power grid corporation of india ltd

36
POWER GRID CORPORATION POWER GRID CORPORATION OF INDIA LTD. OF INDIA LTD. SRLDC,BANGALORE

Upload: kathleen-tanner

Post on 03-Jan-2016

33 views

Category:

Documents


7 download

DESCRIPTION

POWER GRID CORPORATION OF INDIA LTD. SRLDC,BANGALORE. EXCERPTS FROM CERC ORDER DATED 26.06.2002. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: POWER GRID CORPORATION OF INDIA LTD

POWER GRID CORPORATION POWER GRID CORPORATION OF INDIA LTD.OF INDIA LTD.

SRLDC,BANGALORE

Page 2: POWER GRID CORPORATION OF INDIA LTD

EXCERPTS FROM CERC ORDER EXCERPTS FROM CERC ORDER DATED 26.06.2002DATED 26.06.2002

““In the interest of security and safety of the In the interest of security and safety of the regional grid, we, therefore, feel that some regional grid, we, therefore, feel that some parts of the States indulging in overdrawals parts of the States indulging in overdrawals have to be isolated/islanded and supplied have to be isolated/islanded and supplied from the State's own resources at whatever from the State's own resources at whatever frequency they want to operate at the risk frequency they want to operate at the risk of their own machinery & equipment; but of their own machinery & equipment; but not through the Inter-State Transmission not through the Inter-State Transmission System or Inter-State Generation System.”System or Inter-State Generation System.”

Page 3: POWER GRID CORPORATION OF INDIA LTD

EXCERPTS FROM CERC ORDER EXCERPTS FROM CERC ORDER DATED 26.06.2002DATED 26.06.2002

““We, therefore, consider that a We, therefore, consider that a Committee ……… may go into the Committee ……… may go into the technicaltechnical and and commercial commercial aspects of aspects of isolating/islanding some parts of the isolating/islanding some parts of the system, without damage to thesystem, without damage to the Regional grid, in detail .”Regional grid, in detail .”VIEW THE

ORDERVIEW THE

ORDER

Page 4: POWER GRID CORPORATION OF INDIA LTD

SECTION 55ELECTRICITY (SUPPLY) ACT, 1948

AMENDED 1998

2) The Regional Load Despatch Centre shall give the apex body to ensure integrated operation of the power system in the concerned region.

3) The Regional Load Despatch Centre may give such directions and exercise such supervision and control as may be required for ensuring integrated grid operation and for achieving the maximum economy and efficiency in the operation of the power system in that state

Page 5: POWER GRID CORPORATION OF INDIA LTD

IEGC-Chapter - 3 Clause - 3.5IEGC-Chapter - 3 Clause - 3.5 (i)(i) As a general rule, the ISTS shall be As a general rule, the ISTS shall be

capable of withstanding and be secured against capable of withstanding and be secured against the following contingency outages without the following contingency outages without necessitating load shedding or rescheduling of necessitating load shedding or rescheduling of generation during Steady State Operation :-generation during Steady State Operation :-

Outage of a 132 kV D/C line orOutage of a 132 kV D/C line or Outage of a 220 kV D/C line or,Outage of a 220 kV D/C line or, - Outage of a 400 kV S/C line or,- Outage of a 400 kV S/C line or, - Outage of single Interconnecting Transformer, - Outage of single Interconnecting Transformer,

oror - Outage of one pole of HVDC Bipole line, or- Outage of one pole of HVDC Bipole line, or - Outage of 765 kV S/C line.- Outage of 765 kV S/C line.

Page 6: POWER GRID CORPORATION OF INDIA LTD

a ) All Regional constituents shall endeavor to

operate their respective power systems and

Power Stations in synchronism with each

other at all times, such that the entire system

within a Region operates as one synchronised

system.

IEGC-Chapter - 6 Clause - 6.2

System Security Aspects:

Page 7: POWER GRID CORPORATION OF INDIA LTD

b) No part of the grid shall be deliberately isolated from the rest of the

Regional Grid, except

(I) under an emergency, and conditions in which such isolation would

prevent a total grid collapse and/or enable early restoration of power

supply

(II) when serious damage to a costly equipment is imminent and such

isolation would prevent it

(III) when such isolation is specifically instructed by RLDC. Complete

synchronisation of grid shall be restored as soon as the conditions again

permit it. The restoration process shall be supervised by RLDC, as per

operating procedures separately formulated.

