Wearing of shaft seal
detection
Water detector 1 - - - 1
vi. Water in guide bearing Oil
reservoir
Water detector 1 - - - 1 set
vii. Ammeter with panel switch
for each motor
Ammeter 1 set - - - 1 set
viii. Voltage with selector switch
for each 415 volts bus bar.
Voltmeter 1 set - - - 1 set
ADDITIONAL INDICATING AND RECORDING INSTRUMENTS
(To be recommended by Supplier)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 137/331
Signature of Bidder Signature of Purchaser 137
ABBREVIATIONS :
RTD means Resistance temperature detector
DTT means Dial type thermometerPG means Pressure gauge
PVG means Pressure/Vacuum gauge
BFV means Butterfly Valve
PG+RL means pressure gauge and guard relay
NOTE:
1 Dial type thermometer and relays shall be used for alarm annunciation/shut
down also.
2. Turbine and generator supplier shall co-ordinate in joint use of
indicators/recorders, wherever possible.
3. Supplier shall indicate changes if any required in number, type and
location of instruments.
4. Information will also be fed to microprocessor based control system
covered under scope of supply of generator supplier. (Information such as
bearing temperatures, cooling water parameters, water pressure, draft tube
pressure, spiral pressure. Governing system parameter, servo strokes,
guide vane opening and limit, inlet valve parameters, compressed air
system details) For this purpose necessary tapping points shall be
provided by turbine supplier in consultation with generator supplier.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 138/331
Signature of Bidder Signature of Purchaser 138
ANNEXURE V3
SCHEDULE OF CONTROL FOR TURBINE AND I TS ASSOCIATED
EQUIPMENT
Sr.
No
Description Type of
device
Number Provided Total emark
Locally
or in
the
vic in i ty
At
enera tor
gauge
panel
At
Governor
Cabinet
At
Unit
Control
Board
1. 2. 3. 4. 5. 6. 7. 8. 9.
1
2.
3.
4.
Guide vane
limit control
Auto / manual
Selection for
Governor
operation
Selection of
location of
governor
control (local/
remote)
Speed load
control
Raise /
Lower
switch
Selector
switch
-do-
Raise /
Lower
Switch
-
-
-
-
-
-
-
-
1
1
1
1
1
-
1
2
1
1
2
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 139/331
Signature of Bidder Signature of Purchaser 139
5.
6.
7.
8
9
10
11
Speed droop
Control
Turbine
Guide vanes
Locking
Emergency
Turbine shut-
down
Governor Oil
pump No.1
starting/
stopping.
Governor Oil
Pump No. 2
Starting/
Stopping
Main /
standby
Selection of
governor oil
pump
Auto / manual
mode selector
of governor oil
Control
Switch
Locking
device
Push
button
-do-
-do-
Selector
Switch
-do-
-
1
-
2
2
1
1
-
-
-
-
-
-
-
1
-
1
-
-
-
-
-
-
1
2
2
-
-
1
1
2
4
4
1
1
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 140/331
Signature of Bidder Signature of Purchaser 140
12
13
14
15
16
17
18
pump No 1
Auto / manual
Selector for
Governor oil
pump No. 2
Local / remote
Mode
selection for
governor oil
pumps.
Control of oil
leakage pump
Auto / manual
Selection for
oil leakage
pump
Headcover
pump starting /
stopping
Unit starting /
stopping
Butterfly
valve ON/
OFF (Closing
/ Opening)
-do-
-do-
Push
button
Selector
switch
Push
button
Control
switch
Push
button
1
1
2
1
2
-
1
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1
1
1
1
2
1
2
1
2
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 141/331
Signature of Bidder Signature of Purchaser 141
ADDITIONAL CONTROLS
(TO BE RECOMMENDED BY SUPPLIER)
NOTE : 1. The items quantities and locations of controldevices tentatively indicated. The supplier shall
indicate changes if any.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 142/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 143/331
Signature of Bidder Signature of Purchaser 143
4.
5.
6.
7.
ii. Oil in governor Oil sump
tank low
iii. Oil in governor air/oil
pressure receiver
iv. Oil in BFV air/oil
receiver
HIGH LEVEL OF
i. Oil in oil leakage unit
ii. Water in Turbine head
cover
LOW PRESSURE IN
I. Governor air/oil pressure
receiver
ii. Governor air/oil pressure
receiver very low
HIGH PRESSURE OF
I. Oil in governor oilpressure receiver
FAILURE OF
i Shear pin
ii.Speed sensing system
iii. Power supply to unit
control board
iv. Supply to governor
cubicle
-do-
-do-
-do-
Level
relay
Float
Pressure
switch
-do-
Pressureswitch
Limit
Switch
-Voltage
relay
-do-
-do-
1
1
1
1
1
1
1
1
Set
1
1
1
-
-
-
-
-
-
-
-
-
A
A
A
AS
A+AS
A+AS
A
A
A
AS
A
A
A
AS
AS
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 144/331
Signature of Bidder Signature of Purchaser 144
8.
9
10
Unit over speed detection
Water in guide bearing oil
detection.
Emergencies
Speed
relay
Water
detection
Emergency
shutdown
switch
1
1
1
A
-
AS
As
A
AS
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 145/331
Signature of Bidder Signature of Purchaser 145
ADDITIONAL SAFETY DEVICES
(TO BE RECOMMENDED BY SUPPLIER)
ABBRIVATION:DTT means dial thermometer.
A means alarm annunciation
AS means shut down and annunciation
A+AS means two stages for alarm and shut down
NOTE : 1. Items, quantities and locations of devices are
indicated and supplier shall indicate changes if
any.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 146/331
Signature of Bidder Signature of Purchaser 146
INDICATION, CONTROL AND SAFETY DEVICES FOR AUXILIARY EQUIPM
Number Provided/Annunciation Total Sr.
No.
Item Type of
instrumentdevice
On or nearthe
equipment
locally
At Auxiliarygenerator
Motor
Control
Board
AtGovernor
Cabinet
At UnitControl
Board
1 2 3 4 5 6 7 8
A INDICATION/RECORDI
NG
1. Air compressors for
Brakes standstill/ running
Indication Lot Lot
2. Drainage & Dewatering
and pumps Standstill
Running Main 1, Main 2
Lamp Lot Lot
3. Cooling water pressure
(High/Low)
Indication Lot Lot
4. Pressure in Air receiver
for Brakes
(pressure
Gauge+RL)
4 4
5. Pressure in air/oil
receiver for Governor
(pressure
Gauge+RL)
4 4
6. Ammeter with selector
switch
Lot Lot Lot
7. Current and voltage
meter for three phase
indicationsVoltmeter withselector switch for each
415 V motor
Lot Lot Lot
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 147/331
Signature of Bidder Signature of Purchaser147
DEPARTURE FROM SPECIFICATION
( To be filled by the Bidder.)
I tem Description of departure Reference to Clause in the specif ication
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 148/331
Signature of Bidder Signature of Purchaser148
DATA SHEETS
DATA SHEETS OF TURBINE
1) Name of the Manufacturer :-………………………….
2) Type :-………………………….
3) Guaranteed rated capacity (output)
at a rated net head of 106 m :-……………………. KW
4) A) Full gate output at a net
head of
i) 117.0 m (max) :-………………………KW
ii) 84.0 m (min) :-………………………KW
iii) 106.0 m (Rated) :-………………………KW
B) Corresponding Discharge
For 4A) Above
i) 117.0 m (max) :…………………… m3 /sec
ii) 84.0 m (min) :-………………… m3 /sec
iii) 106.0 m (Rated) :-…………………. m3 /sec
C) Guide vane opening
Corresponding to rated
Net Head of 106m at
i) 100 % output :---------------------- %
ii) 75 % output :-…………………. %
iii) 50 % output :-……………………%
Guide vane opening corresponding to 110 % output shall be 100 %
D) Head at 110% Output :-……………………m
E) Discharge at 110% output :-………………… m3 /sec
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 149/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 150/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 151/331
Signature of Bidder Signature of Purchaser151
14 Flywheel effect
a) of the generating unit for
regulation stated in item (10) & :-………………tm2
(12) above.
b) of turbine runner & shaft :-……………… tm2
15 Maximum gross head on turbine
(inclusive of water hammer) at
the time of gate closure in (10)
above.
16 Runner
a) Material
i) Cone :-……………..
ii) Blades :-…………….
b) Material of wearing ring :-…………………
c) No. of blades :-……………………
d) Weight :-…………………
e)Inlet dia. :-…………………
f) Velocity of water :-…………….m/sec.
( Full gate, 106 m Net head)
17 Shaft
a) Material :-………………….
b) Weight :-………………Kg.
c)Diameter/bore :-………….mm/mm
d)Length :-……………mm
e)Material of sleeves :-…………..
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 152/331
Signature of Bidder Signature of Purchaser152
f)Method of removing and
attaching the sleeves. :-……………..
18 TURBIN E GUIDE BEARIN G
1) Type of guide bearing :-………………
[adjustable segmental type
self lubricated bearing]
2) Diameter of turbine
guide bearing : . . . . . . . . . . . .. . .mm
3) Radial clearance of turbine
guide bearing :-. . . . . . . . . . . .. .mm
4) Number of segments :-. . . . . …….
5) Total effective surface of
all segments :- ….... . . . . .m2
6) Circumferential length
of segments :-…….…...mm
7) Axial length of segments :- …. ……mm
8) Dynamic viscosity of oil :-………...m/s2
9) Maximum temperature for
-oil film :……. .. . . . . . . .oC
-segment (≤ 70oC ( r) ) : . . . . . . . . . . .. . . .
oC
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 153/331
Signature of Bidder Signature of Purchaser153
10)Total flexibility of turbine
guide bearing
[not more than:≤0.4mm/MN(d)] :-………..mm/MN
11) Quantity of lubricated oil reservoir :-. . . . . ……..m3
12) Quantity of cooling water :-…….... . . . 1/s
13) Total losses in guide bearing
at rated load :…….... . . . .kW
14)Permissible duration of operation
of the unit at rated load without
supply of cooling water. : . . . . . . . . . . . .minutes
19 Head Cover
a) Material and construction :-………………..
b) Weight :-…………………
c) Rating of AC pump motor for :-……………….prevention of accumulation
of water
d) Rating of DC pump motor for :-…………………
prevention of accumulation
of water
e) Method of ensuring water :-…………………..
tightness at shaft entry and
description of the arrangement
proposed.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 154/331
Signature of Bidder Signature of Purchaser154
20 Discharge Ring
a) Material and construction :-………………….
b) Method of connection to the :-…………………..
stay ring.
21 Guide Apparatus
a) Material and construction of
wicket gates :-……………………
b) No. of wicket gates :-……………….
c) Height of wicket gates :-………………
d) Material of wearing plates :-……………….
above and below vanes
e) Material of guide vanes :-…………………..
bearing (stainless steel)
( lubrication bearings DEVAtype (d) ]
f) Leakage through full closed :-……………………
gates under maximum static
head
g) Torque on turbine due to
the above leakage.
22 SPIRAL CASE AND STAY VANES
A) Spiral case
a) Type (constant velocity, :-……………………
acceleration etc.)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 155/331
Signature of Bidder Signature of Purchaser155
b) Material and Construction :-………………….
c) Thickness
i) maximum :-……………….mm
ii) minimum :-………………mm
d) Weight :-………………kg
e) Elevation of centre line of
distributor :-………………m
f) Max. velocity of water for full load
at rated head at outlet pipe from MIV :-……………m/sec
g) Velocity of water for full load at
rated head.
i) at inlet to spiral case :-……………m/sec
ii)at 900
from inlet :-…………..m/sec
iii) at 1800
from inlet :-……………m/sec
iv) at 2700from inlet :-……………m/sec
h) Method of erecting and
Concreting the spiral case
B) Stay ring
i) Material and construction of
Stay ring :-………………
ii) Number of vanes :-…………………
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 156/331
Signature of Bidder Signature of Purchaser156
iii) Weight :-……………….kg
23 Turbine pit liner
a) Material and construction :-……………….
b) Height (approx) :-……………… mm
c) Diameter :-………………mm
d) Weight :-……………….kg
24 Draft Tube
a) Elevation of the lowest point
in draft tube :-……………….m
b) Distance from the C.L. of the
unit to the draft tube exit. :-……………….m
c) Velocity at draft tube exit :-……………m/sec
d) Extent of the draft tube covered
with a steel liner from unit centre :-……………….mm
line.
e) Thickness of the steel liner :-…………….mm
f) Weight of the steel liner :-……………….kg
25) PENSTOCK:-
a) Taper piece between penstock and MIV
i) Inlet diameter :-……………..mm
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 157/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 158/331
Signature of Bidder Signature of Purchaser158
27 Governor
a) Rating :-………………….
b) Guaranteed sensitivity
(Min. speed change to which
governor will respond)
c) Range of adjustment of speed
droop characteristic
d) Stable operation guaranteed
for a min speed droop of :-……………….%
e) Guaranteed range of speed
level setting for which governor
will control the turbine effectively :-………………
f) Range of adjustment of gate
closing time :-……………….
g) Range of adjustment of gate
opening time :-……………….
h) Type of Governor :-…………………
i) Minimum turbine speed at
which governor operation will
start :-………………….
28 Max safe oil pressure for the
governor oil system :-…………. kg/cm2
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 159/331
Signature of Bidder Signature of Purchaser159
29 Max. velocity of oil in pipe
parts of actuators and
servomotors of inter connection :-……………m/sec
pipes.
30 Oil pressure system
a) main oil pump
i) Type of pump :-……………….
ii) Capacity of pump (LPM) :-………………
iii) Rating of pump motor
KW :-……………….
rpm :-………………..
b) Stand by oil pump
i) Type of pump :-……………….
ii) Capacity of pump (LPM) :-………………
iii) Rating of pump motor
KW :-……………….
rpm :-………………..
c) Quantity of oil in one filling :-………………..
:-
d) Max. rate of oil consumption
from pressure tank :-……………..
e) Capacity of sump tank :-………………….
f) Total capacity of pressure tank :-…………………..
g) Number of complete operations
which can be performed by the
amount of oil in the pressure tank
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 160/331
Signature of Bidder Signature of Purchaser160
with oil pump not work :-……………………
31 LUBRICANTS
a) Specification of oil :-……………………
b) Specification of other
lubrications :-……………………
32 Weight of turbine rotating parts :-…………………
33 Max. hydraulic thrust :-………………..
34 Heavies package for shipment
a) Name :-……………………
b) Weight :-………………….
c) Dimensions (L x B x L) :-……………………
35 Largest package for shipment
a) Name :-……………………
b) Weight :-…………………
c) Dimensions (L x B x H) :-…………………
36 Heaviest assembly to be lifted by
crane
a) Name :-………………
b) Weight :-………………
c) Dimensions (L x B x H) :-………………
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 161/331
Signature of Bidder Signature of Purchaser161
41 Longest assembly to be lifted
by crane
a) Name :-………………
b) Dimensions (L x B x H) :-…………….
c) Max . Length :-……………….
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 162/331
Signature of Bidder Signature of Pur162
ANNEXURE -V-5
GUARANTEED AND OTHER TECHNICAL DATA FOR TURBI
Sr.
No.
Maximumcontinuous
power P max at
100% guide vane
opening.
100 %
output
power
75 %
output
power
60%
output
power
50%
outpu
powe
1 For max. net head of 117m
a) Turbine output power (KW)
b) Discharge (m3 /s)
c) Percentage guide vane opening 100%
2 For Rated net head of 106 m
a) Turbine output power (KW)
b) Discharge (m3 /s)
c) Percentage guide vane opening 100 %
3 For min. net head of 84 m
a) Turbine output power (KW)
b) Discharge (m3 /s)
c) Percentage guide vane opening 100%
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 163/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 164/331
Signature of Bidder Signature of Purchaser 164
Section VI
TECHNICAL SPECIFICATION OF MAIN INLET VALVES
INDEX
Sr. No. Description Page No.
6.1 General. 165
6.2 Design requirements. 165
6.3 Design specifications and performance. 166
6.4 Construction. 167
6.5 Valve operating mechanism. 171
6.6 Oil pressure supply system for Inlet valve. 172
6.7 Pressure system oil. 174
6.8 Accessories. 174
6.9 Hydraulic pressure test at site. 175
6.10 Tools and Equipment 175
6.11 Drawings, designs and manuals to be 175
submitted after award of contract.
6.12 Inspection and tests. 175
6.13 Miscellaneous. 178
6.14 Spares. 178
ANNEXURES
Annexure VI-1 179
List of drawings, designs and manuals to be submitted by
the supplier after award of contract.
Annexure VI-2 181
Departure from specifications.
Data Sheets 182
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 165/331
Signature of Bidder Signature of Purchaser 165
SECTION VI
MAIN INLET VALVE
6.1 GENERAL
The Inlet valve shall be butterfly type. Any fittings, accessories of
apparatus which may not have been specifically mentioned in these
specifications but which are indispensable for reliable operation of the
plant shall be provided by the supplier at no extra cost to the purchaser.
6.2 DESIGN REQUIREMENTS
BASIC DESIGN DATA
i) Number of inlet valves : One
ii) Purpose. : Turbine guard valve.
iii) Nominal diameter of inlet valve : 2000 mm Diameter
iv) Test pressure. : 24 kg/cm2
v) Operation.
Opening : by oil pressurevi) Closing time of Inlet valve:
-at still water : 90 sec.
-at rated discharge : 40 sec.
-under breakdown discharge : 30 sec.
vii) Opening time (including time
required to open by pass valve) : ≤ 90 sec.
viii) By pass valve : Oil pressure operated.
ix) Inlet valve shall have its own pressure oil system with air/oil
accumulator.
x) The Inlet valve and its control system shall be suitable for
frequent opening and closing . The minimum opening and
closing operations per day shall be five each.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 166/331
Signature of Bidder Signature of Purchaser 166
6.3 DESIGN SPECIFICATIONS AND PERFORMANCE.
The Inlet valve shall be free from vibration or other abnormality under
steady-state operating conditions and under any possible transient
conditions and shall have sufficient strength and rigidity against
maximum transient water pressure.
6.3.1. REQUIRED SERVICE CONDITIONS
It shall always be possible to close the Inlet valve safely, without
vibrations or pressure surges, particularly
1) In normal service conditions with turbine guide vanes closed i.e.
without significant water flow and with pressure almost equal on
both sides.
2) In case of emergency with turbine guide vanes fully open i.e.
with rated discharge and with full pressure on one side of the
closing element near the end of closure.
3) In case of an accidental rupture of the pipe between the Inlet
valve and the turbine inlet (i.e. with the breakdown discharge and
the whole pressure on one side already at the beginning of closure.)
6.3.2. GUARANTEES
Guarantees for Inlet valves must be given by the Bidders for:
1) Low level of vibration and noise during closing.
2) Strong construction and adequate design of housing.
3) Proved design of rotating parts.
4) High level of water sealing.
5) Minimum losses in the opened position.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 167/331
Signature of Bidder Signature of Purchaser 167
6.3.3. CONTROL
Control of Inlet valve shall be hydraulically by means of its own oil
pressure unit.
The opening shall be performed by an oil pressure unit discharging into
the valves opening cylinders. Closing of the valve shall be by closing
weights and the discs hydraulic self closing tendency with closing
cylinders acting as brake.
Following modes of control shall be provided.
- Manual local from the respective control cabinet near Inlet valve
location.
- Automatic operation from the unit control board and from
computer system as a part of automatic control sequence of
Turbine Generating Unit.
6.3.4. DISCHARGE SHUTDOWN PERFORMANCE
Inlet valve shall be capable of shutting down rated discharge of turbine
at all heads safely and reliably under unbalanced conditions. Also Inlet
valve shall be capable of closing during emergency conditions, safely
and completely against full unbalanced flow occurring as a result of
breakdown of guide vanes and/or expansion joint or downstream air
valve.
6.3.5 AMOUNT OF WATER LEAKAGE.
Amount of water leakage past downstream side seal shall be less than
0.5 litre per minute at the maximum static pressure of 138. m.w.c.
