planning and environment act 1987...good urban design outcomes, enhanced public transport usage,...

168
Planning and Environment Act 1987 Advisory Committee Report Punt Road Public Acquisition Overlay Advisory Committee 30 May 2016

Upload: others

Post on 24-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Planning and Environment Act 1987 

Advisory Committee Report 

Punt Road Public Acquisition Overlay Advisory Committee  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

30 May 2016 

    

Page 2: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Planning and Environment Act 1987 

Advisory Committee Report pursuant to Section 25 of the Act 

Punt Road Public Acquisition Overlay Advisory Committee 

 

30 May 2016 

 

   

Trevor McCullough, Chair  Sue Porter, Member 

 

   

Henry Turnbull, Member  Kevin Breen, Member 

 

Page 3: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

  

 

Contents   Page 

Executive Summary ............................................................................................................. 1 

1  Introduction ................................................................................................................ 7 1.1  Background .............................................................................................................. 7 1.2  Terms of Reference ................................................................................................. 9 1.3  Advisory Committee process ................................................................................... 9 1.4  Acknowledgements ................................................................................................. 9 

2  Identification of issues .............................................................................................. 10 2.1  Summary of issues raised in submissions ............................................................. 10 2.2  The Committee’s approach to assessing the issues .............................................. 13 2.3  Limitations ............................................................................................................. 13 

3  Historical context ...................................................................................................... 14 

4  Background material presented to the Committee ................................................... 16 4.1  VicRoads Background Report ................................................................................ 16 4.2  Options Report ...................................................................................................... 16 4.3  Streamlining  Hoddle  Street  Initiative  and  Punt  Road  Transport 

Investigation .......................................................................................................... 21 4.4  Consultation undertaken by VicRoads .................................................................. 22 4.5  Other documents provided to the Committee ..................................................... 23 

5  Legislative and strategic context ............................................................................... 24 5.1  Road Management Act 2004 ................................................................................. 24 5.2  The Transport Integration Act 2010 ...................................................................... 24 5.3  Planning and Environment Act 1987 ..................................................................... 27 5.4  State Planning Policy Framework (SPPF) ............................................................... 28 5.5  Plan Melbourne ..................................................................................................... 31 5.6  State Strategic work currently underway ............................................................. 35 5.7  Local Planning Policy Framework .......................................................................... 39 5.8  Other relevant policies and strategies .................................................................. 41 5.9  Planning scheme provisions .................................................................................. 42 5.10  Conclusions ............................................................................................................ 44 

6  The strategic importance of the Punt Road PAO ....................................................... 46 6.1  The issue ................................................................................................................ 46 6.2  Evidence and submissions ..................................................................................... 46 6.3  Discussion .............................................................................................................. 50 6.4  Conclusions ............................................................................................................ 53 

7  Economic issues ........................................................................................................ 54 7.1  Broader economic impacts for Melbourne ........................................................... 54 7.2  PAO replacement cost ........................................................................................... 57 

   

Page 4: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

  

 

8  Traffic and transport issues ....................................................................................... 60 8.1  The issues .............................................................................................................. 60 8.2  The role of Punt Road in the transport network ................................................... 60 8.3  Comments on the concept options ....................................................................... 61 8.4  Modified Concept 5 ............................................................................................... 62 8.5  Punt Road traffic performance .............................................................................. 63 8.6  Broader road network performance ..................................................................... 67 8.7  The public transport impacts ................................................................................ 76 8.8  Cycling and pedestrian impacts and opportunities............................................... 78 8.9  Impact on local streets .......................................................................................... 81 8.10  Summary of parties preferred position ................................................................. 81 8.11  Conclusions ............................................................................................................ 82 

9  Heritage issues .......................................................................................................... 84 9.1  The issue ................................................................................................................ 84 9.2  Background ............................................................................................................ 84 9.3  Evidence and submissions ..................................................................................... 85 9.4  Discussion .............................................................................................................. 87 9.5  Conclusions ............................................................................................................ 89 

10  Environmental issues ................................................................................................ 90 10.1  Impacts on the Yarra River .................................................................................... 90 10.2  Air quality and noise .............................................................................................. 93 10.3  Stormwater management ..................................................................................... 96 10.4  Tree removal ......................................................................................................... 97 10.5  Impacts on Fawkner Park ...................................................................................... 99 10.6  Summary of conclusions on environmental issues ............................................. 100 

11  Social issues ............................................................................................................ 101 11.1  Fairness and equity.............................................................................................. 101 11.2  Certainty .............................................................................................................. 105 11.3  Impacts on the community ................................................................................. 109 

12  Impacts on strategic growth objectives ................................................................... 111 

13  Other issues raised in submissions .......................................................................... 115 13.1  The cost of property acquisition and property values ........................................ 115 13.2  Compensation ..................................................................................................... 118 13.3  Streetscape design .............................................................................................. 121 13.4  Implications of emerging technologies ............................................................... 123 13.5  The suggested tunnel option ............................................................................... 125 

14  Findings and recommendations .............................................................................. 128 14.1  Findings ................................................................................................................ 128 14.2  Recommendations .............................................................................................. 133 

15  Response to Terms of Reference ............................................................................. 135 

    

Page 5: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

  

 

Appendix A  Submitters to the Advisory Committee 

Appendix B  Parties to the Hearings 

Appendix C  Document list 

Appendix D  Terms of Reference 

Appendix E  Modified Concept 5 

Appendix F  Heritage map 

 List of Tables 

  Page 

Table 1  Summary of submissions ....................................................................................... 12 

Table 2  VITM Two way estimated daily traffic volumes 2031 ........................................... 68 

Table 3  Scenarios that could affect Punt Road south of the Yarra River ........................... 75 

Table 4  Response to Terms of Reference ........................................................................ 135  

List of Figures   Page 

Figure 1  Locality plan ............................................................................................................. 7 

Figure 2  The existing PAO ...................................................................................................... 8 

Figure 3  SmartRoads road use hierarchy ............................................................................ 60 

    

Page 6: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

  

 

List of Abbreviations AQM  Air Quality Management 

AQST  Air Quality Screening Tool 

BITRE  Bureau of Infrastructure, Transport and Regional Economics 

CBD   Central Business District 

DELWP  Department of Environment, Land, Water and Planning 

EPA  Environment Protection Authority 

GRZ  General Residential Zone 

HO  Heritage Overlay 

LACA  Land Acquisition and Compensation Act 1986 

LPPF  Local Planning Policy Framework 

MAC  Ministerial Advisory Committee 

MMBW  Melbourne Metropolitan Board of Works 

MSS  Municipal Strategic Statement 

NRZ  Neighbourhood Residential Zone  

PAO  Public Acquisition Overlay  

P&EA  Planning and Environment Act 1987 

PPTN  Priority Public Transport Network 

PTV  Public Transport Victoria 

RGZ  Residential Growth Zone 

SEPP  State Environment Planning Policy 

SIDRA  Signalised and unsignalised Intersection Design and Research Aid 

SPPF  State Planning Policy Framework 

TIA  Transport Integration Act 

VAGO  Victorian Auditor General  

VCEC  Victorian Competition and Efficiency Commission 

VITM  Victorian Integrated Transport Model 

VKT  Vehicle Kilometres Travelled 

VMM  Victorian Metroscopic Model 

VPD  Vehicles Per Day 

VPP  Victoria Planning Provisions 

WHO  World Health Organisation  

   

Page 7: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 1 of 162 

 

Executive Summary 

(i) Summary 

The Advisory Committee 

The Victorian Government has committed to review the existing 20 metre Public Acquisition Overlay  (PAO)  that  affects  135  properties  along  the  east  side  of  Punt  Road  between Alexandra  Avenue  in  South  Yarra  and  Union  Street  in  Windsor,  as  well  as  49  and  51 Alexandra Avenue, South Yarra. 

The Minister  for  Planning  has  appointed  an  Advisory  Committee  (the  Committee)  under Section 151 of  the Planning and Environment Act 1987  (P&EA)  to undertake a  review and recommend whether to retain, modify or remove the PAO. 

