power management system by abb
TRANSCRIPT
-
7/22/2019 Power Management System by ABB
1/40
ABB
AS
-1
2007
ABB
Power Management System
for Industrial Plants
-
7/22/2019 Power Management System by ABB
2/40
IndustrialITfor PMS
Introduction
Electrical Process
System configuration
Functionality PMS
ReferencesBenefits
-
7/22/2019 Power Management System by ABB
3/40
ABB
AS
-3
ABB
Tasc of Power Management Systems
Avoiding blackouts in industrial plants!
Power Sharing
Load Shedding
-
7/22/2019 Power Management System by ABB
4/40
ABB
AS
-4
ABB
Critical Loads
Limited In-plant Generation
Insufficient reliability of grid supply
Operational Drivers for IndustrialITfor PMS
Load Shedding
}
Several Generators
Power Sharing with other plants/grids Power Control}
Generator Modes and Operation
Transformer Control and Monitoring
Circuit Breaker Operation
Object Control}Connection to other plants/grids
Bus-Tie operationSynchronization}
-
7/22/2019 Power Management System by ABB
5/40
ABB
AS
-5
ABB
Why ABB IndustrialITfor PMS?
In-depth knowledge of the electrical process
20 years experience in PMS implementations across the world(green-field and brown-field plants)
Standard software, well documented, tested, proven technology
Fast Response Time for Load Shedding and Power Control
High Resolution and Accuracy of Sequence of Event recording
Comply to class 3 EMC immunity Single responsibility: One supplier for PMS integrated with
switchgear, protection, governor, excitation, transformer, tapchanger,Motor Control Centre, Variable Speed Drive, etc.
Experience with EPCs like: ABB Lummus, Bechtel, Chiyoda, Fluor
Daniel, Foster Wheeler, JGC, Kellogg, Larson & Tubro, Mitsubisi,Snamprogetti, Technip, Toyo, Toshiba, etc.
-
7/22/2019 Power Management System by ABB
6/40
ABB
AS
-6
ABB
Functionality Power Management Systems
Load Shedding
Active and Reactive Power Control
Supervision, Control and Data Acquisition (SCADA):
Generator and Turbine
Transformer and Tapchanger
Circuitbreaker, Disconnector and Earthing switches
Motor
Synchronization
-
7/22/2019 Power Management System by ABB
7/40
ABB
AS
-7
ABB
Different names for the same system
PMS : Power Management System
ENMC : Electrical Network Monitoring and Control system
ELICS : ELectrical Integrated Control System
PDCS : Power Distribution and Control System
LMS : Load Management System ECS : Electrical Control System
etc.
-
7/22/2019 Power Management System by ABB
8/40
ABB
AS
-8
ABB
Information Enabled Product . . .
Utilities
Fonts
Drivers
=
-
7/22/2019 Power Management System by ABB
9/40
ABB
AS
-9
ABB
Object approach
Simulation Model
Test Report
Control Program
Elec. Diagram
Mech. Drawing
Technical Spec.
-
7/22/2019 Power Management System by ABB
10/40
ABB
AS
-10
ABB
The global standard common for IEC and ANSI ...
-
7/22/2019 Power Management System by ABB
11/40
ABB
AS
-11
ABB
800xA architecture for Power Management System
TCP/IP Network
Plant & Enterprise Management Systems
Remote Users
ServerOperatorStation
EngineeringStation
Substation N
M M M M
MV
G
IEC 61850
LV
AC800MController
DCS
ProfiNet IO
Control Network
Substation 1 Substation 2 Substation Z
Router
-
7/22/2019 Power Management System by ABB
12/40
ABB
AS
-12
ABB
ControlITAC 800M Hardware
AC 800M
Built in redundant Ethernet Very low power consumption
Communication & fieldbus
interfaces
Hot swap of communication- and
I/O modules
Local and remote I/O options
Industry quality hardware with
excellent EMC and MTBF
properties
ControlIT
-
7/22/2019 Power Management System by ABB
13/40
ABB
AS
-13
ABB
Load Shedding
Functionality IndustrialITfor PMS
?
