policy note: renewable energy procurement and design …
TRANSCRIPT
POLICY NOTE: RENEWABLE ENERGY
PROCUREMENT AND DESIGN OF AUCTIONS
SEPTEMBER 30, 2019
SUSTAINABLE ENERGY FOR PAKISTAN (SEP) PROJECT
Submission Date: September 30, 2019
Contract No.: AID-OAA-I-13-00028
Task Order: AID-391-TO-16-00005
Activity Start Date and End Date: August 3, 2017 to April 26, 2021
Submitted by: Tetra Tech ES, Inc.
1320 North Courthouse Road, Suite 600
Arlington, VA 22201
Tel. +1-703-387-2100 | Fax +1-703-243-0953
www.tetratech.com
This report was produced for review by the United States Agency for International Development. It was
prepared by Tetra Tech ES, Inc. for the Sustainable Energy for Pakistan (SEP) Project.
POLICY NOTE: RENEWABLE ENERGY
PROCUREMENT AND DESIGN OF
AUCTIONS
SEPTEMBER 30, 2019
SUSTAINABLE ENERGY FOR PAKISTAN
(SEP) PROJECT
DISCLAIMER
This report is made possible by the support of the American people through the United States
Agency for International Development (USAID). The contents are the sole responsibility of the
Tetra Tech ES, Inc. and do not necessarily reflect the views of USAID or the United States
Government.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS iii
CONTENTS
EXECUTIVE SUMMARY......................................................................................................... 5
1. INTRODUCTION ............................................................................................................. 9
1.1 BACKGROUND .................................................................................................................. 9
1.2 STATE OF RENEWABLE ENERGY DEVELOPMENT .................................................... 9
1.3 HISTORICAL PROCUREMENT PROCESS .................................................................... 10
1.4 KEY DOCUMENTATION AND TYPICAL TIMELINES FOR
RENEWABLE ENERGY PROJECTS ............................................................................... 10
1.5 ALTERNATE AND RENEWABLE ENERGY POLICY 2019 ......................................... 10
1.6 OBJECTIVES OF THE POLICY NOTE ........................................................................... 11
2. INTERNATIONAL EXPERIENCE ................................................................................ 12
2.1 FEATURES OF ENERGY AUCTIONS ............................................................................ 12
2.2 AUCTION DESIGN .......................................................................................................... 13
2.3 EVALUATION OF FEASIBILITY OF AUCTIONS ........................................................ 14
2.4 FORMATS OF AUCTIONS .............................................................................................. 14
2.5 AUCTION DESIGN ......................................................................................................... 15
2.6 SUMMARY OF GOOD PRACTICES IN AUCTION DESIGN ..................................... 17
3. CONSIDERATIONS FOR COMPETITIVE PROCUREMENT IN PAKISTAN ......... 19
3.1 RISK ALLOCATION AND MITIGATION ...................................................................... 20
3.2 AREAS THAT NEED TO BE REVIEWED AND ADDRESSED .................................... 21
3.3 TIMELINE FOR LAUNCHING THE AUCTION ............................................................ 22
4. RECOMMENDATIONS ................................................................................................. 25
5. REFERENCES AND BIBLIOGRAPHY ......................................................................... 28
ANNEX A: IMPLEMENTING RENEWABLE ENERGY AUCTIONS IN PAKISTAN .... 29
A.1 DISCUSSION NOTE ........................................................................................................ 29
A.2 WHAT ARE RENEWABLE ENERGY AUCTIONS? ...................................................... 29
A.3 PRINCIPLES OF AUCTION DESIGN ............................................................................. 29
A.4 AUCTION DESIGN PROCESS ........................................................................................ 30
A.4.1 EVALUATE FEASIBILITY OF AUCTIONS ....................................................................................... 31
A.4.2 EVALUATE AUCTION FORMATS .................................................................................................... 32
A.4.3 DESIGN AUCTION ............................................................................................................................... 33
A.4.4 CONDUCT THE AUCTION .............................................................................................................. 41
A.4.5 EVALUATE OUTCOMES ..................................................................................................................... 42
ANNEX B: ILUSTRATIVE COMPETITIVE RE PROCUREMENT PROCESS
FOR RE ---- BEST PRACTICES ADAPTED FOR PAKISTAN .......................................... 44
iv RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
ABBREVIATIONS & ACRONYMS
AEDB Alternative Energy Development Board
CfD Contract-for-difference
COD Commercial Operation Date
CPPA-G Central Power Purchasing Agency Guarantees Ltd.
DSICO Distribution Company (electricity)
EOI Expression of Interest
EPA Energy Purchase Agreement or Environmental Protection Agency (as per context)
EU European Union
FiP Feed-in-Premium
FiT Feed-in-Tariff
FX Foreign Exchange
IEA International Energy Agency
IRENA International Renewable Energy Agency
kW Kilowatt
kWh Kilowatt-hour
LOI Letter of Intent
MOE Ministry of Energy
MW Megawatt
MWh Megawatt-hour
NEPRA National Electric Power Regulatory Authority
NREL National Renewable Energy Laboratory
NTDC National Transmission and Dispatch Company
OECD Organization for Economic Co-operation and Development
PPA Power Purchase Agreement
PPIB Private Power & Infrastructure Board
PPRA Public Procurement Regulatory Authority (Pakistan)
PV Photo-Voltaic
RAM Renewable Auction Mechanism (California)
RE Renewable Energy
RES Renewable Energy Sources
RETD Renewable Energy Technology Deployment
REZ Renewable Energy Zone
RFP Request for Proposals
RFQ Request for Qualifications
SEP Sustainable Energy for Pakistan
UK United Kingdom
USAID United States Agency for International Development
USD United States Dollar
USEA United States Energy Agency
VRE Variable Renewable Energy
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 5
EXECUTIVE SUMMARY
Preamble
The Government of Pakistan (GOP) is committed to the development of renewable sources of
energy in the country. In this regard, it has communicated its objective to increase the share of
renewable energy (RE)1 in the overall generation-mix from the current approximately 4% (by
installed capacity) to about 25% by 2025, and to 30% by 2030. A new “Alternative and Renewable
Energy (ARE)” policy is expected to be announced in the near future which is likely to amplify this
emphasis and set out an overall framework for the development of indigenous energy resources
especially solar, wind and bagasse-based power projects.
Creation of appropriate enabling conditions is necessary for mobilizing private investments in RE
development. International experience suggests that while there is no specific “one size fits all”
solution, there are, however, certain conditions that must be met and parameters that must be
adopted for the development of large scale RE deployment in any country. Increasing the share of
the RE projects in the overall generation-mix presents a number of issues that need to be addressed.
These include issues related to the physical and operational characteristics of RE such as variability,
intermittency, dispersed locations and so forth.
Globally a variety of policy options have been deployed to promote renewables. While different
countries may have their own unique features viz their power systems, geography and economies,
their experience can be a useful guide in not only developing RE policies but also can be applied at
operational levels.. RE policies may inevitably vary from country to country to reflect their
respective renewable resource potentials, current state of deployment, regulatory frameworks,
political priorities and fiscal constraints.
This document provides an overview of some of the key lessons learnt from global experience and
summarizes their relevance and applicability to Pakistan to facilitate the development of way forward
in the thematic area of RE Procurement and Design of Auctions.
Issue Analysis and International Experience
International experience has shown that auctions (or other variations of competitive procurement)
are an important mechanism for promoting the deployment of RE. As a market mechanism, auctions
enable governments to contract a pre-defined volume of energy at a competitive cost. When well
designed, the price competition inherent to the auction scheme increases cost efficiency and allows
price discovery of RE-based electricity, avoiding potential windfall profits and underpayments.
Auctions could be multi-stage and could be technology-specific or technology-neutral, although it is
very difficult to design an auction that is actually neutral to all technologies.
Successful auctions that meet the goals of both policymakers and society balance the trade-offs
between: (a) specific auction design elements and the electricity market design; and (b) the context
in which the auctions take place. There are three main types of auction formats2: the sealed-bid
auction, the descending clock auction, and the hybrid auction (used in Brazil).
The design features of auctions, namely the auction’s demand, qualification requirements, winner
selection, and investor risks and liabilities, strongly influence the price outcomes. Across the
different auction design elements, policy makers should carefully consider the inherent trade-offs
between potentially the most cost-effective outcome and other objectives. International experience
shows that auctions can only contribute to effective and efficient RE deployment if they are designed
to match the market environment in the area where the auction is conducted, taking into account
specific policy goals, the supply-demand situation of RE projects, the project pipelines in comparison
1 Excluding large hydro above 50MW
2 Lucas, Hugo, Rabia Ferroukhi and Diala Hawila (2013). Renewable Energy Auctions in Developing Countries. IRENA.
6 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
to deployment targets, potential bidder structure, competitive positioning of bidders, risk of
collusion, experience of bidders and/or the auctioneer, and the level and quality of market and cost
information, among others.3
International experience shows that auctions can only successfully contribute to achieving effective
and efficient RE deployment if they are specifically designed to match the market environment in the
area where the auction is conducted, taking into account specific policy goals, the supply-demand
situation of RE projects, project pipelines in comparison to deployment targets, potential bidder
structure, competitive positioning of bidders, risk of collusion, experience of bidders and/or
auctioneer with previous auctions, level and quality of market and cost information, and more. The
review of literature suggests that the following practices be taken into consideration when designing
auctions:
• Adapt auctions to the specific situation
• Secure sufficient competition
• Secure Project realization
• Simplify and Streamline Procedures
• Provide clear, timely and all relevant available information to stakeholders
The Pakistan Context
Government of Pakistan is currently in the process of developing a revised RE policy and has
indicated its intent that future procurement would be through competitive bidding process. Recent
reforms in Pakistan provide now the context for moving forward to a more competitive
procurement through energy auctions for new renewable energy projects. RE procurement and
design of auctions in Pakistan is likely to be impacted by a number of factors as follows:
Macro-economic environment and state of the power industry: The macro-economic environment
and state of the power industry in Pakistan is of particular concern to the RE investors. It is faced
with balance-of-payment, foreign-exchange reserve, and country risk-rating challenges, and the
power sector is still in transition from a centrally-controlled to market-based industry. Unless the
real and perceived risks arising out of this situation are adequately addressed in the auction design,
investor-interest is expected to be limited. Different design elements should be combined to meet
the goals of the auction, according to the country’s specific requirements and characteristics as well
as the macro-economic realities.
Financial health of the power sector: Circular debt in the power sector and contribution of the
distribution utilities are significant impediments to investment. Unless a clear path towards the
resolution of the structural issues contributing to the phenomenon of circular debt are put in place,
investors are either likely to stay away or ask for substantial risk-coverage by the Government.
Interconnection arrangements: NTDC’s capacity to successfully integrate RE into the grid is of
particular concern for investors. Several projects have been delayed on account of its inability to
provide timely interconnection arrangements.
Quality of investors: Special attention needs to be placed on attracting quality investors under the
auctions to be launched in Pakistan in the future. Prior investor experience in RE project
development lowers operational and credit risks and increases the likelihood of successful
implementation (and ability to reach financial close based on investor track records).
3 Report: “Auctions for renewable energy support - Taming the beast of competitive bidding” Final report of the AURES
Project; 2017
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 7
Selected issues to be addressed: In order to enhance investor interest and assure the success of
auctions in Pakistan, following issues need to be addressed: (a) benchmark tariff-setting and approval
by NEPRA; (b) development of standardized transaction documents in conformance with the rules
and regulations of the relevant institution by AEDB; and (c) review of procurement process and
procedures, including an assessment of information technology (IT) requirements for reverse
auctions.
Recommendations
Development of institutional capacities: There is a need to dedicate resources to develop the
institutional capacities not only in the execution agencies but also in oversight and monitoring
agencies.
Inter-agency coordination: The coordination between MOE, AEDB, and provincial energy
departments, and NEPRA should be improved and institutionalized given the program complexity
envisaged. In this regard, coordination on the Federal- and Provincial sponsored on-grid RE projects
and the roles and responsibilities of relevant institutions should be clearly established.
Empowerment of procurement teams: It is critical that the procurement management team should
be capable and competent in managing transaction advisers and have a high degree of operational
autonomy. The team should It is crucial, that the team comprises professionals from both the private
sector and government officials. The procurement process often requires proof of numerous
consents and approvals at the all levels - national, provincial and municipal levels, and these should be
processed earlier and facilitated from the program’s early stages. The approval process should be
coordinated and streamlined.