IEGC-Chapter - 6 Clause - 6.2

System Security Aspects:

Page 8: POWER GRID CORPORATION OF INDIA LTD

IEGC Chapter - 6 Clause - 6.2

C ) No important element of the Regional grid shall be

deliberately opened or removed from service at any time, except

when specifically instructed by RLDC or with specific and prior

clearance of RLDC. The list of such important grid elements on

which the above stipulations apply shall be prepared by the

RLDC in consultation with the constituents, and be available at

RLDC/SLDCs. In case of opening/ removal of any important

element of the grid under an emergency situation, the same shall

be communicated to RLDC at the earliest possible time after the

event.

Page 9: POWER GRID CORPORATION OF INDIA LTD

EXCERPTS FROM MANUAL ON EXCERPTS FROM MANUAL ON TRANSMISSION PLANNING TRANSMISSION PLANNING

CRITERIA - CEACRITERIA - CEA 2. PLANNING PHILOSOPHY & 2. PLANNING PHILOSOPHY &

GENERAL GUIDELINES GENERAL GUIDELINES 2.1 The transmission system shall be 2.1 The transmission system shall be

planned on the basis of regional self- planned on the basis of regional self- sufficiency with an ultimate objective sufficiency with an ultimate objective of evolving a National Power Grid. of evolving a National Power Grid.

Page 10: POWER GRID CORPORATION OF INDIA LTD

GENERAL ISSUESGENERAL ISSUES

MODUS OPERANDI-MODUS OPERANDI- INITIATION OF THE SCHEME AND INITIATION OF THE SCHEME AND

NORMALISATIONNORMALISATION YARDSTICK FOR INITIATING YARDSTICK FOR INITIATING

ISOLATION/ISLANDINGISOLATION/ISLANDING HOW LONG SHOULD SUCH ISOLATION LAST?HOW LONG SHOULD SUCH ISOLATION LAST? SYSTEM CONSTRAINTS?SYSTEM CONSTRAINTS? WHO DECIDES?WHO DECIDES?

Page 11: POWER GRID CORPORATION OF INDIA LTD

GENERAL ISSUES CONTD…..GENERAL ISSUES CONTD…..

MODUS OPERANDI-MODUS OPERANDI- LOAD CONTROL /SWITCHING TO BE LOAD CONTROL /SWITCHING TO BE

DONE BY STATE SYSTEM – LOGISTICS?DONE BY STATE SYSTEM – LOGISTICS? WHO DECIDES WHAT LOADS ARE TO BE WHO DECIDES WHAT LOADS ARE TO BE

ADDED/REMOVED?ADDED/REMOVED? VARIATIONS OF LOAD INVOLVES MANY VARIATIONS OF LOAD INVOLVES MANY

SWITCHING OPERATIONS – WHO WILL CO-SWITCHING OPERATIONS – WHO WILL CO-ORDINATE THE SAME?ORDINATE THE SAME?

INNUMERABLE HYPOTHETICAL INNUMERABLE HYPOTHETICAL COMBINATIONS POSSIBLE FOR ISLANDINGCOMBINATIONS POSSIBLE FOR ISLANDING

Page 12: POWER GRID CORPORATION OF INDIA LTD

GENERAL ISSUES CONTD….GENERAL ISSUES CONTD….

MODUS OPERANDI-MODUS OPERANDI- CONCURRENT APPLICABILITY TO CONCURRENT APPLICABILITY TO

OTHERS SYSTEMS?OTHERS SYSTEMS? IN CASE OF OVERDRAWALS BY TWO OR IN CASE OF OVERDRAWALS BY TWO OR

THREE CONSTITUENTS AT LOW FREQUENCY-THREE CONSTITUENTS AT LOW FREQUENCY-WOULD THE SCHEME BE APPLIED WOULD THE SCHEME BE APPLIED SIMULTANEOUSLY?SIMULTANEOUSLY?

THIS WOULD REQUIRE CO-ORDINATION OF THIS WOULD REQUIRE CO-ORDINATION OF MANY SWITCHING OPERATIONS.MANY SWITCHING OPERATIONS.