6.4 CONSTRUCTION.
6.4.1 VALVE BODY
Valve body shall be made of welded carbon steel plates. Valve
body shall be suitably minimum divided if necessary considering
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 168/331
Signature of Bidder Signature of Purchaser 168
transportation and shall be connected by flange at site. Valve
body shall be of sufficiently stiff structure to withstand the
maximum water pressure to cause no detrimental deformation
even against the constant maximum hydrostatic design pressure.
Valve disc shall be provided with valve trunnion of forged steel
at both ends and each trunnion with a stainless steel bushing or
stainless steel welding overlay at the sealing and bearing
portions. Valve trunnion shall be designed to be safe under
maximum pressure and shall smoothly move in the bearing.
Valve trunnion shall have sufficient diameter and shall not cause
excessive deflection. Trunnion bearing shall be self-lubricating
with bronze backing and with Teflon fabric liner.
Trunnion bearing seals shall be on both ends of each bearing and
shall be made of self lubricating PTFE compound with integrated
Rubber-o-ring.
Bearings shall be capable of safely supporting the weight of the
valve disc and force caused by water pressure and shall be
capable of operating the valve smoothly.
Water operated, movable stainless steel seal, seal rings shall be
provided at both the upstream and downstream sides.
Wearing surfaces adjacent to seal rings shall be lined with
corrosion resistant material.
6.4.2 SERVICE SEAL AND MAINTENANCE SEAL
- The inlet valve shall be supplied with a service seal and
maintenance seal.
- The service seal shall be located on the downstream side
of the valve with a flexible rubber (or other adequate
better material) and shall not be split. It shall be
adjustable and repairable. The service seal in the valve
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 169/331
Signature of Bidder Signature of Purchaser 169
casing shall be of corrosion and erosion resistant material
(for example stainless steel service seal)
- The maintenance seal shall be located on the upstream
side of the valve. It shall allow maintaining, repairing or
replacing the valve in situ with the upstream waterways
fully pressurised. The design of this seal shall ensure
required tightness in closed valve position and shall not
tend to flutter under any possible hydraulic conditions in
the pressure shaft. The complete material and sequence of
replacing the service seal shall be furnished by the bidder
in his bid comprising explanatory write ups, sketches and
drawings.
6.4.3 VALVE DISC
Valve disc shall be of lattice (biplane) type made of steel plates
and shall have sufficient strength against all operating conditions
so that no detrimental deformation is caused. Besides, valve disc
shall not cause any abnormal vibration during full opening and
closing operation or transit fluttering and shall not cause muchwater leakage.
Valve disc shall be provided with valve trunnions of forged steel
at both ends and with seal ring made of carbon steel overlaid by
stainless steel at the sealing portions. Valve trunnions shall be
designed to be safe under the maximum dynamic pressure and
shall smoothly move in the bearing. Valve trunnions shall have
sufficient diameter and shall not cause excessive deflection.
Valve disc shall be welded steel structure or cast structure but
shall not be lens type.
Arrangements for removal of air trapped in the pressure shaft
shall be made and shall remain operative during operations.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 170/331
Signature of Bidder Signature of Purchaser 170
6.4.4. PRESSURE BALANCING BY PASS VALVE
A needle type by pass valve of adequate size (i.e. dimension)
shall be provided keeping in view the requirement of overall
opening time in the turbine mode. The valve shall be operated by
means of pressure oil system provided for the valve operation.
The sealing of by pass valve shall be leak proof and its operation
shall be by oil pressure of the governor oil pressure unit.
The by-pass valve shall not cause pitting by cavitations and
excessive vibration and noise during operation. It shall operate
reliably and shall be capable of safely preventing water leakage
when closed. By pass valve shall be fitted with an oil operated
needle valve fitted with a hand operated geared guard valve.
6.4.5. AIR VALVES
Suitable capacity air admission valve shall be provided on down
stream side of valve to protect spiral case and shall also act as air
exhaust valve during pressuring of spiral case. However leakage
of water shall not occur during operating conditions. Suitable air
valve shall also be provided on the upstream of inlet valve to
protect pressure shaft.
6.4.6. CONNECTING PIPE
A) the penstock. The connecting pipe shall be made of samematerial as penstock (ASTM 517 Gr. F or equivalent) and shall
be provided up to 12000 mm from the centre of Turbine towards
the penstock with 300 mm allowance, and shall have inner
diameter of 2000 mm and shall withstand the maximum water
pressure caused by Turbine operation. The inlet valve and
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 171/331
Signature of Bidder Signature of Purchaser 171
connecting pipe shall be connected by rigid flanges and
connecting bolts and nuts and packing shall be supplied.
The connecting pipe shall be equipped with a complete set of
pipes, valves etc. required for dewatering of penstock.
B) Connecting pipe shall be provided between the inlet valve and
the spiral. The connecting pipe shall be made of same material as
penstock (ASTM 517 Gr. F or equivalent).
The connecting pipe shall be equipped with a complete set of
pipes, valves etc. required for dewatering of spiral.
6.5 VALVE OPERATING MECHANISM
Valve operating mechanism shall comprise of the servomotor, operating
rod, lever-closing weight etc. During closing, the servomotor shall act
as a brake. The servomotor shall be of balancing type and heavy
supporting plates with anchor bars, fastenings etc. shall be provided to
mount it on its foundation block.
Main parts of the operating mechanism such as servomotor, rod, lever
and connecting part with the valve trunnions shall have strength and
capacity sufficient for safely and reliably shutting down againstmaximum discharge and opening full flow discharge under all operating
conditions of plant without causing any excessive vibration and other
abnormality. Dimensions of rods shall be so as to transmit all
operational forces without deflections all pivots shall be preferably of
the self-lubricated type. The closing weight shall be of cast iron and fast
securely to their levers.
Operating mechanism shall be provided with a locking device for
manually locking of both the main valve and by-pass valve when they
are closed.
Operating mechanism for the valve including the piping and valves shall
safely and reliably operate during the service for a long period of time.
Parts which come in contact with water shall be made of stainless steel.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 172/331
Signature of Bidder Signature of Purchaser 172
Limit switches for open / close, transmitters, contacts etc. for local and
remote operation and indication of valves shall also be provided.
6.6 OIL PRESSURE SUPPLY SYSTEM FOR INLET VALVE
6.6.1 PURPOSE
Oil pressure supply system shall be used for operation of the inlet valve,
by pass valve and operation control devices for the valve.
6.6.2 SYSTEM
Each system shall comprise the following:
- One sump tank located adjacent to inlet valve and dimensioned
for 120% of the combined oil volume in the servomotor in fully
open position, oil piping and valves and pumps. The tanks shall
be provided with a filling opening (with strainer and cover),
breather, breather openings, sight oil level gauge with cocks,
drain with cock and one man hole for inspection, dial type oil
level gauge and oil level relays for oil level low / high warning.
- Two screw type silent running and self-priming oil pumping unitseach with suction strainer and capable for continuous operations.
The pumps shall be vertical type coupled directly with their
moisture and dust proof alternating current 400V electric
induction motors. Both pumping units shall be identical and
equipped with complete control system permitting the selection
of either unit acting as stand-by and starting automatically as
when other pumping unit fails.
- One small pressure oil accumulator in parallel arrangement
between the oil pump and servomotors and located in the cabinet
of pressure oil unit. This accumulator shall act as a buffer and oil
pressure holding means to prevent the oil pump from too frequent
starting.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 173/331
Signature of Bidder Signature of Purchaser 173
- One hand operated double acting oil pump mounted in the sump
tank.
- The control valves for the inlet valve drive.
- All valves such as safety valve, non-return valve etc.
- All oil piping and shut off valves within the oil sump tank and
between the oil pumping set and servomotors.
Control cabinet containing following instruments and switches.
- Two pressure gauges for indication of upstream and downstream
water pressures of inlet valve along with recording facilities.
- One pressure gauge for indication of oil pressure with contacts.
- One selector switch for local, manual, remote control of inlet
valve.
- Control switches of pumps.
- One pump selector switch.
- Three push button switches for opening, stopping and closing of
butterfly valve.
- One switch with ‘ON’ and ‘OFF’ position for testing of oil
pumping unit.
- One electric heating element.- All necessary relays, fuses, signal LED lamps, terminal blocks
and other equipment for a complete and safe local and remote
control of the inlet valve.
- The cabinet shall be of self-standing sheet metal type, moisture,
vapour, vermin and dust proof with lockable front door. All
wiring shall be run in the most efficient manner from point to
point. There shall be no jointing or teeing of wires between
terminals. All control cabling between individual devices,
instruments, switches etc. up to control cabinet of inlet valve
shall be provided.
Control of pumps shall also be possible from the unit control
board located in the Control Room.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 174/331
Signature of Bidder Signature of Purchaser 174
Pressure switches shall regulate on off control operation of
pressure oil pumps. When the normal oil pumps fails, the stand-
by pump shall start automatically.
Change over between the normal operation and stand-by pump
will be carried out through the changeover switch provided on
the control cabinet.
Besides, starting and stopping shall be carried out not only
automatically and remotely but also manually from control
cabinet.
6.7 PRESSURE SYSTEM OIL
First filling plus 25% extra quantity of pressure system oil, required for
inlet valve and its pressure oil system shall be supplied by the supplier.
Supplier shall suggest the oil equivalent available in India for future
maintenance and operation of the plant.
6.8 ACCESSORIES
Following shall be supplied but shall not be limited to
- All necessary sole plates, foundation bolts, anchors etc. for inletvalve and servomotor.
- All platforms, ladders, stairs, handrails, plate coverings, hooks,
pulley blocks etc. necessary for obtaining easy and safe access
to parts and item which are fitted with equipment. The name
plates showing makers name, serial number, year of manufacture,
type, rating, capacity etc. for valve assembly and servomotor
shall be provided.
- All necessary washers, bolts, nuts etc. of high quality steel.
- All necessary turn buckles and pipe jacks needed for erection,
operation and maintenance.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 175/331
Signature of Bidder Signature of Purchaser 175
6.9 HYDRAULIC PRESSURE TEST AT SITE
If the transport limitations permit, the inlet valve shall be despatched in
one piece duly assembled and pressure tested in workshop. In case, it is
not possible to transport assembled valve to project site, it shall be
pressure tested again at site (upto 1.5 times of design pressure for a
period of not less than 60 minutes) after its erection. To carry out this
pressure testing at site the supplier shall provide one set of bulkheads
common to the two inlet valves and all necessary pickings and jointing
material and testing equipment.
6.10 TOOLS AND EQUIPMENT
One sets of ordinary and special spanners, wrenches, special tools,
slings, ropes etc. for the proper erection and maintenance of the inlet
valve shall be supplied.
One set of spanners and standard tools and equipment. Each set shall be
supplied with a sheet metal lockable toolbox, fitted internally so that the
tools may be stored in an orderly manner.
The heavy tools and equipment shall be marked as to size and purpose.
6.11 DRAWINGS, DESIGNS AND MANUALS TO BE SUBMITTED
AFTER AWARD OF CONTRACT
These shall be submitted as per the list given in Annexure-VI-1 of this
section. Mode of submission of drawings, designs will be intimated to
the successful bidder in due course.
6.12. INSPECTION AND TESTS
Inspection and tests at factory shall be carried out by the supplier as per
list given below:
LEGEND
1. Material analysis.
2. Tensile test.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 176/331
Signature of Bidder Signature of Purchaser 176
3. Notch impact test.
4. Bending test.
5. Visual inspection.
6. Magnetic particle examination.
7. Liquid penetration examination.
8. Ultrasonic test.
9. Radiographic test.
10. Pressure test.
11. Leakage test.
12. Dimensional check.
13. Erection check.
14. Welding procedure approved by purchaser.
15. Corrosion protection.
Suffix – A :- Test at workshop in the presence of Purchaser.
SUBMISSION OF TEST CERTIFICATES :-
The supplier shall submit six (6) copies of test certificates to the
purchaser as per the procedure given below :
For inspection and testing specified to be done in presence of PurchaseTest certificates shall be submitted for approval.
For all other inspection and testing test certificates showing that the
specified tests/inspection has been carried out successfully by the
supplier, shall be submitted for reference.
Following assembles will be inspected
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 177/331
Signature of Bidder Signature of Purchaser 177
Sr.No. Particulars of
Assembly
1 2 3 4 5 6 7 8 9 10 11 12 13 1
4
1
5
1. Bipartition flanges
2. Connection
flanges
3. Bearing hubs.
4. Cylinder Shell
5. Valve body
6. Disc trunnions.
7. Disc plates.
8. Valve disc.
9. Assembled valve,
seat, body and
disc.
10.Operating
mechanism
a.Cylinder flanges
b.Cylinder shell
c.Welded cylinder
d. Cylinder covers
e. Piston rod.
f. Piston rod heads
g. Assembled
operating
mechanism.
11. Operating
mechanical lever
hub.
12. Auxiliary valve.
a. By-Pass valve.
b. Air valve.
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√7
A
√7
A
√
√
√
√
√8A
√
√
√8A
√
√
√8A
√
√ √
√
√
√
9A
√
10A
√10
A
√
√
√
11A
√11
A
12A
12A
√12
A
√
√
√
13A
√
√ √
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 178/331
Signature of Bidder Signature of Purchaser 178
13. Upstream pipe
a. Connecting
flange.
b. Cylinder Shell.
c. Welded pipe.
14. Downstream
pipe.
a. Flange rings.
b. Cylinder shell
c. Welded pipe.
√
√
√
√
√
√ √
√
√ √
√
√8A
√
√
√8A
√
√10
A
√11
A
√12
A
√ √
6.13. MISCELLANEOUS
Relevant provisions wherever applicable needed for indicating, recording
instruments, control switches, safety devices, gauges, flow meters, etc. for
normal operations and field test shall be made by valve supplier in consultation
with turbine supplier and facilities needed by supplier of control and protection
system.
6.14. SPARES
Spares shall be supplied as per Section-III of this volume.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 179/331
Signature of Bidder Signature of Purchaser 179
ANNEXURE VI - 1
List of drawings, designs and manuals to be submitted by the supplier after the
award of contract.
Sr.
No.
Brief Description Within months
From the date of Notification of award of
Contract
Remark
1 2 3 4
1.
2.
3.
4.
5.
6.
7.
8.
9
10
11
12
13
14
DRAWINGS
i) Arrangement of Inlet valve
ii) Installation of Inlet valve
Valve servomotor
Tools, tackles and erection devices of Inlet
valve
Arrangement of Inlet valve piping
Outlet pipe with dismantling joint
Control gear diagram for Inlet valve
Arrangement of air valve
Foundation of valve and servomotor and
loading on foundations, under worst
operating and earthquake conditions
Arrangement of operating mechanism
Sealing arrangement
Pressure oil system with piping
Compressed air system piping
Layout with section of trenches, block outs
etc. for piping & cables
Interconnection and wiring diagram and
cable schedule
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
For reference
For approval
For reference
For reference
For approval
For approval
For approval
For reference
For approval
For approval
For approval
For approval
For approval
For approval
For approval
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 180/331
Signature of Bidder Signature of Purchaser 180
1
2
3
4
DATA
Opening and closing characteristics.
Max. Efforts and Max. Toque on foundation
and steel shaft.
Consideration made in data about loading
on foundation of main inlet valve and
servomotors.
Adequacy of oil supply system.
3
3
3
3
For approval
For approval
For approval
For approval
1.
2
3.
4.
5.
MANUALS
Manuals for storage, preservation and
handling of the supplied goods
Manual for erection/ dismantling testing and
commissioning of the supplied goods
Maintenance manual
Tolerance for assembly
List of consumables, oils & Spares
12
12
20
12
12
For reference
For reference
For reference
For reference
For reference
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 181/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 182/331
Signature of Bidder Signature of Purchaser 182
DATA SHEETS
1 Type :- ……………………..
2 Nominal diameter :- …………………….. mm
3 Material of valve :- ……………………..
4 Material of valve disc :- ……………………..
5 Design pressure :- …………………….. Kg/cm2
6 Test pressure :- …………………….. Kg/cm2
7 Factor of safety over yield point :- ……………………..
8 Time of opening :- …………………….. Sec.
9 Time of closing during
Normal operation :- …………………….. Sec.
During emergency :- …………………….. Sec.
10 Leakage through closed valve :- …………………….. Ltr/Sec.
11 Method of opening :- ……………………..
12 Method of closing :- ……………………..
13 No. of Servomotor :- ……………………..
14 Whether maintenance seal is provided :- ……………………..
15 Location of maintenance seal :- ……………………..
16 Weight of valve :- …………………….. Kg
17 Weight of heaviest part to be transported :- …………………….. Kg
18 Dimension of largest part to be transported
(Lx BxH)
:- ……………………..
19 Oil pressure system :- ……………………..
a) Main oil pump
i) Type of pump :- ……………………..
ii) Capacity of pump :- …………………….. LPM
iii) Rating of pump motor
KW :- ……………………..
rpm :- ……………………..
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 183/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 184/331
Signature of Bidder Signature of Purchaser 184
SECTION – VII
TECHNICAL SPECIFICATIONS OF STATION
AUXILIARIES
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 185/331
Signature of Bidder Signature of Purchaser 185
SECTION VII
TECHNICAL SPECIFICATIONS OF STATION AUXILIARIES.
INDEX
Sr. No.. Description Page no.
7.1 General. 186
7.2 Schedule of Requirements. 186
7.3 Compressed Air System. 188
7.4 Drainage and Dewatering System. 191
7.5 Cooling Water System. 195
7.6 Standards. 199
7.7 Inspection and Tests. 200
7.8 Drawing and Data To Be submitted 201
with Bid.
7.9 Drawings, Designs and Manuals to be 201
furnished after Award of Contract.
7.10 Spares. 201
ANNEXURES.
Annexure - VII-1 202
List of Drawings, Designs and Manuals to
be submitted by the supplier after award of
contract.
Annexure - VII-2 205
Departure from specifications.
Data Sheets 206
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 186/331
Signature of Bidder Signature of Purchaser 186
SECTION VII
TECHNICAL SPECIFICATIONS OF STATION AUXILIARIES.
7.1 GENERAL.
This section covers the technical specification and requirement of the
station auxiliary system/equipments.
Any fittings, accessories of apparatus which may not have been
specifically mentioned in these specifications but which are
indispensable for reliable operation of the plant shall be provided by
supplier at no extra cost to the purchaser.
The capacities and ratings mentioned for various auxiliaries in the
scheme shall be rechecked by the supplier and these shall be subject to
approval by the purchaser.
Relevant provisions of section No.I shall be applicable.
7.2 SCHEDULE OF REQUIREMENTS.
7.2.1 COMPRESSED AIR SYSTEM.
1) Compressed air system shall consist of following :-.
2 Nos. of compressors :- (one main and one 100% stand-by) to
cater the compressed air requirement of Generator brakes,
Governor OPU, shaft seal etc. .(one main and one 100% stand-
by).
Air Receivers:
1 No. of adequate capacity Air Receiver located at suitable
location.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 187/331
Signature of Bidder Signature of Purchaser 187
Piping and Valves:
All pipes, valves required for the entire compressor system and to
lead the compressed air to individual equipment with pressure
gauges, pressure switches etc.
2) Motor Control Centre:
For the compressors mentioned above, motor control centre to be
located near compressor shall be provided.
3) Cabling:
All power and control cabling between the motor control centre
to compressor motor sets and all devices such as pressure
switches, etc. complete with clamps, trays, ferrules etc. All cable
shall be of FRLS copper conductor cables.
7.2.2 DRAINAGE AND DEWATERING SYSTEM.
2 sets submersible type or pump motor type pump motor sets of
adequate capacity shall be provided.
Out of these, one set will be in normal operation and other as standby.Piping and Valves: All piping required complete with necessary valves,
fittings etc.
Motor Control Centre: Motor Control Centre for all the above Two (2)
sets and to be located in pump room shall be provided complete with
suitable starter.
Cabling: All power and control cabling between the motor control
centre to pump motor sets and all devices such as level switches, flow
relays etc. complete with clamps, trays, ferrules etc. All cable shall be of
FRLS copper conductor cables.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 188/331
Signature of Bidder Signature of Purchaser 188
7.2.3 COOLING WATER SYSTEM.
The cooling water for main plant shall be tapped from penstock before
BFV. The cooling water after circulation shall be discharged into tail
race. The supplier shall decide whether booster pumps are required for
circulation of water with sufficient pressure.