Without Load SheddingWith Load Shedding
-
7/22/2019 Power Management System by ABB
14/40
ABB
AS
-14
ABB
Load Shedding: The types
Fast Load Shedding on Loss of Power Resources
Load Shedding on Frequency Drop
Slow Load Shedding on Overload
Slow Load Shedding for Peak Shaving
Manual Load Shedding
-
7/22/2019 Power Management System by ABB
15/40
ABB
AS
-15
ABB
Load Shedding: Keywords
Fast
Exact Flexible
Co-ordinated
Deterministic
Security and Reliability
Accurate Event Logging
Operator Guidance
Independent Back-up System
(Click here for details)
-
7/22/2019 Power Management System by ABB
16/40
ABB
AS
-16
ABB
ABBs starting-point for Load Shedding
Secure electrical power to
critical loads
Minimal disturbance to
plant operation
No spurious operation
30MW20MW15MW
G2G1
M1 M2 M3 M4 M7M6M5
9MW
(5)
6MW
(3)
1MW
(3)
20MW
(1)
10MW
(2)
7MW
(4)
12MW
(5)
-
7/22/2019 Power Management System by ABB
17/40
ABB
AS
-17
ABB
M MMM M MMM MMM M MM MM M MMM
M MMM
G G
M MM M
G G
M MM M
G G G
GGG GGG
MM
33 kV level
6 kV level
(back-up)
400 V level
(back-up)
Contingency Load Shedding
-
7/22/2019 Power Management System by ABB
18/40
ABB
AS
-18
ABB
RED bays (Load Shed Groups):
Open Command 5-10 ms.
CB position 1 s.
Power Flow 1 s.
G G
M MM M
G G
M MM M
6 kV
GGG GGG
MM
33 kV
BLUE bays (Critical Signals):
CB position 5-10 ms.
Power Flow 1 s.
6 kV
Substation N
Fast Load SheddingRequired data
Substation 2
Substation 1
-
7/22/2019 Power Management System by ABB
19/40
ABB
AS
-19
ABB
Fast Load SheddingBusbar Load Tables
Busbar Left
1. 0 MW2. 2 MW
3. 2 MW
4. 2 MW
5. 7 MW
6. 9 MW7. 9 MW
8. 9 MW
Busbar Right
1. 0 MW2. 0 MW
3. 5 MW
4. 5 MW
5. 5 MW
6. 5 MW7. 10 MW
8. 12 MW2MW(2)2MW
(6)
5MW
(5)
5MW
(1)
5MW
(3)
2MW
(4)
2MW
(8)
16 MW
G1
16 MW
G2
5MW
(7)
M1 M2 M3 M4
M8M7M5 M6
-
7/22/2019 Power Management System by ABB
20/40
ABB
AS
-20
ABB
Fast Load SheddingContingency Load Table
Busbar L +
1. 0 MW2. 2 MW
3. 2 MW
4. 2 MW
5. 7 MW
6. 9 MW7. 9 MW
8. 9 MW
Busbar R =
0 MW0 MW
5 MW
5 MW
5 MW
5 MW10 MW
12 MW
Cont. 1
0 MW2 MW
7 MW
7 MW
12 MW
14 MW19 MW
21 MW
PInhibit= PGenerationPLoads= 3221 = 11MW
2MW
(2)
2MW
(6)
5MW
(5)
5MW
(1)
5MW
(3)
2MW
(4)
2MW
(8)
16 MW
G1
16 MW
G2
5MW
(7)
M1 M2 M3 M4
M8M7M5 M6
-
7/22/2019 Power Management System by ABB
21/40
ABB
AS
-21
ABB
Fast Load SheddingTrip of Generator 2
Power Balance:
PGen+ PSR PLoad+ PInhibit
PSR = 5 MW
16 + 5 21 + 11
21 32 Shed 11 MW
Check Table Shed Prio 5 Shed M1, M3 and M5
2MW
(2)
2MW
(6)
5MW
(5)
5MW
(1)
5MW
(3)
2MW
(4)
2MW
(8)
16 MW
G1
16 MW
G2
5MW
(7)
M1 M2 M3 M4
M8M7M5 M6
-
7/22/2019 Power Management System by ABB
22/40
ABB
AS
-22
ABB
Display Load Shedding SLD (before)
2.2 1.8 1.8 2.13.3
2.50.1
1.57.2
5.7
MW MWMW MW
MW
MWMW
Hz
kV
Generator trip
-
7/22/2019 Power Management System by ABB
23/40
ABB
AS
-23
ABB
-
7/22/2019 Power Management System by ABB
24/40
ABB
AS
-24
ABB
Display Load Shedding SLD (after)
0.0 1.8 1.8 2.13.3
2.50.1
1.54.8
3.9
MW MWMW MW
MW
MWMW
Hz
kV
Ethernet TCP/IPEthernet TCP/IPEthernet TCP/IPEthernet TCP/IP
-