The Committee is required to respond to the (revised) Terms of Reference approved by the Minister on 16 August 2015.  The Terms of Reference set out the purpose of the Committee, the method to be adopted for the inquiry, and notes that “the Government wishes to provide certainty about this matter as some affected property owners wish to plan for the future of their properties and are concerned about whether the road widening will be going ahead”. 

In  accordance  with  the  Terms  of  Reference,  VicRoads  prepared  a  Background  Report, published  in August 2015.   A further Options Report was published  in October 2015 which set out seven possible concept options for the future road layout on Punt Road. 

The Committee  invited public submissions  in October 2015, with submissions closing on 24 November 2015.  A total of 120 written submissions were received. 

Public Hearings were held on 9, 10, 11, 16, 18 and 19 February 2016.  The Committee heard 23  presentations  from  submitters  and  received  seven  expert  witness  reports  on  traffic engineering, transport planning, economics, planning and open space. 

Submissions 

VicRoads and PTV supported the retention of the PAO, raising the following key submissions: 

The  future of  the PAO  should  consider  the  role  it may play  in meeting  the  long‐term transport requirements of Melbourne. 

The  Punt  Road  corridor  is  considered  vital  to maintaining Melbourne’s  liveability  and access. 

The PAO balances the present and future needs of all Victorians ensuring real options are not built out, resulting in potential significant economic savings for all future Victorians.  

Punt Road is a vital city asset to support economic growth and jobs for the State through the delivery of freight and connecting jobs and opportunities across Melbourne. 

From  a  strategic  planning  perspective,  the  PAO  should  be  retained  to maintain  the opportunity  to  relieve  congestion and  facilitate a  short, medium and  long  term modal shift from private cars to public transport. 

The Punt Road Hoddle Street corridor is the only north‐south arterial that can play a vital strategic bypass of central Melbourne, away from local roads and key activity centres. 

Punt  Road  carries  an  important  north‐south  public  transport  service  (bus)  which  is expected to increase patronage with increased population growth. 

Page 8: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 2 of 162 

 

Whilst  seven  concepts were presented,  there are an  infinite  set of design possibilities that should have regard to changing transport needs and technologies. 

All  but  three  affected  landowners  have  either  been  compensated  or  have  purchased their property with the knowledge of the PAO. 

This  position was  generally  supported  by  the  City  of Melbourne,  but with  the  following additional submissions: 

Works  to Punt Road  should extend beyond  simply  improving  travel  times  and  include good  urban  design  outcomes,  enhanced  public  transport  usage,  improved  pedestrian safety and experience and consideration of impacts on sites of heritage significance. 

The need to minimise  impacts of  future road design on open space,  including Fawkner Park, Alexandra Avenue and the Morrell Bridge area. 

The majority of other submitters,  including the City of Stonnington and Drop Punt (a group representing local residents and land owners along Punt Road) opposed the retention of the PAO and raised the following key issues: 

The future of the PAO should be based on a triple bottom line assessment with the aim of achieving net community benefit. 

There  are  negative  social,  urban  and  environmental  impacts  associated  with  the retention of the PAO, particularly  in relation to heritage properties and along the Yarra River corridor. 

Whilst supporting  improvements to Bus Route 246, a dedicated bus  lane  is not justified on Punt Road. 

The PAO  is creating unacceptable uncertainty for  landowners  in terms of whether their properties will be acquired, and if so when and what compensation will be payable. 

The PAO is outdated as it: “has been in place for over 60 years”; “it has never been called upon”; “VicRoads have no plans to widen the road”; “there is no budget allocated for any works or property acquisition”; and “there is no political will to widen it”; and therefore it should be removed. 

Widening Punt Road will result in a six lane “freeway” within inner Melbourne which will have a significant impact on the liveability of the area, cause community division, impact on access  to community  facilities and open space, reduce pedestrian safety, as well as cause  increased  noise,  air  quality  and  vibrations  and  resultant  health  impacts, particularly for local school children. 

The ability to improve north‐south traffic capacity along Punt Road is constrained by the Hoddle Bridge and the Punt Road Hoddle Street Corridor. 

The  widening  of  Punt  Road  would  result  in  the  removal  of  heritage  properties  and significant vegetation.  The PAO is also hindering restoration of heritage properties. 

The PAO  is making  it difficult  to sell properties and  is adversely  impacting on property values. 

Landowners  have  had  difficulty  obtaining  planning  permits  to  undertake  renovations, repairs and maintenance  to  their properties and are unsure what  they can do  to  their properties  under  the  PAO.    It  acts  as  a  disincentive  to  undertake maintenance  and therefore results in significant deterioration of buildings. 

   

Page 9: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 3 of 162 

 

Committee Assessment 

The Committee has considered the issues in the context of: 

The requirements of the Terms of Reference 

The  objectives  and  decision making  principles  of  the  Transport  Integration  Act  2010 (TIA), and 

The  requirements  of  the  P&EA,  including  whether  the  various  concepts  have  a  net community benefit. 

The  Committee’s  analysis  of  strategic  planning,  economic  and  traffic  issues  confirms  the importance  of  Punt  Road  south  of  the  Yarra  River  as  an  important  arterial  road  link  in Melbourne’s  road  network.    Analysis  of  relevant  policy  documents  and  expert  evidence provided to the Committee confirms that this role is likely to continue in the future. 

The Committee is firmly of the view that Punt Road should be upgraded in the short term to relieve existing congestion, and the PAO should be retained  in the  long term to the extent required to fulfil  its role  in the road network, relieve other parallel north‐south routes and improve  public  transport  operation  along  and  across  the  Punt  Road  corridor.    The  key question for the Committee is therefore the extent of widening required in the longer term. 

The Committee has examined this question based on the evidence and submissions provided to  it,  and  draws  the  following  conclusions with  reference  to  the  seven  concept  options tabled by VicRoads in the Options Report: 

Short  term  measures  such  as  24  hour  clearways,  signal  linking,  turn  bans  and improvements to cross road intersections are worthwhile and should be pursued. 

The  Committee was  not  provided with  any  definitive  evidence  about whether  traffic volumes  would  increase  in  the  Punt  Road  corridor  beyond  2031.    The  Committee, however, believes  that whilst  there may be  growth  in  local  traffic demand,  it  is most likely  that  growth  in  corridor  traffic  demand  would  be  limited  given  the  demand management policies expected to continue and the capacity constraints elsewhere in the corridor. 

A four‐lane road with turn lanes will provide adequate capacity in the short and medium term and is highly likely (given the assumptions adopted by the Committee) to continue to be satisfactory in the long term. 

It was not clearly demonstrated that a six‐ lane road such as that presented by VicRoads as Concepts 6 and 7 is justified in the medium or long term. 

The six lane concepts (supported by VicRoads and PTV) would require the acquisition of 135 properties and  impacts on 40 heritage properties,  including the  likely demolition of 34 buildings with varying degrees of heritage status. 

Concept 5  (involving  substantial  intersection upgrades but  four  lanes midblock) would require  substantially  less  land  acquisition  and  impact  on  9  heritage  properties  and  5 heritage buildings, including the Fawkner Mansions, ‘Shan Teng’ and the Arcadia Hotel. 

The  Committee  is  generally  supportive  of  Concept  5,  but  has  shown  a modified  form  of Concept  5  (Appendix  E)  for  consideration  that  still  provides  for  four  lanes  midblock, additional turn lanes and bus priority at each of the major intersections, but minimises land acquisition  and  removal  of  houses,  and  limits  the  impact  on  heritage  properties.    The Modified Concept 5 would require the demolition of only one heritage building, the Acadia Hotel.    If  the Modified Concept 5 were adopted,  the Committee anticipates  that  the PAO 

Page 10: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 4 of 162 

 

could be removed from 81 properties as  listed  in Section 8.4 of this report (subject to final design). 

The Committee is confident that the modified form of Concept 5 (which needs to be refined through more detailed design) would provide for adequate corridor capacity in the medium term  and well beyond 2031.    The Committee’s believes  that  the Modified Concept 5 will achieve good  levels of  service and more  than adequately  cater  for 2031 Base Case  traffic projections, and more so if permanent clearways and signal linking are implemented. 

The Committee therefore recommends that the PAO be modified to provide only the  land required for a road layout design based on the Modified Concept 5. 