Adequate resources and transaction advisors: Adequate funding is needed to hire expertise for the
design of the procurement program and its associated documentation and contracts. Funding can
come either directly from the government or from a loans or grants from development finance
institutions. What is needed is to secure expertise and experienced advice should be procured at
the design stage, as this is critical to the program's ultimate success. The benefits of low prices from
a well-designed auction justify the costs of hiring professional expertise to help design and run the
auctions. The ongoing costs of subsequent bid rounds may be covered by charging project
development fees to successful bidders.
Standardization of procedures and documents: A successful outcome of competitive tender requires
it to provide a level playing field, with including standardized (template) contracts and documents.
The tender documentation, including Request for Qualification (RfQ) or Request for Proposals
(RfPs), and their associated contracts, must be of the highest standard, based on international best
practice. They should also allocate risks appropriately. At a high level, the RfP requirements must be
carefully designed to filter out parties that are not financially, technically or legally capable of carrying
out the project as promised within the given timeframe. Contracts should be standardized, and non-
negotiable and bankable.
Technology-specific versus technology-neutral competitive tenders: It may be possible to run a
multiple technology competitive tender for multiple technologies, using the same tender
documentation with common qualification and evaluation criteria, as well as certain technology-
specific requirements and contracts (for example, technology-specific PPAs). However, it is
proposed that initially in Pakistan, there may be technology specific tenders and then after a first few
rounds, competition between technologies is held. As Pakistan goes forward, it may be possible that
multiple technology tenders are used for revealing relative market prices, which will reveal those
technologies which have the greatest promise for cost and price reductions. In the medium- to long-
term, it is recommended Pakistan may consider embarking on technology-neutral auctions.
8 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Programmatic approach to tenders – size for the first round: The size of individual projects
permitted should be capped to encourage more competition and to reduce buyer risk through a
diversified seller base. No specific size (MW) is being proposed, as it would be dependent on the
timing of the auction. However, this cap must not be so low that it prevents projects from achieving
economies of scale that would reduce bid prices. There is a tension between designing an auction
that incorporates economies of scale and seeks lowest prices and one that also seeks maximum
participation by smaller local project developers. The creation of a competitive environment should
be balanced with local, broad-based procurement.
Multiple-bid rounds: Multiple bid rounds, with smaller capacity blocks should be made available for
tender. One of the most important lessons from international experience is that there is value in
running sequential auctions at regular intervals, and capping the power capacity that is auctioned in
each auction or bid round. This stimulates competition and drives down tariffs by ensuring that
demand (from bidders) exceeds supply (that is auctioned) in each round. The capacity on offer,
though, should not be so small as to discourage investor interest. Multiple bid windows are
attractive because to bidders because the perceived a greater chance ‘higher chance’ of being
awarded a project at some point, knowing that there will be several rounds of capacity on offer,
encourages more investors to participate. Multiple bid rounds also allow for lessons to be learned
and improvements to be made to streamline and refine the tender documentation and legal
contracts with each bid round. It is thus recommended that Pakistan to start with smaller capacities
to be tendered based on such criteria such as location, grid availability, and required demand, etc.
and then gradually ramping up the program through larger capacity offerings in later rounds.
Interconnection: Grid connection planning must be coordinated with the RE program. This is
especially relevant in Pakistan given issues relating to power evacuation and interconnection, in the
recent past and where transmission constraints have delayed and frustrated the RE project
development of RE projects. It may be beneficial for project sites to be limited to specific zones
where transmission capacity is or would be in place, or could be strategically upgraded to serve
numerous.
Land acquisition: It is recommended that the government plays a facilitation role in site selection and
acquisition of land for RE projects by the private investor. The acquisition is proposed to be on fair
market value.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 9
1. INTRODUCTION
This document is part of Task-8 of SEP work plan for FY19, and the objective is to: (a) analyze
selected policy issues that may impede the development of renewable energy (RE) resources in
Pakistan; (b) bring global best practices in renewable energy policies to develop pros and cons for
feasible options; and (c) present a limited set of recommendations related to policies that are
important for least-cost renewable energy development in Pakistan. This work could be used by the
Government to consider policy options that specifically support large-scale development of the
renewable energy industry.
A series of Policy Notes are being developed under this Task, as follows:
• Value of Variable Renewable Energy (VRE) and Impact on the Power System.
• Renewable Energy Procurement and Design of Auctions.
• Location of Renewables and Renewable Energy Zones (REZs).
• Renewable Energy Market Development.
This Policy Note provides an overview of RE Procurement and design of auctions and specification
of the enabling framework.
1.1 BACKGROUND
The Government of Pakistan and its agencies including the Ministry of Energy (MOE) and Alternative
Energy Development Board (AEDB) had earlier requested assistance on competitive procurement /
bidding process for Renewable Energy (RE) projects. Sustainable Energy for Pakistan (SEP) had
accordingly earlier provided assistance through the:
• Organization and facilitation of a 5 days workshop in Bangkok, Thailand in late 2017 –
supported by the U.S. Agency for International Development (USAID) and the United States
Energy Association (USEA). The focus of the workshop was to introduce participants to
reverse power auctions and identify best practices, as well as provide them with the
institutional and human capacity required for designing, managing, and operating a power
trading entity on the national scale4. The training served as a follow-up to the Pakistan Clean
Energy Business Opportunities Conference, held in December 2015 in Washington, DC.
• Presentation to the then Minister for Power and MOE in early 2018 on the prerequisites for
conducting energy auctions in the country. The presentation highlighted the requirements
and the illustrative steps in this regard.
• Sharing of information with AEDB on the design of auctions and competitive procurement.
This included working group discussions with AEDB and other stakeholders on the enabling
framework and international experiences for competitive procurement / auctions. The first
of such discussion took place in May 2019 wherein the global experience for RE
development was shared.
1.2 STATE OF RENEWABLE ENERGY DEVELOPMENT
The renewable energy market in Pakistan to date has largely evolved through unsolicited projects for
utility-scale on-grid capacity5. The Government had solicited under Renewable Energy Policy 2006
4 The delegates included representatives from Pakistan’s Ministry of Energy, Alternative Energy Development Board,
Private Power Infrastructure Board, and provincial energy departments. The workshop also enabled participants to
interact with speakers from South Africa and Brazil on conducting reverse power auctions
5 Notwithstanding the on-grid RE development, about 25MW of RE distributed generation capacity through Net
Metering has been installed in Pakistan during the last 3-4 years.
10 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
and received proposals for about 8,000 MW of RE capacity (mostly solar, wind and bagasse) in the
past which have been divided into four categories in accordance with the stage of project
development. Categories I and II projects (about 1,500 MW), where either the Letter of Support
has already been provided or the financial-close is imminent (advanced transactions) are being
actively pursued. For the remaining projects (about 6,500 MW), the Government has announced its
intention to undertake a competitive process to procure a pre-determined RE capacity in keeping
with the electricity demand and ability of the transmission system to absorb the Variable Renewable
Energy (VRE).
1.3 HISTORICAL PROCUREMENT PROCESS
Pakistan had historically adopted Feed in Tariffs (FITs) by technology-type which included a
standardized template for energy purchase. For example, National Electric Power Regulatory
Authority (NEPRA) wind FITs were established at USc 6.75/kWh (foreign financing) and at USc
7.73/kWh for projects funded through local financing. The process followed by the sponsors of RE
projects entailed a number of steps as broadly described in the following description. AEDB and the
provincial energy departments issued Letters of Intent (LOI) to private sponsors for establishing the
viability of RE projects including conducting the feasibility studies, technical analysis, environmental
assessments and commercial considerations. Also, the sponsors followed up with NEPRA for a
generation license and tariff setting, pending the AEDB and energy departments’ approvals. Upon
NEPRA approval of the generation license and determination of the tariff, the developer submitted a
performance guarantee. At the same time and upon completion of these steps, both for solicited
and unsolicited projects, a Letter of Support was issued either by AEDB or the provincial energy
departments, and the sponsors could then proceed to negotiate with the lenders and financially-
close the project with different participating stakeholders.
1.4 KEY DOCUMENTATION AND TYPICAL TIMELINES FOR
RENEWABLE ENERGY PROJECTS
The key documents during the past procurement included the Energy Purchase Agreement (EPA),
the Implementation Agreement and the site sublease for land acquisition if the land was allocated by
the AEDB and / or the provincial governments. The timeline envisaged for the process was
approximately 18 months (for the completion of the feasibility study, the National Transmission and
Dispatch Company (NTDC) approval of grid interconnection study and power purchase consent,
the environmental study and the approval by the provincial Environmental Protection Agency (EPA),
and the award of tariff and generation license by NEPRA, finalization of arrangements between the
sponsor and lenders to complete the requirements for financial close). However, in practice, the
overall project preparation process typically took a lot longer than the originally anticipated 18
months.
1.5 ALTERNATIVE AND RENEWABLE ENERGY POLICY
The Government of Pakistan is currently in the process of developing a revised RE policy and has
indicated its intent that future procurement would be through competitive bidding process.
Internationally, the implementation of competitive procurement through energy auctions have over
time demonstrated major reduction in costs and time, building upon the maturity of the markets and
management and technology innovations. Recent reforms in Pakistan provide now the context for
moving forward from FiTs to a more competitive procurement through energy auctions for new
renewable energy projects.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 11
1.6 OBJECTIVES OF THE POLICY NOTE
This note endeavors to provide guidance on the overall framework for competitive bidding for RE
projects and some insights with respect to:
• Policy and processes to make RE procurement lower in cost, more competitive and simpler.
• Approaches for the preparation of bid documents.
• Auction designs to allow price and cost improvements during the bidding process.
• Imposition of specific performance and operational obligations on RE generators to deal with
the impacts of RE on the system.
• Potential obligation on RE generators to pay for and maintain their own transmission
interconnection, and advisability of including the interconnection cost in the bid-price so that
the full cost of RE generation can be determined.
• Establishment of capacity and price caps to ensure timely transmission additions needed for
RE projects.
• Design of auction series including regular auctions to help build the market and in keeping
with the demand and transmission system absorption capability.
12 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
2. INTERNATIONAL EXPERIENCE
International experience shows that renewable energy auctions (or other variation of competitive
procurement) are a policy tool and market mechanism for promoting the deployment of RE. As a
market mechanism, auctions enable governments to contract a pre-defined volume of energy at a
competitive cost. When well designed, the price competition produced by the auction mechanism
improves cost-efficiency and enables price discovery of RE based electricity generation. Despite
difficulties in implementation – auctions are especially context specific and no one model is
applicable to all circumstances - RE auctions have become the most common method for large-scale
procurement of renewable generation capacity, with at least 67 countries implementing RE auctions
in 2017. Since 2010, the Bloomberg New Energy Finance Auctions Database records 267,000 MW of
renewables procured in a total of 726 separate auctions worldwide.
Renewable energy auctions are also known as “demand auctions” or “procurement auctions”,
whereby the government issues a call for tenders to install a certain capacity of renewable energy-
based electricity. Project developers who participate in the auction submit a bid with a price per unit
of electricity at which they are able to realize the project. The government evaluates the offers on
the basis of the price and other criteria and signs a power purchase agreement (PPA) with the
successful bidder.
Auction schemes have benefited from the rapidly decreasing costs of renewable energy technologies,
the increased number of project developers, their international exposure and know-how, and the
considerable policy-design experience acquired over the last decade. When well designed, the price
competition inherent to the auction scheme increases cost efficiency and allows price discovery of
renewable energy-based electricity, avoiding potential windfall profits and underpayments. While
auctions have become very attractive, they largely benefit the successful bidders and tend to favor
relatively large players that are able to afford the associated administrative and transaction costs.
Based on national energy plans as well as the size and maturity of the renewable energy market, the
design of auction schemes reflect each country’s priorities in terms of technology, volume and
location. Technology-specific auctions allow for the promotion of certain technologies and
diversification of the portfolio. In addition to selecting the technology, auctions can be site-specific.
The identification of sites with ideal resources and secured grid connection potentially reduces risks
to investors. Technology neutral auctions have also served to promote renewable energy
technologies, which have even been able to compete with fossil fuels on certain occasions. The
design of auctions allows governments to include other national priorities, the most common one
being local content requirements.
2.1 FEATURES OF ENERGY AUCTIONS
Instrumental to the design of auctions are stringent bidding requirements (financial, environmental,
grid connection, etc.) and strong compliance rules (penalties, bid bonds, project completion
guarantees, etc.) that reduce the risk of underbidding, project delays and project failure.
