planning case law update - 39 essex chambers · based on papers by stephen tromans qc, john...
TRANSCRIPT
![Page 1: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/1.jpg)
1
Planning and Environment Case Law Update
Richard Harwood QC, Martin Edwards and Caroline Allen
Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard
Wald, Rose Grogan and Ned Helme
PLAN-MAKING
Tesco challenged the decision of the local planning authority to grant planning permission to
a competitor for the development of an out-of-centre superstore which was only 800m from
the local Tesco. Tesco argued that the grant of planning permission was based on a
misunderstanding of one of the policies in the development plan.
Tesco Stores v Dundee City Council [2012] UKSC 13
1
1 The particular issue of interpretation before the court was: did “suitable” mean “suitable for the development proposed by the Applicant” (as the Council contended), or “suitable for meeting identified deficiencies in retail provision in the area” (as Tesco contended).
The main issue in the case
was whether it is up to the court to interpret the meaning of policies in the development plan
or whether a local authority may adopt its own interpretation which will be immune from
challenge except on Wednesbury principles.
The Supreme Court held that in principle, policy statements should be interpreted objectively
in accordance with the language used read in its proper context. The meaning of a policy is a
matter for the court to interpret. The application of a particular policy to a particular set of
facts falls within the judgment of the local planning authority and can only be challenged on
the basis of irrationality. Such an error in interpretation would only be material if there was a
real possibility that determination of the application might otherwise have been different.
![Page 2: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/2.jpg)
2
Before this case, it was considered settled law that the interpretation of planning policy was
primarily a matter for the decision maker.2Following the Tesco case, there is now scope for
challenges to planning decisions on the grounds that the decision maker has erred by
misinterpreting a relevant policy.
Tesco has since been followed by the Court of Appeal in R (on the application of TW
Logistics) v Tendring District Council and Anglia Maltings (Holdings) Ltd (CA) [2013]
EWCA Civ 9.
The Court granted the application despite the defendant’s argument that it had no jurisdiction
because the challenge was not in accordance with the provisions of s.113 Planning and
Compulsory Purchase Act 2004 (“PCPA 2004”). Lindblom J held that the ouster clause in
s.113(2)
The Manydown Company Ltd v Basingstoke and Deane BC [2012] EWHC977
This case concerns antecedent documents to Development Plan Documents. The claimant
applied for judicial review of the defendant local authority’s decision to promote a site as
available for development. In 2005, the local authority had unsuccessfully promoted the site
for development and in 2006 it suspended its involvement in promoting the site. In 2010, a
housing land availability assessment concluded that the site was likely to be available for
development. The local authority refused to reconsider its decision to cease promoting the
site for development. In 2012, during the process of preparing a core strategy, the council’s
pre-submission draft core strategy set out sites selected for the promotion of development and
the claimant’s site was not included. The pre-submission core strategy was approved for
consultation and the claimant initiated judicial review proceedings.
3
2 See R v Derbyshire DC ex parte Woods [1997] JPL 958 3S.113(2) A relevant document must not be questioned in any legal proceedings except in so far as is provided by the following provisions of this section. (3) A person aggrieved by a relevant document may make an application to the High Court on the ground that–
(a) the document is not within the appropriate power; (b) a procedural requirement has not been complied with.
must be interpreted strictly. The pre-submission draft core strategy was not a
![Page 3: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/3.jpg)
3
relevant document and the challenge was against two decisions which were antecedent to the
statutory process.
Lindblom J’s approach in this case requires local planning authorities to give careful
consideration to protecting themselves from public law challenges in the earlier stages of
preparing Development Plan documents. Such challenges will inevitably cause delay to the
process. In the Manydown Ltd case itself, the Core Strategy is still in the pre-submission
stages, with further consultation due in Spring 2013.
RSS
The court held that the lawfulness of North Herts’ decision could not be indirectly challenged
by applying to quash the Inspector’s decision. The Inspector did not have jurisdiction to
determine the lawfulness of North Herts’ decision and therefore was required to examine
Stevenage’s core strategy on the basis that North Herts had acted lawfully. Development Plan
R (on the application of Stevenage BC) v SSCLG& North Herts DC [2011] EWHC 3136
This case concerns the impact of the revocation of RSS on the preparation of local plans.
Stevenage BC applied to quash the decision of a planning inspector that its core strategy was
unsound. A large proportion of housing planned under Stevenage’s strategy was to be built in
the neighbouring local authority, North Hertfordshire. When the Secretary of State
announced his decision to revoke RSS, North Hertfordshire decided not to co-operate in
achieving the RSS aim of growth for Stevenage. It planned to submit its core strategy after
RSS had been revoked. The Inspector concluded that because the housing numbers could no
longer be achieved, Stevenage’s core strategy was unsound. Stevenage argued that the
Inspector had erred by finding that North Hertfordshire was entitled to take into account the
revocation of RSS given that the decision in Cala Homes held that it was unlawful for local
authorities to prepare development plan documents to take the planned revocation of RSS
into account.
(4) But the application must be made not later than the end of the period of six weeks starting with the relevant date.
![Page 4: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/4.jpg)
4
documents must be in conformity with national policy but there is no requirement that earlier
steps or decisions also have to be in conformity. The relevant date is when the plan is
submitted for examination. The inspector was entitled to take North Herts’ decision into
account and could not lawfully have ignored the impact of the uncertainty caused by such a
decision because the concept of soundness includes practical implementation.
The treatment of co-operation in this case is of significant interest in seeking to understand
how the duty to co-operate created by section 110 of the Localism Act 2011 will operate. The
NPPF also encourages strategic planning across local boundaries. The exact requirements of
the duty in the Localism Act and provision in the NPPF are yet to be defined, and may be a
fruitful source of litigation in the future.
In mid-February 2012, the Secretary of State signed a consent order quashing his decision.
The Secretary of State conceded that he had erred in law by failing to give adequate reasons
when considering the effect that the SEA process should have on the weight to be attached to
the proposed revocation of RSS. So, ultimate success goes to Cala Homes in this protracted
litigation
Barton Farm (consent order)
The Secretary of State rejected the landowner’s application for permission to build 2000
houses on greenfield land at Barton Farm, Winchester, despite the recommendation from the
inspector to grant planning permission. The Secretary of State concluded that it was
premature to grant the application on the grounds that it would undermine local plan making
because the council’s emerging core strategy and consultation needed time to develop.
4. The Secretary of State granted planning permission for Barton Farm in autumn
2012.
4That started with
Arun District Council v SSCLG & Green Lodge Homes LLP (QBD, unreported, 25 January
2013)
R. (on the application of Cala Homes (South) Ltd) v Secretary of State for Communities and Local Government [2010] EWHC 2866 (Admin) and ended with a decision letter granting planning permission upon the basis of a lack of an adequate five year housing and supply.
![Page 5: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/5.jpg)
5
Here, a first appeal had rejected a housing proposal for being within a strategic gap and
contrary to the South-East Plan. Following the first Cala case, that decision letter had been
quashed by consent and the appeal remitted to a second inspector. She considered matters
afresh, concluded that Localism Act should be given limited weight because environmental
assessments were still taking place regarding the revocation of RSS and granted consent.
Dismissing the appeal the High Court found no error in the inspector’s reasoning.
R (on the application of Hinds) v Blackpool BC (CA) & Kensington Developments Ltd [2012]
EWCA Civ 466
The claimant applied for permission to apply for judicial review of the local authority’s
decision to grant outline planning permission for a residential development. The resolution to
grant planning permission was made in March 2010 and the decision was published in July
2010. In May 2010, the SSCLG wrote to local planning authorities informing them of the
government’s intention to revoke RSS. The claimant sought permission to apply for judicial
review on the basis that 1) the local authority ought to have referred the application back to
the planning committee in light of the government’s announced change in national planning
policy; and 2) the council had failed to take into account the decision to revoke RSS, which
was a material consideration.