Piping and Valves: Piping, manifold and valves required penstock to
each equipment and discharge piping from each equipment to tail race.
Motor Control Centre : Motor Control Centre for all the above pump-
motor sets complete with suitable starter.
Cabling : All power and control cabling between motor control centre
and cooling water pump-motor sets complete with clamps, trays,
ferrules etc. All cable shall be of FRLS copper conductor cables.
NOTES:
Motors : All motors of auxiliary systems mentioned above shall be
suitable for operation at 3 phase, 400 V system, and shall have class F
insulation with temperature rise corresponding to class B insulation. All
motors and starters shall be suitable for 15 times on/off operation per
hour. Degree of protection for motors : IP-54.
7.3 COMPRESSED AIR SYSTEM.
7.3.1 OPERATION SYSTEM.
- Starting and stopping of the air compressors shall be carried out
automatically by pressure relays mounted to pressure system and to
general requirement air pressure reservoirs and by manual operation
from the motor control panel.
- Two Nos. of air compressor shall be provided one for normal
operation and other as stand-by. Normal operating air compressors shall
be selected as desired by change-over switch mounted on motor control
panel. The standby pump shall be selected automatically when air
pressure drops because of a trouble in the normal operating air
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 189/331
Signature of Bidder Signature of Purchaser 189
compressor or other reason. The air compressor shall automatically
stop when the pressure is restored.
7.3.2 ACCESSORIES OF COMPRESSORS.
Following accessories and fittings shall be provided to each set of air
compressors :-
-Water Separator : 1 set.
-Check Valve : 1 set.
-Unloader for starting : 1 No.
-Lubricating device : 1 set.
-Water flow relay (in case of water
cooling type) : 1 set.
-Cooling device : 1 set.
-Drain disposal device : 1 set.
-Interlock switch : 1 set.
-Pressure reducer ( to match required
brake pressure) : 1 set.
7.3.3 PRESSURE AIR RECEIVERS.
(a) Maximum and normal working air pressure, starting pressure of
the standby air compressor and alarm pressure shall be decided
through mutual discussion with Purchaser after the award of
contract.
(b) Air receivers shall be provided with the following accessories :-
i) Air pressure gauge (for : 1 No.
mounting to the turbine
control panel)
ii) Air pressure gauge (for : 1 No.
mounting to the air
pressure reservoir).
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 190/331
Signature of Bidder Signature of Purchaser 190
iii) Air pressure relays : 1 set.
iv) Feed air valves, exhaust
air valves, check valves,
drain valves & other stop
valves. : 1 set.
v) Safety valves : 1 set.
7.3.4 MOTOR CONTROL CENTER FOR COMPRESSED AIR SYSTEM.
From 400 V A.C. auxiliary supply scheme, one feeder shall be brought
to this motor control centre. Power cable for this purpose shall be
provided by the supplier.
Following equipment shall be provided by the supplier on the motor
control centre:-
1. Incoming Breakers : 1No.
2. Bus-Bars : Entire length of panel.
3. Feeder Breakers : 4 Nos. +2 Nos. spare.
4. Control Switches : ON/OFF Switch for each compressor.
Priority selector switchAuto manual switch
5. Indicators : ON/OFF/ Trip Lamps for each compressor.
6. Indicating Meters : i) 1No.Voltmeter with selector switch.
: ii) 1No. Ammeters with selector switch.
7. Starters : ON line starters.
8. Selector Switch : LOCAL/REMOTE for each compressor
9. Protection : thermal over current relay
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 191/331
Signature of Bidder Signature of Purchaser 191
7.3.5 PIPES AND VALVES.
All pipes and valves required up to the respective equipment shall be
supplied along with complete set of flange coupling, bolts, nuts and
packing. Main bus pipeline for braking shall be duplicated. All
compressed air piping shall be of seamless steel.
7.3.6 LUBRICANTS.
Sufficient quantity required for first fill of lubricant, grease, oil etc. plus
25% extra shall be supplied and included in bid cost.
7.3.7 CABLES.
Power supply cables and all control cabling from motor control centre to
compressors, receivers etc. is included in Bidder’s scope. Compressor
starting shall be regulated from the pressure switches provided on air
receivers. The motor control centre shall be located near compressor.
Cables from each auxiliary system equipment to its control panel (both
of which are included in supplier’s scope) shall be supplied. Cables for
interconnection between computer and computer based control panel
shall also be supplied. All cable shall be of FRLS copper conductorcables.
7.4 DRAINAGE AND DE-WATERING SYSTEM.
The drain water of entire power house and fire hydrant discharge will be
collected in Drainage and Dewatering pit located in the machine hall.
The supplier shall inform purchaser after detailed design and calculation
the size of pit required. For dewatering of draft tubes gravity drain shall
be considered. Necessary piping shall be laid by supplier up to the
Drainage and Dewatering pit. The water in the pit shall be discharged
at suitable location outside the power house.
Drainage and dewatering system shall comprise of following:
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 192/331
Signature of Bidder Signature of Purchaser 192
7.4.1 PUMP-MOTOR SET.
a) Pump: The pumps shall be of submersible type and sturdy and of
proven design with one or multi stage and with a double seal
fitted to pump shaft. The pumps shall be suitable to handle the
raw and unscratched water having turbidity of about 6000 ppm
without any damage or adverse effect to any parts of the pump.
The bowls shall be made of closed grain cast iron free of any
defects. The pump impellers shall be of one cast iron or phosphor
bronze and shall be dynamically balanced. Lockout shall be
provided to arrest the excess lift of impeller at the time of
starting. The pump bearing shall be of self-lubricated type. Fully
streamlined discharge case-cum non-return valve shall be
provided at the outlet of each pump. The non-return valve shall
be spring loaded needle type. Depending on the water level in the
sump pit the pumps shall start or switch-off automatically with
the help of float controls. All the control cables required for these
purpose shall be provided by the supplier.
b) Motor: Motor shall be of squirrel cage, induction type, 400 V, 3
phase, alternating current directly coupled to the pump and
forming a part and parcel of pump-motor set. The motor shall be
wet type.
DOL starter shall be provided. The motor shall be provided with
dual seal arrangement and sand guard for its protection from
outside water. The stampings used in motor shall be double
varnished to have better anti-rusting property. The rotor as well
as stator shall be vacuum impregnated with superior qualityvarnish and shall be baked under the controlled conditions to
ensure proper and long life. Stainless steel sleeves ground to
close tolerance shall be provided at the bearing locations. The
motor winding wires shall be made of water resistant type
insulation and shall be of copper. Bearing assembly shall be fitted
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 193/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 194/331
Signature of Bidder Signature of Purchaser 194
7.4.3 FLOAT CONTROLLERS.
Float controllers shall be provided in the sump pit. The control cables
from these controllers shall be taken to motor control centre for
regulation of motor starting.
7.4.4 MOUNTINGS AND SUPPORTING ARRANGEMENTS.
Foundation mountings for pump motors, supporting arrangement for
columns of suction and delivery pipes shall be supplied.
7.5.5 MOTOR CONTROL CENTRE FOR DRAINAGE AND
DEWATERING PUMPS.
From 400 V auxiliary supply scheme, one feeder shall be brought to
this motor control centre. Following equipment shall be mounted on the
motor control centre:
1) Incoming breakers : 1 No.
2) Bus bar : Entire length of panel
3) Feeder Breakers : Two numbers + Two numbers
spares.
4) Control switches : On/Off switch for each pump.5) Indicators : On/Off /Trip lamps for each pump
6) Indicating meters i) One No. Voltmeter with selector
switch.
ii)One No. Ammeter with selector
switch.
7) Starters 2 Nos on line starters.
8) Selector i) Local/remote for each pump - 2
Nos.
ii) Auto/manual for each Pump -
2Nos.
iii) Priority selector switch -1 No.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 195/331
Signature of Bidder Signature of Purchaser 195
9) Protection : Thermal over current protection
10) Cables :- Power supply cables and all control cablings from motor
control centre to motors, load controllers etc. is included in
Bidder’s scope. Cables from each auxiliary system equipment to
its control panel (both of which are included in suppliers scope)
shall be supplied.
Motor starting shall be regulated from the float controllers provided in
drainage and dewatering sump.
7.5 COOLING WATER SYSTEM.
7.5.1 PURPOSE.
This system shall be used for supplying cooling water for following
purposes:
1) Cooling water for generators equipped with water cooled heat
exchangers
2) Cooling water for generator guide and thrust bearings
3) Cooling water for Turbine guide bearing and shaft seal.
4) Cooling water for Turbine governor oil pressure system
5) Other requirements if any.
The cooling water for main plant shall be tapped from penstock before
BFV. The cooling water after circulation shall be discharged into tail
race. The supplier shall decide whether booster pumps are required for
circulation of water with sufficient pressure. If booster pumps are
required then following specification shall be applicable.
One motor- pumps is specified for normal operation conditions and one
pump shall be provided as stand-by pump .
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 196/331
Signature of Bidder Signature of Purchaser 196
The above mentioned motor pumps will pump water from penstock and
supply to each equipment and discharge piping from each equipment
back to the draft tube.
Starting and stopping of the cooling water pump shall be normally
carried out by automatic control ( from main plant start sequence
program) and in case of trouble in the normal working cooling water
pump, the standby cooling water pump shall start automatically.
Besides, it shall be so arranged that the normal working and stand by
cooling water pumps can be started and stopped by manual operations at
the motor panel.
7.5.2 PUMP MOTOR SETS.
a) Pumps: - The pumps shall be centrifugal type and sturdy and
proven design with one stage and with a double seal fitted to
pump shaft. The pumps shall be suitable to handle the raw and
unscratched water having turbidity of about 6000 ppm without
any damage or adverse effect to any parts of the pump. The
impellers shall be made of cast iron or phosphor bronze and shall
be dynamically balanced. Lockout shall be provided to arrest theexcess lift of impeller at the time of starting. The pump bearings
shall be self lubricated type. Fully streamlined discharge case-
cum-non return valve shall be provided at the outlet of each
pump. The non-return valve shall be of spring loaded needle
type. All the control cables required for these purpose shall be
provided by the supplier.
b) Motors: - Motors shall be of squirrel cage, 400 V induction type,
3 phase, alternating current directly coupled to the pump and
forming a part and parcel of pump motor set. The motor shall be
wet type.
The motor shall be provided with dual seal arrangement and sand
guard for its protection from outside water.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 197/331
Signature of Bidder Signature of Purchaser 197
The stampings used in motor shall be double varnished to have
better anti-rusting property.
The rotor as well as the stator shall be vacuum impregnated with
superior quality varnish and shall be baked under the controlled
conditions to ensure proper bonding and long life.
The motor winding wires shall be made of water resistant type
insulation and shall be of copper.
Bearing assembly shall be fitted with tilting pad bearings,
mounted on stainless steel balls, and shall be supported by
rocking pins. Bearings shall be suitable to absorb the vertical
thrust.
Suitable rubber diaphragm shall be provided to the motor for
pressure compensation.
All fasteners shall be chemically treated for protection against
rust.The entry of power supply cables to the motor shall be
through suitable cable gland, fitted on the body of the motor and
the cable entry arrangement shall be fully watertight. The bidder
shall furnish the details about arrangement of cable entry to
motor, in his bid including type of starter. Bidder shall alsosupply details of arrangement for disconnection of the cable
(outside the water) in order to remove the pump.
The pump shall have nameplate indicating:
Name of Manufacturer, Type, rating and rpm,
Serial number of pump, Q (discharge) and H (head) values for
duty point.
7.5.3 FILTER AND STRAINER
The cooling water from (penstock) shall be first passed through rotary
automatic cleaning water filter. The cooling water to be fed to shaft seal
and runner labyrinth shall be again passed through fine strainers. The
filters and strainers shall be provided as under : -
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 198/331
Signature of Bidder Signature of Purchaser 198
- Main rotary filter automatic & manual
- Fine filters for shaft seal (automatic and manual)
- Fine filter for runner labyrinth (manual)
- Strainer
The main strainer and filter shall have a capacity sufficient for passing
the cooling water requirement of entire power station.
The automatic strainer shall be capable of automatically changing over
by rotating the strainer at pre-determined intervals and cleaning inside
of strainer automatically. The design of manual strainer shall be such
that the cleaning is carried out by manual operations of valves.
7.5.4 MOTOR CONTROL CENTRE FOR COOLING WATER PUMPS
From the 400 V A. C. auxiliary supply scheme, one feeder shall be
brought to this motor control centre. Following equipments shall be
mounted on this motor control centre: -
1) Incoming Breakers : 1 No.
2) Bus-Bar : for the entire length of panel.
3) Feeder Breakers : 2 Nos. + 2Nos. spares.
4) Control Switches : ON/OFF switches
5) Indicators : ON/OFF / trip lamps.
6) Switches : i) 1 No. Voltmeter selector Switch
ii) 1 No. Ammeter Selector Switch
7) Indicating Meters : i) 1 No. Voltmeter
ii) 1 No. Ammeter
8) Starters : DOL type
9) Selector Switches : i) LOCAL/REMOTE for each pump.ii) AUTO /MANUAL for each pump.
10) Cables: Power supply cables and all control cabling from motor
control centre to pumps, float controllers etc. is included in
Bidder’s scope. Cables from each auxiliary system equipment to
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 199/331
Signature of Bidder Signature of Purchaser 199
its control panel (both of which are included in supplier’s scope)
shall be supplied. Cables for interconnection between computer
and computer based control panels shall also be supplied.
7.5.5. PIPING AND VALVES;
Piping, manifold, valves etc. required from penstock to each equipment
and discharge piping from each equipment to draft tube shall be
included in Supplier’s scope of works
7.5.6. PRESSURE GAUGES
Pressure gauges shall be provided as required.
7.5.7 PRESSURE CONTROLLERS
Pressure controllers shall be provided in the cooling water system. The
control cables from these controllers shall be taken to motor control
centre for regulation of motor starting.
7.5.8 MOUNTINGS AND SUPPORTING ARRANGEMENT
Foundation mountings for pump motor sets, supporting arrangementsfor suction and delivery columns shall be supplied.
7.6 STANDARDS
Equipment shall be in accordance with the latest IEC standards or
equivalent internationally accepted standards. Some of the standards are
listed below but shall not be limited to: -
IEC 298 - Cased equipment
IEC 264 - Common clauses, IEC 502 - M.V. Cables
IEC 227 - PVC Conductor and Cable.
IEC 287 - Calculations and Dimensions.
IEC 269 - Fuses.
IEC 364 - Installation
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 200/331
Signature of Bidder Signature of Purchaser 200
IEC 439 - Operating Mechanism, IEC 51-1 to 51-5
Measuring Devices.
IEC 145 & 521 - Counters, IEC 255 (1 to 22) - Relays
IEC 72 - Motors
IEC 404 - Magnetic Materials
IEC 349 & ISO 1996 - Noise
VDI 2056 - Vibrations
Swedish Standard 515 - Corrosion Protection
ASTMA 435 - Steel Plate Testing
ASME V - Welding Materials
ASTMA 609 & 709 - Cast Part testing
ASTMA 388 - Forged part testing
7.7. INSPECTION AND TESTS
The Supplier shall carry out inspection and tests at factory and site in
respect of auxiliaries as per the list given below
LEGEND
1. Material test
2. Non-destructive inspection of assemblies/components.3. Pressure test
4. Workmanship test
5. Assembly inspection
6. Operational tests
7. Commissioning tests
SUBMISSION OF TEST CERTIFICATES
The supplier shall submit 6 copies of test certificates to the Purchaser as
per the procedure given below:
i) FOR INSPECTION AND TESTING SPECIFIED TO BE DONE
IN PRESENCE OF PURCHASER.
Test certificates shall be submitted for approval.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 201/331
Signature of Bidder Signature of Purchaser 201
ii) FOR ALL OTHER INSPECTION AND TESTING
Test certificates showing that the specified tests/inspection has
been carried out successfully by the Supplier, shall be submitted
for reference.
7.8 DRAWINGS AND DATA TO BE SUBMITTED WITH BID
Bidder shall submit in his bid information and general drawings
describing and illustrating the equipment he proposes to offer, in such a
manner as to make possible a complete understanding of the equipment
on which bid is based. The information shall include all essential
dimensions, types of materials to be used in major parts with the
chemical and physical properties of materials and the schematics, layout
drawings, control schemes and data for the:
1. Cooling water system
2. Drainage and dewatering system
3. Compressed air system
All “Data Sheets” enclosed with this section must be completely filled
in by the Bidder.
7.9 DRAWINGS, DESIGNS AND MANUALS TO BE FURNISHED
AFTER AWARD OF CONTRACT
These shall be submitted as per the list given in Annexure VII-I to this
section.
Mode of submission of drawings and designs will be intimated to the
successful Bidder in due course.
7.10 SPARES
Spares shall be supplied as per list under Section III of this Volume.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 202/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 203/331
Signature of Bidder Signature of Purchaser 203
10. Pipe layout of drainage and
dewatering system 6 For approval
11. Schematic of drainage and
dewatering system 6 For approval
12. Motor Control centre panel for
drainage and dewatering system 6 For approval
13 Interconnection and wiring
diagram and cable schedules
of equipment 8 For reference
14. Foundation / support
arrangement of, 6 For approval
* Cooling water pumps
* Drainage/dewatering pumps
* Compressor air equipment,
air receivers
* All water piping, valves
pump columns
* Switchgear panels of cooling
water, drainage/dewateringand compressed air system.
DATA
1. Adequacy of cooling
water system 3 For approval
2. Adequacy of dewatering and
drainage pit size and volume 3 For approval
3. Adequacy of pump capacity for
cooling water, drainage and
dewatering system 3 For approval
4. Adequacy of compressed air
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 204/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 205/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 206/331
Signature of Bidder Signature of Purchaser 206
DATA SHEETS
COMPRESSED AIR SYSTEM
-Total number of compressors
-Discharge of one compressor at working rated
pressure
-Rated working pressure of compressor
-Rated power of compressor motor
-Rated speed of compressor motor
-Total number of air tanks
-Volume of one air tank for general
requirement
-Air leakage during operation
………. N m3 /s
........ …. kg/s
... …………MPa
………….. kW
………….. rpm
................
............ m3
... ... kg/s
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 207/331
Signature of Bidder Signature of Purchaser 207
COOLING WATER SYSTEM
TECHNICAL DATA SHEET FOR SUBMERSIBLE MOTOR PUMP-UNITS
ALTERNATIVELY TURBINE PUMP - MOTOR SET
Cooling Water Pumps Offered
Value
Quantity ..........
Type of operation ..........
Manufacturer
Type ..........
Rated speed .......... rpm
Discharge heads .......... m
Corresponding
Discharges Qn (at Hn) .......... m3 /sec
Efficiency (nominal point) .......... %
Power Rating .......... kW
Motor Voltage -------------
Type of starter --------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 208/331
Signature of Bidder Signature of Purchaser 208
DRAINAGE AND DEWATERING SYSTEM
TECHNICAL DATA SHEET FOR SUBMERSIBLE MOTOR - PUMP UNITS
ALTERNATIVELY TURBINE PUMP- MOTOR SET
Drainage Pumps Offered Values
Quantity ............
Type of operation
Manufacture ............
Type
Rated speed ............ rpm
Discharge ............. m3 /sec
Heads Hn ............. m
Corresponding
Discharges Qn (atHn) ............ m3 /sec
Efficiency
(Nominal point ............. m3 /sec
Motor power kW ............. kW
Materials
body .............
Impeller ............
Shaft ............
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 209/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 210/331
Signature of Bidder Signature of Purchaser 210
SECTION NO. VIII
TECHNICAL SPECIFICATION OF GENERATORI N D E X
Sr.No. Description PAGE
NO.
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
812
8.13
Scope
Standards
Type and main characteristics
Particular mechanical design characteristics
Particular electrical design considerations
Performance Guarantee
Technical specifications of Generator.
Technical specifications of Static Excitation
Factory test for Generator-Motor and related
equipment.
Material test
Site tests for Generator and related equipment.