As with other deployment policies and support mechanisms, the successful implementation of
auctions relies on an appropriate regulatory and institutional framework, relevant skills and adequate
infrastructure to attract investors. In designing and implementing auction schemes, policymakers may
want to consider the following elements:
• Type of auction format to be employed: The most common type of auction is the sealed-bid
auction. In a sealed-bid auction, participants submit their bids simultaneously and are
unaware of the competitors’ bids. The auctioneer ranks and awards projects until the
cumulative volume is equal to the volume being auctioned. The sealed-bid auction is simple,
easy to implement, fosters competition and avoids collusion. Descending clock auctions are
more difficult to implement, but they allow for a fast price discovery as well as greater
transparency.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 13
• Ceiling price disclosure: Greater competition is ensured if the ceiling price is disclosed to
the bidders upfront.
• Auction volumes and bidding rounds: The size of the procurement volume may be
determined in relation to the capacity of the market to deliver electricity to the customers.
Determining the optimal number of rounds and the volumes that create greater competition
is a challenge that requires learning by doing.
• Bidding procedures: Streamlined administrative procedures, with communication and
transparency provided equally to all bidders, are essential to the success of an auction
scheme.
• Guarantees and penalties: Strong guarantees and penalties are essential to the success of
auction schemes, preventing potential underbidding and minimizing the risk of project delays
and completion failure.
2.2 AUCTION DESIGN
Successful auctions that meet the goals of both policymakers and society balance the trade-offs
between: (a) specific auction design elements and the electricity market design; and (b) context in
which the auctions take place. In general, auction design is under-pinned by these broad principles:
• The auction scheme should result in RE at the lowest feasible cost and greatest efficiency.
• Auctions should be designed to meet the objectives of the government and
utilities/purchasers that are procuring renewable energy.
• Auction design must be consistent with the broader market context, allocating risk
efficiently among auction participants so that auction trade-offs do not favor one participant
or class of participants (i.e. investors, government, rate-payers) over another.
• Auctions should deliver the required level of RE deployment in the targeted timeframe;
accepted bids must be credible and have a high likelihood of achieving completion on time.
• The auction arrangements should be transparent, open, predictable and objective, earning
broad investor confidence.
• Auction arrangements should minimize market distortions and facilitate market
development.
• Electricity markets and contexts are constantly and rapidly changing. As more auctions are
held, new innovations, previous design flaws and/or unintended consequences may emerge.
Auction administration and design therefore need to be flexible.
Although auction design elements are not universally applicable, most countries follow a somewhat
similar process to implement RE auctions, which comprises of the following steps:
• Evaluation of feasibility of auctions.
• Formats of auction:
Sealed-bid auction.
Descending clock auction.
Hybrid auction.
• Auction design:
General design elements.
Auction procedure.
Conditions of participation.
14 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Deadlines and penalties.
Institutions.
• Implementation and conducting the auctions.
• Evaluation of outcomes.
A summary of good practices in auction design is provided in the following paragraphs. Further
details of the above steps, including the design elements, key options, and considerations for
choosing a particular option, are provided in the succeeding paragraphs and in Annex A.
2.3 EVALUATION OF FEASIBILITY OF AUCTIONS
International experience demonstrates that the Government needs to clearly establish the policy
objectives for the development of RE in the short-, medium- and long-term, and take cognizance of
the market and regulatory environment upfront before launching any auction. In most cases, RE
development is motivated by bulk-generation supply cost reduction through the globally-declining
cost of RE but may include other policy objectives such as ascertaining the true cost of generation by
different technology type (cost discovery) or balancing the development of different sources of
renewable energy (generation-mix diversification) in relation to resource endowment in the country.
An important policy consideration is the socio-economic development of different parts of the
country as RE projects typically spurs economic activities and creates jobs. The Government needs
to also have a clear understanding of the size of the market and the volume of RE capacity that could
be absorbed by the transmission system in the short-term. Market-sounding events can enable the
Government to identify the universe of interested investors and their concerns with the regulatory
environment prevalent in the country. Literature on auctions has shown that preparatory work
relating to an evaluation of the feasibility of auctions, undertaken by a Government-designated entity,
goes a long way in establishing the robust competitive framework in a country.
2.4 FORMATS OF AUCTIONS6
There are three main types of auctions: the sealed-bid auction, the descending clock auction and the
hybrid type of auction (used in Brazil) where the first phase operates as a descending clock auction
then the second phase operates as a pay-as-bid sealed-bid auction.
Sealed-Bid Auction:
In the sealed-bid auction, bidders simultaneously submit their bids with an offer of price and quantity,
and no bidder is envisaged to know the offered price of the other participants. Bids that meet all of
the mandatory requirements outlined in the call for tenders are ranked from the lowest to the
highest price if the evaluation is based on the price only. According to the government’s priorities,
there is a possibility to rank projects not only according to price, but also to include a more
comprehensive set of criteria, such as the project’s contribution to local industrial development, the
project developer’s technical expertise, etc.
The selection of bids can take place in one or two phases. In a single-phase sealed-bid auction, no
pre-qualification exercise is undertaken and all interested investors are allowed to bid. However, in
the two-phase selection process, an initial pre-qualification in the first phase is undertaken to identify
bidders who would be allowed to tender. Pre-qualification is used in certain cases (large projects
and those requiring technical expertise) and it helps narrow the field to only those who have the
technical and financial capability to comply with the terms of the contract. In the second phase, pre-
qualified bidders submit bids which are then evaluated.
6 IRENA_Renewable_Energy_Auctions_in_Developing_Countries.,2013 Hugo Lucas, Rabia Ferroukhi and Diala Hawila
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 15
Descending Clock Auction:
The descending clock uses multi-round bids where the auctioneer announces a price for acquiring
the RE electricity generated. Bidders bid for the right to provide the quantity of RE electricity they
wish to supply at the going price announced. The auctioneer progressively lowers the price (which
results in a lower quantity offered from bidders) until the quantity offered matches the quantity to
be procured. This is a more dynamic auction system where participants know each other’s bids and
adapt their price and quantities accordingly in subsequent rounds.
Hybrid Auction:
A hybrid can be used as in the case of Brazil. This describes an auction where the first phase
operates as a descending clock auction then the second phase operates as a pay-as-bid sealed-bid
auction. In this case, the use of a hybrid auction aims at taking advantage of the benefits of both
auction systems: price discovery in the descending clock auction and avoidance of collusion between
small numbers of participants for setting the final price in the sealed-bid auction.
2.5 AUCTION DESIGN 7
For renewables to achieve their full potential, the auction design needs to be adapted to the specific
conditions of the country, which include: the economic situation, the structure of the energy sector,
the maturity of the power market and the level of renewable energy deployment. In addition, the
design of the auction needs to be aligned with the country’s overall objectives, which may go beyond
the achievement of deployment rates at minimum costs. Although there is no doubt that auctions
have improved the price competitiveness of renewables, a full understanding of the factors that have
contributed to the recent prices is essential to making well-informed decisions regarding future
auction design.
The prices attained in recent auctions are influenced by several factors; some relate to the auction
design and others to an enabling environment, including:1) country-specific conditions and access to
finance; 2) investors’ confidence related to the presence of a conducive environment; and 3) the
presence of other policies aimed at supporting renewable energy development.
Costs of renewable energy projects may be affected by policies adopted to support the development
of renewable energy. In the United States, for example, investment tax credits have been offered to
attract investments in solar PV projects, reducing investment costs by about 30 percent, a reduction
that has been reflected in the price outcomes. Access to finance considerations are largely related to
the variations in the weighted average cost of capital, reflecting both the country’s financing
conditions (the cost of debt) and investors’ perception of the risks of owning renewable assets in the
country (the cost of equity). These factors explain many of the country-to-country differences in
auction prices. Investors’ confidence can be strengthened by a stable, enabling environment that is
conducive to market growth through a clear target backed by a strategy and policy actions. For
instance, the commitment of the Government of India to its ambitious solar target of 100 GW by
2022, coupled with strong policy action, has given project developers, financing institutions and
other market participants confidence in the country’s solar program, despite challenges faced in
some states related to off-taker credibility. Off-taker risks are common in emerging economies and
they strongly influence the risk perception among investors. These risks can be mitigated by ensuring
that demand-side responsibilities will be met by offering additional guarantees to back the contract, if
needed. In Argentina, the government provides liquidity guarantees ensuring the continuity of cash
flow to the developers as well as termination guarantees shielding developers from counterparty
risks that are also backed by the World Bank. The impact of investors’ confidence on the price
outcomes is mainly illustrated by countries where accumulated experience from recurring auctions
has resulted in persistently lower prices (e.g., South Africa and India). A long-term auction program,
with a predictable schedule of auction demand, and a high degree of transparency all contribute
positively to the level of competition in the auction
7 IRENA_Renewable_Energy_Auctions_2017.
16 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
The design features of auctions, namely the auction’s demand, qualification requirements, winner
selection, investors’ risks and liabilities, all strongly influence the price outcomes. Across the
different auction design elements, policy makers should carefully consider the inherent trade-offs
between potentially the most cost-effective outcome and other objectives. Some important
considerations are as follows:
• When the objective is to develop a particular technology, a technology-specific auction can
be selected. If the goal is minimizing costs, a technology-neutral auction can be introduced,
allowing competition between technologies (e.g., Brazil). When the objective is to meet
urgent capacity needs while retaining flexibility in holding auctions, the total volume can be
auctioned at once, through a standalone auction. If the objective is to further enhance
investors’ confidence for a more cost-effective outcome, the total volume auctioned can be
divided into different rounds in a systematic auctioning scheme. This facilitates long-term
planning by policy makers, bidders, and equipment suppliers, which may be beneficial to the
grid planning and to the country’s renewable energy industry. If the objective is to meet
broader development goals, the auction design can include additional selection criteria. Local
content requirements, for example, can support the domestic industry, job creation and
other socio-economic benefits. Such requirements are most effective when aligned with
other design elements, such as a long-term auction schedule, and applied with other
supporting policies.
• Qualification requirements are key determinants of the competition in the auction and the
prices offered by developers. They can be focused on 1) ensuring that the project will
deliver as per the contract by requiring bidders to conduct assessments and obtain permits
as a prerequisite to be able to bid, and 2) ensuring the capability of the developer to
successfully deliver the project through technical, financial and reputational requirements.
• The criteria for selection, ceiling prices and limits on project size can significantly impact the
price outcomes, with the possibility of facing the trade-offs. While a simple winner selection
process based solely on the price can improve cost competitiveness, other objectives can be
achieved by incorporating non-monetary criteria, such as socio-economic benefits and
project location.
• When the main objective is to ensure cost effectiveness, a low ceiling price can be set, above
which bids are not considered. However, there is a risk that a sub-optimal amount of
renewable energy will be contracted, as it could lead to the rejection of some reasonable
bids. Experience has shown that keeping the price ceiling undisclosed can help increase cost
effectiveness, but at the risk of disqualifying potentially good projects that are just above the
ceiling (e.g., early auctions in Peru). Disclosing the ceiling price in auctions where
competition is not fierce might result in equilibrium prices right below the ceiling (e.g., the
first round in South Africa).
• A limit on the project size or on the volume that can be won by one bidder also impacts the
price. Such measures were put in place in Zambia to diversify the portfolio of generators and
reduce risks in case projects do not materialize. Auctions that have no limit on project size
can benefit from economies of scale, as in the case of Dubai and Abu Dhabi in the United
Arab Emirates, where 800 and 1,170 MW of solar was contracted respectively, at record-
breaking prices.
• Appropriate Risk Allocation between the public and private sectors is a critical element in
the auction design. In determining the sellers’ liabilities in the PPA, there are various ways to
allocate financial, operational and production risks between the project developer, the
auctioneer and the off-taker. Trade-offs that need to be considered in the allocation of risks
and liabilities to developers include:
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 17
o Auction design features can limit the developers’ risks resulting in lower prices, but
these risks would then be passed on to the off-taker. Currency, inflation and production
risks can be reduced through auction design. In Chile, contracts are denominated in U.S.
dollars and indexed to U.S. inflation, protecting developers from currency exchange and
inflation risks. In addition, the newly introduced hourly supply blocks protect generators
from production risks, reducing exposure to spot energy prices in case of deviation from
the contracted amount. This is one of the factors that led to the record-breaking low
solar prices in Chile’s 2016 solar auction.
o Liabilities can be reduced to encourage participation and increase competition, but at
the risk of facing project delays or underproduction. Investor liabilities involve
commitment to contract signing and project completion as well as compliance rules and
penalties. These are important measures to ensure that projects are developed as per
schedule to meet the capacity needs of the power sector. However, if these measures
are too strict, competition in the auction will be reduced, leading to higher prices.
