plm220 - project management logistics
TRANSCRIPT
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 1/312
SAP AG 2003
PLM220 Project Management - Logistics
THE BEST RUN E BUSINESSES RUN SAP
© SAP AG 2003
PLM220
Project Management –
Logistics
SAP R/3 Enterprise System
2003/Q2
Material number: 5006 1247
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 2/312
SAP AG 2003
Copyright 2003 SAP AG. All rights reserved.
No part of this publication may be reproduced or transmitted in
any form or for any purpose without the express permission of
SAP AG. The information contained herein may be changed
without prior notice.
All rights reserved.
Copyright
Trademarks:
Some software products marketed by SAP AG and its distributors contain proprietary softwarecomponents of other software vendors.
Microsoft®, WINDOWS®, NT®, EXCEL®, Word®, PowerPoint® and SQL Server® are registered
trademarks of Microsoft Corporation.
IBM®, DB2®, DB2 Universal Database, OS/2®, Parallel Sysplex®, MVS/ESA, AIX®, S/390®,
AS/400®, OS/390®, OS/400®, iSeries, pSeries, xSeries, zSeries, z/OS, AFP, Intelligent Miner,
WebSphere®, Netfinity®, Tivoli®, Informix and Informix® Dynamic ServerTM are trademarks of IBM
Corporation in USA and/or other countries.
ORACLE® is a registered trademark of ORACLE Corporation.
UNIX®, X/Open®, OSF/1®, and Motif® are registered trademarks of the Open Group.
Citrix®, the Citrix logo, ICA®, Program Neighborhood®, MetaFrame®, WinFrame®, VideoFrame®,
MultiWin® and other Citrix product names referenced herein are trademarks of Citrix Systems, Inc.
HTML, DHTML, XML, XHTML are trademarks or registered trademarks of W3C®, World Wide WebConsortium, Massachusetts Institute of Technology.
JAVA® is a registered trademark of Sun Microsystems, Inc.
JAVASCRIPT® is a registered trademark of Sun Microsystems, Inc., used under license for technology
invented and implemented by Netscape.
MarketSet and Enterprise Buyer are jointly owned trademarks of SAP AG and Commerce One.
SAP, SAP Logo, R/2, R/3, mySAP, mySAP.com, and other SAP products and services mentioned herein
as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and in
several other countries all over the world. All other product and service names mentioned are the
trademarks of their respective companies.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 3/312
SAP AG 2003
Basic knowledge of project management, particularly from a
logistics perspective
PLM210 or PLM200* (or their predecessors CA800 and
CA080)
* PLM200 is also a valid prerequisite course. In this case the participant
must be aware that some topics related to planning and implementation
are repeated and covered in greater detail.
Prerequisites
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 4/312
SAP AG 2003
Participants:
Project managers and engineers
Project team
Consultants
Duration: 5 days
Target Audience
Note:
The training materials are not teach-yourself programs. They complement the course instructor's
explanations. Your material includes space for making notes.
The exercises are designed to supplement the topics and examples dealt with in the course. There may
not be enough time during the course to complete all of the exercises. In this case, you can work through
these examples after the course to consolidate what you have learned.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 5/312
© SAP AG PLM220 1-1
SAP AG 2003
Course Overview
Course goals
Course objectives
Course content
Course overview diagram
Main business scenario
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 6/312
© SAP AG PLM220 1-2
SAP AG 2003
Course Goals
This course will prepare you to:
Plan and control projects from a logistics
perspective
Make the necessary settings in Customizing
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 7/312
© SAP AG PLM220 1-3
SAP AG 2003
At the conclusion of this course, you will be able to:
Schedule projects
Plan and execute internal services
Trigger and work on procurement processes
Procure and deliver material for a project
Course Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 8/312
© SAP AG PLM220 1-4
SAP AG 2003
Course Content
Unit 5 External Services
Unit 6 Materials
Unit 7 Progress Tracking
Unit 8 ProMan
Unit 1 Course Overview
Unit 2 Project Structures
Unit 3 Scheduling
Unit 4 Capacities
Introduction
Exercises and Solutions
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 9/312
© SAP AG PLM220 1-5
SAP AG 2003
Course Overview
Course
Overview
Project
Structures
Scheduling
Capacities
External
Services
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 10/312
© SAP AG PLM220 1-6
SAP AG 2003
This course will familiarize you with all aspects of
Logistics in R/3 Project System. You will plan andpost internal and external services. You will also
procure material.
Main Business Scenario
Each unit of the course contains a Business Scenario section that illustrates how you can put the related
topics into practice. It also sets tasks that you will be able to perform after completing each unit. Themain business scenario applies to the entire course.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 11/312
© SAP AG PLM220 1-7
SAP AG 2003
Sample Turbine Project
300030003000
310031003100
200020002000
400040004000
T-200##.1Engineering/
Design
TT--200##.1200##.1Engineering/ Engineering/
DesignDesign
T-200##.2Planning
TT--200##.2200##.2Planning Planning
T-200##.3Purch.
TT--200##.3200##.3Purch.Purch.
T-200##.4Production
TT--200##.4200##.4ProductionProduction
T-200##.5 Assembly
TT--200##.5200##.5 Assembly Assembly
T-200##Turbine
TT--200##200##TurbineTurbine
100010001000
90xxxx
ActivitiesActivities
Relation-
ships
Relation-
ships
NetworkNetwork120012001200
310031003100
300030003000
500050005000
110011001100
130013001300
501050105010
200020002000
503050305030502050205020
400040004000
100010001000
110011001100
120012001200
130013001300501050105010
502050205020
503050305030
T-200##.2.1Systems
TT--200##.2.1200##.2.1SystemsSystems
T-200##.2.2Instruments
TT--200##.2.2200##.2.2InstrumentsInstruments
Project
definition
Project
definition
WBS elementsWBS elements
500050005000
List of activ-
ities for WBS
element
(or network)
List of activ-
ities for WBS
element
(or network)
This slide shows the project that is used as an example in the course. Only dates but no other logistic
aspects are dealt with at WBS element level. The logistic aspects of the project, for example, internal andexternal tasks and material requirements are planned and executed using activities
The icons in this slide correspond to those used in the R/3 System for project definitions, WBS elements,
network headers, activities, and relationships.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 12/312
© SAP AG PLM220 1-8
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 13/312
© SAP AG PLM220 2-1
SAP AG 2003
Project Structures
You will become familiar with various options for
editing project structures
You will use the Project Builder to create a project
for producing a turbine
You will be introduced to claim management
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 14/312
© SAP AG PLM220 2-2
SAP AG 2003
Project Structures: Unit Objectives
Create project structures with WBS elements and
activities in the Project Builder
At the conclusion of this unit, you will be able to:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 15/312
© SAP AG PLM220 2-3
SAP AG 2003
Project Structures: Overview
Course
Overview
Project
Structures
Scheduling
Capacities
External
Services
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 16/312
© SAP AG PLM220 2-4
SAP AG 2003
Project Structures: Business Scenario
Your company produces turbines. It has become
clear that these turbines are too complex toproduce using production orders. As an
alternative, use WBS elements and activities in
Project System.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 17/312
© SAP AG PLM220 2-5
SAP AG 2003
Work Breakdown Structure - Functions
Costs/Revenue
Payment Data
Budget
Commitment
Dates
Periodic Processing
Planned
costs/
revenues
Actual costs/
revenues
Planning of
payments
debit-side/
credit-side
Updating of
actual data
Basic dates
Scheduled dates
Actual dates
Purchase requisition
Purch. order
Overheads,
process costs
Interest calculation
Results analysis
Settlement
Original budget
Budget updates
Budget releases
Availability
control
P u r c h .o r d e r
The work breakdown structure (WBS) forms the basis for all subsequent planning tasks in the project.
The emphasis is on planning, analysis, description, control, and monitoring of costs, basic dates, and the budget.
Costs, dates, and payments are often planned using activities, which are assigned to WBS elements.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 18/312
© SAP AG PLM220 2-6
SAP AG 2003
Work Breakdown Structure: Maintenance Options
Copy 3
Manually 1
Hierarchy Graphic
Paste
Project Builder
= Standard structure
= Operative structure
Display
area
Navigation area
4
2
You can use the Project Builder to create and change WBS elements.
You can use detail screens or the overview list screen for this purpose.
You can use the hierarchy graphic to change WBS elements (by double-clicking). You can also create
new WBS elements, and insert these into the hierarchy (connection mode).
In addition to manual maintenance or maintenance using the hierarchy graphic (1, 2), you can also copy
elements from existing project structures or standard projects:
When you create a new WBS, you can copy elements from an existing WBS, a section of the project
hierarchy, or a standard WBS. You can also incorporate WBS elements from other projects or from a
standard WBS into an existing WBS (3, 4).
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 19/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 20/312
© SAP AG PLM220 2-8
SAP AG 2003
Activities and Networks: Functions
Internal Activity
External
Activity/Service
Material
Periodic Processing
General Costs Activity
Milestones
Billing dates based on
billing milestones
(invoice/down payment) Dates
Costs,
commitments
Payments
Process costs
Overheads
Settlement
Work
Dates,
capacities Cost
Dates
Costs
Payments
Purch. parts/assemblies
Dates Costs, commitments
Payments
You use the activities in the network to plan the labor, capacities, materials, operating facilities, and
services you require to carry out the various tasks in your project.
The unit on capacities discusses internally processed activities in detail.
The unit on external activities deals with externally processed activities and service activities.
The unit on material explains how material components are assigned, procured, and consumed in the
network.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 21/312
© SAP AG PLM220 2-9
SAP AG 2003
Activities: Maintenance Options
Copy Project
with Activities
Copy
= Standard
structure
= Operative
structure
3
5
Manually 1
Paste 4
Network Structure Graphic
Navigation area Insert area
Display area
2
Project Builder
As well as maintaining data manually or using the network graphic (1, 2), you can use existing operative
structures or standard structures as templates.
When you create activities, you can use a standard network or an existing network as a template (3). You
can also incorporate standard networks into an existing network (4).
You can use the Project Builder or the project planning board to copy a standard project or operative
project (including all activities) to a new project structure (5).
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 22/312
© SAP AG PLM220 2-10
SAP AG 2003
Network Graphic
Activitynumber
Control
key
Duration
Description
Earliest
finish
Latest
finishFloats
Relationship
Activity
Days Days Days
Days
Specification Mechanical Layout Procurement
Electronic Layout
16.0 2.2000 18.02. 2000
06.04.200004.04.2000
21.02.2000
07.0 4.2000 07.0 7.20 00
17.05.2000
21.02.2000
07.07.2000
31.03.2000
24.05.2000
10.07.2000
18.05.2000
28.07.2000
08.06.2000
FS
FS FS
FS
34 3434
0 340
64
30
The network graphic displays detail information for each activity. The detail displayed includes:
Activity member, Activity Control key, the activity duration, the description of the activity, the earliest
and latest scheduled dates and any float days.
Each activity is connected using relationships. The relationships are displayed in the network graphic.
Relationships detremine the flow of the activities.
Activities can be created in the network graphic. Relationships can also be created to connect activities
in the network graphic.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 23/312
© SAP AG PLM220 2-11
SAP AG 2003
Project Planning Board
Project Edit Goto Details Settings View Extras System Help
Project: Change
E O E IdentificationWork Pln Proj. cost plan
Work
Pln Name
Universal work center
Capacity Overview
project: Turbine 2000Jan 99 March 99 Apr 99Feb 99 May 99 June 99 July 99
Jan 99 March 99 Apr 99Feb 99 May 99 June 99 July 99
Table
area Graphic
area
Extended
toolbar
Chart, e.g.
capacities
15000
20000
30000
20000
50000
10000
20000
5000
The project planning board is particularly suitable for planning a project. It provides you with an instant
overview of your project deadlines, enabling you to check your project for capacity bottlenecks.Additional options are available for enhancing your project structure. In the following units, you will use
both the Project Builder and the project planning board to work on your project.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 24/312
© SAP AG PLM220 2-12
SAP AG 2003
Claim
Evaluating Claims
Document
as a CLAIM
Start follow-up
actions
Internet
Services
Workflows
Long
Texts
Action Log
Safety Measures
Actions
Cost Integration
BusinessPartners
Cost Planning
Archiving
Documents
Status
Management
Project Plan Variances
Variances from the project plan often occur as a result of delivery problems, price fluctuations,
unforeseeable capacity bottlenecks, and so on. In this case, it is very important to clarify which partner(s)to the contract is/are responsible and to what degree. Claim Management ensures that claims resulting
from variances are drawn up against the contractual partner and submitted at a suitable point in time.
Conversely, it also helps defend against claims made by the contractual partner. You can use the Claim
message type in Project System to document variances from your project plan, appoint persons
responsible for the variance, and initiate follow-up activities.
You can enter claims directly in the R/3 System or create and display them from the Internet (for
example: a customer creates a claim using the Internet).
You can include the following data in a claim:
Descriptions, for example, the cause of variances
Actions and tasks to be initiated because of the variance
Persons responsible and partners using a link to the Partner Management function
Costs incurred as a result of the variance (cost planning using unit costing)
Assignment to WBS elements, SD and MM document items
Assignment of document info records (links to the Document Management System)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 25/312
© SAP AG PLM220 2-13
SAP AG 2003
Create project structures from WBS elements and
activities in the Project Builder
You are now able to:
Project Structures: Unit Summary
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 26/312
© SAP AG PLM220 2-14
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 27/312
© SAP AG PLM220 2-15
Exercises
Unit: Project Structures
Topic: Structures
• Project Builder
• Hierarchy graphic
• Network graphic
• Project planning board
In the following exercises, you will create a work breakdown structure
with assigned activities. You will work mainly with the Project Builder.To display the work breakdown structure, you will call both the hierarchy
and the network graphic. The project planning board will provide youwith an integrated overview of your project.
1-1 You will use the standard structure as a template for creating the project. To do this,
call the Project Builder.
1-1-1 Create project T-100## using the standard project T-20001 as a template. ## is
a placeholder for your group number (if you are in group 3, then replace ##
with 03).
In the dialog box that appears, enter the following data:
Field Name Values
Project def. T-100##
Start Today
Finish date Two years from today
Project profile Turbine model group 1
Template std proj. def. T-20001
1-1-2 Enter a name for your project, and the person responsible. Maintain the data at
project definition level.
Field Name Values
Text Group ##, turbine A
Person responsible ##
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 28/312
© SAP AG PLM220 2-16
1-1-3 Provide details for the WBS element Planning of systems and instrumentation
by creating two further WBS elements.
Enter the description Planning of systems for the new WBS element.
Use the same procedure to create the second WBS element. Call it Planning of
instrumentation.
1-1-4 Display your expanded structure in the hierarchy graphic.
Expand the display to show the entire project.
Set the Planning element indicator for the new WBS elements.
1-1-5 As a result of these changes, activity 2000 Planning of systems and
instrumentation is no longer correctly assigned. Rename it “Planning of systems” and assign it to the appropriate WBS element.
1-1-6 To plan your turbine instrumentation, create an activity for the Planning of
instrumentation WBS element.
The detail screen for the new activity appears. Enter the following data in thedetail screen:
Field Name Values
Long text Planning of instrumentation
Work Center 2000
Work 35 hours Normal duration 5 days
1-1-7 Take a look at your extended network in the network graphic.
Save the project. The temporary network number is then replaced.
1-1-8 Call the project planning board to obtain an integrated view of your project
deadlines. Use the Elevators/Turbines project planning board profile and carryout time scheduling.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 29/312
© SAP AG PLM220 2-17
1-1-9 Plan the material costs for your turbine. You are still unsure about which
components you will procure in the future, but you can still plan material costsfor the activities. Plan the activities Preliminary orders and Material
procurement plant components.
Enter the following data:
Activity Material Planning
3000 Preliminary orders EUR 100,000
3100 Material procurement
plant components
EUR 65,000
Save your data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 30/312
© SAP AG PLM220 2-18
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 31/312
© SAP AG PLM220 2-19
Solutions
Unit: Project Structures
Topic: Structures
• Project Builder
• Hierarchy graphic
• Network graphic
• Project planning board
In the following exercises, you will create a work breakdown structure
with assigned activities. You will work mainly with the Project Builder.To display the work breakdown structure, you will call both the hierarchy
and the network graphic. The project planning board will provide youwith an integrated overview of your project.
1-1 You will use the standard structure as a template for creating the project. To do this,
call the Project Builder.
SAP menu
Logistics Project System Project Project Builder ( Double-click to select the Project Builder )
1-1-1 Create project T-100## using the standard project T-20001 as a template. ## is
a placeholder for your group number (if you are in group 3, then replace ##with 03).
Select Create Copy pr o ject.
In the dialog box that appears, enter the following data:
Field Name Values
Project def. T-100##
Start TodayFinish date Two years from today
Project profile Turbine model group 1
Template std proj. def. T-20001
Select Create project to confirm.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 32/312
© SAP AG PLM220 2-20
The tree structure on the left of the screen now displays various
objects that have been copied from the standard project:
Project definition (1st row)
+ WBS elements
+ Activities+ Network header
+ Milestone (last row)
The activities are grouped together in a network with a provisional
number (%00000000001). This number is replaced when you savethe activities.
1-1-2 Enter a name for your project, and the person responsible. Maintain the data at
project definition level.
Select the project definition in the structure tree.
Enter the following data on the details screen that appears:
Field Name Values
Text Group ##, turbine A
Person responsible ##
Confirm your entries by selecting Enter.
1-1-3 Provide details for the WBS element Planning of systems and instrumentation
by creating two more WBS elements.
Move the cursor to the templates area (bottom left) and expand Individual
objects if necessary.
Drag and drop a WBS element from the templates area to the WBS element
Planning of systems and instrumentation tree structure .
Enter the description Planning of systems for the new WBS element.
Enter the description in the Text field.
Select Enter to confirm your entries.
The new WBS element is now displayed in the tree structure.
Use the same procedure to create the second WBS element. Call it Planning of
instrumentation.
Select Enter to confirm your entries.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 33/312
© SAP AG PLM220 2-21
1-1-4 Display your expanded structure in the hierarchy graphic.
Select Hierarchy graphic in the Project Builder.
Expand the display to show the entire project.
Choose View → Complete view .
Set the Planning element indicator for the new WBS elements.
Double-click the appropriate indicator.
Select Back to exit the hierarchy graphic.
1-1-5 As a result of these changes, activity 2000 Planning of systems and
instrumentation is no longer correctly assigned. Rename it and assign it to theappropriate WBS element.
Position the cursor on the activity in the tree structure.
Drag and drop the activity to the WBS element Planning of systems.
Change the description of the activity.
Enter the new description Planning of systems in the Text field.
Select Enter to confirm your entries.
1-1-6 To plan your turbine instrumentation, create an activity for the Planning ofinstrumentation WBS element.
Expand the Activity icon in the templates area. Drag and drop the Activity (internal) entry from the templates area to the
WBS element Planning of instrumentation in the tree structure.
The detail screen for the new activity appears. Enter the following data on the
detail screen:
Field Name Values
Long text Planning of instrumentation
Work Center 2000
Work 35 hours
Normal duration 5 days
Select Enter to confirm your entries.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 34/312
© SAP AG PLM220 2-22
1-1-7 Take a look at your extended network in the network graphic.
Position your cursor on the Turbine network header in the tree structure.
Select Network graphic.
To display an overview of the entire network, select Complete view .
If you can no longer identify details in the activity display, change it using the
Activities icon and choose the small display format.
Select Back to exit the structure overview.
Save the project. The temporary network number is then replaced.
Choose Save .
1-1-8 Call the project planning board to obtain an integrated view of your project
deadlines. Use the Elevators/Turbines project planning board profile and carryout time scheduling.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project
(Double-click the transaction to select it)
On the initial screen, enter your project definition T-100## and planning board
profile and “Elevators/Turbines” open the project planning board.
Enter the project and project board profile, and select Enter .
Modify the date’s view of the planning board.
Select Adapt graphic area .
Carry out time scheduling for your project.
Choose Select all and then Schedule .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 35/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 36/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 37/312
© SAP AG PLM220 3-1
SAP AG 2003
Scheduling: Contents
Time scheduling with WBS elements
Scheduling activities
Setting scheduling in Customizing
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 38/312
© SAP AG PLM220 3-2
SAP AG 2003
Plan dates for activities and WBS elements usingthe project planning board
Set the relevant tables in Customizing
At the conclusion of this unit, you will be able to:
Scheduling: Unit Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 39/312
© SAP AG PLM220 3-3
SAP AG 2003
Scheduling: Overview
CourseOverview
ProjectStructures
Scheduling
Capacities
ExternalServices
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 40/312
© SAP AG PLM220 3-4
SAP AG 2003
You have already created a project structure toproduce a turbine. The project manager now wantsto know whether the project can be completed ontime. Schedule your project to establish this.
Scheduling: Business Scenario
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 41/312
© SAP AG PLM220 3-5
SAP AG 2003
Dates (1)
Sets of dates Basic dates
Forecast dates Actual dates
Check dates
WBS/WBS
WBS/network
Inherit
Extrapolation++++
Scheduling
Scheduled start/finish
Planning different calendars
Monday
Monday
MondayMay30
Not aworkday
Shift
Planning form
The following functions are available here:
Sets of dates: Basic and forecast dates can be used as planned dates. Actual dates are also shown here.
Check dates: You can check the consistency of dates in the project structure, with or without taking
activities into account.
Inherit: Dates within the WBS can be inherited. This does not affect the activity dates.
Extrapolation: You can use the extrapolate function to calculate the dates for higher-level WBS
elements.
Shift: You can shift all of the planned dates for the WBS elements, or just the dates in sub-hierarchies.
Planning different calendars: You can use a different factory calendar for each activity or WBS
element.
Scheduling: The scheduling function calculates the dates for activities and networks.
Planning form: You can use the planning form to extrapolate dates automatically, for example, when
you save your data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 42/312
© SAP AG PLM220 3-6
SAP AG 2003
Project Dates
BASIC DATES FORECAST DATES Scheduled dates
Actual dates
BASIC DATES Scheduled dates
Actual dates
CONSTRAINTS Earliest (scheduled) dates
Latest (scheduled) dates
Actual dates
Earliest (scheduled) dates
Latest (scheduled) dates
Actual dates
BOLD = Manual planning dates Italics = Dates calculated by the system
BASIC DATES
WBSelements
Networkheader
Networkactivity
Activityelement
Projectdefinition
You define different dates at every level of the project (project definition, network, activities, and
activity elements).
You can adjust these dates in the project hierarchy using either top-down or bottom-up planning.
The following types of dates are available in the system, and occur at all levels:
Basic dates are defined manually, and are often binding for lower-level objects.
Activities can be fixed by means of time constraints.
Scheduled dates (or earliest and latest dates for activities) are determined automatically when network
activities are scheduled. Scheduled dates are determined for WBS elements by summarizing the
scheduling data of the corresponding activities.
In the realization phase of the project, actual dates are set by entering actual dates for WBS elements,
or by confirming activities. Forecast dates are a means of storing a specific scheduling scenario for information purposes.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 43/312
© SAP AG PLM220 3-7
SAP AG 2003
P
P2
P1P1
Basic dates in project definition
Project planning board
Planning forms (Project definition, project profile):1. Top Down (checks consistency)
2. Bottom Up (extrapolates and extends)
3. Free Planning (checks and does not calculate)
4. Strict Bottom Up (extrapolates, extends, and shortens)
Basic Dates WBS
PPS
P2P2P2
PPP
P1P1P1
In projects without networks, dates can be planned manually for the WBS elements (basic dates).
You can use the project planning board to plan basic dates for the WBS elements simply by dragging the
mouse. You can plan these dates in a table using structure planning.
Basic dates can be extrapolated from lower- to higher-level WBS elements, or passed on from higher- to
lower-level WBS elements. You can check the consistency of your scheduling data within the WBS
structure.
In the execution phase, you can enter actual dates by dragging them with the mouse. In the project
planning board or the information system, you can compare the actual dates with the planned basic dates.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 44/312
© SAP AG PLM220 3-8
SAP AG 2003
Scheduling
Earliest/latestdates relationship
Earliest/latestactivity dates
Requirements dateMaterial
EEAA C DDBB
Earliest/latest datesactivity element
Activity element
Activity element
Buffer - Forward scheduling- Backward scheduling- Scheduling fromcurrent date
- No scheduling
Scheduled dateScheduled dateMilestoneMilestone
Capacity requirementsfor each activity
Scheduled start/finishNetwork header
Each time a network is scheduled, the system carries out forward and backward scheduling and
determines floats and capacity requirements (if activated).
- Forward scheduling determines the earliest dates.
- Backward scheduling determines the latest dates.
Floats occur if the earliest dates differ from the latest dates.
The scheduling results are:
- The scheduled start and finish for the network header
- Earliest start and finish dates (earliest dates) and the latest start and finish dates (latest dates) for
the activities
- Earliest and latest dates for the relationships- Reduction levels used to schedule the network
- Float times (total and free float) for the activities
- Capacity requirements for activities
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 45/312
© SAP AG PLM220 3-9
SAP AG 2003
WBS / Overall Network Scheduling
Network scheduling
Scheduling of the overall network
WBS scheduling
You can schedule individual networks (network scheduling). You can schedule all networks that are
connected by means of relationships (scheduling of the overall network). You can also trigger network-scheduling starting from WBS elements (WBS scheduling).
The activity data, relationships between the activities, and date constraints form the basis for determining
dates (scheduling) automatically.
As of Release 4.6A, you can schedule maintenance orders from the Project System. In the Project
Scheduling and Overall Network Scheduling transactions you can specify whether networks are
scheduled together with the maintenance orders that have been assigned as sub-networks.
You can display an overview of the maintenance orders assigned to a project in the project planning
board.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 46/312
© SAP AG PLM220 3-10
SAP AG 2003
PP
P1P1 P2P2
303030 707070505050 808080
Basic dates in project definition
1020
30
40
5060
70
80
ExtrapolateExtrapolatedatesdates
WBS
Network 1 Network 2
Project planning board
101010202020 6060
404040
P1P1P2P2
PP
Transfer Transfer datesdates
Bottom-Up Scenario
In projects with networks, you can use network scheduling to automatically derive the dates of activities
and WBS elements.
Using the project planning board, you can select WBS elements, and schedule the activities assigned to
them. The scheduling parameters determine how the activities are scheduled.
Networks are always scheduled forwards and backwards. The scheduling type determines the direction
in which scheduling is carried out. The system determines the earliest dates of the activities using
forward scheduling, and the latest dates using backward scheduling.
The differences between the earliest and latest dates of an activity are referred to as floats. If these are
less than or equal to zero, the activity is classed as critical.
The dates of the assigned activities are summarized to give the scheduled dates of the WBS elements
(thin time bars in the project planning board).
The dates scheduled in the WBS structure can be copied to the basic dates of the WBS elements and
extrapolated up the project hierarchy.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 47/312
© SAP AG PLM220 3-11
SAP AG 2003
PP
P1P1 P2P2
303030 707070
404040
Basic dates in project definition
10
20
30
40
50
6070
80
Network 1 Network 2
WBS
Project planning board
202020808080
6060101010 505050
WBS determinesWBS determinesdatesdates
P1P1 P2P2
PP
Top-Down Scenario
In work breakdown structures with networks, you can plan basic dates for the WBS elements in order to
specify that a certain part of the project has to be completed within a fixed time period.
You can use the Top-Down scheduling scenario or use suitable scheduling parameters to stipulate that
activities be scheduled within these time constraints: Deselect the Network scheduling and Adjust basic
dates indicators.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 48/312
© SAP AG PLM220 3-12
SAP AG 2003
Scheduling Scenarios
Scheduling
Scheduling Scenario
Scheduling method for WBS structure
Sch. parameters for activities
Plan/basic Plan.fcst
WBS sched. profile
Top-Down Scenario
Sched. type
Scheduling method
Max.red.level
Reduction type
Start in the past
Latest staging
Adjust basic dates
Shift order
Automatic log
Autom. schedul.
Top-down Top-down
Next
WBS determines dates
Do not reduce
All activities of the order
Scheduling
Scheduling Scenario
Scheduling method for WBS structure
Sched. parameters for activities
Plan/basic Plan.fcst
Start in past
Bottom-Up Scenario
Next
Network determines dates
Do not reduce
All activities of the order
Bottom-up Bottom-up
Latest staging
Adjust basic dates
Shift order
Automatic log
Autom. schedul.
WBS sched. profile
Sched. type
Scheduling method
Max.red.level
Reduction type
Two predefinedscenarios or
free scheduling
As of Release 4.6, you can use predefined scheduling scenarios. The standard scheduling options are of
course still available. Depending on the transaction from which you trigger scheduling, you either usethe Parameters for WBS scheduling table or the Scheduling parameters for the network type table.
