pm final presentation
TRANSCRIPT
-
8/10/2019 PM Final Presentation
1/23
Team 7Rohan DeotaRazan FashhoCasey Franz
Ju Lee HyungUzair Mansuri
Basrah Childrens Hospital
-
8/10/2019 PM Final Presentation
2/23
Background
Risks
Problems Timelines and Costs
Prevention
Recovery Lessons Learned
Overview
-
8/10/2019 PM Final Presentation
3/23
Background
Basrah Location
15% Children die before 5years of age
Children suffering from preventable diseases
Childhood Leukemia >8% prior to 2000
Children accounted for 56% of reported Leukemiacases.
-
8/10/2019 PM Final Presentation
4/23
As part of the Iraq Relief and Reconstruction Program, the UnitedStates Agency for International Development (USAID) was taskedwith constructing a State of the Art 50-bed pediatric hospital in
Basrah, Iraq.
Background
-
8/10/2019 PM Final Presentation
5/23
Congress authorized $50 million to be spent for project from IraqRelief and Reconstruction Fund by USAID. (November 2003)
USAID and Project HOPE had Memorandum of Understanding
(MOU) where Project HOPE would take lead in providing asignificant portion of the hospital equipment and have responsibilityfor training medical and administrative staff. (January 2004)
USAID awards Bechtel National Incorporated with a design-buildcontract that required the hospital to be completed by December 31,2005 (October 2004)
July 2005, the design changed to a 94-bed facility including anoncology center at request of Iraqi Ministry of Health
Background
-
8/10/2019 PM Final Presentation
6/23
Natural: Earthquakes, Termites MitigationStructural Design
Location: Insufficient Water, Sewage Systems MitigationAdditional water system inlets, new gravity
conveyance sewage system
People: Hostility, Rebels MitigationSecurity Personnel
Risks
-
8/10/2019 PM Final Presentation
7/23
April 2005 USAID reports completion date to be May 31, 2006 (originally
December 31, 2005)
October 2005 USAID reports completion date to be October 31, 2006
March 2006 Bechtel reports completion date to be July 31, 2007 with an
estimated cost of $98 million (originally $50 million)
July 2006 Special Inspector General for the Iraq Reconstruction (SIGIR)
audited the project and found that USAID had insufficientoversight, inadequate accounting systems, and that they failed toreport the increasing budget to congress.
SIGIR estimated cost of project to be at least $149.5 million
TimelineProblem Signs
-
8/10/2019 PM Final Presentation
8/23
Problem Signs Bechtels in depth analysis submitted in 2005,
though BCH consideration was in 2004. Thorough technical feasibilityanalysis was not done
Error in basic engineering design. (water availability, seismicdesign, pumping stations in parallel)
Unrealistic timeframefor design and constructionBasrah Childrens Hospital
Term-Contract or fee contract
Kadhim Hassan little to no work had been donefor months. James Glanz
-
8/10/2019 PM Final Presentation
9/23
Project Changes
June 2006 USAID issues a Stop-Work notice to Bechtel
Program oversight transferred from USAID to the US Army
Corps of Engineers Gulf Region Division (USACE) Project was approximately 30% complete at time of transfer
September 2006 New contract awarded to MID Contracting with a new
completion date of July 21, 2008
-
8/10/2019 PM Final Presentation
10/23
Vendor Evaluation & Finalization Jul-04 to Oct-04
Detail design started Oct-04
Actual Construction started 14-Apr-05 (9 Mon ths later than JO date)
Structural Timeline
-
8/10/2019 PM Final Presentation
11/23
Seismic design did not meet standards Bechtel had to resubmit design for approval
Soil at sight could not support building
Bechtel added to foundation, adding 90 days to the schedule and $2.5million to budget
Security
By 2005, local militia and gangs had killed 24 on-site workers
Changing Scope
50-bed pediatric hospital100-bed facility based on oncology94-bedfacility supporting oncology and pediatrics