2.6 SUMMARY OF GOOD PRACTICES IN AUCTION DESIGN 8
International experience shows that auctions can only successfully contribute to achieving effective
and efficient RE deployment if they are specifically designed to match the market environment in the
area where the auction is conducted, taking into account specific policy goals, the supply-demand
situation of RE projects, project pipelines in comparison to deployment targets, potential bidder
structure, competitive positioning of bidders, risk of collusion, experience of bidders and/or
auctioneer with previous auctions, level and quality of market and cost information, and more. The
optimal auction design for a single implementation therefore may be very different from the optimal
auction design for a different market or even time period. The review of literature suggests that the
following practices with benefit be taken into consideration when designing auctions:
Adapt auctions to the specific situation:
• Auction design needs to match the current market environment and policy goals.
• Auction design needs to be flexible and be updated often to accommodate changes in
market situation and policy goals and to correct for previous unwanted incentives.
Secure sufficient competition:
• Attract as many serious, true-cost bids as possible, by carefully choosing appropriate auction
designs.
• Ensure a large enough pool of similarly strong bidders.
• Implement participation enhancing measures including an active communication strategy,
stakeholder consultations, on draft specifications, well in advance of bid preparation.
Secure Project realization:
• Ask for binding bids.
• Implement both pre-qualification requirements and penalties (especially material pre-
qualification regarding project development stage and bid bonds).
8 Report D9.2, December 2017 Auctions for renewable energy support - Taming the beast of competitive bidding Final
report of the AURES Project
18 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Simplify and Streamline Procedures:
• Define clear and simple selection criteria.
• Avoid too harsh or confusing rules (such as stringent timelines, difficult to obtain
documentation, etc.).
• Use sealed format auctions and consider pay-as-bid pricing if bidders and/or auctioneer are
inexperienced, little cost or market information is available, and the competitive situation is
uncertain.
Provide clear, timely and all relevant available information to potential investors:
• Avoid uncertainty by missing or unclear information that leaves room for interpretation
and/or speculation by bidders.
• Publish a transparent and continuous auction schedule.
• Implement cost-based ceiling prices (acts also as a safeguard in case of low competition / too
few bids).
• Prioritize stakeholder consultations.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 19
3. CONSIDERATIONS FOR COMPETITIVE
PROCUREMENT IN PAKISTAN
International experience suggests that competitive procurement mechanisms, such as auctions, can
procure RE at lower prices if there is significant interest from investors and thus a high degree of
competition. Policy makers, therefore, need to address barriers to the development of RE posed by
the broader policy and regulatory framework. Policy consistency and predictability have significant
influence on private-sector investment decisions. Having competitive bidding may also be an effective
tool for real price discovery but should also be flexible in the auction design, and tailored to the
specific context and country objectives.
Based on international experience, when selecting design elements, policy makers in Pakistan should
carefully consider the inherent trade-offs between potentially the most cost-effective outcome and
other objectives, keeping in mind the following lessons:
• In defining the auction’s demand, ambition for a greater role of renewables in the energy mix
must be weighed against objectives and cost and system effectiveness. For example, if the
goal is minimizing costs, a technology-neutral (if feasible when weighed against complexity)
auction can be introduced, allowing competition between technologies, therefore favoring
the more tested and cost-competitive ones.
• If the policy objective is to further enhance investors’ confidence for a most cost-effective
outcome, the total volume auctioned, if considerable, can be divided into different rounds in
a systematic auctioning scheme, with a cap on the volume auctioned in each round. This
facilitates long-term planning by policy makers, bidders, and equipment suppliers, which may
be beneficial to the country’s renewable energy industry and for the grid planning and
development by NTDC.
• In establishing the qualification requirements, there is a trade-off between reducing entry
barriers to encourage competition and discouraging potential project implementation issues
i.e. allowing the participation of a large number of bidders while ensuring that they can
successfully deliver the project. This requires a careful selection of qualification
requirements which should as a minimum cover technical credentials (prior experience of
putting-up and operation of a RE project of a certain size (MW) and financial capability (a
balance-sheet commensurate with the size of the RE project being bid).
• If the objective is to also meet broader development goals, policy makers can include
additional selection criteria. Local content requirements, for example, can support the local
industry, job creation and other socio-economic benefits, but should not result in any
significant adverse impact on the commercial and financial viability of the project. Such
requirements are most effective when aligned with other design elements, such as a long-
term auction schedule, and applied with other supporting policies.
• While a simple winner selection process provides greater transparency, some degree of
complexity may have to be implemented to ensure that other objectives of the country are
achieved by the auction. For example, if the objective is to reach the lowest price using a
simple and straightforward procedure, policy makers can choose to adopt the classical
minimum-price criteria for the selection of a winner. However, other objectives can be
achieved by incorporating non-monetary criteria, such as socio-economic benefits, location,
developer’s experience etc. In such cases, the process of evaluation of other non-monetary
elements of the bid must be provided to all bidders upfront and should leave little or no
room for discretion. The process of inclusion of non-monetary factors may, however, result
in higher prices and a more complex mechanism.
20 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
• When the main objective is to ensure cost effectiveness, policy makers can also set a ceiling
price above which bids are not considered. However, if the ceiling price is not calibrated
properly, there is a risk that a suboptimal amount of renewable energy will be contracted, as
it could lead to the outright rejection of certain perfectly reasonable bids. Experience has
shown that keeping the price ceiling undisclosed can help increase the cost effectiveness of
the scheme but at the risk of disqualifying potentially good projects that are just above the
ceiling.
• If though out properly, incorporating the REZs concept in auction design can be a useful tool
in sharing interconnection and grid enhancements costs with potential investors of RE
projects.
• Battery energy storage systems (BESS) are becoming a cost-competitive flexibility provider.
Building these as part of required services in auction is possible but may require
modifications to policy, market and regulatory frameworks to accelerate BESS deployment
and ensure these resources can participate in the power system to provide flexibility
services.
• Developers might be subject to risk, but they should not be subject to uncertainties. The
risk allocated should be clearly communicated, should be transparent, fully quantifiable, and
enforced. Protecting possible bidders against uncertainties is key to gaining their confidence.
• Policy makers need to consider evaluating the process at the end of each bidding round as it
is important to factor lessons learned into the design of the following rounds.
• Administrative procedures should be simplified, streamlined and facilitated when possible
(permits, grid connections, etc.). Setting up a one-stop-shop could help minimize transaction
costs and efforts of the bidders, preventing delays in project implementation.
• The time, resources and skills needed to process the auction modalities have to be carefully
estimated.
3.1 RISK ALLOCATION AND MITIGATION
Policy makers should minimize the investors’ perceived risk through an institutional and regulatory
framework that ensures a predictable and stable environment for investments. A good auction
design is not enough in a market in which the levels of skepticism and lack of credibility is high.
Following are some of the significant aspects requiring consideration:
• Macro-economic environment and state of the power industry: There is no “one-size-fits-
all” formula for successful auctions9. Different design elements should be selected and
combined in a way that is tailored to meet the goals of the auction, according to the
country’s specific requirements and characteristics. While determining which auction design
best fits the specific context, policy makers should take the following types of constraints
into account: (a) those arising from the macro-economic conditions (local and global); (b)
the state and characteristics of the power sector in Pakistan; and (c) the quality of
equipment and lack of enforcement of standards are significant concerns in the Pakistani RE
marketplace.
9 Comparison of prices from bidding processes in other countries to Pakistan may not be appropriate as it is not an
“apples to apples comparison”. For example, in Government in UAE offered many subsidies (like provision of land and
site preparation), bore much of the operational risk, provided clear RE long term energy mix targets with supportive
policy, had a very strong country risk rating, and provided a 60-40 transaction structure where the sovereign owned
40% of the project through the municipality which essentially create a credit enhancement – all of which reduced
project developer risks to enable a world record low price. Given the greater risk perceptions and lack of an enabling
environment in Pakistan these prices cannot be recreated in Pakistan. Who bids and at what price depends very much
on the country, access to affordable finance, and project risk profile.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 21
• Quality of investors: Prior developer experience in RE project development lowers
operational and credit risks and increases likelihood of successful implementation (and ability
to reach financial-close based on track record of the investor).
• Near absence of long-term integrated planning: Lack of long-term electricity supply and
demand forecasting, and sector-wide integrated energy plan, is a significant issue for RE
developers.
• Interconnection arrangements: Ability of NTDC to successfully integrate RE into the grid is
of particular concern for all investors, and several projects have been delayed on account of
inability to provide timely interconnection arrangements.
• Policy and regulatory framework: Consistency of policies, regulations, and terms of the
transaction deals is a major concern. A competitive process with full transparency, and
symmetry of information to all bidders, would minimize this risk going forward.
• Financial health of the power sector: Circular debt and Distribution Company (DISCO) role
are impediments to investment, along with current Pakistan macroeconomic situation/recent
depreciations of currency/depleting Foreign Exchange (FX) reserves, and country risk rating.
3.2 AREAS THAT NEED TO BE REVIEWED AND ADDRESSED
Approval and Tariff-setting by NEPRA: As sole power market regulator, NEPRA has been
determining tariffs for generation, transmission and distribution since 1998. It draws its powers from
an establishing document, “National Electric Power Regulatory Authority (Tariff Standards and
Procedure) Rules, 1998”. Renewable energy projects are categorized as “Solicited” or “Unsolicited”.
The government requests proposals for solicited projects from investors based on predefined
specifications by conducting a competitive bidding. This practice has been carried out in the thermal
power sector, for which the Private Power Infrastructure Board (PPIB) has conducted multiple
international competitive calls for coal and other thermal projects since 2008. In the renewables
sector, AEDB has not yet solicited any projects but several projects are in an advanced stage of
development. However, NEPRA issued directives in January 2017 for future utility-scale wind and
solar Photo-voltaic (PV) projects to undergo a competitive bidding process as solicited projects.
NEPRA set a benchmark tariff for wind projects in January 2017 and instructed AEDB and other
relevant agencies to initiate competitive bidding. For solar PV projects, no benchmark tariff has been
determined either by NEPRA or any other agency. For these auctioning rounds, NEPRA requires the
process to be developed in line with the NEPRA Competitive Bidding (Approval and Procedures)
Regulations 2014.
Development of Transaction documents: A review is required from Transaction and Legal
consultants to assess the existing framework, the requirements of auction and draft template
transaction documents including the Request for Proposals (RFP) and Requests for Qualification
(RFQ) Documents. This will require adapting international best practices10 as and/if appropriate for
Pakistani conditions. It will also necessitate resolving the following items:
• Ensuring conformity between the selected auction mechanism with Public Procurement
regulatory Authority (PPRA) rules and NEPRA regulations. In the event of any
inconsistencies, AEDB will need to facilitate the necessary approvals from the relevant
authorities.
• Should the Government of Pakistan (GOP) decide to pursue multi-stage bidding processes,
sequencing to get there in what manner and by when will be equally important. Rules and
regulations need to be developed and put in place for this situation.
10 Globally, countries have announced their intent to hold an auction process for procurement of RE anywhere between
1 -2 years prior to the actual launch of the RFP and/or bid process.
22 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Process and Procedural Issues: Multi variable and multi stage auctions and reverse action process
have not been tried in Pakistan before. The lack of experience, capacity and real time information
exchange require serious review of such process to ensure transparency and equity. Reverse
auctions around the world have used Information Technology systems, especially for multi-stage
auctions. The NEPRA Power Acquisition Programs (Standards and Procedures) Rules, May 2017
prima facie appear to be unclear on multi-variable, multi-stage or reverse auctions. Also, the skills,
capacity, the infrastructure (such as appropriate Information Technology systems) and importantly
the familiarity and acceptability are not yet in place.
The afore-mentioned NEPRA Rules, May 2017 require that competitive bidding be conducted
keeping in view the “demand forecasted by national grid company in accordance with the least cost
generation plan of each DISCO.” Given lack of consensus in the marketplace on power demand
forecasting, it needs to be defined what methodology and institutional framework will be used.
3.3 TIMELINE FOR LAUNCHING THE AUCTION
Based on global experience, a realistic schedule needs to be drawn for initiating the competitive
bidding processes taking into account the logical sequence of activities in different stages of a typical
auction. In a number of situations, the process has been hurried with some unwelcome results.
Table 1 presents an illustrative overall timeline for the different stages of an auction process.
Annex B presents an illustrative but more detailed schedule for launching different activities for an
auction. The following paragraphs describe the activities broadly associated with transaction
inception, due diligence and structuring, implementation of the procurement, award and post-
competition stage.