Page 13: POWER GRID CORPORATION OF INDIA LTD

ISOLATION OF GRIDISOLATION OF GRIDISSUES INVOLVED ISSUES INVOLVED

OPERATION ISSUESOPERATION ISSUES SCHEDULING ISSUESSCHEDULING ISSUES PROTECTION ISSUESPROTECTION ISSUES COMMERCIAL ISSUESCOMMERCIAL ISSUES STABILITY ISSUESSTABILITY ISSUES

SHORT CIRCUIT LEVELSSHORT CIRCUIT LEVELS L-INDEXL-INDEX – VOLTAGE STABILITY – VOLTAGE STABILITY ANGULAR STABILITYANGULAR STABILITY

REPORT OF HIGH COURTAPPOINTED COMMITTEE

Page 14: POWER GRID CORPORATION OF INDIA LTD

OPERATIONAL ISSUESOPERATIONAL ISSUES

A PART OF LOAD(400-3000MW SAY) A PART OF LOAD(400-3000MW SAY) ISOLATED.ISOLATED. STABILITY ISSUESSTABILITY ISSUES LOWER SHORT CIRCUIT LEVELSLOWER SHORT CIRCUIT LEVELS IN BOTH IN BOTH

PARTS LEADING TO VOLTAGE PARTS LEADING TO VOLTAGE EXCURSIONSEXCURSIONS

LOWER INERTIALOWER INERTIA - LEADING TO - LEADING TO FREQUENCY EXCURSIONSFREQUENCY EXCURSIONS

.............CONTD.............CONTD

47.7

HZ

51.5

HZ

Page 15: POWER GRID CORPORATION OF INDIA LTD

OPERATIONAL ISSUESOPERATIONAL ISSUES

OPERATIONAL FLEXIBILITY LOSTOPERATIONAL FLEXIBILITY LOST DIVERSITY WILL REMAIN UNUTILISEDDIVERSITY WILL REMAIN UNUTILISED TRANSITION BETWEEN PEAK AND OFF-PEAK - TRANSITION BETWEEN PEAK AND OFF-PEAK -

DIFFICULT TO MANAGEDIFFICULT TO MANAGE LINE LOADINGS – A PROBLEM DURING LOAD LINE LOADINGS – A PROBLEM DURING LOAD

CHANGE OVER IN AP – HYDRO FLEXIBILITY CHANGE OVER IN AP – HYDRO FLEXIBILITY UNAVAILABLEUNAVAILABLE

FREQUENCY RISE DIFFICULT TO CONTAIN IN FREQUENCY RISE DIFFICULT TO CONTAIN IN BOTH BLOCKSBOTH BLOCKS

PREDOMINANT THERMAL – LOWER INERTIAPREDOMINANT THERMAL – LOWER INERTIA Df/dt WILL BE SHARPDf/dt WILL BE SHARP VOLTAGE AND FREQUENCY EXCURSIONS –VOLTAGE AND FREQUENCY EXCURSIONS –

EXTREMEEXTREME COMPLEXITY INVOLVED IN SWITCHINGCOMPLEXITY INVOLVED IN SWITCHING

Page 16: POWER GRID CORPORATION OF INDIA LTD

PROTECTION ISSUESPROTECTION ISSUES

DRASTIC REDUCTION IN SC DRASTIC REDUCTION IN SC LEVELS- OCR SETTINGS?LEVELS- OCR SETTINGS?

FREQUENCY AND VOLTAGE FREQUENCY AND VOLTAGE EXCURSIONS- v/f SETTINGS?EXCURSIONS- v/f SETTINGS?

LOAD ENCROACHMENT LOAD ENCROACHMENT PROBLEMS – LOW VOLTAGE - PROBLEMS – LOW VOLTAGE - LOADINGLOADING

POWER SWINGPOWER SWING

Page 17: POWER GRID CORPORATION OF INDIA LTD

ISSUES TO BE EXAMINED FOR ISOLATIONISSUES TO BE EXAMINED FOR ISOLATION

SCHEDULING PROBLEMS-SCHEDULING PROBLEMS- CONTRACTION/EXPANSION OF ISLAND TO CONTRACTION/EXPANSION OF ISLAND TO

BE DONE WITH CHANGING SCHEDULESBE DONE WITH CHANGING SCHEDULES COMPLEXITY INVOLVED IN SWITCHINGCOMPLEXITY INVOLVED IN SWITCHING FORCED OVERDRAWALS – A QUANDRARY FORCED OVERDRAWALS – A QUANDRARY