Drawings, Designs, Studies and Manuals to be
submitted by the supplier after award of
contract
Spares
ANNEXURE
Annexure VIII-1
DATA SHEETSData Sheets
211
211
212
212
213
215
216
249
258
259
266
270
270
271
276
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 211/331
Signature of Bidder Signature of Purchaser 211
SECTION VIII
TECHNICAL SPECIFICATION OF GENERATOR
8.1 Scope :
This section covers technical specification of one number of three phase
vertical shaft synchronous generator and related equipment including static
excitation equipment.
The generator shall be of 15 MW rated output, 0.9 p.f.,11 KV, 375 rpm. 3 ph.
50 Hz, Vertical shaft synchronous Generator and capable of giving
continuous output of 110% of rated output. The generator shall be suitable
for direct coupling to the turbine specified under Section –V. Any fittings,
accessories or apparatus which may not have been specifically mentioned in
these specifications but which are indispensable for reliable operation of the
plant shall be provided by the Supplier at no extra cost to the Purchaser.
8.2 STANDARDS
The applicable standards but not limited to :
1) IEC..... 34 ( parts ...........)
2) VDE Standards of group 05303) IEC 85 (Insulation classes)
4) ANSIB 49-1-1967 Shaft couplings, Integrally Forged
Flange type for Hydro Electric units.
5) N.E.M.A. LG 2 “Vertical Hydraulic Turbine
Generator Shaft Run out tolerances” shop check or IEEE 810
whichever stipulated severe conditions.
6) V.D.I. 2056 for provisions regarding Radial Vibration Amplitudes.
7) V.D.I . 2060 for provisions regarding Rotor balancing.
8) “Rathbone curves” for provisions regarding Radial & Axial Vibration
accelerations.
9) I.E.C. 287 - Calculation of continuous current rating
(100% load factor).
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 212/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 213/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 214/331
Signature of Bidder Signature of Purchaser 214
Rated frequency is 50 Hz. The supplier shall guarantee rated
continuous output within the range of frequency from 47.5 Hz. to 51.5
Hz and voltage range of 0.9 Un to 1.1 Un.
Supplier shall furnish information regarding outputs available below
47.5 Hz. (47 and 46 Hz) and duration of such output. Rated power
factor is 0.90 (over excited) - 1.0-0.90 (under excited)
The most unfavourable sudden two phase terminal short circuit at
nominal voltage, 50% pole short-circuits with simultaneous over speed
for 3 seconds shall be considered. No damage whatsoever must occur
to the generator itself and the foundations in either case.
2) STATOR WINDING CONNECTION
The stator winding shall be star connected and neutral point to be
grounded through primary of power or voltage transformer and
resister.
3) Winding Insulation Class
The stator and field windings shall be entirely insulated with class F
materials (thermosetting type).
4) Wave form and Telephone Harmonic Factor ( THF)
The wave form of the open-circuit terminal voltage shall not deviatefrom a true sine wave by more than 5%. The Telephone Harmonic
Factor shall not exceed 1.5%.
5) Limits of Temperature and Temperature Rises
The maximum output which should be available at its terminals at
power factors cos ∅ 0.9(over excited)...1...0.90(under excited) shall
be 18.333 MVA .
When the generator operates at rated output, power factor, speed and
voltage, the stator and field winding temperature rise of generator
measured by embedded thermostat temperature detector and resistance
method shall not exceed 750
C & 850
C respectively.
When the generator operates at maximum output, rated power factors,
speed and voltage, the stator and field winding temperature rise of
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 215/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 216/331
Signature of Bidder Signature of Purchaser 216
1) Efficiency Guarantee: - The efficiency of the generator shall be guaranteed
by the supplier. The efficiency shall be determined by the summation of
losses method as specified in IS 4889- 1968 or /and latest amendment there to
and shall be subject to the tolerances specified in IS: 4722 -1968. Any
shortfall in the values of guaranteed parameters shall be subjected to penalty
or rejection as given in Volume-I.
6.2 Output and Temperature rise Guarantee:-
The hydro generator shall be guaranteed to give its rated and 10% overload
output at rated voltage and power factor without exceeding the temperature
rises. Any shortfall in the values of guaranteed parameters shall be subjected
to penalty or rejection as given in Volume-I.
The contractor shall be given all reasonable opportunities to make good and
meet the guarantees before the application of penalty or rejection of hydro
generator as a result of above clauses.
8.7 TECHNICAL SPECIFICATION OF GENERATOR
1) All material to be used shall be suitable and adequate for the purpose
intended and shall conform to the IEC standards.No patching, blocking, shimming or any other similar means of
overcoming defects, discrepancies or errors shall be permitted without
approval of Purchaser.
The generator design shall be such that the movements and
deformations due to temperature variations are compensated and the
loads and resulting forces, which would act on the foundation, are
substantially reduced. It should further be ensured that:
i) No buckling of stator core laminations takes place.
ii) The concentricity and the size of air gap shall remain
unchanged.
The unit shall be designed for unit assembly during erection and for
the removal of the complete assembled generator rotor during major
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 217/331
Signature of Bidder Signature of Purchaser 217
maintenance programs. This design shall permit the assembly and
dismantling operations to be performed as conveniently and quickly as
possible with the facilities of the powerhouse crane. Entire stator and
rotor shall be built at site to avoid any deformation in transit. Proper
stator and rotor lifting device for connecting to power house crane
shall be provided. The necessary information regarding the shape of
the hooks shall be taken into consideration.
Supplier shall declare along with bid his work plan for stator and rotor
building at site on service bay, built up in situ or partial building on
service bay and situ. Periods for such activities shall be distinctly
shown and his proposal for execution of job shall be declared in the
bid. Bidder shall note that entire stator and rotor are to be built at site.
Considerations in the design shall be given to the following
requirement for maintenance program.
-The largest component of the turbine shall be capable of withdrawal
through the stator bore after removal of the unit superstructure and
generator rotor.
- Rotor field poles shall be arranged in such a manner as to permit easy
removal with the rotor in place. Field pole electrical connections shallbe located in a position to facilitate ease in inspection, separation and
reconnection.
-The phase terminals of the windings shall be brought out of the
generator concrete housing for proper connections with bus duct. The
neutral terminals of the phase shall be brought out separately to
abominate current transformers before forming the star point of the
winding (Please refer the single line diagram). The two ends of field
windings shall be connected to two slip rings mounted on shaft.
2. STATOR GENERAL
The stator shall consist of a frame with air/water heat exchangers on its
outer periphery, built-in laminated core with radial air ducts and bar
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 218/331
Signature of Bidder Signature of Purchaser 218
winding in slots. The stator frame shall also support the upper bearing
bracket, upper deck and the bushing of the phase bus bars and
generator neutral connection. A portable, steel fabricated, inspection
ladder shall be provided.
STATOR FRAME
The stator frame shall be fabricated from steel plates and shall be of
welded construction. The frame shall be sufficiently strong to
withstand the most severe forces during the abnormal conditions e.g.
sudden short circuit & faulty synchronisation. Air coolers shall be
mounted around the outer periphery of stator frame. The frame shall be
provided with adequate number of horizontal stiffeners.
STATOR CORE
The stator core shall be made of low loss, high grade, non-ageing,
silicon magnetic steel laminations having a favourable bending co-
efficient. The lamination shall be accurately punched and deburred so
as to obtain very smooth surface at winding slots and keys slots. Each
lamination shall be coated on both sides with class F insulating layer toeliminate inter lamination and eddy current circulation.
The stator core shall be built up in stacks of equal height as far as
possible, the bottom and top most stacks shall give a special treatment
so as to form solid mass.
While stacking the lamination, intermediate pressure treatment shall be
given several times and the whole core should be pressed at both ends,
by means of clamping rings with fingers pressing over teeth portion to
ensure high tightness and mechanical strength of the core. The stack
of laminations must be firmly anchored to the frame and pressed
together in a firm and uniform way, which does not require
readjustments after installation. In particular, vibration of stator as a
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 219/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 220/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 221/331
Signature of Bidder Signature of Purchaser 221
conditions but also under severe fault conditions. The insulation on
the stator coils shall be sufficiently durable so that in case it is
necessary to remove coils, removal and replacement may be effected
without damage to the insulation of any of the other coils. The quality
and life of the insulation shall not be impaired in attaining the above
requirements. Class F insulation of proven design and which has
shown no breakdown shall be used. The details of the installation
where such insulation system is used shall be stated in the bid.
Generator winding cyclic & ageing tests (see IEC-34-18-1/1992-02-
Functional evaluation of insulation system for rotating machine.) to
determine the life span under cyclic thermal loadings shall be
conducted by the Bidder. If the supplier has already conducted such
tests at shop, type test reports shall be furnished with the bid.
The construction of winding bars and the winding in slots shall be fully
explained with drawings and detailed description.
The class F insulation system used shall be proven. The bidder must
furnish examples where the same system is used and is in trouble free
operation.
Corona shielding applied to the fully insulated bar shall have thefollowing structure.
The straight part of the bar shall be covered with a conducting varnish
(outer corona protection) in order to avoid potential differences
between the surface of insulation and the core iron. The bend end
portions of bars are covered with a semi-conducting varnish and in
addition a special tape be wound over a certain portion to ensure the
desired potential distribution (Capacitive control of potential
distribution). These measures would avoid creeping discharges along
the surface of insulation or even a breakdown.
The bars shall be carefully inserted in slots and properly aligned. It
shall be ensured that the wedges are firmly and permanently seated and
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 222/331
Signature of Bidder Signature of Purchaser 222
there are no possibilities of damaging the core lamination edges in the
slot. Rewedging should be virtually not necessary.
The packing shall be effective in both the circumferential and radial
directions. When installed, the coil sides shall be tight within the slot
so that a 0.5 mm. filler gauge will not enter any gap between the coil
and slot sides. The 0.5-mm. fillers gauge “no-go” standard shall apply
to at least 90% of the stacked core length. The remaining 10% has
individual ‘go ‘ length of less than 0.80 mm.
After final wedging, there shall be no measurable radial clearance
between the coil and slot or wedge. Slot wedges shall be of phenolic
or glass-reinforced polyester material, highly resistant to thermal
ageing and designed to minimize any tendency to relax the radial
pressure exerted on the coils.
The stator coil insulation, wedging, packing, brazing and tying shall be
such as to minimize the effect of thermal shock and of additional
differential expansion which may occur as a result of the cyclic
loading.
End connections of the stator coils shall be made at the top of winding.
The end portion of the winding shall be rigidly supported to preventany movement and distortion even under the most unfavourable short
circuit conditions. No metallic part, which does not correspond to
class F, shall be used for this purpose.
The slot portion of the bars must be manufactured to close tolerances.
No grinding of insulation will be permitted to achieve required
dimensions.
The connections between half coils shall be covered in the ends by
glass fiber insulation caps.
Bracing shall make all connections in end windings. The strands of
corresponding upper and lower layers bars shall be soldered at the
connecting end using copper clips to ensure adequate mechanical
strength and conductivity. A fiberglass-insulating cap shall be placed
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 223/331
Signature of Bidder Signature of Purchaser 223
over each connection and filled with an epoxy compound to secure it
to the ground insulation.
The winding overhang portion shall be rigidly supported, lashed
together by impregnated glass cords so as to form a rigid cone, which
can withstand the forces due to a sudden short circuit. The system
must be described in bid. Circulating primary split-phase current
under normal operating conditions shall be less than 2.5% of total rated
phase current.
Each winding bar shall be subjected to tangent delta measuring kV test
in shop and the dielectric losses of each coil shall be measured in the
factory and also after assembly at site.
Resistance elements for temperature recorder shall be mounted at 6
positions in the portions where the stator coils of each phase are
presumed to show the highest temperature.
3) ROTOR GENERAL
The rotor shall consist of a spider, laminated rims with brake ring at
the bottom, salient poles with field coils and damper winding cage as
well as upper and lower shafts to be bolted to the upper and lowerflanges of the hub.
ROTOR SPIDER
The rotor spider shall be of fabricated structure. High strength high
yield steel shall be used in the construction of the central hub and the
radial arms.
The attachment of laminated rotor rim with the spider arms shall be
designed to withstand the maximum forces induced in the runaway
condition of the unit.
The arrangement of arms shall not only compensate the expansion and
contractions during operation of generator but also those due to
welding.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 224/331
Signature of Bidder Signature of Purchaser 224
Approved tests for material and welds such as X-ray and ultrasonic
tests and/or liquid penetration tests to ensure the reliability of the
whole spider shall be conducted.
ROTOR RIM
The rotor rim shall be of laminated floating type i.e. it should be
attached to the spider by means of wedges driven in between the key
supports on spider arms and the slots on the inner periphery of the rim.
The rotor rim shall be made up of circular segmental punching from
sheet steel, stacked overlapped layer by layer around the outer
periphery of the spider. The laminated rims shall be clamped to a
compacted ring of solid segmented end plates by means of high tensile
axial bolts so as to ensure firm mechanical connection between the
adjacent segments of any two layers for transmission of tensile forces.
The shape and geometry of laminations and the pattern of stacking
shall be such that the completed rim corresponds to an ideal
homogenous cylinder as the uniform distribution of mass. The brake
ring shall be provided at the bottom of rim. The brake ring may be
constructed in segments so as to allow any replacement.
ROTOR POLES
The pole body shall be made up of steel laminations made of same
material as is used in construction of rim laminations. The pole
laminations shall be held tight between end plates by means of suitable
number of bolts.
The poles shall be secured to the rim by means of wedges in such a
way as to allow the removal of poles in the vertical direction without
requiring removal of the rotor out of the stator bore.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 225/331
Signature of Bidder Signature of Purchaser 225
FIELD COILS AND DAMPER WINDING
The field coil shall be made up of turns of flat rectangular copper cut
to appropriate length and width. To increase the cooling surface area,
alternate turns shall be provided with conductor of greater width so as
to form on the outer side, a finned surface.
The insulation system of class ‘F’ shall be used to ensure compact
assembly with excellent electrical and mechanical properties. The turn
insulation should be thoroughly cemented to adjacent turns to permit
removal of field pole coil as a unit. The pole core insulation must be
separate from the coil. Special attention shall be paid to ensure
prevention of end turns of a coil from deforming or slipping due to
centrifugal forces on the inter-connections. End turn insulations must
be reinforced if necessary.
The field coils of poles shall be connected by means of flexible copper
plates to form as field winding whose ends are brought out for
connection with slip rings.
The coils shall be tested at medium frequency test voltage or impulse
voltage test on the terminals. During this test, the magnetising current
must be measured and this current shall not differ by more than 10%between various coils. Low resistance damper winding of fully caged
construction shall be provided to improve stability under fault
conditions and specially to reduce voltage disruption under conditions
of single-phase fault.
SLIP RINGS
The slip rings shall be in an accessible location above the rotor. The
slip rings shall be so arranged as to minimize the possibility of an
operator causing a short circuit between slip rings while changing or
adjusting the brushes. Provisions shall be made for reversing the
polarity of the slip rings to obtain uniform wear on both slip rings.
The maximum run out of the slip rings shall not exceed 0.25 mm. The
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 226/331
Signature of Bidder Signature of Purchaser 226
brushes shall be staggered, and the slip rings shall be so located that
they will not interfere with the removal of the upper guide bearing.
The brushes and slip rings shall also be so positioned as to avoid
contamination by oil vapour or oil leakage from this bearing. The lead
from the slip rings shall run directly to the field breaker and discharge
resistor. An extra set of slip ring brushes, insulated brush holders, and
terminals shall be provided. One 45 mV drop shunt to be mounted in
the generator field leads shall be furnished complete with calibrated
shunt leads for connection to a field current ampere meter.
A separate slip ring and brush assembly shall be mounted on generator
shaft for the field winding earth fault relay and the leads shall be
terminated in the generator terminal box.
The slip ring and brush gear shall be separately enclosed from the
generator housing. It shall be so arranged that ventilating air from the
ring and brush gear housing cannot enter the generator housing. This
will prevent suspended carbon dust from the brushes entering the
generator housing.
A self-fan or motor fan shall be provided for cooling and exhausting
the carbon dust. Isolating switch for the fan motor shall be locatedwithin the brush gear housing.
4) BRACKETS
UPPER BRACKET
Upper bracket shall be designed to accommodate combined thrust and
Generator upper guide bearing and also to lift the complete stator from
erection bay to the generator pit. It shall also support top flooring.
The flooring shall be divided into a number of sections so as to allow
withdrawal of air/water heat exchangers and or rotor poles.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 227/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 228/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 229/331
Signature of Bidder Signature of Purchaser 229
all high pressure piping, flexible hose, strainers, regulators and check
valves.
The control equipment shall be of the heavy duty type. One pressure
gauge to indicate establishment of oil film shall be provided having
two sets of adjustable, electrically independent contact (both set closed
at normal operating pressure and open at low pressure), one set to be
used as an interlock to prevent starting the generator unit, if pressure to
establish an oil film is not available and the other set to be used for
operation of indicating lights. The contacts shall be suitable for use in
220V D.C. circuits. Suitable damping devices shall be provided in the
high pressure piping system, if necessary to prevent undue pulsations
of the pressure gauge. The pumping unit shall be of sufficient capacity
to force the oil completely between the thrust bearing surfaces when
the unit is at standstill. The high pressure oil grooves on the bearing
pads shall be so designed that they will not interfere with normal
lubrication of the bearing while the high pressure system is shut down.
The control arrangement for the pumps shall be subject to purchaser’s
approval and shall include provisions for remote control of the system,
annunciation or failure of the A.C. motor driven pump, and automaticstart of the stand-by D.C. motor on failure of the A.C. motor - driven
pump.
The bearing oil shall be cooled by means of externally placed oil /
water heat exchangers. The cooling capacity shall be 150%. The
cooling tubes shall be of non-corrosive metal e.g. stainless steel and
shall be tested to a hydrostatic pressure of 1.5 times of maximum
pressure for a period of 10 minutes. The cooling water supply system
shall be designed jointly by turbine and generator suppliers.
Manufacturer shall supply all necessary valves and controls. The main
shut off valve for the bearing water supply shall be A.C. motor
operated with manual override.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 230/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 231/331
Signature of Bidder Signature of Purchaser 231
journal surface of the upper guide bearings. Effective means shall be
provided for cooling the bearings. Water cooling for the separate
guide bearing design shall be similar to that of the combined guide and
thrust bearing.
Each guide bearing shall be equipped with the following : -
- 1 No. Oil-level relay in the bearing reservoir with high and low
level alarm contacts.
- 3 Nos. Dial type temperature controllers two nos. embedded in
the bearing metal to indicate the temperature of the bearing and
one no. thermometer in the oil. The controllers shall have two
sets of electrical contacts. The controllers shall also have a
contact to indicate loss of bulb pressure or loss of power to the
instrument. The indicator shall be mounted on the gauge
panel.
- 3 Nos. Resistance temperature detectors. Two Nos. shall be
located in recesses in the bearing metal on diametrically
opposite sides of the bearing and one in the oil, with leads
brought out to the terminal box.
- 1 No.Direct-reading water flow gauge with two low-flow alarmcontacts.
- One Oil-water contamination detector.
Adequate baffles shall be provided, if necessary to prevent excessive
churning or aeration of the oil.
Each lubrication system shall include suitable oil reservoirs, supply
and drain oil piping, valves, including valve bypass piping for flushing
the lines and necessary appurtenances. Oil filters of the low pressure
drop type shall be provided in the oil supply line to the thrust bearing
oil circulating system.
Supplier shall provide the initial supply of lubricating oil required to
fill the entire lubricating system. The quality and the specification of
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 232/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 233/331
Signature of Bidder Signature of Purchaser 233
permitted. Provisions shall be made for mechanical blocking the rotor
in the fully raised position. The blocking device shall be such that it
will be unnecessary to maintain hydraulic pressure on the jacks while
the rotor is in the raised position.
A brake dust extraction system shall be provided by the supplier. A
position switch having two sets of contacts shall be provided for each
brake shoe. One set of open contacts (when brakes ‘OFF’) shall be
wired in parallel and will be used for brakes ‘ON’ indication. The set
of closed contacts (when brakes ‘OFF’) shall be wired in series and
will be used in the unit start interlock circuit. Wires from both sets of
contacts shall be brought out and terminated in the generator terminal
box. The equipment shall be complete with necessary control cabinet,
piping, valves, fixtures etc.