The judge held that while the decision to revoke RSS could be a material consideration even
though it was subsequently held to be ineffective, on the facts of this case the decision had
been made on the basis of local planning strategies and provision of affordable housing. The
revocation of RSS would have had no effect on the planning committee’s decision. The Court
of Appeal dismissed the appeal on the basis that the emerging policy was not a material
consideration for this particular planning application and there was no evidence to show that
the judge had erred in concluding that the government’s emerging policy was not a material
consideration because a material consideration has to be something which is capable of
tipping the balance.
Fox Strategic Land and Property Limited v Secretary of State for Communities and Local
Government & Cheshire East Council [2012] EWHC 444 and [2012] EWCA Civ 1198 (CA).
![Page 6: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/6.jpg)
6
The Secretary of State refused an appeal against the refusal of planning permission on the
basis that while the proposed housing development would contribute towards meeting a
shortfall in housing land (and therefore was compliant with the RSS post-Cala Homes), that
benefit was outweighed by the proposal’s conflict with saved development plan policies in
respect of settlement boundaries and restrictions on development in the countryside. His
decision was inconsistent with a previous decision he had made in respect of a similar
development in the same town. In particular, he raised new points such as prematurity and
localism. No explanation was given for the difference in approach. The Secretary of State did
not address the apparent conflict between the two decisions and instead concluded that his
earlier decision carried no weight.
The High Court granted the claimant’s challenge on a number of grounds. First, the Secretary
of State had erred by failing to give weight to his previous decision. The two cases were
concerned with very similar facts and the Secretary of State could not, without giving clear
reasons, determine one appeal in a way that was contradictory to another. No reasons were
given for the Secretary of State’s conclusion in one case that the application conflicted with
spatial policy objectives and in the other that a very similar application did not. Secondly, the
Secretary of State had failed in his earlier decision to mention the “prematurity” argument
and the effect that granting permission would have on the local development framework
process. Finally, the Secretary of State had failed to apply the correct test in PPS7 (loss of
agricultural land). HHJ Gilbart QC also commented that when the Secretary of State is faced
with two appeals relating to similar proposals in the same town, he would significantly
reduce the risk of inconsistent decisions if he heard the appeals together.
The Secretary of State appealed to the Court of Appeal. The Court of Appeal dismissed the
appeal on similar grounds to the High Court. Again, the Court of Appeal stressed the need for
consistency in the planning process and deciding like cases alike. A decision-maker is free to
disagree with a previous decision but he must have regard to that decision and give reasons
for departing from it. However, the Court of Appeal disagreed with the High Court that the
Secretary of State had failed to apply the correct test in PPS7. On reading the decision letter
as a whole it was clear that he had taken the correct approach to the policy and one instance
of a hyperbolic expression was not a ground for quashing the decision. In any event, as the
![Page 7: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/7.jpg)
7
judge below held that the approach to PPS7 was not a sufficient reason to quash the decision,
there was no reason to allow the appeal and restore the Secretary of State’s decision5
Environmental Impact Assessment
EIA is an area that continues to generate a significant proportion of environmental law
litigation. This is likely to continue in the near future, although in the medium term it
is possible that the volume of case law will be reduced by amendment to the EIA
Directive.
Proposed amendment to the EIA Directive
The EIA Directive has been in existence for over 25 years and is considered by the
European Commission to be in need of a "comprehensive overhaul". On 26 October
2012 the Commission published a draft Directive proposing various amendments to
the current Directive (2011/92/EU). The most significant are:
.
a. Changing the definition of "project" in Art 1 to make it clear that
demolition works are included.
b. Amending Art 2(3) to introduce an EIA "one-stop shop" to allow for the
coordination of assessment procedures under the EIA Directive and other
EU legislation.
c. Amending Art 4 to streamline the screening procedure and to seek to
enhance the consistency of Member States' approaches to ensure that EIAs
are required only when it is clear that there are significant environmental
impacts.
d. Amending Art 5 with a view to reinforcing the quality of information and
streamlining the EIA process.
5By way of a postscript, the Secretary of State has now issued (February 2013) a “minded to allow” decision upon the basis of a lack of an adequate five year housing land supply.
![Page 8: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/8.jpg)
8
e. Amending Art 6(6) with a view to reinforcing the role of environmental
authorities and defining concrete time-frames for the consultation phase on
the environmental report.
f. Significant amendment to Art 8 including: (i) the setting of a requirement
for a time-frame for the conclusion of the EIA procedure; (ii) a
requirement for competent authorities to include in the development
consent itself some items substantiating the decision; (iii) mandatory post-
completion monitoring, but only for projects that will have significant
adverse environmental effects, according to the consultations carried out
and the information gathered (including the environmental report); and (iv)
a requirement that the competent authority verify that the information of
the environmental report is up to date before deciding to grant or refuse
development consent.
g. An amendment to Art 9 to include a description of the monitoring
arrangements in the information provided to the public when development
consent is granted.
h. Various amendments to the Annexes including clarification of and
addition to the Annex III criteria.
The draft Directive will now be considered by the European Parliament and the
Council to be adopted through the co-decision procedure. It is expected to enter into
force in March 2014, depending on the progress of the legislative process.
Test for EIA development
In R (Loader) v SSCLG and others[2012] 3 CMLR 29 the Court of Appeal gave
important guidance on the proper test in screening. It rejected the Appellant’s
suggestion that screening was required in all cases where the effect would influence
the development consent decision (Pill LJ suggesting at [46] that such an approach
would “devalue the entire concept”). In the Court’s view the test to be applied is: “is
this project likely to have significant effects on the environment?” The criteria to be
applied are those set out in the EIA Regulations and judgment is to be exercised by
planning authorities focusing on the circumstances of the particular case. The
![Page 9: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/9.jpg)
9
decision-maker must, however, have regard to the precautionary principle and the
degree of uncertainty as to environmental impact at the date of the decision.
Split projects
Two recent cases concerning splitting are of note. The first is Bowen-West v SSCLG
[2012] EWCA Civ 321 in which Laws LJ held that the question whether an
environmental statement for the deposit of low level radioactive waste should have
considered a larger scheme (a future expansion of the landfill in question intended to
be achieved by 2026) within the context of “indirect, secondary or cumulative effects”
(para.4 of Pt I of Sch.4 to the 1999 Regs) was an issue of fact and judgment. He
rejected the Appellant’s contention that the question is one of law and declined to
refer the matter to the ECJ.
The second is R (Burridge) v Breckland DC [2012] EWHC 1102 (Admin) in which
HHJ Waksman QC considered the screening opinion requirements of the 1999
Regulations in the context of a renewable energy facility application which had been
‘split’ into two sites. He considered that Regulation 7 required the authority to
consider the “application before it” and that the “development in question” referred
only to the development in the individual application. His judgment has recently been
challenged in the Court of Appeal on the basis that, although his construction
accorded with domestic principles of construction, a broader purposive construction
of the Regulations focusing on the proper ‘project’ was required under
Marleasingprinciples. It is to be hoped that the Court of Appeal’s (hopefully
imminent) judgment will give some much needed clarity in this tricky area.
Screening directions
With his usual thoroughness, Lindblom J has given guidance on the Secretary of
State’s power of direction under Regulation 4(8) of the 1999 Regulations (now
replaced by Regulation 4(9) of the 2011 Regulations) in Threadneedle Property
Investments v Southwark LBC [2013] Env LR 1. The judge emphasised the
exceptional nature of the power, exceptional not just in the sense that it was reserved
to the SSCLG but also in the sense that he would only use it in an exceptional case.
The law in this area is likely to be addressed again in the upcoming Court of Appeal
judgment in Burridge.