Table 1: Indicative Timeline for Competitive Procurement Process in Pakistan
(months)
Different Stages of a
Typical Auction 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 Inception Stage
2 Due Diligence and Transaction
Structuring Stage
3 Procurement Stage
4 Bid Award Stage
5 Post-Procurement Stage
Inception Stage Activities:
AEDB may take the lead to undertake inter alia the following activities during the inception stage:
a. RE grid integration arrangements, plan, and necessary pre-auction approvals.
b. Clarity on the competitive arrangements — long-term contract, take or pay provisions,
finalization of arrangements with Central Power Purchase Agency Guarantees Ltd.
(CPPA-G) as market operator, aggregators least cost generation dispatch, etc.
c. Location and site selection and required Federal/Provincial/Local approvals.
d. Choice of technology and/or quality criteria.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 23
e. Needs/options assessment, which determines the supply and demand of electricity, cost-
benefits, and Strength-Weakness-Opportunities-Threat (SWOT) analysis of the auction.
All the preceding activities are pre-requisites for the decision to launch an auction and should be
followed by: (a) development of a Concept Note in parallel to RFP as per normal Pakistani process;
decision/approval in principle to conduct auction; and disclosure of pre-feasibility/preparatory studies
already done by AEDB; and (b) announcement of the intent to issue RFP for the auction and the
associated timeline (international practice is at least 1 year in advance).
Due Diligence and Transaction Structure Stage:
During this stage, analysis / assessments need to be undertaken by the investor, as follows:
a. National and regional demand analysis, supply assessment, and supply-demand balance.
b. Grid-integration study and seeking necessary approvals from NTDC/DICO or other
relevant entity.
c. Environmental and social community assessment and obtaining necessary approvals.
d. Viability and/or feasibility analysis including technical, commercial, financial and
legal/regulatory conformance to RE development framework.
AEDB may undertake the following analysis and propose specific measures for Government
approval:
a. Market and affordability assessment including customer profile, willingness-to-pay survey,
and safety nets – this is international best practice in deregulated market.
b. Description of the bidding process and seeking necessary decisions: (i) aims, goals, and
strategies; (ii) minimum eligibility rules for bidders; (iii) contract lengths and desirability
of the use of standard PPAs/EPAs; (iv) approvals for taxation, subsidies, and other
incentives for bidders, to be mentioned in the RFP; (v) price rule for the auction e.g.
initial bid price, 'clearing price’, floor price consideration, and concerns about windfall
profits; (vi) proposed billing and payment process; and (vii) lead time between bidding
process technology-wise and when capacity must be delivered.
c. Development of the bidding format and auction design customized for local conditions:
bidding documents, regulations, rules, processes, procedures, schedule and timing of
bids.
The GOP (Ministry of Energy) should review and approve all key provisions of the competitive
process and authorize AEDB to launch the auction on its behalf. In completing the due diligence,
following key points may be kept in mind:
• If reverse auctions are chosen/allowed by the Government, then as per international
practice, this may require development of necessary Information Technology systems for
real-time bids by AEDB.
• Timely dissemination of requisite project and auction information is crucial. There is a
trade-off between amount of information to publish in advance of competitive bidding to
reduce barriers to entry but caution must be exercised to prevent collusion, and ensure
competition.
• Ensure competition between new and existing RE resources and should guide timing of
bidding processes and length of RE contracts.
• Formal Announcement of intention to hold auction and call for EOIs, along with
dissemination of RE targets, key projects, and bidding mechanism can gauge market interest.
24 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Procurement Stage:
Management of the RE procurement process is envisaged to be the prime responsibility of AEDB,
and would comprise of the following concurrent and sequential activities: (a) issuance of Preliminary
Information Memorandum (PIMS) and invitation for submission of EOI/queries; (b) PIMS to be
followed by Road Show; (c) development of RFP including soliciting feedback on pre-qualification
criteria, collateral rules, etc.; (d) public outreach and publicity; (e) pre-bid meeting after EOI
announcement; (f) issuance of draft RFP (including security package and incentives for project
developers and penalties i.e. bid bonds, underperformance penalties, etc.; EPA/IA etc.); (g) post-draft
RFP pre-bid meetings; (h) finalization of pre-qualification criteria, bidding process structure and
bidding rules, and completion of final RFP; and (i) issuance of the final RFP to solicit bids (with a
minimum of 30 days response time).
The draft and final RFP need to be submitted to NEPRA to seek regulatory approvals. The winner
selection rules, procedures, and processes have to be also approved by competent authorities, and
consistency with the PPRA rules and regulations has to be ensured. Bids are received from the pre-
qualified bidders (who have been issued the RFP) and opened in front of the duly-authorized
representatives of the bidders for evaluation.
Bid Award Stage:
At the bid-award stage, the risk mitigation instruments and affordable financing mechanisms need to
be finalized so as to enable an expeditious financial-close by the winning bidder. Based on the bid-
evaluation criteria, the winner is identified, and necessary approvals obtained before the issuance of
provisional award letter(s). Execution of security package and incentives for project developers, as
well as review of EPA/Implementation Agreement is also completed in this stage.
Post-Procurement Stage:
The post-procurement and award stage is marked by the following activities: (a) Finalization of the
Implementation Agreement after award; and (b) financial close by the bidder/investor. This stage
also initiates the monitoring and evaluation process, and enforcement of rules, regulations and
procedures.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 25
4. RECOMMENDATIONS
The most important aspect for consideration while designing a competitive procurement of RE in
the context of Pakistan relates to (i) the institutional readiness and capacities and (ii) infrastructure
and resource availability. The Government needs to focus and facilitate procurement of resources to
develop the institutional capacities not only in the execution agencies but also strengthen oversight
and monitoring agencies. Investments are also required for requisite strengthening of infrastructure
in terms of absorption and dealing with the operational issue of VRE. While not being prescriptive,
broad recommendations for designing and implementing competitive a competitive procurement for
RE projects is provided below for consideration:
Establishing the validity of Auctions
The Government should task AEDB to undertake the preparatory work to clearly articulate the
policy objectives and review the overall policy and regulatory environment in close consultation with
the potential investors. AEDB should also organize market-sounding events where the policy
framework and the impending design of the competitive process is discussed with private investors.
Coordination
The Coordination between MOE, AEDB and provincial energy departments and NEPRA should be
improved and institutionalized given the complexity envisaged. In this regard, coordination on the
Federal and Provincially-sponsored on-grid RE projects and roles and responsibilities of respective
institutions should be clearly established.
Empowerment of procurement teams
Critically, the procurement management team/entity should be capable and competent in managing
transaction advisers and have a high degree of operational autonomy. It is crucial, that the team
comprises professionals from both private sector and government officials. The procurement
process often requires proof of numerous consents and approvals at all levels - national, provincial
and municipal and these should be processed earlier and facilitated from the early stages of the
program and should coordinate and streamline their approval processes. The procurement team
should also tap into the cumulative knowledge and the lessons learned from the disposition of the
Wind and Solar projects in Category III, once the process has been implemented.
Adequate resources and transaction advisors
Upfront and adequate funding is necessary to hire expertise for the design of the procurement
program and its associated documentation and contracts. Funding can come either directly from
GOP or from a loan or grant from development finance institutions. What is needed is to secure
expertise and experienced advice at the design stage, as this is critical to the program's ultimate
success. The benefits of low prices from a well-designed auction justify the costs of hiring
professional expertise to help design and run the auctions. The ongoing costs of subsequent bid
rounds may be covered by charging project development fees to successful bidders
Standardization of Procedures and Documents
GOP is recommended to provid a level playing field including standardized contracts and documents.
The tender documentation including RFQ and RFPs, and associated contracts, must be of the highest
standard, based on international best practice and should allocate risks appropriately. At a high level,
the RFP requirements must be carefully designed to filter out parties that are not financially,
technically or legally capable of carrying out the project as promised within the given timeframe.
Contracts should be standardized and non-negotiable and be bankable. Documents currently under
preparation by AEDB (RFP, EPA, and the Implementation Agreement) for the disposition of wind
and solar projects under a competitive process can also be used as a starting point to advance and
shorten this work.
26 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Technology-specific versus technology-neutral competitive tenders
It may be possible to run a multiple technology competitive tender, using the same tender
documentation with common qualification and evaluation criteria, as well as certain technology-
specific requirements and contracts (for example, technology-specific PPAs). However, it is
proposed that initially AEDB may initiate technology-specific tenders and gain experience on
auctions, and then after the first few rounds, organize competition between technologies. As
Pakistan goes forward, it may be possible that multiple technology tenders are used for revealing
relative market prices and which technologies show the greatest promise for cost and price
reductions. In the medium- to long-term, it is recommended Pakistan embark on technology-neutral
auctions.
Programmatic Approach to Tenders – Size for the first round
The size of individual projects permitted should be capped by AEDB to encourage more competition
and to reduce buyer risk through a diversified seller base. No specific size (in MW) is being
proposed as it would be dependent on the absorption capacity, market appetite and other factors
such as supply and demand situation, incumbency of existing PPAs etc. at the time of the auction.
However, this cap must not be so low that it prevents projects from achieving economies of scale
that would reduce bid prices. There is a tension between designing an auction that incorporate
economies of scale, seek lowest prices, and also seek participation by local developers (due to their
smaller financial capabilities). The creation of a competitive environment should be balanced with
local, broad-based procurement.
Multiple bid rounds
There is value of running sequential auctions at regular intervals and capping the power capacity that
is auctioned in each auction or bid round. This is likely to stimulate competition and drive down
prices by ensuring that offers (from bidders) exceed supply (that is auctioned) in each round.
Multiple bid windows are expected to be attractive to bidders because the perceived ‘higher chance’
of being awarded a project at some point, knowing that there will be several rounds of capacity on
offer. Multiple bid rounds would also allow AEDB to learn the lessons and improve the process on
the government side, as they are able to streamline and refine the tender documentation and legal
contracts. It is therefore recommended to start with smaller capacities to be tendered based on
criteria such as location, grid availability, required demand etc. and then gradually ramping up the
program through larger capacity offerings in later rounds.
Interconnection
Grid Connection planning by NTDC must be coordinated with the RE program. This is especially
relevant in Pakistan given the numerous issues relating to power evacuation and interconnection in
the recent past and where transmission constraints have delayed and frustrated the development of
RE projects. The development of RE resources, in most countries, implies a reconfiguration and
strengthening of the grid. A RE procurement program needs to be complemented with an adequate
transmission planning and investment program. It would be beneficial for project sites to be limited
to specific zones where transmission capacity is or would be in place or could be strategically
upgraded to serve numerous projects (wind and solar power projects can be concentrated in
specific geographical areas where investments in transmission grid by NTDC will be concentrated).
Land
A key design feature is whether government or private parties choose the project sites. This
question is relevant in Pakistan given the problems with land access and acquisition. It is
recommended that the government plays a facilitation role in selection of sites and its availability and
performs some of the preparatory work prior to the tender. Acquisition of land should be
encouraged by private-developer to be based on fair market value, so as to minimize community
unrest or dissatisfaction.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 27
Technical Standards
Where possible, the technology components for power generation must either be internationally
certified (by prescribed certification bodies) or comply with relevant international best practice
standards. This is not to say they cannot be locally manufactured, provided they meet international
standards of acceptable design. Alternatively, certain components should exhibit a "proven
reliability". A credible mechanism for the enforcement of technical standards for the RE projects also
needs to be instituted.
28 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
5. REFERENCES AND BIBLIOGRAPHY
• Michael Hochberg & Rahmatallah Poudineh, Renewable Auction Design in Theory and
Practice: Lessons from the Experiences of Brazil and Mexico, April 2018.
• IRENA (2017), ‘Renewable Energy Auctions: Analysing 2016’. IRENA, Abu Dhabi. ISBN 978-
92-9260-008-2.
• Renewable Energy Auctions: A Global Overview: Report 1: Energy and Economic Growth
Research Programme May 2018 Version 1.1 Wikus Kruger, Anton Eberhard & Kyle Swartz
Management Programme in Infrastructure Reform and Regulation (MIR).
• Recommendations for the Design of Successful Renewable Energy Auctions or Competitive
Renders in Africa --- Anton Eberhard and Raine Naude.
• Mora Alvarez, D. F., Kitzing, L., Soysal, E. R., Steinhilber, S., del Río, P., Wigand, F., ...
Woodman, B. (2017). Auctions for renewable energy support - Taming the beast of
competitive bidding. Aures
• IRENA and CEM (2015), Renewable Energy Auctions – A Guide to Design.
