Mechanical Systemsl dVirtual Design and Construction
Presenters:
Zach SargentHealthCare Division MangerSuperior Air Handling
Bryan JohnsonPrincipal, HealthCare Capital Engineering Consultants IncSuperior Air Handling Capital Engineering Consultants, Inc
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
1Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
Th “A3”The “A3”:
ISSUE: (in the eyes of the customer) – PROVIDE THE MECHANICAL DESIGN, FABRICATION AND AGENCY REVIEW DOCUMENTS IN THE MOST EFFICIENT MANNER WHILE PROVIDING HIGH QUALITY SERVICE AND PRODUCT
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
2Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
BACKGROUND / CURRENT CONDITIONS
Design Bid Build Design Assist
D i B ild Design Build Integrated Project Delivery, IPD (early development)
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
3Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionPROBLEM STATEMENT / ROOT CAUSE ANALYSISPROBLEM STATEMENT / ROOT CAUSE ANALYSIS
The current systems lend them selves to re‐work, lack of communication between Engineering and Construction, the relationship can be contiguous, there is a low level of cost control and a level of un‐certainty of constructability until after shop drawings are complete.
Design Bid Build
o A lot of re‐ work, Engineer design the design then Trade Partner does shop drawings. o Risk of different interpretation of documents o The Engineer can not optimize the design to the Trade Partner’s strengths. o Contractor’s constructability knowledge is not taken advantage ofo Contractor s constructability knowledge is not taken advantage of.o Low Cost Control
Design Assist o Brings the Trade Partner into Design, but often input is limited to;
Cost control, value engineering, constructability reviews, g g, yo Usually very defined hand offs, o Often still Engineered drawings re‐drawn and developed into shop drawings. o Depending on Team there can be little to no Trade Partner direct Input into the design, to a high level. o Can still be contiguous o Not necessarily any more efficient, unless the Trade Partner’s shop drawings can be incorporated into
the Agency Review Documents. o Does save time by starting Shop Drawings sooner in process.
IPD (early development) o All the benefits of Design Assist, different contracting strategy to encourage more corporative behavior.
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
4Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionPROBLEM STATEMENT / ROOT CAUSE ANALYSISPROBLEM STATEMENT / ROOT CAUSE ANALYSIS
“Responsibility Matrices' ….
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
5Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionPROBLEM STATEMENT / ROOT CAUSE ANALYSISPROBLEM STATEMENT / ROOT CAUSE ANALYSIS
Engineering Drawing ….
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
6Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionPROBLEM STATEMENT / ROOT CAUSE ANALYSISPROBLEM STATEMENT / ROOT CAUSE ANALYSIS
Turns into Trade Partners Fabrication Model ….
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
7Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
PROPOSED SOLUTION / FUTURE STATE Trust Each Other Have common Goals and have them drive the work, don’t let traditional roles drive work Maximize the use of each Partners Strengths Completely eliminate waste associated with the Design/Detailing/Modeling process. Seamless digital exchange between the engineer and contractor.g g g Engineer & Contractor both working on the same model without translation and data issues. Achieve transparency in engineering and fab/install related data. Real time deep collaboration. Real Time Cost of Construction Input into design and engineering – Model Based Estimating Conduct work so that the rest of the Team can’t distinguish between Engineer and Trade Partner Value Conduct work so that the rest of the Team can t distinguish between Engineer and Trade Partner Value Constructability and Engineering Review in real time. Learn and grow Trust Each Other Have a good time
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
8Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
O OS SO O / SPROPOSED SOLUTION / FUTURE STATE
Matrix of Shared Responsibility – TrustShared Responsibility Matrix
Primary Secondary
E C
ItemResponsibility
HVAC Calcs, sizing criteria, air flows and equipment selectionModeling of HVAC Systems E & CDesign within Model E CConstructability within Model C EClash Detection / Overhead Coordination E & C TDetails Concept E CDetails Constructability C EControls and Energy Mgmt System V E & CSeismic Restraint Design and OSHPD Deliverable V E & CFinal Equipment Vendor C EProduction of OSHPD Deliverables E CDetailed fabrication drawings C E