![Page 10: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/10.jpg)
10
Concept of ‘consent’
In Case C-121/11 Pro-Braine ASBL and others v Commune de Braine-le-Chateau
(19 April 2012) the Third Chamber of the ECJ held that a definitive decision relating
to the carrying on of operations at an existing landfill site, taken on the basis of a
conditioning plan, pursuant to Article 14(b) of the Landfill Directive (1999/31), does
not constitute a ‘consent' within the meaning of Article 1(2) of the EIA Directive
unless that decision authorises a change to or extension of that installation or site,
through works or interventions involving alterations to its physical aspect, which may
have significant adverse effects on the environment within the meaning of point 13 of
Annex II to the EIA Directive and thus constitute a ‘project' within the meaning of
Article 1(2) of that Directive.
Definition of ‘development’
In the important case of R (Save Woolley Valley Action Group Ltd) v Bath and
North East Somerset Council [2013] Env LR 8 Lang J found that the Council had
erred in law in taking too narrow an approach to the meaning of ‘development’ in
relation to some poultry units. On the basis of that error, the Council had not
addressed itself to the question of whether the units fell within the scope of the EIA
Directive or Regulations. Lang J found that the units were capable of coming under
‘intensive livestock installation’ under the Regulations and, as such, should have
been considered by the Council for an EIA. Of particular interest in this case is Lang
J’s view (see [113]) that the EIA Directive could only be effectively implemented in
the UK if the definition of ‘development’ in section 55 of the TCPA was interpreted
broadly so as to include projects which required an EIA under either the Directive or
the Regulations.
Consultation
In R (Halebank Parish Council) v Halton Borough Council [2012] EWHC 1889
(Admin) HHJ Gilbart QC found that a decision not to extend a consultation period on
an environmental statement amounted to a breach of Article 6 of the EIA Directive
and a legitimate expectation the Parish Council had as to the conduct of the
consultation process.
The role of inspectors
![Page 11: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/11.jpg)
11
Judge Keyser QC has drawn attention to the limited role of Inspectors under
Regulation 9(2) of the 1999 EIA Regulations (now Regulation 12(2) of the 2011
Regulations) in Gregory v Welsh Ministers[2013] EWHC 63 (Admin). If on a section
78 appeal there is a question as to whether the application is an EIA application: (i) a
negative screening opinion from the local planning authority is not conclusive of the
issue; and (ii) the Inspector’s role is to ask himself whether the application “may be”
an EIA application; if he answers that in the affirmative he must refer the question to
the Secretary of State and has no jurisdiction to determine the appeal (except by
refusing planning permission) before he receives a screening direction.
Strategic Environmental Assessment
Alternatives
The key decision on alternatives in the last twelve months is Heard v Broadland
District Council [2012] Env LR 23 in which Ouseley J adopted a broad and purposive
approach to the issue under Article 5(1) of the SEA Directive and Regulation 12 of
the SEA Regulations. He found that there was no express requirement in the directive
or regulations for the selection of the preferred option, as distinct from the reasons for
the selection of the alternatives, to be considered, but that “a teleological
interpretation of the directive, to my mind, requires an outline of the reasons for the
selection of a preferred option, if any, even where a number of alternatives are also
still being considered” [69]. He also found that there was no express requirement that
alternatives be appraised to the same level as the preferred option but he considered
that the directive was best interpreted as requiring an equal examination of the
alternatives which it is reasonable to select alongside the preferred option.
Another key case is Cogent Land LLP v Rochford District Council [2013] 1 P&CR 2
which is a good illustration of the fact that SEA is a process in which defects may be
cured. In the Cogent case Singh J was inclined to accept that there had been errors in
the assessment of alternatives at the preferred options stage. However, he found that
an Addendum report which had later been produced was adequate and capable in law
of curing any defects which had arisen.
SEA of local development documents
![Page 12: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/12.jpg)
12
The scope of the SEA Directive is governed by Art 2 which provides that “plans and
programmes shall mean plans and programmes … which are subject to preparation
and/or adoption by an authority at national, regional or local level… and which are
required by legislative, regulatory or administrative provisions”. The meaning of
‘required’ in this context has been explained by the ECJ in the recent case of Inter
Environment Brussels ASBL and others v Region of Brussels (C-567/10). The ECJ
rejected an argument that required meant ‘compulsory’ and held that “plans and
programmes whose adoption is regulated by national legislative or regulatory
provisions which determines the competent authority adopting them and the
procedure for preparing them must be regarded as ‘required’ within the meaning and
for the application of Directive 2001/42 and accordingly subject to an assessment on
their environmental effects in the circumstances which it lays down.”
This definition of ‘required’ was applied by the High Court in R (Wakil) v
Hammersmith and Fulham LBC [2013] Env LR 3. In that case there was an issue as
to whether the document was an SPD or a DPD. Neither sort of document is
‘compulsory’ but both are ‘required’ under the ECJ’s definition. On that basis both
come within the definition of ‘plans and programmes’ in Art 2 (and also Regulation
2(1) of the SEA Regulations). On the document at issue in Wakil the High Court
found that, whether it was an SPD or a DPD, it did fall under the description in Reg 5
of the SEA Regulations and so a determination under Reg 9(1) had been required on
whether or not it was likely to have significant environmental effects.
Scottish roads
In Walton v The Scottish Ministers[2012] UKSC 44the Supreme Court considered a
challenge to the Ministers’ decision to authorise a new road. This was a development
consent authorising a project and as such had been subject to EIA. The principle basis
for the appeal was an attempt to bring the project within the SEA Directive on the
basis that a decision to enlarge the project was a modification of the regional transport
strategy, an attempt which was comprehensively rebuffed by Lord Reed at [63]-[70].
For an English audience, the case is of principle interest for Lord Carnwath’s obiter
discussion of discretion after Berkeley at [124]-[140] (discussed at para 10 above).
![Page 13: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/13.jpg)
13
DECISION-MAKING: MATERIAL CONSIDERATIONS
R (on the application of Vieira and Saph) v London Borough of Camden &Bozi[2012] EWHC
287
In a neighbour dispute, the interested party erected a conservatory and trellis screen without
planning permission. An application for retrospective planning permission was made. The
local authority consulted the claimant, who objected. Following negotiation, the interested
party re-submitted revised drawings of the trellis, amending the application. Planning
permission was granted but the claimant had not been consulted by the local authority on the
amended application. The claimant claimed breach of legitimate expectations on the basis
that the council’s Statement of Community Involvement, published on its website, provided
that it would consult objectors on revised applications, and that documents and reports would
be available for comment online before they were referred to the members briefing panel.
Finally, the claimant argued that following the revised drawing, the local authority should
have reconsidered whether to determine the application in committee or under delegated
powers.
The court held that there had been a breach of legitimate expectation in respect of all grounds
on the basis that it was unfair to deny the claimant the opportunity to know the precise details
of the application and be given the opportunity to comment on it. It was also prejudicial to the
claimant to be denied the benefit of a re-consideration of how the application should be
determined. The local authority sought to argue that in any event, no relief should be granted
because it was inevitable that planning permission would be granted. The Court rejected this
argument, quashing the planning permission. The grant of permission was not inevitable
because there remained a question of whether the amendments to the scheme made it
acceptable.
R (on the application of Godfrey) v Southwark LBC [2012] EWCA Civ 500
In another case about legitimate expectations, the Court of Appeal considered an appeal
against a decision of the High Court refusing permission to judicially review the grant of
planning permission by a planning authority for mixed use development.
![Page 14: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/14.jpg)
14
The site had been a district centre providing community facilities, including a freestanding
community hall of around 400m2. In 2002, the Council prepared a planning brief relating to
the site which made it clear that any developer would be expected to improve the site’s
community facilities or create new infrastructure, which may include building a new
community hall on the site. In 2007 the council adopted a UDP which identified the uses for
the site as a community centre and health centre. Planning permission was granted by the
Council in 2010 for redevelopment of the site, which included a community centre of around
124 m2 contained within the Health Centre.