The Committee has suggested Modified Concept 5 in order to show how some of the issues raised  in  submissions might be addressed.   The Committee  is conscious  that  the modified layout was  not  produced  until  after  the Hearing,  and  so  has  not  yet  been  fully  ‘tested’.  However,  the  issues  that  have  prompted  the  modified  layout  were  well  canvassed  in submissions and at  the Hearing.   The Committee believes  that modifying Concept 5  in  the way shown would resolve the vast majority of concerns raised with the Committee, whilst still providing adequate  future  traffic capacity.   The Committee acknowledges  that  further design work will be  required whichever  future concept  is adopted, and any change  to  the PAO will require a planning scheme amendment. 

The Committee believes  that Modified Concept 5  represents  a  reasonable balance of  the needs  of  the  local  community  versus  that  of  the  broader  Victorian  community,  and  the needs  of  current  versus  future  generations.    The  Committee  believes  that  the  outcome proposed  substantially  reduces  the  impacts  on,  and  improves  certainty  for,  landowners while responsibly providing  for  future capacity  improvements  for Punt Road.    In short, the Modified Concept 5 provides the greatest net community benefit. 

In making  this  recommendation, however,  the Committee  is  aware  that  its  assessment  is based on a number of critical assumptions.   The most critical of  these  is  that government policy will continue to support traffic demand management policies that discourage private vehicle trips into the Melbourne CBD and encourage mode shift to public transport.  Another critical assumption is that Punt Road north of the Yarra River will continue to be the capacity constraint  in  the corridor, and as a consequence  there  is  little  to be gained  in significantly increasing the capacity of Punt Road south of the Yarra River. 

The Committee believes that it may be worthwhile waiting for the completion of the 30 year infrastructure strategy being prepared by Infrastructure Victoria (expected to be completed in late 2016) to confirm support for these assumptions before making a final decision on the future of the Punt Road PAO. 

The  Committee  has  also made  findings  and  recommendations  in  relation  to  submissions made to it on environmental and social issues, including addressing the key issue of certainty for landowners.   

Page 11: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 5 of 162 

 

(ii) Recommendations 

The  Committee  makes  the  following  recommendations  in  response  to  its  Terms  of Reference: 

The Public Acquisition Overlay 

A Public Acquisition Overlay should be  retained  to  the extent  required  to ensure 1.that Punt Road can continue to fulfil its role in the short, medium and long term. 

On  the  basis  of  the  evidence  and  submissions  provided  to  the  Committee  in 2.relation  to  traffic demand and  the  future  role of Punt Road  in  the  road network, the Committee recommends: a) VicRoads develop a more detailed design layout that generally accords with 

the Modified  Concept  5  as  shown  in  Appendix  E, minimising  impacts  on heritage properties and minimising overall land acquisition whilst providing for a safe and functional design. 

b) The Punt Road Public Acquisition Overlay should be modified to provide for a  road  layout  generally  in  accordance with  the design based on Modified Concept 5. 

The Committee notes  that  Infrastructure Victoria  is currently preparing a 30 year 3.Infrastructure  Plan  for  Victoria,  and  recommends  that  the  Committee’s assumptions regarding the future strategic role of Punt Road are confirmed before a final decision to remove the balance of the Punt Road Public Acquisition Overlay. 

If  the Committee’s assumptions are confirmed,  then  the Committee  recommends 4.removal of the balance of the Public Acquisition Overlay not required to implement the final approved road configuration. 

Other actions recommended for Stonnington and Melbourne Councils 

The Cities of Stonnington and Melbourne,  in consultation with VicRoads, develop 5.an  integrated  land  use  and  transport  strategy  for  the  Punt  Road  corridor  that addresses: 

The  impact of  future  road widening on development potential of  land abutting Punt Road; 

Restrictions  on  direct  property  access  to  Punt  Road  for  future development in favour of access via other roads; and 

Preferred  urban  design  outcomes,  including  improved pedestrian/bicycle access and landscaping. 

Other actions recommended for VicRoads 

In order to improve certainty for landowners, VicRoads should: 6.

Define  the  areas  of  the  Public  Acquisition  Overlay  required  for  the future widening of Punt Road according to  its priority, that being short (0‐5 years), medium (5‐15 years) and long term (15+ years). 

Adopt a more flexible arrangement with regards to works owners could undertake to their properties, particularly properties  identified as  long term priorities  and develop  guidelines  to  clearly  identify  the  range of works that may be permitted and the conditions that would apply. 

Page 12: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 6 of 162 

 

Give priority  to  acquiring properties  that  are  identified  as  required  in the short and medium term, or at least give these property owners the option of acquisition.  

Prepare a Punt Road Public Acquisition Overlay Fact Sheet which simply and concisely outlines the strategic context of Punt Road, the purpose of the Public Acquisition Overlay, the proposed stages of work and the owner’s rights and obligations. 

Page 13: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 7 of 162 

 

1 Introduction 

1.1 Background 

The Victorian Government has committed to review the 20 metre Public Acquisition Overlay (PAO) along the east side of Punt Road between Alexandra Avenue in South Yarra and Union Street in Windsor as shown in Figures 1 and 2.  The PAO has been in place since 1954. 

 

Figure 1  Locality plan 

The  PAO  affects  135  properties  on  the  east  side  of  Punt  Road  and  49  and  51 Alexandra Avenue,  South  Yarra.    VicRoads  has  paid  compensation  on  ‘loss  on  sale’  or  purchased outright a number of affected properties, however no funding has been allocated for further acquisition or the construction of any road widening to date. 

The Punt Road/Hoddle Street corridor is one of Melbourne’s busiest and most congested key arterial  roads.   Punt Road  is  a declared  State  arterial  road  and  is used by  around 33,000 vehicles per day1.  It forms a boundary between the Cities of Melbourne and Stonnington. 

                                                       1   Source:  VicRoads  two  way  traffic  count  Punt  Road  (South  Yarra)  between  Alexandra  Avenue  and  Domain  Road  (2013)  ‐ 

https://www.vicroads.vic.gov.au/traffic‐and‐road‐use/road‐network‐and‐performance/road‐use‐and‐performance 

Page 14: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 8 of 162 

 

   

Figure 2  The existing PAO 

The Minister  for  Planning  has  appointed  an  Advisory  Committee  (the  Committee)  under Section 151 of the P&EA to undertake a review and recommend whether to retain, modify or remove the PAO. 

Page 15: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 9 of 162 

 

1.2 Terms of Reference 

The Committee is required to respond to the (revised) Terms of Reference approved by the Minister on 16 August 2015.  A copy of the Terms of Reference is attached as Appendix D. 

The Terms of Reference set out the purpose of the Committee, the method to be adopted for  the  inquiry,  and  notes  that  “the  Government  wishes  to  provide  certainty  about  this matter as some affected property owners wish to plan for the future of their properties and are concerned about whether the road widening will be going ahead”. 

The  Committee  has  conducted  the  inquiry  process  in  accordance  with  the  ‘Method’ requirements  in  the  Terms  of  Reference  and  all materials  required  to  be  prepared  and exhibited by VicRoads have been provided in accordance with the Terms of Reference. 

1.3 Advisory Committee process 

The  Advisory  Committee  consisting  of  Trevor  McCullough  (Chair),  Kevin  Breen  and  Sue Porter were appointed by the Minister for Planning on 5 March 2015.   Henry Turnbull was added to the Committee on 20 November 2015. 

In  accordance  with  the  Terms  of  Reference,  VicRoads  prepared  a  Background  Report, published in August 2015, and an Options Report, published in October 2015. 

The Committee  invited public submissions  in October 2015, with submissions closing on 24 November 2015.  A list of the 120 submitters is attached at Appendix A. 

A Directions Hearing was held on 8 December 2015, following which the Committee  issued directions to the parties on matters to be addressed prior to or at the Hearings.  Included in these directions was a requirement for VicRoads and PTV to circulate a ‘Part A’ submission clarifying their position on a number of matters by 24 December 2015. 

Public Hearings were held at the offices of Planning Panels Victoria on 9, 10, 11, 16, 18 and 19  February  2016.    The  Committee  heard  23  submissions  from  the  parties  and  expert witnesses  listed  in  Appendix  B.    The  Committee  conducted  several  unaccompanied  site inspections  to  assist  in  familiarising  itself  with  the  area  and  to  collect  data  for  the preparation of the report. 

