power grid corporation of india ltd
DESCRIPTION
POWER GRID CORPORATION OF INDIA LTD. SRLDC,BANGALORE. EXCERPTS FROM CERC ORDER DATED 26.06.2002. - PowerPoint PPT PresentationTRANSCRIPT
POWER GRID CORPORATION POWER GRID CORPORATION OF INDIA LTD.OF INDIA LTD.
SRLDC,BANGALORE
EXCERPTS FROM CERC ORDER EXCERPTS FROM CERC ORDER DATED 26.06.2002DATED 26.06.2002
““In the interest of security and safety of the In the interest of security and safety of the regional grid, we, therefore, feel that some regional grid, we, therefore, feel that some parts of the States indulging in overdrawals parts of the States indulging in overdrawals have to be isolated/islanded and supplied have to be isolated/islanded and supplied from the State's own resources at whatever from the State's own resources at whatever frequency they want to operate at the risk frequency they want to operate at the risk of their own machinery & equipment; but of their own machinery & equipment; but not through the Inter-State Transmission not through the Inter-State Transmission System or Inter-State Generation System.”System or Inter-State Generation System.”
EXCERPTS FROM CERC ORDER EXCERPTS FROM CERC ORDER DATED 26.06.2002DATED 26.06.2002
““We, therefore, consider that a We, therefore, consider that a Committee ……… may go into the Committee ……… may go into the technicaltechnical and and commercial commercial aspects of aspects of isolating/islanding some parts of the isolating/islanding some parts of the system, without damage to thesystem, without damage to the Regional grid, in detail .”Regional grid, in detail .”VIEW THE
ORDERVIEW THE
ORDER
SECTION 55ELECTRICITY (SUPPLY) ACT, 1948
AMENDED 1998
2) The Regional Load Despatch Centre shall give the apex body to ensure integrated operation of the power system in the concerned region.
3) The Regional Load Despatch Centre may give such directions and exercise such supervision and control as may be required for ensuring integrated grid operation and for achieving the maximum economy and efficiency in the operation of the power system in that state
IEGC-Chapter - 3 Clause - 3.5IEGC-Chapter - 3 Clause - 3.5 (i)(i) As a general rule, the ISTS shall be As a general rule, the ISTS shall be
capable of withstanding and be secured against capable of withstanding and be secured against the following contingency outages without the following contingency outages without necessitating load shedding or rescheduling of necessitating load shedding or rescheduling of generation during Steady State Operation :-generation during Steady State Operation :-
Outage of a 132 kV D/C line orOutage of a 132 kV D/C line or Outage of a 220 kV D/C line or,Outage of a 220 kV D/C line or, - Outage of a 400 kV S/C line or,- Outage of a 400 kV S/C line or, - Outage of single Interconnecting Transformer, - Outage of single Interconnecting Transformer,
oror - Outage of one pole of HVDC Bipole line, or- Outage of one pole of HVDC Bipole line, or - Outage of 765 kV S/C line.- Outage of 765 kV S/C line.
a ) All Regional constituents shall endeavor to
operate their respective power systems and
Power Stations in synchronism with each
other at all times, such that the entire system
within a Region operates as one synchronised
system.
IEGC-Chapter - 6 Clause - 6.2
System Security Aspects:
b) No part of the grid shall be deliberately isolated from the rest of the
Regional Grid, except
(I) under an emergency, and conditions in which such isolation would
prevent a total grid collapse and/or enable early restoration of power
supply
(II) when serious damage to a costly equipment is imminent and such
isolation would prevent it
(III) when such isolation is specifically instructed by RLDC. Complete
synchronisation of grid shall be restored as soon as the conditions again
permit it. The restoration process shall be supervised by RLDC, as per
operating procedures separately formulated.