THAT MAY BE UNAVOIDABLETHAT MAY BE UNAVOIDABLE STATE SYSTEM – INABILITY TO DRAW STATE SYSTEM – INABILITY TO DRAW

ENTITLEMENTENTITLEMENT LOAD MANAGEMENT/SWITCHING LOAD MANAGEMENT/SWITCHING

OPERATION – STILL IN STATE PURVIEWOPERATION – STILL IN STATE PURVIEW

Page 18: POWER GRID CORPORATION OF INDIA LTD

ISSUES TO BE EXAMINED FOR ISOLATION ISSUES TO BE EXAMINED FOR ISOLATION CONTD....CONTD....

SCHEDULING PROBLEMS-SCHEDULING PROBLEMS- DRAWAL PATTERN VARIATION –:(MIN/MAX IN %)DRAWAL PATTERN VARIATION –:(MIN/MAX IN %)

CONTRACTION AND EXPANSION OF CONTRACTION AND EXPANSION OF ISLANDISLAND

COMMERCIAL IMPLICATION- OD/UDCOMMERCIAL IMPLICATION- OD/UD

STATE SYSTEMSTATE SYSTEM MIN/MAX IN %MIN/MAX IN %

ANDHRAPRADESHANDHRAPRADESH 75-85%75-85%

KARNATAKAKARNATAKA 55-65%55-65%

KERALAKERALA 55-60%55-60%

TAMILNADUTAMILNADU 80-85%80-85%

3D LOAD

PROFILE

3D LOAD

PROFILE

Page 19: POWER GRID CORPORATION OF INDIA LTD

COMMERCIAL ISSUESCOMMERCIAL ISSUES

INABILITY TO DRAW AS PER INABILITY TO DRAW AS PER ENTITLEMENT DUE TO INSUFFICIENT ENTITLEMENT DUE TO INSUFFICIENT LOAD IN ISGS/ISTS BLOCK :-LOAD IN ISGS/ISTS BLOCK :- STATE MAY BE FORCED TO UNDERDRAW STATE MAY BE FORCED TO UNDERDRAW

FROM ISGS AND FORCED TO GENERATE FROM ISGS AND FORCED TO GENERATE AT COSTLY IPP’S/DEPLETED HYDRO – AT COSTLY IPP’S/DEPLETED HYDRO – COMMERCIAL IMPLICATION?.COMMERCIAL IMPLICATION?.

OVERDRAWAL MAY CONTINUE OVERDRAWAL MAY CONTINUE FORCING OTHER CONSTITUENTS TO FORCING OTHER CONSTITUENTS TO COMMIT COSTLY GENERATIONCOMMIT COSTLY GENERATION

Page 20: POWER GRID CORPORATION OF INDIA LTD

SHORT CIRCUIT LEVELS – SHORT CIRCUIT LEVELS – RELEVANCE TO GRID RELEVANCE TO GRID

OPERATIONOPERATION SC LEVELS ARE AN INDICATOR OF THE SC LEVELS ARE AN INDICATOR OF THE ‘STRENGTH’ OF THE BUS TO REACTIVE ‘STRENGTH’ OF THE BUS TO REACTIVE POWER FLUCTUATIONSPOWER FLUCTUATIONS

HIGHER SC LEVELS – BUS IS MORE HIGHER SC LEVELS – BUS IS MORE STABLE – LIMITS VOLTAGE STABLE – LIMITS VOLTAGE EXCURSIONSEXCURSIONS

HIGHER SC LEVELS- BUS IS WELL HIGHER SC LEVELS- BUS IS WELL INTERCONNECTED-PROXIMITY OF INTERCONNECTED-PROXIMITY OF GENERATORSGENERATORS

ESPECIALLY IMPORTANT DURING ESPECIALLY IMPORTANT DURING RESTORATION.RESTORATION.