Local residents challenged the grant of permission on a number of grounds, and the Court of
Appeal’s judgment concentrates on the fourth ground that there was a substantive legitimate
expectation that better and larger facilities would be provided. The appellant argued that
previous consultation between the Council and local community, combined with the terms of
the planning brief, had given rise to a substantive legitimate expectation that any grant of
planning permission would include a freestanding community hall at least as large as the
existing hall on site.
The Court of Appeal held that a rigorous standard is to be applied when a substantive
legitimate expectation is claimed on the basis of a representation or promise by a public
authority. The duty of public authorities to exercise powers in the public interest must be kept
in mind. Only when, in the court's view, to fail to give effect to the promise would be so
unfair as to amount to an abuse of power, should it override other considerations. Further an
earlier approach of the local planning authority to an issue, even if amounting to a planning
policy, cannot have primacy over the statutory duty of the council to assess the current
situation. The Court of Appeal placed significant weight on the Council’s duty under s. 70(2)
TCPA 1990 and s.38(6) PCPA 2004 to determine an application in accordance with the
development plan unless other material considerations indicate otherwise. The UDP policy
did not require a particular size of provision for community facilities and the Council was
required to assess current needs.
![Page 15: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/15.jpg)
15
What clearly emerges from this decision is thata local authority had a statutory duty to take
into account all material considerations and existing circumstances at the time of the
decisions and that the statutory duty will not be discharged lawfully if one consideration
could in law prevail over the duty to have regard to other considerations. Whilst local
residents have an expectation that consideration would be given to particular matters, the
expectation does not extend to give legal primacy to that expectation. It is unlikely that a
substantive legitimate expectation of a particular outcome (i.e. the terms of planning
permission, conditions to be attached to a planning permission, or whether permission will in
principle be granted for a particular type of redevelopment) will be established based on
previous planning briefs, planning policies, or discussions with the planning authority.
The Supreme Court held that as a custodian of public funds, the local authority is entitled to
have regard to the cost to the public of its actions. Section 97 requires a local authority to
consider whether revocation is “expedient” and it is entitled to take into account material
considerations when coming to a view. Where one of the effects of the decision is the liability
to pay compensation, it is difficult to see why consideration of the financial effects should be
Health and Safety Executive v Wolverhampton City Council [2012] UKSC 34
The question in this case was whether, in considering whether to revoke or modify a planning
permission under s.97 TCPA 1990, a local authority is entitled to take into account the
compensation that it would or might have to pay under s.107 TCPA 1990.
The local authority had refused to revoke a planning permission to a developer for the
erection of four blocks of student accommodation in close proximity to a liquefied petroleum
gas facility. The Health and Safety Executive asked the local authority to revoke planning
permission but the local authority refused, giving one reason as the compensation it would be
liable to pay under s.107 TCPA 1990. The Health and Safety Executive applied for judicial
review and the Court of Appeal held that the decision was unlawful and the local authority
ought to reconsider. The Court of Appeal was divided on the issue of whether compensation
is capable of being a material consideration.
![Page 16: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/16.jpg)
16
excluded. There was no requirement that the assessment of whether to exercise powers under
s.97 should be limited to planning considerations.
This case clarifies the previously contradictory cases from lower courts on the question of
whether compensation under s.107 is capable of being a material consideration.
CHANGE OF USE
Hertfordshire CC v SSCLG [2012] EWCA Civ 1473
This case concerned intensification of use constituting a material change of use.A scrap metal
yard had been operated under an extant planning permission since 1972. The County Council
considered that the substantial increase in throughput and the erection of buildings had
constituted a material change of use and issued enforcement notices concerning the increased
noise, dust, vehicles and new buildings. Upholding the Inspector’s decision the Court
considered that he had applied the right test, namely, whether the material change of use had
changed the character of that use.In assessing whether there had been a change of character in
the use, the impact of the use on other premises was a relevant factor. It was necessary to
consider both what was happening on the land and its impact off the land when deciding
whether the character of the use had changed; and although the inspector's reasoning about
throughput and extraneous factors was questionable those matters should have been identified
in the enforcement notices in order for the local authority to rely on them.
This case reached the national media as it concerned a challenge to the grant of planning and
listed building consent of a property constructed in the late 1890s by Sir Arthur Conan Doyle.
The Interested Party had used the property as a hotel, but since then it had stood vacant for
several years. It applied for planning permission to divide up the property into separate
dwellings. An individual, Mr Norris, subsequently applied for planning permission to change
the property into a single dwelling house. The Council's planning officer informed the
planning committee of Mr Norris’ application, but nonetheless it decided to grant planning
R (on the application of Gibson) v Waverly Borough Council [2012] EWHC 1472
![Page 17: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/17.jpg)
17
permission on the basis that its proposed development would not result in harm justifying
refusal in the public interest. Mr Norris' application for planning permission was later
granted.
Allowing the application Cranston Jdrew attention to the statutory mandate to have regard to
the preservation of heritage assets. He found that national planning policies seek the optimum
viable use for a building, which includes a consideration of what the optimum viable use is in
the interests of the asset’s long term conservation, not simply its optimum use. He held that
the optimum use and optimum viable use was as a single dwelling (albeit that it was not the
most profitable use), and, crucially, that the planning officer should have referred the matter
back to the committee following the grant of Mr Norris’s planning application; for that was a
new material consideration which should have been taken into account.
An appeal by the developer to the Court of Appeal was dismissed.
Sheila Tara Moore v SSCLG and Suffolk Coastal DC [2012] EWCA Civ 1202
This case concerned whether using a dwelling for commercial holiday lettings could amount
to a material change of use. The property had been used for large parties of people instead of
being let to single households. The Court of Appeal held, unsurprisingly, that this would be a
question of fact and degree in each case and the answer would depend on the particular
characteristics of the use as holiday accommodation.
APPEALS & LITIGATION
In Ashley, the claimant objected to a housing development on the grounds of noise and loss of
amenity to the neighbouring houses. Planning permission was refused on the basis of the
noise considerations and the matter proceeded to an appeal by way of written representations.
The claimant was invited to provide written comments by a certain date after which point he
Ashley v SSCLG & LB Greenwich & Taylor Wimpey (CA) [2012] EWCA Civ 547
![Page 18: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/18.jpg)
18
was informed that no further representations could be made. On the last day before the
deadline for representations, the appellant developer submitted detailed expert evidence on
the noise issue. No copy was provided to the claimant and no prior notice of the report was
given. The Inspector concluded that there was no objection to the expert evidence and that it
adequately addressed the issue of noise and granted the appeal.
The claimant challenged the decision on the basis of procedural unfairness. The Developer
resisted the challenge on the basis that all the claimant had to do was attend the council’s
offices the day after the deadline, see the report and then apply to make further
representations.
At first instance, the challenge failed but the Court of Appeal allowed the appeal. The Court
of Appeal found that there was no duty incumbent on the claimant to attend the council’s
offices. He did not attend the offices on the basis that the deadline had passed and he did not
think there was much point. Further, he was not aware that the expert evidence had been
submitted. The claimant had not had a fair crack of the whip because he had been denied the
opportunity to comment on the expert evidence. Lord Justice Pill expressed the view that the
Planning Inspectorate’s guidance on written representations should be revised to prevent this
sort of unfairness occurring in the future by an overly strict approach to deadlines.
Welsh Ministers v RWE Npower Renewables [2012] EWCA Civ 311
RWE sought permission for a wind farm. The Countryside Council for Wales said that the
impact on peat bog habitat was significant whereas the Environmental Statement from RWE
said there was no significant impact. The Countryside Council for Wales failed to attend the
Inquiry and its concern about the conclusions in the Environmental Statement was not put to
RWE’s experts. The Inspector recommended refusal of planning permission on the basis that
there was an unacceptable risk of harm to the peat habitat that was sufficient to justify the
refusal of the proposal, which was confirmed by the Welsh Ministers.