IEGC-Chapter - 6 Clause - 6.2
System Security Aspects:
IEGC Chapter - 6 Clause - 6.2
C ) No important element of the Regional grid shall be
deliberately opened or removed from service at any time, except
when specifically instructed by RLDC or with specific and prior
clearance of RLDC. The list of such important grid elements on
which the above stipulations apply shall be prepared by the
RLDC in consultation with the constituents, and be available at
RLDC/SLDCs. In case of opening/ removal of any important
element of the grid under an emergency situation, the same shall
be communicated to RLDC at the earliest possible time after the
event.
EXCERPTS FROM MANUAL ON EXCERPTS FROM MANUAL ON TRANSMISSION PLANNING TRANSMISSION PLANNING
CRITERIA - CEACRITERIA - CEA 2. PLANNING PHILOSOPHY & 2. PLANNING PHILOSOPHY &
GENERAL GUIDELINES GENERAL GUIDELINES 2.1 The transmission system shall be 2.1 The transmission system shall be
planned on the basis of regional self- planned on the basis of regional self- sufficiency with an ultimate objective sufficiency with an ultimate objective of evolving a National Power Grid. of evolving a National Power Grid.
GENERAL ISSUESGENERAL ISSUES
MODUS OPERANDI-MODUS OPERANDI- INITIATION OF THE SCHEME AND INITIATION OF THE SCHEME AND
NORMALISATIONNORMALISATION YARDSTICK FOR INITIATING YARDSTICK FOR INITIATING
ISOLATION/ISLANDINGISOLATION/ISLANDING HOW LONG SHOULD SUCH ISOLATION LAST?HOW LONG SHOULD SUCH ISOLATION LAST? SYSTEM CONSTRAINTS?SYSTEM CONSTRAINTS? WHO DECIDES?WHO DECIDES?
GENERAL ISSUES CONTD…..GENERAL ISSUES CONTD…..
MODUS OPERANDI-MODUS OPERANDI- LOAD CONTROL /SWITCHING TO BE LOAD CONTROL /SWITCHING TO BE
DONE BY STATE SYSTEM – LOGISTICS?DONE BY STATE SYSTEM – LOGISTICS? WHO DECIDES WHAT LOADS ARE TO BE WHO DECIDES WHAT LOADS ARE TO BE
ADDED/REMOVED?ADDED/REMOVED? VARIATIONS OF LOAD INVOLVES MANY VARIATIONS OF LOAD INVOLVES MANY
SWITCHING OPERATIONS – WHO WILL CO-SWITCHING OPERATIONS – WHO WILL CO-ORDINATE THE SAME?ORDINATE THE SAME?
INNUMERABLE HYPOTHETICAL INNUMERABLE HYPOTHETICAL COMBINATIONS POSSIBLE FOR ISLANDINGCOMBINATIONS POSSIBLE FOR ISLANDING
GENERAL ISSUES CONTD….GENERAL ISSUES CONTD….
MODUS OPERANDI-MODUS OPERANDI- CONCURRENT APPLICABILITY TO CONCURRENT APPLICABILITY TO
OTHERS SYSTEMS?OTHERS SYSTEMS? IN CASE OF OVERDRAWALS BY TWO OR IN CASE OF OVERDRAWALS BY TWO OR
THREE CONSTITUENTS AT LOW FREQUENCY-THREE CONSTITUENTS AT LOW FREQUENCY-WOULD THE SCHEME BE APPLIED WOULD THE SCHEME BE APPLIED SIMULTANEOUSLY?SIMULTANEOUSLY?
THIS WOULD REQUIRE CO-ORDINATION OF THIS WOULD REQUIRE CO-ORDINATION OF MANY SWITCHING OPERATIONS.MANY SWITCHING OPERATIONS.