Page 21: POWER GRID CORPORATION OF INDIA LTD

SHORT CIRCUIT LEVELS – SHORT CIRCUIT LEVELS – RELEVANCE TO GRID RELEVANCE TO GRID

OPERATIONOPERATION AN EXAMPLE:-AN EXAMPLE:-

CHARGING A 300 KM LINE FROM A 2000 CHARGING A 300 KM LINE FROM A 2000 MVA 400 KV BUS WOULD INCREASE THE MVA 400 KV BUS WOULD INCREASE THE VOLTAGE BY 33 KVVOLTAGE BY 33 KV

CHARGING A 300 KM LINE FROM A 6000 CHARGING A 300 KM LINE FROM A 6000 MVA 400 KV BUS WOULD INCREASE THE MVA 400 KV BUS WOULD INCREASE THE VOLTAGE BY 11 KVVOLTAGE BY 11 KV

SHRT CKT STUDYRESULT

Page 22: POWER GRID CORPORATION OF INDIA LTD

L INDEXL INDEX INDICATES THE PROXIMITY TO VOLTAGE INDICATES THE PROXIMITY TO VOLTAGE

COLLAPSECOLLAPSE IF THE INDEX APPROACHES 1 THEN THE BUS IF THE INDEX APPROACHES 1 THEN THE BUS

IS INCREASINGLY VULNERABLE TO VOLTAGE IS INCREASINGLY VULNERABLE TO VOLTAGE COLLAPSECOLLAPSE

DERIVED FROM LOAD FLOW JACOBIAN DERIVED FROM LOAD FLOW JACOBIAN MATRIXMATRIX

SHOULD BE GENERALLY WITHIN 0.3 DURING SHOULD BE GENERALLY WITHIN 0.3 DURING NORMAL OPERATION FOR SR GRID.NORMAL OPERATION FOR SR GRID.

GENERALLY IN LINE WITH WHAT IS GENERALLY IN LINE WITH WHAT IS OBSERVED BY THE SYSTEM OPERATORSOBSERVED BY THE SYSTEM OPERATORS

L INDEX STUDYRESULT

L INDEX STUDY400 KV SUMMARY

Page 23: POWER GRID CORPORATION OF INDIA LTD

GOOTY 0.3126 AP

CUDDAPAH 0.268 AP

HYDERABAD 0.236 AP

KHAMMAN 0.1794 AP

NUNNA 0.1693 AP

RAMAGUNDAM 0.1197 AP

SIMHADRI 0.1177 AP

BANGALORE 0.3431 KAR

HOODY 0.3175 KAR

NELAMANGALA 0.3101 KAR

KOLAR 0.3043 KAR

DAVANGERE 0.2157 KAR

MUNIRABAD 0.1721 KAR

RAICHUR 0.0804 KAR

TRICHUR 0.2262 KER

HOSUR 0.2539 TN

SALEM 0.2011 TN

L INDEXL INDEX

Page 24: POWER GRID CORPORATION OF INDIA LTD
Page 25: POWER GRID CORPORATION OF INDIA LTD

KER TN

KAR AP

ISGS

SCIENTIFIC SETTLEMENT

SYSTEM?

Page 26: POWER GRID CORPORATION OF INDIA LTD
Page 27: POWER GRID CORPORATION OF INDIA LTD

LINKSLINKSSR GRID MAP KAR ISL CASE3 TN ISL CASE1 AP GRID MAP

KARNATAKAGRID MAP

KERALAGRID MAP

TN GRID MAPSHORT CKT STDYRESULTS 400 KV

L INDEX STUDY RESULTS

3D DEMAND SRJUNE 2002

3D DEMAND SRMAY2002

3D DEMAND SRMARCH 2002

SHORT CKT STDYRESULTS 220 KV

SHORT CKT STDYRESULTS 230 KV

Page 28: POWER GRID CORPORATION OF INDIA LTD

ISOLATION OF PART OF ISOLATION OF PART OF KARNATAKA: CASE STUDYKARNATAKA: CASE STUDY

CASE 1: SOMANAHALLY TRANSFORMER CASE 1: SOMANAHALLY TRANSFORMER CONNECTED TO AP-TN-KER GRID AND CONNECTED TO AP-TN-KER GRID AND RADIALLY FEEDING 700MW LOAD, KAIGA RADIALLY FEEDING 700MW LOAD, KAIGA EMBEDDED IN KARNATAKA SYSTEM.400 KV EMBEDDED IN KARNATAKA SYSTEM.400 KV RTPS-N’SAGAR OPENRTPS-N’SAGAR OPEN