7) SOLE PLATES AND FOUNDATION BOLTS
The supplier shall provide adequate number of soleplates, anchor bolts
etc., for fixing lower bracket and stator frame to foundation. The
whole anchorage shall be designed and constructed to resist the forces
under most abnormal condition, resulting from sudden short circuit orfaulty synchronising. The supplier shall furnish the detailed drawings
& calculations to the Purchaser for his consent and approval.
8) AIR COOLING SYSTEM
The generator shall be cooled by means of closed circuit ventilating
system. The cooling air shall be circulated to effectively and
uniformly cool the rotor poles, the stator winding, the stator core along
the coil and peripheral areas. The complete details of the system shall
be furnished in the bid. To facilitate inspection and cleaning of the
windings and to permit removal and replacement of field poles and
stator winding coils, the air baffles provided to control the direction of
air flow shall be so designed that they may be removed in segments,
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 234/331
Signature of Bidder Signature of Purchaser 234
with relative ease. Hinged panels in the baffles may be supplied to
permit convenient access to parts of the unit. The circulating air shall
be of cooled by air / water heat exchangers evenly spaced around the
stator frame. The air shall be cooled to a temperature not exceeding
450C. Baffles shall be provided for separation of the generator air
cooling system from the Turbine pit. The air/water heat exchangers
shall have sufficient capacity to maintain the cooled air temperature
not exceeding 450
C. on the housing unit, with cooling water inlet
temperature of 350
C, when one exchanger is out of service and the
unit is in operation at full power. The discharge pressure at the exit of
the heat exchanger shall be sufficient to discharge the water to draft
tube.
The air cooling coils shall be stainless steel or copper nickel material
and able to withstand a test pressure equal to double maximum
working pressure for a sufficient length of time to permit adequate
inspection of leaks. The heat exchangers shall be equipped with
suitable automatic air vent valves and the entire system shall be
provided with suitable drain outlets. The pressure drop through the
cooling heat exchangers shall be stated by supplier. The heatexchangers shall be provided with connections having brass plugs in
an accessible position, one on the supply and one on the discharge
pipe, to permit the attachment of a manometer. The heat exchangers
shall be conveniently located to facilitate cleaning without removing
them from the generator. To minimize the frequency of maintenance
each heat exchangers shall be provided with 20% additional cooling
coils to maintain adequate cooling during service even if some of the
tubes are clogged.
The supplier shall supply all piping, including terminations to the
outside of the unit housing. The discharge water piping will be
terminated similarly and supplied by supplier. All cooling water
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 235/331
Signature of Bidder Signature of Purchaser 235
piping shall be lagged with approved insulation to prevent
condensation.
Main water piping for the cooling water shall be of mild steel of
appropriate strength with valves for open / close operation at the water
entry and exit of each cooler element. Cooling water piping inside the
barrel shall be provided with anti-condensation paint. The manifolds
of cooling water supply and exhaust pipe inside the generator housing
shall be placed in a trench below the walkway in the housing. Cooling
elements shall be arranged in such a way that the cooling water always
remain in the heat exchangers.
Access to all tubes for inspection and cleaning shall be possible
without disturbing the header piping.
The heat exchangers shall be mounted in such way as to facilitate
assembly, dismantling, maintenance and repairs. They must be
interchangeable between each other. The necessary water headers
shall be furnished with the heat exchangers. All connections between
coolers and headers shall be of flange type. Isolating valve shall be
provided in each connection between each coolers and headers so that
any heat exchangers can be removed without interfering with theoperation of remaining coolers. Approved means for draining and
releasing entrapped air of all coolers and pipe work shall be provided.
Condensed water on cooler surfaces shall be collected in receiving
dishes installed below the coolers and drained to the station drainage
pit. All piping shall be of flanged construction, using standard piping
sizes suitable for its function. The system shall be provided with the
following :
2 Nos. resistance temperature detectors (pt. 100 ohm), one mounted
suitably for measuring the cooling water inlet temperature and other
mounted for measuring the cooling water exhaust temperature.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 236/331
Signature of Bidder Signature of Purchaser 236
One or more resistance temperature detectors for each exchanger
mounted with suitable mechanical shields to measure the
temperature of the cooled air entering the generator rotor.
Resistance temperature detectors shall be supplied in accordance with
the relevant IEC- standards. The location and method of mounting of
these resistance temperature detectors shall be such as to avoid the
necessity for removing the resistance temperature detectors when the
exchangers are removed from the machine for servicing.
One approved direct-reading type water flow gauge with low-flow
alarm contacts shall be fitted on the exchangers. The indicating dials
shall be mounted on the gauge panel.
Dial-type indicating thermostats with adjustable alarm contacts shall
be supplied and installed in the inlet air path entering each exchanger
and for the discharge air from each exchanger. The indicating dials
shall be mounted on the gauge panel. All gauges required to ensure
proper functioning of the cooling system shall be provided by supplier
and all alarm contacts and solenoids shall be suitable for 220V D.C.
9) HEATERSAdequate no. of electric heaters, designed and located conveniently
within generator housing to prevent condensation of moisture or
sweating during idle periods shall be provided. Heaters shall be
designed and wired for operation of a 400-V, 3-phase, 4 wire circuit.
The supplier shall furnish all wiring within rigid conduit between the
individual heaters and heater circuits terminal box which shall be
furnished for installation, within the generator housing or at other
approved locations, except that flexible conduit may be used for
connections to the individual heaters when required. Provision shall be
made to switch on the heater automatically by thermostatic control
whenever the generator is shut down. The thermostatic control device
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 237/331
Signature of Bidder Signature of Purchaser 237
for switching on the heater shall be of the differential type with
adjustable differential range of 0-100C approximately.
10) SHAFT AND COUPLINGS
The generator shaft shall be of one single piece and shall be coupled
with the turbine coupling and thrust collar. The upper guide bearing
collar shall be forged integral with the shaft. Shaft shall be of forged,
open hearth or electric furnace, carbon or alloy steel and properly heat
treated in one piece and coupling with thrust collar is also acceptable
but detailed description of design, fixation of shaft and thrust block
and generator for trouble free operation shall be proven.
The shaft shall be machined accurately all over and polished at the
guide bearing region. At least two concentrically true polished surface
bands at approved location for dial type eccentricity indication shall be
available.
All half coupling of the shaft shall be of the integrally forged pattern.
Coupling dimensions for connections of turbine to generator shall be
agreed upon by the generator and the turbine suppliers and shall be in
accordance with relevant IEC standards.The generator supplier shall provide the generator and turbine shaft
coupling and the coupling bolts and nuts as well as the nut guard on
the turbine side of coupling. The coupling bolts shall be provided with
locking devices and shall have dimensions and tolerances in
accordance with reverent IEC standards.
Design of shaft assembly for the complete set (turbine and generator)
shall be done jointly by the turbine and generator suppliers, who will
solely be responsible for calculations of the first critical speed.
Ensuring the correctness of the shaft length and coupling flange
machining shall be the combined responsibility of both suppliers.
Generator supplier shall be responsible to shift the turbine shaft to his
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 238/331
Signature of Bidder Signature of Purchaser 238
work and return the same when done with. Cost therefore is deemed to
have been included in the bid price.
Drilling of coupling boxes in the upper flange of turbine shaft and that
on lower generator coupling flange shall be performed in generator
supplier’s works.
11) RUNNER AND MAIN SHAFT
The turbine shaft shall be before hand completely machined with
coupling bolt holes drilled 3 mm. under size. Generator supplier shall
be responsible and shall take extra care in the final reaming of the
coupling bolt holes and the coupling and aligning of the turbine shaft
and generator spider before shipping to site. The supplier will also
supply the steel drilling template and pin gauge for the coupling. The
main shaft shall be material inspected by radiographic inspection or
ultrasonic inspection and after confirming no defect existing inside, the
final machining shall be proceeded.
The coupling between the turbine shaft and generator spider shall be
sized to suit relevant standards. The coupling shall be amply strong to
transmit the power involved and in addition, carry the downward thrustof the turbine. For the protection of the bearings from damages due to
shaft current, a perfect insulation shall be done in the supporting part
of the thrust collar.
The critical speed of the main shaft due to unbalance of the rotating
parts shall be higher than 120% of the maximum momentary speed
which may happen at the transient time such as load rejection of
runaway condition of the turbine. The supplier shall prepare shaft
critical speed computer analysis which shall be approved by Purchaser.
The following design and machining tolerances shall apply to the
driving disc, runner plate and coupling flange where applicable.
- Where the thrust load is supported by the bottom surface of a driving
disc or shaft flange, the following tolerances shall apply. The surface
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 239/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 240/331
Signature of Bidder Signature of Purchaser 240
generator housing shall also form part of supply. Doors shall be
airtight, lockable and interlocked.
13) GENERATOR TERMINAL BOX, ELECTRICAL ITEMS AND
WIRING & PIPINGS.
All electrical items supplied by supplier shall comply with the
appropriate sections of the relevant IEC standards. They shall be
arranged in a manner approved by the Purchaser. The supplier shall
provide and install terminal boxes in locations approved by Purchaser,
and shall provide and install all wiring and conduit from its electrical
components to these terminal boxes. All wiring shall be standard wire,
with oil proof insulation. Further a common marshalling box shall be
provided. Wiring from all individual terminal boxes shall be brought
by the supplier up to this marshalling box. Leads for all auxiliary
electrical circuits such as current transformers, resistance elements,
limit switches; various kinds of relays shall be supplied up to the
terminal blocks installed in the air housing.
All wiring within the generator housing, including main field leads,
lighting, resistance temperature detectors leads and control andindicating leads shall be adequately clipped or otherwise supported and
protected. The wiring shall be bundled and tied together, where
possible, to provide a neat arrangement. The wiring passing through
openings in metal members of the generator, or otherwise passing over
or near metal edges, shall be carefully protected against abrasion.
A cable trough shall be provided by supplier, mounted to the inside
surface of concrete air housing and extending around the complete unit
for carrying the wiring. To facilitate disconnecting the generator field
leads when removing the top bracket, supplier shall supply and install
a junction box just inside the stator casing at a suitable location and he
shall supply and install the field leads from the slip rings to this box,
with cable terminals at both ends. These leads will be extended by
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 241/331
Signature of Bidder Signature of Purchaser 241
cables or insulated bars, supplied and installed by the Supplier from
the junction box to the field circuit breaker. Supplier shall supply and
install a cable through inside the casing to carry the cables of bars from
the slip rings to the junction box and to the point of exit through the
casing.
In general, close attention shall be given in order to prevent failures or
shutdowns occurring as a result of generator vibration. The wire
insulation shall be resistant to flow and abrasion under the conditions
to which it may be exposed. Liquid type flexible conduit shall be used
where wiring may be exposed to oil or water leakage.
All piping shall be supplied such as feed / drain oil pipes of the
generator bearing oil tank, oil jacks, piping of oil level relays and oil
level gauges, feed / drain water pipes for bearing coolers and air
coolers, connecting pipes between respective coolers, drain pipes of
leakage oil and leakage water at respective positions and other piping
installed in the generator air housing and barrel including valves and
flanges.
14) GENERATOR HOUSING LIGHTINGSuitable lighting, which shall also include the area under the generator
rotor, and a minimum of four convenient outlets, shall be provided in
the generator housing. A terminal box shall be supplied to terminate
the supply leads, lighting, wiring etc. Supplier shall supply and install
lighting control switches at service door.
15) GENERATOR FLOORING, PLATFORMS ETC.
All necessary floor plates and curbing including floor covers for all
pipe and cable trenches as required for completing the floors on and
around the generator and their related installation shall also be
supplied. Floor plates shall be of anti-skid type or similar safety
pattern. The generator shall be provided with suitable platforms,
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 242/331
Signature of Bidder Signature of Purchaser 242
stairways, handrails etc. for access to various generator parts.
Necessary hooks, pulleys etc., for handling shall be provided. Suitable
guards, over and around all energised or moving parts shall be
provided for the generator and their accessories. Wherever required,
suitable mesh wire barriers shall be provided within the generator
housing / pit for protection of workmen while generator is in operation.
16) CREEP DETECTORS
- A creep detector shall be provided complete with all necessary
wiring and controls to perform the following functions.
- When the unit has been brought to rest by closing of the guide
vanes and application of brakes, the detector shall operate if
shaft rotation occurs after expiration of the normal stopping
period. The total rotation required to operate the detectors shall
not exceed 10 degrees of shaft movement. On operation the
detector shall perform the following functions.
- Close an annunciation contact which shall be wired to the
generator terminal cabinet.
- When the high pressure oil pump provided for unit starting andstopping is on “automatic” control, start the high pressure oil
pump.
- De-energize the brakes if the brakes are on “automatic” control.
- When the unit is started under normal control, detector shall be
disconnected to prevent spurious control and annunciation
signals.
17) TEMPERATURE DETECTORS
The Supplier shall provide six resistance temperature detectors (pt. 100
ohm at 0 degrees C) per parallel circuit per phase, embedded in the
various parts of the stator winding in accordance with relevant IEC
standards.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 243/331
Signature of Bidder Signature of Purchaser 243
Twelve resistance temperature detectors (pt. 100 ohm at 0 degrees C)
shall be embedded in a suitable location, six at each end of the stator
core for temperature measurement for the detection of end iron
heating.
Twelve resistance temperature detectors shall be equally spaced in the
stator core for temperature measurement at 12 teeth locations.
RTD’s and hotspot temperature indicator shall be furnished.
Requirements of temperatures to be measured have been described;
however supplier shall decide number of scanners required. The exact
location of the temperature detectors in the stator winding and core
shall be subject to the approval of purchaser. All temperature detectors
in and around the generator shall be wired to the terminal box mounted
on the outside of the generator air housing. This terminal box shall be
separated from other terminal boxes.
All connections from the temperature detectors to the terminal boards
shall consist of twisted leads in shielded cables. The leads from each
stator bearings, water and air temperature detectors shall be brought in
a neat and substantial manner to suitable terminal blocks located in a
terminal box on the generator barrel. This box shall be usedexclusively for resistance temperature detectors. The terminal box, to
be provided by supplier shall have provision for connection to external
conduit and wiring. The leads shall be supplied as twisted three wire
leads suitably shielded and otherwise protected to minimize stray
“pick-up”. The insulated leads shall be capable of with-standing an
applied potential test of 2000V to ground for 1 min. Separate
terminals shall be provided for terminating the shields of individual
Resistance Temperature Detector (RTD) leads. The resistance
temperature detectors shall be platinum type and have a resistance of
100 ohms at 00C. Resistance ratio between 0
0C and 100
0C shall be
1.3926.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 244/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 245/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 246/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 247/331
Signature of Bidder Signature of Purchaser 247
updraft etc. The system shall also be designed in such a way that
steam is generated in sufficient amount so that air is displaced and
extinguishing of fire is quicker.
Following points shall be considered in the design of components: -
i) ATOMIZED WATER SPRAY NOZZLES
Nozzles shall be specially designed having three parts of holes
arranged, in such a manner that jet of water flowing out of one
hole strikes against the jet of water emerging out of another hole
at right angle such that the collision of two high velocity jets
results in very fine fog formation required for extinguishing the
fire.
ii) PIPES & FITTINGS
Steel tubes with thread flange joints shall be used. The tubes
shall be suitably bent to size at factory for ready installation.
iii) WATER MOTOR GONG
The jet of water itself shall operate a gong to give an alarm.
iv) INLINE STRAINER
For cleaning the water of impurities, foreign particles etc.suitable strainer is required. This shall be made of stainless steel
and shall be installed in the pipeline itself. Arrangements for
cleaning the strainer shall also be provided.
v) VALVE
A suitable valve shall be provided in the pipeline, which should
open automatically in case of fire and allow water to the ring
headers. Details thereon shall be described.
vi) DRAIN VALVE
A drain valve should be provided in the pipeline to drain the
water.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 248/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 249/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 250/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 251/331
Signature of Bidder Signature of Purchaser 251
output of main channels. If this channel fails then the controls shall be
automatically switched to standby channel.
The normal mode of operation shall be auto-control. Additionally,
manual control of the excitation shall be available for testing and
setting up purposes or in unlikely event of failure of the auto control of
both channels.
The auto-control circuits shall consists of two interdependent feed back
control loops (Voltage and Current) with limiting circuits for under-
excited MVAr, rotor heating, current and power system stabilisers.
The excitation system shall be capable of switching from 25% of rated
generator voltage and at 60% of voltage it shall be capable of
supplying rated excitation current. The time constant of excitation
system shall be less than 0.10 sec.
2) CAPABILITY
With rated generator voltage, the excitation system shall be capable of
delivering continuously, within rated temperature rise, any value from
0 to 120% of the field current required when the generator is operating
at 110% of rated voltage, and rated power factors at 0.90 (over-
excited). With rated generator voltage, the excitation system shall becapable of providing a ceiling current to the field of not less than 1.5
times rated field current for at least 30 seconds. De- excitation time
between rated voltage and 10% of voltage shall not be more than 10
sec.
3) SYSTEM RESPONSE
With the generator initially at rated apparent output power, rated
voltage, power factor and speed, the excitation system shall be capable
of changing from rated field voltage to 100% of ceiling voltage within
25 to 30 ms. for a sustained drop in generator terminal voltage of 10
%. The rated voltage shall be calculated assuming that at rated
apparent power, field winding is operating at rated field current.
Response in the negative (reverse) direction to suppress terminal
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 252/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 253/331
Signature of Bidder Signature of Purchaser 253
8.8.2 DIGITAL VOLTAGE REGULATOR
1) Micro-processor based voltage regulator shall be digital type. It shall
be liberally designed so as to be as reliable as possible and shall
incorporate sufficient redundancy so that failure of any control
equipment will not cause mal-operation of the system.
2) The digital voltage regulator should periodically calculate the control
signal from measured and reference values. Calculation should be
repeated at every short time intervals where by an apparently
continuous regulator output characteristic is produced.
3) Calculation is to be carried out in binary system. The analog measured
values of generator voltage and current as well as field current must be
transformed in an Analog / Digital converter into binary signals. From
the calculated control signals, pulses should be generated for firing the
thyristor.
4) Various control functions like voltage regulation, limitations of field
current, rotor angle, stator current, slip stabilising etc. shall be stored as
programs to be executed in a cyclic pre-programmed manner.
5) Control to maximum converter voltage shall be achieved in less than
10 milliseconds thus ensuring fast reaction to network disturbances.6) Internal conditions monitoring of devices with light emitting diode
(LED) indication be provided which means short failure detection
times.
7) Set values shall be digital, absolutely reproducible and not vulnerable
to changes ensuring long term stability
8) Number of different units shall be small so that spare parts stock could
be kept to a minimum.
9) Low sensitivity to external electro-magnetic influences shall be
ensured which means high noise immunity.
10) Electrical control points shall be bare minimum to reduce potential
trouble sources.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 254/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 255/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 256/331
Signature of Bidder Signature of Purchaser 256
8.8.3 THYRISTOR CUBICLE
1) This cubicle contains full three phase thyristor bridges with its
associated equipment. The design should be modular in such a way
that changing of a thyristor or part of a bridge shall be easily possible.
In case forced ventilation system is adopted, noise level outside the
panel shall be negligible.
2) Number of thyristor cubicles provided shall be such that, even with
failure of one thyristor bridge, the generator should be able to supply
rated output and with failure of two bridges, the generator should trip.
3) All thyristors shall be fuse protected. Voltage safety factor for
thyristor, defined as the ratio between the maximum operating voltage
and the rated peak cut-off voltage shall be more than 2.5. Excitation
response shall not be less than 4.0 s.
4) Suitable protection shall be provided for thyristor to prevent voltage
spikes from reaching them and damaging them.
5) Over voltage protection to protect the thyristor bridges and the field
circuit shall be provided.
8.8.4 SWITCHGEAR EXCITATION CUBICLE
This cubicle shall contain all switchgear equipment necessary for the
operation of excitation.
Field breaker and all equipment necessary for rapid suppression of
generator-motor field circuit shall be provided. The principle of
suppression of field shall be the reversing of rectifier operation into an
AC converter operation and shunting the generator field terminals by a
discharge resistor. Over-voltage protection devices, start-up excitation
devices, auxiliary relays and contactors shall be provided.