Caution: The scheduling result depends on the transaction from which you start scheduling.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 49/312
© SAP AG PLM220 3-13
SAP AG 2003
Customizing for Scheduling 1
1
2
34
Forward
Backward
Cap.requirements only:Today's date
Forw. Backw. Cap.re. Da.Sched.Bas.Time
Adjust dates
Scheduling control det. scheduling
Adjust basic dates, dep. reqs in activity dates
Scheduling type
Start in past
Backwards Automatic scheduling
Automatic log
Break scheduling
Shift order
Latest material
dates
Reduction
Reduction type
Maximum reduction level Do not reduce
All activities of order are reduced
Workforce planning
Rescheduling Redist. dist. work acc. to old distribution
Scheduling parameters
Scheduling types
The PSP should be spelled out. Could create and appendix of glossary of terms used in this course and
there spell out what PSP is.The indicators function as follows: Forward: Forward scheduling is carriedout first, followed by backward scheduling. Backward: Backward scheduling is carried out first,
followed by forward scheduling. Cap.requirements only: No scheduling is carried out. Instead, the start
and finish dates of the network header are copied to each activity. Today's date: Backward scheduling is
carried out first, followed by forward scheduling based on today's date. Basic dates with times: This
indicator is not relevant for networks.
Scheduling parameters are created for specific plants and network types. The scheduling parameters
determine scheduling, for example, in transactions network maintenance (CN22) and scheduling of the
overall network (CN24). The indicators function as follows: Adjust basic dates: Determines that the
scheduled dates are copied to the basic dates of the network header after a scheduling run. The settings
for secondary requirements do not have any impact in the network. Scheduling type: Determines the type
of scheduling, for example, forward first, then backward. Start in the past: Determines how long ago (indays) the start date can be. If it is more than the specified number of days, today scheduling is carried
out. Automatic scheduling: Scheduling is carried out when you save. Log automatic: If a log is
generated, it is displayed automatically. Break scheduling : The exact time at which a break is scheduled
(in the work center) is taken into account. Shift order: Determines how the system deals with partially
confirmed activities during scheduling (see below). Latest material dates: The requirements dates for a
material are determined based on the earliest or latest date. Reduction type: Either all activities or only
those along the critical path are reduced. Maximum reduction level: A reduction strategy can have up to
six levels. The highest level of reduction is specified here. Rescheduling: Determines how the system
deals with work allocated in Workforce planning after another scheduling run has been carried out.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 50/312
© SAP AG PLM220 3-14
SAP AG 2003
Customizing for Scheduling 2
WBS scheduling profile 130000000000 IDES scheduling backwards
Scheduling
Scheduling type
Start in past
Backwards
Scheduling form Network determines dates
Adjust basic dates
Latest material dates
Shift order
Sch. when saving
Automatic log
Reduction
MaxRedLevel
Reduction type
Parameters for WBS scheduling
The profile for WBS scheduling is used for scheduling in the project planning board or in the project
scheduling transaction (CJ29), for example.
The indicators function as follows: Scheduling type: Determines the type of scheduling, for example,
forward first, then backward. Start in the past: Determines how long ago (in days) the start date can be.
If it is more than the specified number of days, today scheduling is carried out. Scheduling form:
Specifies which object - network header or WBS element - is used as a basis for scheduling. Adjust basic
dates: Determines that the scheduled dates are copied to the basic dates of the WBS elements after a
scheduling run. Automatic log: If a log is generated, it is displayed automatically. Shift order:
Determines how the system deals with partially confirmed activities during scheduling (see below).
Schedule when saving: Scheduling is carried out when you save. Latest material dates: The requirements
dates for a material are determined based on the earliest or latest date. Maximum reduction level: A
reduction strategy can have up to six levels. The highest level of reduction is specified here. Reduction
type: Either all activities or only those along the critical path are reduced. The WBS scheduling profile is stored in the project definition control data. It can be copied as a default
value from the project profile. One (or neither) of the two scheduling scenarios is displayed by default in
the project profile.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 51/312
© SAP AG PLM220 3-15
SAP AG 2003
Scheduling: Duration
Internalprocessing
Planned delivery time or
Duration
Planned delivery time or
Duration
Externalprocessing
Duration Duration
Generalcosts activity
Relationship
Time interval
Fixed
As a percentage
Time interval
Fixed
As a percentage
Operating time
Calendar
Operating timeOperating time
Calendar
Work center
Operating time
Calendar
Operating timeOperating time
Calendar
Work center
Duration
Time unit
Duration
Time unit
When scheduling internally processed activities and general costs activities, the system uses the normal
duration you maintained in the activity. The duration can be calculated from the work planned, if youhave stored a formula for calculating the duration from internal processing in the work center.
For externally processed activities, scheduling usually uses the planned delivery time that has been
entered for the external activity for calculation. You can, however, also use the normal duration from the
internal processing screen of the external activity if you activate this explicitly in the control key of the
external activity.
Scheduling interprets the time interval for relationships as the minimum time interval. When calculating
the dates, scheduling can increase, but not reduce, the time interval.
You can maintain a work center in internally and externally processed activities and in relationships. The
following information is stored for scheduling in the work center:
Formulas for calculating the duration of activities
A factory calendar and the operating time for each workday
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 52/312
© SAP AG PLM220 3-16
SAP AG 2003
Control Key
Control key in operation
Control key
Indicators
Network - external processing
Schedule
Det. cap.req.
Costs act.:
Costing
Print time tick.
Confirmation Confirmation possible, but not required
External proc. Ext. processed activity
Service
Confirmation dr.
Sched. ext. act.
The control keys for activities are set in Customizing using transaction OPSU. The control key indicators
function as follows: Schedule: Activities and activity elements are scheduled. For activity elements, thedates for the activity are determined. Det. cap. req.: Capacity requirements are determined for activities
and activity elements. The capacity requirements are determined using the scheduling results. Therefore,
only set this indicator if you also set the scheduling indicator. Costs act.: This indicator specifies that
you use the control key for general costs activities. Costing: This determines that activities and activity
elements are taken into account in costing. Print time ticket: This determines whether time tickets can be
printed. Time tickets are only printed if the Print indicator is also selected. For more information, see the
online help. Confirmation: Determines whether activities and activity elements can be confirmed.
External proc.: Determines whether activities and activity elements are processed internally or
externally. Service: Determines whether services can be planned for activities and activity elements.
Only set this indicator if you select the External proc. indicator to allow external processing. Print conf.:
This determines whether completion confirmation slips can be printed. Confirmation slips are only
printed if the Print indicator is also selected. For more information, see the online help. Print:
Determines whether work papers such as time tickets, and completion confirmation slips can be printed.
For more information, see the online help. Sched.ext.proc.: Determines whether activities are to be
scheduled in line with the Planned delivery time or Normal duration.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 53/312
© SAP AG PLM220 3-17
SAP AG 2003
Relationships
AssemblyAssemblyProductionProduction
Time sequence:
WorkWorkschedulingscheduling
Eng/designEng/design
Eng./designEng./designPurch.Order
Purch.order Purch.order
TestTestrunrunTÜV
ApprovalApproval
Logical sequence:
FS relationship
SS relationship
FF relationship
SF relationship
Relationships determine the chronological sequence of the individual activities in a network (or standard
network). You can enter additional data (such as a time interval or reference to a particular factorycalendar) on the detail screen for each relationship.
The network graphic enables you to represent relationships in a time-dependent manner to display the
logical sequence. All relationships in the network graphic are displayed as FS relationships by default.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 54/312
© SAP AG PLM220 3-18
SAP AG 2003
Example of Scheduling
2020 6 D6 D
333 88833 88
3030 2 D2 D
444 55533 44
4040 3 D3 D
666 88855 77
1010 2 D2 D
111 22211 22
5050 3 D3 D
999 11111199 1111
50
40
30
20
10
1 2 3 4 5 6 7 8 9 10 11 12 Days
A network is always scheduled forward and backward. The scheduling type specifies whether forward
scheduling or backward scheduling is carried out first.
Forward scheduling calculates the earliest start and finish dates for the activities (earliest dates). A start
activity is a network activity that does not have a predecessor. The start date is the start date in the
network header or the start date determined from backward scheduling.
Backward scheduling calculates the latest start and finish dates for all the activities (latest dates). An
ending for final activity is a network activity that does not have a successor. The start date is the finish
date in the network header or the finish date determined from forward scheduling.
In the example above, the start dates are set to the beginning of the day (00:00) and the finish dates set to
the end of the day (24:00). If work centers are specified for the activities, the start and finish dates are
within the operating time of the corresponding work centers.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 55/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 56/312
© SAP AG PLM220 3-20
SAP AG 2003
Example of Floats
2020 6 D6 D
333 88833 88
3030 2 D2 D
444 55533 44
4040 3 D3 D
666 88855 77
1010 2 D2 D
111 22211 22
5050 3 D3 D
999 11111199 1111
50
40
30
20
10
Days1 2 3 4 5 6 7 8 9 10 11 12
This slide describes how total floats and free floats are calculated:
The total float of activity 40 can be calculated from the difference between the earliest and latest start
of an activity.
Day 6 (0:00) - Day 5 (0:00) = 1 day.
The free float of activity 40 can be calculated from the difference between the earliest start of the
successor (activity 50) and the earliest finish of the actual activity.
Day 9 (0:00) - Day 7 (0:00) = 1 day.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 57/312
© SAP AG PLM220 3-21
SAP AG 2003
Time Constraints
Set time constraints for activities
1. An exact start / finish ( =must)
2. The earliest value limit ( = not before)
3. The latest value limit ( = not after)
After
Before
Start Start Finish
After
Before
1 2
You can maintain constraints for the start and finish of activities and/or activity elements.
Constraints can be relevant for both the earliest and the latest dates.
You can maintain constraints for basic and forecast sets of dates.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 58/312
© SAP AG PLM220 3-22
SAP AG 2003
Scheduling of the Overall Network
SDorder
S = Start dateF = Finish date
(confirmed delivery date)
Item 1
Item 2
Item 3
S1
S2 F2S3 F3
F1
The confirmed delivery date of an item in the sales order corresponds to the finish date of the assigned
network. If the end of a network is postponed due to scheduling problems, the confirmed delivery date inthe sales order is automatically changed. You can, however, also fix a confirmed delivery date for the
item on the Schedule lines tab.
As of Release 4.0, the scheduling of the overall network for the sales order item can be started in the
sales order itself.
This function schedules the network assigned to the sales order item and all other networks that are
linked to this network via a relationship.
This function updates all of the items in the sales order that are connected to the overall network.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 59/312
© SAP AG PLM220 3-23
SAP AG 2003
Reductions
2 days
4 days
6 days
10 days
1.5 D.
3 days
4.5 days
10 days
Before:
After reductionof 25%:
After reductionof 25%:
Prerequisite:One strategy per activityMax. reduction level and type per network
Reduction can be used when the time range within which the activities are to be scheduled is not
sufficient to process all activities. You can use reduction to decrease the scheduled duration of externally processed activities.
Only those activities for which a reduction strategy has been entered are affected by reduction. At the
most, the system reduces up to the level of the reduction strategy that is entered in the network header.
During scheduling, the system determines one reduction strategy for each activity. For example: The
system calculates the earliest dates and determines reduction level 2 for an activity. This reduction level
is transferred to the latest dates.
Caution: Remember to be careful when using the reduction function, as the system does not know
whether the duration of an activity can actually be reduced. The system does not carry out plausibility
checks or check available capacities.
You can use reduction strategies to control how an activity's lead-time can be reduced in levels. You can
enter a reduction strategy in each activity.
You can define up to six reduction levels for each reduction strategy. For each reduction level you can
enter the percentage by which you want to reduce.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 60/312
© SAP AG PLM220 3-24
SAP AG 2003
Dates: Activity Elements
-1 D+1 D
ActivityActivity
ActivityActivityelementelement
+1 D -1 D
D u r a t i o nD u r a t i o n
Unlike activities, activity elements are not scheduled independently. The system calculates the dates for
activity elements with reference to the start or finish dates of the activity. You maintain a time intervalfor the start and for the finish. The dates of the activity element must always lie completely within the
duration of the higher-level activity.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 61/312
© SAP AG PLM220 3-25
SAP AG 2003
Requirements Date: Material
Earliest/latest dates either from WBS scheduling parameters orScheduling parameters for network type
Component 1Component 1Time interval:Time interval: +2 days+2 days
Ref. date:Ref. date: StartStart
Component 2Component 2Time interval:Time interval: --1 day1 day
Ref. date:Ref. date: FinishFinish
= Requirementsdate
+ 2D
- 1D
ActivityActivity
Replenishment
lead time
Replenishmentlead time
Latest datesLatest dates
Earliest datesEarliest dates
The system calculates the requirements date for components with reference to the start or finish date of
the activity. You can use the Scheduling parameters for the network type or the Parameters for WBS scheduling to control whether the earliest or latest start date is used as the requirements date. The
transaction used to trigger the scheduling determines which of the two tables is used. If you schedule
within the network or the overall network, the Scheduling parameters for the network type apply. If you
schedule in the project planning board or using structure planning, the Parameters for WBS scheduling
apply.
If the requirements date is before the finish date of the activity, you can store a corresponding time
interval.
You can also set a requirements date for a material manually.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 62/312
© SAP AG PLM220 3-26
SAP AG 2003
Dates: Milestone
ActivityActivity
Basic data Functions Admin.
Use
Activity Assembly
Use
Milestone functions
Release stop ind.
Trend analysis
Progress analysis
Sales document date
Dates
Fixed date
Actual date
Scheduled date
Offset to activity
Latest dates
Offset to fin.
Time interval
Billing plan
InvoicePercentg
Progress analysis
Completion
Final billing
10 day
This slide describes milestones that are assigned to activities. The planned date is either entered
manually or references the activity dates. If the date references the activity dates, you must decidewhether it is to refer to the earliest or latest dates and to the start or the end of the activity. You can also
enter a positive or negative time interval for this date.
You can also assign milestones to WBS elements. As of Release 4.6, the planned dates of a milestone
can refer to the basic start or finish date of a WBS element.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 63/312
© SAP AG PLM220 3-27
SAP AG 2003
Work breakdownstructures
Work breakdownstructures
Network,network activity
Network,network activity
Apr 7.
Actual WBSdates Activityconfirmation
Apr 7.
Actual Dates
To monitor the dates for a project, compare the basic dates with the actual dates or the forecast dates.
Actual dates can be set manually for WBS elements. If you are using network activities, confirming
activities sets the actual dates. If activities are assigned to a WBS element, the actual dates of the
activities are proposed to the WBS element as provisional dates, which can be transferred to the actual
dates of the WBS element, if necessary.
Caution: Actual dates are usually updated to an activity during an activity confirmation. You can
suppress this update if necessary. To do this, select the No date update indicator during confirmation.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 64/312
© SAP AG PLM220 3-28
SAP AG 2003
Actual start
Actual finish
CONF CONF
Actual start
Provisional actual
finish
CONF
CONFCONF CONF
AS+AF
AS+AF
Actual finish
RELDRELD
Status:Released or partiallyreleased
Status:Released or partiallyreleased
WBS WBS with activities
Actual WBS Dates
Legend:
AS = Actual start AF = Actual finish
CONF = Final confirmation REL = Released
For WBS elements without assigned activities:
You can always maintain the actual start if the WBS element has the status Released or Partially
released .
You can only maintain the actual finish if all lower-level WBS elements have an actual finish date.
The following also applies to WBS elements to which activities are assigned:
You can only maintain the actual start if the assigned activity has the status or Partially released or
Released . You can only maintain the actual finish date if all the lower-level WBS elements also have an actual
finish date and all the activities for the WBS element have the status Finally confirmed .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 65/312
© SAP AG PLM220 3-29
SAP AG 2003
Scheduled dates
10
20 20
Final confirmation 10
30
2010 40
30
2010 40
Partial confirmation 20(shift order)
10
AS PF
10
20
TimeTime TimeTime TimeTime
AS = Actual startPF = Provisional finish
Actual Dates of Activities
30
10 4020
Actual dates are entered in networks by confirming activities. This can be carried out using individual or
collective confirmations, or the time sheet, for example.
Once an activity has been finally confirmed, the start and finish of the earliest and latest dates match the
actual start and actual finish dates.
Partial confirmations affect the scheduling result for the earliest date in accordance with the Shift order
indicator.
The Shift order indicator is not set: The actual start date and forecast duration of the partial
confirmation are taken into account when the earliest date is calculated.
The Shift order indicator is set: Neither the actual start date nor the forecast duration of the partial
confirmation is taken into account when the earliest date is calculated.
To display an overview of your planned dates at a certain point in time (baseline), use either projectversions or forecast dates.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 66/312
© SAP AG PLM220 3-30
SAP AG 2003
You are now able to:
Plan dates for activities and WBS elements usingthe project planning board
Set the relevant tables in Customizing
Scheduling: Unit Summary
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 67/312
© SAP AG PLM220 3-31
Exercises
Unit: Scheduling
Topic: Scheduling
• Time planning with predefined scenarios
• Relationships and restrictions
• Effects of actual dates on time scheduling
In the following section you will work through three sets of exercises. Inthe first set, you will use the project planning board for time scheduling
based on predefined scheduling scenarios. The next section will
familiarize you with more scheduling details. In the last section, you willinvestigate how actual dates affect time scheduling.
1-1 Call the project planning board.
1-1-1 Edit your project T-100## in the project planning board. Use the Elevators/Turbines planning board profile.
1-1-2 Optimize the project display to show all activities completely.
1-1-3 Plan dates for your project using the predefined bottom-up scenario.
First check the time scheduling settings.
Set the scheduling scenario to Bottom-up scenario (pre-defined) if necessary.
Plan the dates for the entire project.
The bottom-up scheduling scenario is set to firstly determine all
activity dates, and then to copy the earliest and latest dates to the
assigned WBS elements. Finally, dates are extrapolated for upper-level WBS elements within the hierarchy.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 68/312
© SAP AG PLM220 3-32
1-1-4 Check the floats for your project. Display both the earliest and the latest dates.
Scheduling always calculates the dates of activities forwards and
backwards. Each activity (and activity element), therefore, has twotime bars. Different colors (usually blue and red) are used to
distinguish between activities in the planning board that still haveor no longer have time floats.
1-1-5 Change the duration of activity 4000 Production of running gear, bearing,
valves and look at the effect this has on scheduling.
Reduce the duration of the activity to 30 days.
Although the system adjusts the time bars of activity 4000 in thegraphic, the overall project dates are no longer up-to-date. You
need to run scheduling again. Note the changes to activities 3000
and 3100.
The reduced duration of the activity affects the entire network.
Question A: How are activities 3000 and 3100 affected? The answer is providedat the end of the exercises for this unit.
1-1-6 Save your scheduling data.
Do not save any user-specific settings.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 69/312
© SAP AG PLM220 3-33
1-2 Take a look at the scheduling details. Once again, use the project planning board for
this purpose. Call your project.
1-2-1 Create two more activities in activity 5010 Planning of instrumentation. The
activities will be linked to each other at a later stage.
1-2-2 Enter the appropriate data for the two new activities.
Enter the following information on the detail screen for activity 5020:
Field Name Values
Long text Detailed planning for
instruments
Work center 2000
Work 10 hours
Normal duration 3 days
If the system asks you to enter a business area, choose business area 2000.
The detail screen for activity 5030 appears. Enter the following data:
Field Name Values
Text Corrections for instruments
Work center 2000
Work 10 hours
Normal duration 72 hours
1-2-3 Schedule your project.
Question B: How does scheduling affect the WBS elements in the project?
1-2-4 Connect activities 5010, 5020, and 5030 using relationships. Use FS
relationships.
1-2-5 Schedule your project. Note how the time bars for activities 5010, 5020, and 5030 change.
1-2-6 The three activities are not yet integrated into the rest of the network. In thegraphic, create an FS relationship between activity 1000 and activity 5010.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 70/312
© SAP AG PLM220 3-34
1-2-7 Schedule your project.
1-2-8 Using the table, create an FS relationship between activity 5030 and activity
3100.
1-2-9 Schedule your project.
1-2-10 Check the floats in your project. To do this, select the Dates tab on the detailscreen for activity 5010 Planning of instrumentation.
What is the total float of the activity? _____________
Display the total float directly in the diagram area. Configure the system in such
a way that only those activities with a negative total float are highlighted ascritical activities.
1-2-11 Activity 5020 Detailed planning for instruments is not to start before a certaindate. Set a date constraint on the Dates detail screen for the activity.
Set a date constraint for the start date.
Enter the earliest start date plus one week as the start date.
1-2-12 Schedule your project.
What is the free float of activity 5010? _____________
Question C: Why does activity 5010 have a free float?
1-2-13 Save your scheduling data.
Do not save any user-specific settings.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 71/312
© SAP AG PLM220 3-35
1-3 Up to now, you have planned dates but have not yet begun to enter actual dates.
However, the actual dates may affect your planned dates. Take a look at how actual
dates affect planned dates in the project planning board.
1-3-1 Before you start to enter actual dates, transfer the dates planned previously
(basic dates) to the set of dates for alternative time scheduling (forecast dates).
Show the forecast dates, compare them with the basic dates, and then hide them
again.
Forecast dates can be determined via scheduling in the same way as basic dates. These dates are simply alternative dates for time
scheduling and are used in the course to freeze time scheduling at a
certain point in time. This allows comparison with changed timescheduling (basic dates) at a later stage.
1-3-2 Before you can enter actual data, you have to release activities or WBSelements. Release the WBS element T-100##.1 Engineering and Design.
The status is passed onto lower-level activities to allow you to continue entering
actual activity data.
1-3-3 Enter a partial confirmation for activity 1000 Engineering of
drawing/calculation/design. Display both the actual dates and the basic dates in
the diagram area.
Enter the following data in the confirmation dialog window:
Field Name Values
Completed Deselect
Final conf. Deselect
Processing % 20 %
Actual start Copy the earliest start date
Actual finish Actual start plus 2 working
daysForecast duration 14 days
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 72/312
© SAP AG PLM220 3-36
1-3-4 Schedule your project.
Note how the basic dates for activity 1000 change.
The system uses the confirmation dates to determine a provisional finish for the
activity being processed. The activity takes longer. As a result, the planneddates of the following activities in the network move.
1-3-5 You can use the Shift order indicator to prevent the actual dates from affecting
scheduling. Activate this indicator and reschedule.
Except for the Shift order indicator, the settings for the predefined profile IDES scheduling forward correspond to the bottom-up scenario.
Reschedule your project.
Notice how the time bar of activity 1000 becomes shorter and the dates of all
following activities are adjusted.
1-3-6 Compare the basic dates with the forecast dates.
Hide the forecast and actual dates again.
1-3-7 Select the bottom-up scheduling scenario again.
1-3-8 Save the changes to your time scheduling settings.
Do not save any user-specific settings.
Answer to question A (How are activities 3000 and 3100 affected?):
Previously, activity 3000 was critical (it had negative floats). After scheduling,
it has positive floats. Activity 3100 behaves in a completely different way. Inthe network structure graphic, you can see that the activities lie in two different,
parallel paths. Before scheduling, the first path (with activity 3000) is the
critical path in the network. After scheduling, the other path (with activity
3100) represents the critical path.
Answer to question B (How does scheduling affect the WBS elements in the project?)
Bottom-up is still chosen as the scheduling scenario. The activity dates aretransferred to the higher-level WBS elements. In the example above, the date of
the WBS element Planning of instrumentation is adjusted. Note the different
durations (3 days or 72 hours) of the two new activities.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 73/312
© SAP AG PLM220 3-37
Answer to question C (Why does activity 5010 have a free float?)
The free float is the difference between the earliest finish of an activity and the
earliest start of its successor. The earliest start of the successor was only set to a
later date by restricting the start date of the successor (5020, Cannot start before). Free floats also appear for parallel activities that have the same
successor. In this case, the longer activity determines the earliest start date ofthe successor and the shorter activity has a free float.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 74/312
© SAP AG PLM220 3-38
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 75/312
© SAP AG PLM220 3-39
Solutions
Unit: Scheduling
Topic: Scheduling
• Time planning with predefined scenarios
• Relationships and restrictions
• Effects of actual dates on time scheduling
In the following section you will work through three sets of exercises. Inthe first set, you will use the project planning board for time scheduling
based on predefined scheduling scenarios. The next section will
familiarize you with more scheduling details. In the last section, you willinvestigate how actual dates affect time scheduling.
1-1 Call the project planning board.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project (Double-click the transaction to select it)
1-1-1 Edit your project T-100## in the project planning board. Use the
Elevators/Turbines planning board profile.
Enter your project in the Project def. field, select W. activities, enter the
corresponding planning board profile, and select Open project.
1-1-2 Optimize the project display to show all activities completely.
Use Zoom in on graphic to choose a suitable zoom factor.
Optimize the graphic display using the Adapt graphic area icon.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 76/312
© SAP AG PLM220 3-40
1-1-3 Plan dates for your project using the predefined bottom-up scenario.
First check the time scheduling settings.
Select Options.
Set the scheduling scenario to Bottom-up scenario (pre-defined).
Confirm your entries by selecting Copy.
Plan the dates for the entire project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
The bottom-up scheduling scenario is set to firstly determine all
activity dates, and then to copy the earliest and latest dates to the
assigned WBS elements. Finally, dates are extrapolated for upper-level WBS elements within the hierarchy.
1-1-4 Check the floats for your project. Display both the earliest and the latest
dates.
Select Set of dates / View.
Activate the Latest dates indicator.
Select Copy to confirm your entries.
Scheduling always calculates the dates of activities forwards and
backwards. Each activity (and activity element), therefore, has two
time bars. Different colors (usually blue and red) are used to
distinguish between activities in the planning board that still haveor no longer have time floats.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 77/312
© SAP AG PLM220 3-41
1-1-5 Change the duration of activity 4000 Production of running gear, bearing,
valves and look at the effect this has on scheduling.
Double-click the row containing activity 4000 to call the activity detail screen.
Reduce the duration of the activity to 30 days. Enter this duration in the Normalduration field on the Internal tab.
Select Back to confirm your entries.
Although the system adjusts the time bars of activity 4000 in the
graphic, the overall project dates are no longer up-to-date. Youneed to run scheduling again. Note the changes to activities 3000
and 3100.
Select all the objects by choosing Select all.
Start scheduling by selecting the appropriate icon.
The extended duration of the activity affects the entire network.
Question A: How are activities 3000 and 3100 affected? The answer is provided
at the end of the exercises for this unit.
1-1-6 Save your scheduling data.
Choose Save.
Do not save any user-specific settings.
1-2 Take a look at the scheduling details. Once again, use the project planning board for
this purpose. Call your project.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project
(Double-click the transaction to select it)
Enter your project in the Project def. field, select W. activities, and choose Open
project.
As before, optimize the display of your project by selecting Zoom in on graphic andAdapt graphic area.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 78/312
© SAP AG PLM220 3-42
1-2-1 Create two more activities in activity 5010 Planning of instrumentation. The
activities will be linked to each other at a later stage.
Select activity 5010 Planning of instrumentation.
Select Create.
The templates area is shown on the left of the project planning board.
Double-click the Activity (Internal processing) object in the templates area.
The system creates an internal processing activity with default values. The
assignment to the WBS element is copied by the selected activity. The detailsettings of the activity will be defined later.
Create the second activity.
Double-click the Activity (Internal processing) object again in the templates
area.
Hide the templates area.
Select Open/close left-hand window.
1-2-2 Enter the appropriate data for the two new activities.
To select both activities, keep the Control key pressed.
Call the detail screen for the activities.
Select Detailed information for object.
Enter the following information on the detail screen for activity 5020:
Field Name Values
Long text Detailed planning forinstruments
Work center 2000
Work 10 hours
Normal duration 3 days
Select Next.
If the system asks you to enter a business area, choose business area 2000.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 79/312
© SAP AG PLM220 3-43
The detail screen for activity 5030 appears. Enter the following data:
Field Name Values
Long text Corrections for instruments
Work center 2000
Work 10 hours
Normal duration 72 hours
To exit the transaction, select Back.
1-2-3 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
Question B: How does scheduling affect the WBS elements in the project?
1-2-4 Connect activities 5010, 5020, and 5030 using relationships. Use FSrelationships.
Select the activities by keeping the Control key pressed.
Select Connect selected activities.
The system creates FS relationships between the activities. The order of the
relationships is determined by the order in which the activities are displayed inthe planning board (from top to bottom).
1-2-5 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
Note how the time bars for activities 5010, 5020, and 5030 change.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 80/312
© SAP AG PLM220 3-44
1-2-6 The three activities are not yet integrated into the rest of the network. In the
graphic, create an FS relationship between activity 1000 and activity 5010.
Activate the connect mode.
Select Switch connect mode on/off, or click anywhere on a blank area of the
project planning board.
The cursor is displayed as a pencil in the graphic area. Create the FS
relationship.
Keep the mouse button pressed, and drag the cursor from the right half of
activity 1000 to the left half of activity 5010. Release the mouse button.
Deactivate connect mode.
Select Switch connect mode on/off.
1-2-7 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
1-2-8 Using the table, create an FS relationship between activity 5030 and activity3100.
Select activity 5030.
Select Edit relationships (tabular).
