  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    1/16

    Z-Axis

    Have Engineered A Solution

    ETABS

    toARC BDSLite

    A Boon Tool To Generate RC Beam L.S

    Details

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    2/16

    Why use this Plug-In

    As of now ARC BDS does not generate layout

    from ETABS file hence, to generate Beam L.S forentire floor this Plug-In can be used.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    3/16

    Procedure generate Beam L.S Details from ETABS MDB file

    To Generate the MDB file (from ETABS ) the following tables are

    required

    Please set the output unit to kN-m before generating the table.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    4/16

    "Control Parameters"

    "Story Data"

    "Point Coordinates"

    "Column Connectivity Data"

    "Beam Connectivity Data"

    "Frame Section Assignments"

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    5/16

    "Concrete Beam Section Design Data"

    Concrete Column Section Design Data

    "Concrete Design 2 - Beam Summary Data - Indian IS 456-2000";

    From ETABS generate an MDB file having the above tables.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    6/16

    In ARC BDS-> Add On Tools -> Plugins -> Etabs to Lite

    The dialog below appears

    Select Etabs MDBIntelli Rein Excel option and click Process

    Button the dialog box below appears

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    7/16

    Click on Extract Button or button the following dialog appears

    1. Select an appropriate MDB file and click Open button

    2. Click Extract Button the program generates an XLS sheet

    ******_Intellirein.xls (where ***** is the MDB file name)

    The Path of the XLS file is shown as Hint when the mouse is taken near

    the Link.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    8/16

    That file is the BASE for generating the ARC BDS Lite file,

    a. It contains all the Beams extracted from ETABS file

    b. Each extracted beam has

    Row Name (the program creates a row nameautomatically by clubbing all the individual span

    names of the row of beam) Preferred Diameters to be used for reinforcement

    Each Individual Span name

    Size & Length of each span

    Steel Reinforcement AREAS of Each span of beam

    including stirrups

    Left and right parent type and sizes

    For a detailed explanation of the ******_Intellirein.xls file seeEditing the INTELLI-REIN SHEET help document

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    9/16

    Once the ******_Intellirein.xls is modified,

    Select Create ARC BDSLite Input file and click Process button.

    The dialog below appears

    if the process of creating the ******_Intellirein.xls isdone in this session of work only, the Excel Name

    will be populated with appropriate******_Intellirein.xls file

    Otherwise if the ******_Intellirein.xls file ismodified else where or in a different session click[] button and select an appropriate

    ******_Intellirein.xls file.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    10/16

    Click on Load from Excel button

    Click on Export to ARC BDSLite

    Click on OK

    Click on Exit the ARC BDSLite file is generated; it can be loaded by

    ARC BDSLite version.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    11/16

    Once Loaded

    Once the file is opened by ARCBDS

    In the list of beams click right buttonand click Sort By Row Name

    It will sort all the beams row wise,

    and that is how the output will come.

    Click on Reinforcement Tab

    Click on Open Reinforcement

    Data Sheet

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    12/16

    Ensure that you have the backup of the OLD reinforcement sheet ifrequired as by CLICKING YES in this dialog.

    YOU WILL LOOSE OLD REINFORCEMENT DATA if any.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    13/16

    The xls file created when clicking Yes will contain the data that is

    there in the Current *.ZBLD file

    Up to this point, all this can be done by the draftsmen in charge.

    The draftsmen should save the xls file and give that file to the engineer.

    Note:- The draftsmen should complete all the things required such

    as

    Row Grouping

    Splitting of rows if required

    Deleting of Beams

    Adding of beams

    Adding of Grid Numbers etcAll this should have been already done when editing the

    ******_Intellirein.xls file, in case something is missed the draftsmen can

    use the features of ARC BDSto modify them.

    Once the file XLS file is generated, the draftsmen in charge should NOTadd / deleted any beams in the *.ZBLD file until the Design Engineer has

    completed the Modification of the reinforcement.

    The design engineer should take care that this reinforcement XLS is done

    properly, if this is done perfectly the drawing NEED NOT BECHECKED for REINFORCEMENT.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    14/16

    If all the steps above are followed in perfect sequential manner the onlywork the design engineer will have is to modify the xls file given by the

    draftsmen.

    Once the draftsmen receive the modified xls file.

    Click on Open Reinforcement

    Data Sheet

    In the xls sheet opened, replace allthe reinforcement data given by

    Design engineer using copy

    /paste

    Save the xls file

    Click Load Reinforcement FromData Sheet and save the ARCBDS lite file

    Warning: - if this process is NOTdone, the changed reinforcement

    will NOT be saved.

    Once this is done; WORK IS OVER. Click GO (Generate Output)

    button and generate the entire beam L.S.

    If the process is done perfectly, in days time you can generate Beam

    L.S for entire floor, the only thing left will be to put them in title block

    and edit some clashes.

    By Editing the Reinforcement in xls sheet instead of the final drawing,the advantage is that the steel take off will be very accurate.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    15/16

    Precautions to be taken in Input file of ZBLD.

    1. To reduce the number of sections in the final output

    In Settings MenuBeam General Settingsa. Remove all the checks in Show Sections At

    b.

    If you are having varying slab depths in the floorselect Show Total Depth in Cross Section Depth

    c. Select Row in Show Cross Sections per

    2. Ensure Proper scaling is set, if the beams are very large or

    spans are many you can have a different Horizontal scale &

    different scale i.e. select 1:100 scale for LS & 1:50 scale forsection, that way most of the beams will be within the title

    block of A1.3. Ensure the grids of the beams are properly placed (you can

    use the Open Excel Data button

    Note: - Only for the 1stbeam Left and right Grids need to be

    given for all the other beams in the row you can give only the Right Grid.

    4. Do a dry run of the file once it generates the layout, see the

    important beams that require the cross section to be shownnote the numbers and go back to Detailed Edit of the

    beams for which the section is required.

  • 8/10/2019 Plug-In of Arc Bds Etabs to Lite

    16/16

    Select the required section

    5.

    For getting your title block in the paper space, where everthe ARC BDS.exe is present normally C:\Program

    Files\ZaxisES\ARC BDS Lite there will be aLayouts.DWG file Open the dwg

    Insert your title block in appropriate Layout of AutoCAD

    for example insert (SI units) A1 Title Block in A1MMTab and erase the green lines.

    If this process is done every drawing will be generated yourtitle block.

    Please Note:- if these procedures are followed in Toto, youwill get a 95 % ready drawing with beams placed in your title