7/22/2019 Power Management System by ABB
25/40
ABB
AS
-25
ABB
Display Load Shedding SLD (after)
0.0 1.8 1.8 2.13.3
2.50.1
1.54.8
3.9
MW MWMW MW
MW
MWMW
Hz
kV
-
7/22/2019 Power Management System by ABB
26/40
ABB
AS
-26
ABB
Display Accumulated LoadShed table
-
7/22/2019 Power Management System by ABB
27/40
ABB
AS
-27
ABB
Functionality IndustrialITfor PMS
Load Shedding
Active and Reactive Power Control
Minimum
Excitation
Rotor Instability Line
Operating
Minimum
Turbine Maximum
P
Q-LagQ-Lead
Maximum Excitation
(Rotor Heating)
MVA-circle
(Stator Heating)
Minimum
PF-Leading
MinimumPF-lagging
Display Generator Capability Diagram
-
7/22/2019 Power Management System by ABB
28/40
ABB
AS
-28
ABB
-
7/22/2019 Power Management System by ABB
29/40
AB
B
AS
-29
ABB
Turbine Control
Primary Turbine Controller
Droop or isochronous
PMS provides:
Manual control (Droop)
Manual MW setpoint
Automatic frequency control
Automatic setpoint control
(MW sharing)
Automatic mode change:
CB trip
Turbine trip etc.
-
7/22/2019 Power Management System by ABB
30/40
AB
B
AS
-30
ABB
Generator Control
Primary AVR:
Droop or voltage control
PMS provides:
Manual control (Droop)
Manual setpoint control
(setpoint is PF)
Automatic Voltage Control
(AVR receives raise/lower
from PMS)
Automatic setpoint control(MVar sharing)
Automatic mode change:
CB trip
-
7/22/2019 Power Management System by ABB
31/40
AB
B
AS
-31
ABB
P
Q-LagQ-Lead
Active and Reactive Power Control
In island operation:
Maintain system frequency
Maintain system voltage
Connected to grid:
Control active power exchange
Control re-active power exchange
Share active and reactive power amongst the machines
Participation factors
Efficient Power Generation optimization
Spinning Reserve optimization
Standby optimization
NOx constraints
Objectives
Coordinated control of power generation
Achieve stable operation
-
7/22/2019 Power Management System by ABB
32/40
AB
B
AS
-32
ABB
Generator Control
2.2 1.8 1.8 2.13.3
2.50.1
1.57.2
5.7
MW MWMW MW
MW
MW
MW
Hz
kV
3.3
50.02.20.9
0.9
20.0
120.0
3.3
50.0
2.20.9
0.9
20.0
120.01.61.6
-
7/22/2019 Power Management System by ABB
33/40
AB
B
AS
-33
ABB
Measuring of U,I,E,calculation of P & Q
Monitoring & Control
Interlockings
Alarm annunciation
Event Time Tagging
Disturbance Recording
Local storage of trip-events
Communication to PMS
Integration with Protection & Control Units
Protection
-
7/22/2019 Power Management System by ABB
34/40
AB
B
AS
-34
ABB
Automatic Synchronisation
Manual Synchronisation Adjust voltage magnitude
Adjust voltage frequency
Adjust voltage angle
Rough adjustments by PMS
Fine tuning by a Synchroniser
Close the breaker by the Synchoniser
Synchronisation
-
7/22/2019 Power Management System by ABB
35/40
AB
B
AS
-36
ABB
Customers needs
Reliable Electrical Power.
Stable operation to avoid blackouts.
ABBs response
Power Management system including
Load Sheding system based ondynamic fast loadbalance
Power Control.
Customers benefits
No more blackouts due to trip chain of
own generation units.
