SAFER, SMARTER, GREENER DNV GL © 2014 Risk from Theory to Practice. The example of Marine Operations Ungraded Bartlomiej Zygmunt Kolosowski OIL & GAS 1 Polito 21.12.2016 Risk from Theory to Practice The example of Marine Operations DNV GL Oil & Gas Italy & Mediterranean Bartlomiej Zygmunt Kolosowski

Upload: others

Post on 21-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016 SAFER, SMARTER, GREENERDNV GL © 2014 Risk from Theory to Practice. The example of Marine Operations

Ungraded

21 November 2016

Bartlomiej Zygmunt Kolosowski

OIL & GAS

1

Polito 21.12.2016Risk from Theory to Practice

The example of Marine Operations

DNV GL Oil & Gas Italy & Mediterranean

Bartlomiej Zygmunt Kolosowski

Page 2: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Breadth of knowledge: you must be big to afford lots of highly specialized experience

2

15,000employees

2,500mill. Euro (2012)

100countries

Americas

3,000 staffAsia, Oceania

4,000 staff

Europe, Africa,

Middle East

10,000 staff

Page 3: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

DNV FoundationMayfair

Headquartered in

Hamburg, Germany

Headquartered in

Høvik, Norway

Headquartered in

Arnhem, Netherlands

Headquartered in

Milan, Italy

Maritime Oil & Gas EnergyBusiness

Assurance

Research & Innovation

DNV GL Group

Headquarter: Oslo, NorwayGroup President & CEO: Remi Eriksen

SoftwareCybernetics

Global Shared Services

3

Industry Focused Organization

Page 4: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

DNV GL Italy Organisation

400 people

All business areas

Services covered in Business Area Oil & Gas:

– Risk Advisory

– Verification/Certification

– MAA

– Inspection Services

4

Page 5: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Agenda

A A Story of Risk and Insurance

Co

nte

nt

B Marine Warranty: introduction to Risk Management

C Handling Risk in Practice

D Dangerous Lifts

Page 6: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Risk and the ideal Scope of Insurance

6

Necessary &

Planned

Cost of

Planned

Possible &

Unplanned

Cost of

Unplanned

Budget

Total Cost of Project

Insurance

Premium

Page 7: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Risk and the actual Scope of Insurance

7

PlannedCost of

Planned

Possible &

Unplanned

Cost of

Unplanned

Budget

Unforeseen

expenditures

Total Cost of Project

Insurance

Premium

Page 8: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

In 1760 the Risk was not coming back

8

Edward Lloyd’s

Page 9: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

An independent Class is born to assess unrestricted seaworthiness

9

Ship Cost of ShipProbability of

shipwreck Cost of Cargo

Budget

Total Cost of Project

Insurance

Premium

Shipper P & I

Page 10: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

In 1960 the Risk was underestimating critical steps in a project

10

Page 11: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Marine Warranty is born to assess scope & execution of the Plan

11

Planned

Execution

Cost of

Planned

Possible &

Unplanned

Cost of

Unplanned

Budget

Unforeseen

expenditures

Total Cost of Project

Insurance

Premium

Investor Insurance company

Page 12: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

What is “MWS”

The fundamental

objective of the Marine

Warranty Surveyor is to

make reasonable

endeavours to ensure

that the risks associated

with the warranted

operations to which a

Marine Warranty

Surveyor is appointed

are reduced to an

acceptable level in

accordance with best

industry practice.

-JRC-MWS CoP 2010

27/12/2016

12

Page 13: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Is this crane’s operation insured?

13

Class:

MWS:

No.

Yes, under the following

operational conditions: …

Page 14: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Let’s apply this to an Oil & Gas Project

14

Design ConstructionTransp/

Inst.Operation

Co

mp

on

en

ts

Verification and/or Classification

Marine Warranty

Decom-

missioning

Page 15: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 201621 November 2016

Ungraded

15

A Typical O&G Field Development

Page 16: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 201621 November 2016

Ungraded

16

Page 17: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Agenda

A A Story of Risk and Insurance

Co

nte

nt

B Marine Warranty: introduction to Risk Management

C Handling Risk in Practice

D Dangerous Lifts

Page 18: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Priority SAFETY

Priority TIME

Priority PRICE

Why an

inspection?

