post award monitoring formats
TRANSCRIPT
-
7/27/2019 Post Award Monitoring Formats
1/17
(Name of the Port)
Construction Stage Monitoring Report of (Name of the Project) for the month
ended..
Compliance of Obligations of the Port
S.No. Obligations of the Port (Related MCAClause)
Whetherany actionrequired(Yes/ No)
If yes, givedetails of
action taken*
1 Meeting the Conditions Precedent (Clause3.1)
Procurement of clearance from Ministryof Environment & Forests
Handing over physical possession of
Project Site/ Port Assets for the project(Stage wise, if so envisaged)
Putting in place arrangement forprovision of Supporting ProjectInfrastructure
2 In case conditions precedent are not compliedwithin the specified time, details of extensionof time availed
3 Recovery of liquidated damages for failure toachieve Financial Close (Clause 3.5)
4 Appointment of Independent Engineer 5.1(a)
5 Furnishing of comments/ observations on theDesigns & Drawings to Independent Engineer 6.2 (b)
6 Grant applicable permits, approval andconsents as may be required byconcessionaire under concession agreement 6.5 (a)
7 Make available records of sub soilinvestigation. 6.5 (b)
8 Assist the concessionaire in obtainingimmigration clearance, employment permitsand residential premises for any foreignpersonnel engaged or employed byconcessionaire. 6.5 (d)
9 Assist concessionaire or contractor to importinto India all items of equipment and materialrequired for the project. 6.5 (e)
-
7/27/2019 Post Award Monitoring Formats
2/17
10 If required on advice of Independent Engineer,suspend the construction works (Clause 6.6)
11 Review the rectification works if anysuggested by Independent Engineer whilevisiting the project site Clause 6.4 (e)
12 On advise of IE, revoke the suspension afterthe rectifications (Appendix 7)
13 If required as advised by IndependentEngineer, concession authority may extendthe construction phase, if the delay is notattributable by concessionaire 6.2(e)
14 To witness the tests along with IndependentEngineer to ensure project meets withconstruction standards. 6.7 (a)
15 To verify the performance security ismaintained as per clause 4.1, or otherwisetermination of agreement for non-maintenanceof performance security as per clause 15.1(a)(xii)
16 Recovery damages of liquidated if any fromperformance guarantee for failure to achievemilestones (Clause 6.9)
17 In case of change of scope, whetherprocedures laid down in Article 6.8 is followed
18 Ensuring issue of Completion Certificate byIndependent Engineer (Clause 6.7)
19 In case of aggregate delay exceeds 180 daysor LD exceeds 5% of project cost, Terminate
the agreement (Clause 6.9)20 Is any action required on monthly Inspection
report from IE (Appendix 7)21 In case concessionaire fails to complete the
works on account of Force Majeure or due toreasons attributable to authority, reduce thescope of work and recover the 80% of sumsaved from work not completed (Clause6.7(e))
22 In event of non-compliance conditionsprecedent within the time including theextended time if any termination of the
agreement (Clause 3.6)23 Ensuring Operation of Escrow account in an
orderly manner (Clause 9.5)
24 Issue of Notice for a Force Majeure Event(Clause 14.5)
25 In case of force majeure event, whetherextension of time has been granted (Clause14.9 (b))
-
7/27/2019 Post Award Monitoring Formats
3/17
26 In the event of termination due to forcemajeure event, whether compensation hasbeen paid as per clause 17.1(a)
27 Issue of Notice on occurrence of an event ofdefault (Clause 16.1)
28 Informing Lenders of Intent to Terminate(Clause 16.1)
29 Termination Payment for termination due toPort Event of Default as per clause 17.1(c)
30 Exercising Rights and meeting obligationsupon termination (Clause 17.7)
31 Assessment of change in law and treatmentof costs out of change in law (Clause 13.2(b))
32 Amicably resolving disputes (Clause 19.1 &19.2)
33 Declaration of Project Facilities & Services asready for operation in accordance with Section37 of MPT Act (Clause 6.5 (c))
34 Execution of Substitution Agreement within 30days of notice from the concessionaire as perclause 12.3 (b) v
35 Any other observation, complaint orsuggestion
-
7/27/2019 Post Award Monitoring Formats
4/17
(Name of the Port)
Construction Stage Monitoring Report of (Name of the Project) for the month
ended..
