planning of seip activities for delhiseip.urban-industrial.in/live/hrdpmp/hrdpmaster/...12.08.2015...
TRANSCRIPT
Page 1
Implemented by
Page 1
Planning of SEIP Activities for Delhi [Sustainable and Environment-Friendly Industrial Production Project]
SEIP Planning Workshop,
September 01, 2016
Page 2
Implemented by
Page 2
Overall Aim
“Private and public stakeholders jointly implement
strategies for efficient, and environmental & climate-friendly
industrial development”
Reduction of pollution by 20%
- Surroundings of industrial areas
- River Ganga, River Yamuna, River Damanganga
New measures in policies/plans/programmes
Replication/scaling up SEIP Planning Workshop, September 01, 2016
Page 3
Implemented by
Page 3
S No Date Meeting / Activity
2. 29.06.2015 MoEFCC sent letter to Chief Secretaryof Govt. of Delhi for
participation in SEIP Project .
3. 10.08.2015 GIZ made project presentation to Shri Sanjiv Kumar (Secretary-
Environment and Forest)
4. 12.08.2015 GIZ had meeting with MD-DSIIDC (Mr. Sanjeev Ahuja) to explain the
Project
5. 01.09.2015 Visit to OKHLA CETP
6. 02.09.2015 GIZ made presentation at stakeholders meeting at DSIIDC
DPCC, Parparganj Industrial Association, GIZ and CEPT societies
ware present.
7. 14.10.2015 MoEFCC sent reminder letters to Chief Secretaries of Govt. of Delhi
8. 19.10.2015 Visit by GIZ team to Mayapuri CETP
Important Dates
SEIP Planning Workshop, September 01, 2016
Page 4
Implemented by
Page 4
S No Date Meeting / Activity
9. 04.11.2015 Meeting with General Secretary, Mayapuri CETP
10. 20.11.2015 Meeting with DSIIDC (Shri Arun Mishra, ED)
11. 21.12.2015 Meeting called by DSIIDC (With GIZ, GoNCTD, National Productivity
council)
12. 03.02.2016 Visit to Parparganj Industrial area
13. 09.02.2016 Meeting with PFEA for Prioritisation of Activities for Delhi under
14. 10.02.2016 Meeting with Secretary (DoNCTD)
15. 19.04.2016 Meeting with PFEA in presence of DSIIDC for Environmental
Improvement Drive
16. 21.04.2016 Final Report Submission by NPC on Waste and Waste Water
Management in CETPs in Delhi
SEIP Planning Workshop, September 01, 2016
Important Dates
Page 5
Implemented by
Page 5
S No Date Meeting / Activity
17. 17.05.2016 Meeting with PFEA to Finalise schedule for Environment Improvement
Drive and discussion of Industrial Survey form
18. 31.05.2016 Meeting with PFEA for further discussion on Environment Improvement
Drive and Industrial Survey
19. 06.06.2016 Environment Drive Launch in Patpargunj Industrial Area
20. 25.07,2016 IIT KGP Interns Report Submission on Patpargunj Indutrial Area
SEIP Planning Workshop, September 01, 2016
Important Dates
Page 6
Implemented by
Operational Planning
Session 1:
SEIP Planning Workshop, September 01, 2016
Page 7
Implemented by
SEIP Planning Workshop, September 01, 2016
Operational planning
Activities to be taken up on priority basis
The milestones/targets for each activity
Time lines/ Responsible persons/
Resources
Page 8
Implemented by
SEIP Planning Workshop, September 01, 2016
List of agreed activities under SEIP project
1. Planning of new CETP/STP, Recycle/reuse
2. Environment Improvement in Industries
3. Online/Continuous Monitoring System
4. Skills Development – ETP/CETP Operators (Helpers, Technicians)
5. Other activities for Delhi
6. Complementary Activities of SEIP project
Page 9
Implemented by
Pro
ble
m
Inadequate water supplies to industries
Storm water drainage has potential to cause pollution
Wastewater discharges to nallah, ultimate discharge to Yamuna
ZLD, recycle/reuse to be achieved
20%
red
ucti
on
of
po
llu
tio
n
Rep
licati
on
gu
ideli
nes
Po
lic
y m
easu
res f
or
ZL
D
Actio
ns ta
ke
n
Scoping of GIZ’s Technical Cooperation done
Tender in process. International experts to start work in Feb.2017
Survey Formats developed – discharges data collection will be
done by GIZ team
Baseline infrastructure report prepared by IIT, KGP interns
Pro
po
se
d m
ea
su
res