All in feeds from station battery shall be taken through D.C./D.C.
converters. Redundancy shall be built in, in modules.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 257/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 258/331
Signature of Bidder Signature of Purchaser 258
16) Total losses at rated load should be at minimum.
8.8.6 Lightning Arrestors, Voltage Transformers, Surge protection capacitors and
Neutral grounding equipment are included under Section X Generator
supplier shall coordinate with the supplier of these equipments in respect of
characteristics and performance requirements of these items.
8.9 FACTORY TESTS FOR GENERATOR AND RELATED EQUIPMENT
Tests to be conducted in factory on various material, assemblies etc. on
generator at different stages of manufacture are indicated in the enclosed
statements. legends of the nomenclature of tests is as below ;
LEGEND FOR FACTORY TESTS OF ELECTRICAL LOT
1) Test at shop on random sample of raw material.
2) Test at shop on random sample of raw material and on semi or fully
finished part.
3) Test at shop on 5% of consignment .4) Check straightness of bolts taking random sample of 10 bolts per
machine.
5) Test at shop in the presence of Purchaser’s representative.
6) Test at shop on each piece.
7) Spot check at shop of brazed parts of semi or fully finished parts.
8) Test at shop on random sample of one per sheet.
9) Test at shop on complete sheet.
10) Test at shop - once per item.
11) Test to be conducted by manufacturer and Test Certificates given to
Purchaser.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 259/331
Signature of Bidder Signature of Purchaser 259
SUBMISSION OF TEST CERTIFICATES
The Supplier shall submit 6 copies of test certificates to the Purchaser as per
the procedure given below :
i) FOR INSPECTION AND TESTING TO BE DONE IN PRESENCE
OF PURCHASER’S REPRESENTATIVE.
Test certificates shall be submitted for approval.
ii) FOR ALL OTHER INSPECTION AND TESTS
Test certificates showing that the specified tests / inspection has been
carried out successfully by the Supplier shall be submitted for
reference.
8.10 MATERIAL TEST
Sr.N
o.
Particular of Test 1 2 3 4 5 6 7 8 9 1
0
1
1
1) ROTOR RIM SHEETS:
Tensile Test √ √
Chemical analysis √ √
Visual check √ √ √
Dimensional check √ √ √
2) ROTOR RIM BOLTS
Tensile Test √
Chemical analysis √
Visual check √
Dimensional check √ √
3) FIELD WINDING (POLE COIL)
FINISHED
Tensile Test √
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 260/331
Signature of Bidder Signature of Purchaser 260
Sr.N
o.
Particular of Test 1 2 3 4 5 6 7 8 9 1
0
1
1
Visual check √
Dimensional check √
Test for short circuited turns √
Acceptance test of each piece √
Insulation Simulation Test √
4) POLE FINISHED
Visual check √
Dimensional check √
High voltage test √
Test for short circuited turns √
Weight check √
Acceptance Test of each piece
(H.V.Test)
√
5) DAMPER BAR
Hardness Test √
Visual check √
Dimensional check √
Electric conductivity Test √
Acceptance Test on 5% of
consignment
√
6) DAMPER SEGMENT RAW
Hardness Test √
Visual check √
Dimensional check √
Acceptance Test on 5% of
consignment
√
7) POLE LAMINATION SHEETS
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 261/331
Signature of Bidder Signature of Purchaser 261
Sr.N
o.
Particular of Test 1 2 3 4 5 6 7 8 9 1
0
1
1
Tensile Test √
Chemical Analysis √
Visual check √ √
Dimensional check √ √ √
Induction Test √
8) POLE AND PLATE RAW
Tensile Test √
Notched Bar Impact Test √
Chemical Analysis √
Ultrasonic Test √
Visual Test √
Dimensional Test √
Acceptance Test of each piece √
9) POLE END PLATE MACHINING
Visual check √
Dimensional check √
Acceptance Test of each piece √
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 262/331
Signature of Bidder Signature of Purchaser 262
Sr.No Particular of Test 1 2 3 4 5 6 7 8 9 1
0
1
1
10) POLE BOLTS
Tensile Test √
Chemical analysis √
Visual check √ √
Dimensional check √
11) ROTOR LAMINATION
Tensile Test √
Notched Bar Impact Test √ Chemical Analysis √
Ultrasonic Test √ √
Aging characteristic √
Acceptance Test of each piece √
12) STATOR LAMINATION
SHEETS
Tensile Test √
Chemical analysis √
Visual check √ √
Dimensional check √ √
Induction Test with determination
of specific losses at 1.0 and 1.5 t
√
13) STATOR PUNCHING
Tensile Test √
Chemical analysis √
Visual check √ √
Dimensional check √ √
14) STATOR RIM BOLTS
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 263/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 264/331
Signature of Bidder Signature of Purchaser 264
18) OIL COOLERS (EACH)
Tensile Test √
Visual Test √
Dimensional check √
Hydrostatic Test √
19) GENERATOR SHAFT
Material Analysis √
Tensile Test √
Notch Impact Test √
Visual Inspection √
Magnetic particles Examination √
Ultrasonic Test √
Dimensional check √
Roughness Test √
Baroscopic Inspection √
Matching with Pump-Turbine shaft √
20) BRAKE AND JACK
Visual Test √ √ √ √
Dimensional check √ √ √ √
Measurement of Stroke
Hydrostatic Test √ √ √ √
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 265/331
Signature of Bidder Signature of Purchaser 265
Sr.
No.
Particular of Test 1 2 3 4 5 6 7 8 9 1
0
1
1
21) E.T.D. THERMOMETER
THERMAL SWITCH
Calibration Test √
Check and setting of switches and
relays
√
22) VARIOUS SWITCHES AND
RELAYS
Check and setting of pressure,
Level, Flow
√
Temperature switches and Relays √
23) STATIC EXCITATION
EQUIPMENT
A) FOR EACH SET
H.V. Test √
Functional Check of modules by
simulation
√
Control sequence interlock Test √
B) FOR ONE SET
Load Test and current sharing Test
on thyristor bridge
√
Heat run test on thyristor bridges √
Heat run and Impulse test on
excitation transformer
√
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 266/331
Signature of Bidder Signature of Purchaser 266
8.11 SITE TESTS FOR GENERATOR AND RELATED EQUIPMENT
Site tests to be conducted on various assemblies in presence of
Purchaser are as below but shall not be limited to.
DURING ERECTION
STATOR WINDING :
- D.C. Resistance.
- Insulation Resistance.
- H.V. Test
- Dielectric Test.
ROTOR WINDING :
- D.C. Resistance
- Insulation Resistance.
- H.V. Test
- Rotor Impedance.
- Dielectric Test
- High frequency induced voltage test on poles.
MEASUREMENT OF CENTERING AND LEVELLING- Together through upper bracket, Stator Core, Lower Bracket and
Turbine Upper Cover and Casing.
UPPER AND LOWER GUIDE BEARING
- Insulation Resistance
- Check of vibration response
- Check of setting of oil level switches.
SHAFT :
- Check of shaft alignment together with Turbine Shaft.
- Check of vibration response.
- Check of slip ring deflection.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 267/331
Signature of Bidder Signature of Purchaser 267
HIGH PRESSURE INJECTION OIL SYSTEM FOR THRUST BEARING:
- Check of settings of pressure switches, relays etc.
- Check of pumps
- Operational check in all modes.
BRAKE AND JACK SYSTEM
- Check of setting of pressure switch, limit switches,
relays etc.
- check of pumps.
- Operation pump check in all mode.
STATOR FINISHED
- Magnetic flux test
- Di-electric Test.
- Measurement of stator winding resistance D.C. resistance.
- Measurement of stator winding insulation resistance.
- Measurement of stator winding impedance.
- H.V. Test
- Check of concentricity of core.
- Check of core height.
ROTOR FINISHED- Measurement of Rotor winding D.C. resistance.
- Measurement of rotor winding impedance.
- Measurement of rotor winding insulation resistance.
- H.V. Test
- Check of concentricity.
DURING PRECOMMISSIONING AND POST COMMISSIONING
1) AUXILIARIES
Auto/Manual operation of all auxiliary system connected with
Generator .
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 268/331
Signature of Bidder Signature of Purchaser 268
2) OTHER GENERATOR TESTS
NO LOAD TESTS :
- Initial run
- Check of smooth run at gradually increased speed from zero to
rated speed
- Vibration and noise level measurement
BEARING HEAT RUN
- Running test of bearings
- Recording of bearing metal and oil temperature at rated speed
no load until all bearings reach stable temperature.
OVER SPEED TESTS
- Functional check of vibration & seismic monitor
- Run for 2 minutes at 150% over speed.
EXCITATION SYSTEM
- Commissioning test .
SYNCHRONISING TEST
- Auto / Manual synchronising.
LOAD REJECTION TESTS
- Load rejection at 1/4, 1/2, 3/4 ,1.1& 1.0 of rated output at ratedpower factor.
- Oscillograph measuring of voltage rise at each rejection.
SHUT DOWN TESTS
- Normal stopping operation of generator
- Quick shut down tests.
- Emergency shut down test.
- Vibration and noise level measurement.
LOAD TESTS
- Check of operation of various controlling and regulating.
- Temperature recording of windings and bearings.
- Vibration and noise level measurement.
- Measurement of thrust bearing bracket deflection.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 269/331
Signature of Bidder Signature of Purchaser 269
6) STATIC EXCITATION SYSTEM
- Measurement of insulation resistance.
- H.V. Test. .
- Functional test of system component.
- Loading characteristic test.
- Measurement of range of voltage regulation.
- Measurement of range of power factor regulation.
- Test of generator current limiter and exciting current limiter.
8) GENERATOR CHARACTERISTIC AND PERFORMANCE
TESTS :
- Open circuit characteristic (without step-up power transformer).
- Three phase sustained short circuit condition characteristic.
- Line to line sustained short circuit condition (without step-up power
transformer)
- Various Reactances
- Measurement of Air gap
- Measurement of Noise level.- Measurement of Moment of Inertia.
- Determination of balanced and residual component of telephone
harmonic factor (THF)
- Measurement of following losses (according to IEC 34-2A
Calorimetric method)
i) Losses in active iron and additional no load losses in metal
parts.
ii) Losses due to friction and windage
iii) Stator winding copper losses at 750
C
iv) Additional load losses
v) Field winding copper losses at 750
C
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 270/331
Signature of Bidder Signature of Purchaser 270
vi) Excitation system losses (Excitation transformer + thyristors
+ ac/dc link)
vii) Electrical losses in brushes.
- Measurement of vibration and noise level at rated output
- Measurement of all bearing temperatures at rated output.
- Measurement of reactive power
- Determination of generator guaranteed output with reference to
guaranteed temperature rise.
- Determination of generator guaranteed efficiency
8.12 DRAWINGS, DESIGNS, STUDIES AND MANUALS TO BE
SUBMITTED AFTER AWARD OF CONTRACT BY THE BIDDER.
The list of drawings, designs, studies, data needed and manuals etc. required
to be submitted by the supplier is enclosed with this section (Please refer
Annexure VIII-1 - I).Mode of submission of designs and drawings will be
intimated to the successful bidder in due course.
8.13 SPARES
Spares shall be supplied as per the list under Section - III of this volume.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 271/331
Signature of Bidder Signature of Purchaser 271
ANNEXURE VIII-1
DRAWINGS, DESIGNS AND MANUALS TO BE FURNISHED AFTER
AWARD OF CONTRACT.
Sr.
No.
Brief description within months
from the date
of award of
contract
Remarks
1 2 3 4
I GENERATOR
1. Arrangement drawings describing
and illustrating the information of:
3 For approval
* General layout drawing
*Combined turbine and Generator
cross section
* General arrangement and
overall dimensions of
generator showing
position and marking of main and
neutral leads, important elevations
etc
* Thrust and guide bearing Assembly
* Air circulation arrangement
* Excitation system
* Description of thrust bearings
and data regarding
construction, adjustment,
accessibility and method.
* Description and section of stator
and rotor insulation
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 272/331
Signature of Bidder Signature of Purchaser 272
2. Installation, assembly drawings of :
1 2 3 4
Generator and turbine shaft
coupling
8 For approval
Top and bottom brackets 8 For approval
Thrust and lower guide bearings 8 For approval
Upper Guide bearing 8 For approval
Rotor 8 For approval
Stator Foundation 6 For approval
Stator windings 10 For approval
Rotor arrangement including poles 10 For approval
Slip ring arrangement 10 For approval
Generator brakes 10 For approval
Assembly of stator and rotor with
lifting arrangement
10 For approval
Speed sensing element
arrangement
10 For approval
Vapour seal assembly 10 For approval
Lifting beam and attachment
drawing
6 For approval
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 273/331
Signature of Bidder Signature of Purchaser 273
3. Drawings illustrating dimensional details with schematics for :
1 2 3 4
Lubrication and cooling system
of thrust and guide bearings
10 For approval
Generator cooling with heat
exchangers, air guides etc
10 For approval
Turbine- Generator gauge panel 10 For approval
Schematic diagram of air, oil
and water piping
10 For reference
Schematic diagram of brake &
jack system
10 For reference
Thermometers, R.T.Ds etc 10 For reference
General scheme giving details of
excitation system, D.V.R.
Thyristors, field breaker, field
discharge resistance, etc.
10 For reference
Arrangement of generator heaters 10 For reference
Arrangement of rotor pit on
service bay, Rim building stools
and loading on service bay floor.
6 For approval
Arrangement of staircase, hand-
rails, doors, coverings etc.
10 For approval
Arrangement of oil cooler
withdrawal
10 For reference
Schematic diagram of thrust
bearing High Pressure injection
of lubrication system
10 For reference
4 Layout, plan and cross sections of
floor openings for piping, cables
6 For approval
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 274/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 275/331
Signature of Bidder Signature of Purchaser 275
MANUALS.
1 2 3 4
1 Manual for storage, preservation
and handling of the supplied
goods
18 For reference
2 Manual for erection /
dismantling, testing and
commissioning of the supplied
goods
18 For reference
3 Manual giving operating
instructions for all the ‘DO’s and
‘DONT’s’
20 For reference
4 Manual giving detailed
maintenance schedule
20 For reference
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 276/331
Signature of Bidder Signature of Purchaser 276
DATA SHEETS
1) Name of Manufacturer :- ………….-------------------
--
2) Manufacturers type
reference
:- -------------------------------
---
3) Type :- ----------------------------
4) Line voltage
Rated
Maximum
Minimum
:-
:-
:-
-----------------kV
-----------------kV
-----------------kV
5) Normal Synchronous
speed ( For a system
frequency of 50 Hz)
:- ----------------rpm
6)
A)
Guaranteed continuous
output under temp. rise
conditions specified in
item 6 (b) and under the
terminal conditions of
a) Rated output at 11 kV ,
0.9 power factor (lag)
b) ) Maximum continuous
output at 11 kV , 0.9
power factor (lag)
:-
:-
---------------------
---------------------
B) Maximum temperature
rise for the rated output
and continuous maximum
output over and above the
cooled air temp. of 450c
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 277/331
Signature of Bidder Signature of Purchaser 277
with temp. of cooling
water not exceeding 350c
a) stator winding by
RTD
b) stator winding by
resistance
c) other parts by
thermometer
Rated output
-------------------
-------------------
-------------------
Maximum continuous
.output
-------------------
-------------------
--------------------
7
A)
Guaranteed overall
efficiency of the
generator at 11 kV
terminal voltage 0.9.
power factor (lag) and
rated speed and 750c wdg
.temp by summation of
losses method as per IS
& subject to tolerance as
specified in IS
i) 110 % of rated
load
ii) Full load
iii) ¾ full load
iv) ½ full load
B) Guaranteed
arithmetical mean of
above efficiencies.
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
8 Inherent regulation i.e
Increase in voltage at
constant Speed and
excitation on taking off
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 278/331
Signature of Bidder Signature of Purchaser 278
9)
i) 110 % of rated
load
ii) Full load
iii) ¾ full load
iv) ½ full load
Generator Reactances
a) Synchronous reactance
( saturated )
i)Direct Axis –xd
ii)Quadrature axis-xq
b) Direct axis transient
resistance
i) saturated
ii) unsaturated
c) Sub transient reactance
i)Direct Axis –xd
ii) Quadrature axis-xq
d) Negative phasesequence reactance
e) Zero phase sequence
reactance
f) Resistance of armature
winding at phase at 75
0c
g) Resistance of field
winding at750c
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
---------------------%
-------------------ohm
-------------------ohm
10) Generator Time constants :-
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 279/331
Signature of Bidder Signature of Purchaser 279
a) Direct axis transient ,
open circuit
b) Direct axis transient
short circuit
-------------------Sec
-------------------Sec
11) Generator characteristics
curves :-
a) open circuit
characteristics curve
b) Full load saturation
curve
i) Zero power factor
ii) 0.9 power factor
c) Generator power
capability diagrams
:-
------------------------
-------------------------
-------------------------
------------------------
------------------------
12) Short circuit ratio -------------------------
13) Synchronizing power ( at
11 kV) Full load, 50 cycle
, 0.9 p.f.(lag)
-------- -- kW/Electrical
radiation
14) a) Fly wheel effect of the
rotating parts of the
Generator and exciters.b) Inertia constant
--------------Tm2
---------KW Sec/kVA
15) Stress levels.
a) Maximum speed ---------------------rpm
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 280/331
Signature of Bidder Signature of Purchaser 280
(Runaway speed)
which all parts are
guaranteed to
withstand safely for 5
minutes
b) Name and location of
parts having the least
factor of safety under
runaway or short
circuit condition
c) Guaranteed minimum
factor of safety based
on yield point of
material at runaway
speed
--------------------------
-------------------------
16 Embedded temperature
detectors in
a) stator winding
i) Number
ii) type
b) core
i) Number
ii) Type
c) teeth
i) Number
ii)Type
-------------------------
--------------------------
-------------------------------
---------------------
-------------------------------
--------------------
17 Static Excitation
equipment
a) Name of manufacturer
:-
-------------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 281/331
Signature of Bidder Signature of Purchaser 281
b) Type
c) Continuous rating of
excitation equipment
d) Ceiling Voltage and
duration
e) Primary Voltage rang
allowed for
continuous operation
f) Minimum primary
Voltage for ceiling
operation
g) AVR output range
h) Accuracy of AVR
control
i) D.C battery equipment
j) Looses at full load in
static Excitation
equipment
k) No. of Thyristorbridges
l) Excitation
Transformer
a) Rating
b) Type
c) Basic Impulse level
-------------------------------
----------------…………
-------------------------------
----------------------
---------------------------
-------------------------------
-------------------------------
-------------------------------
------------………………..