1.4 Acknowledgements 

The Committee would like to acknowledge the substantial work undertaken by VicRoads and other submitters in providing the large body of material for the Committee’s consideration.  The  quality  of  submissions  was  high  and  the  Committee  commends  the  parties  for  the respect shown to the process and to the range of views that were expressed. 

The Committee also wishes  to  thank Greta Grivas  (Senior Project Officer, Planning Panels Victoria) and the Planning Panels administration team for their support during the course of the Inquiry. 

Page 16: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 10 of 162 

 

2 Identification of issues 

2.1 Summary of issues raised in submissions 

The key issues raised in the 120 written submissions are briefly summarised as follows: 

(i) VicRoads and PTV 

The key issues raised by VicRoads and PTV were: 

The  future of  the PAO  should  consider  the  role  it may play  in meeting  the  long‐term transport requirements of Melbourne. 

The  Punt  Road  corridor  is  considered  vital  to maintaining Melbourne’s  liveability  and access. 

The PAO balances the present and future needs of all Victorians ensuring real options are not built out, resulting in potential significant economic savings for all future Victorians.  

Punt Road is a vital city asset to support economic growth and jobs for the State through the delivery of freight and connecting jobs and opportunities across Melbourne. 

From  a  strategic  planning  perspective,  the  PAO  should  be  retained  to maintain  the opportunity  to  relieve  congestion and  facilitate a  short, medium and  long  term modal shift from private cars to public transport. 

Punt Road/Hoddle  Street  corridor  is  the only north‐south  arterial  that  can play a vital strategic bypass of central Melbourne, away from local roads and key activity centres. 

Punt  Road  carries  an  important  north‐south  public  transport  service  (bus)  which  is expected to increase patronage with increased population growth. 

Whilst  seven  concepts were presented,  there are an  infinite  set of design possibilities that should have regard to changing transport needs and technologies. 

All  but  three  affected  landowners  have  either  been  compensated  or  have  purchased their property with the knowledge of the PAO. 

(ii) Stonnington City Council 

The key issues raised by Stonnington City Council were: 

Concerns  regarding  the  time‐frame  and  analysis  undertaken  in  relation  to  traffic modelling assumptions. 

In balancing  competing  interests,  the  future of  the PAO must be  considered not only from a traffic modelling perspective, but from an urban planning perspective. 

Retention of the PAO will impact on Council’s ability to accommodate future residential growth along Punt Road. 

The future of the PAO should be based on a triple bottom line assessment with the aim of achieving net community benefit. 

There  are  negative  social,  urban  and  environmental  impacts  associated  with  the retention of the PAO, particularly  in relation to heritage properties and along the Yarra River corridor. 

Whilst supporting  improvements to Bus Route 246, a dedicated bus  lane  is not justified given the lack of investigation into all modes of public transport outside Punt Road. 

A future bicycle route is problematic particularly towards the northern end. 

Page 17: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 11 of 162 

 

(iii) Melbourne City Council 

The key issues raised by Melbourne City Councils were: 

The need for a vision and clearly articulated priorities to be achieved by a potential Punt Road upgrade before deciding on a final option. 

Works  to Punt Road  should extend beyond  simply  improving  travel  times  and  include good  urban  design  outcomes,  enhancing  public  transport  usage,  improved  pedestrian safety and experience and consideration of impacts on sites of heritage significance. 

The need to minimise  impacts of  future road design on open space,  including Fawkner Park, Alexandra Avenue and the Morrell Bridge area. 

The need for a reduction in speed limits should a clearway be introduced. 

The importance of prioritising public transport over the private vehicle. 

The need to improve pedestrian safety. 

The current presentation of Punt Road is poor and needs improvement. 

(iv) Individual Submitters 

The key issues raised by submitters were: 

The PAO  is creating unacceptable uncertainty for  landowners  in terms of whether their properties will be acquired, and if so when and what compensation will be payable. 

Above all,  landowners want certainty and  to  them certainty equates  to  the removal of the PAO, or for some submitters the immediate purchase of the reservation. 

There  is  a  need  to  develop  a  longer  term  plan  to  deal  with Melbourne’s  transport problems and Punt Road should not be considered in isolation. 

The PAO is outdated as it: “has been in place for over 60 years”; “it has never been called upon”; “VicRoads have no plans to widen the road”; “there is no budget allocated for any works or property acquisition”; and “there is no political will to widen it”; and therefore it should be removed. 

Alternative measures  should be  considered before  full  scale widening  is  contemplated including  clearways, permanent  removal of parking, off  road bus  stops, express  lanes, tunnelling, congestion tolls, limiting right hand turns, light sequencing. 

Widening Punt Road will result  in a six  lane freeway within  inner Melbourne which will have a significant impact on the liveability of the area, cause community division, impact on access  to community  facilities and open space, reduce pedestrian safety, as well as cause  increased  noise,  air  quality  and  vibrations  and  resultant  health  impacts, particularly for local school children.    

The proposed widening will attract induced traffic to Punt Road, which has experienced declining vehicle numbers over  the  last 20 years.   This will  increase  congestion  rather than achieving a modal change. 

The proposed widening of Punt Road should not be considered in isolation, but rather in the context of broader road network and with an increased focus on public transport and more sustainable transport options, such as walking and cycling. 

The widening of Punt Road will only lead to marginal improvements in travel times. 

The ability to improve north‐south traffic capacity along Punt Road is constrained by the Hoddle Bridge and the Punt Road Hoddle Street Corridor. 

The  widening  of  Punt  Road  would  result  in  the  removal  of  heritage  properties  and significant vegetation.  The PAO is also hindering restoration of heritage properties. 

Page 18: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 12 of 162 

 

The PAO is a misuse of a temporary planning instrument and has led to planning blight. 

Removal of the PAO will regenerate the area, including derelict VicRoads sites. 

The PAO is making it difficult to sell properties and is impacting property values. 

Landowners  have  had  difficulty  obtaining  planning  permits  to  undertake  renovations, repairs and maintenance  to  their properties and are unsure what  they can do  to  their properties  under  the  PAO.    It  acts  as  a  disincentive  to  undertake maintenance  and therefore results in significant deterioration of buildings. 

Support for the retention of the PAO and identification of the need to upgrade the road, ensuring improvements to local amenity by providing a median strip and landscaping. 

What impact will emerging technologies have on future transport planning? 

There has been inadequate consultation and unreasonable timeframes for input. 

A  very  useful  numerical  summary  of  issues  raised  in  submissions  was  also  provided  by Kinghorn and Carter in their expert evidence: 

Issue raised  No. submissions 

Increasing capacity will add more traffic to Punt Road  80 

Historic traffic decline  58 

Short term – clearways  27 

Short term – off road parking  7 

Short term – improvements to public transport  22 

Short term – banning right turns  3 

Short term – changing signal phasing  1 

Long term ‐ widening  1 

Long term – tunnel  16 

Long term – public transport  7 

Long term ‐ congestion  11 

Long term – planning strategy   4 

Loss in amenity to precinct (inc heritage)  90 

Widening would divide suburb  20 

Property values and uncertainty  60 

Safety of school children and pedestrians  38 

40 km/hr speed limit needed  55 

Modelling indicates only marginal travel improvements  58 

Further modelling is required  4 

Table 1  Summary of submissions 

The  issues raised  in submissions have been assessed as required  in the Terms of Reference and the assessment is set out under each subject heading in the report. 

Page 19: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 13 of 162 

 

2.2 The Committee’s approach to assessing the issues 

The Committee considered all background  reports and written submissions, as well as  the further submissions and expert evidence presented to it during the Hearings. 

The approach taken by the Committee in this report is as follows: 

Firstly, in Chapters 3 and 4, the report provides background to the issues and documents the material presented to the Committee. 

Secondly,  in  Chapters  5  to  7  the  Committee  examines  the  historical,  legislative  and strategic  context  of  the  issues  and  seeks  to  answer  whether  there  are  strategic  or economic imperatives that guide what the ultimate form of the PAO should be. 