Reduced consumption electrical power
from utility company due to better in-
house generation control.
N+1 purpose.
Industrial plants / complexes / platforms
-
7/22/2019 Power Management System by ABB
36/40
AB
B
AS
-37
ABB
QatarGas II LNG
Customers needs
Experienced PMS supplier to be able to cope
with new concept for LNG Compressor drivessystems
ABBs response
Intelligent Power Management System
controlling:3* STGs (each 44 MW)
1* GTG (33 MW)
6* VFD/GTG (each 45 MW)
including:
* NOx constrains considerations
* Power flow limitations to QG 1 and QG 3 & 4
* Contingency Load Shedding.
Customers benefits
Reliable operation and
avoiding black-outs.
-
7/22/2019 Power Management System by ABB
37/40
AB
B
AS
-38
ABB
Malaysia MLNG, Petronas/Shell
Customers needs
Extension of Power Distribution System with
100 MW to 300 MW for two extra LNG trains
ABBs response
Intelligent Power Management System including
Load Shedding and Power Control
Is-limiters between the three 33 kV substations
(triangle configuration)
Customers benefits
No need for a 132 kV substation including six
132/33 kV Power Transformers
Reliable operation and avoiding black-outs.
ABB
bv-60
-
7/22/2019 Power Management System by ABB
38/40
AB
B
AS
-39
ABB
Named Project References
HAR, refinery in Greece
Shell Pernis refinery in the Netherlands
Shell BLNG in Brunei
Shell PDO in Oman
ThaiOil, ThaiLube, RRC refineries in Thailand
La Roche, CHP inUK
Petrobras: REPAR, REDUC, RLAM refineries in Brazil
Reliance: Hazira, Jamnagar & Haldia refineries in India
AFPC, Omar refinery in Syria
ABF, Petronas MLNG Satu, Dua & Tiga in Malaysia
StatOil Gullfaks, LNG Hammersfest & BP Amoco Valhall
QatarGas II, III & IV, PS2 & PS3 in Qatar
http://presentation%20in%20c/OVERHEAD/Displays-ThaiOil.ppthttp://presentation%20in%20c/OVERHEAD/Displays-Jamnagar.ppthttp://presentation%20in%20c/OVERHEAD/Displays-Jamnagar.ppthttp://presentation%20in%20c/OVERHEAD/Displays-ThaiOil.ppt -
7/22/2019 Power Management System by ABB
39/40
AB
B
AS
-40
ABB
Named Customer References
-
7/22/2019 Power Management System by ABB
40/40
B
B
AS
-41
ABBM i t i i d P F t
The total accumulated switched-off
shortcurrents by a circuitbreaker or
the number of generator starts
t i f i tN d f bi i i f i i t
Power Control, Standby Optimization,
n+1 Criteria, SCADA, etc. are performed by
th t d t b th t
The Human Machine Interfaces for all the
electrical sub-systems can be integrated in
th E M t S t
Serial interfaces with protection & control
it id h tti i i & bl d t
A B B T r a n s m i t O y
N e t w o r k P a r t n e r
FEEDER TERMINAL REF541A B B N e t w o r k P a r t n e r
Uaux = 80...265Vdc/ac
fn =50Hz
In = 1/5 A (I)
1MRS xxxxxx
98150Un = 100/110 V (U)
Uon = 100/110 V (Uo)
Ion = 1/5 A (Io)
9509
ABB PMS allows you to:
Avoid black-outs (up to 500 kUSD / hour) Power control including voltage control, frequency control, sharing power
among generators and tie-line(s). High Speed Contingency Load Shedding (< 100 ms.)
Reduce electricity costs Peak-shaving
Re-active Power Control & Sharing
In case of a shortage of electrical power,
secure the available power to critical loads
by switching off the none important loads
di t d i l d t bl
?
Limit electrical import during peak time and
d k b d h
Minimize operational costs
Decreased number of operators
Event driven maintenance
Single Window concept
Transformer Overload Management
In case of a shortage of electrical power,
secure the available power to critical loads
by switching off the none important loads
di t d i l d t bl
?
Optimizing the stability of the operation of
the electrical generation- and distribution
t k f l t
Minimized cabling and engineering
Optimized network design
Reduce investment costs