Compliance of Obligations of the Concessionaire
S.No. Obligations of the Concessionaire (RelatedMCA Clause)
Whetherany actionrequired(Yes/ No)
If yes, givedetails of
action taken*
1 Providing and maintaining the PerformanceSecurity (Clause 4.1)
2 Compliance of Conditions Precedent(Clause 3.1(a))
Execution of Escrow Agreement Procuring all Applicable Permits as per
Appendix 8
Submission of Financial Package,Financing Documents Financial Modeland other Financial Close documents toPort
Submission of Confirmation ofRepresentation & Warranties byConsortium Members
Submission of legal opinion withrespect to the authority ofconcessionaire
Furnishing a copy of ManagementContract
3 In case conditions precedents are notcomplied within the specified time, details ofextension of time availed
4 Submission of Designs and Drawings to theIndependent Engineer & concession authority(Appendix 6)
5 Arrangement of financial and other resourcesas per financing Plan as evidenced by EscrowAccount (Clause 6.4(a))
6 Carry out works in compliance with theConstruction Standards (clause - 6.4 (b)
7 Obtain Applicable Permits and comply withApplicable Laws. - 6.4 (d)
-
7/27/2019 Post Award Monitoring Formats
5/17
8 Providing access to Port representatives forinspections for ascertaining compliance ofrequirements (Clause 6.4(e))
9 Submission of Monthly Progress Reports toIndependent Engineer
10 Removal of Defects/ deficiencies as observedby Independent Engineer (Clause 6.4(f))
11 Ensure safe and timely construction andcompletion of the Project/ - 6.4 (h)
12 At least 60 days prior to the likely completionof the Project, notify the Independent Engineerof the date when it intends to commencecommercial operations- 6.7 (a)
13 Providing assistance to Independent Engineerfor conducting all requisite Tests onstructures/ equipments etc., - 6.7 (a)
14 To obtain Provisional Certificate of Completionas per clause 6.6(d)
15 To complete all outstanding items listed inpunch list within 90 days or extended periodby concessioning authority. 6.7 (d)
16 Procurement of Security Clearance forManagement Contractor. 12.1 (f) (ii)
17 Pay License fee annually. 9.1 (a)
18 Pay Liquidated damages to ConcessioningAuthority, if applicable. 6.9
19 Maintenance of Insurance as per clause12.1(c)
20 In case of Execution of substitution
agreement, whether notice has been issuedby the concessionaire to the port as perclause 12.3 (b) v
21 Whether equity Holding requirements are metby lead member/ members of the applicantconsortium as per clause 11.2
-
7/27/2019 Post Award Monitoring Formats
6/17
(Name of the Port)
Operation Stage Monitoring Report of (Name of the Project) for the month
ended..
Compliance of Obligations of the Concessionaire
S.No. Obligations of the Concessionaire (RelatedMCA Clause)
Whetherany actionrequired(Yes/ No)
If yes, givedetails of
action taken*
1 Prompt commencement of operations afterReady for Operation declaration (Clause7.1(a)(I)(a))
2 Operation of Project facilities as per Project
Requirement (Clause 7.1(a) (i)(c))
3 Achieving Performance Standards (Clause7.1(a) (i)(d))
4 Compliance of O&M and Safety Standards(Clause 7.1(a) (i)(e))
5 Rapid & Effective response in the event ofaccident/ emergency (Clause 7.1(a) (i)(f))
6 Replacement and repair of project facilities in
a timely manner (Clause 7.1(a) (i)(g)
7 Manage & Operate project facilities on FirstCome First Served basis except for Priority &Preferential berthing as per GOI guidelines(Clause 7.1(a) (i)(h))
8 Maintenance of Proper Records relating toRevenue and operation of project facilities(Clause 9.4)
9 Obtaining, Maintenance of Applicable Permitsand Compliance of Applicable laws (Clause7.1(a) (j))
10 Prevention of encroachment / unauthorizeduse of project assets (Clause 7.1(a) (i)(l))
11 Repair & Maintain all Project Facilities as perGood Industry Practice at all times during theConcession Agreement.7.1(a)(ii)
-
7/27/2019 Post Award Monitoring Formats
7/17
12 Repair, Replace or Restore the damagedProject Facilities at its own costs.7.1(a)(iv)
13 Obtaining prior written permission ofconcessioning authority for removal of assetsclause 7.1(a)(v)
14 Replacement of equipments/ assets as perGood Industry Practice (Clause 7.1(a) (iii))
15 Make timely payments to the ConcessioningAuthority viz Royalty & Licence Fee etc.9.1(a)& 9.2(a)
16 Compliance with Monthly ReportingRequirements(Clause 7.1(a) (viii))
17 Cooperation to experts appointed byconcession authority in access for inspectionfor safety audit once in a year (Clause 7.1(a)(vii))