A list of the activity relationships appears.
Create an FS relationship for activity 3100 Material procurement plant
components.
Select the Successors tab.
Select activity 3100 in the Activity Selection section.
Select Create rel.
Confirm your entries by selecting Continue.
1-2-9 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 81/312
© SAP AG PLM220 3-45
1-2-10 Check the floats in your project. To do this, select the Dates tab on the detail
screen for activity 5010 Planning of instrumentation.
Double-click either the activity time bar or the activity number.
Select Dates.
What is the total float of the activity? _____________
Select Back to exit the detail screen.
Display the total float directly in the diagram area. Configure the system in such
a way that only those activities with a negative total float are highlighted ascritical activities.
Select Options.
Choose Planning board in the tree structure and then choose the Diagram
area tab.
Select the Show total float indicator.
Enter the value 1- in the Critical from field (note the sign).
Confirm your entries by selecting Copy.
1-2-11 Activity 5020 Detailed planning for instruments is not to start before a certaindate. Set a date constraint on the Dates detail screen for the activity.
Double-click either the activity time bar or the activity number.
Select the Dates tab.Set a date constraint for the start date.
Choose the Cannot start before value in the Start field.
Enter the earliest start date plus one week as the start date.
Select Back to confirm your entries.
1-2-12 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
What is the free float of activity 5010? _____________
Question C: Why does activity 5010 have a free float?
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 82/312
© SAP AG PLM220 3-46
1-2-13 Save your scheduling data.
Choose Save.
Do not save any user-specific settings.
1-3 Up to now, you have planned dates but have not yet begun to enter actual dates.
However, the actual dates may affect your planned dates. Take a look at how actual
dates affect planned dates in the project planning board.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project (Double-click the transaction to select it)
Enter your project in the Project def. field, select W. activities and choose Open
project.
As before, optimize the display of your project by selecting Zoom in on graphic and
Adapt graphic area.
1-3-1 Before you start to enter actual dates, transfer the dates planned previously(basic dates) to the set of dates for alternative time scheduling (forecast dates).
Select all objects using Select all.
In the menu, choose Edit Reconcile dates Transfer basic date to
forecast.
If the Schedule WBS elements dialog box appears, select No.
Show the forecast dates, compare them with the basic dates, and then hide themagain.
Select Set of dates / View.
In the dialog box, select Forecast dates and confirm your entries by choosing
Confirm.
Use the same procedure to hide the forecast dates again.
Forecast dates can be determined via scheduling in the same way as
basic dates. These dates are simply alternative dates for timescheduling and are used in the course to freeze time scheduling at acertain point in time. This allows comparison with changed time
scheduling (basic dates) at a later stage.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 83/312
© SAP AG PLM220 3-47
1-3-2 Before you can enter actual data, you have to release activities or WBS
elements. Release the WBS element T-100##.1 Engineering and Design.
Select the WBS element T-100##.1 Engineering and Design.
Choose Edit Status Release.
The status is passed onto lower-level activities to allow you to continue enteringactual activity data.
1-3-3 Enter a partial confirmation for activity 1000 Engineering ofdrawing/calculation/design. Display both the actual dates and the basic dates inthe diagram area.
Select activity 1000 Engineering of drawing/calculation/design.
Click Confirm activity.
Enter the following data in the confirmation dialog window:
Field Name Values
Completed Deselect
Final conf. Deselect
Processing % 20 %
Actual start Copy the earliest start date
Actual finish Actual start plus 2 working
days
Forecast duration 14 days
Confirm the confirmation by selecting Enter and choose Back to exit.
Select Set of dates / View.
In the dialog box, select Actual dates and choose Copy to confirm your
entries.
The corresponding time bar is then displayed in the diagram area.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 84/312
© SAP AG PLM220 3-48
1-3-4 Schedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
Note how the basic dates for activity 1000 change.
The system uses the confirmation dates to determine a provisional finish for the
activity being processed. The activity takes longer. As a result, the planned
dates of the following activities in the network move.
1-3-5 You can use the Shift order indicator to prevent the actual dates from affectingscheduling. Activate this indicator and reschedule.
Select Options.
All settings in the predefined bottom up scheduling scenario are fixed. In
particular, you cannot change the Shift order indicator.
Change the scheduling scenario to Free scheduling .
Except for the Shift order indicator, the settings for the predefined profile IDES
scheduling forward correspond to the bottom-up scenario.
Select the Shift order indicator.
Select Copy to confirm your entries.
Reschedule your project.
Select all objects using Select all.
Start scheduling by selecting the appropriate icon.
Notice how the time bar of activity 1000 becomes shorter and the dates of allfollowing activities are adjusted.
1-3-6 Compare the basic dates with the forecast dates.
Select Set of dates/View.
In the dialog box, select Forecast dates and choose Confirm to confirm your
entries.
Hide the forecast and actual dates again.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 85/312
© SAP AG PLM220 3-49
1-3-7 Select the bottom-up scheduling scenario again.
Select Options.
Change the scheduling scenario to bottom-up.
Select Copy to confirm your entries.
1-3-8 Save the changes to your time scheduling settings.
Choose Save.
Do not save any user-specific settings.
Answer to question A (How are activities 3000 and 3100 affected?):
Previously, activity 3000 was critical (it had negative floats). After scheduling,it has positive floats. Activity 3100 behaves in a completely different way. In
the network structure graphic, you can see that the activities lie in two different, parallel paths. Before scheduling, the first path (with activity 3000) is the
critical path in the network. After scheduling, the other path (with activity3100) represents the critical path.
Answer to question B (How does scheduling affect the WBS elements in the
project?)
Bottom-up is still chosen as the scheduling scenario. The activity dates aretransferred to the higher-level WBS elements. In the example above, the date of
the WBS element Planning of instrumentation is adjusted. Note the different
durations (3 days or 72 hours) of the two new activities.
Answer to question C (Why does activity 5010 have a free float?)
The free float is the difference between the earliest finish of an activity and theearliest start of its successor. The earliest start of the successor was only set to a
later date by restricting the start date of the successor (5020, Cannot start
before). Free floats also appear for parallel activities that have the samesuccessor. In this case, the longer activity determines the earliest start date of
the successor and the shorter activity has a free float.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 86/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 87/312
© SAP AG PLM220 4-1
SAP AG 2003
Capacities: Contents
Planning internal processing
Determining and evaluating capacity requirements
Workforce planning and capacity leveling
Confirmation
Cross-Application Time Sheet (CATS)
Setting the relevant tables in Customizing
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 88/312
© SAP AG PLM220 4-2
SAP AG 2003
Plan and confirm internal services via internal
processing activities
Analyze capacity requirements
Distribute work to personnel resources
At the conclusion of this unit, you will be able to:
Capacities: Unit Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 89/312
© SAP AG PLM220 4-3
SAP AG 2003
Capacities: Overview
Course
Overview
Project
Structures
Scheduling
Capacities
External
Services
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 90/312
© SAP AG PLM220 4-4
SAP AG 2003
A large proportion of the services for the turbinewill be performed in your own company. You may,
however, not have enough available capacity. Plan
the services and analyze the capacity
requirements.
Capacities: Business Scenario
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 91/312
© SAP AG PLM220 4-5
SAP AG 2003
Capacities: Overview
Internal activity
100 H Work
Work center
ProgressStructure
Bottlenecks
/Comparison
Persons
External
assignment1
Machines
Analyses
The planning of internal activities influences capacity planning and other objects and aspects in Project
System to a large degree. The degree to which it influences other elements is depicted by the width ofthe lines in the above slide.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 92/312
© SAP AG PLM220 4-6
SAP AG 2003
Life Cycle Internal Activity
Confir-mation
Capacityrequirements,planned dates,planned costs
Activities
Workforceplanning
Capacity evaluation
Capacityleveling
Capacity loadreduction,
actual dates,actual costs
The slide shows all the events in the life cycle of an internal processing activity. You may be able to
leave out some of these events, however. Capacity leveling or workforce planning may not be necessary,for example, if the time and effort involved outweigh the benefits.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 93/312
© SAP AG PLM220 4-7
SAP AG 2003
Project Edit Goto Details Settings View Extras System Help
Project: Change
E O E Ident if icat ion Work Pln Proj . cost p lan
Work Pln Name
Universal work center
Capacity Overview
Project: Turbine 2000
Jan 99 March 99 Apr 99Feb 99 May 99 June 99 July 99
Jan 99 March 99 Apr 99Feb 99 May 99 June 99 July 99
15000
20000
30000
20000
50000
10000
20000
5000
Internal Processing in the Project Planning Board
1. Create
activity
2. Generate
capacity
requirements
4. Release
activity
3. Evaluate
capacity
requirements
5. Confirm
activity
You can use the project planning board to carry out all steps involved in processing internal activities.
The slide shows the processing basics. You can also call Workforce planning and capacity leveling
directly from the planning board.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 94/312
© SAP AG PLM220 4-8
SAP AG 2003
Internal Processing Activity Details
General Data
External AllocationsDates Long text User fieldsInternal
Scheduling
System status
WBS element
Work center
Work
Calculation key
Activity type
Priority
Usage
Std text key
Business proc.
Executn factor
Quantity Percent
DistKey Int proc.
Project sum.
Subntwk exists
Normal duration
Min. duration
Factory cal.ID
Red. strategy
CRTD
Flexible
Control key
SAP020
DAY
h
The slide highlights the key settings for the capacity requirements of internally processed activities.
You use the Control key, amongst other things, to establish whether the activity is relevant for
determining capacity requirements.
The value in the Work field usually determines the planned capacity requirements.
The Distribution key field determines how the capacity requirements will be distributed across the
duration of the activity. If this field is blank, the distribution key is determined from the work center.
If the work center field is also blank, the work is evenly distributed to the latest dates.
The system can only determine capacity requirements if you have entered a work center. The
requirements are generated at this work center and the work center provides the available capacity.
The activity type is determined from the work center (and its assignment to a cost center). You need
the activity type to cost the activity.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 95/312
© SAP AG PLM220 4-9
SAP AG 2003
Work Center, Capacities Details
Proj.reqmts int.prcg
Capacit ies SchedulingBasic data
Person
Costing
Capacity cat.
Pool capacity
002
Capacity
Formula cond.int proc.
Int. dist. key
Formula Formula Formula c
Planner grp
Pool capacity
General data
Group
Stan. av. cap.
Available
Planning details
Factory calendar ID
Active version
Base unit of meas.
Germany standard
Hours
01
Start
Finish
Lnth of breaks
Usage time
Capacity utiliz.
No. of indiv. cap.
Capacity
H
Relevant to finite scheduling
Can be used by several operations
Overload
Long-term planning
SAP030
10
This slide highlights the key settings for the capacity view of a work center.
On the Capacities tab, you can specify the individual capacity categories (labor, machine, for
example) of a work center. Each capacity category has its own available capacity.
The formula for calculating the internal processing requirement defines how the capacity requirements
will be determined from the activity details. Usually, only the Work field from the activity is used.
The distribution key of the work center is only used by the system if no distribution key is specified in
the activity.
Features of the header screen for the capacity category:
The standard available capacity of the capacity category is defined. This standard available capacity
can be refined using additional intervals.
You use the Relevant to finite scheduling indicator to determine whether the capacity category will beconsidered in an availability check. You can perform this availability check from the network, or
during capacity leveling.
The overload specifies the percentage of capacity requirements that the available capacity may exceed
without the availability check affecting activity scheduling.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 96/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 97/312
© SAP AG PLM220 4-11
SAP AG 2003
Capacity Requirements
Formula: For example, capacity
requirements = work
Distribution key: e.g. Equal distributionLatest dates
Function: Duration Work
25% 15%
50% 30%
75% 60%
100% 100%
Strategy: Continuous/discrete
Earliest/latest dates
Calendar
Distribution key: Function + strategy
Discrete:
Continuous:
Duration / %
W o r k %
Scheduling determines the capacity requirements for the required output.
The system determines the capacity requirements using the formula in the work center and the work
from the network activity.
Capacity requirements can also be determined for externally processed activities.
To do so, you must set the scheduling and capacity planning indicators in the control key. The capacity
requirements are determined at the same time as internally processed activities.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 98/312
© SAP AG PLM220 4-12
SAP AG 2003
Capacity Analysis in the Structure InformationSystem
Work center 2000
Work center 2100
Plant Work ctr Typ. Network Op. CapaReq Actual work Forecast work RemCapaReq
Plant Work ctr Typ. Network Op. CapaReq Actual work Forecast work RemCapaReq
You can evaluate capacity requirements directly in the PS Information System. Use the individual
overview of capacity requirements from the Structures Information System. The overview is structuredin exactly the same way as the Structures Information System. You can use display variants, for
example, to determine which information is displayed.
You may also use the Capacities individual overview, which was developed for the SAP R/3 Enterprise
Release. This is designed for occasional users, and is easy to use. However the information it provides is
not as detailed as the extended individual overview.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 99/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 100/312
© SAP AG PLM220 4-14
SAP AG 2003
Extended Capacity Evaluation
Number of entries: 7 PersNo inidividual capacity
PlantWork center Capacity category
FrankfurtElectrical specs.Person
Entries CapReqmtsDbt CapReqmts A ctual CapReqmts Rmdr AvailCap Rem. avail. cap.
Total
Number of entries: 7 Work center type per iod
Entries Pggd reqts Act. WCe NorDur Target proc. cap. req. Act. proc. cap. req. Rem. processing
Total DaysDay
DaysDays
DaysDays
Days
Days
Caution: In the extended capacity evaluation for projects in the R/3 standard system, you cannot select
actual capacity requirements. The selection profile SAPPS_S020 has been changed for the course so thatyou can evaluate the actual capacity requirements. This selection profile is used in the overall profile
SAPPS_G020. All profiles for extended capacity evaluation are set up in Customizing for Capacity
Planning.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 101/312
© SAP AG PLM220 4-15
SAP AG 2003
Customizing the Extended Capacity Evaluation
Overall profile (extended evaluation)Overall profile (extended evaluation)
Control profile
Selection profile
List profile
Evaluation profile
Time profile
Period profile
Which data will be evaluated?
Comparison or evaluation of data?
What period will be evaluated?
Which requirements do you want to display?
Which period do you want to split?
Which fields do you want to display?
The overall profile contains all settings required for extended evaluations and for capacity leveling. You
can set the overall profile and all associated sub-profiles in Customizing for capacity planning.
All of the Customizing activities required are discussed in course SCM360 (Capacity Planning).
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 102/312
© SAP AG PLM220 4-16
SAP AG 2003
Project planning board
n Click to insert text ??
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxx XXxxxx XX
Capacity planning tablePlanning table (graph.)
Workforce
planning
Project 1234Activity
Activity
DurationPerson
Person
Period
Duration
Person
Person
PSPS
PPPP
PMPM
With / without
filter
Capacity Leveling
There are different capacity leveling options for networks / activities:
You can use the project planning board to display the capacity load on the work centers involved. This
is displayed as bars on the time axis. Red sections of the bars indicate that the work center is
overloaded for a specific time period. You can select such a work center and display a capacity load
curve, with capacity requirements as well as available capacity. You can use the project planning
board to level capacities - for example, by changing the work center or by moving the activity in the
specified time.
For capacity leveling, you can use the capacity planning table, either in graphical or in tabular form.
Each of them has at least two sections, one for the available capacities of the work centers by period
and the other for the capacity requirements by the orders or networks.
Workforce planning is an interface that you can use to distribute given work to persons allocated to the
work center.
There are different views for capacity planning and for workforce planning:
The work center view selects all capacity requirements on the specified work centers for a given time.
The project view selects all activities with work centers of a specified project.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 103/312
© SAP AG PLM220 4-17
SAP AG 2003
Workforce Planning
Period (day, week, ...)
Period (day, week, ...)
Project
view
Work
center
view
Project: T-200##
Work center: 2700
Duration of activity
Duration of activity
Duration of activity
Duration of activity
Network 901939
Activity 1200
Network 901939
Activity 1500
Person 1
Person 2
Person 1
Person 2
Network 901939
Activity 1200
Network 901940
Activity 1000
Network 901939
Activity 1200
Person 3
Person 4
Workforce planning assigns persons to activities.
Characteristics of workforce planning:
Two different views: The work center view and the project view
Persons can be assigned to activities quickly and easily
Data display:
- Availability of the person (read from HR)
- Total capacity load on the person
- Activity data
You can assign persons who a) are assigned to the work center of the activity, b) belong to the project
team or c) only exist in HR.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 104/312
© SAP AG PLM220 4-18
SAP AG 2003
Reporting in Workforce Planning
Project Selection Work center selection Personnel resource selection
Select. personnel resource
Person
Position
Organizational unit
With pers. resource avail.
Quality Assurance
Activities Allocations Project WBS element
Project definition: E-15001
Ex. Activity/personnel resource Tot. work Dist. UoM
H
H
H
H
H
Specification
Technical acceptance
Gaspard Coriolis
Richard Feynman
This evaluation enables you to display work scheduling for projects, work centers, or human resources.
When you call workforce planning in the project view, you use project definitions, WBS elements or
networks to make a selection. The project view displays all activities that are assigned to the selected
networks or WBS elements.
When you access the work center view, you make your selection using work centers, plants, or human
resources (here: person or position).
Selection using personnel resources also enables you to evaluate according to organizational units.
The evaluation is based on the ABAP List Viewer (ALV). The standard functions of this tool allow you
to use the evaluation as a basis for printing workforce planning, sending it to other users, or storing it in
a local file.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 105/312
© SAP AG PLM220 4-19
SAP AG 2003
Project team
Project team:Organizational units
and/or positionsand/or persons
Processing options:
• Project Builder
• Project planning board
• In WBS element detail screen
• Workforce planning in the project
view
• HR organizational management
Inheritance:
As of Release 4.6, you can create a project team for a WBS element. Project teams consist of the
employees that you can involve in workforce planning. The employees are assigned directly, using theHR organizational units or positions.
If a WBS element does not have its own project team, the project team of the superior WBS element
can be used during workforce planning.
If a WBS element does have its own project team, the project team of the superior WBS element cannot
be used during workforce planning.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 106/312
© SAP AG PLM220 4-20
SAP AG 2003
Work Center: Assigning Persons
LO - Work center
HR organizational
unit
HR work center
Capacity category
Person
Person and position
Person and position
Person and position
Employees can be assigned to work centers:
At capacity category level
At work center level
This assignment is important for:
Workforce planning
The cross-application time sheet (CATS), which proposes a worklist to enter activities for a person.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 107/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 108/312
© SAP AG PLM220 4-22
SAP AG 2003
Work centers
Work
center
Work center
description
Cap June 99 July 99
CW 26 CW 28 CW 29
2000 Eng./Design 002
CW 27
Order
June 99 July 99
CW 26 CW 28 CW 29CW 27Order Activity
902933 1000
60001650 0030
Deallocate ActivityDispatch Capacity Order
2500 Production
902933 1010
002
Capacity Planning: Graphical Planning Table
In the graphical capacity planning table, you can dispatch activities by dragging them with the mouse to
the work center /capacity category for a certain period.
You can call various transactions from the graphical planning table, such as:
- Change/display the order or activity
- Change/display the work center or the capacity screen of the work center
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 109/312
© SAP AG PLM220 4-23
SAP AG 2003
Capacity Planning: Capacity Planning Table
08.1998 09.1998 10.1998 11.1998 12.1998
24.0 8.0 16.0 32.0 16.0
8 33%
2 8.3% 6.5 81%
6.5 h
13.0 h
X
X
Period
Avail.capacity
Dispatched
Worklist
Work center 2000, capacity category 002
WBS E-1399-2, Network 902933, Activity 1000
WBS E-1399-3, Network 902934, Activity 1140
The planning table contains the following types of display:
Work center / capacity with availability, load, dispatched, and pool for several periods
Multiple work centers / capacities with availability and load for several periods
The planning table (tabular form) can be called in work center, individual capacity, and order view. It
displays the available capacity and distributed capacity requirements.
The output unit for the available capacity and capacity requirements is specified in the evaluation profile.
The planning table (tabular form) is broken down into a resources section and a requirements section.
The resources section contains: The name of the work center or the capacity with the capacity category,
scheduling periods, dispatched capacity requirements, and requirements in the worklist that have not yet
been dispatched.
In the requirements section you can display requirements (dispatched and/or not dispatched).
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 110/312
© SAP AG PLM220 4-24
SAP AG 2003
Confirmation Options
-
CATSCATS
CC
OO
MMMM
HR
PMPM
PSPSCSCS
Non-SAP system
PDC
120012001200
100010001000
200020002000
130013001300
110011001100
140014001400 150015001500
400040004000
300030003000
310031003100
500050005000 600060006000
P a l m
P a l m
P i l o
t
P i l o
t
InternetInternet
Collective confirmation
Individual confirmation
Cross-Application
Time Sheet
PDC confirmation
Open PS
Internet confirmation(indiv./coll. confirmation, CATS)
Confirmation from
information system,
confirmation workflowR/3R/3
Confirmations document the processing status of activities and activity elements, and enable you to
make forecasts as to how the project will progress. Various business transactions are executedautomatically using confirmations. These include posting actual costs, actual dates, actual labor, and, if
applicable, changing the activity status.
You can create confirmations in the following ways:
Individually for a network, activity, activity element, or capacity split
As a collective confirmation
Using the structure information system (by selecting activities, and accessing individual or collective
confirmation). You can send a confirmation workflow from the Information System to another user, or
to an organizational unit.
Using the Cross-Application Time Sheet (CATS) Using the Internet (by creating an individual or collective confirmation, or entering time data using the
CATS)
Using a Palm Pilot and the Open PS for Palm Pilot interface
Using the plant data collection (PDC) interface
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 111/312
© SAP AG PLM220 4-25
SAP AG 2003
Individual and Collective Confirmation
-
Network
902153
902153
Act.
1000
1200
Start
10.04.00
15.04.00
Finish
20.04.00
20.04.00
Work
143
87
Detail screen:
Actual work
(actl/forecast)
Processing %
Activity type
Dates
(actl/forecast)
Final conf. ind.
Individual confirmation
Structure information system
Collective confirmation
Confirmation workflow
You can confirm one activity or activity element using an individual confirmation. You enter the data on
the detail screen.
You can confirm various networks, activities, activity elements and individual capacities at the same
time with collective confirmation. You enter the data in the form of a list.
From the Structure Information System, you can perform the following actions for the activities that you
have selected:
Go directly to the individual confirmation transaction
Go directly to the collective confirmation transaction
Store a pool of confirmations - you can then select this pool later in the collective confirmation
transaction or in the Time Sheet
Send a pool of confirmations as a workflow to other users who can then call the collectiveconfirmation transaction directly from their Office inbox.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 112/312
© SAP AG PLM220 4-26
SAP AG 2003
Customizing Confirmations
Default valuesDefault values
- Final confirmation
- Post material issue
- Propose dates
- Propose services
- Automatic milestone dates
ChecksChecks
- Dates in the future
- Work variance
- Duration variance
Logs/workflowLogs/workflow- Actual costs
- Goods movement
- Work workflow
- Duration workflow
Confirmation parameters
Variances
ReasonReason
-- StatusStatus
Field selection
Screen groupScreen group
- Modifiable fields
- Influencing fields
SchedulingScheduling
- Shift order
Parameters for
scheduling
The system settings for confirmation are defined for each plant and network type.
They specify the following parameters for confirmation:
- Final confirmation is proposed automatically during confirmation
- Confirmation dates may be in the future
- Whether the error log for cost determination is displayed
- Percentages for permitted work and duration variances
During the confirmation, you can enter reasons for plan data variances.
You can make a field selection for the confirmation screens in the network.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 113/312
© SAP AG PLM220 4-27
SAP AG 2003
Explanation
Feedback:
Answer
required
Maximum
variance
exceeded
A c t. v a l
.
> m a x.
v a l.
W o r k i t e m
MRP controller
checks
M a i lM a i l
Work
Activity
User
Duration
Work %
MRP
controller
User
MRP controller
Confirmation
Variances in Confirmation
Workflow to
MRP controller
If the actual duration or work exceeds the values you set for the confirmation parameters in Customizing,
the system triggers a workflow automatically.MRP controllers receive work items in their Office inboxes and can display the confirmation or the
network, or return correspondence by mail to the person who entered the confirmation.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 114/312
© SAP AG PLM220 4-28
SAP AG 2003
Actual Capacity Requirements
Proj.reqmts int.prcg
Capacities SchedulingBasic Data
Person
Costing-ID
Capacity categ.
Pool capacity
002
Capacity
Formula cond. Int proc.
Int. dist. key
Formula Formula Forma const. ActCapReqmts
Selection profile
Actual, target, remaining capacity reqs
List profile
Standard overview -> Displayed fields
Overall profile (enhanced capacity evaluation)
1
2
Settings for determining the actual capacity requirements
ActCapReqmts internal proc.
Capacity category
Calc.actual cap.reqmts ActCapReqmts from services
ActCapReqmts from services
002 Person
2
As of Release 4.5A, you can determine actual capacity requirements. This is done using confirmation. In
Extended evaluation in capacity planning, you can then compare the planned capacity requirements withthe actual capacity requirements and display the remaining capacity (the difference).
The prerequisite is that the actual capacity requirements in the capacity detail screen of the work center
and the actual capacity requirements in the Extended capacity evaluation are activated.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 115/312
© SAP AG PLM220 4-29
SAP AG 2003
Attendance/
absence types
HRConfirmation of
activitiesPMPM
CSCS
ServicesMMMMPSPS
CATSCATS
COCOMMMM
HR
PMPM
PSPSCSCS
Transfer Transfer
1Enter
2Release
3Approve
4Transfer
Cross-Application Time Sheet - CATS
Working
hours
Internal cost
allocation
COCO
CATS is an integrated function for entering actual times, which are important in HR, PS, PM, CS, CO,
and MM-SRV.
You can determine the layouts yourself, using data entry profiles.
Report programs pass on the released (and, if necessary, approved) data to the various applications. The
actual times may be important for various applications at the same time. In this case, the data is
transferred to the applications in question. As of Release 4.6, you can use a report to transfer the data to
several target applications at once.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 116/312
© SAP AG PLM220 4-30
SAP AG 2003
Time Sheet: Data Entry View
Worklist:+ Workforce planning
+ Work center
+ Info system
Structure/dates
Worklist:+ Workforce planning
+ Work center + Info system
Structure/dates
Data entry section:
Various entries via
data entry profiles
Data entry section:
Various entries via
data entry profiles
HRPSPS
PMPM
CSCSMMMMPSPS
COCO
HR
Enter travel
expenses HR
Enter travel
expenses HR
CheckCheck
CopyCopyCopy
Time data from
hours required (HR)
Time data from
hours required (HR)
01.01.
Personnel number
Date entry period
1248
Network Acty Short text Total
TotalNetwork Acty ActTy. ATy.
01.01. 02.01.
02.01.03.01.
03.01.04.01.
04.01. 05.01.
05.01.06.01.
06.01. 07.01.
07.01. 08.01.
08.01.09.01.
09.01.10.01.
10.01.
Time data is entered for one or more people.
The screen configuration (for the request screen, worklist, and data entry part) is flexible:
- Depending on the group of employees (via data entry profile)
- User-defined (using table control)
Worklist for employees, using:
- Activities to which the employee is assigned via the work center or workforce planning (for PM,
PS, CS).
- Activities via pool of confirmations (for PS, PM, CS)
- Objects the employee is working on (using the CATS database)
- Objects via user exits
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 117/312
© SAP AG PLM220 4-31
SAP AG 2003
CATS - Customizing Using the Data Entry Profile
01.01.
Personnel number
Date entry period
1248
Network Acty Short text Total
TotalNetwork Acty ActTy. ATy.
01.01. 02.01.
02.01.03.01.
03.01.04.01.
04.01. 05.01.
05.01.06.01.
06.01. 07.01.
07.01. 08.01.
08.01.09.01.
09.01.10.01.
10.01.
Data entry profile:
+ With/without times+ Period type (weeks, months)
+ Workdays only
Data entry profile:
+ With/without times+ Period type (weeks, months)
+ Workdays only
Data entry profile - worklist
+ Workforce planning
+ Using assigned work center
Work center+ Pool of
confirmations info system
Data entry profile - worklist
+ Workforce planning
+ Using assigned work center
Work center+ Pool of
confirmations info system
Data entry profile:
+ Periods relative to today's
date
Data entry profile:
+ Periods relative to today's
dateData entry profile:
+ Weekdays/calendar days
Data entry profile:
+ Weekdays/calendar days
Data entry profile:
+ Approval required before
transfer to applications
Data entry profile:
+ Approval required before
transfer to applications
Field selection
of worklist and
data entry
section
Field selection
of worklist and
data entry
section
Data entry profiles are maintained in Customizing for cross-application components.
The data entry profile determines how the times are entered (via field selection of the receiver) and to
which modules activity data is transferred. It determines whether or not the entered times are released
when you save and whether authorization is required.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 118/312
© SAP AG PLM220 4-32
SAP AG 2003
Field selection: Influencing field
Modified fields
Att./absence type
Work center
Description
Rec. WBS element
Receiver cost obj.