![Page 19: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/19.jpg)
19
In the High Court, RWE’s appeal was allowed on the basis that the Inspector failed to give
reasons for his conclusion on the effects on the peat bog habitat and that by failing to raise his
concern with RWE’s experts, there had been procedural unfairness. The decision was
overturned in the Court of Appeal. It was held that the Inspector was concerned with whether
the harm or risk of harm was sufficient to justify refusal. He was not bound to accept the
unchallenged expert evidence before him and was entitled to make his own planning
judgment. The background of the decision had to be taken into account when assessing
whether the reasons were adequate, RWE was aware of the issues and the importance of the
peat bog habitat. The Court of Appeal also held that there was no procedural unfairness.6
The claimant argued that the court had a duty to read the provisions of the statute in
accordance with the EU law principle of effectiveness and/or the claimant’s right to a fair
trial under article 6 ECHR. In confirming the decision of the High Court that it did not have
jurisdiction because the application was made out of time, the Court of Appeal held that the
wording of the statute was clear that time started to run on the date of adoption. The
Barker v Hambleton DC [2012] EWCA Civ 610
The Court of Appeal confirmed the principle in Hinde v Rugby BC and SSCLS [2011] EWHC
3684 that time to challenge under s.113 PCPA 2004 begins on the date of adoption of
theDevelopment Plan document.
In this case, the DPD was adopted on 21 December 2010 and time expired on 1 February
2011. In the afternoon of 1 February 2011, the applicant posted an application to quash part
of the Allocations DPD under the door of Leeds Court Centre. The application was sealed by
the court on 2 February 2011. The council’s Adoption Statement stated that an application
could be made within six weeks of 31 December 2010, in order to give people more time
over the holidays.
6 This case was applied in the recent case of Macarthur and others v SSCLG, King’s Lynn & West Norfolk Borough Council, E.ON Climate & Renewables UK Developments Ltd, Res UK & Ireland Ltd[2013] EWHC 3 where it was held that Inspectors are not generally under a duty to give reasons for accepting or rejecting expert evidence and that the inspector was not required to record or summarise what an expert had said in his written an oral evidence. The requirement to give reasons had been satisfied because there was no doubt as to what the Inspector had decided and why.
![Page 20: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/20.jpg)
20
applicant’s right of access to the court had not been infringed because there was no
impairment of the very essence of his right of access. Similarly the EU principle of
effectiveness had not been broken. There was no reason why the claimant could not bring an
application within the time specified and the limit of 6 weeks was in any event a reasonable
one.
Permission to appeal to the Supreme Court was sought by the claimant and refused.7
Following Uniplex (UK) Ltd v NHS Business Services Authority [2010] PTSR 1377, the
requirement for promptness in bringing judicial review proceedings under rule 54(4) Civil
Procedure Rules
R (Berky) v Newport City Council [2012] EWCA Civ 378
8
In this case the Local Authority granted planning permission for the erection of a supermarket
and restoration of a former social club despite officers’ recommendation that the scheme did
not comply with retail policies and was on an out-of-centre site. The decision to grant
planning permission was made on 26 January 2011 and on 21 April 2011 the claimant
was held to be unlawful in cases concerned with EU law because it
contravened the principle of effectiveness. This has had a direct impact on domestic planning
cases because if the claimant can find an EU point (for example, EIA), the requirement for
promptness falls away and an application can be made on the last day before the 3 month
time limit expires (see e.g. R (U & Partners (East Anglia) Ltd) v The Broads Authority [2011]
EWHC 1824 (Admin)).
7See also: Lukaszewski v District Court in Torun, Poland [2012] UKSC 20. This is case from the extradition field and
is mentioned because it has the potential to impact on the recent line of cases about time limits and the absolute bar to
proceedings brought out of time in respect of planning appeals. The Supreme Court held in this case that in the
context of human rights cases the short statutory time limits for extradition appeals could be extended in exceptional
circumstances notwithstanding the clear wording of the statute. This case was raised in the grounds of appeal in
Barker but the point may be re-opened in another case in the future. 8(1) The claim form must be filed – (a) promptly; and (b) in any event not later than 3 months after the grounds to make the claim first arose.
![Page 21: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/21.jpg)
21
instructed solicitors, grounds of judicial review were filed on 26 April 2011, the Tuesday
after the Easter Monday Bank Holiday. The grounds included the decision not to require EIA
and the reasons for not following officers’ advice. The claimant failed at first instance
following a rolled-up hearing and appealed to the Court of Appeal.
The Court of Appeal addressed a number of important issues, including time limits for
judicial review proceedings. First, it held that the three month time period starts to run the
day after the grounds for the decision arise, therefore time ran from the 27 January 2011 and
expired on 26 April 2011. The claim was therefore brought just in time and in would have
been in time anyway because the day preceding it was a bank holiday.
The Court of Appeal addressed (obiter) the issue of timing more generally. It held that
promptness does not apply in respect of European law points raised in judicial reviews.
However, where there are mixed grounds of European and domestic law, promptness may
still apply to domestic grounds. The judges’ reasoning on this point does not reveal a clear
answer to the issue. Carnwath LJ held that the domestic grounds had not been brought
promptly whereas Sir Richard Buxton disagreed. The final judge, Moore-Bick LJ, did not
address the point in detail but said that he agreed that there was no reason that domestic law
and Community law challenges could not be subject to different time limits but that he agreed
that this case was not the right forum for resolving the issue. Berky will not be the last word
on timing. The court was further split on the issue of whether the court could decline relief on
the basis of undue delay for Community law points. The majority, Moore-Bick and Sir
Richard Buxton held that Uniplex did apply to the s.31(6) Senior Courts Act 1981 discretion
to refuse relief on the grounds of “undue delay” in making an application for Judicial
Review).
R (on the application of Macrae) v Herefordshire County Council & John Heath [2012]
EWCA Civ 457
Around the same time as Berky, Macraecame before the Court of Appeal. It touches on the
application of promptness to judicial review claims which raise purely domestic points.
![Page 22: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/22.jpg)
22
The case concerned the duty to give summary reasons for granting planning permission. In
this case, the planning committee resolved to grant planning permission despite a
recommendation to refuse by the planning officer. The judge at first instance held that the
reasons given were inadequate because they referred back to a planning report which
recommended refusal of the application. The judge nonetheless declined to grant permission
to apply for judicial review on the basis that the application (brought within a few days of the
expiry of the 3 month time limit) had not been brought promptly.
The Court of Appeal upheld the claimant’s appeal against the judge’s refusal to grant
permission on the basis that the judicial review time limit could not be viewed in isolation of
the issue before the court. The Court of Appeal described the reasons for the grant as
“puzzling” and concluded that they left the claimant in the dark as to why the decision had
been made. The Court of Appeal held that the lapse of time caused no prejudice and that
permission should have been granted. The Court of Appeal allowed the claim and granted a
declaration that the summary reasons were inadequate. Although this was a victory for the
claimant, the Court of Appeal side-stepped the issue of whether promptness is still a feature
of domestic law following Uniplex.
