plug-in of arc bds etabs to lite
TRANSCRIPT
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
1/16
Z-Axis
Have Engineered A Solution
ETABS
toARC BDSLite
A Boon Tool To Generate RC Beam L.S
Details
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
2/16
Why use this Plug-In
As of now ARC BDS does not generate layout
from ETABS file hence, to generate Beam L.S forentire floor this Plug-In can be used.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
3/16
Procedure generate Beam L.S Details from ETABS MDB file
To Generate the MDB file (from ETABS ) the following tables are
required
Please set the output unit to kN-m before generating the table.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
4/16
"Control Parameters"
"Story Data"
"Point Coordinates"
"Column Connectivity Data"
"Beam Connectivity Data"
"Frame Section Assignments"
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
5/16
"Concrete Beam Section Design Data"
Concrete Column Section Design Data
"Concrete Design 2 - Beam Summary Data - Indian IS 456-2000";
From ETABS generate an MDB file having the above tables.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
6/16
In ARC BDS-> Add On Tools -> Plugins -> Etabs to Lite
The dialog below appears
Select Etabs MDBIntelli Rein Excel option and click Process
Button the dialog box below appears
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
7/16
Click on Extract Button or button the following dialog appears
1. Select an appropriate MDB file and click Open button
2. Click Extract Button the program generates an XLS sheet
******_Intellirein.xls (where ***** is the MDB file name)
The Path of the XLS file is shown as Hint when the mouse is taken near
the Link.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
8/16
That file is the BASE for generating the ARC BDS Lite file,
a. It contains all the Beams extracted from ETABS file
b. Each extracted beam has
Row Name (the program creates a row nameautomatically by clubbing all the individual span
names of the row of beam) Preferred Diameters to be used for reinforcement
Each Individual Span name
Size & Length of each span
Steel Reinforcement AREAS of Each span of beam
including stirrups
Left and right parent type and sizes
For a detailed explanation of the ******_Intellirein.xls file seeEditing the INTELLI-REIN SHEET help document
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
9/16
Once the ******_Intellirein.xls is modified,
Select Create ARC BDSLite Input file and click Process button.
The dialog below appears
if the process of creating the ******_Intellirein.xls isdone in this session of work only, the Excel Name
will be populated with appropriate******_Intellirein.xls file
Otherwise if the ******_Intellirein.xls file ismodified else where or in a different session click[] button and select an appropriate
******_Intellirein.xls file.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
10/16
Click on Load from Excel button
Click on Export to ARC BDSLite
Click on OK
Click on Exit the ARC BDSLite file is generated; it can be loaded by
ARC BDSLite version.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
11/16
Once Loaded
Once the file is opened by ARCBDS
In the list of beams click right buttonand click Sort By Row Name
It will sort all the beams row wise,
and that is how the output will come.
Click on Reinforcement Tab
Click on Open Reinforcement
Data Sheet
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
12/16
Ensure that you have the backup of the OLD reinforcement sheet ifrequired as by CLICKING YES in this dialog.
YOU WILL LOOSE OLD REINFORCEMENT DATA if any.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
13/16
The xls file created when clicking Yes will contain the data that is
there in the Current *.ZBLD file
Up to this point, all this can be done by the draftsmen in charge.
The draftsmen should save the xls file and give that file to the engineer.
Note:- The draftsmen should complete all the things required such
as
Row Grouping
Splitting of rows if required
Deleting of Beams
Adding of beams
Adding of Grid Numbers etcAll this should have been already done when editing the
******_Intellirein.xls file, in case something is missed the draftsmen can
use the features of ARC BDSto modify them.
Once the file XLS file is generated, the draftsmen in charge should NOTadd / deleted any beams in the *.ZBLD file until the Design Engineer has
completed the Modification of the reinforcement.
The design engineer should take care that this reinforcement XLS is done
properly, if this is done perfectly the drawing NEED NOT BECHECKED for REINFORCEMENT.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
14/16
If all the steps above are followed in perfect sequential manner the onlywork the design engineer will have is to modify the xls file given by the
draftsmen.
Once the draftsmen receive the modified xls file.
Click on Open Reinforcement
Data Sheet
In the xls sheet opened, replace allthe reinforcement data given by
Design engineer using copy
/paste
Save the xls file
Click Load Reinforcement FromData Sheet and save the ARCBDS lite file
Warning: - if this process is NOTdone, the changed reinforcement
will NOT be saved.
Once this is done; WORK IS OVER. Click GO (Generate Output)
button and generate the entire beam L.S.
If the process is done perfectly, in days time you can generate Beam
L.S for entire floor, the only thing left will be to put them in title block
and edit some clashes.
By Editing the Reinforcement in xls sheet instead of the final drawing,the advantage is that the steel take off will be very accurate.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
15/16
Precautions to be taken in Input file of ZBLD.
1. To reduce the number of sections in the final output
In Settings MenuBeam General Settingsa. Remove all the checks in Show Sections At
b.
If you are having varying slab depths in the floorselect Show Total Depth in Cross Section Depth
c. Select Row in Show Cross Sections per
2. Ensure Proper scaling is set, if the beams are very large or
spans are many you can have a different Horizontal scale &
different scale i.e. select 1:100 scale for LS & 1:50 scale forsection, that way most of the beams will be within the title
block of A1.3. Ensure the grids of the beams are properly placed (you can
use the Open Excel Data button
Note: - Only for the 1stbeam Left and right Grids need to be
given for all the other beams in the row you can give only the Right Grid.
4. Do a dry run of the file once it generates the layout, see the
important beams that require the cross section to be shownnote the numbers and go back to Detailed Edit of the
beams for which the section is required.
-
8/10/2019 Plug-In of Arc Bds Etabs to Lite
16/16
Select the required section
5.
For getting your title block in the paper space, where everthe ARC BDS.exe is present normally C:\Program
Files\ZaxisES\ARC BDS Lite there will be aLayouts.DWG file Open the dwg
Insert your title block in appropriate Layout of AutoCAD
for example insert (SI units) A1 Title Block in A1MMTab and erase the green lines.
If this process is done every drawing will be generated yourtitle block.
Please Note:- if these procedures are followed in Toto, youwill get a 95 % ready drawing with beams placed in your title
block and with NO errors in reinforcement and only few dimclashes that can be edited easily.