Receiver order Cost center
Activity type
Network
Activity
Screen group: Data entry section
Influencing field: Data entry profile
Influencing value: 1301
Input Req Disp Hide HiLi
CATS - Field Selection
Field selection determines which of the many fields in the worklist and data entry screen groups are
displayed or accept input.
Field selection can be controlled in accordance with the data entry profile field.
Keep the field selection as simple as possible and do not include any unnecessary fields. All possible
receivers and activities should appear for a person or group of persons. If the person works for a network
as well as a receiver cost center, for example, both receivers should appear as options in the field
selection.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 119/312
© SAP AG PLM220 4-33
SAP AG 2003
You are now able to:
Plan and implement internal services with internal
processing activities
Analyze capacity requirements
Distribute work to personnel resources
Confirm activities
Enter activities using CATS
Capacities: Unit Summary
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 120/312
© SAP AG PLM220 4-34
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 121/312
© SAP AG PLM220 4-35
Exercises
Unit: Capacities
Topic: Capacities
• Brief recap of planning and implementation of internal activities
• Available capacity and capacity requirements
• Workforce planning
• Confirmation, CATS, and actual capacities
In the following section, you will work through four individual sets of
exercises. The first set is simple. You will plan an activity, determinerequirements, and then reduce them. In the second section, you will be
introduced to details on capacity requirements and available capacitiesand see how they are evaluated. In the third set, you will distribute the planned work to persons. In the fourth section, you will apply the various
options for confirming activities.
1-1 Call the project planning board.
1-1-1 Edit your project T-100## in the project planning board. Use the
Elevators/Turbines project planning board profile.
1-1-2 Plan work on activity 1100 Engineering of running gear .
Enter the following data:
Field Name Values
Work center 2200
Work 120 hours
Activity Type 1429
Normal duration 16 days
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 122/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 123/312
© SAP AG PLM220 4-37
1-1-5 The activities 1000 Engineering of drawing/calculation/design and 1100
Engineering of running gear are complete. Enter appropriate finalconfirmations and investigate the status of the activities.
The dialog screen for confirming activity 1000 appears. Enter the earliest finish
as the finish date. Copy the remaining data and call the next activity.
Enter the earliest start or finish as the actual start or finish, and copy theremaining data.
Display the status of activity 1000.
The activity should have the status Released , Manually confirmed , and
Confirmed .
As a result of the final confirmation, the system resets all the
capacity requirements of the activity to zero. In the previous unit,you entered a partial confirmation of 20%, which left a capacity
requirement of 80%.
1-1-6 Save your project.
1-2 In the following section, you will create your own work center, use the work center in
the network, and investigate the capacity requirements for the work center. Start from
the Easy Access menu.
1-2-1 Create a work center for your project.Enter the following data on the initial screen:
Field Name Values
Plant 1300
Work center 25##
Work center category 0006
The basic data screen for the work center appears. Enter the following data:
Field Name Values
Text Group ##, assembly
Person Responsible 001
Usage 003, only networks
Save your entries before continuing.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 124/312
© SAP AG PLM220 4-38
1-2-2 Enter the data for the available capacity of the work center.
Use the following data:
Field Name Values
Capacity category 002
Other formula SAP008
Int. distribution key SAP030
The detail screen of the capacity category that you just created appears. Now
specify the available capacity. Use the following data:
Field Name Values
Capacity planner group 001
Factory calendar ID 01Base unit of meas. Hours
Start 8 a.m.
Finish 6 p.m.
Length of breaks 1 hour
Capacity utilization 100 %
No. of indiv. cap. 1
Relevant to finite scheduling Select
Can be used by severaloperations
Select
Overload 20 %
Long-term planning Deselect
Save your entries before continuing.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 125/312
© SAP AG PLM220 4-39
1-2-3 Your new work center is still missing scheduling data and needs to be assigned
to a cost center. Maintain this data.
The detail screen for scheduling appears. Enter the following data:
Field Name Values
Capacity category 002
Other formula SAP004
Enter the cost center assignment.
Enter the following data for costing:
Field Name Values
Start date Start of current month
Cost center 4290
Formula key (field has no label) SAP008
Activity type internal processing 1421
Save your entries.
1-2-4 Use your new work center in your project, in activity 4000 Production ofrunning gear, bearing, valves. Use the project planning board for this purpose.
Plan work in your work center. Use the following data:
Field Name Values
Work center 25##
Work 300 hours
Duration 30 days
Distribution key SAP020
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 126/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 127/312
© SAP AG PLM220 4-41
1-2-7 Take a look at the capacity load from your work center view.
Enter the following values on the initial screen:
Field Name Values
Work center 25##
Capacity planner group 001
Plant 1300
A week-by-week list of your work center's capacity requirements appears. Thiswork center will probably be overloaded for several weeks by the capacity
requirements of your project.
If you cannot see all the capacity requirements of your project, adjust the
evaluation period.
Take a closer at the requirements of an individual period.Display the activity field.
Return to the display of all periods and display the load graphic.
Exit the graphic and the report.
1-3 In the next section of exercises, you will apply your knowledge of workforce planning.
Before doing so, however, you will set up a project team and assign a person to your
work center.
1-3-1 Create a project team for the top WBS element of your project. Use the project
planning board for this purpose.
You can assign the project team on the detail screen of a WBS element.
Assign the organizational unit 1300 Project Center Frankfurt to the WBS
element Turbine.
Which persons make up your project team? ___________________
(Expand all the branches in the overview to display the persons).
Exit the project team assignment.
Save your data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 128/312
© SAP AG PLM220 4-42
1-3-2 Assign a person to the capacity category in your work center. The positions and
persons have already been created in the HR system.
Change your work center 25##.
Link the capacity category 002 with the HR system.
A screen appears in which you can create a link to a person, a position, or arequirements profile. Link to a position. Assign position 500141## to the
capacity category.
Save your entries.
1-3-3 Assign the personnel resources created previously to your project. Use the project view of workforce planning.
Enter the following data on the initial screen:
Field Name ValuesProject T-100##
Profile 1302
Profile 1302 is used to calculate the planning period relative to the current date.
In this case, you do not need to enter a start or finish date for workforce
planning.
An overview of all activities that have capacity requirements in the planning period appears. Filter out the activities that are assigned to the WBS element
T-100##.1 Engineering and Design.
The employee Howard Clayton is a member of your project team. Assign him
to activity 1200 Engineering of case.
You can now assign the person to individual days for the activity. Enter severalhours for a few periods on the right-hand side of the graphic.
If none of the fields are ready for input, the capacity requirements for
the activity are outside the planning period. You can now adjust theassignment: Select the assignment and choose Change assignment .
You can change the assignment period here. Select Copy.
Display availability or load for Thomas Schneider.
Stay in workforce planning and now assign the person from your work center
25## to activity 4000 Production of running gear, bearing, valves.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 129/312
© SAP AG PLM220 4-43
The (inherited) project team appears again. The person from your work center
is not yet listed.
Schedule this person for a few hours at the proposed times. Allocate 5 hours forthe activity today and tomorrow. Since the activity is planned far in the future,
you now have to adjust the planning period (see above note).
Save your entries.
1-3-4 Evaluate the workforce planning settings for your project.
Enter the following data on the initial screen:
Field Name Values
Project T-100##
Profile 1302
With availability pers. res. Select
An overview of the personnel assigned to the project appears. The first column
shows Exceptions. These exceptions are highlighted using traffic light colors.
Create an exception. Set the traffic lights to change to red if less than 5% of therequirements is assigned to a resource.
Exit the evaluation.
1-4 In the next set of exercises, you will enter actual activities and dates for your project.The prerequisite is that you release your activities or WBS elements (set status
Released ).
Release your entire project in the Project Builder.
Save your entries.
1-4-1 In the exercises for the scheduling unit, you have already dealt with individual
confirmation. Now use collective confirmation to confirm several of your
project activities at once. You can call the collective confirmation function fromthe Structure Information System. Enter final confirmations for activities 1300
and 2000.
If prompted by the system, specify the profile YIDES_130000.
Call the collective confirmation function for these two activities from the menu.
Save the data.
Exit the Information System without saving the overview.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 130/312
© SAP AG PLM220 4-44
1-4-2 Change your work center so that actual capacities (from a confirmation) are
updated. You will enter the confirmation in the next exercise.
Save the changes.
1-4-3 Use the time sheet to enter actual data for internal processing activities.
Confirm the activities for the person that you have assigned to work center 25##(using position assignment).
The corresponding personnel number is: 1920 + ## (for example, if ## = 11, the personnel number is 1920 + 11 = 1931).
Call time recording with CATS.
Enter the following data on the initial screen:
Field Name Values
Data entry profile 1301
Personnel number 1920 + ##
The worklist should display the activities to which you previously assigned the person in workforce planning.
Enter six hours of work for today for activity 4000 Production of running gear,
bearing, valves.
Change the times for today accordingly.
Note which status (partial confirmation or final confirmation) will be entered
for the activity.
Save the times entered.
You have entered the times but they have not yet been updated in the activity.Transfer the entered times to Project System.
Enter the following data on the initial screen:
Field Name Values
Personnel number 1920 + ##
Test run indicator Deselect
An overview appears that shows how many records have been read and the
activities to which data has been transferred. Actual capacities are written using
the confirmation. You will analyze the capacity requirements in the nextexercise.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 131/312
© SAP AG PLM220 4-45
1-4-4 Take another look at the capacity requirements of your project. This time, use
the extended evaluation of capacity planning.
Enter the top WBS element T-100## on the initial screen.
You use extended capacity evaluation that is based on a standard
delivery. The underlying overall profile has the key SAPPS_G020.This profile normally has no actual capacities. However, your trainer
changed the corresponding standard profile before the start of theexercise.
An overview appears, which does not yet display any actual capacity
requirements. Change the field selection to display the following fields:
Field Name
Actual capacity requirements
Target capacity requirement
Remaining capacityrequirements
Available capacity
Actual capacity load
Target capacity load
The field selection proposes requirements, loads, and available
capacities. The loads are always calculated from the relationship between the requirement and the available capacity. For example:
Actual capacity load = actual capacity requirements/available
capacity). The free capacity is the difference between requirementand available capacity.
Now investigate the capacity requirements of a work center in an individual
period.
How many different projects have requirements in this period?
You can also change the field selection in this overview and call the workcenter or activities.
Exit the report.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 132/312
© SAP AG PLM220 4-46
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 133/312
© SAP AG PLM220 4-47
Solutions
Unit: Capacities
Topic: Capacities
• Brief recap of planning and implementation of internal activities
• Available capacity and capacity requirements
• Workforce planning
• Confirmation, CATS, and actual capacities
In the following section, you will work through four individual sets of
exercises. The first set is simple. You will plan an activity, determinerequirements, and then reduce them. In the second section, you will be
introduced to details on capacity requirements and available capacitiesand see how they are evaluated. In the third set, you will distribute the planned work to persons. In the fourth section, you will apply the various
options for confirming activities.
1-1 Call the project planning board.
SAP Menu
Logistics Project System Project Project Planning Board Change Project
(Double-click the transaction to select it)
1-1-1 Edit your project T-100## in the project planning board. Use the
Elevators/Turbines project planning profile.
Enter your project in the Project def. field, select W. activities , and choose the
Open project icon.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 134/312
© SAP AG PLM220 4-48
1-1-2 Plan work on activity 1100 Engineering of running gear .
Call the detail screen for the activity by double-clicking the time bar or the
activity number.
Select the Internal tab and enter the following data:
Field Name Values
Work center 2200
Work 120 hours
Activity type 1429
Normal duration 16 days
Select Back to confirm your entries.
1-1-3 Determine the capacity requirements for your project.
Select all objects using Select all .
Choose Edit Functions Activate capacities.
Look at the status bar in the project planning board. The capacity requirementswill only be calculated after the next scheduling run.
You can determine capacity requirements automatically whensaving data by activating the Capacity requirements indicator in the
network header. You can also calculate this directly in the project planning board by selecting an activity and choosing Details→
Network header .
Start scheduling by selecting the appropriate icon.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 135/312
© SAP AG PLM220 4-49
1-1-4 Analyze the capacity requirements of the WBS element T-100##.1 Engineering
and Design.
Select the WBS element T-100##.1.
Call the capacity overview directly in the project planning board.
Select Capacity overview .
A bar chart showing the capacity requirements appears. Display a histogram ofthe requirements for work center 2200 Specifications statics.
Select the work center.
Choose Load as histogram in the context menu (right mouse button).
Show the legend and hide it again.
Choose the appropriate entry in the context menu.
Show the legend and hide it again using Close chart in the menu.
Double-click the work center to view it from the project planning board
Close the capacity overview.
Choose Close chart in the context menu.
1-1-5 The activities 1000 Engineering of drawing/calculation/design and 1100 Engineering of running gear are complete. Enter appropriate final
confirmations and investigate the status of the activities.
To select both activities, keep the Control key pressed.
Select Confirm activity .
The dialog screen for confirming activity 1000 appears. Enter the earliest finish
as the finish date. Copy the remaining data and call the next activity.
Select Next operation .
Enter the earliest start or finish as the actual start or finish, and copy theremaining data.
Select Back .
Display the status of activity 1000.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 136/312
© SAP AG PLM220 4-50
Call the detail screen of the activity by double-clicking the activity bar or the
activity number.
The Internal tab displays the system status of the activity.
The activity should have the status REL (Released), MCNF (Manually
confirmed), and CNF (Confirmed).
Exit the detail screen of the activity.
Select Back .
As a result of the final confirmation, the system resets all the
capacity requirements of the activity to zero. In the previous unit,
you entered a partial confirmation of 20%, which left a capacityrequirement of 80%.
1-1-6 Save your project.
Choose Save .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 137/312
© SAP AG PLM220 4-51
1-2 In the following section, you will create your own work center, use the work center in
the network, and investigate the capacity requirements for the work center. Start fromthe Easy Access menu.
Select Back until the Easy Access menu appears.
1-2-1 Create a work center for your project.
SAP Menu
Logistics Project System Basic Data Master Data Work Center
Master Record Create
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Plant 1300
Work center 25##
Work center cat. 0006
Select Next screen .
The basic data screen for the work center appears. Enter the following data:
Field Name Values
Text Group ##, assembly
Person Responsible 001
Usage 003, only networks
Save your entries before continuing.
Choose Save .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 138/312
© SAP AG PLM220 4-52
1-2-2 Enter the data for the available capacity of the work center.
Choose Work center Change .
Enter the plant and your work center.
Select Capacities and enter the following data:
Field Name Values
Capacity category 002
Other formula SAP008
Int. dist. key SAP030
Select Enter to confirm your entries.
The detail screen of the capacity category that you just created appears. Specifythe available capacity. Use the following data:
Field Name Values
Capacity planner group 001
Factory calendar ID 01
Base unit of meas. Hours
Start 8 a.m.
Finish 6 p.m.
Length of breaks 1 hour
Capacity utilization 100 %
No. of indiv. cap. 1
Relevant to finite scheduling Select
Can be used by several
operationsSelect
Overload 20 %
Long-term planning Deselect
Select Enter to confirm your entries.
Save your entries before continuing.
Choose Save .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 139/312
© SAP AG PLM220 4-53
1-2-3 Your new work center is still missing scheduling data and needs to be assigned
to a cost center. Maintain this data.
Select Scheduling on the initial screen.
The detail screen for scheduling appears. Enter the following data:
Field Name Values
Capacity category 002
Other formula SAP004
Select Enter to confirm your entries.
Enter the cost center assignment.
Select the Costing tab.
Enter the following data for costing:
Field Name Values
Start date Start of current month
Cost center 4290
Formula key (field has no label) SAP008
Activity type internal processing 1421
Confirm your entries by selecting Enter .
Save your entries.
Choose Save .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 140/312
© SAP AG PLM220 4-54
1-2-4 Use your new work center in your project, in activity 4000 Production of
running gear, bearing, valves. Use the project planning board for this purpose.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project
(Double-click the transaction to select it)
Call the detail screen for activity 4000 by double-clicking the time bar or the
activity number.
Select the Internal tab.
Plan work in your work center. Use the following data:
Field Name Values
Work center 25##
Work 300 hours
Duration 30 days
Distribution key SAP020
Select Back .
1-2-5 The capacity requirements and planned dates are no longer up-to-date.Determine the requirements again.
Select all objects using Select all .
Start scheduling by selecting the appropriate icon.
Check the capacity load of the work center.
Select the WBS element T-100##0.4, Production .
Select Capacity overview .
View the histogram load display.
Choose the appropriate entry in the context menu (right mouse button).
Is there an overload? Note down the earliest start date and the latest finish date of the activity for
comparison at a later stage.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 141/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 142/312
© SAP AG PLM220 4-56
Select the grouping criteria in the left half of the dialog box and choose Hide fields (Do not choose)
Choose the WBS element field and display it by selecting Show fields .
Select Continue.
Exit the report.
Select Back .
When you exit the Information System, a save prompt dialog box appears.
Choose No.
1-2-7 Take a look at the capacity load from your work center view.
SAP Menu
Logistics Project System Information System Resources Capacity
Load Work Center View(Choose transaction by double-clicking it)
Enter the following values on the initial screen:
Field Name Values
Work center 25##
Capacity planner group 001
Plant 1300
Select Standard overview .
A week-by-week list of your work center's capacity requirements appears. This
work center will probably be overloaded for several weeks by the capacity
requirements of your project.
If you cannot see all the capacity requirements of your project, adjust theevaluation period.
If this is the case, choose Settings General and position your cursor in the
Int. finish field in the Interval to be evaluated section. Increase the value
accordingly (if necessary, compare it with the latest finish of the activity you
noted down previously).
Take a closer look at an individual period.
Select a period whose requirements are greater than zero.
Select Cap. details/period .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 143/312
© SAP AG PLM220 4-57
Display the activity field.
Select Choose fields .
Look for the Operation field in the right half of the dialog box that appears.
Select it and copy it to the left half of the dialog box by selecting Choose.
Select Continue to confirm your entries.
Which activity creates the requirement?
Return to the display of all periods and display the load graphic.
Select Back .
Select Standard overview .
Exit the graphic and the report.
Select Back twice.
1-3 In the next section of exercises, you will apply your knowledge of workforce planning.
Before doing so, however, you will set up a project team and assign a person to yourwork center.
1-3-1 Create a project team for the top WBS element of your project. Use the project
planning board for this purpose.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project
(Double-click the transaction to select it)
Enter your project in the Project def. field, select W. activities , and choose the
Open project icon.
You can assign the project team on the detail screen of a WBS element. Call the
detail screen for the top WBS element.
Double-click the WBS element T-100## Turbine .
Select Project team for WBS element .
An overview of the personnel resources assigned to this element appears.Assign the organizational unit 1300 Project Center Frankfurt to the WBS
element Turbine.
Position the cursor on the line Turbine .
Select Create assignment .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 144/312
© SAP AG PLM220 4-58
Another dialog box appears. Assign an organizational unit.
Double-click the line Organizational unit.
Enter proj* on the Abbreviation and Name tab and select Start search .
Select the top entry and confirm your selection by selecting Copy .
In the next dialog box, select Save to create the assignment.
You return to the initial screen.
Which persons make up your project team? ___________________
(Expand all the branches in the overview to display the persons).
Exit the project team assignment.
Select Back .
Exit the WBS element detail screen.
Select Back .
Save your data.
Choose Save .
1-3-2 Assign a person to the capacity category in your work center. The positions and
persons have already been created in the HR system.
Change your work center 25##.
SAP Menu Logistics Project System Basic Data Master Data Work Center
Master Record Change
(Choose the transaction by double-clicking it)
Enter your work center and choose Capacities .
Link the capacity category 002 with the HR system.
Double-click capacity category 002 to access the header for the capacity
category.
Select HR assignment. A screen appears in which you can create a link to a person, a position, or a
requirements profile. Link to a position. Assign position 500141## to the
capacity category.
Double-click the yellow line Position .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 145/312
© SAP AG PLM220 4-59
A dialog box appears, in which you can enter position 500141##.
Enter position 500141## and select Copy .
Save your entries.
Choose Save .
1-3-3 Assign the personnel resources created previously to your project. Use the
project view of workforce planning.
SAP Menu
Logistics Project System Resources Workforce Planning Project
View
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name ValuesProject T-100##
Profile 1302
Profile 1302 is used to calculate the planning period relative to the current date.In this case, you do not need to enter a start or finish date for workforce
planning.
Choose Execute .
An overview of all activities that have capacity requirements in the planning period appears. Filter out the activities that are assigned to the WBS elementT-100##.1 Engineering and Design.
Select Other WBS element .
Choose the WBS element in the dialog box by double-clicking it .
The employee Howard Clayton is a member of your project team. Assign himto activity 1200 Engineering of case.
Select activity 1200 Engineering of case .
Select Create assignment .
A dialog box containing your project team appears.
Select the line Howard Clayton and choose Assign.
You can now assign the person to individual days for the activity. Enter several
hours for a few periods on the right-hand side of the graphic.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 146/312
© SAP AG PLM220 4-60
If none of the fields are ready for input, the capacity requirements for
the activity are outside the planning period. You can now adjust the
assignment: Select the assignment and choose Change assignment .You can change the assignment period here. Select Copy.
Display availability or load for Thomas Schneider.
Select the assignment and select Availability pers. resource.
Stay in workforce planning and now assign the person from your work center25## to activity 4000 Production of running gear, bearing, valves.
First call the activity view of WBS element T-100##.4 Production.
Select Other WBS element and choose the WBS element T-100##.4 Production
by double-clicking it.
Select activity 4000 Production of running gear, bearing, valves .
Select Create assignment .
The (inherited) project team appears again. The person from your work center
is not yet listed.
Select Work center organization structure .
Expand the display until you find the person in question.
Select the person by choosing Person .
Select Continue.
The person is now listed along with the project team. You can now continue as
before. Select the person, and choose Assign.
Schedule this person for a few hours at the proposed times. Confirm your
entries.
Allocate 5 hours for the activity today and tomorrow. Since the activity is
planned far in the future, you now have to adjust the planning period (see abovenote).
Save your entries.
Choose Save .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 147/312
© SAP AG PLM220 4-61
1-3-4 Evaluate the workforce planning settings for your project.
SAP Menu
Logistics Project System Resources Workforce Planning
Evaluation
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Project T-100##
Profile 1302
With availability pers. res. Select
Choose Execute .
An overview of the personnel assigned to the project appears. The first columnshows Exceptions. These exceptions are highlighted using traffic light colors.
Create an exception. Set the traffic lights to change to red if less than 5% of the
requirements is assigned to a resource.
Choose Settings .
Select the Exceptions tab.
In the section Activity work distributed in %, enter the value 5 after the Less
than or equal to sign.
Select the Display indicator.
Change the color of the traffic light to red by clicking it with the left mouse
button.
Select Copy .
Exit the evaluation.
Select Back .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 148/312
© SAP AG PLM220 4-62
1-4 In the next set of exercises, you will enter actual activities and dates for your project.
The prerequisite is that you release your activities or WBS elements (set status Released ).
Release your entire project in the Project Builder.
SAP Menu
Logistics Project System Project Project Builder(Choose the Project Builder by double-clicking it)
Drag and drop your project T-100### from the worklist to the structure tree.
Position the cursor on the project definition and choose Edit → Status → Release .
Save your entries.
Choose Save .
1-4-1 In the exercises for the scheduling unit, you have already dealt with individual
confirmation. Now use collective confirmation to confirm several of your project activities at once. You can call the collective confirmation function from
the Structure Information System. Enter final confirmations for activities 1300
and 2000.
SAP Menu
Logistics Project System Information System Structures Structure
Overview
(Choose the transaction by double-clicking it)
If prompted by the system, specify the profile YIDES_130000.
The initial screen for the structure information system appears.
Specify your project and select Execute .
In the overview, select only activities 1300 Engineering of control valves and
2000 Planning of systems and instrumentation .
Call the collective confirmation function for these two activities from the menu.
Choose Extras/environment Confirm Collective confirmation to call the
collective confirmation screen.
Activate the Final confirmation indicator for both activities and select Enter to
confirm your entries. The indicator is in column F .
Once you have confirmed your entries the planned data of the activities is read.
You can of course still change this data.
Save the data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 149/312
© SAP AG PLM220 4-63
Choose Save .
Select Back to exit the Structure Information System without saving the
overview.
1-4-2 Change your work center so that actual capacities (from a confirmation) are
updated. You will enter the confirmation in the next exercise.
SAP Menu
Logistics Project System Basic Data Master Data Work Center
Master Record Change
(Choose the transaction by double-clicking it)
Enter your work center 25## and choose Capacities.
Activate the updating of actual capacities by selecting ActCapReqmn on the
lower part of the capacity detail screen.
Select this button. Another dialog box appears. Enter the value 2 in the Calc. actual cap. reqmts
field.
Select Continue to confirm your entries.
Save the changes.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 150/312
© SAP AG PLM220 4-64
1-4-3 Use the time sheet to enter actual data for internal processing activities.
Confirm the activities for the person that you have assigned to work center25## (using position assignment).
The corresponding personnel number is: 1920 + ## (for example, if ## = 11, the
personnel number is 1920 + 11 = 1931).
Call time recording with CATS.
SAP Menu
Logistics Project System Progress Confirmation Time Sheet
CATS Classic Record Working Times
(Choose transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Data entry profile 1301
Personnel number 1920 + ##
Select Enter to confirm your entries.
Call time recording by selecting Enter times.
The worklist should display the activities to which you previously assigned the
person in workforce planning.
Enter six hours of work for today for activity 4000 Production of running gear,
bearing, valves.
Select the activity in the worklist and choose Copy row.
Change the times for today accordingly.
Note which status (partial confirmation or final confirmation) will be enteredfor the activity.
Double-click the cell with the time entered .
A dialog box appears in which you can determine the status.
Select the Determine status automatically indicator .
Select Continue to confirm your entries.
Save the times entered.
Choose Save .
You have entered the times but they have not yet been updated in the activity.
Transfer the entered times to Project System.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 151/312
© SAP AG PLM220 4-65
SAP Menu
Logistics Project System Progress Confirmation Time Sheet
Transfer Project System Transfer
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Personnel number 1920 + ##
Test run indicator Deselect
Choose Execute .
An overview appears that shows how many records have been read and the
activities to which data has been transferred. Actual capacities are written usingthe confirmation. You will analyze the capacity requirements in the next
exercise.
Select Back to exit the overview.
1-4-4 Take another look at the capacity requirements of your project. This time, use
the extended evaluation of capacity planning.
SAP Menu
Logistics Project System Resources Capacity Requirements Planning
Evaluation Extended Evaluation Project View WBS
Element/Version(Choose the transaction by double-clicking it)
Enter the top WBS element T-100## on the initial screen.
Select Continue.
You use extended capacity evaluation that is based on a standarddelivery. The underlying overall profile has the key SAPPS_G020.
This profile normally has no actual capacities. However, your trainerchanged the corresponding standard profile before the start of the
exercise.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 152/312
© SAP AG PLM220 4-66
An overview appears, which does not yet display any actual capacity
requirements. Change the field selection to display the following fields:
Field Name
Actual capacity requirements
Target capacity requirement
Remaining capacityrequirements
Available capacity
Actual capacity load
Target capacity load
Select Choose fields .
Select Choose and Do not choose to choose the required fields.
Select Continue to confirm your entries.
The field selection proposes requirements, loads, and available
capacities. The loads are always calculated from the relationship between the requirement and the available capacity. For example:
Actual capacity load = actual capacity requirements/available
capacity). The free capacity is the difference between requirement
and available capacity.
Now investigate the capacity requirements of a work center in an individual
period.
Select any period .
Select Single.
How many different projects have requirements in this period?
You can also change the field selection in this overview and call the work
center or activities.
Exit the report.
Select Back twice.
Another dialog box appears. Choose Yes to confirm.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 153/312
© SAP AG PLM220 5-1
SAP AG 2003
External Services: Contents
Planning externally processed activities,
purchase orders, and goods receipts
Planning service activities, purchase orders,
entering services and acceptances
Setting the relevant tables in Customizing
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 154/312
© SAP AG PLM220 5-2
SAP AG 2003
External Services: Unit Objectives
Create externally processed and service activities
Enter purchase orders in Purchasing
Enter goods receipts
Enter and accept services
At the conclusion of this unit, you will be able to:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 155/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 156/312
© SAP AG PLM220 5-4
SAP AG 2003
Due to capacity bottlenecks, you must procurecertain services externally. You will assign some of
the activities of your turbine project (for example,
engineering and design work) to an external design
office.
External Services: Business Scenario
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 157/312
© SAP AG PLM220 5-5
SAP AG 2003
Resource Planning
Company
Purch.Order
Internally processed activityExternally processed activity
Service activity
Vendor
Purch.Order
Capacity load utilization
Workforce planningWork center
120012001200
400040004000100010001000
300030003000
200020002000 310031003100
130013001300
280028002800
150015001500
500050005000
140014001400
You use activities in the network to plan the resources required for a project.