ISOLATION OF GRIDISOLATION OF GRIDISSUES INVOLVED ISSUES INVOLVED
OPERATION ISSUESOPERATION ISSUES SCHEDULING ISSUESSCHEDULING ISSUES PROTECTION ISSUESPROTECTION ISSUES COMMERCIAL ISSUESCOMMERCIAL ISSUES STABILITY ISSUESSTABILITY ISSUES
SHORT CIRCUIT LEVELSSHORT CIRCUIT LEVELS L-INDEXL-INDEX – VOLTAGE STABILITY – VOLTAGE STABILITY ANGULAR STABILITYANGULAR STABILITY
REPORT OF HIGH COURTAPPOINTED COMMITTEE
OPERATIONAL ISSUESOPERATIONAL ISSUES
A PART OF LOAD(400-3000MW SAY) A PART OF LOAD(400-3000MW SAY) ISOLATED.ISOLATED. STABILITY ISSUESSTABILITY ISSUES LOWER SHORT CIRCUIT LEVELSLOWER SHORT CIRCUIT LEVELS IN BOTH IN BOTH
PARTS LEADING TO VOLTAGE PARTS LEADING TO VOLTAGE EXCURSIONSEXCURSIONS
LOWER INERTIALOWER INERTIA - LEADING TO - LEADING TO FREQUENCY EXCURSIONSFREQUENCY EXCURSIONS
.............CONTD.............CONTD
47.7
HZ
51.5
HZ
OPERATIONAL ISSUESOPERATIONAL ISSUES
OPERATIONAL FLEXIBILITY LOSTOPERATIONAL FLEXIBILITY LOST DIVERSITY WILL REMAIN UNUTILISEDDIVERSITY WILL REMAIN UNUTILISED TRANSITION BETWEEN PEAK AND OFF-PEAK - TRANSITION BETWEEN PEAK AND OFF-PEAK -
DIFFICULT TO MANAGEDIFFICULT TO MANAGE LINE LOADINGS – A PROBLEM DURING LOAD LINE LOADINGS – A PROBLEM DURING LOAD
CHANGE OVER IN AP – HYDRO FLEXIBILITY CHANGE OVER IN AP – HYDRO FLEXIBILITY UNAVAILABLEUNAVAILABLE
FREQUENCY RISE DIFFICULT TO CONTAIN IN FREQUENCY RISE DIFFICULT TO CONTAIN IN BOTH BLOCKSBOTH BLOCKS
PREDOMINANT THERMAL – LOWER INERTIAPREDOMINANT THERMAL – LOWER INERTIA Df/dt WILL BE SHARPDf/dt WILL BE SHARP VOLTAGE AND FREQUENCY EXCURSIONS –VOLTAGE AND FREQUENCY EXCURSIONS –
EXTREMEEXTREME COMPLEXITY INVOLVED IN SWITCHINGCOMPLEXITY INVOLVED IN SWITCHING
PROTECTION ISSUESPROTECTION ISSUES
DRASTIC REDUCTION IN SC DRASTIC REDUCTION IN SC LEVELS- OCR SETTINGS?LEVELS- OCR SETTINGS?
FREQUENCY AND VOLTAGE FREQUENCY AND VOLTAGE EXCURSIONS- v/f SETTINGS?EXCURSIONS- v/f SETTINGS?
LOAD ENCROACHMENT LOAD ENCROACHMENT PROBLEMS – LOW VOLTAGE - PROBLEMS – LOW VOLTAGE - LOADINGLOADING
POWER SWINGPOWER SWING
ISSUES TO BE EXAMINED FOR ISOLATIONISSUES TO BE EXAMINED FOR ISOLATION
SCHEDULING PROBLEMS-SCHEDULING PROBLEMS- CONTRACTION/EXPANSION OF ISLAND TO CONTRACTION/EXPANSION OF ISLAND TO
BE DONE WITH CHANGING SCHEDULESBE DONE WITH CHANGING SCHEDULES COMPLEXITY INVOLVED IN SWITCHINGCOMPLEXITY INVOLVED IN SWITCHING FORCED OVERDRAWALS – A QUANDRARY FORCED OVERDRAWALS – A QUANDRARY
THAT MAY BE UNAVOIDABLETHAT MAY BE UNAVOIDABLE STATE SYSTEM – INABILITY TO DRAW STATE SYSTEM – INABILITY TO DRAW
ENTITLEMENTENTITLEMENT LOAD MANAGEMENT/SWITCHING LOAD MANAGEMENT/SWITCHING
OPERATION – STILL IN STATE PURVIEWOPERATION – STILL IN STATE PURVIEW
ISSUES TO BE EXAMINED FOR ISOLATION ISSUES TO BE EXAMINED FOR ISOLATION CONTD....CONTD....