Thirdly,  the  Committee,  in  Chapter  8,  reviews  the  traffic  and  transport  issues  and examines  the most  appropriate  form of  road  layout  to meet  short, medium  and  long term requirements in the Punt Road corridor.  This includes an examination of the seven concept  options  for  future  widening  of  Punt  Road  that  were  publicly  exhibited  by VicRoads. 

Fourthly, the Committee, in Chapters 9 to 13 examines a range of other issues raised in submissions and how they  impact, or are  impacted on, by the various widening options going forward. 

Finally, the Committee summarises its findings and recommendations in Chapter 14. 

The Committee has considered the issues in the context of: 

The requirements of the Terms of Reference 

The objectives and decision making principles of the TIA, and 

The  requirements  of  the  P&EA,  including  whether  the  various  concepts  have  a  net community benefit. 

2.3 Limitations 

The  assessment  carried  out  by  the  Committee  has  been  necessarily  limited  by  the information  that was able  to be provided  to  it.   While  the Committee acknowledges  that VicRoads  has  pulled  together  a  substantial  body  of  information  and  developed  concept options in a relatively short timeframe, the Committee was at times frustrated by not having access to information because “it could not be made publicly available”.  An example of this is the unavailability of any detailed information on the Streamlining Hoddle Street Initiative. 

The Committee was also disappointed with the absence of any submission from the RACV. 

Notwithstanding  these  limitations,  the  Committee  is  satisfied  that  the material  before  it provides  a  balanced  and  very  broad  cross  section  of  relevant  views  across  the  range  of stakeholders. 

The Committee also notes the work currently being done by Infrastructure Victoria on a 30 year  infrastructure strategy for Victoria.   This work  is still  in the consultation stage, but the direction coming out of the work may need to be monitored to see  if  it changes any of the Committee’s  assumptions  about  the  future  of  the  Punt  Road  corridor.    This  is  discussed further in Chapter 5. 

Page 20: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 14 of 162 

 

3 Historical context 

The earliest days of European settlement of Melbourne saw the establishment of ferry and punt services connecting the north and south banks of the Yarra River.  As noted in the City of Stonnington’s 2013 heritage citation for the Hoddle Bridge which now connects modern day Punt Road across the river: 

From the mid 1850s, another punt crossed the Yarra between South Yarra and Richmond, thus giving the name Punt Road to the track that  lead downhill to the river2. 

The citation goes on to note: 

In  1866,  a  footbridge  was  erected  near  Punt  Road,  but  the  punt  itself continued  to  operate  until  1898  when  a  bridge  opened  downstream  at Anderson Street, South Yarra.  The footbridge near Punt Road was replaced by a steel truss footbridge in the 1890s. 

By  the  1920s,  increased  use  of motor  cars was  placing  a  heavy  burden  on Melbourne's limited number of river bridges3. 

Among  the earliest bridge projects proposed  to  address  this  increase  in motorised  traffic was what was  to become  the current Hoddle Bridge, officially opened  in December 1938.  The citation goes on to state: 

The opening of Hoddle Bridge enabled Punt Road to become a major transport route  connecting Melbourne's  northern  and  southern  suburbs.    By  October 1939, the bridge was carrying over 10,000 cars a day4, 

VicRoads provided the Committee with an historical overview of how planning for the Punt Road transport corridor has evolved over the past century, particularly since 1929, as part of their Review of Punt Road Public Acquisition, Background Report, August 2015. 

In 1929 the then Metropolitan Town Planning Commission proposed a planning scheme to prevent  'misuse'  of  land  and  protect  property  values,  highlighting  traffic  congestion,  the distribution  of  recreational  open  space  and  haphazard  intermingling  of  land  uses  as  key issues.  This Plan included recommendations for a General Road Scheme which proposed an extensive network of  roads and  tramways with a proposed  tramline partly on  the current Punt Road alignment and partly to the west of the current road. 

The 1929 plan was not implemented and it was only after the Second World War in the early 1950s  that  the  broad  planning  system  as  it  is  today  commenced  with  the  Melbourne Metropolitan  Planning  Scheme  1954  Report.    This  plan,  prepared  by  the Melbourne  and Metropolitan Board of Works (MMBW), set out a network of proposed arterial roads which was  later enabled by an adopted planning scheme that “designated  land required  for road construction to be compulsorily acquired from its owners”.  It was through this 1954 planning scheme that the current PAO was imposed. 

                                                       2  City of Stonnington, Heritage Citation and Background Report, 2013  3  Ibid 4  Ibid 

Page 21: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 15 of 162 

 

VicRoads also state that the proposed routes in the 1954 scheme have “formed the basis for much of the major freeway construction and major road widening that has since occurred in Melbourne over the past  five decades.”5   They also note that variations to the  locations of some routes, route deletions and new connections to rural highways have occurred since. 

The  1954 MMBW plan  for Punt Road between  St Kilda  Junction  and  the  Yarra River was included as part of the ‘Proposed Arterial Road System’.  In that plan, “Punt Road between St Kilda  Junction  and  the  Yarra  River, was  intended  to  be  an  arterial  road with  intersecting roads and adjoining properties having access.    It was not  intended  to be a  freeway, which would not have access to other roads or adjoining properties other than via interchanges.”6 

VicRoads  listed  other  sections  of  roads  that  generally  affect  Punt  Road  that  have  been constructed  or widened  over  decades  up  to  the  1980s  including  Punt  Road  and  Hoddle Street north of  the river; Nepean Highway and St Kilda Road south of and around St Kilda junction; and sections of Queens Way/Dandenong Road. 

In 1969, a State Government Transportation Committee recommended a transport plan for Melbourne  that  included  a  comprehensive  network  of  freeways  as  well  as  railway  and tramways improvements.  In this plan a “freeway (‘F2’) was proposed in the general vicinity of  the Punt Road  ‐ Hoddle Street corridor crossing Melbourne  from  the outer north  to  the outer south east”7.  As VicRoads stated: 

The  implementation  of  this  freeway  network  would  have  resulted  in  very extensive property acquisition, severance and adverse environmental effects.  Such was  the  level  of  public  concern,  having  regard  to  factors  such  as  fuel shortages  in  the 1970s,  reaction  to property acquisition and neighbourhood severance,  and  preferences  for  public  transport,  that many  reservations  for future freeways were deleted from planning schemes, or were not proceeded with, particularly  in established areas, where  large scale property acquisition would have been required.8 

While reservations for freeways  in what were then outer areas were retained, or relocated or modified in response to environmental or heritage values, “the proposed inner sections of the F2, including the section in the vicinity of Punt Road between the Yarra River and Union Street, Windsor, have never proceeded”.9  The retention of the PAO along the section of Punt Road currently under consideration still enables strategic  road widening projects  to occur, although arguably in line with the 1954 designation of an arterial road system, rather than as part of a freeway system. 

As  described  elsewhere  in  this  report,  under  the  provisions  of  the  PAO  the  acquiring authority  (VicRoads as  it  is now known) made some property acquisitions up  to 1980 and have  continued  to  respond  to  the  administration  of  the  Planning  Scheme  in  respect  of planning permit applications on affected properties and  their basic obligations under  land compensation legislation such as ‘Loss on Sale’ compensation. 

                                                       5  VicRoads Review of Punt Road Public Acquisition, Background Report, August 2015.pp 6 6  Ibid 7  Ibid 8  Ibid pp7 9  Ibid 

Page 22: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 16 of 162 

 

4 Background material presented to the Committee 

4.1 VicRoads Background Report 

The  VicRoads  Review  of  Punt  Road  Public  Acquisition  Overlay:  Background  Report (Background Report) was published by VicRoads  in August 2015.   The Background Report was prepared in response to the Committee’s Terms of Reference.  The Terms of Reference identified  that  the  Background  Report  should  include  information  in  relation  to  the following: 

The history and background to the road widening/the overlay 

Detailed mapping of the overlay 

The  current  and  projected  traffic  volumes  for  all  modes  of  transport, including pedestrian, cyclist, car, heavy and public transport along and near Punt Road 

The  current  and  projected  traffic  volumes  for  all  modes  of  transport, including pedestrian, cyclist, car, heavy and public transport along and near Punt Road 

The current and projected regional road and transport network operation 

The  current  and  possible  future  configurations  of  Punt  Road  with  and without the overlay 

The current land use and built form of land subject to the overlay 

The current public transport along and crossing Punt Road 

The current planning controls 

The  benefits  (advantages)  and  costs  (disadvantages)  of  retaining  the overlay 

The  benefits  (advantages)  and  costs  (disadvantages)  of  removing  the overlay, including possible alternate road and transport network response 

Whether any modifications to the overlay are necessary. 