Communication Multi le artners involved fundin sources
Problems
-
8/10/2019 PM Final Presentation
12/23
Lack of effective oversight No on-site project management by USAID
Nationwide construction cost escalation 30-40% per year
Complex chain of subcontractorsused by Bechtel
Quality Issues
Civil work was not ready for installation Contract work was poor (cracks in walls and floors)
Since project was so far delayed, medical equipment providedin 2005 was not longer State of the Art
In 2009, the hospital had to change slogan to Modern
Problems
-
8/10/2019 PM Final Presentation
13/23
USGovernment
Project HOPE(US based
HealthOpportunities
PeopleEverywhere)
USAID (USAgency
InternationalDevelopment)
Bechtel(original
contractor)
MIDCON, UHS &Hospital Design and
Planning(HDP)
Sub-contractors
Departmentof State(DoS)
Government ofSpain (GOS) UNDP (United
NationDevelopment
Program)
Ministry ofHealth (MOH)
Iraq
USACE (GRD)
( US Armycorps of
Engineers Gulfregion
division)
Government ofIraq(GOI) US CommandersEmergency Relief
Program (USCERP)
MOU
Stakeholders/Agencies Involved
-
8/10/2019 PM Final Presentation
14/23
0
20
40
60
80
100
120
140
160
180
2004-Jun2006-Jun
2009-May
50
117.4
165.7
TotalProjectCost($Millio
ns)
Duration
Origin al Total Project Cos t: $50 m il l ion
Project Cost
-
8/10/2019 PM Final Presentation
15/23
2003 2003 2004 2005 2006 2007 2008 2009 2010 2010
BCH completelyinaugurated
10/21/10
Phase opening ofBCH started
11/30/09
USACE
takingoverproject
fromUSAID
6/27/06
USAID issued"Stop Work"
6/1/06
Initial ProjectCompletion date
12/31/05
JO amendmentwith official
scope defined7/7/04
JO released
on Bechtel
6/7/04
USAID awardedcontract to
Bechtel
1/5/04
Conceptualization 2003 - 2004
Fundamental Scope Change 2004 - 2005
Bechtel Work: (30% ProjectCompleted, 9 Months Delay with
cost overrun)
2004 - 2006
8 subsequent modifications in scope 2006 - 2007
United Nations ordering of 18 contracts in process 2007 - 2009
Phase Opening of BCHstarted
2009 - 2010
1 year
1 year
2 year
1 year
2 year
1 yr
Project Timeline
-
8/10/2019 PM Final Presentation
16/23
PMI Areas Matrices
Level: 1 2 3 4 5
Requirements
Definition
Statement of
purpose
Process to
identify
requirements
Stakeholders
involved in
requirements
Functions fully
documented
Incorporates
quality
improvement
Deliverable
Identification
Names of
deliverables
Customer &
management
identify deliv.
Detailed
description of
deliverable
Consistent
template for all
projects
Improvement
in process
Scope
Definition
Ad hoc, no
standards
Defined scope
statement
Assumptions
& constraints
clear
Documented &
monitored
Project
experience
data used
WBS Basic work
components
Third level
template
Jointly identify
all tasks
Inter-project
dependencies
documented
Regularly
monitored
Scope Change
Control
Ad hoc
communi-
cation
Documented
change
process
Baselines
established &
managed
Integrated with
organ.s
systems
Lessons
learned
Project ScopeManagement
Level: 1 2 3 4 5
Activity
Definition
Few or no
activities or
milestones
Scope
statement,
milestones
Process,
assumptions,
constraints
Activities
regularly
monitored
Continuously
improve
activity defin.
Activity
Sequencing
Ad hoc
sequencing
Process for
precedence
analysis
External
dependencies
dependencies
regularly
monitored
Improve
dependency
analysis
Schedule
Development
No process for
scheduling
Process for
scheduling
time & costs
Historical data
base for
scheduling
Resource
utilization
maximized
Improve
networks,
resource alloc
Schedule
Control
No baseline
control or
reporting
Schedule
status, chg.
control
Change
control,
earned value
Assess project
efficiency
Schedule
performance
analysis
Schedule
Integration
Ad hoc
grouping of
schedules
Manual
grouping of
schedules
Organization-
wide
schedules
Decisions
across
programs
Lessons
learned for
integration
Project TimeManagement
-
8/10/2019 PM Final Presentation
17/23
Level: 1 2 3 4 5
Resource
Planning
Individuals
identify
resource req.