Project System draws a distinction between the following resources:
An internally processed activity defines the output to be provided by machines or personnel in order to
complete the activity. You can evaluate the capacity load utilization of the work centers involved,
reschedule these capacities as necessary, and distribute work among employees.
You use an externally processed activity to specify the services that need to be provided by other
companies in order to complete the activity. External processing is carried out through the purchasing
department.
Service activities are also used to procure services externally. In contrast to externally processed
activities, service activities allow you to draw up service specifications and enter value limits for any
unplanned services.
Service processing, as well as the entry and acceptance of the services performed, is also carried out
by the purchasing department.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 158/312
© SAP AG PLM220 5-6
SAP AG 2003
Services to be provided by a vendor
Purchaserequisition
Bidinvitation
Entry ofquotation
Selectionof vendor
Purchaseorder
processing
Purchase
ordermonitoring
Invoiceverification
Goodsreceipt
External Processing
140014001400
Material group
Purchasing group
Quantity and unit
Vendor 1000
Purch.Order
Description
You can create activities and activity elements in the network as externally processed activities or create
external elements (if you commission a design office to design a machine, for example). When youcreate such an activity, a purchase requisition is also created, and processed further in purchasing. You
can access data from Purchasing for external processing (a purchasing info record, for example, which
contains prices and delivery times for external processing).
You can generate a purchase requisition for externally processed activities from Project System. This
purchase requisition is converted into a purchase order in Purchasing. A goods receipt and invoice
receipt can then be posted for the purchase order. Depending on whether the goods or invoice receipt is
valuated, you post the costs of both transactions to the externally processed activity.
Externally processed or service activities are determined using the control key.
You can also assign a work center and planned work to an externally processed activity. This allows you
to carry out capacity planning for your vendors.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 159/312
© SAP AG PLM220 5-7
SAP AG 2003
External Activity Detail Screen
Extnl
0010
Internal Dates Allocations Long text User fields
Activity Check by external suppliers
External Processing
System status
WBS element
Info rec
Vendor
Outl. agreement
Price DM
Plnd dely time
Activity qty
PostgData FixPrice
Received
Requisition
Res./Purc. req. From release
CRTD Control key Subntwk exists
Purc. ord exists Service exists
Project sum.
Material groupPurchasing org.
Purchasing group Sort string Certific.
Requester
Recipient
Req.tracking no
Executn factor
Unloading point
PReq Invoicing plan Settlement rule Plan/act. costs PS text
Immediately
From release
Never
In the example above, the external processing data is read from a purchasing information record. The
fields that are read, for example the price per unit, are referenced, which means that changes can nolonger be made in the activity.
In Customizing for the network, you can define default values for the following fields of the externally
processed activity in the network profile: Control key, cost element, currency, purchasing organization,
material group, purchasing group, and order unit.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 160/312
© SAP AG PLM220 5-8
SAP AG 2003
Workflow for a Purchase Order Change
Network activity
External services
Purch.order 1 _ _ _ 2 _ _ _
Change
Service XY 15 hours
on 04.02.00
PSPS
Order 15 h
Service XY 10 hours
on 02/02/00
Change
quantities
Changedates
Purchaseord. 10 h
Purch.Purch.
PReq10 h
Inbox
PS:Change
pur. order
Inbox
2
31
If changes are made in the network to dates or quantities for material components or external activities
for which a purchase order has already been created, the system triggers a workflow automatically. Theonly prerequisite is that this workflow has been activated in the Parameters for the network type table.
The persons responsible in Purchasing receive a work item in SAP Office with information on the
required changes. They can then process the purchase orders directly from the mail.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 161/312
© SAP AG PLM220 5-9
SAP AG 2003
Workflows and Mails in Project System
Confirmation pool
Purch.Availability
check
Confirmationvariance
PS texts
PSPS
MM COCO
Pool
Info System
PSPS
42
Workflow Workflow
and and
MailsMails
Start workflow frommilestone
Model: xx
Color: Red
P u r c h .
o r d e r
P u r c h .
o r d e r
Total: 3200
PSPS
SAP Business Workflow combines technical information and tools to control and process cross-
application procedures automatically. You can use workflow in Project System to automate and integrateall the processes in a project.
Project System uses SAP Office:
- To send PS texts (no workflow)
- For budget deficits (no workflow)
- In the Purchasing procedure (standard task, predefined)
- For variances in confirmations (standard task, predefined)
- For sending pools of confirmations (standard task, predefined)
- In the milestones with user-defined standard tasks or user tasks Claim Management and corresponding workflows were introduced as of R/3 Release 4.6C.
Close claim (TS20000749), edit claim (TS20000750), approve measure (TS20000751), edit new claim
(TS20000754) and approve claim (TS20000907)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 162/312
© SAP AG PLM220 5-10
SAP AG 2003
Settings for Workflow
PO change
Model:xxColor: Red
P u r c h a s e
P u r c h a s e
Total:3200
Confirmation pool
Parameter network type
Parameter network type
Structuresinfo systemStructuresinfo system
Standard task
7951
Standard task
7951Standard
task 7944
Standard
task 7944
Organizational unit HR
SAP organizational object
T024
(Purchasing group)
SAP organizational object
T024
(Purchasing group)
Position
Person
User User
Position
Person
++ ++
Variance too large
Confirmationparameters
Confirmationparameters
Standard task
8015
Standard task
8015
Organizational unit HR
SAP organizational object
T024D
(Plant/MRP controller)
SAP organizational object
T024D
(Plant/MRP controller)
Position
Person
User
++
Settings for workflows are maintained in IDES (Internet Demonstration and Education System).
Organizational units:
- For purchase order changes: 50010294 (PS-EKGRP-001)
- For confirmation variances: 50010295 (PS-DISGR-101)
The organizational units are assigned to positions:
- Organizational unit 50010295 to position 50010297 (for confirmation variances)
- Organizational unit 50010294 to position 50010296 (for purchase order changes)
Pools of confirmations are sent from the structure/dates information system to a position or person. You
can specify position 50010298 in IDES, for example.
If budgets are exceeded, workflow mails can be sent to the person responsible. In this case, you canspecify a user in Customizing or in the application by maintaining the table for the person responsible.
In IDES, all workflows point to the user WF-PS-1, who in turn receives all workflow tasks in his or her
office inbox.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 163/312
© SAP AG PLM220 5-11
SAP AG 2003
280028002800
Description
Material group
Purchasing group
Service specifications
Plannedservices
Unplannedservices
Service masteror text / value Value limit
PReq Value check
ServiceServiceService
DefinitionDefinitionDefinition
Allows you to define
all services to be
procured. Individual service
specifications can be created for
each planned procurement in the
purchasing document.
Service
Vendor 1000
Purch.order
As well as externally processed activities, you can create service activities or service activity elements
for services to be provided externally.
A service activity triggers a similar purchasing process, but can also contain a hierarchy of planned
services to be purchased and value limits for unplanned services.
Goods receipt for services involves two steps:
Service entry
Acceptance of services performed
For service activities, you can maintain service specifications for various services to be provided by the
service provider (planned services).
You can use value limits to restrict services that the service provider has not planned.
You can create the link to the MM Service component (MM-SRV) using service activities.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 164/312
© SAP AG PLM220 5-12
SAP AG 2003
External Services Management
Purchaseorder monitoring
Purchaseorder processing
Purchaserequisition
Invoiceverification
Activityacceptance
Extension of service
specifications
Bid invitation
Vendor selection
Activityentry
Invoice
?? _ _ _ _
PO
Entry of quotation
Service
activities
Service
activities
PO
Component MM-SRV supports the entire cycle of bid invitation, award of contract, and entry and
acceptance of services.
Unlike externally processed activities, goods receipt is broken down into two steps:
Entry of services performed
Acceptance of services performed
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 165/312
© SAP AG PLM220 5-13
SAP AG 2003
Details - Service Operations
Extnl
0010
Internal Dates Assignments Long txt User fields
Activity Check by external suppliers
External processing
System status
WBS element
Info rec
Vendor
Outl. agreement
Price DEM
Planned del. time
Activity quantity
Cost element FixPrice
Received
Requisition
Res./Purc. req. From release
CRTD Control key Subntwk exists
Purc. ord. exists Service exists
Project sum.
Material groupPurchasing org.
Purchasing group Sort string certificat
Requisitioner
Recipient
Req. tracking no
Executn factor
Unloading point
PReq Invoic. plan Settlement rule Plan/act. costsService
PS05
LE
You can access the details for service activities from the "External" tab page. Here you can distinguish
between service and external activities using the control key and the "Service exists" indicator. In the project planning board and network maintenence, use the "Service" push-button to maintain service
specifications, services, and limits. In the Project Builder use the context menu.
In Customizing for the network, you can define the following default values for service activities in the
network profile: Control key, cost element, material group, purchasing group, and unit of measure.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 166/312
© SAP AG PLM220 5-14
SAP AG 2003
Service Specifications
Service sel.
Service specs. outlineExternal check
Cleaning
Outside
Inside
Check
Rework
Short text External check DEM
DEM
Overall value
Overall limitLimits
Services
No limit
Functional Test
Security
Electrical Parts
Voltage
Mechanical Parts
Line
Grouped into
individual levels -
one service specification
per level
Service
specifications withindividual
items
Short text
for outline
level
Item Del. Ind. Service number Short text Quantity Un
You can call up an outline of levels and service specifications for the activity via the detail screen of a
service activity.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 167/312
© SAP AG PLM220 5-15
SAP AG 2003
Service Entry With CATS
Personnel number
Data entry period
Cost cntr
Week
20.12
20.12 21.12
21.12 22.12
22.12 23.12
23.12 24.12
24.12 25.12
25.12 26.12
26.1227.12
27.12
Total
Total
A/ATyService number
Short textSOp.
Op.
Op.
Network
Network
Item
Item
PO no.
PO no.
Ti
45000017
45000017 10
10
902198
902198
1000
1000 Final check
800E-1301 5 4
45000017 20 902200 2000 E-1302 800 2 2
Services performed can on the one hand be entered and processed in the Service Entry transaction in
Purchasing. You can also use CATS for entering services. In IDES, entry profile 1306 is available forthis purpose.
As of Release 4.6, you can use other units of measure, not just hours. Note that previous releases only
support recording times with CATS. For this reason, they can only be used to record services that use
"time" as a base unit of measure.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 168/312
© SAP AG PLM220 5-16
SAP AG 2003
Customizing External Activities
• Collective purchase requisition indicator
• Workflow for purchase order change indicator
• Acct. assgmt. gen.: F
• Acct AssCat projects: Q
• AccAssCat Sales Order: E
• Sales doc.
- settlement to project: D
• External activity: PS02
• Service: PS05
• New indicator:
External activity scheduling
Account assignment category
purchase requisitionControl key
Parameters for network type
The account assignment categories for purchase requisitions are generally valid for external procurement
in Project System. Only the general account assignment category is relevant to externally processed andservice activities. The remaining account assignment categories, however, refer to project stock that only
affects material procurement.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 169/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 170/312
© SAP AG PLM220 5-18
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 171/312
© SAP AG PLM220 5-19
Exercises
Unit: External Services
Topic: External Services
• Planning and purchasing external services
• Planning and purchasing services
Your project will not only provide internal services. You will also purchase services from external suppliers and use externally processed
activities and service activities. In the first section of the exercises, you
will create two externally processed activities and purchase services. Inthe second section, you will plan a service activity and purchase services.
1-1 Call the Project Builder.
1-1-1 Create an externally processed activity for the top WBS element.
Enter the following data on the detail screen:
Field Name Values
Long text External appraisal
Purchasing org. 1000
Purch.group 001
Material group 00107 (other)
Vendor 1000
Price EUR 150
Plnd dely time 5
Activity qty 12 hours
Res./Purc. req. Immediately
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 172/312
© SAP AG PLM220 5-20
1-1-2 Create a second externally processed activity. This time, you do not need to
enter the detail information manually, instead use a prepared purchasing inforecord.
Create the activity for the WBS element T-100##.5 Production.
Enter the following data on the detail screen:
Field Name Values
Text External acceptance
Info record 5500000057
Modify the activity quantity. Plan 42 hours. Ensure that a purchase requisition
is written when you save the data.
When you save your entries, the purchase requisitions are generated for both
externally processed activities.
1-1-3 Display the purchase requisitions for your project.
Enter your project T-100## on the initial screen and call the report.
An overview of all purchase requisitions for the project appears. Assign a fixed
vendor to the purchase requisition for the External appraisal activity. Choosevendor 1000.
You can also display details on the purchase requisition. Select the
purchase requisition and choose Display requisition.
1-1-4 Create a purchase order for your project. To do so, use collective processing in
Purchasing.
Enter the number of your network in the Network field on the initial screen. To
find the number, use the matchcode search for the project definition.
An overview of purchase requisitions for the network appears, sorted accordingto vendors.
Check the purchase requisitions.
Create a purchase order.
A dialog box with information on creating the purchase order appears.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 173/312
© SAP AG PLM220 5-21
An overview is displayed showing the existing purchase orders and open
purchase requisitions on the left. The details of the new purchase order areshown on the right. Copy your purchase requisitions and save the purchase
order.
The purchase order number is displayed in the status bar (lower part of the
window). Make a note of the number: _________________
Exit the purchase order and the report.
1-1-5 Before you enter a goods receipt, you must release the activities (the goods
receipt is valuated in IDES - actual data can only be entered if the status of theactivity allows it). Check the status of the activities and, if necessary, release
them (since you released the project in a previous exercise, the status should
have been inherited).
Use the Project Builder again. Check the status of activities 5040 Externalappraisal and 5050 External acceptance of services performed .
1-1-6 Enter a goods receipt for your purchase order. Do not enter the entire purchase
order quantity.
Enter the following data on the initial screen:
Field Name Values
Purch.order Your order number
The data from the purchase order is copied as default values. Reduce the
quantities and select the OK indicator. Post the goods receipt.
The number of the goods receipt posting appears in the status bar.
1-1-7 Analyze the purchase requisitions for your project. Call the report Purchase
order for project in the information system of Project System.
Enter your project on the initial screen, and execute the report.
You should now be able to see the purchase order with two items and the
quantities still to be delivered.
Exit the report.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 174/312
© SAP AG PLM220 5-22
1-2 In this section of the exercises you will plan a service activity, and enter and accept
services.
Once again, start from the Project Builder.
1-2-1 Create a service activity for the WBS element T-100##.5 Production.
Name the new activity Service and assign purchasing group 001.
The new activity is created and the system calls the service specifications for
the service activity.
Enter values for the limits of unplanned services. Use the following data:
Field Name Values
Overall limit No limit indicator Select
Expected value EUR 10,000
You can now enter the planned services in the Services section. Refer to theservice master and use the following data:
Field Name Values
Service number E-1301
Quantity 15
Check whether a price is entered for each service unit.
If no price is entered, enter the value 250 in the Gross price field.
Exit service specifications processing.
Check the status of the activity. If necessary, release the activity (so that you
can post the service entry at a later stage).
Save your project.
What is the purchase order number? ___________
Exit the Project Builder.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 175/312
© SAP AG PLM220 5-23
1-2-2 Order the service for your project from vendor 1000. The purchasing group
responsible is group 001.
Enter the following data for the purchase order:
Field Name Values
Purchase requisition (on the farright of the table)
The purchase requisition forthe service activity
Requisition item 10
You can of course still change the order data. To do so, edit the Services section
for the item. Save the purchase order.
What is the purchase order number? _______________
1-2-3 Enter the services for the service activity purchase order. Then accept the
activity.
Create an entry sheet for your purchase order.
Enter the following data in the header that appears:
Field Name Values
Short text Group ##, sheet 1
External number ##
You can now enter services manually. This is, however, time-consuming.
Instead, copy the services from the purchase order service specifications. Onlyenter part of the services.
Reduce the service entered by 5 service units and save the service entry.
Until now, you have only entered services, not accepted them. The actual datafor the services provided is only updated in the service activity when it is
accepted. Accept the services.
Save the changed data. Note the message in the status bar.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 176/312
© SAP AG PLM220 5-24
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 177/312
© SAP AG PLM220 5-25
Solutions
Unit: External Services
Topic: External Services
• Planning and purchasing external services
• Planning and purchasing services
Your project will not only provide internal services. You will also purchase services from external suppliers and use externally processed
activities and service activities. In the first section of the exercises, you
will create two externally processed activities and purchase services. Inthe second section, you will plan a service activity and purchase services.
1-1 Call the Project Builder and create two externally processed activities for the top WBS
element of your project T-100##.
SAP menu
Logistics Project System Project Project Builder
(Select Project Builder by double-clicking)
Drag and drop your project from the worklist to the structure tree.
1-1-1 Create an externally processed activity for the top WBS element.
In the templates area, expand the Individual objects section and then the
Activity section.
Drag and drop the External processing object to the top WBS element in thetree structure.
The new activity has been created. You can store the exact planning data on the
detail screen for the activity.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 178/312
© SAP AG PLM220 5-26
Enter the following data on the detail screen:
Field Name Values
Long text External appraisal
Purchasing org. 1000
Purch.group 001
Material group 00107 (other)
Vendor 1000
Price EUR 150
Plnd dely time 5
Activity qty 12 hours
Res./Purc. req. Immediately
Select Enter to confirm your entries.
1-1-2 Create a second externally processed activity. This time, you do not need to
enter the detail information manually, instead use a prepared purchasing info
record.
Create the activity for the WBS element T-100##.5 Production.
Drag and drop the External processing object to the WBS element Production in the tree structure.
Enter the following data on the detail screen:
Field Name Values
Text External acceptance
Info record 5500000057
Select Enter to confirm your entries.
Select Continue to confirm.
Modify the activity quantity. Plan 42 hours. Ensure that a purchase requisition
is written when you save the data.
Enter 42 hours in the Activity quantity field.
Confirm your entries and save the project.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 179/312
© SAP AG PLM220 5-27
If a warning message appears, confirm it.
When you save your entries, the purchase requisitions are generated for both
externally processed activities.
1-1-3 Display the purchase requisitions for your project.
SAP Menu
Logistics Project System Information System Material Purchase
Requisitions For Project
(Choose the report by double-clicking it)
Enter your project T-100## in the field and call the report.
Choose Execute.
An overview of all purchase requisitions for the project appears. Assign a fixed
vendor to the purchase requisition for the External appraisal activity. Choose
vendor 1000.Select the purchase requisition and select Assign manually.
Enter the value 1000 in the Fixed vendor field.
Confirm your entries by selecting Assign supply source.
You can also display details on the purchase requisition. Select the
purchase requisition and choose Display requisition.
Save the changed purchase requisition by selecting Change requisitions.
Select Back to exit the report.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 180/312
© SAP AG PLM220 5-28
1-1-4 Create a purchase order for your project. To do so, use collective processing in
Purchasing.
SAP Menu
Logistics Materials Management Purchasing Purchase Order
Create Via Requisition Assignment List
(Choose the transaction by double-clicking it) Enter the number of your network in the Network field on the initial screen. To
find the number, use the matchcode search for the project definition.
Confirm the entries and execute the report.
Choose Execute.
An overview of purchase requisitions for the network appears, sorted according
to vendors.
Check the purchase requisitions.
Position the cursor on vendor 1000.
Select Reqs per assignment .
Return to the overview.
Select Back .
Create a purchase order.
Position the cursor on vendor 1000.
Select Process assignment .
A dialog box with information on creating the purchase order appears.
Select Continue to confirm the information.
An overview is displayed showing the existing purchase orders and open
purchase requisitions on the left. The details of the new purchase order are
shown on the right. Copy your purchase requisitions and save the purchaseorder.
Keep the Control key pressed and select the purchase requisitions. Choose
Copy.
Save the purchase order.
Choose Save.
The purchase order number is displayed in the status bar (lower part of the
window). Make a note of the number: _________________
Exit the purchase order and the report.
Select Back twice.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 181/312
© SAP AG PLM220 5-29
1-1-5 Before you enter a goods receipt, you must release the activities (the goods
receipt is valuated in IDES - actual data can only be entered if the status of theactivity allows it). Check the status of the activities and, if necessary, release
them (since you released the project in a previous exercise, the status should
have been inherited).
Use the Project Builder again. Check the status of activities 5040 External
appraisal and 5050 External acceptance of services performed .
SAP menu
Logistics Project System Project Project Builder
(Select Project Builder by double-clicking)
Drag and drop your project from the worklist to the structure tree.
Call the detail screen for the activities.
If necessary, choose Edit → Status → Release in the menu.
Save the changes.
Choose Save.
1-1-6 Enter a goods receipt for your purchase order. Do not enter the entire purchase
order quantity.
SAP Menu
Logistics Materials Management Purchasing Purchase Order
Follow-On Functions Goods Receipt
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Purch.order Your order number
Enter your purchase order number on the right of the Purchase order field.
Choose Enter to confirm your entries.
The data from the purchase order is copied as default values. Reduce the
quantities and select the OK indicator. Post the goods receipt.
Enter your changes for each item. To change to a different item, select the
item you just edited. The next item is then ready for input.
Select Post .
The number of the goods receipt posting appears in the status bar.
Select Back to exit the transaction.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 182/312
© SAP AG PLM220 5-30
1-1-7 Analyze the purchase requisitions for your project. Call the report Purchase
order for project in the information system of Project System.
SAP Menu
Logistics Project System Information System Material Purchase
Orders For Project
(Choose the report by double-clicking it) Enter your project on the initial screen, and execute the report.
Choose Execute.
You should now be able to see the purchase order with two items and the
quantities still to be delivered.
Exit the report.
Select Back .
1-2 In this section of the exercises you will plan a service activity, and enter and accept
services.
Once again, start from the Project Builder.
SAP menu
Logistics Project System Project Project Builder
(Select Project Builder by double-clicking)
Drag and drop your project from the worklist to the structure tree.
1-2-1 Create a service activity for the WBS element T-100##.5 Production.
In the templates area, expand the Individual objects section and then the
Activity section.
Drag and drop the Activity (service) object to the WBS element T-100##.5
Production in the tree structure.
Name the new activity Service and assign purchasing group 001.
Enter the appropriate values in the Text and Purchasing group fields.
Select Enter to confirm the entries.
The new activity is created and the system calls the service specifications for
the service activity.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 183/312
© SAP AG PLM220 5-31
Enter values for the limits of unplanned services. Use the following data:
Field Name Values
Overall limit No limit indicator Select
Expected value EUR 10,000
Select Enter to confirm your entries.
You can now enter the planned services in the Services section. Refer to the
service master and use the following data:
Field Name Values
Service number E-1301
Quantity 15Confirm your entries.
Check whether a price is entered for each service unit.
If no price is entered, enter the value 250 in the Gross price field.
Exit service specifications processing.
Select Back .
The detail screen of the service activity appears.
Check the status of the activity. If necessary, release the activity (so that youcan post the service entry at a later stage).
Choose Edit Status Release.
Save your project.
Choose Save.
Confirm the scheduling warnings that appear.
Call the Project Builder again to determine the purchase requisition number.
The service activity detail screen contains this number.
What is the purchase order number? ___________
Exit the Project Builder.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 184/312
© SAP AG PLM220 5-32
1-2-2 Order the service for your project from vendor 1000. The purchasing group
responsible is group 001.
SAP Menu
Logistics Materials Management Purchasing Purchase Order
Create Vendor/Supplying Plant Known
(Choose the transaction by double-clicking it) In the Vendor field enter the value 1000 and confirm by choosing Enter.
If necessary, enter purchasing group 001 on the Org. data tab.
Enter the following data for the purchase order:
Field Name Values
Purchase requisition (on the far
right of the table)The purchase requisition forthe service activity
Requisition item 10
Select Enter to confirm your entries.
You can of course still change the order data. To do so, edit the Services sectionfor the item. Save the purchase order.
Choose Save.
The purchase order number appears in the status bar.
What is the purchase order number? _______________
Select Back .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 185/312
© SAP AG PLM220 5-33
1-2-3 Enter the services for the service activity purchase order. Accept the activity.
SAP Menu
Logistics Materials Management Purchasing Purchase Order
Follow-On Functions Service Entry Sheet Maintain
(Choose transaction by double-clicking it)
Create an entry sheet for your purchase order.
Select Other purch. order.
Enter your purchase order number and select Continue.
Select Create entry sheet .
Enter the following data in the header that appears:
Field Name Values
Short text Group ##, sheet 1
External number ##
You can now enter services manually. This is, however, time-consuming.Instead, copy the services from the purchase order service specifications. Only
enter part of the services.
Select Service selection.
Enter your purchase order and select Continue.
An overview of the service specifications from the purchase order appears.
Select a line and copy it to the service specifications screen.
To copy, select Adopt services.
Reduce the service entered by 5 service units and save the service entry.
Choose Save.
Until now, you have only entered services, not accepted them. The actual data
for the services provided is only updated in the service activity when it isaccepted. Accept the services.
Select Display/Change.
Choose Save.
Save the changed data. Note the message in the status bar.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 186/312
© SAP AG PLM220 5-34
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 187/312
© SAP AG PLM220 6-1
SAP AG 2003
Material: Contents
Assignment of material components to activities
Purchasing and production of components in theproject.
Delivery of material from the project
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 188/312
© SAP AG PLM220 6-2
SAP AG 2003
Assign material to the activity and carry out theBOM transfer
Process purchase requisitions and purchaseorders
Carry out requirements planning for projects
At the conclusion of this unit, you will be able to:
Material: Unit Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 189/312
© SAP AG PLM220 6-3
SAP AG 2003
Material: Overview
CourseOverview
ProjectStructures
Scheduling
Capacities
ExternalServices
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 190/312
© SAP AG PLM220 6-4
SAP AG 2003
Material: Business Scenario
The turbine you are manufacturing in your projectis made up of a variety of components, which inturn consist of further components. Procure thecomponents required by purchasing them orproducing them in your facilities. Also ensure thatthe turbine is delivered to your customer.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 191/312
© SAP AG PLM220 6-5
SAP AG 2003
Material in the Project
Sales order Sales order
TurbineTurbineTurbine
Generator Generator Generator
CableCableCable
CasingCasingCasing
GearboxGearboxGearbox
RequirementsRequirementsRequirements
ProcurementProcurementProcurement AssemblyAssemblyAssembly
DeliveryDeliveryDelivery
Materialsplanning
Purch.
Purch.
Production
Assembly processing
Controlling the project, or the project stock indicator
1
2
1
2
Materials link projects to Sales and Distribution, Materials Management (Purchasing and Inventory
Management), and to Production Planning and Control.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 192/312
© SAP AG PLM220 6-6
SAP AG 2003
Integration with MM and PP
MaterialMaterialMaterial
Reservation(MRP)
Purchaserequisition
Stock item(L)
Non-stockitem (N)
Material required for carrying out an activity or for
manufacturing the product
Definition
Item category
PPPP MMMM MMMM
To plan the material requirements for a particular project, you assign material to the activities. The
system differentiates between stock items (item category L) and non-stock items (item category N).
Stock items are entered for materials that are kept in stock, (warehouse, sales order, or project stock).
Reservations are generated for stock items.
Non-stock items are entered if materials are to be procured directly for the network (that is, not using
MRP). Purchase requisitions are created for non-stock items. These requisitions are passed on directly to
Purchasing.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 193/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 194/312
© SAP AG PLM220 6-8
SAP AG 2003
Selecting the Procurement Type (1)
Selection depends on the material, the item category, and the project definition.Default values are set using procurement indicators.
Choose
Material E-1317
Cabin door
Purc. req. f. network
Third-party order
Purchase requisition
Choose
Material
Reservation
E-1500B
Engine unit 50 kVA
Reserv. for network
Planned ind. reqmts
Reserv. WBS element
Plnd ind. reqs WBS el.
PReq + Res - WBS elem.
Prelim. PReq - WBS el.
3rd party req. WBS el.
Stock item(Inventory Management)
Non-stock item(No Inventory Management)
The way in which components are procured depends on a variety of settings. The item category of the
component assignment is one key indicator. You have two options. If you do not want to include thecomponents in Inventory Management but want to use them immediately in the network, choose the item
category Non-stock item (N). However, if you want to post the components to a warehouse (in other
words increase stock), and use the components in the network at a later stage, choose item category
Stock item (L). Variable-size items are also available, for example.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 195/312
© SAP AG PLM220 6-9
SAP AG 2003
Selecting the Procurement Type (2)
Item category:Item category:Stock item/non-stock item
Material:Material:Sales order/collective stock, or bothInternal/external procurement, or bothWith or without mixed MRP
Project definition:Project definition:With or without project stock
BOM:BOM:Special procurement key
Sales order:Sales order:With or without sales order stock
1
2
3
4
5
The way in which components are procured depends on both the item category and the attributes of the
material. The material master stores information on whether:
The material is purchased or manufactured internally (or both)
Individual or collective requirements (or both) are possible for the material
The material can be procured in advance
The project definition's control data determines whether stocks can be built up for your project.