RESPONSIBLE PARTY ABBREVIATIONSRESPONSIBLE PARTY ABBREVIATIONSE: Engineer (Capital Engineering Consultants)C: Contractor (Superior Air Handling)V: Vendor / equipment supplierA: Architect (Devenney)G: General Contractor (DPR)T: IFOA Team
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
9Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
O OS SO O / SPROPOSED SOLUTION / FUTURE STATE
Mapping the Design Process – Transparency
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
10Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
O OS SO O / SPROPOSED SOLUTION / FUTURE STATE
Digital Work Flow – Eliminate Process Waste
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
11Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
IMPLEMENTATION PLAN Spend the effort to get to know each other, personally, professionally, and corporate, including corporate culture. Trust and Respect each other Understand what work needs to be done (Value Added), and spend time planning how to do it efficiently with built
in qualityin quality. Utilize a common digital / BIM platform and storage platform (ProjectWise)
o Do common training in collaborating using these tools for BIM o Do common investigation and training using these tools for model based cost estimating
Early discussions and agreement on fabrication Criteria Early discussions and agreement on specifications and design / sizing criteria Early discussions and agreement on specifications and design / sizing criteria Regular (almost daily) communication utilizing all methods;
o In‐Person o Phone o Web Meetings
Push this deep into the Trade Partner and Engineering project Team p g g p j Maximize use of “standard work” Allow the most appropriate person to answer questions and provide information to the rest of the Project Team Regular and real time cost of design evaluations Don’t be afraid to try something new. Laugh on a regular basis Laugh on a regular basis
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
12Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionIMPLEMENTATION PLAN
Team Developed Mechanical Model Production Cycle - Planning
IMPLEMENTATION PLAN
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
13Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionIMPLEMENTATION PLAN
And Deeper Planning
IMPLEMENTATION PLAN
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
14Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionIMPLEMENTATION PLAN
Digital Work Flow – Use Technology
DATABASE DRIVEN
IMPLEMENTATION PLAN
ENGINEERING CONTENT CAD‐MEP
FABRICATION CONTENT CAD‐DUCT / CAD‐MECH
DATABASE DRIVEN
DESIGN LINE
ENGINEERING ANALYSIS FABRICATE
VERIFY GEOMETRY APPROVE
MODEL DRIVEN
INSTALLCONSTRUCTABILITY REVIEW
CODE COMPLIANCE
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
15Capital Engineering ConsultantsSuperior Air Handling
MODEL DRIVEN
Mechanical Systems ‐ Virtual Design and ConstructionIMPLEMENTATION PLAN
Utilize BIM – Cost Control, Extract Multiple Deliverables
IMPLEMENTATION PLAN
view
y
DO
Cs
= atio
n C
s
Rev
Age
ncy =
Fabr
icD
OC
PIECE NUMBERSDIMENSIONSPICKOFFS ETC.
CODE COMPLIANCEPERMIT TO BUILD
OWNERS RECORD DOCMENTS
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
16Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and ConstructionIMPLEMENTATION PLANIMPLEMENTATION PLAN
“Design Line” – Common Communication
BIM Model – Multiple Deliverables
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
17Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
CHALLENGES / FOLLOW‐UP
Challenges – Technology, Technology, Technology Follow up – Monitor; $$ Spent, judge quality and constructability, frequent self‐evaluation and correction, re‐
plan, review previous plans for stand work.
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
18Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
CHALLENGES / FOLLOW‐UP
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
19Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
CHALLENGES / FOLLOW‐UP
Monitor $$ Spent
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
20Capital Engineering ConsultantsSuperior Air Handling
Mechanical Systems ‐ Virtual Design and Construction
Results
Leveraging Virtual Design & Construction for Lean Project DeliveryLean Design Forum ● St. Louis, MO ● June 18, 2009
21Capital Engineering ConsultantsSuperior Air Handling