The  Background  Report  focused  on  the  history  of  Punt  Road,  land  use  and  transport planning,  legislative  and  policy  frameworks,  current  alignment  and  land  use  contexts including the mapping of the PAO, property  issues, current planning controls,  land use and built form, current and future road configuration options.  It also provided a summary of the advantages and disadvantages of retaining or removing the PAO, and  included maps of the land  subject  to  the  PAO,  detailed  aerial  review maps,  road  hierarchy maps  and  a  traffic works report. 

VicRoads  noted  that  the Background Report was  a  preliminary  report  and  not  a  detailed examination of the design, or a business case, for a future widened road. 

4.2 Options Report 

The Punt Road Concept Report (Options Report), published  in October 2015, was prepared for VicRoads by Arup.  The Options Report was prepared as part of Stage 2 of the Punt Road PAO  Committee  Terms  of  Reference,  to  expand  on  traffic modelling  and  projections  for various future concept options (concepts) along Punt Road. 

Page 23: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 17 of 162 

 

The Options  Report  had  the  purpose:  ‘to  outline  the  key  findings  from  an  appraisal  of  a range of possible improvement concepts for the Punt Road corridor that respond to forecast travel conditions in order to provide input into the PAO review’. 

The  scope  of  the Options  Report  includes  the  consideration  of  concepts  that  provide  for various configurations of at‐grade  intersections along the corridor, as well as concepts that include new  lanes  for existing public  transport  routes both along and across  the  corridor.  Concepts  that may  include  grade  separation,  tunnels  or major  new  transit  corridors  (e.g. new light rail systems) were not considered part of the scope of the study. 

To accompany the Options Report, VicRoads prepared the VicRoads Overview Report.   This was to be read in conjunction with the VicRoads Background Report and the Options Report. 

Concepts identified in the Options Report 

The Options Report focused on seven possible future concepts for Punt Road.  The concepts included options  that  could be  contained within  the existing  road  reservation boundaries, and others that would require the use of part or all of the land covered by the existing PAO.  The concepts all focussed on improved through‐traffic efficiency of the existing corridor. 

The Options Report included the following comments on the concepts presented: 

Each  of  the  concepts  are  considered  to  be  preliminary  only  and  include  a number of components  that are common  to each of  the concepts as well as assumptions for improvements to the network including: 

24  hour  clearways  implemented  for  all  concepts  with  the  extent  of reprovision of parking varying between the concepts; 

while outside the scope of this study, improvements to the intersection of St Kilda Road and Punt Road have been assumed to be undertaken if required which may include new turn lanes to be accommodated within the existing corridor; 

the  existing  delays  experienced  along  Hoddle  Street  (north  of  the investigation area) have been assumed to be  improved  in response to the forecast  travel  demands  through  signal  timing  adjustments  in  order  to facilitate  the delivery of  the capacity  improvements  that are  identified by each of the concepts; 

tram  lanes and new accessible  tram  stop have been proposed on Toorak Road, Commercial Road and High Street with the specific  location, time of day of application, type and extent of the facility is to be further developed; 

the changes that each of the concepts presents for property and local road access  has  not  been  considered  in  detail  and  would  require  further development including consultation with the community, Council and other stakeholders.    This  may  require  slight  modification  to  the  concepts  to increase  access  to  Punt  Road  or may  require mechanisms  to  reduce  the potential  for  increases  in  traffic on  the  local  road network as a  result  of restrictions to the right turn movements; 

general  improvements  to  the walking  and  cycling  facilities with  possible treatments  including new  footpaths,  improved signage, cycling head‐start storage boxes etc; and 

Page 24: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 18 of 162 

 

peak period right turn bans are included in each of the concepts with these applying  to  both  the  morning  and  evening  peak  hour  unless  indicated otherwise. 

The  seven concepts are  summarised  in  the  following paragraphs.   Concept drawings were provided for each concept showing the possible lane configuration and property impact. 

(i) Concept 1 – 24 Hour Clearways 

Clearways  currently  apply  along  Punt Road  in  both  the morning  (6:30am  to  9:30am)  and evening (3:30pm to 6:30pm) on weekdays.  Concept 1 involves the extension of clearways to 24 hours a day, 7 days a week,  in order  to  improve  the efficiency of Punt Road between Union Street and the Yarra River outside peak periods. 

The Options Report assessed  this concept as viable  for  the short  term only, as  it does not address  the  congestion  issues during  the AM  and PM peak periods or provide  significant benefits for other modes of transport. 

The  Government  is  currently  undertaking  the  statutory  requirements  to  allow  the implementation of the 24 hour clearway option.  This is briefly discussed in Chapter 4 of this report. 

(ii) Concept 2 – 4 Lane: Central Right Lane Turn 

Concept 2  involves changes within the existing road reserve to provide a fifth central  lane.  This lane would be designated to provide right turn lanes at some major and minor roads.  A number of changes would take place to the operation of key movements such as simplifying traffic signal operations and improving efficiency for all modes of transport. 

The  Options  Report  assessed  this  concept  as  a  viable  short  term  improvement  concept, however, it does not have the flexibility to address the long term demands for travel across the network.   This concept would address short to  long term congestion  issues to a degree and  provide  some  benefits  for  users  crossing  the  corridor  including  pedestrians,  cyclists, tram and bus passengers. 

(iii) Concept 3 – 4 Lane: Narrow Central Median 

Concept 3  involves  changes within  the existing  road  reserve  to provide a  central median.  This  concept  includes  the  same  intersection  changes  as  Concept  2  and  modifies  the operation of key right turn movements in order to simplify traffic signal operations. 

The  Options  Report  assessed  this  concept  as  providing  similar  benefits  and  impacts  to Concept 2.   Further assessment would be required  in relation to the changes to  local roads and property access. 

(iv) Concept 4 – 5 Lane: Reversible Lane 

Concept 4 involves changes within the existing road reserve (in most areas) to provide a fifth reversible central lane.  A reversible central lane would utilise overhead signs to operate as a reversible  lane,  serving  the  typical  peak  direction  of  travel  along  the  corridor  (e.g. northbound in the morning peak and southbound in the evening peak hour).  This concept is 

Page 25: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 19 of 162 

 

similar  to  the  treatments  along Queens  Road  in Melbourne  and  along  Johnson  Street  in Collingwood/Abbotsford. 

The Options Report assessed this concept as unviable  in the short, medium and  long term, would not offer significant benefits for road users and would require restrictions to strategic movements on the corridor. 

Prior to the Hearing, VicRoads advised that it no longer regarded this as a viable option and accordingly, it was not considered further. 

(v) Concept 5 – 4 Lane/6 Lane Widened Intersections 

Concept  5  involves  flaring  of  each  of  the  major  intersections  through  acquisition  of properties on the east side of Punt Road.  The cross sections would narrow back to broadly match the existing kerb line between intersections. 

Concept 5 includes: 

construction of a new or widened Hoddle Bridge 

additional through and turn  lanes at the  intersections of High Street, Commercial Road, Toorak Road and Alexandra Avenue 

increased green time for crossing roads; and 

partial or full acquisition of 65 properties. 

Similar to previous concepts, the operation of key right turn movements are modified in this concept in order to simplify traffic signal operations. 

The Options Report assessed  this  concept as viable  for  the medium  to  long  term and  the overall travel demands of the corridor.    It would provide benefits for the surrounding road network and for users crossing the corridor including pedestrians, cyclists, and tram and bus passengers.    However,  there  would  also  be  significant  impacts,  in  particular  for approximately  half  the  existing  properties  currently  subject  to  the  PAO.    Impacts  on  a substantial number of heritage properties would also result. 