The account assignment category of the sales order determines whether sales order or project stocks can
be built up.
You can define a setting within the BOM to specify that the components are to be procured
independently of the material master settings.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 196/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 197/312
© SAP AG PLM220 6-11
SAP AG 2003
Projectrouting
Routing
Networkafter BOMtransfer
MaterialBOM
ProjectBOM
WBS BOM and Project Routing
1010
2020
30301010
2020
3030
4040
MRP run+ Convert the
planned orders------------------------------
Production order (according to projectrouting)
MRP run+ Convert the
planned orders------------------------------
Production order (according to projectrouting)
Project bills of material are BOMs that are valid for a particular WBS element. You can create a project
BOM by copying a material BOM or another project BOM. You create and edit project BOMs in themaster data for the Production component.
You can assign project BOMs to projects using the BOM transfer transaction. To do so, you must select
the corresponding indicator on the selection screen.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 198/312
© SAP AG PLM220 6-12
SAP AG 2003
Bill of Material Transfer
130*, 1310
Reference points(* = wildcard)
T-20000
T-20210(1302)
T-20300(1310)
T-20200
T-20220(1302)
T-20230(1302)
T-20300(1310)
120012001200
100010001000 500050005000
200020002000
130013001300
110011001100
3000(130*)
30003000(130*)(130*)
3100(1310)
31003100(1310)(1310)
400040004000
T-200##Turbine
TT--200##200##TurbineTurbine
WBS elements, activities(project view)
WBS elements, activities(project view)
PSPSBOM
(product view)
BOM(product view)
T-20300(1301)
PDM
The logical link between a BOM component and a network activity is called the reference point, and is
essential for ensuring the correct automatic assignment of a material component.
The assignments themselves are project-specific, but can be made simultaneously for a large number of
networks in the project. You can assign individual components, individual BOM assemblies, or a multi-
level BOM. You can assign components manually without reference points.
Procedure:
Specify which field in the BOM and network activity is to be used as a reference point. These fields
must have the same structure in both objects (example: CHAR, eight digits). As of Release 4.6, both
the BOM and network contain a field called Reference point . You can define possible entries for this
field in Customizing.
Define reference points in the BOM components and the network activities.
Once you have made changes to the BOM, start the BOM-PS interface.
During this process, BOM components are assigned to activities.
If the Reservation/purchase req. indicator is activated, purchase requisitions and reservations are
created for the assigned components.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 199/312
© SAP AG PLM220 6-13
SAP AG 2003
Selection Parameters of the BOM Transfer
Plant
Restrictions
BOM usage
BOM application
Reqts Qty
Multi-level
All items
External data
Display log from
Material BOM
Sales order BOM
Project BOM
Preliminary requirements
Availability check
No dialog
Plant stock
Project stock
Sales order stock
GeneralBOMtype
Stocksegments *
* = Cannot be preassigned using the profile,but using procurement parameters
BOMexplosion
All itemsor only those with
reference point
Detailed constraintsof the BOM
Preliminarypurchase order or real
requirements
Most of the selection parameter settings for the BOM transfer can be pre-assigned in the BOM transfer
profile in Customizing. The priorities for the stock segments and the selection date for all logs, cannot be pre-assigned, however.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 200/312
© SAP AG PLM220 6-14
SAP AG 2003
Customizing the Reference Points
BOM transfer data fields
BOM
Network
RFPNT
RFPNT
Reference point for BOM transfer
Reference point Description
Procurement for production general
Procurement for production 1
Procurement for production 2
Procurement plant components
Production assembly items
Assembly
1
2
As of Release 4.6, you can predefine the description and definition of the reference points in
Customizing. This gives you the advantage of being able to find reference points using a matchcodesearch. You can no longer enter reference points that do not actually exist.
As of Release 4.6, there are special table fields for reference points in the network and the BOM. As in
earlier releases, you can, however, still determine which table fields are to be used as reference points.
You define this setting in Customizing rather than in the BOM transfer transaction used in earlier
releases.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 201/312
© SAP AG PLM220 6-15
SAP AG 2003
MaterialMaterialMaterial
Direct Procurement, Non-Stock Items
“N”
Material procured directly using theactivity
Purchaserequisition
Bidinvitation
Entry of quotation
Vendor selection
Purchaseorder
processing
Purchaseordermonitoring
.
Invoiceverification
Item category
"N"Goodsreceipt
Non-stock item (N):
The item category "non-stock item" ("N") is used for components that are not procured using warehousestock, project stock, or sales order stock, but are procured directly by the network activity.
Purchase requisitions are created for these components. These requisitions are passed on directly to
Purchasing. When the goods are received, they are not placed into stock, but posted to the activity.
Non-stock items cannot be managed as project stock or sales order stock.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 202/312
© SAP AG PLM220 6-16
SAP AG 2003
Assigning Non-Stock Items
Overall Purch.
Components
Itm Material Plant Quantity UM Procurement Item cat R es. St.lo. Description Reqs date ST FD RD
Cabin door
Engine Unit
General Data Purchasing data Proc. param. Long text
PReq Invoicing plan Unit costing Procurement PS text
Req.tracking no
Purchasing data
PReq
Reqts Qty
Requirements date
Time interval
Purchasing group
Info rec
Outl. Agreement
Vendor
Material group
Requester
Unloading point
Purc. Org.
Purc. req. f. network
Costing
UnitCost
Manual reqs. date
Align. finish date
Align. Startdate. Comp
Price/currency
Price unit
UNI
FixPrice
G/L account
GR proc. time DelTime (T)
Sort string
Recipient
1002
If you choose direct procurement with item category N, you can choose between two procurement types:
Either purchase requisition for the network or third-party requisition for the network . The procurementtype is displayed on the Purchasing data tab on the detail screen for the assigned component. You can
change the procurement type at a later stage.
The purchase requisition number is displayed on this tab. You can call the purchase requisition directly
from here. If a purchase order is already available, its number is displayed on the Procurement
parameters tab. You can also call the purchase order from here.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 203/312
© SAP AG PLM220 6-17
SAP AG 2003
Purchasing Process
Purch. req. for project
Purch. req. for project
Purch.order for
project
Purch.order for
project
Here you can:Assign the vendor and info record, change the purchase requisition,call the stock/requirements list, create the purchase order
Here you can: Change your purchase order
S C R OTy. I A Ordered quantity Un Release date Trackg. no. SPl. MC
Network
Material Short text PGp Mat. gp.PReq Item Requested qty. Un Deliv. date Requester Plnt SLoc
Info rec Purch. org.Vendor
Cabin door
Still to be invoiced
PO Type Vendor Name PGp Order date
Item Material Short text PGp Mat. gp.D I A Plant SLoc Order qty. Un Net price Curr. per Un
NB Schmidt AGCabin door
Network
Still to be delivered
As soon as you have activated the requirements in your network (for the entire network, the individual
activity, or the individual component), a purchase requisition is generated when you save data. You cananalyze all purchase requisitions for your project in the information system. In the Purchase requisitions
for the project report, you can analyze the purchase requisition, assign vendors, and create purchase
orders for the purchase requisition.
In the Purchase orders for the project report, you can check and change all purchase orders for your
project.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 204/312
© SAP AG PLM220 6-18
SAP AG 2003
Procurement Using Requirements Planning, StockItem
Material component procured usingrequirements planning.
Reservations are generated for stock
items.
Item category
“L”
Materialreservation
MRPrun
Plnd order/
Preq
ConvertPlnd order/
Preq
Order/purch. orderprocessing
Warehouse
receipt
Materialwithdrawal
MaterialMaterialMaterial
“L”
The stock item (L) item category is used for components kept in stock. When you save, the system
creates a reservation for the required material.
The main function of material requirements planning is to ensure material availability (in other words, to
procure the required quantities on time - both in-house and for sales). This includes monitoring stocks
and, above all, creating procurement proposals for purchasing and production.
Independent requirements (requirements for finished products, saleable assemblies, trading goods and
spare parts) trigger requirements planning. In order to cover the requirements, order quantities and dates
have to be determined, and the corresponding procurement elements scheduled. The procurement
element for requirements planning is a planned order and, for external procurement, a purchase
requisition. Dependent requirements are determined by exploding the bill of material for materials
produced in-house to determine the quantity of components required to manufacture a finished product
or assembly. Planned orders are created at each BOM level to cover requirements when a material
shortage occurs.
Once quantities and dates have been planned in requirements planning, these planned procurement
elements are converted to "exact" procurement elements: For production, this is the production order
and, for external procurement, the purchase order.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 205/312
© SAP AG PLM220 6-19
SAP AG 2003
Assigning Stock Items
T-20600
1
1 10.01.2000Warehouse unit comp.
Overall Purch.
Components
Itm Material Plant Quantity UM Procurement Item cat R es. St.lo. D escription Reqs date ST FD RD
Cabin door
Engine Unit
Committed quantity
General Data
General Data
Proc. param Long text
Reqts Qty
Requiremts date
Reservation
Recipient
Unloading point
Time interval
Withdrawal quantity
13406 1 Reservation for WBS element
Manual req. date
Algn.start date.comp
Align finish date
CostRel
UnitCost
Storage location
Batch
Sort string
ProcurementUnit costing
1 PC
10.04.2000
On the detail screen of component assignment for stock items, you can select the General data tab to
change the requirements date, check the withdrawal and confirmed quantity, and check the reservationnumber. On the Procurement parameters tab you can determine when the reservation will take effect for
planning.
The reservation either takes effect a) immediately, b) after release, or c) never. Case c) is possible as of
Release 4.6. This enables you to release the activity but leave the reservation inactive for planning. You
can make the reservation active for planning at a later stage.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 206/312
© SAP AG PLM220 6-20
SAP AG 2003
Stock Item with BOM
Goods issueProduction order
Purchasingcomponents
Goods receipt for purchase order
Production
T-20620T-20620
Production
order for T-20600
Production
order for T-20600
101010
T-20600TT--2060020600
T-20000-1TT--2000020000--11
T-20610T-20610 T-20630T-20630
Goods issuenetwork activity(consumption)
DeliveryProduction order
Vendor 1000
T-20000TT--2000020000
Planned order anddep. requirementsw. planned orders
or purch. req.
Convert plannedorder into prod.
order
MRP run
Assign materialto activity
Create reqs
In the sample process displayed, material T-20600 produced in-house is assigned to activity 10 in a
project with valuated sales order or project stock. To procure dependent requirements for the material, arequirements planning run is carried out. The dependent components are then purchased and consumed
by the production order. The production order is processed and material T-20600 posted to stock. The
process ends with T-20600 being issued from the project stock and the network activities being
confirmed.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 207/312
© SAP AG PLM220 6-21
SAP AG 2003
Material: Stock/Requirements List
Additional Data for MRP Element
Reservation
Reqts Qty
Pegged reqmt
Network
Requirements date
Latest req. date
13406 1
1 PC
902703 10 Activity
10.04.2000
10.04.2000 DKey
ST
Material
Planning area
Plant
T-20600
1300
1300
Bearing box
1300 (Frankfurt)
MRP type Material typePD SEMI Unit PC
Date MRP el. MRP element data Resched.Except. Acquis. Avail. qty
10.01.2000
10.01.2000
10.04.2000
Stock
PrdOrd
AR-RES
T-20000 -1
902703
0
0
1-1-
Vendor Customer OnGRDat
The current stock/requirements list shows the current stock/requirements situation for a material. This
evaluation is contained in Project System under Info system -> Material .
Each time the list is set up, the system reads and displays the various MRP elements. This means that the
list always shows the up-to-date availability situation for the material. Changes made after the planning
date are shown directly. The list is therefore dynamic. Stock/requirements lists are not stored in the
system, only in the working memory.
From this list, you can display and change the individual objects that generate and cover requirements,
you can display the associated master data, and convert planned orders to production orders or purchase
orders, for example.
As of Release 4.6A, you can access the stock/requirements list not only by entering individual material
numbers, but also using collective access - that is, by entering a product group, class, MRP controller,
vendor, or production line.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 208/312
© SAP AG PLM220 6-22
SAP AG 2003
MRP Run for Project
Project definition
WBS element
With hierarchy
T-20000
MRP control parameters
Create pur. req.
Planning mode
Schedule lines
Scheduling
1
1
3
1
Process control parameters
Also plan unchanged components
Display results
Display material list
Materials planned
Materials with new exceptions
Materials with terminated MRP listParameters
Statistics
Database statistics
Hit list of the materials with the longest CPU times (in ms)
Runtime Read Net CPU time BOM LdTmeSched Update
Planned orders createdDependent requirements created
Material MRP area Plant
The MRP run for the project differs from the standard planning run. When the MRP run is carried out for
the project, all components for the project are selected (as long as you select them using the projectdefinition and not using sub-hierarchies). The MRP run generates the dependent requirements of
components with a BOM and generates a procurement element for these dependent requirements.
In the example above, material T-20600 was assigned to the project. The MRP run generates a planned
order for the reservation. Since T-20600 has a BOM with three components, the MRP run generates
reservations for the corresponding dependent requirements and generates three more planned orders.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 209/312
© SAP AG PLM220 6-23
SAP AG 2003
Material for the Production Order
T-20620T-20620
Productionorder
T-20600
Productionorder
T-20600
101010
T-20600TT--2060020600
T-20000-1TT--2000020000--11
T-20610T-20610 T-20630T-20630
Vendor 1000
T-20000TT--2000020000
Purchasingcomponents
Goods receipt for purchase order
Goods issuefor production
order
Production order
Plan Act.
E V10 3000
M T-20610 600 600M T-20620 2000 2000M T-20630 100 100
å 5700 2700
Goods are received for the purchase orders for components T-20610, T-20620, and T-20630. The goods
receipt increases the project stock of the materials. The goods receipt reduces commitmentscorresponding to the order value and stocks are formed according to the standard costs (for standard
price control) or the order value (for moving price control).
The planned order for T-20600 is converted into a production order. The planned costs for materials are
only displayed for valuated project stock and for collective stock.
The project stocks T-20610, T20620, and T-20630 are consumed by the production order at the price
calculated in valuation. The respective actual costs are debited from the production order.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 210/312
© SAP AG PLM220 6-24
SAP AG 2003
Editing the Production Order
Production
order
Production
order
101010
T-20600TT--2060020600
T-20000-1TT--2000020000--11
Productionorder
Plan Act.
E V10 3000 3500M T-20610 600 600M T-20620 2000 2000M T-20630 100 100
Delivery - 5700 - 5700
∑ 0 500
Production
DeliveryProduction order
Goods issuefor activity
(consumption)
T-20000TT--2000020000
The final confirmation is entered for the production order and material T-20600 is delivered to the
project stock.
This increases the stock value for material T-20600 in project stock by the value of the material project
stock segment.
A goods issue is posted for the network for assembly T-20600.
This reduces the project stock (crediting the WBS element). The actual costs are debited from the
network.
The actual network activity costs are aggregated and displayed for the higher-level WBS elements.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 211/312
© SAP AG PLM220 6-25
SAP AG 2003
Third-Party Purchase Orders
Third-partyPO
Directly for
Customer 1600
Address: XY
Address from:• Central address
management
• Vendor master data• Customer master data
Vendor Customer Directly from vendor to customer
Third-party purchase orders are documents where the purchased material is delivered directly from the
vendor to the customer.
When assigning material components to network activities for which the Third party indicator has been
selected, the system asks you to maintain the address of the customer to which the vendor is to ship the
goods.
You can use addresses from:
- Central address management
- Customer master data
- Purchasing master data
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 212/312
© SAP AG PLM220 6-26
SAP AG 2003
Advance Procurement
I know that I will needcomponent XY sometime in
the future. I should buy it today,since it has a long delivery time.
I still don't know whichactivity I will use the
component for.
Today:Build stock
Later:
Consumestock
Procurement
ConsumptionProcurement
Item category: L=> Planned independent requirements=> Preliminary purchase requisition
Item category: L=> Reservation
In engineering projects, it is common for critical components with long and unreliable delivery times to
be purchased at an early stage in the project, well before the project activities where these componentswill be consumed are specified. Preliminary procurement is used to this end.
You can only use preliminary procurement if you are working with sales order or project stock. This
means that you must use item category L when you assign your components to ensure that stock can be
managed. In order to calculate the requirements for procurement with those of consumption, the
components must be managed internally in sales order or project stock.
The following section distinguishes between two scenarios: Planned independent requirements and
preliminary purchase requisition.
Scenario 1: Assemblies that need to be produced well in advance of consumption can be allocated as
stock-items ("L"), with the planned independent requirement indicator set for the procurement
activity. The MRP run then generates a planned order, which triggers a production process. The production order will be delivered to stock where it will be consumed later by a second allocation to
the consuming assembly activity.
Scenario 2: Assemblies that need to be ordered well in advance of consumption can be allocated as
stock-items ("L"), with the preliminary purchase requisition indicator set for the procurement activity.
The system then generates a preliminary purchase requisition, which triggers a purchasing process.
The goods receipt for the component builds up stock. You can allocate the component later to the
consuming activity (assembly) thus reserving and consuming the stock.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 213/312
© SAP AG PLM220 6-27
SAP AG 2003
Assembly Items
W i t h o u t a s s e m
b l y
i t e m s
100010001000
3100(1310)
31003100
(1310)(1310)
3000(130*)
30003000
(130*)(130*)
4000
(1320)
40004000
(1320)(1320)
5000
(1330)
50005000
(1330)(1330)
T-20210 1
T-20220 1
T-20230 1
100010001000
3100
(1310)
31003100
(1310)(1310)
3000(130*)
30003000
(130*)(130*)
4000(1320)
40004000
(1320)(1320)5000
(1330)
50005000
(1330)(1330)
T-20300 1
T-20400 1
TT--2020020200 --11
T-20220 1
T-20210 1
T-20230 1
TT--2000020000 --11
W i t h t w o a s s e
m b l y
i t e m s
T-20200 1T-20300 1
T-20400 1
Scenario without assembly items:
The components are procured for activities 3000 and 3100. Texts and other data in network activities
describe the assembly of T-20200 (running gear) and product T-20000 (turbine). Quantity flow does
not take place for T-20200 and T-20000.
Scenario with assembly items:
The components T-20210, T-20220, and T-20230 are procured for activity 3000 as dependent
requirements of the assembly T-20200 that are produced in activity 4000. You can carry out receipt
posting by reserving the assembly with a negative quantity after confirmation of activity 4000.
Assembly T-20200 is consumed in activity 5000 - if applicable, together with components T-20300
and T-20400. The product T-20000 is produced in this activity and posted to stock. An SD delivery to
the customer can be created from this stock at a later stage and a goods issue posted.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 214/312
© SAP AG PLM220 6-28
SAP AG 2003
Material Availability Check
Material AMaterial A
Network Checking control Checkingrules
Material Checkinggroup
Which material?When will material
be needed/procured?How much?
Confirm default
Item
Material
Plant
Open quantity
Engine
pc
Confirm. on requested dely dt.
Date
Date
Confirmed quantity
Confirmed quantity
Scope of check
++ --
The availability check is controlled by multi-part checking rules.
Checking rules must be determined for the individual application (for example, requirements planning,
order management) in Customizing.
Checking rules include the following elements:
- Checking group: Assignment in material master (planning data screen)
- Checking rule: Assignment to order type
- Scope of check: Specification of checking details for each checking rule and group
Check times: Checks carried out manually or automatically (at network creation and/or network release)
Checking results: Missing material status or assignment of confirmed quantity
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 215/312
© SAP AG PLM220 6-29
SAP AG 2003
Productionorders
Plannedorders
Purchaseorders
Purchase
requis-itions
Warehousestock
Salesorders
Reser-vations
Plantsegment
Projectsegment
Individualcustomersegment
Secondaryrequirements
Plannedindependentrequirements
Scope of Check
The scope of checking determines which stocks, issues, and receipts will be taken into account in the
availability check. In the ATP check, only receipts that are booked before a requirement (issue) areincluded in the check for this issue. The ATP quantity of a receipt is the quantity that has not yet been
consumed by issues.
A material that is kept in plant stock is not allocated to a specific order and is available for all orders.
From an MRP point of view, sales orders can have their own stock, known as sales order stock. The
sales order stock is allocated to an item in the sales order. You can only withdraw components for the
sales order item.
From an MRP point of view, projects can have their own stock, known as project stock. The project
stock is allocated to a WBS element. You can only withdraw components for the WBS element.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 216/312
© SAP AG PLM220 6-30
SAP AG 2003
Customizing for the Availability Check
Dependent on:
Network type, plant, and
status (CRTD, REL)
Contents:
Will checks be carried out?
Will checks be carried out
when saving?
Which checking rules will
be used?
Dependent on:
Checking group (of the material)
Checking rule (of checking control)
Contents:
Which stocks will be
checked?
What are receipts and
issues?
Will storage locations be
checked?
One name for one rule
Checking control Scope of check
Checking rule
Based on the status, the checking control function determines whether an order type will be checked and
if so, which checking rules will be used. The order type corresponds to the network type in ProjectSystem. The checking rule, however, is just a descriptive text.
The scope of the check is an important factor for the ATP availability check. It is determined using the
checking rule (that was defined previously in checking control) and using the checking group for the
material to be checked. The scope of the check determines how the ATP availability check will be
carried out: What are receipts and issues, which sales order or project stocks are checked? Will storage
locations or entire plants be checked?
The checking group of the material is set in Customizing for Sales and Operations Planning, for
example. It determines whether individual or collective requirements will be generated for the material,
for example.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 217/312
© SAP AG PLM220 6-31
SAP AG 2003
Requirements Grouping
PP --11 PP --22
PP
902100 902110
Mat A:Mat A: 22 Mat A:Mat A: 33
Stock/requirements list for project stock
Stock/requirements list for project stock with requirements
grouping
Date MRP element Quantity
02.02.00 P-BEST P-1 0OrdRes 902100 -2
OrdRes 902110 -3
Material A
02.02.00 P-BEST P-2 0
Pur. ord. 2
Pur. ord. 3
Date MRP element Quantity
02.02.00 P-BEST P 0OrdRes 902100 -2
OrdRes 902110 -3
Material A
Purchaseorder 5
To use requirements grouping, you need:
Valuated project stock
Grouping WBS elements (to which the stock is grouped)
MRP groups that permit requirements grouping (in the material master, MRP view 1)
The assigned components require period lot sizes (material master, MRP view 1) and it must be
possible to keep them as project stock
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 218/312
© SAP AG PLM220 6-32
SAP AG 2003
Background of Requirements Grouping
Max controlMax control
Maximum effectivityMaximum effectivity
11 22 33 44 Project
1 and 21 and 2 3 and 43 and 4
Cross-
project
Plant stockPlant stockIndependentof project
WBS element
Up to now, you managed material either in the plant stock or for each individual WBS element. You
either had no control over procurement, or you were completely in charge. Using requirements grouping,you can determine the level of control yourself.
In the most basic scenario, you group the requirements of all the WBS elements in your project into
one WBS element.
You can also create projects whose only role is to group together the requirements of other projects.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 219/312
© SAP AG PLM220 6-33
SAP AG 2003
Requirements Grouping Options
Project-related Cross-project
MRP element type 1 MRP element type 2
There are different methods for grouping requirements:
You can group requirements within a project (the easiest way of doing this is to group requirements
automatically).
You can group requirements from various projects into one (or more) project. However, the WBS
elements must then be assigned manually.
You can group together all components of a WBS element in one WBS element (which means that
components are assigned to activities that, in turn, are assigned to WBS elements that, in turn, are
grouped)
You can group the components of a WBS element to various WBS elements according to the MRP
group of the components.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 220/312
© SAP AG PLM220 6-34
SAP AG 2003
Settings for Requirements Grouping
Project definition:Valuated project stock
Automatic requirements grouping
WBS elements:Determine MRP elements (type 1 or 2)MRP element assignment
PS Customizing:Determine MRP groups for requirements grouping
Material:Allow individual stockAssign MRP groupAllow periodic lot size
1
2
3
4
Requirements grouping is set up at various points in the system:
Project stock must be permitted in the control data of the project definition. The Automatic
requirements grouping indicator can also be activated for the entire WBS. In this case, the
requirements are grouped under one WBS element (the top-level WBS element).
The MRP element indicator must be set for WBS elements (exception: Automatic requirements
grouping). The MRP element determines whether and how the requirements are grouped under one
WBS element.
In PS Customizing you must determine the MRP groups involved in requirements grouping.
The materials that are to take part in requirements grouping must permit project stock; an MRP group
that allows requirements grouping must be assigned to them; the lot sizes of the materials cannot be
"exact", but must allow a periodic procedure (otherwise several requirements cannot be grouped).
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 221/312
© SAP AG PLM220 6-35
SAP AG 2003
Delivery Information
Delivery address
Delivery information Turbine to customer 1000
Delivery data
Project definition
GI via delivery
Shipping point
Planned GI
Delivery date
Ship-to party
Organizational data
Sales org.
Distribution path
Division
Germany, Frankfurt
End customer sale
For all sectors
Frankfurt
Becker, Berlin
WBS elementWBS element
NetworkNetwork 1)1)
ActivityActivity2)2)
Component
1) If the network is header assigned2) If the network is activity assigned
The delivery information is transferred from the superior object to the subordinate objects. For example:
If a component has no delivery information but the upper-level activity does, this information istransferred to the component. If a subordinate object has delivery information, then it does not take the
information from the superior object. For example: A component and the upper-level activity have
different delivery information. Priority is given to the delivery information that the component already
has.
The dates from the delivery information can be used to filter by component in the Delivery from PS .
If components that have different delivery information are selected in the Delivery from PS , then
individual deliveries are created for these components.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 222/312
© SAP AG PLM220 6-36
SAP AG 2003
Delivery
PPP
P -1PP --11 P -2PP --22
Withdrawalquantity
SD SD
Sales order Sales order Delivery noteDelivery note Pickingand goods issue
Pickingand goods issue
Quantity indelivery
Selection of thematerial
Order data(opti
onal)
Construction siteConstruction site
You can select material components that are to be delivered to the customer, and create an SD delivery
note automatically.
You can select components by specifying the project definition, the WBS element, a sales order, or a
network.
You can limit the selection:
By specifying delivery information that describes the components in greater detail (delivery date, ship-
to party, requirements date, for example)By specifying network data (the activity number, for
example)
By specifying network data (the activity number, for example)
By specifying material characteristics (G/L account, purchase requisition number, for example)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 223/312
© SAP AG PLM220 6-37
SAP AG 2003
Delivery from Project
Quantity/dates Allocations
Delivery items for E-1500
Material Name Outstg Delivery UM Del date Goods iss.Cabin door
Counterbalance
Pump
Bearing box
Delivery from project E-1500
Delivery Delivery date Ship-to party Status
Selection of thecomponents:
• For the project definition• For the WBS element• For the activity• For the sales order
Selection of thedelivery:
• For the project definition
If you deliver from PS, detail screens for each component display the various quantities related to the
component (requirement quantities, item quantities, quantity in delivery, open quantities, available openquantities, for example).
Once the material is selected, the delivery note is created with a reference to the network components.
You can deliver materials from stock, project stock, or sales order stock. Every item in the delivery is
directly related to the reservation or purchase requisition.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 224/312
© SAP AG PLM220 6-38
SAP AG 2003
Delivery Quantities in PS
Special stock
Delivery date
Material Cabin door
Quantities
General Data
Delivery quantity
Reqts Qty
Withdrawal quantity
Qty in delivery
Open quantity
Avail. open qty.
Requirements date
Item
Item category
Storage location
Sort string
Goods issue
Assignmts
Network
Activity
WBS element
Quantity that isto be transferred
to the delivery
Quantity fromthe reservation
Componentswhose goods issue
is posted
Quantity fromdeliveries without
withdrawnquantities
Quantity that muststill be delivered for
requirementscoverage
Open quantitythat can be delivered for the
goods issue acc. to theavailability check
After the material is selected, the delivery note is created with reference to the network component.
If a delivery note (document type LP) is created from a project, every delivery item (item category DLP)
has a direct reference to a reservation or purchase requisition in the network. This is used for availability
checks and for updating actual data for the goods issue.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 225/312
© SAP AG PLM220 6-39
SAP AG 2003
You are now able to:
Assign material to the activity and carry out theBOM transfer
Process purchase requisitions and purchaseorders
Carry out requirements planning for projects
Deliver material from the project
Material: Unit Summary
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 226/312
© SAP AG PLM220 6-40
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 227/312
© SAP AG PLM220 6-41
Exercises
Unit: Material
Topic: Material
• Manual component assignment
• Bill of material transfer
• Purchasing and production
• Monitoring dates
• Delivery from Project System
In the following section, you will work through four individual sets of
exercises. The first set is simple. You will manually assign twocomponents to the project and check them in the information system. In
the second section, rather than manually assigning the components, you
will assign them using BOM transfer. In the third section, you will purchase and produce components. In the final section, you will deliver
components from the project.
1-1 Call the Project Builder and assign two components to activity 3100 Material
procurement plant components for your project T-100##.