MWS provides Risk Managementthrough complex contractual chains

I need to receive my pipe

I need to transport the pipe

I need a barge

I provide the cheapest barges on the market

18

MWS

Ris

k M

anagem

ent

Page 19: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

MWS provides transparency of critical decisions

19

Investors Lenders Suppliers Insurers

Transparency of decision making

Page 20: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

MWS assures the alignment between the project’s Planned Execution and the Insurance policy

20

Ris

k M

anagem

ent

Transparency of decision making

T&I

Insurance

Policy

Page 21: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

I have a Certificate of Approval, am I insured?

21

Certificate of Approval

Towage

Page 22: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

To bring value to project, there are some requirements

22

MWS must receive:

Early involvement

Access to Project Information

Open communication with Project Team

MWS must offer:

Shortlisting by Insurer

Applicable reference list

Access to broad engineering and offshore expertise

Reliable documentation management system

Page 23: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Agenda

A A Story of Risk and Insurance

Co

nte

nt

B Marine Warranty: introduction to Risk Management

C Handling Risk in Practice

D Dangerous Lifts

Page 24: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

DNV GL

• Documentorganisation

•TRN generation

•DocumentIN

•TRN OUT

Step4

Step1

Step2

Step3

Supplier SupplierSupplier

Client

Documentation is massive, and a management system is key

24

Page 25: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Ad-hoc database for document management is vital

25

Page 26: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Handling of additional equipment, like Noise Mitigation Systems, often provide

“unexpected” weather limitations

Highlight criticalities: are critical items documented?

Weather limits?

26

Page 27: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Documentary review: is the data quality good enough?

27

Sub-seabed survey:

geophysical + borehole?

Page 28: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

PROJECT NAME

PROJECT No.

PROJECT NAME & No.

Document review follows till all necessary information is submitted and Acceptable (with or without Comments)

28

Page 29: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Once documents and Comments are clarified, the MWS onsite signs the pre-filled Certificate of Approval

29

Page 30: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Agenda

A A Story of Risk and Insurance

Co

nte

nt

B Marine Warranty: introduction to Risk Management

C Handling Risk in Practice

D Dangerous Lifts

Page 31: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Two slings broke during the lift of a tug: the tug crashed back in the sea

31

Page 32: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Rigging Gear Management Supply

Design

Manufacturing

Traceability

UseLimitations

Rigging construction

Lifting execution

MaintenanceWithdrawal criteria

Record of examination

An investigation followed the tug incident: where was the problem?

32

Page 33: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Supply Design Construction standard

Material composition

Testing scope

Manufacturing Quality management

Manufacturing processes

Test execution

Traceability Construction certificate

Testing documentation

Markings & Labels

How transparent was the information from the supply side?

33

Page 34: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Supply Design Construction standard

Material composition

Testing scope

Manufacturing Quality management

Manufacturing processes

Test execution

Traceability Construction certificate

Testing documentation

Markings & Labels

How transparent was the information from the supply side?

Can I conclude that the Supply side was reliable?

34

Page 35: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

Lack of transparency undermines project’s risk evaluation

35

Project’s

risk?

Page 36: Polito 21.12.2016 OIL & GAS Risk from Theory to Practice ... … · DNV GL © 2014 Ungraded 21 November 2016 Breadth of knowledge: you must be big to afford lots of highly specialized

DNV GL © 2014

Ungraded

21 November 2016

SAFER, SMARTER, GREENER

www.dnvgl.com

36

Bartlomiej Zygmunt Kolosowski

Manager Noble Denton marine services

[email protected]

[email protected]

Questions?