SCHEDULING PROBLEMS-SCHEDULING PROBLEMS- DRAWAL PATTERN VARIATION –:(MIN/MAX IN %)DRAWAL PATTERN VARIATION –:(MIN/MAX IN %)
CONTRACTION AND EXPANSION OF CONTRACTION AND EXPANSION OF ISLANDISLAND
COMMERCIAL IMPLICATION- OD/UDCOMMERCIAL IMPLICATION- OD/UD
STATE SYSTEMSTATE SYSTEM MIN/MAX IN %MIN/MAX IN %
ANDHRAPRADESHANDHRAPRADESH 75-85%75-85%
KARNATAKAKARNATAKA 55-65%55-65%
KERALAKERALA 55-60%55-60%
TAMILNADUTAMILNADU 80-85%80-85%
3D LOAD
PROFILE
3D LOAD
PROFILE
COMMERCIAL ISSUESCOMMERCIAL ISSUES
INABILITY TO DRAW AS PER INABILITY TO DRAW AS PER ENTITLEMENT DUE TO INSUFFICIENT ENTITLEMENT DUE TO INSUFFICIENT LOAD IN ISGS/ISTS BLOCK :-LOAD IN ISGS/ISTS BLOCK :- STATE MAY BE FORCED TO UNDERDRAW STATE MAY BE FORCED TO UNDERDRAW
FROM ISGS AND FORCED TO GENERATE FROM ISGS AND FORCED TO GENERATE AT COSTLY IPP’S/DEPLETED HYDRO – AT COSTLY IPP’S/DEPLETED HYDRO – COMMERCIAL IMPLICATION?.COMMERCIAL IMPLICATION?.
OVERDRAWAL MAY CONTINUE OVERDRAWAL MAY CONTINUE FORCING OTHER CONSTITUENTS TO FORCING OTHER CONSTITUENTS TO COMMIT COSTLY GENERATIONCOMMIT COSTLY GENERATION
SHORT CIRCUIT LEVELS – SHORT CIRCUIT LEVELS – RELEVANCE TO GRID RELEVANCE TO GRID
OPERATIONOPERATION SC LEVELS ARE AN INDICATOR OF THE SC LEVELS ARE AN INDICATOR OF THE ‘STRENGTH’ OF THE BUS TO REACTIVE ‘STRENGTH’ OF THE BUS TO REACTIVE POWER FLUCTUATIONSPOWER FLUCTUATIONS
HIGHER SC LEVELS – BUS IS MORE HIGHER SC LEVELS – BUS IS MORE STABLE – LIMITS VOLTAGE STABLE – LIMITS VOLTAGE EXCURSIONSEXCURSIONS
HIGHER SC LEVELS- BUS IS WELL HIGHER SC LEVELS- BUS IS WELL INTERCONNECTED-PROXIMITY OF INTERCONNECTED-PROXIMITY OF GENERATORSGENERATORS
ESPECIALLY IMPORTANT DURING ESPECIALLY IMPORTANT DURING RESTORATION.RESTORATION.