--------------------------
-------------------------------
-------------------------------
--------------------kV(peak)
18) Generator coolers
a) No of air coolers
b) Maximum safe water
----------------------
---------------kg/cm2
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 282/331
Signature of Bidder Signature of Purchaser 282
pressure
c) Cooling water
requirement at 350c
and for full load on
generator
i)Quantity of water
ii) Water pressure
d) Temp. of cooled air
under condition c )
--------Ltr/minutes per
cooler
-----------kg/ cm2
--------------------0c
19 Stator
a) Material of stator
core
b) Insulation of
lamination
c) Stator frame
construction
d) No of sections in
which divided for
transport
e) Insulation of stator
winding
f) Stator
i) Height including end
winding
ii) Diameter at air gap
---------------------------
---------------------------
---------------------------
-------------------------------
----------------------
--------------------mm
--------------------mm
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 283/331
Signature of Bidder Signature of Purchaser 283
iii) outside diameter of
frame
iv) shape
v) Weight
--------------------mm
--------------------mm
--------------------kg
20) Generator Housing
a) Height
b) Diameter (D)
c) No. of generator pit
heaters
d) No. of temp. detector
for fire protection
--------------------mm
--------------------mm
------------------------
------------------------
21) Rotor
a) Construction of field
poles
b) Method of attaching
field poles on rotor
rim
c) Rotor rim material
and construction
d) Rotor spider material
e) Field winding
construction
-------------------------
------------------------
------------------------
-----------------------
----------------------
-----------------------
--------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 284/331
Signature of Bidder Signature of Purchaser 284
f) Insulation of field
winding
g) Construction of
damper winding
h) Air gap width
i) Factor of safety at
max. runaway Speed
based on yield point
of material
-----------------------
-----------------------
--------------------mm
---------------------
22) Shaft
a) Material
b) Diameter
c) Length
d) Diameter of axial
holes
e) Weight
f) Diameter of coupling
flange
------------------------
------------------------
------------------------
-------------------------
--------------------kg
--------------------mm
23) Thrust and guide bearing
a) Cooling water at
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 285/331
Signature of Bidder Signature of Purchaser 285
350c required
j) Quantity
ii) Pressure
b) Location of bearing
c) Thrust bearing and
guide bearings
i)Type
ii)Diameter of
bearing
iii) Bearing area
iv) No of pads
Thrust Bearing
-------------
--------------
------------------
------------------
--------------------------
-------------------------------
--------------------
--------------------------
Guide Beaing
------------------------
------------------------
-----------------------
------------------------
24) Bearing (Bracket)
Material and construction --------------------------
25) Height that the rotor must
be raised to dismantle the
thrust bearing
--------------------------
26) Generator brake and jacks
a) Air pressure range for
the brakes forsatisfactory operation
b) Speed at which
brakes are to be
applied during
normal shut down
---------------------
--------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 286/331
Signature of Bidder Signature of Purchaser 286
c) No of brakes
d) Stopping time of
generator
-----------------------
-----------------------
27) Oil pressure for jacking ---------------------
28) Capacity of jacking pump --------------------lpm
29) Lubricating system
A) Oil
a)Specifications
b)Quantity for filling
i) Thrust and guide
bearing system
ii) Lower guide
bearing
c)Oil cooling
arrangement
d) Description of
arrangement
to prevent
circulating current
in the bearing
-----------------------
-------------------------
-----------------------
-----------------------
--------------------------
30) Weight of generator
rotating parts.
--------------------------
31) Weight of complete
generator
--------------------------
32) Total load on thrust
bearing
( including hydraulic
thrust etc.)
---------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 287/331
Signature of Bidder Signature of Purchaser 287
33) Heaviest package for
shipment
a) Name
b) Weight
c) Dimension
--------------------------
------------------------
------------------------
34) Largest package for
shipment
a) Name
b) Weight
c) Dimension
-------------------------
------------------------
35) Heaviest Assembly to be
lifted by power house
crane
a) Name
b) Weight
c) Dimension
-------------------------
--------------------------
-------------------------
36) Largest assembly to be
lifted by the power house
EOT crane
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 288/331
Signature of Bidder Signature of Purchaser 288
a) Name
b) Weight
c) Dimension
------------------------
-----------------------
-----------------------
37) Recommended crane
capacity
--------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 289/331
Signature of Bidder Signature of Purchaser289
TABLE NO.1
GUARANTEED VALUES OF GENERATOR LOSSES AND EFFICIENCY AT RATED VOLTAGE Un a
No. Losses (According to IEC 34-2) Symbol unit Apparentterminals
Smax= 110 %MVA
Losses in active iron and additional no loadLosses in metal parts
Pfe kW
1 Constantlosses
Losses due tofriction andwindage (*)
Turbine bearing losses Pu.g.b kW
Generator bearing losses Pl.g.b. kW
Windage and friction losses Pwi+f kW
Brushes losses Pbr kW
2 Excitationparameters
Field voltage Uf V
Field current If A
3 Load losses Stator windings copper losses at 75° C Pcu 1 kW
Additional load losses Padd. kW
Field winding copper losses at 75° C Pcu2 kW
Excitation system losses (excit trasf. +thyristors + ac/dc links)
Pe.s kW
Electrical losses in brushes Pe.br kW
4
:
SUMMATION OF LOSSES I p kW5 CALCULATED GENERATOR EFFICIENCY f i G.c6 GUARANTEED GENERATOR EFFICIENCY f jG.g
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 290/331
Signature of Bidder Signature of Purchaser290
TABLE NO.2
GUARANTEED VALUES OF GENERATOR LOSSES AND EFFICIENCY AT RATED VOLTAGE Un a
No. Losses (According to IEC 34-2) Symbol unit Apparenterminal
Smax110 % MVA
Losses in active iron and additional no loadLosses in metal parts
Pfe kW
1 Constantlosses
Losses due tofriction andwindage (*)
Turbine bearing losses Pu.g.b kW
Generator bearing losses Pl.g.b. kW
Windage and friction losses Pwi+f kW
Brushes losses Pbr kW
2 Excitationparameters Field voltage Uf V
Field current If A
3 Load losses Stator windings copper losses at 75° C Pcu 1 kW
Additional load losses Padd. kW
Field winding copper losses at 75° C Pcu2 kW
Excitation system losses (excit trasf. +thyristors + ac/dc links)
Pe.s kW
Electrical losses in brushes Pe.br kW
4 : SUMMATION OF LOSSES I p kW5 CALCULATED GENERATOR EFFICIENCY f i G.c6 GUARANTEED GENERATOR EFFICIENCY f jG.g
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 291/331
Signature of Bidder Signature of Purchaser291
TABLE NO.3
GUARANTEED VALUES OF GENERATOR LOSSES AND EFFICIENCY AT RATED VOLTAGE Un a
No. Losses (According to IEC 34-2) Symbol unit Appatermin
Smax110 % MV
Losses in active iron and additional no loadLosses in metal parts
Pfe kW
1 Constantlosses
Losses due tofriction andwindage (*)
Turbine bearing losses Pu.g.b kW
Generator bearing losses Pl.g.b. kW
Windage and friction losses Pwi+f kW
Brushes losses Pbr kW
2 Excitationparameters
Field voltage Uf V
Field current If A
3 Load losses Stator windings copper losses at 75° C Pcu 1 kW
Additional load losses Padd. kW
Field winding copper losses at 75° C Pcu2 kW
Excitation system losses (excit trasf. +thyristors + ac/dc links)
Pe.s kW
Electrical losses in brushes Pe.br kW
4
:
SUMMATION OF LOSSES I p kW5 CALCULATED GENERATOR EFFICIENCY f i G.c6 GUARANTEED GENERATOR EFFICIENCY f jG.g
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 292/331
Signature of Bidder Signature of Purchaser292
SECTION –IX
SUPERVISORY CONTROL AND DATA ACQUISITIONSYSTEM
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 293/331
Signature of Bidder Signature of Purchaser293
SECTION NO. IX
Supervisory control and data acquisition system
I N D E X
SR.
NO.
Description PAGE
NO.
9.1
9.2
9.3
General Requirements
Computer based SCADA system
Unit control Board
Departure from specification
Data Sheets
294
295
305
309
310
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 294/331
Signature of Bidder Signature of Purchaser294
SECTION IX
SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM
9.1 GENERAL REQUIREMENT:-
1 Comprehensive system for automation of the power station
complex as a whole shall be provided by the supplier.
2. The plant to be controlled shall consist of the following:-
i) One No.:- Turbines-Generator set including all connected
auxiliaries.
ii) Station service auxiliaries
iii) 220 kV switchyard equipments.
3. The system shall use the most up to date & proven technology
based on microprocessors reliable transducers which require no
or little maintenance and/or calibration during services.
4. The system shall be arranged to provide (2) two levels of controls
:- viz
i) “Plant Control” in automation mode from Unit Control
board or from LCD console.
ii) “Unit control,” in manual mode, from Unit Control board
or from respective control cubicles ( Generator excitation
cubicle, auxiliary equipment control board and generator
metal clad switchgear cubicle/etc.)
5. Normally, the plant control in remote automatic mode shall be
used. When the communication link is not available, or when the
equipment in Central Control Room is being inspected and/or is
under repairs, the control and monitoring functions of the unit
can be performed in Unit Control in “Manual Mode,”.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 295/331
Signature of Bidder Signature of Purchaser295
9.2 COMPUTER BASED SCADA SYSTEM :-
9.2.1 System:
Computer based SCADA system shall be used. Computer based
SCADA system uses microprocessor based control technology
physically distributed through out the power house. The separate
microprocessor units are linked together by a number of digital
communication paths to form a completely integrated control system.
9.2.2 Control Parameters:
SCADA system should be complete with primary sensors, cables
analysers/transmitters, monitors, system hardware/ software and
peripherals etc. to monitor/control the following parameters.
• Generator stator and rotor winding temperatures
• Generator and turbine bearing temperature
• Lubrication oil temperatures
• Status of generator cooling system
• Governor control monitoring of turbine speed
• Generator terminal voltage, current, KW, KVAR, KVA, KWH, Hz,PF, field voltage and field current.
• Annunciation for violation of permissible limits of above parameter
• Turbine guide bearing temperature detector
• Generator guide & thrust bearing temperature detector
• Guide and thrust bearing oil level indicator
• Generator winding temperature detector
• Turbine speed
• Generator speed
• Governor oil pumps, oil pressure indicator and low pressure indicator
and low pressure switch
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 296/331
Signature of Bidder Signature of Purchaser296
• Cooling water pumps, section and discharge pressure switch / gauge.
• Inlet pressure gauge at inlet of turbine
SCADA should provide monitoring of parameters listed above. The list
may have additional parameters as per requirement and shall be
finalised during design stage.
9.2.3 SCADA should have following controllers:
• Unit controller
• Common plant controller/ supervisory control
• Remote supervisory control
9.2.4 Unit Controller:
It is microprocessor based / PLC based and is required to perform all
functions as below. It is required to have capability to implement closed
loop PID function for governing and to perform all monitoring, control,
protection and recording functions that a power plant required
independently.
(a) It should monitor and control items
• Turbine wicket gate• Turbine/ Generator RPM
• Generator power out put
• Generator excitation
• Generator breaker
• Line breaker
(b) Automatic unit control modes should include following:
• Unit automatic start sequence
• Unit automatic shutdown sequence
• Unit automatic synchronizing
• Unit wicket gate set point control
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 297/331
Signature of Bidder Signature of Purchaser297
• Unit load set point control
• Unit flow control
(c) The unit should include digital governor with proportional, integral
and derivative gains. The governor be with in a position loop controlled
by speed loop and capable of 0-10% droop. A manual position control
should be provided. Following governing functions should be provided.
• Speed evaluator
• Speed control
• Speed set point adjustment
• Gate limiter
• Start up and shutdown control of turbine
• Position controller for guide vanes with power amplifier for control of
servo valve.
(d) Unit Auto synchronization
The controller should automatically synchronize the generator to the bus
by reading the slip frequency (generator-bus) and adjusting the governor
speed set point until the correct slip frequency is obtained while sending
voltage raise/lower pulses to the voltage regulator to match generator
voltage to bus voltage. When the slip frequency is obtained and thegenerator and bus voltage are equal, the controller
shall send a close breaker command when the generator voltage and the
bus are in phase. An additional external synchro check relay should also
be provided to supervise the controller close breaker command and the
manual close breaker command. The controller should follow
synchronization limits in terms of breaker closing angle and voltage
matching condition specified by generator manufacturer.
(e) Shutdown sequence
The shutdown sequence provided by controller should be such that the
turbine generator set from any moving state to a complete standstill with
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 298/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 299/331
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 300/331
Signature of Bidder Signature of Purchaser300
(vii) Reactive power control
The controller should have four reactive control modes, one manual and
three automatic. The generator capability curve should be entered into
the controller during configuring. All automatic reactive power control
modes should be limited by the generator capability curves. If an
operator enters a set point, that will take the generator outside its
capability curves, the reactive power control program should control
reactive power to get as close to the set point as possible, but remain
within the generator's capability.
• Manual:
The controller should provide operator capability, using "raise/lower"
keys on the VDT keyboard and the "raise/lower" switch on the manual
control panel to control voltage and reactive power.
• Automatic VAR control:
The controller should automatically control the generator output to that
VAR set point set by operator. The generator voltage limit and
capability curve should not be exceeded regardless of the VAR set
point.
• Automatic PF Control:The operator should enter power factor set point from the keyboard and
the controller should automatically control the generator output to that
power factor (leading or lagging) set point set by operator. The
generator voltage limit and capability curve should not be exceeded
regardless of the power factor set point.
• Automatic voltage control:
The controller should automatically control the generator output to
match that voltage set point set by operator. The generator voltage limit
and capability curve should not be exceeded regardless of the voltage set
point.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 301/331
Signature of Bidder Signature of Purchaser301
• Alarm Annunciation
There should be two types of alarms used by the controller. One type
should be the external alarms from contacts fed into the digital inputs of
the controller and the second, the internal alarms generated by the
controller. All alarms, whether internal or external, should be capable of
being configured to cause different sequences.
Unit controller should be capable of providing audible and visual alarms
in the event of faults occurring in the power plants. The instant the fault
occurs the relevant fault indicator is activated. All faults have to be
acknowledged by the operators and can only be reset when the fault has
been resolved. The list of faults on occurrence of which audible warning
should be given will be finalised during design stage. .(viii) Manual
control panel
The unit controller should have a manual control panel that bypasses the
processor and allows the generator to be operated manually. The manual
operation shall be done from UCB. The manual control panel should
include start relay circuitry that is station battery powered. Manual
switches to trip and close the breaker, turn the field on and off, start and
stop the turbine and raise and lower the voltage should also be included.The gate should be capable of manual operation by a potentiometer that
is located on a manual control panel and should be calibrated to position
within 0.1 percent.
(ix) Unit Protection
The protection system shall be based on the use of discrete
microprocessor based relays with the following features:
• Continuous self monitoring
• Online display of actual values
• Should be capable to communicate with supervisory system through
unit controller. Details of protection relays are covered in section -XI
.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 302/331
Signature of Bidder Signature of Purchaser302
(x) Supervisory Controller
It should monitor and control the status of power plant, provide
automatic unmanned operation, log data, display the process through a
mimics, Depending on the station requirements, the operator should be
able to enter set points for power output, voltage and power factor. It
should also have online documentation and expert diagnostics,
efficiency management and plant management.
9.2.6 Operator Interface Requirements:
The controller should use a video display terminal or PC as the main
operator console. It should have powerful graphical user interface to the
operators. The operator should be able to completely operate the plant
by typing commands/function key on the keyboard or by push button on
control panel. All information required to operate the plant should be
shown on the screen. A printer should be used to print out plant
information. Symbols and colours specified in the international standard
IEC 204 should be used for display.
9.2.7 Screen display:The screen display should include all metering, indication and
annunciator information normally displayed on a typical power plant
control panel. This should include all metered data such as three phase
generator volts and amps, generator watts, VARS, power factor, speed
and frequency. This display should also show generator stator and
bearing temperatures, breaker status, line volts, line frequency, and
kilowatt-hours. The time and date should also be displayed with time to
the minute. Screen data should be updated promptly whenever actual
data changes. Alarm and status information should be updated within
one second of actual changes. Analog data should be updated within two
seconds of a change. Calculated value such as temperature, watts,
VARS, and power factor should be updated within five seconds of an
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 303/331
Signature of Bidder Signature of Purchaser303
actual change. All DC analog readings on the screen display should
have configurable scale factors. All except speed should have
configurable labelling on the screen.
The AC scaling should be configurable by specifying WYE or DELTA
and maximum AC voltage and current.
Data shown on the display should have the following minimum
accuracies.
AC Voltage 1% of full scale
AC Current .1% of full scale
Frequency ± .005 HZ
DC Inputs .25% of full scale
KW, KVAR, PF .25% of full scale
Temperatures + .5 degrees C
9.2.8 Annunciator display:
A portion of the screen should be dedicated for an annunciator. Alarms
should be displayed in order of occurrence with the oldest alarm at the
top of the screen. The sequence of alarms should be distinguishable if
alarms are more than 1/60 th of a second a part. The display shouldinclude space for a least 23 alarms. When an alarm clears, the alarm
below it should move up to fill in the blank space keeping the sequence.
No alarms should be lost. Any alarms that do not fit on the screen
should be saved until there is room. Alarms should flash until the
acknowledge key on the keyboard is pressed. If the alarm is still on after
it is acknowledged, it should stop flashing but remain on the screen. If
the alarm has cleared, it should be disappeared from the screen when the
acknowledge key is pressed.
The annunciator should display both alarms that are internally generated
by the controller and alarms that are sensed external to the controller.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 304/331
Signature of Bidder Signature of Purchaser304
9.2.9 Control status display:
The display should include an indication of the status of the turbine i.e.,
starting, stopping, synchronizing, etc...
9.2.10 Automatic control status display:
The display should show the current automatic control mode, its set
point, turbine gate limit, and any overriding control modes.
9.2.11 DT Keyboard:
The keyboard should be a standard keyboard with upper and lower
cases, ten key numeric pad and at least ten function keys. The function
keys should be assigned important functions.
The operator should be able to start and stop the turbine from the
keyboard using simple commands. The operator should be able to enter
set points via keyboard, select any one of automatic power control
modes and select any one of reactive power control modes
9.2.12 External Interface
Supervisory Controller should have a number of protocol moduleswhich should provide connectivity to other devices including remote
terminal units and programmable logic controllers.
9.2.13 Event Recording and Data Logging
(a) Data logging
Their should be a provision for a data logging printer at the plant to
provide data logging at adjustable intervals, trouble logs and operator
comments entered manually at the keyboard. The data logging interval
for each printers should be adjustable by the operator in increments of
one minute.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 305/331
Signature of Bidder Signature of Purchaser305
(b) Alarm and status logging
All alarms annunciated on the screen should be recorded on the data log,
time-tagged to 1/60 of a second resolution. Plant status or operational
changes should also be recorded on the data log, time-tagged to 1/60 of
a second resolution. The operator should be able to enter comments on
the log manually through the keyboard.
(c) kWH logging
Plant watthours should be accumulated and recorded on the data log at
both daily and monthly intervals. The integrated power generation
controller should have the capability to accumulate these data by one of
two methods: internally, by a calculation method based on direct
monitoring of generator CT and PT inputs, or externally, by receiving
and totalizing counts from pulse initiator output from an external
watthour meter.
9.3 UNIT CONTROL BOARD (UCB)
Unit Control Board shall be installed in Control Room.
Controls, Indications, Alarms etc. required on UCB are givenbelow :
1. All control switches required for manual operation shall be
mounted on this board.
2. Following control switches for Auto operation of plant shall be
provided on UCB
a) Unit Start/Stop
b) Auto/ Manual
c) Emergency Stop
3. Three annunciation windows shall be provided.
a) Operation indication window
b) 30 window annunciator for Electrical fault
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 306/331
Signature of Bidder Signature of Purchaser306
c) 30 window annunciator for Mechanical fault
4. Digital clock for indication of time
5. Digital type temp. scanner (0-150oc) with selector switch for
temperature indication of selective equipments of power plant
such as stator, rotor, guide bearing etc. shall be provided.
6. Following meters shall be provided.
- Guide Vanes Limiter Position Indicator (0-100%)
- Guide Vanes Position Indicator (0-100%)
- Runner blades Limiter Position Indicator (0-100%)
- Runner blades Position Indicator (0-100%)
- Generator Voltage Meter with Selector Switch
(0-20 kV)
- Generator Current Meter with Selector Switch
(0-10 kA)
- Generator MW meter (MW-0-20 MW)
- Generator MVAr Meter
- Generator Power Factor Meter (0.9 over excited ....1.0
...0.9 under excited).- Frequency Meter 45-55 Hz
- Field Voltage Meter 0-500 V
- Field Current Meter 0-4000A
- Turbine Speed Indicator 0 to 500 rpm
- Speed/Load Setting Indicator.
- Running Hour Meter (Hours)
7. Dual channel AUTO/MANUAL Synchronizer shall be provided.
Auto synchroniser shall consist of following modules :-
PHASE DETECTION MODULE :
This module shall detect the phase difference between incoming
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 307/331
Signature of Bidder Signature of Purchaser307
generator and grid voltage. Output of the module shall be a pulse
train whose width should vary as the phase difference.
FREQUENCY DIFFERENCE MEASUREMENT MODULE :
This shall measure the frequency difference between the
incoming generator and grid voltage in the frequency difference
of 0.01Hz to 1.00 Hz.
POLARITY MODULE :
This module shall compare the frequency difference obtained
with the set value. (The set value is the one which is set on the
front plate of the module) The module should then generate
control signals for frequency matching.