Design/redesign retrofitting of wastewater conveyance and storm
water drainage
Proposal for new CETP /STP (centralised/decentralised)
ZLD solutions - recycle/reuse of treated wastewater
Pollution reduction measures (20% reduction target)
SEIP Planning Workshop, September 01, 2016
❶ Planning of new CETP/STP, Recycle/reuse
Page 10
Implemented by
Tasks
1. Conveyance systems for waste water □ Secondary information collection – drainage/conveyance designs & specifications
(GIZ, DSIIDC)
□ Survey and mapping (GIS) of existing conveyance, stormwater drainage network
(GIZ, DSIIDC)
□ Identification of problematic stretches for upgradation (GIZ, DSIIDC)
□ Assessment of baseline pollution levels (GIZ)
□ Assessment of improvement needs in conveyance, stormwater drainage (GIZ,
PFEA, DSIIDC)
2. Industry inventory a) 24-hr flow profiling of industries
□ develop questionnaires (GIZ)
□ circulation of questionnaires (PFEA)
□ survey of sample industries (GIZ)
□ completion of survey (GIZ)
b) Inventory of ETPs (GIZ, PFEA)
c) Selection of ETPs for upgradation/modernization (GIZ, PFEA)
d) Inventory of water requirements (GIZ, PFEA)
SEIP Planning Workshop, September 01, 2016
Page 11
Implemented by
Tasks
3. Water recycle/reuse potentials □ Inventory of requirements – industry, horticulture etc. (GIZ, PFEA)
4. Engagement of international consultants
□ Engagement of consultants (GIZ)
□ Proposal of solutions
□ Implementation of solutions (PFEA, DSIIDC)
□ Replication measures (PFEA, DSIIDC)
5. Monthly Facilitation Meetings
(Information exchange on improving ETPs, ZLD, experience sharing etc.) □ Organize monthly meetings (PFEA)
□ Follow-up (GIZ)
□ Document success stories on pollution reduction (GIZ)
SEIP Planning Workshop, September 01, 2016
Page 12
Implemented by
Tasks
6. Month long environmental drives (two events in a year)
(for cleaning up drains, sewers, repairs, maintenance)
7. Participation in International/National events on wastewater /waste
management (seminars, trade fairs etc.)
SEIP Planning Workshop, September 01, 2016
Page 13
Implemented by
SEIP Planning Workshop, September 01, 2016
❷ Environment Improvement in Industries
Pro
ble
m
Problems of inefficiency, pollution, non-compliance
20%
red
ucti
on
of
po
llu
tio
n
Reso
urc
e e
ffic
ien
cy
Rep
licati
on
gu
ideli
nes
Actio
ns ta
ke
n
Formats developed - survey of industries to be initiated by GIZ team
Scoping of services developed.
Tender in process. International experts to start work in January
2017
Pro
po
se
d m
ea
su
res
Monthly meetings are to be conducted with industries for knowledge
exchange and to promote Best Available Techniques (BAT).
Detailing of solutions (target – 10 industries) by German experts.
Support during implementation of solutions in industries (20%
pollution reduction target)
Enable replication of successful models in other industrial areas.
Page 14
Implemented by
1. Inventory of industries □ develop questionnaire (GIZ)
□ circulation of questionnaire (PFEA)
□ survey of sample industries (GIZ)
□ completion of survey (GIZ)
2. Monthly Facilitation Meetings (Information exchange on BAT, experience sharing etc.)
□ Organize monthly meetings (PFEA)
□ Follow-up (GIZ)
□ Document success stories on pollution reduction and resource efficiency (GIZ)
3. Month long environmental drives (two events in a year)
(environment drives for improvements in industries)
SEIP Planning Workshop, September 01, 2016
Tasks
Page 15
Implemented by
4. Engagement of international consultants □ Engagement of consultants (GIZ)
□ Providing of solutions (GIZ)
□ Implementation of solutions (PFEA, industries)
□ Replication measures (PFEA, DSIIDC)
SEIP Planning Workshop, September 01, 2016
Tasks
Page 16
Implemented by
SEIP Planning Workshop, September 01, 2016
Pro
ble
m
Online monitoring required for 33 categories of industries, CETP,
industries discharging to Yamuna
Problems in identifying suppliers, calibration, reliability etc.