SHORT CIRCUIT LEVELS – SHORT CIRCUIT LEVELS – RELEVANCE TO GRID RELEVANCE TO GRID
OPERATIONOPERATION AN EXAMPLE:-AN EXAMPLE:-
CHARGING A 300 KM LINE FROM A 2000 CHARGING A 300 KM LINE FROM A 2000 MVA 400 KV BUS WOULD INCREASE THE MVA 400 KV BUS WOULD INCREASE THE VOLTAGE BY 33 KVVOLTAGE BY 33 KV
CHARGING A 300 KM LINE FROM A 6000 CHARGING A 300 KM LINE FROM A 6000 MVA 400 KV BUS WOULD INCREASE THE MVA 400 KV BUS WOULD INCREASE THE VOLTAGE BY 11 KVVOLTAGE BY 11 KV
SHRT CKT STUDYRESULT
L INDEXL INDEX INDICATES THE PROXIMITY TO VOLTAGE INDICATES THE PROXIMITY TO VOLTAGE
COLLAPSECOLLAPSE IF THE INDEX APPROACHES 1 THEN THE BUS IF THE INDEX APPROACHES 1 THEN THE BUS
IS INCREASINGLY VULNERABLE TO VOLTAGE IS INCREASINGLY VULNERABLE TO VOLTAGE COLLAPSECOLLAPSE
DERIVED FROM LOAD FLOW JACOBIAN DERIVED FROM LOAD FLOW JACOBIAN MATRIXMATRIX
SHOULD BE GENERALLY WITHIN 0.3 DURING SHOULD BE GENERALLY WITHIN 0.3 DURING NORMAL OPERATION FOR SR GRID.NORMAL OPERATION FOR SR GRID.
GENERALLY IN LINE WITH WHAT IS GENERALLY IN LINE WITH WHAT IS OBSERVED BY THE SYSTEM OPERATORSOBSERVED BY THE SYSTEM OPERATORS
L INDEX STUDYRESULT
L INDEX STUDY400 KV SUMMARY
GOOTY 0.3126 AP
CUDDAPAH 0.268 AP
HYDERABAD 0.236 AP
KHAMMAN 0.1794 AP
NUNNA 0.1693 AP
RAMAGUNDAM 0.1197 AP
SIMHADRI 0.1177 AP
BANGALORE 0.3431 KAR
HOODY 0.3175 KAR
NELAMANGALA 0.3101 KAR
KOLAR 0.3043 KAR
DAVANGERE 0.2157 KAR
MUNIRABAD 0.1721 KAR
RAICHUR 0.0804 KAR
TRICHUR 0.2262 KER
HOSUR 0.2539 TN
SALEM 0.2011 TN
L INDEXL INDEX
KER TN
KAR AP
ISGS
SCIENTIFIC SETTLEMENT
SYSTEM?
LINKSLINKSSR GRID MAP KAR ISL CASE3 TN ISL CASE1 AP GRID MAP
KARNATAKAGRID MAP
KERALAGRID MAP
TN GRID MAPSHORT CKT STDYRESULTS 400 KV
L INDEX STUDY RESULTS
3D DEMAND SRJUNE 2002
3D DEMAND SRMAY2002
3D DEMAND SRMARCH 2002
SHORT CKT STDYRESULTS 220 KV
SHORT CKT STDYRESULTS 230 KV
ISOLATION OF PART OF ISOLATION OF PART OF KARNATAKA: CASE STUDYKARNATAKA: CASE STUDY
CASE 1: SOMANAHALLY TRANSFORMER CASE 1: SOMANAHALLY TRANSFORMER CONNECTED TO AP-TN-KER GRID AND CONNECTED TO AP-TN-KER GRID AND RADIALLY FEEDING 700MW LOAD, KAIGA RADIALLY FEEDING 700MW LOAD, KAIGA EMBEDDED IN KARNATAKA SYSTEM.400 KV EMBEDDED IN KARNATAKA SYSTEM.400 KV RTPS-N’SAGAR OPENRTPS-N’SAGAR OPEN
CASE 2: CASE 1 WITH KAIGA ISLANDEDCASE 2: CASE 1 WITH KAIGA ISLANDED CASE 3: SPLIT BUS AT RTPS, KAIGA & CASE 3: SPLIT BUS AT RTPS, KAIGA &
400KV UNITS OF RAICHUR WITH AP-KER-400KV UNITS OF RAICHUR WITH AP-KER-TN-KOLAR-SOMANAHALLI-HOODY-GUTTUR TN-KOLAR-SOMANAHALLI-HOODY-GUTTUR SYSTEM. SOMANAHALLY AND HOODY SYSTEM. SOMANAHALLY AND HOODY RADIALLY FEEDING BANGALORE LOADS RADIALLY FEEDING BANGALORE LOADS EXCEPT PEENYA. EXCEPT PEENYA.