CASE 2: CASE 1 WITH KAIGA ISLANDEDCASE 2: CASE 1 WITH KAIGA ISLANDED CASE 3: SPLIT BUS AT RTPS, KAIGA & CASE 3: SPLIT BUS AT RTPS, KAIGA &

400KV UNITS OF RAICHUR WITH AP-KER-400KV UNITS OF RAICHUR WITH AP-KER-TN-KOLAR-SOMANAHALLI-HOODY-GUTTUR TN-KOLAR-SOMANAHALLI-HOODY-GUTTUR SYSTEM. SOMANAHALLY AND HOODY SYSTEM. SOMANAHALLY AND HOODY RADIALLY FEEDING BANGALORE LOADS RADIALLY FEEDING BANGALORE LOADS EXCEPT PEENYA. EXCEPT PEENYA.

GRID

MAP

GRID

MAP

Page 29: POWER GRID CORPORATION OF INDIA LTD

LOAD 3000 MW

LOW VOLTAGE

ZONE

ABOUT 700 MW ON AP-

TN-KER GRID

CASE 1 BANGALORE LOADS ON AP-TN-KER GRID

Page 30: POWER GRID CORPORATION OF INDIA LTD

ISLANDING IN KARNATAKA SYSTEM KARNATAKA

STN_NAME STATE BASE CASE CASE1 CASE2 CASE3

RST4 AP 8760 8378 8371 8194

TPL4 AP 6768 5926 5916 5697

CNP4 AP 5055 4782 4776 4747

GTN4 AP 2936 3027 3018 2789

KOLAR4 KAR 6479 5362 5358 5868

RTPS4 KAR 5859 3962 3692 3149

SOMN4 KAR 5540 4394 4390 4850

HOODY4 KAR 5536 1522 1305 4911

NLMNG4 KAR 4818 1656 1423 3979

DVGRE4 KAR 4349 2545 2120 2890

GDHL4 KAR 3767 2777 2546 2330

KARNATAKA-SC LEVELS IN MVAKARNATAKA-SC LEVELS IN MVA

Page 31: POWER GRID CORPORATION OF INDIA LTD

ISOLATION OF PART OF ISOLATION OF PART OF KERALA AND TAMILNADU: KERALA AND TAMILNADU:

CASE STUDYCASE STUDY TAMILNADU : TTPS, BALAJI TAMILNADU : TTPS, BALAJI

POWER,WIND, NILAGIRIS HYDRO, POWER,WIND, NILAGIRIS HYDRO, KADAMPARAI HYDRO IN ISOLATED KADAMPARAI HYDRO IN ISOLATED PORTION. PORTION. AP-KAR-KER AND AP-KAR-KER AND N.TAMILNADU(NEYVELI-MAPS-ETS-N.TAMILNADU(NEYVELI-MAPS-ETS-NMTPS-MTPS – GMR) IN ONE BLOCKNMTPS-MTPS – GMR) IN ONE BLOCK

KERALA- SPLIT BUS AT EDAMON AND KERALA- SPLIT BUS AT EDAMON AND THRISSUR WITH LOADS TAKEN THRISSUR WITH LOADS TAKEN RADIALLY AT BOTH POINTSRADIALLY AT BOTH POINTS

Page 32: POWER GRID CORPORATION OF INDIA LTD

TAMILNADU AND KERALA SC LEVELS IN MVATAMILNADU AND KERALA SC LEVELS IN MVA      KERALA TN

STN_NAME STATE BASE CASE CASE1 CASE1

RST4 AP 8760 8740 8725

CNP4 AP 5055 5014 4987

SOMN4 KAR 5540 5441 5312

KOLAR4 KAR 6479 6537 6526

TRICH4 KER 3838 2724 3239

N2MIN4 TN 10556 10128 9828

NLYEU4 TN 10223 9818 9537

SALEM4 TN 8119 7639 6523

SPBUDUR4 TN 7011 6923 6895

TRICHY4 TN 6661 6266 5654

MADURAI4 TN 5755 5251 4094

HOSUR4 TN 5474 5346 5277

UDMLPT4 TN 5433 4363 4032

Page 33: POWER GRID CORPORATION OF INDIA LTD

OPERATIONAL ISSUESOPERATIONAL ISSUES KARNATAKAKARNATAKA

KAIGA REMAINS EMBEDDED IN ISOLATED KAIGA REMAINS EMBEDDED IN ISOLATED PORTION OF KARNATAKAPORTION OF KARNATAKA FREQUENT HOUSE LOADING AND POISONING FREQUENT HOUSE LOADING AND POISONING