(vi) Concept 6 – 6 Lane: Dual Carriageway 

Concept 6  involves  the  full utilisation of  the PAO and  the acquisition of properties on  the east side for the length of Punt Road in order to provide a lane dual carriageway.  Similar to previous concepts, the operation of key right turn movements are modified in this Concept, in order to simplify traffic signal operations. 

The Options  Report  assessed  this  concept  as  only  viable  in  the  long  term.    This  concept provides similar benefits  to Concept 5 but will  impact on all 135 properties subject  to  the PAO including those with a heritage overlay.  Although there is limited additional benefit of this option in its current form when compared to Concept 5, the Options Report states that this concept would  involve flexibility over a  longer planning horizon (e.g. 30 plus years) for further  enhancements  to  the  corridor  (e.g.  high  capacity  public  transport  linkages)  and streetscape improvements through landscaping. 

(vii) Concept 7 – 4 Lane/6 Lane: Bus Lanes 

Concept 7 involves acquisition of properties on the east side for the majority of the length of Punt Road in order to provide a six lane dual carriageway comprising two traffic lanes and a 

Page 26: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 20 of 162 

 

bus  lane  in each direction.   This concept also  incorporates widening on  the approaches  to the intersections to provide further capacity enhancements. 

Similar  to  previous  concepts,  the  operation  of  key  right  turn movements  are modified  in order to simplify traffic signal operations. 

The Options Report assessed this concept as a viable concept for the Punt Road corridor  in the medium  to  long  term.    This  concept  provides  similar  benefits  to  Concept  5  and  also provides the opportunity to encourage mode shift to public transport  in the  long term and streetscape  improvements  through  landscaping.    It would address  the  short, medium and long  term  travel demands  for  the  corridor, and provide benefits  for  the  surrounding  road network.  It also offers a similar level of flexibility to Concept 6 for further enhancements to the  corridor  in  the  long  term.   However,  similar  to Concept  6  there would  be  significant impacts, due to the extent of land acquisition that would be required and impacts within the Heritage Overlay. 

(viii) Other alternatives for side roads and intersection improvements 

The Options Report showed a number of additional improvement alternatives not involving use of the Punt Road PAO including: 

Raised tram stops in High Street, Commercial Road and Toorak Road 

Changed lane configurations on High Street, Commercial Road and Toorak Road 

U turn treatment in Commercial Road west of Punt Road 

U turn treatment in Toorak Road west of Punt Road adjacent to Walsh Street (potentially requiring minor intrusion into Fawkner Park) 

A continuous flow right turn lane from Alexandra Avenue south‐east to Punt Road north 

A new bridge along‐side Morrell Bridge to allow right turns from Alexandra Avenue and linking across the River to Batman Avenue and Punt Road north (with no right turn from Alexandra Avenue into Punt Road north) 

A new Batman Avenue link to Punt Road at Kelso Street 

No right turn from Alexandra Avenue  into Punt Road from either direction and use of a widened Dobson Street to access Punt Road. 

Each  of  these  alternatives were  presented  to  show  that  there  are  other  alternatives  for improving  traffic along and across Punt Road  in addition  to  those  that use  the PAO.   The Committee  has  not  given  detailed  consideration  to  any  of  these  additional  alternatives.  Some of the alternatives arguably would assist relieving congestion or improving traffic flow, however, none of them are considered ‘game changers’ in terms of the resolving the issue of the  need  to widen  Punt  Road  or  not.    The  Committee  generally  supports  the  notion  of implementing other network  improvements, but  it  is outside the scope of the work of the Committee to give detailed consideration to these alternatives. 

(ix) The Committee’s Modified Concept 5 

The Committee has shown a modified version of Concept 5 for comparison purposes.   The layout  is  similar  to  Concept  5  but  with  substantially  reduced  land  acquisition  and  not including  a  new  or widened Hoddle  Bridge.    The Modified  Concept  5  proposed  is  shown graphically in Appendix E. 

Page 27: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 21 of 162 

 

As is the case for the concepts presented by VicRoads, the Committee’s modified concept is a preliminary concept only and would need further refinement of the design before property acquisition boundaries could be finalised. 

The performance of  the modified  layout  is discussed  in  the Committee’s analysis of  traffic and transport issues in Chapter 8. 

4.3 Streamlining  Hoddle  Street  Initiative  and  Punt  Road  Transport Investigation 

VicRoads  is currently undertaking  these  two studies aimed at short  term  improvements  in the Hoddle Street‐Punt Road corridor. 

Streamlining Hoddle Street Initiative 

This Project  is  to explore  innovative  ideas  to  increase  the movement of people along and across the section of Hoddle Street from the Eastern Freeway to CityLink. 

As part of  its  investigations  for Hoddle Street, VicRoads will  look at short to medium term improvements that could be implemented in the next two to four years. 

Strategies being investigated include: 

enhancing computerised traffic management systems 

revising operations at intersections 

prioritising public transport 

exploring  the  use  of  ‘continuous  flow  intersections’,  which  are  designed  to  improve traffic flow through intersections by reducing delays caused by right‐turning traffic. 

The Project  is  relevant  to  the Punt Road  section  if  it  is  successful  in  relieving  the existing congestion  north  of  the  Yarra  River  as  a  core  assumption  underpinning  all  the  VicRoads Concepts was that the existing delays experienced along Hoddle Street  (north of the Yarra River) have been assumed to be improved through signal timing adjustments. 

The Government announced  in April 2016  that $60 million has been allocated  to  fund  the first stage of the Streamlining Hoddle Street initiative. 

The first stage will  include an upgrade to the Swan Street  intersection with a concept for a continuous  flow  intersection  being  developed  and  construction  expected  to  begin  in mid 2017.  The Committee requested more detailed information on the plans and information on expected  capacity  improvements;  however  VicRoads  was  unable  to  make  any  detailed information publicly available. 

Punt Road Transport Investigations 

This Project  is considering  short  term  road network changes  to  improve  traffic movement within the existing road cross section on Punt Road between Alexandra Avenue and Union Street (south of the Yarra).  The Project is considering 24 hour clearways, the potential for a fifth  lane  and  concepts  for  improving  traffic  and  public  transport  operations  across  Punt Road. 

This investigation has directly informed the development of Concepts 1 to 4. 

As  a  result  of  the  investigation  and  associated  consultation,  steps  to  implement  the introduction of 24 hour clearways were commenced in January 2016. 

Page 28: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 22 of 162 

 

It is proposed to change clearway operating times in the following locations: 

Punt Road – from St Kilda Junction to Alexandra Avenue 

Alexandra Avenue – for up to 80 metres in both directions on the west side of the Punt Road intersection 

Toorak Road intersection on the: - East side for 55 metres outbound and 35 metres inbound - West side for 100 metres in both directions 

Commercial Road –  for 65 metres  in both directions on the east side of the Punt Road intersection 

High Street – for 70 metres in both directions on each side of the Punt Road intersection. 

The  clearways  are  proposed  to  operate  24  hours,  7  days  a week  (with  the  exception  of Toorak Road east and Punt Road south of Gladstone Street where some sections will only operate in the morning and afternoon peak periods). 

VicRoads  is currently conducting consultation on the proposal  in accordance with the Road Management Act 2004.  Subject to the outcome of that consultation, the 24 hour clearways are likely to be implemented in mid‐2016. 

4.4 Consultation undertaken by VicRoads 

VicRoads  undertook  community  consultation  from  24  August  to  21  September  2015,  in relation  to  several  projects  along  the  Punt  Road‐Hoddle  Street  Corridor.    These  projects included the Streamlining Hoddle Street Initiative and the Punt Road Transport Investigation. 

As  part  of  this  consultation,  VicRoads  conducted  online  community  consultation,  which received 668 contributions.   A total of 280 participants commented on the section of Punt Road south of the Yarra River, and of these participants, 54 per cent were concerned with issues that related to traffic and freight.  Private Car Users made up the largest proportion of participants  (30  per  cent),  followed  by  Residents  (21  per  cent),  whilst  20  per  cent  of participants chose not to answer.10  Online participants raised the following issues: 

Congestion is a major issue throughout the corridor for all user groups 

There is support for extended clearways to ease congestion, enhance safety and improve traffic flow 

Participants generally favoured higher priority for public transport 

Cyclists and pedestrians do not feel safe in the corridor.11 

The  VicRoads  community  consultation  also  included  ‘drop  in’  information  sessions  about several projects  in the Punt Road – Hoddle Street corridor and  information about the Punt Road  PAO  Committee.    These  ‘drop  in’  information  sessions were  held  on  12  September 2015  at Catholic  Leadership Centre,  Simonds Hall, East Melbourne,  and on 16  September 2015 at Wesley College, St Kilda Road Campus. 

