planning - weebly · preliminary planning 17 preliminary planning is a quick overall picture of the...

30
PLANNING Ahmed Elyamany, PhD

Upload: others

Post on 24-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

PLANNING

Ahmed Elyamany, PhD

Page 2: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Lecture Topics

Benefits of Planning

Use of Project Plan

Problems with “Day-to-Day” Planning

Problems Caused By Not Planning

Definition of “Activity”

Activity durations

Sequencing Activities

2

Page 3: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

The Project Life Cycle

The project life cycle consists of four phases

Project Initiation

Project Planning

Project Execution

Project Closure

3

Page 4: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Develop a business case

Undertake a feasibility study

Establish the terms of reference

Appoint the project team

Setup a project office

Project Phases-project Initiation

4

Page 5: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Create a Project plan

Create a Resource plan

Create a Financial plan

Create a Quality plan

Create a Risk plan

Create a Acceptance plan

Create a Communication plan

Create a Procurement plan

Contract the suppliers

Project Phases-project Planning

5

Page 6: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Project Phases-project Execution

Implementing the plans created during the project planning phase.

The deliverables being monitored and controlled during execution.

All deliverables have been produced

The customer has accepted the final solution

The project is ready for closure.

6

Page 7: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Project Phases-project Closeout

Releasing the final deliverables to the customer

Handing over project documentation to the business,

Terminating supplier contracts

Releasing project resources

Communicating the closure of the project to all

stakeholders

7

Page 8: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Planning

8

The Development of a workable program of operations

to accomplish established objectives when put into

action.

Page 9: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Planning

Planning is important to managing a construction project.

Done before project starts

The plan needs to be communicated.

Planning for: Construction process

Jobsite safety

Jobsite layout

Workforce

9

Page 10: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Planning need ..

Decision making

Information gathering

Identifying/defining activities

Creativity

Flexibility

Interrelationships

10

Page 11: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Benefits of Planning

Able to analyze the entire project

Efficiencies gained from planning:

Saving cost

Saving time

Increase quality

Reduces problems

Avoid work conflicts

Ensures safety

11

Page 12: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Problems with “Day-to-Day” Planning

Wasted time Labor cost

Longer construction time

Possible rework Not anticipating future work

Cost and time impact

Inadequate project quality

Conflicts between subcontractors

Safety planning gets overlooked

12

Page 13: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

How Planning Was Successful

Savings:

Cost

Time

Quality improvements

Solved problems

Avoided problems

13

Page 14: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

What did inadequate planning do?

Delayed project

Incurred additional costs

Labor

Material

Strained relations with Architect/Engineer

Strained relations with rebar supplier

14

Page 15: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Problems Caused By Not Planning

Additional costs

Project delays

Conflicts with other parties

Quality problems

15

Page 16: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Who Needs Planning

16

Owner

Designer

Contractor

Pre-tendering planning

Project Planning

Page 17: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Preliminary Planning

17

Preliminary planning is a quick overall picture of the

project and the capacity of the unit to accomplish it.

Serves as a guide for detailed planning.

Includes preliminary material and equipment estimates,

and procurement of critical items, identify work activities.

Page 18: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Detailed Planning

18

Detailed planning includes:

Reviewing project specifications and drawings.

Detailed estimates of resources,(i.e. equip. hours).

Scheduling work activities.

Procurement of materials.

Page 19: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Steps of Planning

19

Define Work Tasks

Choose Method of Construction

Estimating Activities Resources

Determine Activities Durations

Arrange Activities in Logical Sequence

Coding System

Planning technique

Page 20: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Work Breakdown Structure (WBS)

20

A task-oriented "family tree" of activities, which organizes,

defines, and graphically displays the work to be

accomplished.

Page 21: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

WBS Steps

21

Listing of project tasks to be performed

Starts at the major project view

Next the major phase levels are added

Then details for each phase are added

Page 22: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Project Tree

22

P

P1 P2

P1.1 P1.2 P2.1 P2.2

P2.2.1 P2.2.2

Page 23: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

WBS Construction

23

There are many ways of breaking down the activities in a

project, but the most usual is into:

Work packages

Tasks

Deliverables

Milestones

Page 24: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

An Activity...

Is a specific task

Has a beginning and an end

Has a duration

Usually consumes resources

Material, labor, equipment, subcontractors

24

Page 25: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

An Activity...

Is assignable (someone does it)

Is measurable in quantity or time

Has a relationship to other activities

Has delivery associated with it

25

Page 26: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Activity Scope

Relates to quantity of installation and time

Relates to size of project

Relates to crew size and number of crews

Relates to detail required by contract documents

Relates to the amount of jobsite control of the schedule

26

Page 27: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Comparison of Activity Detail

Form and pour footings

footings layout

footings Forms

footings rebar Installation

footings pouring

footings form removal

27

Page 28: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Duration of Activities

28

The amount of time between the start and the finish of the activity

Usually in “days”, “Day” = working day

Need to make accurate estimate of time

Account for minor delays in activity duration

Activity Duration = Work Quantity

No. of Crew x Production Rate

Page 29: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Sequencing Activities

Assemble activities in “logical sequence”

How are we going to build the project?

No right or wrong way

Always trying to be efficient

Continuous flow of work

29

Page 30: PLANNING - Weebly · Preliminary Planning 17 Preliminary planning is a quick overall picture of the project and the capacity of the unit to accomplish it. Serves as a guide for detailed

Questions?

http:\\drahmedelyamany.weebly.com

[email protected]

30