18 Cooperation to port representatives forinspection and review of operations also tocompliance with requirements of agreement(Clause 7.1(a)(vii))
19 Installation & Operation of specified computersystem and Network as specified byconcession authority (Clause 7.1(a) (ix)
20 Ensuring the prescribed SecurityArrangements conforming to ISPScode(Clause 7.1(a) (x)
21 Employment of personnel of foreign origin onlyafter requisite approvals from Government ofIndia (Clause 7.1(a) (xi))
22 Employ qualified and skilledpersonnel.7.1(a)(xi)
23 Meeting Minimum Guaranteed Cargorequirements(Clause 7.1(a) (xi))
24 To recover tariff from users of the projectfacilities as per Tariff Order Notification and
deposit all Tariff in Escrow Account (Clause8.1)
25 If requested by CA, collect the cess andcharges from the users on behalf ofConcessioning Authority 8.2
26 Make timely payments to concessioningAuthority viz Royalty & Licence fees (Clause9.1(a) & 9.2 (b)
-
7/27/2019 Post Award Monitoring Formats
8/17
27 To operate escrow account as per priority ofpayments as per clause 9.5(a)
28 To submit financial statement of grossrevenue every six months. Clause 9.4End 30th September and 31st March
29 Meeting any claim/ action/ suit etc. alleging
loss/ destruction of goods (Clause 7.19a)(xiii))30 Inform Concessioning Authority if any Direct or
indirect change of management ofconcessionaire as per clause 11.2
31 Payment of all taxes/ duties/ levies etc., to theGovernment Authorities (Clause 12.1(b)
32 Purchasing and Maintaining of Insurancerequirements in accordance with GoodIndustry Practice (Clause 12.1(c))
33 Providing copies of insurance policies to thePort (Clause 12.1(c) (iii)
34 In case money is received under insurancepolicy it should be utilized as per terms ofAgreement (Clause 12. 1(c) (iv)
35 Engagement of Management Contractor asenvisaged in RFP(Clause 12.1(f))
36 Ensuring conduct of Conditional Survey froman expert appointed by mutual consent andcompliance of remedies thereof before expiry
of concession period. (Clause 12.1(g))
37 Issue of consultation notice and compliance ofremedial process in case of Event of Defaulton the part of Port (Clause 15)
38 Submit bank guarantee two years prior toexpiry of concession period for repairs if anyfor condition survey [Clause 12.1 (g) ii]
-
7/27/2019 Post Award Monitoring Formats
9/17
(Name of the Port)
Operation Stage Monitoring Report of (Name of the Project) for the month
ended..
Compliance of Obligations of the Port
S.No. Obligations of the Port (Related MCAClause)
Whetherany actionrequired(Yes/ No)
If yes, givedetails of
actiontaken *
1 To get from the concessionaire copies of asbuilt design and drawings maintenanceschedule of equipments etc. as vetted by
Independent Engineer as per (Appendix 6) &clause 18.2 2 Release of Performance Security
after 6 months from the date of commercialoperation(Clause 4.1)
3 Scheduling entry, berthing and sailing of thevessels, pilotage and towage on a non-discriminatory basis subject to priority berthingnorms.- Clause 7.1 (i) (a)
4 Maintenance of entrance channel draft Clause
7.1(c) (i)(b)
5 Provide waterside safety and safety ofnavigation; - Clause 7.1 (c) (i) (c)
6 Provision and maintenance of all general portinfrastructure other than covered under theconcession Clause 7.1 (c) (i) (f)
7 Grant approvals/ consents sought by theConcessionaire as required under theagreement Clause 7.1 (c) (i) (ii)
8 Evolve mutually acceptable mechanism forsharing the common costs by existing andfuture terminal operators Clause 7.1 (c) (i) i
9 Provide access to all applicable infrastructurefacilities and utilities including water, electricityetc. Clause 7.2
-
7/27/2019 Post Award Monitoring Formats
10/17
10 Review performance standards from themonthly report submitted by concessionaireand take remedial action as per Clause 7.3
11 Organize a special audit of the Gross revenue,Financial statements etc. if required, and take
action as per Clause 9.412 To operate escrow account as per priority of
payments as per clause 9.5(a)
13 Whether equity Holding requirements are metby lead member/ members of the applicantconsortium as per clause 11.2
14 Assistance to concessionaire by givingrecommendation letter for getting applicablepermits Clause 12.2 (a)
15 Pay levy (or) levies including increase in taxes,duties etc., on account of port assets payableto State Govt. Clause 12.2 (b)