1-1-1 Assign the component E-1517 to activity 3100 Material procurement plantcomponents as a non-stock item.
Assign the material in the component overview.
Use the following data for the assignment:
Field Name Values
Material E-1517
Reqts Qty 1
Item category N
A dialog box appears in which you can select the procurement type. Create a purchase requisition for the network.
Display the detail screen of the component.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 228/312
© SAP AG PLM220 6-42
Check the account assignment category for the component.
Which account assignment category has been entered for the quantity/value
flow? ___
When will the purchase requisition be generated? __________
On which date will the component be procured? __________
1-1-2 Assign another material component to the same activity. Assign material E-
1203A as a stock item.
First return to the component overview for the activity.
In the second item, enter the material with the following data:
Field Name Values
Material E-1, 203ARequirement qty 1
Procurement Indicator Delete field contents
Item category L
The dialog box for selecting the procurement type appears again. Create areservation for the WBS element.
Check the account assignment category for the component.
Which account assignment category has been entered for the quantity/value
flow? ___Can the material be purchased? ______
Save the changed data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 229/312
© SAP AG PLM220 6-43
1-1-3 Purchase requisitions and reservations were generated the last time data was
saved. Display the components of your project in the extended individualcomponents overview.
Ensure that the PS info profile YIDES_130000 is chosen for the report.
Change the field selection for the report. Display the following fields in the
report:
Field Name
Material
Material text
Purchase requisition
Requisition item
Requirements date
Requirement quantity
Quantity withdrawn
Account assignment category
Special stock
Exit the report without saving the overview.
1-1-4 Display the component overview in the project planning board.
Display the component overview for all objects of your project.
The procurement dates of the components are displayed in the graphic. Change
the procurement dates. Use the following data:
Component E-1517 7 days earlier
Component E-1203A At the start of the activity
Save your entries.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 230/312
© SAP AG PLM220 6-44
1-2 If you want to assign several components, assigning materials manually can be quite
time consuming. As an alternative, you can assign bills of material (BOMs). Createyour own BOM and assign it to the project.
1-2-1 Create a WBS BOM for the top WBS element of your project. Use the material
BOM T-20000 as a template.
Enter the following data on the initial screen:
Field Name Values
WBS Element T-100##
Material T-20000
Plant 1300
BOM usage 3 (universal)
Use the material BOM T-20000 as a template.
Use the following data when copying the BOM:
Field Name Values
Material T-20000
Plant 1300
Use 3
An overview of the material BOM appears. Choose all components except for
material P-100 and copy the items to the WBS BOM.
Save the WBS BOM.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 231/312
© SAP AG PLM220 6-45
1-2-2 Use the BOM transfer to assign the components of your WBS BOM to your
project activities.
Enter the following data on the initial screen:
Field Name Values
Project definition T-100##WBS element T-100##
Material T-20000
Plant 1300
BOM usage 3
Check the BOM transfer selection parameters.
Use the following parameters:
Field Name Values
WBS BOM Select
Multi-level Select
Plant stock 2
Project stock 1
Call the BOM transfer.
First the results list appears, in which you see all the components that the
system can assign automatically.
Save the assignments.
If necessary, confirm the scheduling warnings.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 232/312
© SAP AG PLM220 6-46
1-2-3 BOMs are often changed during the course of a project. Expand your WBS
BOM to include material P-100 and double the requirement quantity forcomponent T-20100.
Enter the following data on the initial screen:
Field Name Values
WBS Element T-100##
Material T-20000
Plant 1300
BOM Usage 3 (universal)
Enter material P-100 as an additional component with the following data:
Field Name Values
Item category L
Component P -100
Quantity 1
Store another reference point for the components so that they can be assigned
automatically with the BOM transfer. Enter the reference point 1310 Procurement plant components.
Save your entries.
1-2-4 Update the component assignment for your project. Use the BOM transferagain.
Enter the following data on the initial screen:
Field Name Values
Project definition T-100##
WBS element T-100##
Material T-20000
Plant 1300
BOM usage 3
Check the selection parameters of the BOM transfer again.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 233/312
© SAP AG PLM220 6-47
Use the following parameters:
Field Name Values
WBS BOM Select
All items Select
Multi level Select
Plant stock 2
Project stock 1
If you always call the BOM transfer with the same parameters, you
should create a selection profile that contains these settings.
Call the BOM transfer.A dialog box appears as a result of the quantity change in the BOM. Save the
change.
The overview of components that cannot be assigned automatically appears.
The components T-20200, T-20610, T-20620 and T-20630 should be listed
here. Instead of assigning components manually, go to the results list.
The results list appears. The symbols in the first column indicate whether thecomponent is being created, deleted, changed, or reallocated.
Save your entries.
1-3 In the next exercise, you will procure material for your project and use it in the
network. Take component T-20600 that you assigned previously and trace all steps of
its procurement and use in the system.
1-3-1 First display the stock/requirements list for material T-20600.
Enter the following data on the initial screen:
Field Name Values
Material T-20600Plant 1300
You should notice an individual requirements stock segment for your project in
the list with reservation via a unit of the material. Until now, only onerequirement has been generated. However, you need one more procurement
element.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 234/312
© SAP AG PLM220 6-48
1-3-2 Perform a planning run for your project to generate procurement elements. The
best way of doing this is to open a second session so that you can always process the stock/requirements list in one session.
Use the following settings on the initial screen:
Field Name ValuesProject definition T-100##
Create purchase requisition 1
Display material list Select
A results list appears, which also contains the dependent requirements for your project. You have created procurement elements for the requirements. These,
however, are planning procurement elements. You will generate the actual
procurement elements in the next step.
1-3-3 Display the stock/requirements list for material T-20600 and create a production order for your reservation.
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
In the individual stock segment for your project, the list contains a planned
order as well as the reservation.
Convert the planned order into a production order and release it immediately.
Refresh the data selection in the requirements/stock list.
You should now see a production order for your reservation.
Make a note of the production order number: ___________
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 235/312
© SAP AG PLM220 6-49
1-3-4 During the planning run, the system has created requirements and procurement
elements for dependent components. Component T-20600 has requirements for
component T-20610, T-20620, and T-20630. Order the components and post
them to the warehouse.
Suitable purchase requisitions have already been created by the MRP run.
Convert these to purchase requisitions in the information system.
An overview of all purchase requisitions appears. First assign purchase
requisitions automatically to purchasing information records, and then createthe purchase order.
Display the overview of the assignments and then create the purchase order.
The purchase requisitions are sorted in the overview according to their
assignments. You can create new purchase orders by selecting Process
assignment .
The purchase order appears.
On the left-hand side of the overview, select your three purchase requisitionsand copy them to the purchase order.
Save the purchase order.
The purchase order number appears in the status bar.
Make a note of the order number: ____________
1-3-5 The components you ordered have been delivered. Post them to the warehousewith a reference to your purchase order.
Use the following data:
Field Name Values
Purch.order Your order number
OK Activate
StLoc 0001
The components are now in the warehouse, ready to be used in the productionorder.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 236/312
© SAP AG PLM220 6-50
1-3-6 Take the components from warehouse 001 and use them in the production
order.
Post the goods issue.
1-3-7 Once the components for the production order have been withdrawn, the order
can be processed. Confirm the order with the planned quantity. Set the status Final confirmation.
Save the confirmation.
1-3-8 You have posted services to the production order but not yet posted the
completed material T-20600 to the warehouse. Post the goods receipt for your
order.
Enter the following data on the initial screen:
Field Name Values
Transaction type 101
Order Your production order
Plant 1300
StLoc 0001
Copy the default values from the order and post the goods receipt.
1-3-9 Check the stock situation for material T-20600 in your project. Use the
stock/requirements list.
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
The production order should no longer be visible in the list and stock should
now be built up for your project.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 237/312
© SAP AG PLM220 6-51
1-3-10 Use material T-20600 in the project. Remove the material from storage location
0001 with reference to your reservation. The reservation and item number is inthe stock/requirements list or the activity.
Display all reservations for your network and choose those for material T-
20600.
Select component T-20600 and post the goods issue.
1-3-11 Call the stock/requirements list for material T-20600 again.
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
The goods receipt has reduced the individual requirements stock segment for
your project.
1-4 In the final exercise, take a look at the delivery from the project.
1-4-1 Prepare your project for delivery from Project System. Create delivery
information with the Project Builder.
Manually create delivery information for activity 3000 Preliminary orders.
Enter Group## as a description for the delivery information.
Use the following data:
Field Name Values
Project definition T-100##
Shipping point 1300
Planned GI Tomorrow
Delivery date Two weeks from today
Ship-to party 1600
Sales Organization 1000
Distribution path 10
Division 00
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 238/312
© SAP AG PLM220 6-52
Assign the delivery information already available (Group ##) to activity 3100
Material procurement plant components.
Save the changes made to your project.
1-4-2 You can only deliver goods that are available. Post a goods receipt for the
project. Post a pump p-100 to your project stock.
Enter the following data on the initial screen:
Field Name Values
Movement type 501
Plant 1300
Storage Location 0001
Special stock indicator Q (Project)
The screen for entering goods receipts appears. Enter the following data:
Field Name Values
Material p-100
Quantity 1
WBS element T-100##
Post the goods receipt.
You can now call the stock/requirements list for the material in order to checkthe project stock.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 239/312
© SAP AG PLM220 6-53
1-4-3 Create a delivery for goods recipient 1600.
Combine the components for the delivery from your project to recipient 1600.
If a dialog box appears asking you to provide missing information on the
delivery, provide this information.
Confirm warnings that appear regarding missing settings in the material masterof individual components.
An overview of the materials that meet the filter conditions appears. Somecomponents, for example pump p-100, are available in the warehouse and can be delivered. Create a delivery containing the pump.
Check the delivery information again for the component. Select Deliveryinformation.
Check the available open quantity on the component detail screen.
Check the delivery date and goods issue date.
Field Name Values
Delivery date Two weeks from today
Goods issue Tomorrow
Create the delivery.
1-4-4 Process the delivery that you created previously. Post a goods issue.
Enter your project T-100## on the initial screen.
An overview of the deliveries for your project appears. Process the delivery.
Normally, the delivery should now be picked and packed. You can leave outthis step. Post the goods issue directly.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 240/312
© SAP AG PLM220 6-54
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 241/312
© SAP AG PLM220 6-55
Solutions
Unit: Material
Topic: Material
• Manual component assignment
• Bill of material transfer
• Purchasing and production
• Monitoring dates
• Delivery from project system
In the following section, you will work through four individual sets of
exercises. The first set is simple. You will manually assign twocomponents to the project and check them in the information system. In
the second section, rather than manually assigning the components, you
will assign them using BOM transfer. In the third section, you will purchase and produce components. In the final section, you will deliver
components from the project.
1-1 Call the Project Builder and assign two components to activity 3100 Material
procurement plant components for your project T-100##.
SAP menu
Logistics Project System Project Project Builder(Select Project Builder by double-clicking)
Drag and drop your project from the work list to the structure tree.
1-1-1 Assign the component E-1517 to activity 3100 Material procurement plant
components as a non-stock item.
Expand the project definition and the WBS elements Turbine and Purchasing tocall the detail screen of the activity.
Assign the material in the component overview.
Select Component overview.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 242/312
© SAP AG PLM220 6-56
Use the following data for the assignment:
Field Name Values
Material E-1517
Requirement qty 1
Item category N
Select Enter to confirm your entries.
A dialog box appears in which you can select the procurement type. Create a purchase requisition for the network.
Select the Purchase requisition for network indicator.
Select Continue to confirm your entries.
Display the detail screen of the component.
Select the component in the overview and choose General to call the detail
screen.
Check the account assignment category for the component.
Select Procurement parameters.
Which account assignment category has been entered for the quantity/value
flow? ___
When will the purchase requisition be generated? __________
On which date will the component be procured? __________
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 243/312
© SAP AG PLM220 6-57
1-1-2 Assign another material component to the same activity. Assign material E-
1203A as a stock item.
First return to the component overview for the activity.
Position the cursor on activity 3100 in the tree structure.
Select Component overview on the activity detail screen.
In the second item, enter the material with the following data:
Field Name Values
Material E-1, 203A
Requirement qty 1
Procurement Indicator Delete field contents
Item category L
Select Enter to confirm your entries.
The dialog box for selecting the procurement type appears again. Create a
reservation for the WBS element.
Select the Reserv. WBS element indicator.
Select Continue to confirm your entries.
Display the detail screen for the component.
Select the component in the overview and choose General to call the detailscreen.
Check the account assignment category for the component.
Select Procurement parameters.
Which account assignment category has been entered for the quantity/value
flow? ___
Can the material be purchased (see the Procurement field in the Materialmaster data section)? ______
Save the changed data.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 244/312
© SAP AG PLM220 6-58
1-1-3 Purchase requisitions and reservations were generated the last time data was
saved. Display the components of your project in the extended individualcomponents overview.
SAP Menu
Logistics Project System Information System Structures
Enhanced Individual Overviews Components
(Choose the transaction by double-clicking it)
Ensure that the PS info profile YIDES_130000 is chosen for the report.
Select PS Info profile and assign the appropriate profile. Confirm your
entries by selecting Continue.
Call the report for your project.
Enter the project definition T-100## in the Project field.
Choose Execute.
Change the field selection for the report. In the View menu, select the Choose fields… option and display the following fields:
Field Name
Material
Material text
Purchase requisition
Requisition item
Requirements dateRequirement quantity
Quantity withdrawn
Account assignment category
Special stock
Select Continue to confirm your entries.
Exit the report without saving the overview.
Select Back and exit the dialog box without saving.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 245/312
© SAP AG PLM220 6-59
1-1-4 Display the component overview in the project planning board.
SAP Menu
Logistics Project System Project Project Planning Board Change
Project
(Double-click the transaction to select it)
Enter your project in the Project def. field, select W.activities, and choose theOpen project icon.
Optimize the display of your project as before by selecting Zoom in on graphic
and Adapt graphic area .
Display the component overview for all objects of your project.
Choose Select all to select all objects.
Choose Component overview.
The procurement dates of the components are displayed in the graphic. Change
the procurement dates. Use the following data:
Component E-1517 7 days earlier
Component E-1203A At the start of the activity
You can call the detail screen by double-clicking the description of the
component or by selecting the component, then use your right mouse button
to choose Detail Screen.
For E-1517, enter the value 7- in the Offset field and the time unit Day in the
next field.
Confirm your entries by selecting Back .
On the detail screen for E-1203A, select the Algn.Startdate.Comp indicator.
Confirm your entries by selecting Back .
Save your entries.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 246/312
© SAP AG PLM220 6-60
1-2 If you want to assign several components, assigning materials manually can be quite
time consuming. As an alternative, you can assign bills of material (BOMs). Createyour own BOM and assign it to the project.
1-2-1 Create a WBS BOM for the top WBS element of your project. Use the material
BOM T-20000 as a template.
SAP Menu
Logistics Production Master Data Bills of Material Bill of
Material WBS BOM Single-Level Create
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
WBS Element T-100##
Material T-20000
Plant 1300
BOM usage 3 (universal)
Use the material BOM T-20000 as a template.
Select Copy material BOM .
Use the following data when copying the BOM:
Field Name Values
Material T-20000
Plant 1300
Use 3
Select Continue to confirm your entries.
An overview of the material BOM appears. Choose all components except for
material P-100 and copy the items to the WBS BOM.
Select the components.
Select Adopt .
Save the WBS BOM.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 247/312
© SAP AG PLM220 6-61
1-2-2 Use the BOM transfer to assign the components of your WBS BOM to your
project activities.
SAP Menu
Logistics Project System Material Planning Bill of Material
Transfer
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Project definition T-100##
WBS element T-100##
Material T-20000
Plant 1300
BOM usage 3
Check the BOM transfer selection parameters.
Choose Selection Parameters.
Use the following parameters:
Field Name Values
WBS BOM Select
Multilevel Select
Plant stock 2
Project stock 1
Confirm your entries by clicking the appropriate pushbutton.
Call the BOM transfer.
Choose Execute.
First the results list appears, in which you see all the components that the
system can assign automatically.
Save the assignments.
Choose Save.
If necessary, confirm the scheduling warnings.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 248/312
© SAP AG PLM220 6-62
1-2-3 BOMs are often changed during the course of a project. Expand your WBS
BOM to include material P-100 and double the requirement quantity forcomponent T-20100.
SAP Menu
Logistics Production Master Data Bills of Material Bill of
Material WBS BOM Single-Level Change(Choose transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
WBS Element T-100##
Material T-20000
Plant 1300
BOM usage 3 (universal)
Select Item.
Double the requirement quantity for material T-20100 Turbine casing .
Enter material P-100 as an additional component with the following data:
Field Name Values
Item category L
Component P -100
Quantity 1
Select Enter to confirm your entries.
Store another reference point for the components so that they can be assigned
automatically with the BOM transfer. Enter the reference point 1310
Procurement plant components.
Double-click the item number .
Enter the value 1310 in the Reference point field in the General data section
of the Basic data tab.
Save your entries.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 249/312
© SAP AG PLM220 6-63
1-2-4 Update the component assignment for your project. Use the BOM transfer
again.
SAP Menu
Logistics Project System Material Planning Bill of Material
Transfer
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Project definition T-100##
WBS element T-100##
Material T-20000
Plant 1300
BOM usage 3
Check the selection parameters of the BOM transfer again.
Choose Selection criteria.
Use the following parameters:
Field Name Values
WBS BOM Select
All items Select
Multilevel Select
Plant stock 2
Project stock 1
Confirm your entries by selecting the appropriate pushbutton.
If you always call the BOM transfer with the same parameters, create
a selection profile that contains these settings.
Call the BOM transfer.
Choose Execute.
A dialog box appears as a result of the quantity change in the BOM. Save the
change.
Select Confirm.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 250/312
© SAP AG PLM220 6-64
The overview of components that cannot be assigned automatically appears.
The components T-20200, T-20610, T-20620 and T-20630 should be listedhere. Instead of assigning components manually, go to the results list.
Select Results.
The results list appears. The symbols in the first column indicate whether thecomponent is being created, deleted, changed, or reallocated.
Save your entries.
Choose Save.
1-3 In the next exercise, you will procure material for your project and use it in the
network. Take component T-20600 that you assigned previously and trace all steps of
its procurement and use in the system.
1-3-1 First display the stock/requirements list for material T-20600.
SAP Menu
Logistics Project System Material Planning Stock/Requirements
List
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Material T-20600Plant 1300
Select Continue to call the list.
You should notice an individual requirements stock segment for your project inthe list with reservation via a unit of the material. Until now, only one
requirement has been generated. However, you need one more procurementelement.
Select Back to exit the transaction.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 251/312
© SAP AG PLM220 6-65
1-3-2 Perform a planning run for your project to generate procurement elements. The
best way of doing this is to open a second session so that you can always process the stock/requirements list in one session.
SAP Menu
Logistics Project System Material Planning MRP Project
(Choose the transaction by double-clicking it)
Use the following settings on the initial screen:
Field Name Values
Project def. T-100##
Create purchase req. 1
Display material list Select
Carry out the planning run.
Select Enter twice.
A results list appears, which also contains the dependent requirements for your project. You have created procurement elements for the requirements. These,
however, are planning procurement elements. You will generate the actual
procurement elements in the next step.
Select Back to exit the overview.
1-3-3 Display the stock/requirements list for material T-20600 and create a production order for your reservation.
If you also opened the list in a different session, select Refresh.
Otherwise, choose:
SAP Menu
Logistics Project System Material Planning Stock/Requirements
List
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
Select Continue to call the list.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 252/312
© SAP AG PLM220 6-66
In the individual stock segment for your project, the list contains a planned
order as well as the reservation.
Convert the planned order into a production order and release it immediately.
Double-click the planned order field.
In the dialog box, select -> Production ord.
The header screen for the production order appears. Release and save the
production order.
Select Release .
Choose Save.
You have returned to the stock/requirements list. Refresh the data selection.
Select Refresh.
You should now see a production order for your reservation.Make a note of the production order number: ___________
1-3-4 During the planning run, the system has created requirements and procurementelements for dependent components. Component T-20600 has requirements for
component T-20610, T-20620, and T-20630. Order the components and post
them to the warehouse.
Suitable purchase requisitions have already been created by the MRP run.Convert these to purchase requisitions in the information system.
SAP Menu Logistics Project System Information System Material Purchase
Requisitions For Project
(Choose the transaction by double-clicking it)
Specify the project definition T-100## and choose Execute.
An overview of all purchase requisitions appears. First assign purchase
requisitions to purchasing information records, then create the purchase order.
Select material T-20610.
Select Assign automatically.
Assign materials T-20620 and T-20630 the same way.
Display the overview of the assignments and then create the purchase order.
Choose Assignments.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 253/312
© SAP AG PLM220 6-67
The purchase requisitions are sorted in the overview according to their
assignments. You can create new purchase orders by choosing Processassignment .
Place your cursor on the line below vendor C.E.B..
Select Process assignment .
Confirm the first dialog box by selecting Continue .
If another dialog box appears, choose New purchase order .
The purchase order appears.
On the left-hand side of the overview, select your three purchase requisitions
and copy them to the purchase order.
Select Adopt .
Save the purchase order.
Select Save .
The purchase order number appears in the status bar.
Make a note of the order number: ____________
Select Back to exit the assignments overview.
Save the changed purchase requisitions.
Select Back to exit the report.
1-3-5 The components you ordered have been delivered. Post them to the warehousewith a reference to your purchase order.
SAP Menu
Logistics Materials Management Purchasing Purchase Order
Follow-On Functions Goods Receipt
(Choose the transaction by double-clicking it)
Use the following data:
Field Name Values
Purch.order Your order number
OK Activate
StLoc 0001
Enter your purchase order number on the right of the Purchase order number field and select Execute to transfer the data.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 254/312
© SAP AG PLM220 6-68
Activate the OK flag and specify the storage location for each of the three
items. Once you have processed the item, click it to process the next item
The storage location can be located on the Where tab for each item in the
item details..
Save the goods receipt .
The components are now in the warehouse, ready to be used in the production
order.
Select Back to exit the transaction.
1-3-6 Take the components from the warehouse and use them in the production order.
SAP Menu
Logistics Materials Management Inventory Management Goods
Movement Goods Issue
(Choose the transaction by double-clicking it)
Select To order… .
Enter your production order number in the dialog box.
Confirm the information by selecting Continue.
A goods withdrawal overview appears. Specify the storage locations for thematerials.
Enter the value 0001 in the SLoc field.
Post the goods issue
Select Post .
1-3-7 Once the components for the production order have been withdrawn, the order
can be processed. Confirm the order with the planned quantity. Set the status
Final confirmation.
SAP Menu
Logistics Production Production Control Confirmation Enter
For Order
(Choose the transaction by double-clicking it)
Enter the number of your production order and call the confirmation.
Select Enter .
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 255/312
© SAP AG PLM220 6-69
Activate the Final confirmation indicator.
Enter the planned quantity in the Yield to confirm field .
Save the confirmation.
Choose Save.
1-3-8 You have posted services to the production order but not yet posted the
completed material T-20600 to the warehouse. Post the goods receipt for your
order.
SAP Menu
Logistics Production Production Control Goods Movements
Goods Receipt
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Movement type 101
Order Your production order
Plant 1300
Storage location 0001
Select Enter to confirm your entries.
Copy the default values from the order and post the goods receipt.
Select Adopt .
Select Post .
1-3-9 Check the stock situation for material T-20600 in your project. Use thestock/requirements list.
If the list is also open in a different session, select Refresh.
Otherwise, call the list again.
SAP Menu
Logistics Project System Material Planning Stock/Requirements
List
(Choose the transaction by double-clicking it)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 256/312
© SAP AG PLM220 6-70
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
Select Continue to call the list.
The production order should no longer be visible in the list and stock shouldnow be built up for your project.
1-3-10 Use material T-20600 in the project. Remove the material from storage location
0001 with reference to your reservation. The reservation and item number is in
the stock/requirements list or the activity.
SAP Menu
Logistics Materials Management Inventory Management Goods Movement Goods Issue
(Choose the transaction by double-clicking it)
Enter storage location 0001.
Select To reservation.
A dialog box appears, in which you can enter the reservation number and the
item number. Display all reservations for your network and choose those for
material T-20600.
In the Network field, enter your network number (if you don't know it, use thematch code to search for it).
Select Continue.
An overview of the reserved components appears.
Select component T-20600 (you might have to scroll through the overview).
Copy the data by choosing Adopt .
Post the goods issue.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 257/312
© SAP AG PLM220 6-71
1-3-11 Call the stock/requirements list for material T-20600 again.
If the list is also open in a different session, select Refresh.
Otherwise, call the list again.
SAP Menu
Logistics Project System Material Planning Stock/Requirements List
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Material T-20600
Plant 1300
Select Continue to call the list.
The goods receipt has reduced the individual requirements stock segment foryour project.
1-4 In the final exercise, take a look at the delivery from the project.
1-4-1 Prepare your project for delivery from Project System. Create delivery
information with the Project Builder.
SAP Menu
Logistics Project System Project Project Builder
(Select the Project Builder by double-clicking it)
Drag and drop your project from the work list to the structure tree.
Manually create delivery information for activity 3000 Preliminary orders.
Expand the project and select activity 3000.
Choose Extras Delivery information .
Generate new delivery information by selecting Create .
Enter Group## as a description for the delivery information.
Select Continue to confirm your entries.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 258/312
© SAP AG PLM220 6-72
Use the following data:
Field Name Values
Project def. T-100##
Shipping point 1300
Planned GI date Tomorrow
Delivery date Two weeks from today
Ship-to party 1600
Sales org. 1000
Distribution channel 10
Division 00
Confirm your entries by selecting Copy.
Assign the delivery information already available (Group ## ) to activity 3100
Material procurement plant components.
Select the activity.
Choose Extras Delivery information .
Enter the value Group ## in the Delivery info field.
Select Enter to confirm your entries.
Confirm your entries by selecting Copy.
Save the changes made to your project.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 259/312
© SAP AG PLM220 6-73
1-4-2 You can only deliver goods that are available. Post a goods receipt for the
project. Post a pump p-100 to your project stock.
SAP Menu
Logistics Materials Management Inventory Management Goods
Movement Goods Receipt Other
(Choose the transaction by double-clicking it)
Enter the following data on the initial screen:
Field Name Values
Movement type 501
Plant 1300
Storage location 0001
Special stock Q (Project)
Select Enter to confirm your entries.
The screen for entering goods receipts appears. Enter the following data:
Field Name Values
Material p-100
Quantity 1
WBS element T-100##
Select Enter to confirm your entries.
Confirm all information by selecting Continue.
Post the goods receipt.
Select Post .
You can now call the stock/requirements list for the material in order to check
the project stock.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 260/312
© SAP AG PLM220 6-74
1-4-3 Create a delivery for goods recipient 1600.
SAP Menu
Logistics Project System Material Execution Delivery from
Project
(Choose the transaction by double-clicking it)
Combine the components for the delivery from your project to recipient 1600.
Enter your project T-100## and ship-to party 1600 on the initial screen.
Select Components .
If a dialog box appears asking you to provide missing information on the
delivery, provide this information.
Confirm any warnings that appear regarding missing settings in the material
master of individual components.
An overview of the materials that meet the filter conditions appears. Somecomponents, for example pump p-100, are available in the warehouse and can
be delivered. Create a delivery containing the pump.
Select all components except pump p-100.
Select Delete.
Check the delivery information again for the component.
Select pump p-100.
Select Delivery information .
Exit the delivery information by choosing Copy.
Check the available open quantity on the component detail screen.
Select pump p-100.
Select Details.
Check the delivery date and goods issue date.
Field Name Values
Delivery date Two weeks from today
Goods issue Tomorrow
Exit the detail screen by choosing Copy.
Create the delivery.
Choose Save.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 261/312
© SAP AG PLM220 6-75
1-4-4 Process the delivery that you created previously. Post a goods issue.
SAP Menu
Logistics Project System Material Execution Delivery from
Project
(Choose the transaction by double-clicking it)
Enter your project T-100## on the initial screen.
Select Deliveries pushbutton.
An overview of the deliveries for your project appears. Process the delivery.
Double-click the delivery.
Select Display/Change.
Normally, the delivery should now be picked and packed. You can leave outthis step. Post the goods issue directly.
Select pump p-100.
Select Post goods issue.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 262/312
© SAP AG PLM220 6-76
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 263/312
© SAP AG PLM220 7-1
SAP AG 2002
Using Progress Tracking
Customizing settings for Progress Tracking
Progress Tracking
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 264/312
© SAP AG PLM220 7-2
SAP AG 2002
Use Progress Tracking and make the required
system settings
At the conclusion of this unit you will be
able to:
Progress Tracking: Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 265/312
© SAP AG PLM220 7-3
SAP AG 2003
Progress Tracking: Overview
Course
Overview
Project
Structures
Scheduling
Capacities
External
Services
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 266/312
© SAP AG PLM220 7-4
SAP AG 2002
In this unit, you will find out about the capabilities ofProgress Tracking
Progress Tracking: Business Scenario
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 267/312
© SAP AG PLM220 7-5
SAP AG 2002
What is Progress Tracking?