GRID
MAP
GRID
MAP
LOAD 3000 MW
LOW VOLTAGE
ZONE
ABOUT 700 MW ON AP-
TN-KER GRID
CASE 1 BANGALORE LOADS ON AP-TN-KER GRID
ISLANDING IN KARNATAKA SYSTEM KARNATAKA
STN_NAME STATE BASE CASE CASE1 CASE2 CASE3
RST4 AP 8760 8378 8371 8194
TPL4 AP 6768 5926 5916 5697
CNP4 AP 5055 4782 4776 4747
GTN4 AP 2936 3027 3018 2789
KOLAR4 KAR 6479 5362 5358 5868
RTPS4 KAR 5859 3962 3692 3149
SOMN4 KAR 5540 4394 4390 4850
HOODY4 KAR 5536 1522 1305 4911
NLMNG4 KAR 4818 1656 1423 3979
DVGRE4 KAR 4349 2545 2120 2890
GDHL4 KAR 3767 2777 2546 2330
KARNATAKA-SC LEVELS IN MVAKARNATAKA-SC LEVELS IN MVA
ISOLATION OF PART OF ISOLATION OF PART OF KERALA AND TAMILNADU: KERALA AND TAMILNADU:
CASE STUDYCASE STUDY TAMILNADU : TTPS, BALAJI TAMILNADU : TTPS, BALAJI
POWER,WIND, NILAGIRIS HYDRO, POWER,WIND, NILAGIRIS HYDRO, KADAMPARAI HYDRO IN ISOLATED KADAMPARAI HYDRO IN ISOLATED PORTION. PORTION. AP-KAR-KER AND AP-KAR-KER AND N.TAMILNADU(NEYVELI-MAPS-ETS-N.TAMILNADU(NEYVELI-MAPS-ETS-NMTPS-MTPS – GMR) IN ONE BLOCKNMTPS-MTPS – GMR) IN ONE BLOCK
KERALA- SPLIT BUS AT EDAMON AND KERALA- SPLIT BUS AT EDAMON AND THRISSUR WITH LOADS TAKEN THRISSUR WITH LOADS TAKEN RADIALLY AT BOTH POINTSRADIALLY AT BOTH POINTS
TAMILNADU AND KERALA SC LEVELS IN MVATAMILNADU AND KERALA SC LEVELS IN MVA KERALA TN
STN_NAME STATE BASE CASE CASE1 CASE1
RST4 AP 8760 8740 8725
CNP4 AP 5055 5014 4987
SOMN4 KAR 5540 5441 5312
KOLAR4 KAR 6479 6537 6526
TRICH4 KER 3838 2724 3239
N2MIN4 TN 10556 10128 9828
NLYEU4 TN 10223 9818 9537
SALEM4 TN 8119 7639 6523
SPBUDUR4 TN 7011 6923 6895
TRICHY4 TN 6661 6266 5654
MADURAI4 TN 5755 5251 4094
HOSUR4 TN 5474 5346 5277
UDMLPT4 TN 5433 4363 4032
OPERATIONAL ISSUESOPERATIONAL ISSUES KARNATAKAKARNATAKA
KAIGA REMAINS EMBEDDED IN ISOLATED KAIGA REMAINS EMBEDDED IN ISOLATED PORTION OF KARNATAKAPORTION OF KARNATAKA FREQUENT HOUSE LOADING AND POISONING FREQUENT HOUSE LOADING AND POISONING
OUT - EXPECTED.OUT - EXPECTED. KAPS TO REDUCE GENERATION BY 40-50 MW KAPS TO REDUCE GENERATION BY 40-50 MW
TO PREVENT HUNTINGTO PREVENT HUNTING DEPLETED HYDRO POSITION IN ISOLATED DEPLETED HYDRO POSITION IN ISOLATED
PART:PART: PEAKING HYDRO TO BE RUN AS BASE STATION PEAKING HYDRO TO BE RUN AS BASE STATION STORAGE POSITION ALREADY CRITICALSTORAGE POSITION ALREADY CRITICAL EXTREMELY LOW VOLTAGES TO BE EXPECTED EXTREMELY LOW VOLTAGES TO BE EXPECTED
IN SOUTH KARNATAKA.IN SOUTH KARNATAKA.