• IEA-RETD (2016), RE TRANSITION – Transitioning to Policy Frameworks for Cost-
Competitive Renewables, [Jacobs et al., IET – International Energy Transition GmbH], IEA
Technology Collaboration Programme for Renewable Energy Technology Deployment (IEA-
RETD), Utrecht, 2016.
• IRENA, IEA and REN21 (2018), ‘Renewable Energy Policies in a Time of Transition’. IRENA,
OECD/ IEA and REN21.
• Lena Kitzing,, Vasilios Anatolitis, Oscar Fitch-Roy, Orinna Klessmann, Jane Kreiss, PabloDel
Rio, Fabian Wigand, Bridget Woodman. “Auctions for Renewable Energy Support: Lessons
Learned in the AURES Project”, IAEE Energy Forum / Third Quarter 2019.
• Competitive Selection and Support for Renewable Energy, Policy Guidelines Prepared jointly
by the European Bank for Reconstruction and Development and the Energy Community
Secretariat in collaboration with the International Renewable Energy Agency March
2018IRENA (2018), Renewables Readiness Assessment: Pakistan, International Renewable
Energy Agency (IRENA), Abu Dhabi.
• IRENA_Renewable_Energy_Auctions_in_Developing_Countries.,2013 Hugo Lucas, Rabia
Ferroukhi and Diala Hawila.
• The Procurement Process, Melbourne Renewable Energy Project.
• Procurement Options for New Renewable Electricity Supply Claire E. Kreycik National
Renewable Energy Laboratory Toby D. Couture E3 Analytics Karlynn S. Cory National
Renewable Energy Laboratory, 2011.
• Fabian Wigand, Ana Amazo, Ecofys, RES auctions – Insights for the Energy Community
Presentation at IRENA – Energy Community Workshop on Renewable Energy Auctions.
2017.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 29
ANNEX A: IMPLEMENTING RENEWABLE
ENERGY AUCTIONS IN PAKISTAN
A.1 DISCUSSION NOTE11
This discussion note reviews recent analysis and research on renewable energy (RE) auction design12
and highlights global lessons on auction implementation. The purpose of the note is to facilitate
dialogue and elicit comments from public and private sector stakeholders on moving the RE auction
process forward in Pakistan by addressing the following leading-questions:
• Evaluate auction feasibility: The government of Pakistan’s Cabinet Committee on Energy
(CCOE) has already approved a first competitive procurement program with the specific
objective to advance under-development RE projects stalled by a previous CCOE decision in
2017. Following this mandatory first-round, what target objectives would subsequent RE
auctions achieve? Are auctions a suitable mechanism for long-term RE support in Pakistan,
given the country’s current electricity market and regulatory context?
• Select auction format: Which competitive procurement or auction format is best-suited
to Pakistan’s local market context and auction objectives?
• Select auction design elements: Which design elements should be included (e.g. size or
technology eligibility, auction procedure, participation eligibility and penalties etc.)? What
parameters should be applied to each element? Which institutions will be involved in the
process as a result of the selected auction design specifications?
• Conduct auction: Which institutions will bear responsibility for conducting the auction?
Are the required procurement documents, such as request for quotation (RFQ), request for
proposal (RFP) and PPA etc. available? Do the designated institutions have the capacity to
conduct auctions and execute contracts?
A.2 WHAT ARE RENEWABLE ENERGY AUCTIONS?
Renewable energy auctions (or other variation of competitive procurement) are a policy tool and
market mechanism for promoting the deployment of RE. As a market mechanism, auctions enable
governments to contract a pre-defined volume of energy at a competitive cost. When well
designed, the price competition produced by the auction mechanism improves cost-efficiency and
enables price discovery of RE based electricity generation. Despite difficulties in implementation –
auctions are especially context specific and no one model is applicable to all circumstances - RE
auctions have become the most common method for large-scale procurement of renewable
generation capacity, with at least 67 countries implementing RE auctions in 2017. Since 2010, the
Bloomberg New Energy Finance Auctions Database records 267,000 MW of renewables procured in
a total of 726 separate auctions worldwide.
A.3 PRINCIPLES OF AUCTION DESIGN
Successful auctions that meet the goals of both policymakers and society balance the trade-offs
between specific auction design elements, and the electricity market design and context in which the
auctions take place. In general, auction design is under-pinned by these broad principles:
11 Implementing Renewable Energy Auctions in Pakistan: Discussion Note: SEP (Dr Allen Eisendrath & Ermeena Malik)
12 Michael Hochberg and Rahmatallah Poudineh, “Renewable Auction Design in Theory and Practice: Lessons from the
Experience of Brazil and Mexico” (Oxford Institute for Energy Studies), April 2018; IRENA and CEM, “Renewable Energy
Auctions - A Guide to Design,” 2015; IRENA, “Renewable Energy Auctions: Analyzing 2016” (Abu Dhabi: IRENA, 2017);
Hugo Lucas, Rabia Ferroukhi, and Diala Hawila, “Renewable Energy Auctions in Developing Countries” (Abu Dhabi: IRENA,
2013); Silvana Tiedemann, “Renewable Energy Auction Design,” Open Electricity Economics (OEE); Fabian Wigand et al.,
“Auctions for Renewable Energy Support: Lessons Learnt from International Experiences” (AURES, June 2016).
30 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
• The auction scheme should provide support to RE at the lowest feasible cost and greatest
efficiency.
• Auctions should be designed to meet the objectives of the government and utilities that are
procuring renewable energy.
• Auction design must be consistent with the broader market context, allocating risk
efficiently among auction participants so that auction trade-offs do not favor one participant
or class of participants (i.e. investors, government, rate-payers) over another.
• Auctions should deliver the required level of RE deployment in the targeted timeframe;
accepted bids must be credible and have a high likelihood of achieving completion on time.
• The auction arrangements should be transparent, open, predictable and objective, earning
broad investor confidence.
• Auction arrangements should minimize market distortions and facilitate market
development.
• Electricity markets and contexts are constantly and rapidly changing. As more auctions are
held, new innovations, design flaws and unintended consequences emerge. Auction
administration and design therefore need to be flexible.
A.4 AUCTION DESIGN PROCESS
Although auction design elements are not universally applicable, most countries follow a similar
design process to implement RE auctions:
Figure 1: Auction Design and Implementation process13
13 Adapted from Ana Amazo, “Renewable Energy Auction Design,” (2016).
3. Auction design 4. Implementation1. Feasibility
evaluation2. Format
Selection
Define policy goals and
objectives
General design elements
Procurement procedure
Conditions for
participations
Evaluate auction formats Develop auction design Conduct auction
Deadlines and Penalties
Institutional setup
Drafting of required
documents
Market building
Procurement conduction
(RFP, RFQ, bid award)
Contracting
Monitoring of realization
5. Evaluation
Evaluate outcomes
Conduct market and
regulatory assessment
Market size
Pre-developed projects
Market players
Technology costs
Project development and
operations
Existing regulations and
incentives
Compare auction
schemes
Evaluate qualitative
parameters
Evaluate quantitative
parameters
Evaluate static and
dynamic efficiency
Lessons learned
Adjust auction design
and/or process
Stakeholder consultation and feedback
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 31
A.4.1 EVALUATE FEASIBILITY OF AUCTIONS
Activity Options Key Considerations
Define policy goals Common policy objectives
include:
Cost reduction. The most
common policy objective is
to lower the cost of
renewables. There are
however several different
dimensions of this objective:
Reduce the overall system
cost by selecting least
expensive projects, stabilize
or reduce the overall budget
that is allocated for
renewables, incentivize cost-
efficiency through
competitive pressure, and
support technological
learning and progress.
Cost discovery. Closely
related to cost reduction is
the objective to discover the
real cost of renewables. In
this case, auctions can
overcome the information
asymmetry between project
developers and the
government: developers can
estimate the amount of
support they need much
better than the government.
Volume control. A third
prominent policy objective is
to control or influence the
overall volume and type of
technology that is being built
(e.g. through technology
specific auctions)
Other objectives. Other
policy objectives include a
positive socio-economic
impact, a regional and
technological distribution
that is in line with planned
grid infrastructure or
resource dispersion, project
size and technology diversity
in the auction, job creation,
attracting foreign direct
investment and incentivizing
research and development.
• Policymakers should develop and publish
a strategy for the development of
renewable energy, including: long-term
plans that identify targets for renewable
energy generation (for example, looking
10 years ahead); and short-term plans
identifying the auctions that will deliver
the target for the coming two to three
years.
• Plans should be developed with a view to
promoting a viable long-term RE market
that is of a sufficient scale to interest
market participants and can be easily
integrated in the competitive electricity
market.
• Long-term targets should be consistent
with any international obligations and be
part of an integrated energy and climate
policy planning framework.
• The strategy for implementing plans
should be consistent with the legal
framework in the country e.g. public
procurement and competition laws etc.
Conduct a market and
regulatory analysis
An analysis of the
• Market size
• Stage of project
development
• What is the potential market size? How
much RE is the government looking to
procure and over what time-frame?
32 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Activity Options Key Considerations
market situation and
regulations is crucial for
determining the
appropriate auction type
and selecting the right
design elements (see
Section 3 for more
detail)
• Market participants
• Technology costs
• Existing regulations and
incentives
• Project development and
operations
• Existing infrastructure
• Is the auction targeting early or late stage
development? (See Section 3.1 for more
details on project stage criteria)
• Who are the market players? Although
auctions have been applied to support
small- (France) to medium-scale
technologies (California), and do not per
se exclude smaller players, experience
shows that large and experienced project
developers win the largest share of the
auctioned capacities or energy. If size
diversity is a policy objective,
governments might consider size-specific
auctions (e.g. in France and Taiwan).
• What are the technology costs?
• Will the existing regulations and
incentives support effective RE auctions?
• Is the existing infrastructure in the
country appropriate for project
development in locations with high RES
potential? Weak or insufficient
infrastructure can negatively affect the
efficiency (e.g. in Portugal) and
effectiveness (e.g. in Brazil) of auctions.
A.4.2 EVALUATE AUCTION FORMATS
Activity Options Key Considerations
• Analyze and compare
international auction
schemes and identify
best practice or
mechanism best-suited
to Pakistan.
• Evaluate options with
quantitative and
qualitative parameters
(e.g. policy goals,
volume and location
of energy to be
procured etc.)
• Identify a successful
bidding strategy.
• Static Auctions: Also known
as sealed bid auctions.
Include first-price and
second-price, pay-as-bid or
pay-as-clear auctions. Most
countries use this auction
format.
• Dynamic Auctions (also
known as iterative
auctions): Include ascending-
clock and descending-clock
auctions.
• Hybrid Auctions: Multi-
phase auctions with a mix of
at least one static and one
dynamic phase.
• Administrative costs: The sealed-bid
auction is simple, easy to implement,
fosters competition and avoids collusion.
Descending clock auctions are more
difficult to implement, but they allow for a
fast price discovery as well as greater
transparency.
• Market situation; pay-as-bid pricing
may disadvantage small project
developers, as profits largely depend on
the bidder’s capacity to accurately
estimate the clearing price. Large
developers, which often enjoy significant
resources and experience, may guess
clearing prices more precisely than their
smaller counterparts. Auction design that
limits actor diversity could have long-term
implications for the market and the sector
as a whole, as providing a level playing
field between large and small participants
would be more likely to lead to the
inclusion of both, which has positive
implications for competition and
innovation. Pay-as-bid pricing can also
limit actor diversity due to favoritism for
market incumbents and low pricing.
• Project structure for each technology
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 33
Activity Options Key Considerations
type.
• Assess past experience with energy
auctions and their outcomes.
A.4.3 DESIGN AUCTION
A.4.3.1 GENERAL DESIGN ELEMENTS
Design elements Options Key Considerations
Selection of project
locations and sites • Government site e.g.
Tanzania (Hydro), UAE,
Morocco, Zambia. Includes
Renewable Energy Zones
(REZs) or designated areas
for RE development e.g. in
Texas (US), Turkey and
South Africa
• Bidder site e.g. South Africa
(REZ), Mexico, Chile,
Tanzania (solar and wind)
Government site auction: If sites are
pre-developed by the auctioning
authority (single item auction), care must
be given to provide correct information
in order to avoid unnecessary risks for
bidders. Pre-development by the
auctioneer might include:
• Grid connection
• Land lease
• Environmental assessments
• Resource measurements
Bidder site: Bidders compete with their
projects and pre-develop their projects,
e.g.:
• Defining site boundaries
• Measuring resource availability
• Procuring land lease
• Ensuring grid connection: Grid
connection risk borne entirely by the
bidder, exposes bidder to considerable
financial risk
The government or auctioneer can set
location constraints, even under the
bidder-site model to meet policy goals
such as regional quota, achieve greater
geographic diversity of projects, and
ensure proximity to the grid and/or
loads.