ENFORCEMENT
The Claimant applied for judicial review of a decision of the magistrates’ court to re-open his
conviction for breach of an enforcement notice. The Local Authority and the Claimant had
been negotiating in the run up to proceedings in the Magistrates’ Court and had agreed that
the Claimant could retain part of the extensions to his property which had been the subject of
the enforcement notice. The Claimant was notified of the hearing in the Magistrates’ Court
the day before it was due to take place and, after calling the court, was under the impression
that he did not have to attend because there would be an adjournment. The hearing went
ahead and the Claimant was convicted and sentenced in his absence. He was fined the
R (on the application of Manorgale Ltd) v Thames Magistrates Court and Hackney London
Borough Council (Unreported, 22 January 2013)
![Page 23: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/23.jpg)
23
maximum £20,000 fine. The Claimant applied to the Magistrates’ Court under s.142
Magistrates’ Court Act 19809
The Divisional Court held that this reasoning had been flawed. A Magistrates’ Court did have
the power to re-open the case if it was in the interests of justice to do so and the right of
appeal to the Crown Court did not allow for the Crown Court to correct a substantial
procedural error. The Divisional Court declined to exercise its discretion to direct the
Magistrates’ Court to re-open the conviction, because there was no substantial dispute of fact
between the parties and the suggestion that there may be legal argument by the appellant was
not evidenced. However, the sentence would be re-opened because when sentencing the
Court had failed to take into account the question of financial benefit under s.179(9) TCPA
1990.
to re-open the case but the application was refused on the
ground that the Magistrate’s Court did not want to act as an appellate court, that the matter
should go to the Crown Court and that it only had power to re-open the case if it had made a
mistake.
10 The Claimant was entitled to make the argument that he had not benefitted
financially from the breach of planning control.
Oxfordshire County Council v Wyatt Brothers (Oxford) Ltd & Others (CA) (unreported,
7 December 2012)
This case is an example of the full might of the courts’ power when it comes to breaches of
planning control. The defendants were sent to prison for a consistent failure to comply with
enforcement notices and an injunction requiring their company to remove unlawfully
deposited waste from the company’s site. The defendants were directors of the company and
there was evidence that the company had received over £1 million for the waste during the
1990s.
9s.180(1) A magistrates' court may vary or rescind a sentence or other order imposed or made by it when dealing with an offender if it appears to the court to be in the interests of justice to do so, and it is hereby declared that this power extends to replacing a sentence or order which for any reason appears to be invalid by another which the court has power to impose or make. 10 179(9)In determining the amount of any fine to be imposed on a person convicted of an offence under this section, the court shall in particular have regard to any financial benefit which has accrued or appears likely to accrue to him in consequence of the offence.
![Page 24: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/24.jpg)
24
The Local Authority was granted an injunction, which was not complied with and contempt
of court proceedings were initiated. The Defendants, who were both over 70, received
suspended sentences of 4 months and six months imprisonment. They had one year to comply
with the injunction and remove the waste, which they failed to do. The sentences were
activated and both defendants were sent to prison. The sentence was upheld on appeal on the
basis that there was no alternative but to send the defendants to prison.
Doncaster Metropolitan Borough Council v AC and Others [2013] EWHC 45
The Local Authority applied for an injunction against the defendants, who owned and
occupied a green belt site outside Doncaster and who had been living there without planning
permission for some years. The defendants argued that they had no alternative pitches to go
to and granting an injunction would have a detrimental effect on their children and be a
disproportionate interference with their rights, and their children’s rights under article 8
ECHR.
HHJ Richard Salter QC reviewed the authorities and reminded himself that, following South
Cambridgeshire DC v Gammell[2005] EWCA Civ 1429, injunctive relief is unlikely unless
properly thought to be proportionate to the breach of planning control that has taken place. A
key consideration in the balancing exercise was the best interests of the Claimants’ children
and the Claimants’ and their families’ article 8 ECHR rights. It was a drastic step to require
six families to move from their home. However, this had to be balanced against the fact that
the claimants’ occupation of the site had always been unlawful.
The judge granted the application, reasoning that against the background of three and a half
years’ unlawful use of the site, there was a real risk that the planning system and criminal law
would be brought into serious disrepute if the court were to hold that the grant of an
injunction would be disproportionate because of the interference with the claimants’ and their
children’s rights. It would not be correct to give only limited weight to a local authority’s
decision and the requirements of the criminal law.
![Page 25: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/25.jpg)
25
Localism Act 2011: Planning Enforcement Orders
The new enforcement provisions, contained in Chapter 5 Localism Act 2011 came into force
in the last year. These provisions include new powers for the enforcement of concealed
breaches of planning control after the normal time limit for enforcement has expired. Under
s.124 Localism Act 2011, a new s.171BA of the TCPA 1990 is inserted, allowing local
planning authorities to apply to the magistrate’s court for a Planning Enforcement Order
(“PEO”). An application for a PEO may be made up to 6 months after “evidence of the
apparent breach of planning control sufficient in the opinion of the local planning authority
to justify the application came to the authority’s knowledge” and this section applies
notwithstanding the usual time limits in s.171B. A PEO entitles the local authority to take
enforcement action at any time within an “enforcement year”, defined as beginning 22 days
after the court’s decision to make the order is given.
A magistrate’s court may make a PEO in relation to an apparent breach of planning only if it
is satisfied on the balance of probabilities that the breach has been deliberately concealed by
any person or persons and the court must consider the making of a PEO to be just in all the
circumstances. The meaning of “deliberately concealed” is not defined, and is very likely to
be the source of future litigation.
The Localism Act also inserts new provisions into the TCPA 1990 relating to: twin-tracking
of applications for retrospective planning permission with enforcement appeals on the
grounds that permission ought to have been granted; assurances by a local authority that a
person is not at risk of being prosecuted in connection with the enforcement notice or certain
matters relating to the enforcement notice; increased powers to LPAs in relation to
advertisements, graffiti and fly posting. There is also an increase in the maximum fine for a
breach of condition notice.
Environmental Update
Nuisance
![Page 26: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/26.jpg)
26
2. The most significant case of the year was the Court of Appeal’s decision in Barr v
Biffa [2012] EWCA Civ 312 in which CarnwathLJ (as he was then) made clear that
nuisance is to be assessed according to the traditional 19th century principles (no
absolute standard; assess by the character of neighbourhood) as opposed to any new
21st century approach whereby nuisance is considered in the context of statutory
regulation of the site. In addition the Judge’s assessment that an environmental
permit is not strategic enough to change the character of the area is noteworthy.
3. Whilst the legal principles may be clearer there are still practical problems associated
with resolving group litigation cost effectively. Technical modelling appears to be
assuming a greater importance in this respect. Anslow v Norton [2012] EWHC 2610
was the first case post Barr and Biffa. The judgment marks a new chapter in the story
on quantum of damage awards by providing for a range of awards assessed according
to odour modelling which had been done to establish the likely odour impact on a
range of Claimants.
4. The decision of the Supreme Court in Coventry v Lawrence [2012]1 WLR 2127 is
awaited and could herald another significant development in nuisance law about the
relevance of planning permission for an activity which is alleged to give rise to a
nuisance.
5. In the parallel field of statutory nuisance, challenges continue to the drafting of
abatement notices despite the plethora of previous cases, and the Administrative Court
in R (Fullers Farming Limited) v. Milton Keynes Council [2012] Env LR 17 is
another in the line which rejects legalistic points of challenge (in this case the failure
to specify whether the odour nuisance in question was prejudicial to health or simply
a nuisance).
Environmental permitting
6. The case of London Borough of Newham v John Knights (ABP) Limited is an
interesting case study in enforcement under the Environmental Permitting
Regulations. The company were prosecuted for alleged breaches of an environmental
permit and in particular the odour conditions. The company ran an abuse of process
argument that a Planning Inspector and not the Criminal Courts should consider
complex matters like BAT for odour control. The abuse argument was rejected. The
![Page 27: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/27.jpg)
27
company was convicted and fined £120,000, plus £68,000 costs, plus compensation
orders of £250 each to affected residents. This is the largest fine yet obtained by a
local authority under the environmental permitting regime (the second largest being
the £75,000 imposed on the same company in February 2011).
7. In R(oao European Metal Recycling Ltd) v Environment Agency [2012] EWHC
2361 (Admin)) the Administrative Court quashed a suspension notice on the basis the
Environment Agency failed to specify in the notice the steps by which the operator
was to eliminate a risk of serious pollution by noise.