Order
confirmation
Goods
receipt
Shipping
advice
Approval
Delivery
Export
documents
How can I monitor
these processes?
Progress Tracking enables you to closely monitor the progress of network components by tracking self-
defined events. These events are either defined in Customizing or directly in the application. You can seesome examples on the slide: Order confirmation, approval, delivery, export documents, goods receipt,
and shipping advice. The corresponding transaction code is COMPXPD.
Progress Tracking is a new function in the SAP R/3 Enterprise Release. It contains all the features of the
Monitoring Dates function (transaction NWTM). However, Progress Tracking is enhanced by a series of
new developments: more flexible Customizing, status information, mass change, copying and filtering
functions, evaluation, and printing functions. Progress Tracking is user-friendly and allows you to create
user-specific layouts.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 268/312
© SAP AG PLM220 7-6
SAP AG 2002
Progress Tracking Objects - Differences
Components in a Network
Transaction: COMPXPD
⇒ Initial screen
⇒ Layouts
Customizing for Network
Components Purchase Orders
Transaction: AXPD
⇒ Initial screen
⇒ Layouts
Customizing for Purchase
Orders
Progress Tracking can be executed for different objects:
Network components
Purchase orders
The respective object is called a progress tracking object.
The two different progress tracking objects each have their own:
Transactions (COMPXPD or AXPD)
Customizing settings
Selection screens
Field selections within Progress Tracking
In addition to the Project System, Progress Tracking can be used in Materials Management to monitor
the progress of purchase orders. This course, however, only deals with Progress Tracking for network
components.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 269/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 270/312
© SAP AG PLM220 7-8
SAP AG 2002
Progress Tracking Procedure
Prerequisites
Decide which progress tracking object is to be analyzed
Create a progress tracking profile
Create standard events
Create an events scenario
Procedure
Call up the relevant transaction
Fill out the selection screen
Select components or purchase orders
Assign events or a scenario Manual dates processing or scheduling
Evaluation
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 271/312
© SAP AG PLM220 7-9
SAP AG 2002
Progress Tracking Profile
Actual/Today > Basel.
Project Selection
Further Selection Parameters
Progress Tracking Parameters
Profile PS01 Progress Tracking IDES
Project
WBS Element
Network
Activity
Material
T-0001
Plant
Storage Location
Requirement Quantity
Item Category
Requirements Date
Changed on
Scenario
Priority
Event
Baseline
Plan
Forecast
Actual
Planned > Baseline
Forecast > Baseline
Forecast > Planned
Actual/Today > Planned
Selection screen
Network Component Selection
Entries
Change Display
Mat. Date Qty UoM Network Acty Material Description
PC
PC
PC
PC
PC
PC
PC
M
PC
PC
M
Turbine casing
Rotor disk
Guide vane
Rotating blade
Generator
Elec.cabinet
Oil feed
Pump
Steam line turbine
Power cable
Bearing box (complete)
2
1
Progress Tracking has two selection screens that you work through one after the other.
In the first selection screen, you determine the selection of components for which Progress Tracking is to
be carried out. To do this, you enter projects or networks that contain the required components.
The second selection screen contains all the components that matched your selection criteria in the first
stage, from which you can now make a more detailed selection. It is from here that Progress Tracking
itself starts. As a rule, a lot of components are listed in this section. Select those that you want to look
into now. You can return to the selection screen at anytime to track other components.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 272/312
© SAP AG PLM220 7-10
SAP AG 2002
Standard Events and Scenarios
Progress Tracking Overview
Components
Events
PS0001PS0001
MaterialReqtsDate
SpecificationDescription Baseline Fixed Planned Fixed
Description
Scenario Material ReqtsDate QuantityStInfoEvts Network
Standard Events
Request for quotation
Description
Evaluation of quotationPurchase order
ApprovalDelivery
Arrival at site
1
2
Progress Tracking evaluates the dates of events that are assigned to network components. This
assignment can be carried out in different ways:
Direct assignment of a standard event (see slide)
Generation and assignment of a new event (not a standard event!)
Assignment of a scenario that contains standard events (event relationships)
Automatically by assigning a scenario to a material group (otherwise, as in 3).
Using a BAdI (see later in unit)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 273/312
© SAP AG PLM220 7-11
SAP AG 2002
Progress Tracking Overview
Components
Events
Scenario Material ReqtsDate QtyStInf Evts Netwk
Material
Reqmnts date
Description Baseline Fixed Plan Fixed
Description
Forecast Fixed Act. FeGr Scenario Scen. Var.StdE Prio
Turbine casing
Specification
Request for quotationEvaluation of quotation
Purchseorder Approval
Priority Descr.
Scheduling
Scheduling Settings
Baseline
PlannedForecast
Backwards
ForwardsBackwards -> Forwards
Forwards -> Backwards
Do not display
1
2
Progress Tracking allows you to schedule the standard events of a scenario. This can either be triggered
manually or automatically when Progress Tracking is executed.
A prerequisite for scheduling is the use of standard events, a scenario, and the definition of event
relationships within the scenario. All three tables must be set up in Customizing beforehand.
Manual scheduling: Select an individual standard event in the event overview. Start scheduling. You
branch to a dialog box (see slide) where you can define the settings for scheduling. After confirming the
dialog box, scheduling is carried out.
Automatic scheduling: If the Automatic scheduling indicator in the Event Relationships table is set for an
event in a scenario, scheduling is carried out automatically according to the setting in the Progress
Tracking profile.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 274/312
© SAP AG PLM220 7-12
SAP AG 2002
Evaluation
ReservNo.
Progress Tracking: Evaluation
Networks/Activities/Items Item Name Reqts Date Planned Forecast Actual
Display Display Close All
Specification
Request for quotation
Evaluation of quotation
Purchase order
Approval
Delivery
Arrival at site
Specification
Request for quotation
Turbine casing
Turbine casing
Turbine casing
Turbine casing
Turbine casing
Turbine casing
Turbine casing
Turbine casing
Rotor disk
Guide vane
Guide vane
Guide vane
Variance
Progress Tracking has its own interface for evaluations. It is called up from Progress Tracking. The
evaluation shows all data for a progress tracking object on one interface. This gives you a betteroverview and also allows you to compare and analyze in detail.
The evaluation interface is split into two areas. On the left, a tree structure shows the progress tracking
objects. On the right, the related events, including dates and variances, are displayed. The variances are
evaluated according to the settings in the progress tracking profile.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 275/312
© SAP AG PLM220 7-13
SAP AG 2002
Status Information
Status Information
Material
Reqmts date
Description Turbine casing
Status Note
Cat. Disp.Only Prog.Tr.StatusInfoTitle Complete Created by Created on Time TimeChanged by Changed on
Critical part
Warning: Due to a fire in the warehouse, delivery of T-20100 could be delayed.
Caution: Status information has nothing to do with status management in general.
Status information is used to provide information about individual components in a network (or purchase
orders). This information is assigned to the component as a text (see slide). You can assign as many
status notes to a component as required. Each one is assigned to a status information category. This
enables you to control who has access to the information.
In the component overview you can tell by way of an icon whether status information exists for a
component.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 276/312
© SAP AG PLM220 7-14
SAP AG 2002
Additional Functions
Mass Change
Scenarios Dates
Copying Dates
Copying all dates of all events
Copying dates of particular events
Subitems
Hotspots
Branch to the master data display for underlined fields
Mass change of scenarios:
You can assign one or more progress tracking objects to a scenario using mass change. When you do
this, the new scenario overwrites all events that are not contained in the scenario itself.
Copying dates:
You can copy all dates of all events belonging to one progress tracking object to another progress
tracking object.
Subitems:
You can add several subitems to an individual progress tracking object (for example, a component). In
turn, each individual subitem can have events.
Hotspots:
You can branch to the master data display of objects that are underlined, for example, material master,
network.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 277/312
© SAP AG PLM220 7-15
SAP AG 2002
Customizing
Where?
Network components: Project System -> Progress -> Progress Tracking
Purchase orders: Materials Management -> Purchasing -> Purchase
Orders -> Progress Tracking
What?
Progress Tracking profile (required!)
Standard events
Event scenarios
Event relationships within a scenario
Priorities for events
Assignment of default scenario to a material group
Status info types
Number ranges for status info
Customer-specific evaluations
Customizing for Progress Tracking is very extensive and flexible. To carry out a simple test, all you need
to do is set up a progress tracking profile.
However, if you want to use scheduling, then you also need standard events, scenarios, and event
relationships within a scenario. All four tables are shown in the following.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 278/312
© SAP AG PLM220 7-16
SAP AG 2002
Customizing the Progress Tracking Profile
Profile PS0001
Progress Tracking Profile for Components
Description Progress Tracking IDES
Scheduling
Baseline
Planned
Forecast
Backwards
Forwards
Backwards-> Forwards
Forwards -> Backwards
Do not display
Variances Column display
Planned > Baseline
Forecast > Baseline
Actual/today > BaselineForecast > Planned
Actual/today > Planned
Baseline
Planned
Forecast Actual
In detail, the indicators have the following meaning:
Description: Enter an explanatory short text here.
Scheduling baseline, planned, and forecast: Specifies whether the respective dates are to be
scheduled.
Forward (backward) scheduling: Determines that with one event as the starting point, the system
calculates the dates of the subsequent (preceding) events. Caution: Only those events are scheduled
that have the entry Forward scheduling (Backward scheduling) in the table of event relationships for
the scenario.
Backward – Forward Scheduling: In backward-forward scheduling, you start the scheduling
backwards first and schedule all events in a scenario for which the indicator for backward scheduling
is set. Afterwards, the system uses forward scheduling to determine the dates for events for which the
forward scheduling indicator is set.
Forward– Backward Scheduling: The same principle as backward-forward scheduling.
Do not display: The dialog box is not shown during manual scheduling.
Variances: The traffic light colors of the individual variances are defined here.
Column Display: Here you define which dates can be shown in the columns of the events overview.
Note:You can also maintain a layout in the application.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 279/312
© SAP AG PLM220 7-17
SAP AG 2002
Customizing Standard Events
New Entries
Events for Components
PS001
PS002
PS003
PS004
PS005
PS006
PS007
Event Description Rank RfBa RfPl RfFr RfActSpecification
Request for quotation
Eval.of quot.
Purchase order
Approval
Delivery
Arrival at site
In detail, the indicators have the following meaning:
Event: Specifies the number of the event.
Description: Contains a short description of the event.
Rank: Specifies the sorting sequence of the events display in the events overview.
Reference: Defines whether and how a date can be referenced. The actual reference date is determined
using a BAdI. The indicator activates a user exit.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 280/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 281/312
© SAP AG PLM220 7-19
SAP AG 2002
SET_OBJ_TYPE
GET_DEFAULT_SCENARIO
GET_NEWS_EVENTS
UPDATE_SUB_ITEMS
GET_REFERENCE_DATE
UPDATE_FIELDCAT_MAINITEM
UPDATE_FIELDCAT_SUBITEM
UPDATE_OFFSET
PRINT_STATUS_NOTE
SAVE_EVENTS
Business Add-Ins (BAdIs)
Set up a particular progress tracking object when
Progress Tracking is called up
On calling up Progress Tracking, generate customer-
specific events for Progress Tracking
Generate, delete, and update subitems when Progress
Tracking is called up
Determine reference dates for events when Progress
Tracking is called up
Influence the ALV grid field catalog for events of
Progress Tracking objects
Influence the ALV grid field catalog for subitems
Update time intervals for event relationships whenscheduling is called up for the events of a progress
tracking object
Control the printing of status information
Assign a default scenario to a progress tracking object
when it is called up, if it does not have a scenario orevent already assigned to it
Update events for Progress Tracking on saving
!!
For customer enhancements, you can use the methods of the BAdI definition EXPD_UPDATE shown in
the slide. Use transaction SE18 to look at the methods and interfaces. Use transaction SE19 to implementthem.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 282/312
© SAP AG PLM220 7-20
SAP AG 2002
You are now able to:
Progress Tracking: Summary
Use Progress Tracking and make the required
system settings
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 283/312
© SAP AG PLM220 7-21
Exercises
Unit: Progress Tracking
Topic: Progress Tracking
1-1 Use Progress Tracking to plan and monitor dates for the material procurement of your
project.
1-1-1 Find out the dates of the first four material components in your project. CallProgress Tracking using the following data.
Field Name Input Data
Profile Progress Tracking PS
Project Your project definition
Hint: To select more than one object, keep the Ctrl key pressed.
Question: To which activities are the components assigned?
Answer: See the solutions.
1-1-2 Manually assign an event to the first component. Plan one date in the past.
Set one date to two weeks in the past and update the evaluation.
Question: What has changed?
Answer: See the solutions.
1-1-3 Assign two standard events to the first component.
Question: Can you schedule the events?
Answer: See the solutions.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 284/312
© SAP AG PLM220 7-22
1-1-4 Enter additional information for the first component. Use a status note to do
this. Enter a text of your choice.
Question 1: What effect does the category of the status note have?
Question 2: How many status notes can you enter per component?
Answer 1: See the solutions.
Answer 2: See the solutions.
1-1-5 Save your data.
Question: What do you notice when you save?
Answer: See the solutions.
1-1-6 Assign event scenario PS0001 to the remaining components.
1-1-7 Display the event overview for the second component. How many events have been assigned?
Answer: See the solutions.
1-1-8 Schedule the start date of the Specification event to two weeks ago today andtrigger scheduling of the planned dates.
Question: Do you see any variances?
Answer: See the solutions.
1-1-9 Set up the variances so that a yellow traffic light appears as soon as the planneddate goes past the baseline date.
1-1-10 For the Specification event, enter an actual date that corresponds to the
schedule, and a baseline date that is for three weeks ago. Update the data.
Question: What color is the traffic light?
Answer: See the solutions.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 285/312
© SAP AG PLM220 7-23
1-1-11 Question: How long is the time interval between the events Purchase order and
Approval ?
Answer: See the solutions.
1-1-12 Save your data and exit the transaction.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 286/312
© SAP AG PLM220 7-24
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 287/312
© SAP AG PLM220 7-25
Solutions
Unit: Progress Tracking
Topic: Progress Tracking
1-1 Use Progress Tracking to plan and monitor dates for the material procurement of your
project.
Choose SAP Menu Accounting Project System Progress Progress
Tracking
1-1-1 Find out the dates of the first four material components in your project. CallProgress Tracking using the following data.
Field Name Input Data
Profile Progress Tracking PS
Project Your project definition
Execute Progress Tracking.
Choose Program Execute
Select the first four material components and choose Change.
Hint: To select more than one object, keep the Ctrl key pressed.
Question: To which activities are the components assigned?
Answer: The components are assigned to activity 3000.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 288/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 289/312
© SAP AG PLM220 7-27
1-1-5 Save your data.
Choose Save and confirm the dialog box, if necessary.
Question: What do you notice when you save?
Answer: The system does not exit the transaction when you save. You cancarry on using Progress Tracking.
1-1-6 Assign event scenario PS0001 to the remaining components.
Select the three components and choose Scenario Mass Change.
A dialog box appears.
There, choose event scenario PS0001 and confirm your entries by selecting Enter .
Confirm any messages that appear.
1-1-7 Display the event overview for the second component. How many events have been assigned?
Double-click the scenario in the second row in the component overview.
Answer: Seven events are assigned.
1-1-8 Schedule the start date of the Specification event to two weeks ago today and
trigger scheduling of the planned dates.
Enter the relevant date in the Planned field.
Select the Specification event.Choose Schedule.
A dialog box containing the detailed settings for scheduling appears. Confirm
this.
Question: Do you see any variances?
Answer: Yes, the events Specification and Request for quotation arehighlighted in color.
1-1-9 Set up the variances so that a yellow traffic light appears as soon as the planned
date goes past the baseline date.
Choose Profile.
Double-click the traffic light of exception Planned > Baseline.
Confirm your entries.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 290/312
© SAP AG PLM220 7-28
1-1-10 For the Specification event, enter an actual date that corresponds to the
schedule, and a baseline date that is for three weeks ago. Update the data.
Enter the respective dates in the Actual and Baseline fields.
Choose Update.
Question: What color is the traffic light?
Answer: The traffic light is now yellow.
1-1-11 Question: How long is the time interval between the events Purchase order and
Approval ?
Choose Event Scenario.
Answer: The time interval is 30 days.
1-1-12 Save your data and exit the transaction.
Choose Progress Tracking Exit and confirm the dialog box by choosing
Yes.
Choose Progress Tracking Exit again.
Choose Program Exit.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 291/312
© SAP AG PLM220 8-1
SAP AG 2002
Using ProMan (Project-Oriented Procurement)
Customizing settings for ProMan
ProMan
Contents:
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 292/312
© SAP AG PLM220 8-2
SAP AG 2002
Use ProMan and make the required system
settings
At the conclusion of this unit, you will beable to:
ProMan: Objectives
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 293/312
© SAP AG PLM220 8-3
SAP AG 2003
ProMan: Overview
Course
Overview
Project
Structures
Scheduling
Capacities
External
Services
Material
ProgressTracking
ProMan
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 294/312
© SAP AG PLM220 8-4
SAP AG 2002
In this unit, you will find out about the capabilities of ProMan.
ProMan: Business Scenario
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 295/312
© SAP AG PLM220 8-5
SAP AG 2002
What is ProMan?
ProMan is a tool that helps you carry out
project-oriented procurement.
It supplies information about the status and progressof internal and external procurement activities.
ProductionInventory
managementPurchasing Shipping
ProjectManagement
Activity D
Material B
Activity C Plannedorder PReq.
Quotation
Material ADeliveryReservation
RFQ
The Project System is one of the most integrated modules within SAP R/3. An area in which this is
particularly noticeable is the internal and external procurement of material and services: As soon as anobject is generated in the Project System, the relevant documents (for example, purchase requisitions)
are created in other applications.
These documents are processed by the corresponding departments (for example, Purchasing).
Previously, this meant that the project team only had limited access to information that was important for
the project, information that was actually triggered by the Project System.
ProMan solves this problem:
Consolidated information from the procurement process from a variety of applications. Structured
display of information. The display can be adapted to suit the individual user.
Execution of individual steps in the procurement process directly from ProMan.
Access to data from the Project System, Purchasing, Production, Requirements Planning, and
Inventory Management. All objects and documents are taken into account, both planned and
unplanned objects. Manually created documents are also displayed.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 296/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 297/312
© SAP AG PLM220 8-7
SAP AG 2003
Scenario – Purchase Components
Create project
with
components
Purchase
order, goods
receipt
Goods issueReservation,
ppurchasereq.
Selection,
ProMan
ProMan is a tool for monitoring procurement processes, and also for controlling these procurement
processes. A definite prerequisite is a work breakdown structure and/or a network to which thecomponents or services to be procured are assigned.
The ProMan selection screen allows all, or only some, of these components or services to be selected for
processing in ProMan.
For example, the slide shows several procurement processes that can be executed or analyzed in
ProMan:
Reservation, purchase requisition, purchase order, goods receipt, goods issue
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 298/312
© SAP AG PLM220 8-8
SAP AG 2002
Selection Screen
Project Selection
PS0001: ProMan, Demonstration, IDES
Project Definition
Sales Document
WBS Element
Network
Default Settings
Profile
Components Activities/Elements
Network MRP Controller
Activity
Material
Plant
Sort string
Requirements Date
Material Group
Purchasing Group
Vendor
Item Category
Relevant for Reqs
Procured Externally
Withdrawable
Missing Part
Plant Stock
Project Stock
Order Stock
to
to
to
to
to
to
to
to
to
to
Object
selection
Filter criteria
Settings for
views and
exceptions
The entire selection
can be saved
as a variant!
The overall selection screen for ProMan is subdivided into three sections.
The first section is where the components and external services are actually selected. You do this by
specifying the project definition, sales order number, WBS element, or network.
In the second section, you can enter a ProMan profile. This determines the display of variances and the
selection of documents that ProMan is to display.
In the third section you define the criteria for filtering the selection. In general, the filters can refer to
attributes of the components or the activities and activity elements.
The selections you make here can be very complicated. So that you do not lose the settings completely
each time you exit the selection screen, you can save the entire selection screen as a variant.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 299/312
© SAP AG PLM220 8-9
SAP AG 2002
Component Overview
Components
Rotor disk
Orders/Docs Quants Dates Stock Deliveries
Res.No. Itm Mat. Mat. Desc.Plant Network Acty Quantity UOMReqtDate
Turbine casing
Components
Guide vane
Rotating blade
Elec. switch cabinet
Oil feed
Steam line
Cable 10kA
Generator
Pump
Bearing box
Project Structure
The main ProMan screen is divided into two areas. A hierarchical navigation area on the left, and the
area for detailed information on the right. Tab pages subdivide this second area into individual sections.The slide shows the component overview.
In the component overview, you are provided with the following information, for example:
Reservation number including item
Name and description of the material
Requirements quantity with unit of measure
Item category
Purchasing data (purchasing organization, purchasing group)
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 300/312
© SAP AG PLM220 8-10
SAP AG 2002
Orders and Documents View
Components Orders/Docs Quantities Dates Stock Deliveries
Orders/Documents
ReservNo. Itm Exception Material Res/Preq Vendor PReq. RFQ Purch.Order MatDoc Status
Transfer Posting of Stock
Generate Reservation/Preq
Group to Purchase Req.
Generate Purchase Order
Generate Delivery
Post Goods Issue
The overview of orders/documents gives you information about orders (for example, planned orders,
production orders) and documents (purchase requisitions, purchase orders, requests for quotation,material documents and so on) that are assigned to the selected components (or external services). The
individual documents and orders can be displayed directly from ProMan. Simply double-click the
individual document or order number to do this.
You can also create new documents from all of the overviews. The context determines which documents
you can create. The slide shows all the options that can be created:
Reservation or purchase requisition
Grouping to purchase requisition
Purchase order
Delivery
Goods issue
Transfer stock posting
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 301/312
© SAP AG PLM220 8-11
SAP AG 2002
Quantities View
Components Orders/Docs Quantities Dates Stock Deliveries
Quantities
ReservNo. Itm Exception Material Plant Material desc. Res/Preq ReqtsQtyWthdQty POrQty PReq.UOM
Rotor disk
Turbine casing
The Quantities view supplies you with detailed information about the quantities and stock levels of
components. In detail, you see the following:
Requirements quantity of the reservation
Quantity in the planned order and in the production order
Quantity of the purchase requisition and the purchase order
Stock
Quantity withdrawn
Quantity in the material document
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 302/312
© SAP AG PLM220 8-12
SAP AG 2002
Dates View
Components Orders/Docs Quantities Dates Stock Deliveries
Dates
ReservNo. Itm Exception Material ReqtsDate ReqDate DelPReq RelDate PostMatDoc StatusPreq
The date overview gives you detailed information about the dates of components (and external services).
For example, you are provided with the following information:
Requirements date
Delivery date of the purchase requisition and purchase order
Basic start and finish date of planned orders and production orders
Final delivery date of production orders
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 303/312
© SAP AG PLM220 8-13
SAP AG 2002
ProMan: Additional Functions
Integration
Order progress, order report
Requirements planning run, stock/requirements list
Navigation for all displayed objects
Material master, planned order, production order
Network, purchase requisition, purchase order
Request for quotation, quotation, vendor master
Highlighting exceptions
You can select other functions from the ProMan menu. In ProMan, choose Edit -> Functions to carry
out the following functions:
Order progress
Order report
Single-item, single-level (requirements planning run, MRP)
Single-item, multi-level (requirements planning run, MRP)
Project planning (requirements planning run, MRP)
Stock/requirements list
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 304/312
© SAP AG PLM220 8-14
SAP AG 2002
ProMan: Customizing Settings
ProMan, Demonstration, IDESDialog Structure
Profile for ProMan
Document Exceptions
Sched. Exceptions
Quantity Exceptions
Schedule Line Exceptions
Confirmation Exceptions
Exceptions POrder History
Docs
Dates
Exception
Red Rule
Yellow Rule
Demo Purchasing Documents
PReq Without Purchase
No procurement yet
Exception
Rule red
Rule yellow
Profile
ProMan Profile
Description ProMan, Demonstration, IDES
Settings
Exception Profile ProMan, Demonstration, IDES
Orders/Docs Views
Purchase Requisition
Request for Quotation
Purchase Order
deliveryMaterial Doc.
Planned Order
Production Order
Maintenance Order
Reservation for WBS
Components
Activities/Elements
Quants
datesDeliveries
Stock
Orders/Docs
Both profilesare optional!
In Customizing, you can set up two profiles for ProMan:
ProMan profile. This is optional and is selected when ProMan is called up. The individual indicators are
as follows:
Profile and Description: Contains number and short description of the profile
Exception Profile: This is the second ProMan profile (see below)
Orders/Documents: This defines per document or order whether it is read and evaluated in ProMan.
Views: Defines which views are displayed in ProMan.
Exception profile. This is optional. It is not assigned directly when ProMan is called up, instead it is
selected via the ProMan profile (see above). The exception profile specifies rules that are evaluated and
the result of this evaluation determines whether the traffic lights are then set to red or yellow. The traffic
lights are displayed on the individual overviews. The rules for exceptions are therefore adjusted to fit theindividual views, such as exceptions for documents, for example.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 305/312
© SAP AG PLM220 8-15
SAP AG 2002
You are now able to
ProMan: Summary
Use ProMan and make the required system
settings
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 306/312
© SAP AG PLM220 8-16
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 307/312
© SAP AG PLM220 8-17
Exercises
Unit: ProMan
Topic: ProMan
1-1 Call ProMan to monitor and control material procurement for your project.
1-1-1 Call ProMan using the following data:
Field Name Input Data
Project definition Your Project
Profile ProMan,
Demonstration, IDES
Question: What do you see on the screen?
Answer: See the solutions.
1-1-2 What is the material group of component T-20230?
Answer: See the solutions.
1-1-3 Reservations have been generated for all components. Look at reservation T-
20100. What is the reservation number and what is the assigned movement
type?
The number of the reservation is: _________________
The movement type is:
1-1-4 Look at the assigned or account assigned orders and documents for your project
and answer the following question.
Question 1: Why are no documents displayed for activity 3000?
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 308/312
© SAP AG PLM220 8-18
Question 2: How many and what type of documents are assigned or account
assigned to your project?
Answer 1: See the solutions.
Answer 2: See the solutions.
1-1-5 Create a purchase order for components T-20100 and T-20210. Use thefollowing data:
Field Name Input Data
Vendor 1000
Company code 1000
Purchasing org. 1000
Purchasing group 001
Question: What is the number of the purchase order?
Answer: See the solutions.
Display the purchase order number in ProMan.
1-1-6 Display the delivery date of the purchase order in ProMan. Then change the
delivery date of the purchase order. Change the delivery date to an earlier date
(for example, one month before the original delivery date).
1-1-7 Optional:
Post a goods receipt for the purchase order in ProMan.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 309/312
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 310/312
© SAP AG PLM220 8-20
Double-click the reservation number in the first row of the component
overview.
The movement type of the reservation is displayed on the top-left of the
reservation.
The movement type is: 281, GI for network
Exit the reservation.
Choose Reservation Exit.
1-1-4 Look at the assigned or account assigned orders and documents for your project
and answer the following question.
Question 1: Why are no documents displayed for activity 3000?
Question 2: How many and what type of documents are assigned or accountassigned to your project?
Choose the Orders/Docs tab page.
Double-click the top WBS element in the navigation area to select it.
Answer 1: The documents are assigned or account assigned to the top WBS
element and not to activity 3000. This is because of the automatic requirements grouping and the default setting of the procurement indicator .
Answer 2: There are already 10 purchase requisitions.
8/11/2019 PLM220 - Project Management Logistics
http://slidepdf.com/reader/full/plm220-project-management-logistics 311/312
© SAP AG PLM220 8-21
1-1-5 Create a purchase order for components T-20100 and T-20210. Use the
following data:
Field Name Input Data
Vendor 1000
Company code 1000 Purchasing org. 1000
Purchasing group 001
Select both components.Select Execute and then the entry Generate purchase order .
Enter the above date and choose Execute.
The purchase order is created automatically.
Question: What is the number of the purchase order?Answer: A dialog box containing the purchase order number appears.
Display the purchase order number in ProMan.
Choose Refresh and scroll to the right.
1-1-6 Display the delivery date of the purchase order in ProMan. Then change the
delivery date of the purchase order. Change the delivery date to an earlier date(for example, one month before the original delivery date).
Select the Dates tab page.Scroll to the right until you can see the Delivery Date Purchase Order column.
In change mode, go to the purchase order.
Select the purchase order number and in the context menu choose Change(right-hand mouse key).
Enter a new delivery date and save the purchase order using the relevant icon.
Choose Refresh to update the data in ProMan.
1-1-7 Optional:Post a goods receipt for the purchase order in ProMan.