Auctioned items
Auctioned items can include:
• Energy i.e. kWh (in Mexico,
Brazil),
• Firm energy i.e. production
at a specific time of day (in
Mexico),
• Capacity in MW (Germany,
Thailand, Malaysia and
Indonesia),
• Budget (Netherland, UK),
• Green electricity certificates
(Mexico)
Auctioned items can be offered as a
single item or grouped together in a
multi-item auction.
Setting volume caps below the potential
market volume enhances competition,
which can lead to price reductions. South
Africa’s first auction (2011) was not very
successful in enhancing competition,
given that there was no capacity limit
attributed to this first phase except the
overall program volume, which meant
that the auction volume far outstripped
demand.
34 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Design elements Options Key Considerations
Remuneration or
Support Mechanism
Support or remuneration is
provided to RE projects
through long-term Power
Purchase Agreements (PPAs)
with one of two types of
remuneration or financial
support:
• Contract-for-difference
(CfD) with the successful
bidder:
• The support granted under
this contract is the difference
between the price with
which the successful bidder
was awarded (the strike
price) and the market price
for electricity (the reference
price). The remuneration
awarded under a CfD is
called a Feed-in-Premium
(FIP) and can be a sliding, or
with higher risks, fixed
premium on top of the
market revenues (e.g. the
Contract for Difference or
CFD in the UK). Most
European countries use
sliding premiums to limit the
revenue risk for RE
generators.
• Feed-in-Tariff (FiT)
• CfD and FiPs are dependent
on the existence of a
reference electricity
price (for example, a liquid
day-ahead electricity market
accessible to the RE
producer). When such a
reference price does not
exist, policymakers should
provide support in the form
of a guaranteed purchase at a
feed-in tariff, where the level
of the tariff is determined by
an auction. In such cases, the
terms of the support for a
given project can include
transitioning from the feed-
in-tariff to a sliding-scale
feed-in premium once an
easily accessible reference
price materializes.
Using standardized, long-term PPAs
with conditions known in advance by
bidders can lower risk premiums.
Moreover, making contract duration
compatible with the duration of the
typical financing maturity given by banks
can increase a project’s bankability.
Investor confidence can be enhanced
through different methods of sharing
financial risks related to exchange rate
and/or inflation that can impact income
throughout the contract period.
Offering a FiP to RE generators selling
directly into the wholesale energy
market ensures profitability of RE
generators and reduces the risks
associated with RE projects. The
premium ensures that RE generators
recover all their costs when market
revenues are insufficient or when
dispatch instructions diverge from their
dispatch schedule.
The CfD arrangement should be
symmetrical so that the RE producer
pays to the support provider the
difference if the reference price exceeds
the strike price.
Technology eligibility
• Technology-neutral
procurement (all
technologies can participate)
Technology participation rules
involve trade-offs in terms of cost,
competition and other auction
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 35
Design elements Options Key Considerations
• Technology specific
procurement (only one
specified technology can
participate e.g. wind, solar,
storage, hybrid, distributed
generation, rooftop
installations etc.)
• Multi-technology
procurement (a specified
group of technologies can
participate)
outcomes.
Technology-specific auctions are
typically used to help provide the
foundation for nascent or non-
existent technologies to prove they
are viable and can compete in future
auctions. In addition to supporting
emerging technologies, technology-
specific auctions can help diversify
the generation mix, support the
development of local industry and
encourage diversity of market
participants. Specific auction design
catering to specific technologies
could have positive externalities
since pre-qualification requirements,
regulatory procedures and other
factors vary by technology. Tailoring
auction design for a single
technology could enhance auction
efficiency when technologies are at
different stages of maturity.
However, the absence of
competition between technologies
also reduces the chances of
achieving least-cost generation.
In technology neutral auctions,
all energy technologies and
resources compete directly with
one another. This can also include
demand-side resources like energy
efficiency and demand response,
which may bid into the market as
well (if they can demonstrate that
savings are achieved, or generation
is offset during peak periods). These
auctions increase the likelihood of
the development of least-cost
technologies, yet reduce or
eliminate government control over
which technologies are developed. If
held when technologies are not at
the same level of maturity,
technology neutral auctions can
sometimes lead to unintended
consequences.
While the dollar per unit cost of
electricity is likely to be higher in
technology-specific auctions, this
metric does not consider grid
integration costs according to
technology, local development
benefits, generation mix diversity or
resource adequacy. Accordingly, the
ideal mix of technology-specific,
multi-technology and
technology neutral auctions
36 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Design elements Options Key Considerations
depends largely on specific market
and societal needs.
Project size eligibility Auctions can be designed to
procure power from a specific
size of projects ranging from a
few kW to several MWs.
Implementing minimum project size
requirements has the potential to reduce
the transaction costs associated with
small bids, although potentially deterring
their participation, which may have
detrimental effects on competition.
Maximum size requirements can
encourage the participation of smaller
actors and help avoid market
concentration, but limit economies of
scale.
Frequency Annual, bi-annual etc. Continuity in the implementation of
auction rounds, as opposed to a "stop-
and-go" implementation, increases long-
term planning certainty for market
players. Auction frequency is context-
dependent and should allow regulators
to adjust according to perceived shifts in
market conditions.
A.4.3.2 AUCTION PROCEDURE
Design elements Options Key Considerations
Auction format • Static Auctions: Also known
as sealed bid auctions.
Include first-price, second-
price, pay-as-bid and pay-as-
clear auctions. Most
countries use this auction
format.
• Dynamic Auctions: Also
known as iterative auctions.
Include ascending-clock (e.g.
the Netherlands) and
descending-clock auctions
(e.g. in Brazil)
• Hybrid Auctions: Multi-phase
auctions with a mix of at
least one static and one
dynamic phase (e.g. in Brazil).
The trend to implement static (sealed-
bid) auctions in many EU and non-EU
countries is due to their relative
simplicity and the regulator and
bidder’s familiarity with the sealed-bid
process.
Ceiling Price • Undisclosed ceiling price
(e.g. in South Africa and
Peru).
• Disclosed ceiling price (e.g.
in Brazil).
• Disclosed ceiling price
combined with undisclosed
auction volume (e.g. in
Mexico and India).
Disclosing ceiling price helps prevent
projects from being rejected in the
auction and gives bidders more
planning security (sunk costs).
However, in markets where
competition is low, disclosing ceiling
prices can result in all bids close to
the ceiling price.
Benefits:
• Control over maximum costs
protects government from high prices
in case of low competition.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 37
Design elements Options Key Considerations
• Cap increases budget certainty for
years in advance.
• Create price signal for market.
Challenges:
• Bids close to ceiling price if low
competition market distortion.
• Overly aggressive ceiling prices can
be distorting auction unattractive for
investors.
• Ceiling difficult to set if little
information.
Ceiling prices that define the
maximum possible support level limit
the risk of high support costs for
governments/consumers. Determining
appropriate ceiling prices remains
challenging and may involve relatively
high transaction costs.
In addition, when setting a ceiling
price, competition from other regional
markets and equipment supply bottle-
necks must also be accounted for. In
Denmark’s Anholt auction only one
bidder participated in the auction. The
lack of interest from other producers
was possibly due to financially more
attractive markets at the time,
especially in the UK.
Selection criteria Price only auctions:
Price is the only criteria.
Price only auctions are the
most common method of bid
evaluation in EU countries.
Multi-criteria auctions:
In addition to price, several
other criteria are considered
during bid- evaluation e.g.
locally produced
components, additional
environmental benefits,
suitable production profile,
grid connection costs and
locational distribution etc.
Most non-EU countries use
multi-criteria evaluation.
• A purely price-only selection process
is associated with lower support and
transaction costs, while the inclusion
of other criteria imposes restrictions
that might lead to higher costs and
decreased transparency.
• However, multi-criteria auctions can
also help promote social acceptability
and local economic development.
• The more transparent and
quantitative the criteria, the lower
the risk of collusion.
Pricing rule Pay-as-bid (also known as
the discriminatory pricing
rule): Pay successful projects
what is offered in their bids.
Most countries use the pay-
as bid pricing rule.
Pay-as-clear (also known as
the uniform pricing rule): All
Pay-as-bid has been the preferred
pricing rule in most EU and non-EU
auctions. Pay-as-bid tends to be more
robust against undesired, strategic
behavior than uniform pricing, despite
some advantages in auction theory. In
addition, and since it offers bidders no
more than their bid, this pricing rule
38 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Design elements Options Key Considerations
successful bidders receive
the same clearing price (e.g.
the Netherlands and UK)
usually finds high public acceptance.
The Pay-as-clear rule discourages
bidders from submitting unfeasible
bids and aggressive under-bidding.
Number of rounds • Single round
• Multiple, iterative rounds
• Administrative costs
• Institutional capacity
A.4.3.3 CONDITIONS FOR PARTICIPATION
Pre-qualification requirements (or setting conditions on who can participate in the auctions) are
applied in almost every country that has conducted RE auctions. Pre-qualification conditions help to
identify serious bids and sort out projects with low realization probability. Pre-qualification
requirements and conditions can favor larger, more established developers and prove prohibitive to
small developers. However, implementing low pre-qualification and penalty levels might attract
speculation and result in poor project realization rates.
Design Element Options Key Considerations
Timing of the auction
This refers to the
amount of preparatory
work that the bidders
are required to complete
before participating in
an auction. Countries
can, for instance, specify
whether bidders can
participate without any
preliminary site
assessment, land
acquisition or permits
(early auction) or
whether site and
resource assessments,
land and permits are a
prerequisite for
participation (late
auction).
• Early stage auction: Bidding
projects are in an early stage of
development i.e. bidders are
not required to provide
significant preliminary
assessment, proof of land
ownership or permits etc.
• Late stage auction: Participating
projects are in a relatively
advanced stage of development
i.e. preliminary planning and
approvals are in place. Late
stage auctions by definition
require significant lead time
between the auction
announcement and execution.
• If the auction takes place early in the
project development process, i.e. before
permits affecting the business case of a
project (depending on the country: land
lease, grid connection), the risk that the
project will be delayed or cancelled
increases.
• Conducting sufficient site feasibility
studies and procuring key permits before
the auction allows bidders to better
estimate costs and makes projects more
bankable.
• However late-stage auctions expose
participating bidders to additional
transaction costs. The number of agencies
and process involved in securing
approvals for instance has a critical impact
on the transaction costs developers must
face to participate in a late-stage auction.
Establishing a one-stop shop for
permits (e.g. Denmark) or auctioning
projects in designated renewable energy
zones (REZs) can reduce costs associated
with late stage auctions.
Prequalification
requirements
• Pre-qualification requirements
can include:
• Land rights secured or proof of
reasonable expectation.
• Experience implementing
projects of a certain size or
capacity.
• Audited financial statement for
last three years.
• Net worth of bidder at least
30% of project value.
Balance with financial requirements and
consider burden on bidder and risks.
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 39
Design Element Options Key Considerations
• Disclosure of lines of debts.
Financial guarantees
Splitting financial guarantees
between commitment (bid
bond) and completion (project
completion bond).
Sufficiently high financial guarantees help
ensure seriousness of bid and project
completion.
Balance with technical requirements and
consider burden on bidder and risks.
A.4.3.4 DEADLINES AND PENALTIES
Risks should be allocated to the actor best able to deal with them. This would reduce transaction
costs for bidders and reduce the probability of non-realization, while issues related to project
development are probably better dealt with by the project developer.
Design Element Options Key Considerations
Deadlines for
commissioning
projects.
Varies based on project scale
and technology type. Examples
include:
• South Africa: Approximately 2
years (1.5 years COD after
financial close + 0.5 years
financial close after contract
award).
• Germany: Solar PV - 1.5 years;
onshore wind – 2.5 years
• Mexico: 1.5 – 3.5 years from
auction announcement (all
technologies).
• USA-California RAM: 2 years
(all technology baskets).
• Project scale
• Technology type
• Location
• Existing infrastructure in the project
area and accessibility of project
location.
• Interconnection availability.
• Local content requirements.
Penalties Penalties imposed in case
project is delayed or fails to
comply with the requirements
stated in the PPA contract may
include:
• Enforcement of bid bonds or
financial guarantees.
• Support reduction.
• Reductions in support
duration.