16 Shall not operationalise competing facility asper Clause 12.2 (c)
17 Issue notice of Force Majeure In the event ofoccurrence of any Force Majeure event(Clause 14.5)
18 Extension of time for performing obligationsdue to occurrence of Force majeure(Clause14.9 (b))
19 Compliance of provisions of Clause 14.10 inthe event of force majeure continuing beyond120 days
20 Payment of compensation in the event oftermination due to force majeure event as perclause 17.1(a)Payment of compensation in the event oftermination due to concessionaire event ofdefault as per clause 17.1(b)Payment of compensation in the event oftermination due to concessioning authorityevent of default as per clause 17.1(c)
21 Authorize the concessionaire to collect cessesand charges including infrastructure cess ifrequired and remit the same to concessioning
authority if required22 Initiate action for amicably resolution of
disputes (Clause 19.1 and 19.2)
23 Any other observation, complaint or suggestion
-
7/27/2019 Post Award Monitoring Formats
11/17
Key Performance Indicators (KPI)/Performance Standards
(Based on MCA of Major Ports)
S.No. Maintenance/Performance
Standards
Indicative
norms
Actual
during the
month
Shortfall, if
any
Action
taken to
remedy
shortfall
1 Gross Berth
Output Appendix-
15
2 Transit Storage
Dwell timeAppendix 15
3 Turn-around time
for receipt/
delivery operation
Appendix 15
-
7/27/2019 Post Award Monitoring Formats
12/17
(Name of the Port)
Construction/ Operation Stage Monitoring Report of (Name of the Project) forthe month ended.. (Prepared by Port to the Ministry)
I. Basic Data of the project
Sl.
No.
Project Parameters Details
1. Name of the concessionaire
2. Percentage of equity holding in case of
consortium
3. Percentage of revenue sharing
4. Date of Issue of Letter of acceptance by
the port to concessionaire
5. Date of signing of Concession
Agreement
6. Time duration for fulfilling the condition
precedent as per concession
agreement
7. Actual Date of award of concessionafter fulfilling condition precedent
8. Date of starting of commercial
operation
9. Estimated cost
-
7/27/2019 Post Award Monitoring Formats
13/17
10. Capacity
11. Project details like length of berth,
design vessel size can be handled,
equipments installed, backup area etc.,
12. Present tariff rate
13 MGT if any as per concession
agreement
14. Cargo handled during this month
15. Cumulative cargo handled during the
financial year
16. Any other remarks
-
7/27/2019 Post Award Monitoring Formats
14/17
(Name of the Port)
Construction/ Operation Stage Monitoring Report of (Name of the Project) for
the month ended.. (Prepared by Port to the Ministry)
II REPORT AT A GLANCE
S.No. The issues Action Taken
by the Port
Action
Taken /
Proposed by
Ministry
1 Timelines not met by the
Concessionaire
(i)
(ii)
2 Timelines not met by the Port
(i)
(ii)
3 Performance Standards not met by
the Concessionaire
(i)
(ii)
4 Defaults in Payments by the
Concessionaire
(i)
(ii)
5 Defaults in Payments by the Port
(i)
(ii)
6 Other issues which may lead to
default on the part of concessionaire
-
7/27/2019 Post Award Monitoring Formats
15/17
(i)
(ii)
7 Other issues which may lead to
default on the part of concessioning
Authority
(i)
(ii)
8 Issues under Arbitration / Litigation
(i)
(ii)
9 Brief Comments on the progress/performance of the project
10 Suggestions, if any
-
7/27/2019 Post Award Monitoring Formats
16/17
(Name of the Port)
Name of the Project
EXCEPTION REPORT BY THE MINISTRY (PRU)TO THE COMPETENT
AUTHORITY
S.No. Subject Action Taken
by PMU/ Authority
Action
Taken by PRU
I Exception Report on non-compliance
1 Timelines not met by the
Concessionaire
(i)
(ii)
2 Timelines not met by the Port
(i)
(ii)
3 Performance Standards not met by
the Concessionaire
(i)
(ii)
4 Defaults in Payments by the
Concessionaire/ Authority
(i)
(ii)
5 Other issues which may lead to
default on the part of concessionaire
(i)
(ii)
6 Other issues which may lead to
default on the part of Authority
-
7/27/2019 Post Award Monitoring Formats
17/17
(i)
(ii)
7 Issues under Arbitration / Litigation
and their status
(i)
(ii)
II Report on matters affecting public exchequer
1 Any additional project costs or
expenditure affecting the Authority
(i)
(ii)
2 Levy or collection of any user
charges having adverse impact on
Users or Authority
(i)
(ii)
3 Any other financial matter having
adverse bearing on Users or
Authority
(i)
(ii)
III General remarks about the progress and performance of the project
IV Suggestions, if any.