VOLTAGE DIFFERENCE MEASUREMENT MODULE :
This shall measure the voltage difference between the incoming
generator voltage and grid voltage and generate control signals
for voltage matching.
VOLTAGE COMMAND MODULE:
This shall issue final command to AVR for raising or lowering
the incoming generator voltage depending upon the measuredcondition. Interposing relays shall be provided for this purpose.
FREQUENCY COMMAND MODULE :
This shall issue the final command to the E.H.G for lowering or
raising the incoming generator frequency depending on the
measured condition. Interposing relays shall be provided for this
purpose.
BREAKER COMMAND MODULE :
After the voltage and frequency are matched this module shall
issue the closing command to the breaker. It should also take
into account the breaker closing time which can be set on the
front plate of the module.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 308/331
Signature of Bidder Signature of Purchaser308
AUTOMATIC POWER OFF MODULE :
After synchronisation, the feed back is received in this module
which shall switch off the auto synchroniser.
POWER SUPPLY MODULE :
This module should accept the input voltage of 230V A.C. and
generate necessary voltage required for functioning of auto
synchroniser.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 309/331
Signature of Bidder Signature of Purchaser309
DEPARTURE FROM SPECIFICATION
(To be filled in by Bidder.)
Item Description of departure. Reference to clause in the specifications
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 310/331
Signature of Bidder Signature of Purchaser310
DATA SHEETS
MAIN CONTROLLER UNIT CONTROL BOARD
Sr.
No.
Description Offered By Supplier
1 Manufacturer / Type :- --------------------------
2 No of CPU :- --------------------------
3 Characteristics of CPU :- --------------------------
3.1 Microprocessor :- --------------------------
3.2 Maximum memory capacity
( Program/data)
:- --------------------------
3.3 Maximum No of flags :- --------------------------
i) Retentive :- --------------------------
ii) Non Retentive :- --------------------------
3.4 Maximum No of Timers
0.01-9990s
:- --------------------------
3.5 Maximum No of Counters
0-999s
:- --------------------------
3.6 Max. Number of inputs/outputs :- --------------------------
i Digital inputs :- --------------------------
ii Digital outputs :- --------------------------
iii Analog inputs :- --------------------------
iv Analog outputs :- --------------------------
3.7 Power supply module :- --------------------------
i Voltage :- --------------------------
ii Frequency :- --------------------------
iii Converters :- --------------------------
3.8 Programming Language :- --------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 311/331
Signature of Bidder Signature of Purchaser311
WORK AND OPERATING STATION
Sr No Description Offered by supplier
1 Manufacturer /Type :- ---------------------------
2 Number of CPU :- ---------------------------
3 CPU Details :- ---------------------------
4 RAM Capacity :- ---------------------------
5 Hard Disc capacity :- ---------------------------
6 Operating system :- ---------------------------
7 Video display unit :- ---------------------------
a Number :- ---------------------------
b Display screen :- ---------------------------
c Key board :- ---------------------------
d Printer :- ---------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 312/331
Signature of Bidder Signature of Purchaser312
SECTION – X
TECHNICAL SPECIFICATION FOR LAVT CUBICLE, NGCUBICLE AND ISOLATOR
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 313/331
Signature of Bidder Signature of Purchaser313
SECTION NO. XTECHNICAL SPECIFICATION FOR LAVT CUBICAL,NG CUBICAL,
GENERATOR EXTENDED TERMINALS
I N D E X
SR.
NO.
Description PAGE
NO.
10.1
10.2
10.3
Scope
Codes and Standards
Removable and Shorting Links.
Data sheets
314
316
317
318
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 314/331
Signature of Bidder Signature of Purchaser314
SECTION- X
TECHNICAL SPECIFICATION FOR LAVT CUBICLE, N.G CUBICLE AND
ISOLATOR CUBICLE
10.1 SCOPE :-
The scope of these specifications shall cover the design, manufacture,
assembly, testing at manufacturer’s works before despatch, supply,
delivery, supervision, onsite erection, testing and commissioning of:-
1) LAVT CUBICLE
One set of lightning arrestor and voltage transformer cubicle of sheet
steel construction shall be supplied complete with fluorescent lamp,
internal wiring, space heater etc. The equipment details are as under:-
1 set 11000/ √3/110/ √3V/110/ √3V PT
Core-1, 100 VA, Cl 0.2
Core-2, 200 VA, Cl 3P
1 set 11000/ √3/110/ √3V/110/ √3V PT
Core-1, 100 VA, Cl 0.2
Core-2, 200 VA, Cl 3P
1 Set of 12 KV, 10 KA lightning Arrestor
1 Set of 12 KV, Surge Capacitor
3 Nos. MCB
2) N.G. CUBICLE
One set of NG cubicle of sheet construction complete with space
heater, marshalling box, illumination lamp etc. The cubicle shall havefollowing :
1 No. Disconnecting link
1 No. 11/3 KV/220 V single phase NG transformer
1 No. secondary loading resistor.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 315/331
Signature of Bidder Signature of Purchaser315
Galvanised steel supports, shorting bar etc.
3) BUS DUCT
A) 1000 A, 11 kV, segregated phase busduct for the inter connection
between Generator terminals and LAVT cubicle.
Following taps shall be provided
a) Tap for Excitation Transformer
b) End terminals for interconnection of LAVT cubicle with Isolator
cubicle.
B) Segregated phase busduct for generator neutral connection to NG
cubicle.
Phase busduct comprises of 3.2 thick Aluminium alloy enclosure and
Aluminium alloy conductor in box formation shall be provided.
4) CURRENT TRANSFORMERS :-
Following CTs shall be provided on Generator phase side .
a) Current Transformer 1000/5A
30 VA CL 5P 20 for Generator Diff. Protection
b) Current Transformer 1000/5A
30 VA CL 5P 20 for Transformer Diff. Protection
c) Current Transformer 1000/5A
30 V.A .0.2 for AVR
d) Current Transformer 1000/5A
30 V.A CL 5P 20 for other protection relays.
Following CTs shall be provided on Generator Neutral side.
e) Current Transformer 1000/5a
30 VA CL 5P 20 for Generator Diff. Protection
d) Current Transformer 1000/5A
30 V.A CL 5P 20 for overall Diff. protection .
Note:- The power transformer is not in the scope of supply of this contact.
Also synchronising is proposed to be at 220 kV switchyard supplier
for following aspects.
a) CT specification on 220 kV side for Overall Diffi Protection.
b) Control and power cable termination
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 316/331
Signature of Bidder Signature of Purchaser316
c) Coordination regarding exchange of information regarding status of
220 kV breakers, breaker closing and opening command from SCADA
system etc.
d) UAT is not in the scope of this contact. Diff .protection of UAT is
included in the scope of this contact .Main plant supplier shall co-
ordinate with other supplier in respect of exchange of information
regarding CT specification requirement ,control and power cable
termination etc.
5) ISOLATOR CUBICLE :- For the purpose of keeping main power
transformer in charged condition during major shutdown of power
plant ,a motor operated isolator cubicle with 1000 A current carrying
capacity shall be provided . A tap for connection of 11 KV XLPE
cable between isolator cubicle and power transformer shall be
provided .It shall possible to operate the isolator from USB . To
avoid operation of isolator during operation of the main plant . Lock
and key arrangement shall be provided for push buttons . The isolator
contacts shall be taken in the auto plant operation sequence
programme such that at all times isolator shall be in closed position
before starting the machine.
10.2 CODES AND STANDARDS
All Equipment shall be designed ,manufactured and tested in
accordance with standards mentioned as below :-
CURRENT TRANSFORMERS
15) IEC 185/1987 Current Transformer
16) IS- 2705 Current Transformer
VOLTAGE TRANSFORMERS
17 ) IEC-186/1987 Voltage Transformer
SURGE PROTECTION CAPACITOR
18 ) IS-3070 Lighting Arrestors
19) VDE-0657 Capacitors
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 317/331
Signature of Bidder Signature of Purchaser317
GENERATOR NEUTRAL EARTHING
20) IS-3151 Earthing Transformer
NOTE :-
IS – Indian Standard
IEC - International Electro technical Commission
VDE –Verband Deutscher Eletrotechniker
10.3 REMOVEBLE AND SHORTING LINKS
10.3.1 SCOPE
The scope of this specifications shall cover the design ,manufacture,
assembly and testing at manufacturer’s works before dispatch, supply
delivery ,supervision .on –site erection ,testing and commissioning of :-
- 1 set of three phase removable links to be provided in the main run to
facilitate disconnection of generator and step up transformer during testing
, commissioning and maintenance.
- 1 set of three phase removable links to be provided for tap run to unit
auxiliary transformer (UAT) to facilitate disconnection of CTs. And UAT
during testing , commissioning and maintenance.
- 1 set of three phase removable links to be provided for tap run to exitation
transformer (ET) to facilitate disconnection of CT;s ,VT-1.VT-2 and ET
during testing , commissioning and maintenance.
- 1 set of removable links in the run of neutral bus duct for segregation of
generator phase from neutral point.
- One (1) three phase set of bolted type main run shorting links for the
purpose of drying out of generator stator before commissioning or for
carrying out sustained short-circuit tests shall be provided.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 318/331
Signature of Bidder Signature of Purchaser318
DATA SHEETS
CURRENT TRANSFORMER
MAIN RUN
Sr. No. Description
1 Manufacturer / type :- ……………………………2 Rated Primary Current (A) :- ………………………
3 Rated Secondary Current (A) :- ………………………
4 Rated Secondary Output :
i) Measuring (1) :- ………………..............VA
ii) Protection (2) :- …………………...........VA
iii) Protection (3) :- ……………..................VA
iv) Protection (4) :- …………….................VA
5 Accuracy Class
i) Measuring (1) :- ………………..............VAii) Protection (2) :- …………………...........VA
iii) Protection (3) :- ……………..................VA
iv) Protection (4) :- …………….................VA
6 Instrument security factor :- ……………………………
7 Accuracy limit factor for Protection
core
:- ……………………………
8 Short time current rating
i) Thermal current (Ith) :- ……………………………KA
ii) Dynamic current (Idyn.) :- ……………………………KA
iii) Short circuit duration :- ……………………………Sec
9 One minute Power Frequency
withstand Voltage (between
bus-bars and secondary
windings)
:- ……………………………KV
10 Inter turn insulation of
secondary winding :
- one minute across complete
winding
:- ……………………………KV
- one minute between the sections
:- ……………………………KV
11 Temperature rise of winding :- ………………………….K
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 319/331
Signature of Bidder Signature of Purchaser319
CURRENT TRANSFORMER
TAP OFF RUN TO EXCITATION TRANSFORMER
Sr. No. Description Offered by supplier
1 Manufacturer / type :- ……………………………
2 Rated Primary Current (A) :- ………………………3 Rated Secondary Current (A) :- ………………………
4 Rated Secondary Output :
i) Measuring (1) :- ………………..............VA
ii) Protection (2) :- …………………...........VA
5 Accuracy Class
i) Measuring (1) :- ………………..............VA
ii) Protection (2) :- …………………...........VA
6 Instrument security factor :- ……………………………
7 Accuracy limit factor for Protectioncore
:- ……………………………
8 Short time current rating
i) Thermal current (Ith) :- ……………………………KA
ii) Dynamic current (Idyn.) :- ……………………………KA
iii) Short circuit duration :- ……………………………s
9 One minute Power Frequency
withstand Voltage (between
bus-bars and secondary
windings)
:- ……………………………KV
10 Inter turn insulation of
secondary winding :
- one minute across complete
winding
:- ……………………………KV
- one minute between the sections
:- ……………………………KV
11 Temperature rise of winding :- ………………………….K
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 320/331
Signature of Bidder Signature of Purchaser320
CURRENT TRANSFORMER
NEUTRAL TERMINAL
Sr. No. Description Offered by supplier
1 Manufacturer / type :- ……………………………
2 Rated Primary Current (A) :- ………………………3 Rated Secondary Current (A) :- ………………………
4 Rated Secondary Output :
ii) Protection (1) :- …………………...........VA
iii) Protection (2) :- ……………..................VA
iv) Protection (3) :- …………….................VA
5 Accuracy Class
ii) Protection (1) :- …………………...........VA
iii) Protection (2) :- ……………..................VA
iv) Protection (3) :- …………….................VA6 Instrument security factor :- ……………………………
7 Accuracy limit factor for Protection
core
:- ……………………………
8 Short time current rating
i) Thermal current (Ith) :- ……………………………KA
ii) Dynamic current (Idyn.) :- ……………………………KA
iii) Short circuit duration :- ……………………………s
9 One minute Power Frequency
withstand Voltage (betweenbus-bars and secondary
windings)
:- ……………………………KV
10 Inter turn insulation of
secondary winding :
- one minute across complete
winding
:- ……………………………KV
- one minute between the sections
:- ……………………………KV
11 Temperature rise of winding :- ………………………….K
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 321/331
Signature of Bidder Signature of Purchaser321
VOLTAGE TRANSFORMERS
VT-1 & VT-2
Sr. No. Description Offered by supplier
1 Manufacturer /type :- …………………………….
2 Primary Rated Voltage (kV) :- ………………………KV rms3 Secondary Rated Voltage
- core 1 (measuring) :- ……………………………V
- core 2 (Protection) :- ……………………………V
4 Accuracy Class
- core 1 (measuring)
- core 2 (Protection)
5 Rated Burden
- core 1 (measuring) :- ……………………………VA
- core 2 (Protection) :- ……………………………VA6 Thermal Burden
- core 1 (measuring) :- ……………………………VA
- core 2 (Protection) :- ……………………………VA
7 Voltage Factor
- Continuous service :- …………………………….
- During 8 hours :- …………………………….
- During 4 hours :- …………………………….
8 Short-circuit current
(guaranteed for secondary
windings.)
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 322/331
Signature of Bidder Signature of Purchaser322
SURGE PROTECTION CAPACITORS AND LIGHTING ARRESTERS
Sr. No. Description Offered by supplier
A Surge Protection Capacitors 1 Manufacturer / type :- ………………………
2 Max. Voltage for equipment (kV) :- ……………………… KV
3 Rated voltage :- ………………… KV
4 Rated capacitance :- ……………………microfarad
4 Dielectric :- ………………………
5 Temperature class :- ………………………
6 Insulators creepage distance min :- ……………………… mm/kV
B Lighting Arresters1 Manufacturer/ type :- ……………………………
2 Rated Voltage (kV) :- ……………………………KV
3 Number of stacks
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 323/331
Signature of Bidder Signature of Purchaser323
GENERATOR NEUTRAL EARTHING
Sr. No. Description Offered by supplier
A LOADING RESISTOR
1 Manufacturer / type :- ………………………2 Max. system voltage for equipment
(Um)
:- ……………………… KV
3 Rated current (A), 10 s. :- ………………… A
4 Overload capacity
i) 1s. (A) :- ………………… A
ii) 2s. (A) :- ………………… A
iii) 5s. (A) :- ………………… A
5 Resistance t = 20º C :- ………………… ohm
6 Test Voltagei) one minute 50 Hz (kVrms) :- …………..………(kVrms)
ii) Impulse 1.2/50 microsecond
(kVcr)
:- …………..……… V
B Neutral voltage transformer
or neutral point grounding
transformer
1 Manufacturer /type
2 Year VT or power transformer iscommercialised
3 Primary Voltage :- …………..……… KV
4 Secondary Voltage :- …………..……… V
5 Burden :- …………..……… VA
6 Class :- …………..………
7 One minute 50 Hz test voltage :- …………..……… KV rms
8 Impulse test voltage 1.2/50 micro
second
:- …………..………
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 324/331
Signature of Bidder Signature of Purchaser324
BUSDUCT
DESIGNATION : OFFERED BY
BY SUPPLIER
Technical Particulars:-
1) Name of manufacturer :-
2) Rated voltage :-
3) Continuous current ratingat rated voltage :-
4) Type :-
5) Reference standard :-
6) Symmetrical short
Circuit rating :-
7) One minute power
Frequency with-stand :-
8) Impulse level (1.2/50)
Micro sec ;_
9) Frequency :-
10) Enclosure-a) shape
b) Material :-
11) Conductor material :-
12) Support Insulator :-
13) Ambient Insulator :-
14) Temperature rise of
enclosure above ambient :-
15) Temperature rise of Conductor above ambient :-
16) Finish of bus duct :-
17) Finish of cubicles :-
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 325/331
Signature of Bidder Signature of Purchaser325
SECTION – XI
PROTECTIVE GEAR
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 326/331
Signature of Bidder Signature of Purchaser326
SECTION NO. XI
PROTECTIVE GEAR
I N D E X
SR.
NO.
Description PAGE
NO.11.1
11.2
11.3
Scope
Requirement
Data sheets.
327
327
330
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 327/331
Signature of Bidder Signature of Purchaser327
SECTION- XI
PROTECTIVE GEAR11.1 Scope:-
For the protection of Turbine Generator set, Excitation Transformer,
Main Transformer, unit auxiliary transformer microprocessor based
Protection Relay scheme shall be provided.
11.2 Requirement :-
1) protection scheme shall consist of main protection scheme and backup
Protection scheme.
2) Protection scheme shall consist of
a) Protection panel to accommodate all protection equipments.
b) Power supply unit: - Two power supply unit shall be used in each
protection scheme (main and backup) changeover between the
power supply unit shall be automatic.
c) Input module: - it shall consist of transformer module, relay
module etc.
d) CPU module with storage.
e) O /P relay module.
f) Software
g) LCD console to load software and setting the parameters.
h) Interfacing cables.
3) LED Indication of each protection shall be provided on panel.
4) Master trip relay with hand reset shall be provided.
5) Protection CTs on 220 KV side, UAT differential protection CTs, 220
KV Generator circuit breaker are not in the scope of this contract. TheProtection relay supplier shall co-ordinate with 220 KV equipment
supplier and other contractors for following co- ordination aspects.
a) Step up transformer differential protection :-
CT specification on 220 KV side & cable termination.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 328/331
Signature of Bidder Signature of Purchaser328
b) Overall differential protection :-
CT specification on 220 KV side & cable termination.
c) UAT differential protection:-
CT specification & cable termination.
11.3 Following protection shall be covered by protection system.
1) Generator Differential Protection.
2) Overall Differential Protection.
3) Step-up transformer differential protection.
4) Generator Stator Earth- fault protection.
5) Generator-Rotor Earth- fault protection.
6) Voltage controlled over- current protection.
7) Loss of excitation (Minimum reactance protection)
8) Reverse power protection.
9) Under-impedance protection.
10 ) Thermal over-load protection.
11) Negative sequence phase current protection.
12) Restricted earth-fault protection for star- connected
secondary Winding of step-up transformer.13) Over-frequency protection.
14) Under-frequency protection.
15) Generator over-voltage protection.
16) Generator under –voltage protection
17) Step-up transformer over-current protection.
18) Step-up transformer over-fluxing protection.
19) Excitation transformer differential protection.
20) Unit auxiliary transformer differential protection.
21) Any other protection required.
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 329/331
Signature of Bidder Signature of Purchaser329
DEPARTURE FROM SPECIFICATION
(To be filled in by Bidder.)
Item Description of departure. Reference to clause in the specifications
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 330/331
Signature of Bidder Signature of Purchaser330
DATA SHEET
1 Name of Manufacturer :- -------------------------------
2 Type Designation :- -------------------------------
3 Size of panel :- -------------------------------
4 No of input analog modules :- -------------------------------
5 No of analog inputs per module :- -------------------------------
6 No of input digital modules :- -------------------------------
7 No of digital inputs per module :- -------------------------------
8 No of output relay module :- -------------------------------
9 No of outputs per modules :- -------------------------------
10 No of power supply module
( Details shall be furnished )
:- -------------------------------
11 No of CPU modules :- -------------------------------
12 List of protection function provided(separate list shall be furnished )
:- -------------------------------
14 Whether Master trip relay is provided :- -------------------------------
8/6/2019 Power Plant Sec
http://slidepdf.com/reader/full/power-plant-sec 331/331
Signature of Bidder Signature of Purchaser331
15 Will the operating console be supplied :- -------------------------------
16 Operating language :- -------------------------------
17 Operating voltage :- -------------------------------