Imp
roved
co
mp
lian
ce
Gu
ideli
nes b
y C
PC
B
Actio
ns ta
ke
n
International experts identified. Work to start in Sept. 2016
TORs shared with DSIIDC, CPCB, DPCC, CETP operator
TORs shared with German agencies (UBA, DWA, GWP)
Pro
po
se
d m
ea
su
res
Survey of industries and CETPs/ETPs is to be taken up using the
questionnaire on the online system by GIZ team.
Study of existing system at individual industries and CETPs is to be
carried out.
Recommendations - online monitoring system for ETPs/CETPs,
analyzers, parameters, receiving waterbody; data acquisition and
display
Training and capacity building of stakeholders are required.
Policy analysis and advice to CPCB on the effective way of
implementing and using the online monitoring systems in industries.
❸ Online/ Continuous Monitoring System for ETPs/CETP
Page 17
Implemented by
SEIP Planning Workshop, September 01, 2016
Online Monitoring Portal of
Wazirpur Industrial Area CETP
Online Monitoring System
Installed in Lawrence Road
CETP
No online monitoring systems in Patparganj
Industrial Area
Page 18
Implemented by
SEIP Planning Workshop, September 01, 2016
Pro
ble
m
ETPs/CETPs lack certified operators
GoI is promoting skills development
6 training institutions affiliated already by SCGJ/NSDC
Skil
ls d
evelo
pm
en
t
20%
red
ucti
on
of
po
llu
tio
n
Po
licy m
easu
res
Actio
ns ta
ke
n
QPs for ETP/CETP Helpers, Technicians brought by SCGJ
ToT conducted by GIZ through international expert
DWA (German Water Association) contracted by GIZ
Occupation mapping for other jobs initiated through NPC Delhi
Pro
po
se
d m
ea
su
res
The baseline surveys are to be conducted by GIZ team.
6-day skills development programme ongoing in Vapi for helpers
and technicians.
The performance of operators need to be analysed and monitored
before and after skills development programmes.
Skills competition is to be organised for teams at IFAT trade Fair
Mumbai on Sept. 30, 2016.
❹ Skills Development – ETP/CETP Operators (Helpers,
Technicians)
Page 19
Implemented by
SEIP Planning Workshop, September 01, 2016
Glimpse of Skilling Programme in Vapi: August 29 - September 3, 2016
Page 20
Implemented by
Skills Demonstration event at IFAT Mumbai 2015
SEIP Planning Workshop, September 01, 2016
Page 21
Implemented by
NSDC - Qualification Packages (QPs)
SEIP Planning Workshop, September 01, 2016
Page 22
Implemented by
SEIP Planning Workshop, September 01, 2016
Tasks
1. Inventory of Qualifications of Technicians and Helpers □ develop questionnaire (GIZ)
□ circulation of questionnaire (PFEA)
□ survey of sample industries (GIZ)
□ completion of survey (GIZ)
2. Participation in skills courses and competitions □ Courses to be organised by GIZ (GIZ)
□ Participants (upto xx nos.) from Patpargnaj (PFEA)
□ Post training survey (GIZ)
Page 23
Implemented by
Pro
ble
m
Lacking well defined management structure for Industrial Areas
Lacking Action Plan for industrial pollution to River Yamuna
Inadequate awareness and participation by industries
Solid waste management in Patparganj Industrial Area
Cap
acit
y b
uild
ing
/de
ve
lop
men
t
Actions taken
Planning students from IIT Kharagpur prepared a report and drawings on
Patparganj Industrial Area.
Waste and Wastewater Management of CETPs located in Delhi , report
prepared by Environment Management Group,NPC Delhi.
Environmental drive – initiated in June 2016 in Patparganj Industrial Area
Pro
posed m
ea
sure
s
Management structures for Patparganj Industrial Area and Lawrence Road
Industrial Area are to be proposed by German experts.
Inventory, GIS based mapping of industrial pollution in Yamuna is to be
completed.
Strategic/Action Plan is to be developed for industrial pollution control to River
Yamuna.
Environmental drives, workshops, meetings, conferences are to be organised
for increasing awareness and information/knowledge sharing.