Environmental judicial review
Intensity of review
8. The courts have tended to adopt a relatively “hands off” deferential approach to
environmental decision makers like the Environment Agency and Natural England,
interfering only where the decision-maker can be shown to have acted irrationally in
the traditional Wednesburysense. However Lang J in R (Manchester Ship Canal Co
Ltd & Peel Holdings Ltd) v Environment Agency[2012] EWHC 1643 took an
interventionist approach to the interpretation of the Environment Agency’s flood
defence policies. The Environment Agency has permission to appeal on the basis the
Court’s approach was too interventionist.
9. In Bowen West v Sec of State [2012] EWCA Civ 321 Laws LJ declined to rule on an
argument that the Courts should adopt a more intensive scrutiny to questions of
European law which often arise in environmental judicial review. Nonetheless the
point remains pertinent given the prevalence of EU law in environmental law.
Discretion
10. The case of Berkeley v Sec of State remains the high point for Claimants seeking to
argue that the Court has no discretion not to quash a defective environmental decision.
Lord Carnwath has however been mounting a steady campaign to limit its boundaries,
the latest expression of which is inWalton v The Scottish Ministers [2012] UKSC 44
at [124]-[140]. The Courts will scrutinise the nature of the breach and the statutory
context in deciding how to exercise their discretion.
Promptness
![Page 28: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/28.jpg)
28
11. It has been a central requirement of Judicial Review that a claim should be filed
promptly and in any event not later than 3 months after the grounds to make the claim
first arose. Following C-406/08 Uniplex; R. (Buglife) v Medway Council and R (U
& Partners (East Anglia) Ltd) v The Broads Authority,it is clear that promptness is
disapplied in environmental cases which raise EU law. However, the Court of
Appeal’s decision in Berky v Newport City Council[2012] EWCA Civ378 is now the
leading case in the domestic context albeit that all the observations on promptness
were strictly obiter and each Judge took a different view on whether and how Uniplex
applied in the purely domestic context. It remains to be seen how long it remains the
position that there are different timing requirements for making a claim according to
whether the claim raises matters of EU law or not.
Costs in discontinued and compromised claims
12. The default position had been that in the absence of a clear view as to how the
litigation would have resolved itself there would be no order to costs (the Boxall
guidance). However the number of instances in subsequent cases in which claimants
were deprived of their costs led some to question the default rule. The more nuanced
position is apparent in Court of Appeal’s decision in M v London Borough of
Croydon [2012] EWCA Civ 595 in which the Court emphasised that the general rule
is that the successful party is entitled to his costs, so the defendant would need to
justify another order but also emphasising that the Court is not in a good position to
ascertain who might have won and on what terms where a matter settles as opposed to
where a case is heard.
Costs protection
13. Costs and funding can raise significant practical obstacles for claimants who are often
interest groups or local residents. As a consequence, environmental judicial review is
leading the way in developing jurisprudence on costs protection, drive in large part by
the Arhus Convention. The Courts have also led the way and it is now difficult for
defendants in environmental judicial reviews to resist some form of PCO. The issue is
often the terms of the Protective Costs Order. The main issue which has occupied the
domestic Courts in recent times is whether the Aarhus requirement that litigation is
not “prohibitively expensive” is to be decided on an 'objective' basis (by reference to
![Page 29: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/29.jpg)
29
the average citizen) or on a 'subjective' basis (ie the Claimant in question).The
position is uncertain.
14. Further developments in costs jurisprudence are likely. The European Commission
has commenced infraction proceedings against UK in respect of costs in
environmental JR cases under the PP Directive. The Supreme Court referred the
question of costs to the European Court in the case of C-260/11 Edwards v
Environment Agencyand judgment is awaited.
15. Meanwhile, the Ministry of Justice has proposed a costs regime for judicial review
cases falling within the scope of the Aarhus Convention and the EU Public
Participation Directive. A PCO would limit the liability of a claimant to pay a
defendant’s costs to £5,000, and £10,000 in the case of an organisation. It would limit
the liability of a defendant to pay the claimant’s costs to £35,000.
Consultation
16. R (Friends of the Earth& Others) v Secretary of State for Energy and Climate
Change[2012] EWCA Civ 28, is authority for the proposition that, exceptionally, a
challenge to a potential decision can be brought during a consultation period on the
decision. The Ministry of Justice Consultation Paper entitled “Judicial Review
Proposals for Reform” Ministry of Justice, Consultation Paper CP25/2012 is arousing
a great deal of concern among environmental groups.
References to the European Court
17. Our domestic judiciary are reluctant to refer cases to the European Court. Despite the
prevalence of EU law in environmental law only 10 cases were referred from 2007 to
2012. Two are currently pending before the European Court – R (Edwards) v
Environment Agencyand Fish Legal v The Information Commissioner, United
Utilities, Yorkshire Water and Southern Water which was referred in 2012.
18. Where given, the judiciary’s reasons for refusing an application to refer demonstrate a
variety of reactions ranging from irritation to rewriting the constitutional relationship
between the EU and domestic Courts (Lord Brown in Morge characterising the
European Court as an unhelpful assistant to the Supreme Court). During the course
of 2012 (in the face of repeated applications for a reference from Richard Buxton
Solicitors) there have however been indications that the Judiciary consider it prudent
![Page 30: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/30.jpg)
30
(maybe to avoid a Kobler v Austria damages claim) to better explain their reasons for
refusing references. The reasons given by the Supreme Court in Bowen West for
refusing the application for a reference are fulsome in comparison with earlier cases.
Administrative decision making and expert evidence and reasons
19. Inspectors, who are experts in their own right, are finding it tricky to know how much
they need to explain the view they take of expert evidence before them. The Courts
also appear to be finding it difficult. In Macarthur v Secretary of State for
Communities and Local Government[2013] EWHC 3 (Admin) Lang J made clear
that she thought the Court of Appeal in RWE v N Powerhad got it wrong with the
consequence that ‘an unsuccessful party will usually not know, in any detail, why the
evidence of an expert has been accepted or rejected by the Inspector and therefore will
not be able to discern whether the Inspector has correctly understood and applied the
evidence of the expert’. She was however bound to follow the Court of Appeal and
did so. It looks like this issue has further to run.
Transfrontier shipment of waste
20. R v Ezeemo [2012] EWCA Crim2064,saw the Court of Appeal consider the
Transfrontier Shipment of Waste regime11for the third time12
21. In short, the three cases establish the following about the regime: 1) the criminal
offence of transporting hazardous waste to a country that is not a member of the
OECD is one of strict liability and is not ultra vires the EU parent Regulation or
disproportionate. 2) Art 36 of the EU Reg(exports for recovery to non OECD
countries is prohibited ) contains 2 simple but key concepts a) waste must be destined
for recovery b) export is the action of waste leaving the EU. 3) Waste can be destined
in 12 months. The
Court decisions arose from the large scale high profile prosecutions by the Agency in
relation to the shipping of televisions and paper to Africa and South Korea. Whilst the
prosecutions have been hugely expensive for the Agency and the fines low, the
Agency will nonetheless be pleased that all defendants pleaded guilty or changed their
plea over the course of 18 months as the Court of Appeal successively rejected their
defences.
11EU Regulation 1013/2006 and UK TFS Regulations (2007) 12The other cases are KV &Othrs v R [2011] EWCA Crim 2342 and R v Ideal Paper Co [2011] EWCA Crim 3237
![Page 31: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/31.jpg)
31
for foreign parts long before it gets anywhere near the English/Welsh docks but it is a
question of fact to determine when it is ‘destined’ for another country. 4) The breadth
of activities caught by the regime is wide – anyone involved in the transport of waste
(by road, rail, sea) from point of origin where waste is collected/stored to the point it
is delivered to the foreign country. 5) Whether household waste has become paper
waste is a question of fact for the jury. There appears to be a de minimis threshold for
‘contamination’ by other materials but this is a question of fact (but the CA thought
the EA should produce guidance).