DELIVERING CGS ENTITLEMENT TO DELIVERING CGS ENTITLEMENT TO KARNATAKAKARNATAKA
KPTCL’S CGS ENTITLEMENT WITH FULL KPTCL’S CGS ENTITLEMENT WITH FULL GENERATION AT NTPC,NLY,KAPS AND ONE GENERATION AT NTPC,NLY,KAPS AND ONE UNIT AT MAPS IS AND WITH ALLOCATION OF UNIT AT MAPS IS AND WITH ALLOCATION OF 156 MW ER AND 100 MW PTC POWER 156 MW ER AND 100 MW PTC POWER = = 1206 MW1206 MW
GOA’S ENTITLEMENT TO BE WHEELED BY GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL KPTCL = 94 MW.= 94 MW.
TOTAL ENTITLEMENT OF KPTCL TOTAL ENTITLEMENT OF KPTCL = 1310 MW= 1310 MW AS AS KAIGAKAIGA GENERATION OF GENERATION OF 400 MW400 MW IS IS
EMBEDDEDEMBEDDED KPTCL HAS TO IMPORT 9 KPTCL HAS TO IMPORT 910 10 MWMW
AT AT 330 KV/400 MVAR330 KV/400 MVAR IMPORT THE IMPORT THE CAPACITY OF SOMANAHALLI TRANSFORMER CAPACITY OF SOMANAHALLI TRANSFORMER IS IS 720 MW720 MW
DELIVERING CGS ENTITLEMENT TO DELIVERING CGS ENTITLEMENT TO KARNATAKAKARNATAKA
KPTCL’S CGS ENTITLEMENT WITH FULL KPTCL’S CGS ENTITLEMENT WITH FULL GENERATION AT NTPC,NLY, ONE UNIT AT KAPS GENERATION AT NTPC,NLY, ONE UNIT AT KAPS AND MAPS IS AND WITH ALLOCATION OF 156 AND MAPS IS AND WITH ALLOCATION OF 156 MW ER AND 100 MW PTC POWER = MW ER AND 100 MW PTC POWER = 1140 MW1140 MW
GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL GOA’S ENTITLEMENT TO BE WHEELED BY KPTCL = 94 MW= 94 MW..
TOTAL ENTITLEMENT OF KPTCL TOTAL ENTITLEMENT OF KPTCL = 1234 MW= 1234 MW ASAS KAIGA KAIGA GENERATION OF GENERATION OF 200 MW200 MW IS IS
EMBEDDED KPTCL HAS TO IMPORT EMBEDDED KPTCL HAS TO IMPORT 1034 MW1034 MW AT AT 330 KV/400 MVAR330 KV/400 MVAR IMPORT THE CAPACITY IMPORT THE CAPACITY
OF SOMANAHALLI TRANSFORMER IS OF SOMANAHALLI TRANSFORMER IS 720 MW720 MW DIFFICULTY IN DELIVERING ENTITLEMENTDIFFICULTY IN DELIVERING ENTITLEMENT LOADS AT SOMANAHALLI TO BE LOADS AT SOMANAHALLI TO BE
REARRANGED DEPENDING ON KAPS REARRANGED DEPENDING ON KAPS GENERATIONGENERATION