❺ Other Activities for Delhi
SEIP Planning Workshop, September 01, 2016
Page 24
Implemented by
SEIP Planning Workshop, September 01, 2016
Solid Waste Dumping around Ghazipur Drain (May/June 2016)
Solid Waste Dumping in Patparganj Industrial Area (May/June 2016)
Page 25
Implemented by
SEIP Planning Workshop, September 01, 2016
Removal of debris and waste from
the park and its surroundings
Environment improvement drive : Patparganj Industrial area
Redevelopment of the Central Park (June/July 2016)
Plantation in the park
as a part of plantation drive Park after plantation
Page 26
Implemented by
SEIP Planning Workshop, September 01, 2016
Environment improvement drive : Patparganj Industrial area;
Redevelopment of the Central Park
Before
After
Page 27
Implemented by
1. Management structure □ Engagement of German consultants (GIZ)
□ Solutions from the German experts (GIZ)
□ Consultations and finalization (GIZ)
□ Implementation (DSIIDC)
2. Waste management
a) Inventory of computable waste; b) Inventory of recyclable waste (plastic,
paper etc.) □ develop questionnaire (GIZ)
□ circulation of questionnaire (PFEA)
□ survey of sample industries (GIZ)
□ completion of survey (GIZ)
c) Implementation of solutions □ Engagement of consultants (GIZ)
□ Implementation (PFEA, DSIIDC)
SEIP Planning Workshop, September 01, 2016
Tasks
Page 28
Implemented by
3. Environmental improvement drives (June/July and November) □ Proposal on activities (GIZ)
□ Finalisation by Task Force (PFEA)
□ Implementation of the drive (PFEA)
□ Documentation (GIZ)
SEIP Planning Workshop, September 01, 2016
Tasks
Page 29
Implemented by
SEIP Planning Workshop, September 01, 2016
❻ Complementary Activities of SEIP Project
Pro
ble
m
Technology transfer on industrial wastewater and waste - lack of
access to information and transfer mechanisms
Pollution index exists for industrial estates, but rating on
infrastructure basis doesn’t exist
Cap
acit
y b
uil
din
g/d
evelo
pm
en
t
Actio
ns ta
ke
n
Concept note for Technology platform submitted to MoEFCC and
approved in principle
Consultant engaged for pre-feasibility study of green rating systems
for industrial parks in India
Pro
po
se
d m
ea
su
res
Establishment of an industry-led Environmental Technology Platform
based on a viable business model
Green rating and certification system for industrial areas
Policy measures
Upscaling/replication of successful models
Page 30
Implemented by
German Green Rating System for Industrial Areas
SEIP Planning Workshop, September 01, 2016
Page 31
Implemented by
Innovative tools developed for planning
new industrial parks and retrofitting exiting
industrial areas/zones
SEIP Planning Workshop, September 01, 2016
Page 32
Implemented by
Stakeholders and their roles
for Patparganj Industrial Area
Session 2:
SEIP Planning Workshop, September 01, 2016
Page 33
Implemented by
SEIP Planning Workshop, September 01, 2016
DSIIDC
PFEA
GIZ
CPCB
MoEFCC
DPCC
DIPP/MoC&I
MoMSME
MoEFCC CETP
Funding
Page 34
Implemented by
Steering Structures
Session 3:
SEIP Planning Workshop, September 01, 2016
Page 35
Implemented by
SEIP Planning Workshop, September 01, 2016
National Level Project Steering Committee at MoEFCC
State level Project Steering Committee at DSIIDC
Site level Project Advisory Group/Task Force
Page 36
Implemented by
SEIP Planning Workshop, September 01, 2016
Project Steering Committee (PSC), National
Review & monitor progress, decisions, replication/policy measures
Twice a year
Page 37
Implemented by
Project Steering Committee (PSC), Delhi
SEIP Planning Workshop, September 01, 2016
Managing Director, DSIIDC or Secretary,
Industries Department Chairman
Member Secretary, DPCC Member
Reps. of CETP societies Member
Reps. of industry associations, industries
(PFEA etc.) Member
Chief Engineer, DSIIDC Member Convener
Review & monitor progress, decisions, replication/policy measures
Twice a year
Page 38
Implemented by
Project Advisory Group/Task Force
President PFEA OR Chief Engineer, DSIIDC Chairman
Rep. of DSIIDC Member
Rep. of PFEA (5 nos.) Members
Rep. from DPCC Member
Rep. of GoNCT Delhi Member
Others??? Member
GIZ representative Member
Rep. of PFEA Member Convener
SEIP Planning Workshop, September 01, 2016
Monthly
Page 39
Implemented by
Functions
□ Review and monitor project progress
□ Foster implementation of activities and solutions
□ Decisions as may be necessary for project progress and achieving
results
SEIP Planning Workshop, September 01, 2016
Meeting on every first Wednesday of the month (2 pm to 4 pm?
Page 40
Implemented by Implemented by
SEIP Planning Workshop, September 01, 2016
Thank You