Habitats
Multiple authorities
22. Cornwall Waste Forum St Denis Branch v SSCLG [2012] Env LR 34 is an
important decision on the allocation of responsibilities under the Habitats regime
between the SSCLG and the Environment Agency. The case concerned a planning
permission for a waste incinerator which had been granted on appeal following a local
inquiry. The planning inspectorate had indicated that the Inspector would consider as
part of his remit whether an appropriate assessment under the Habitats Regulations
was needed. However, the Inspector had instead accepted the views of the EA, which
indicated that it would grant a permit for the scheme as it considered that there could
not be any adverse effects, so that appropriate assessment was not required. At first
instance the planning permission was quashed, the High Court accepting that C had a
legitimate expectation that the SSCLG would address whether an appropriate
assessment was required and would act as the competent authority in undertaking it.
The SSCLG appealed. Allowing the appeal, Carnwath LJ considered there to be three
reasons why the LE argument did not avail CWF: (i) the SSCLG was the relevant
competent authority and could not be bound by PINS or the Inspector to an election
under Reg 65(2) or to the form of his decision; (ii) the representations made had not
been binding; and (iii) the debate about responsibility under the Directive was of no
practical significance since whether or not he was decision-maker under the Habitats
Directive, he was entitled to rely on expert guidance from EA (and Natural England).
It would only be if their guidance was flawed that his decision would be open to
challenge. CWF had asserted that it was arguable that EA’s guidance was unlawful
![Page 32: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/32.jpg)
32
but had not challenged it, thus providing no basis for sending the decision back to the
SSCLG for reconsideration.
IROPI
23. Elliott v SSCLG [2013] Env LR 5 concerned a challenge to the proposed “makeover”
of Crystal Palace Park. There were five grounds of challenge, the fourth of which
concerned bats and raised issues relating to “imperative reasons of overriding public
interest” for the purposes of Regulation 62 of the Habitats Regulations. The Inspector
had raised an issue as to whether the planned makeover might constitute IROPI but
had not decided the point. The SSCLG did not spell out that he had considered IROPI
but Keith J held that he must have done so. The point of wider interest in the case
concerns Keith J’s assessment of the Claimant’s contention that the need to raise
funds for a development could not as a matter of Community law constitute
exceptional circumstances forming the basis of an IROPI. Keith J noted the passage in
Solvay v Region Wallonne(C-182/10) where the ECJ stated at [76]-[77] that “[w]orks
intended for the location or expansion of an undertaking [will] only in exceptional
circumstances” satisfy the condition that the development “must be of such
importance that it can be weighed up against [the] directive’s objective of the
conservation of natural habitats …”. But he went on to find that “you cannot get from
that that if a particular feature of a set of proposals was included only because it
would provide some of the funding for the development as a whole, and if it happened
to be that aspect of the development which would have an impact on the conservation
of natural habitats, there cannot have been imperative reasons of overriding public
interest for permitting the development”. The Claimant therefore failed on the habitats
ground and also failed on the other grounds. There is an outstanding appeal to the
Court of Appeal including on the IROPI issue.
Other Areas - Case Digest
24. Freedom of Information: Birkett v DEFRA [2011] EWCA Civ 1606, a public
authority that holds environmental information for the purposes of the Environmental
Information Regulations 2004, and on a request for information made pursuant to the
Regulations refuses to give disclosure and states its reliance upon one of the permitted
exceptions in accordance with Reg.14(3), may then rely as of right upon a different
exception or exceptions in proceedings before the Information Commissioner and/or
![Page 33: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/33.jpg)
33
the First-Tier Tribunal (General Regulatory Chamber) (Information Rights) so long as
the new or additional exceptions are set out within the notice of appeal, or response to
a notice of appeal.
25. IPPC directive
26.
- themeaning of sows in subheading 6.6(c) of Annex 1 Møllerv.
HaderslevKommune(Case C-585/10). The expression ‘places for sows’, in
subheading 6.6(c) of Annex I to Directive 96/61, has to be interpreted as meaning that
it includes places for gilts.
Waste: Scope of duty of care
27.
. The Administrative Court has provided guidance on the
scope of the Duty of Care for Waste imposed by virtue of section 34 of the
Environmental Protection Act 1990. See Mountpace Ltd v Haringey London
Borough Council[2012] EWHC 698 (Admin)
Liability of parent for actions of subsidiary
28.
Chandler v Cape plc[2012] EWCA Civ
525.In appropriate circumstances the law may impose on a parent company
responsibility for the health and safety of its subsidiary’s employees. Those
circumstances include a situation where, as in the present case: (1) the businesses of
the parent and subsidiary are in a relevant respect the same; (2) the parent has, or
ought to have, superior knowledge on some relevant aspect of health and safety in the
particular industry; (3) the subsidiary’s system of work is unsafe as the parent
company knew or ought to have known; and (4) the parent knew or ought to have
foreseen that the subsidiary or its employees would rely on it using that superior
knowledge for the employee’s protection.
Contaminated Land
29.
The Administrative Court has granted a declaration that a grant of
planning permission was unlawful because of failure to address contaminated land
issues R. (on the application of Gawthorpe) v Sedgemoor DC[2012] EWHC 2020
(Admin)
EU emissions trading and aviationCase C-366/10, Air Transport Association of
America et al. v. Secretary of State for Energy and Climate Change, the European
Court upheld the validity of the application of EU emissions trading to passenger
aircraft. The decision repays careful attention on various fronts, in particular the close
analysis of the relevance of international agreements and public international law
generally to the approach in considering Directives. In the event, no incompatibility
![Page 34: Planning Case Law Update - 39 Essex Chambers · Based on papers by Stephen Tromans QC, John Pugh-Smith, Justine Thornton, Richard Wald, Rose Grogan and Ned Helme PLAN-MAKING Tesco](https://reader036.vdocuments.site/reader036/viewer/2022062508/5ffc0c2661733126d11078b6/html5/thumbnails/34.jpg)
34
was found between Directive 2008/01 and the international material, in particular the
EU/US “Open Skies” Bilateral Agreement signed in Washington DC in 2007. The
key point was that the EU ETS scheme was (a) non-discriminatory and (b) was not in
the nature of an obligatory levy, duty, tax, fee or charge.
30. Rylands& Fletcher and fire
31.
: The Court of Appeal has handed down an important
judgment considering the application of the rule in Rylands v Fletcher to cases
involving the escape of fire. See Mark Stannard (t/a Wyvern Tyres v Gore [2012]
EWCA Civ 1248.
UK in breach of Urban Waste Water Treatment Directive
32.
. The CJEU has found the
UK to be in breach of its obligations under the Urban Waste water Directive (91/271).
Commission v United Kingdom (Case C-301/10)
UK Compliance with the Air Quality Framework Directive
Thirty Nine Essex Street LLP is a governance and holding entity and a limited liability partnership registered in England and Wales (registered number
0C360005) with its registered office at 39 Essex Street, London WC2R 3AT Thirty Nine Essex Street's members provide legal and advocacy services as
independent, self-employed barristers and no entity connected with Thirty Nine Essex Street provides any legal services. Thirty Nine Essex Street (Services)
Limited manages the administrative, operational and support functions of Chambers and is a company incorporated in England and Wales (company number
7385894) with its registered office at 39 Essex Street, London WC2R 3AT
In March 2013 the
Supreme Court will hear the case of R(oaoClientEarth) v Secretary of State for
Environment Food and Rural Affairs (UKSC 2012/0179). The issue arising is
whether, as regards areas where compliance with nitrogen dioxide limits set out in
Directive 2008/50/EC (the Air Quality Directive) cannot be achieved by 1 January
2010, the Air Quality Directive requires the Respondent to prepare an air quality plan
which demonstrates compliance by 1 January 2015.