pool schedule delay. pool delays pool phase began as scheduled on june 1 st. removal of plaster...
TRANSCRIPT
![Page 1: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/1.jpg)
Pool Schedule Delay
![Page 2: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/2.jpg)
Pool DelaysPool phase began as scheduled on June 1st. Removal of plaster revealed concrete
degradation of the shell.Walls have deteriorated in multiple areas.Rebar inside the walls have rusted.Existing wall has been determined to be
unfit.N0 indication of this condition was evident
prior to removal of the plaster coat.
![Page 3: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/3.jpg)
FindingsRe-plastering began our final phase of
renovations.Project was proceeding on schedule with best
efforts put forth to re-open July 1st. Structural Engineer, Soil testing agency, and Pool
Builder were consulted for opinions and recommendations.
Although this delay is unavoidable, we are working diligently to finalize the change in scope and deliver an exceptional amenity for our residents and guests.
![Page 4: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/4.jpg)
About GuniteA mixture of cement, sand, and water applied
through a pressure hose, producing a dense hard layer of concrete .
It is mixed on site and sprayed into a form creating a pool shell.
Gunite provides structural stability and is the base to which plaster is applied.
![Page 5: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/5.jpg)
Deteriorated wall section
![Page 6: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/6.jpg)
Rusted rebar inside wall
![Page 7: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/7.jpg)
Degraded shell section
![Page 8: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/8.jpg)
Water intrusion through wall
![Page 9: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/9.jpg)
Water seeping through wall
![Page 10: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/10.jpg)
Next StepsConstruction plans are now being developed.Permit for constructing new pool is required.Other renovation work is near completion.Build new pool.Reopen indoor pool as soon as possible.
![Page 11: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/11.jpg)
Completed Renovation Work
![Page 12: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/12.jpg)
Completed Work Cont.
![Page 13: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/13.jpg)
Completed Work Cont.
![Page 14: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/14.jpg)
Completed Work Cont.
![Page 15: Pool Schedule Delay. Pool Delays Pool phase began as scheduled on June 1 st. Removal of plaster revealed concrete degradation of the shell. Walls have](https://reader035.vdocuments.site/reader035/viewer/2022062805/5697c0291a28abf838cd724a/html5/thumbnails/15.jpg)