Resource
listing defined
Project office
resource
repository
Integrated w/
project office &
HR
Improve
resource
priorities
Cost
Estimating
Scope
statement; ad
hoc estimates
Top WBS,
cost-estimate
template
Cost analysis
of alternatives
Integrated w/
finance, acct,
risk mgt
Improve
forecasting vs.
estimates
Cost
Budgeting
No established
practice
Baselining
process not
org standard
Time phased
estimates,
baselines
Integrated w/
finance, acct,
risk mgt
Baseline
lessons
learned
Performance
Management
Informal, ad
hoc
Summary level
tracking
Earned value,
corporate
financials
Performance
indices
Measure
efficiency &
effectiveness
Cost Control Non-standard
tracking
Periodic cost
reports
Variance
analysis, est to
complete
Cost reports
integrated w/
tech reports
Cost
assessments,
lessons learn
Level: 1 2 3 4 5
Risk
Identification
Risks not
identified
Risk
identification
process
Standards for
risk/symptom
identification
Integrated w/
cost & time
mgt, PMO
Identify org.
priority,
lessons learn
Risk
Quantification
Speculate on
impact if risks
occur
Structured
approach to
rating risks
Multiple
criteria
prioritization
Integrated w/
cost & time
mgt, finance
Improve
quantification
Risk
Response
Development
Risks
considered as
they arise
Informal
strategy for
handling risks
Contingency
plans
Integrated w/
cost & time
mgt, PMO
Tracking
project
reserves
Risk Control Day-to-day
problem
solving
Individualized
approach to
managing risk
Risks routinely
tracked
Integrated with
control
systems
Risk assess
included in
proj execution
Risk Docu-
mentation
No historical
database
Some
historical data
Historical data
on common
risks
Interdepen-
dent risks
betw projects
Improve
collection
activity
Project CostManagement
Project RiskManagement
PMI Areas Matrices
-
8/10/2019 PM Final Presentation
18/23
Identification
Scope
Prior to Design
Risks
Location
Engineering
Financial
Contingent Contract
Realistic Timeframe Cost
Contract Details
Management
Analysis
Location
Design
Funding Allocation
Technical and FinancialFeasibility
Monitoring and Reporting
Identify warning signs for
potential problems Communication between
stakeholders
Prevention
-
8/10/2019 PM Final Presentation
19/23
Evaluate/Audit Project
Problem areas and flaws
Review objectives and assumptions
Feasibility
Must have versus would like to have
Determine Tradeoffs
Urgent changes
Cost Effective changes
Feasible changes
Revise Goals
Change deliverables
Update WBS
Incorporate customers/stakeholders
Recovery
-
8/10/2019 PM Final Presentation
20/23
Technical feasibility of basic design and approval of those prior to startof work
Project timeframe should be evaluated and should be realistic
Evaluate risks and their impact on scheduling and cost
Ensure availability of resources required for the project and site surveyfor understanding the suitability of surrounding.
Baseline scheduling, monitoring and reporting for warning signs inproject
Designated project team with project manager coordinating betweendifferent agencies and taking the accountability of the project progress
Lessons Learned
-
8/10/2019 PM Final Presentation
21/23
Have personnel for on-site management and project oversight
Identification and implementation of control process.
Define a specific communication protocol for stakeholders withthe project management team
Cost estimation and cash flow to be organized and distributedover the project life cycle
Understand different local governments budgeting process
Progress status reporting at regular intervals of time
Lessons Learned
-
8/10/2019 PM Final Presentation
22/23
Works Cited"Al Basra Children Hospital Historical Records"Enr. Construction.com. N.p., n.d. Web. 10 Apr. 2013.
Basrah Childrens Hospital Basrah, Iraq. Special Inspector General for Iraq Reconstruction (SIGIR) Report. PA-08-160. 28 July 2009.
Glanz, James. "SERIES OF WOES MAR IRAQ PROJECT HAILED AS MODEL." The New York Times. The New York
Times, 28 July 2006. Web. 10 Apr. 2013.
Kerzner, Harold. Recovery Project Management: Techniques and Tactics for Reversing Failing Projects. InternationalInstitute for Leaning, Inc. www.iil.com. Web. 10 April 2013.
Rageh, Rawya. "Iraq Hospital Touted by Laura Bush Delayed." The Washington Post. N.p., 28 July 2006. Web. 10 Apr.
2013.
Review of the US Agency for International Developments Management of the Basrah Childrens Hospital Project.Special Inspector General for Iraq Reconstruction (SIGIR) Report. SGIR-06-026. 31 July 2006.
Photos: http://www.fayeandsteve.com/Basrah%20Children's%20Hospital.htm, http://www.army.mil/article/47156
http://www.fayeandsteve.com/Basrah%20Children's%20Hospital.htmhttp://www.army.mil/article/47156http://www.army.mil/article/47156http://www.fayeandsteve.com/Basrah%20Children's%20Hospital.htm -
8/10/2019 PM Final Presentation
23/23
Questions