OUT - EXPECTED.OUT - EXPECTED. KAPS TO REDUCE GENERATION BY 40-50 MW KAPS TO REDUCE GENERATION BY 40-50 MW

TO PREVENT HUNTINGTO PREVENT HUNTING DEPLETED HYDRO POSITION IN ISOLATED DEPLETED HYDRO POSITION IN ISOLATED

PART:PART: PEAKING HYDRO TO BE RUN AS BASE STATION PEAKING HYDRO TO BE RUN AS BASE STATION STORAGE POSITION ALREADY CRITICALSTORAGE POSITION ALREADY CRITICAL EXTREMELY LOW VOLTAGES TO BE EXPECTED EXTREMELY LOW VOLTAGES TO BE EXPECTED

IN SOUTH KARNATAKA.IN SOUTH KARNATAKA.

Page 34: POWER GRID CORPORATION OF INDIA LTD

DELIVERING CGS ENTITLEMENT TO DELIVERING CGS ENTITLEMENT TO KARNATAKAKARNATAKA

KPTCL’S CGS ENTITLEMENT WITH FULL KPTCL’S CGS ENTITLEMENT WITH FULL GENERATION AT NTPC,NLY,KAPS AND ONE GENERATION AT NTPC,NLY,KAPS AND ONE UNIT AT MAPS IS AND WITH ALLOCATION OF UNIT AT MAPS IS AND WITH ALLOCATION OF 156 MW ER AND 100 MW PTC POWER 156 MW ER AND 100 MW PTC POWER = = 1206 MW1206 MW

GOA’S ENTITLEMENT TO BE WHEELED BY GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL KPTCL = 94 MW.= 94 MW.

TOTAL ENTITLEMENT OF KPTCL TOTAL ENTITLEMENT OF KPTCL = 1310 MW= 1310 MW AS AS KAIGAKAIGA GENERATION OF GENERATION OF 400 MW400 MW IS IS

EMBEDDEDEMBEDDED KPTCL HAS TO IMPORT 9 KPTCL HAS TO IMPORT 910 10 MWMW

AT AT 330 KV/400 MVAR330 KV/400 MVAR IMPORT THE IMPORT THE CAPACITY OF SOMANAHALLI TRANSFORMER CAPACITY OF SOMANAHALLI TRANSFORMER IS IS 720 MW720 MW

Page 35: POWER GRID CORPORATION OF INDIA LTD

DELIVERING CGS ENTITLEMENT TO DELIVERING CGS ENTITLEMENT TO KARNATAKAKARNATAKA

KPTCL’S CGS ENTITLEMENT WITH FULL KPTCL’S CGS ENTITLEMENT WITH FULL GENERATION AT NTPC,NLY, ONE UNIT AT KAPS GENERATION AT NTPC,NLY, ONE UNIT AT KAPS AND MAPS IS AND WITH ALLOCATION OF 156 AND MAPS IS AND WITH ALLOCATION OF 156 MW ER AND 100 MW PTC POWER = MW ER AND 100 MW PTC POWER = 1140 MW1140 MW

GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL = 94 MW= 94 MW..

TOTAL ENTITLEMENT OF KPTCL TOTAL ENTITLEMENT OF KPTCL = 1234 MW= 1234 MW ASAS KAIGA KAIGA GENERATION OF GENERATION OF 200 MW200 MW IS IS

EMBEDDED KPTCL HAS TO IMPORT EMBEDDED KPTCL HAS TO IMPORT 1034 MW1034 MW AT AT 330 KV/400 MVAR330 KV/400 MVAR IMPORT THE CAPACITY IMPORT THE CAPACITY

OF SOMANAHALLI TRANSFORMER IS OF SOMANAHALLI TRANSFORMER IS 720 MW720 MW DIFFICULTY IN DELIVERING ENTITLEMENTDIFFICULTY IN DELIVERING ENTITLEMENT LOADS AT SOMANAHALLI TO BE LOADS AT SOMANAHALLI TO BE

REARRANGED DEPENDING ON KAPS REARRANGED DEPENDING ON KAPS GENERATIONGENERATION

Page 36: POWER GRID CORPORATION OF INDIA LTD