• Unilateral contract
terminations in case delays
were not sufficiently justified
(e.g. in China).
• Exclusion of bidder from
future auctions (black-listing).
Benefits: Incentivize project
realization due to penalties.
Costs: Risk for bidders increases.
Prohibitive barrier for some (especially
smaller) bidders.
Next to pre-qualification requirements,
strict compliance rules help to ensure
serious bids, but they can also lead to
low participation and competition.
Lower penalties reduce the risk related
to construction delays and failure,
which could stimulate a higher number
of bids, but they do not encourage
project realization.
Striking a balance between pre-
qualification requirements and penalties
is therefore of key importance, as well
as adapting penalties to local
circumstances.
Case studies show that penalties are
not a guarantee for project realization.
Looking at penalties, reviewed schemes
also show the importance of
differentiating between delays caused by
40 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
Design Element Options Key Considerations
the project developer or by external
factors (e.g. environment license or grid
connection).
Policymakers should closely monitor
potential loopholes or other factors
that could render penalties toothless.
Also, leaving room for legal dispute
about who caused the delays can block
project pipelines and prolong project
realization.
Settlement rules to manage production
deviations can help discourage
developers from systematically over- or
underestimating their generation
expectations. Setting up early warning
systems to identify delays at early stage
helps to constructively address delays in
a timely manner.
A.4.3.5 INSTITUTIONS
Design Element Options Key Considerations
Identify the institution
running the auction.
Typically, a central procurement
body (‘the auctioneer’) will run
the auction on behalf of the
buyer of the electricity, also
known as the ‘counter-party to
the PPA’ or ‘support counter-
party’.
Which institution is best-placed to run
the auction?
What is the extent of technical or
capacity-building support required by
the designated auctioneer?
Identify the counter-
party to the PPA.
PPA counter-party (also known
as the support counterparty)
should be identified. This entity
will deliver support to RE
projects (acting as the ‘buyer’)
through a remuneration or
support level determined
through the auction process.
The PPA counter-party or
buyer could be a federal or
provincial entity (such as a
provincial distribution
company).
The support counterparty must be a
creditworthy entity, allowing projects
to raise financing at a reasonable cost
and the creditworthiness of the
counterparty must be maintained for
the full duration of the support or PPA
period.
Identifying other
institutions directly
or indirectly involved
in the auction
development and
implementation
process.
Organizations involved in
drafting the RFQ, RFP, PPA and
other contract documents or
providing technical assistance or
capacity-building support to the
institutions involved. These
institutions can include:
• Public sector organizations.
• Private sector organizations
(project developers, financial
institutions etc.)
• International development
• What are the roles of the different
institutions involved in the design of
the auction process? For example,
what is the role of the transmission
company in the transaction?
• What are the roles of different
institutions involved in conducting the
auction?
• Will the various institutions require
technical assistance or capacity-building
support?
• Are there any unnecessary institutional
or process overlaps that could delay
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 41
Design Element Options Key Considerations
organizations. the auction or post-auction project
developing process (e.g. during the
permitting phase)?
• Can the number of institutions involved
in the auction and project development
process be reduced?
• What is the involvement of other
technical assistance agencies and
development banks so far?
• How is the exchange with the private
sector taking place? Have consultations
with the private sector on the
RfQ/RfP/draft PPA taken place or are
planned?
Identify institution
responsible for
evaluating auction
outcomes.
(See A.4.5 Below)
One or more government
entities that would review the
effectiveness of the auction
design to achieve a set of pre-
defined auction objectives.
The responsibility for reviewing the
success of the auction process,
documenting the lessons learnt and
adjusting the auction design or process
accordingly should ideally be assigned
during the auction design process and
before conducting the auction.
A.4.4 CONDUCT THE AUCTION
Activity Key considerations Responsibility
Drafting of required
documents. • Assess past experience with
energy auctions, if any.
• Assess utility of existing
procurement documents and
contracts for RE auctions.
• Assess capacity of institutions
involved.
• Identify capacity gaps.
Assign responsibility for individual
activities to the institutions involved in
the auction and establish a timeline for
monitoring progress. Although the
designated ‘auctioneer’ will have over-
all responsibility for conducting the
auction, other entities could
contribute to specific tasks within
auction implementation, e.g. market
building, preparing auction documents
(RFQ, RFP, PPA etc.), contracting with
the winning bidder and monitoring the
progress of the winning projects.
Assign responsibility to specific
organizations or government
departments for:
• Drafting of auction documents
• Market building
• Procurement conduction
• Contracting
• Monitoring of realization
Market building.
Procurement
conduction:
• RFQ
• RFP
• Awarding of bids
Contracting
Monitoring of
realization.
42 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
A.4.5 EVALUATE OUTCOMES
The effectiveness of auctions is measured by their ability to efficiently contract new RE capacity and
by project realization rates. Lessons learnt from the auction experience can be used to calibrate or
modify auction design elements or the implementation process for future auctions.
Activity Options Key Considerations
Evaluate the
effectiveness of the
auction to achieve
strategic objectives
or auction targets.
Static efficiency: Static
efficiency is achieved if a
predetermined target can be
fulfilled at the lowest possible
overall cost or at a lower cost
compared to ceiling prices or
previous (administratively
defined) support levels, such as
administratively defined FiTs.
Dynamic efficiency: In
contrast to static efficiency,
dynamic efficiency evaluates the
costs of target achievement over
the long-term and considers
whether a policy instrument
helps drive down costs of less
mature technologies. Overall, it
is more difficult to assess
dynamic efficiency because its
measurement requires longer
time spans.
Efficiency gains in countries like
California, Brazil and South Africa have
been impressive; Support levels in
California fell from USD 88.7/MWh in
the first round, to USD 78.62/MWh in
the third one. In Germany, the average
price of the first auction round was
USD102.27/MWh (min.: USD
94.57/MWh, max.: USD 105.16/MWh),
significantly below the ceiling price of
USD 125.91/MWh. In the second
auction, the price further declined to
USD 94.68/MWh.
More recently, Mexico achieved
$45/MWh, $32MWh and $20/MWh in
solar auction rounds 1, 2 and 3
respectively, while Kazakhstan
achieved $49/MWh, $45/MWh and
$44/MWh respectively.
Case studies show that there may be a
trade-off in the short-term between
high competitions and fostering
innovative RE solutions. However,
differentiation through technology-
specific auctions seems to be more
suitable due to the diversity it
promotes (both EU and non-EU
countries have some form of
differentiated support that reflects
technology-specific costs, whether in
the form of technology-specific or
multi-technology auctions). Evaluating
auctions based on both static and
dynamic efficiency therefore appears
useful.
Project realization rate: The
number of projects successfully
commissioned compared to the
number of projects awarded
bids.
Research shows that full project
realization is rarely achieved, and
delays are frequent. Auction schemes
in China, Denmark, and Portugal have
now commissioned 100% of
contracted capacities but not without
delays in some cases.
At least 75% of projects (whose
realization period has ended) in
California and South Africa have been
built. In Brazil, France, and Italy, less
than 50% of projects (whose
realization period has ended) have
been realized. Grid connection
problems have been an important
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 43
Activity Options Key Considerations
factor behind the construction delays
in Italy and Brazil.
Document lessons
learnt.
Document and inform
stakeholders of the lessons
learnt from the auction process.
The responsibility for reviewing the
success of the auction process,
documenting the lessons learnt and
adjusting the auction design or process
accordingly should ideally be assigned
during the auction design process and
before conducting the auction.
Adjust auction design
based on experience.
Adjust one or more elements of
the auction design (or adjust the
auction procedure) to improve
upon the results of the previous
auctions.
44 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
ANNEX B: ILUSTRATIVE COMPETITIVE RE PROCUREMENT PROCESS FOR
RE ---- BEST PRACTICES ADAPTED FOR PAKISTAN
(months)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 Inception Stage
a RE Grid Integration Study, Plan, and Approvals in place (pre-requisite)
b Clarity on competitive model for generation — on long-term contract and on take or
pay contract —CPPA-G market operator, aggregators least cost generation dispatch
(pre-requisite)
c Site selection and Federal/Provincial Approvals in place-(pre-requisite); Ensure siting
within project location that is well suited for operational success and guaranteed grid
access that is responsibility of government (pre-requisite)
d Choice of Technology and/or Quality Criteria
e Develop Concept Note in parallel to RFP (As per normal Pakistani process;
Decision/Approval in Principle to Conduct Auction; announce pre-feasibility already done
by AEDB)
f Announce intent to issue RFP and hold auction/s with sufficient notice (international
practice is at least 1 year in advance)
g Conduct a needs/options assessment — determine cost benefit, supply and demand, and
SWOT analysis to the extent possible in Pakistan (pre-requisite for RFP; no standard
process in Pakistan)
2 Due Diligence and Transaction Structuring Phase
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 45
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
a Conduct viability/feasibility analysis (share existing documents) for potential projects
(both AEDB & bidders as relevant), including tariff structure, demand, RE grid integration,
etc.
b Develop market and affordability assessment (international best practice in deregulated
market; only applicable in competitive market environment post-2023 in Pakistan) done
by implementation agency (AEDB) Conduct customer assessment —willingness to pay,
ability to pay, inability to pay and 'safety-net' for customers (International; pre-requisite;
needs appropriate/modified documents)
c Approvals in place for taxation, subsidies, other incentives for RE RFP bidders
d Pricing rule (initial bid submitted or 'clearing price’; floor price consideration given excess
generation estimates, but concerns about windfall profits to beneficiaries) Currently not
applicable to Pakistan
e Decide Bidding Process Aims, Goals, and Strategies; Establish Demand
f If reverse auctions are chosen/allowed as per GoP rules, then as per international
practice, this may require development of Information Technology systems
g Determine minimum eligibility rules for bidders
h Design bidding format and auction design customized for local conditions: bidding
documents (share existing documents for competitive bidding), regulations, rules,
processes, procedures, schedule and timing of bids
i Determine billing and payment process
J Conduct environmental and social community assessment for underlying projects & get
necessary approvals
k Ensuring competition between new and existing resources —timing of bidding processes
+ length of contracts available
l Lead time — between bidding process & when capacity must deliver (give enough time
for different types of technology to develop)
46 RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
m Contract lengths and Standard PPAs/EPAs
n Timely dissemination of requisite project and auction information — how much
information to publish in advance of competitive bidding to reduce barriers to entry but
prevent collusion, and ensure competition
o Formal Announcement of intention to hold auction and call for EOIs, along with key
project and bidding mechanism/RE targets information (gauges market interest)
3 Procurement Stage
a Issue Preliminary Information Memorandum (PIMS) and invite queries (4-8 weeks) shows
demonstration of interest; GoP intent
b PIMS to be followed by Road Show
c Develop RFP, EPA and Implementation Agreement (review existing documents)
d Pre-qualification criteria and collateral rules (Feedback Loop; Financial, Technical,
Partners (what type of individual firms are allowed or only consortia etc.)
e Public outreach campaigns & publicity with media & local communities; Public feedback
(international best practice)
f Send draft RFP to NEPRA for approval
g Ensure consistency with PPRA/solicitation of PPRA comments
h Pre-Bid Meeting after EOI announcement
i Issuance of draft RFP (including security package and incentives for project developers
and penalties i.e. bid bonds, underperformance penalties, etc.; EPA/IA etc.)
j Post-draft RFP pre-bid meetings (provides useful feedback for finalizing RFP; 4-6 weeks
minimum for RFP issuance)
RENEWABLE ENERGY PROCUREMENT AND DESIGN OF AUCTIONS 47
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
k Finalize pre-qualification criteria based on market input
l Bidding process structure and bidding rules (Feedback Loop; procedures for determining
Short List, procedures for determining & launching Final Bid, procedures for determining
winning bid)
m Finalize RFP based on market input (including pre-qualification criteria for bidders and
discussion with bidders on EPA/IA))
n If any changes to draft RFP pursuant to pre-bid meetings, send revised RFP to NEPRA
and competent approval forum
o Final RFP (30 days response time minimum PPRA rules)
p Business plans and capacity in bid (TBD if viable in Pakistani context)
q Winner Selection rules, procedures, & process (Open meeting— envelopes are opened
in front of all bidders, etc.)
4 Bid Award Stage
a Risk mitigation & affordable financing mechanisms
b Issue provisional award letter/s
c Execution of security package and incentives for project developers and penalties (bid
bonds, underperformance penalties, etc.); EPA/IA etc.
5 Post-Procurement Stage
a Finalize Implementation Agreement after Award
b Financial close
c Monitoring, evaluation and enforcement procedures