VicRoads  also  conducted  stakeholder engagement with Government agencies,  community representative groups, public transport operators, user groups and the RACV, and conducted three  Council  workshops  with  Councils  interfacing  with  the  Hoddle  Street  –  Punt  Road corridor. 

                                                       10  VicRoads Concept Options Overview Report, p7. 11  VicRoads Information Update brochure, October 2015. 

Page 29: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 23 of 162 

 

4.5 Other documents provided to the Committee 

The  Committee  was  provided  with  a  wide  range  of  material.    A  full  list  of  documents provided at the Hearings is attached as Attachment C. 

The following is a list of the more significant documents provided: 

VicRoads Noise Reduction Policy 2005 

Plan Melbourne and Plan Melbourne Refresh (extracts) 

VicRoads SmartRoads brochure 2011 

Principal Bicycle Network Fact Sheet 2012 

Various heritage property citations 

VicRoads Traffic Monitor 2012‐13 2015 

Punt Road Community Engagement Report 2015 

Fawkner Park Master Plan 2006 

City of Melbourne Open Space Strategy 

City of Melbourne Road Safety Plan 2013‐2017 

City of Melbourne Transport Strategy 2012 

City of Stonnington Strategies for Creating Open Space 

City of Stonnington Street Tree Strategy 

City of Stonnington Significant Tree Registry 

City of Stonnington heritage information for Punt Road properties 

City of Stonnington Road Management Plan 2013 

City of Stonnington Road Safety Policy 2008‐2017 

City of Stonnington Public Transport Advocacy Statement 2014 

City of Stonnington Cycling Strategy 2013‐2018. 

In  addition,  the  Committee  considered  expert  witness  reports  provided  to  it  from  the following expert witnesses: 

Mr Paul Carter and Mr Jonathon Kinghorn on Transport 

Mr Reece Humphreys on Traffic Engineering and Transport 

Mr Rob Milner on Planning 

Mr Andrew Kinnaird on Economic/valuation 

Mr Knowles Tivendale on Traffic and Transport 

Mr Ian Shears on Open Space 

Mr Jim Higgs on Traffic Engineering. 

Page 30: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 24 of 162 

 

5 Legislative and strategic context 

VicRoads, Stonnington City Council and Melbourne City Council all referred to the legislative and strategic framework in place that guides the Committee’s decision making in relation to whether the PAO should be retained, modified or removed. 

The  Committee  has  reviewed  the  legislative  framework  and  State  and  local  strategic frameworks that guide the Committee’s consideration about the future of the PAO. 

5.1 Road Management Act 2004 

The Road Management Act 2004 provides the overarching governance for the road network, its  management  and  performance.    It  is  a  statutory  framework  that  provides  a  set  of principles for the management of the road system. 

Section  20(1)  seeks  to  ensure  that  a  network  of  roads  is  provided  primarily  for  the movement of persons and goods as part of an  integrated  transport  system and  that  road reserves are available for other appropriate uses.  Further, Section 20(1A) states: 

In giving effect to the principal object of road management consistent with the transport  system  objectives  under  the Transport  Integration  Act 2010 , the road network is to be managed to reflect the priorities of different modes of  transport having  regard  to  the  intended  function or functions of different parts of the road network. 

5.2 The Transport Integration Act 2010 

The Transport  Integration Act 2010  (TIA)  is  the primary  transport  statute  for Victoria  and guides how transport decisions are to be made. 

(i) Vision 

In doing so, the TIA establishes a vision for the transport system based on five key objectives, these are: 

Social and economic inclusion12 

The transport  system should  provide  a means  by which  persons  can  access social  and  economic  opportunities  to  support  individual  and  community wellbeing including by— 

(a) minimising barriers  to access so  that so  far as  is possible  the transport system is available to as many persons as wish to use it; 

(b) providing  tailored  infrastructure,  services and  support  for persons who find it difficult to use the transport system. 

Economic prosperity13 

The transport system should facilitate economic prosperity by— 

                                                       12  Transport Integration Act 2010 Section 8 13  Transport Integration Act 2010 Section 9 

Page 31: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 25 of 162 

 

(a) enabling efficient and effective access for persons and goods to places of employment, markets and services; 

(b) increasing efficiency through reducing costs and improving timeliness; 

(c) fostering competition by providing access to markets; 

(d) facilitating investment in Victoria; 

(e) supporting financial sustainability. 

Environmental sustainability14 

The transport  system should  actively  contribute  to  environmental sustainability by— 

(a) protecting, conserving and improving the natural environment; 

(b) avoiding,  minimising  and  offsetting  harm  to  the  local  and  global environment,  including  through  transport‐related  emissions  and pollutants and the loss of biodiversity; 

(c) promoting  forms  of  transport  and  the  use  of  forms  of  energy  and transport  technologies  which  have  the  least  impact  on  the  natural environment  and  reduce  the  overall  contribution  of  transport‐related greenhouse gas emissions; 

(d) improving the environmental performance of all forms of transport and the forms of energy used in transport; 

(e) preparing  for  and  adapting  to  the  challenges  presented  by  climate change. 

Efficiency, coordination and reliability15 

(1) The transport  system should  provide  for  the  effective  integration  of transport  and  land  use  and  facilitate  access  to  social  and  economic opportunities. 

(2) Without  limiting  the  generality  of  subsection  (1),  transport  and  land use should be effectively  integrated so as to  improve accessibility and transport efficiency with a focus on— 

(a) maximising access to residences, employment, markets, services and recreation; 

(b) planning and developing the transport system more effectively; 

(c) reducing  the  need  for  private motor  vehicle transport  and  the extent of travel; 

(d) facilitating  better  access  to,  and  greater mobility within,  local communities. 

                                                       14   Transport Integration Act 2010 Section 10 15   Transport Integration Act 2010 Section 12 

Page 32: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 26 of 162 

 

Safety and health and wellbeing16 

(1) The transport system should be safe and support health and wellbeing. 

(2) Without  limiting  the  generality  of  subsection  (1), the transport system should— 

(a) seek  to  continually  improve  the  safety  performance  of the transport system through‐ 

(i) safe transport infrastructure; 

(ii) safe forms of transport; 

(iii) safe transport system user behaviour; 

(b) avoid and minimise the risk of harm to persons arising from the transport system; 

(c) promote forms of transport and the use of forms of energy which have the greatest benefit for, and least negative impact on, health and wellbeing. 

(ii) Decision Making Principles 

The Act also specifies a number of ‘Decision Making Principles’, these include: 

 Principle of integrated decision making17 

The  principle  of  integrated  decision  making  means  seeking  to  achieve Government  policy  objectives  through  coordination  between  all  levels  of government and government agencies and with the private sector. 

Principle of triple bottom line assessment18 

The principle of triple bottom‐line assessment means an assessment of all the economic,  social  and  environmental  costs  and  benefits  taking  into  account externalities and value for money.

Principle of equity19 

The principle of equity means— 

(a) equity between persons irrespective of their— 

(i) personal  attributes,  including  age,  physical  ability,  ethnicity, culture, gender and financial situation; or 

(ii) location, including whether in a growth, urban, regional, rural or remote area; 

(b) equity between generations by not compromising the ability of future generations to meet their needs. 

                                                       16  Transport Integration Act 2010 Section 13 17  Transport Integration Act 2010 Section 15 18  Transport Integration Act 2010 Section 16 19  Transport Integration Act 2010 Section 17 

Page 33: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 27 of 162 

 

Principle of the transport system user perspective20 

The transport system user perspective means— 

(a) understanding  the  requirements  of transport  system users,  including their information needs; 

(b) enhancing  the  useability  of  the transport  system and  the  quality  of experiences of the transport system. 

Precautionary principle21 (1) The precautionary principle means  that  if  there are  threats of serious 

or  irreversible  environmental  damage,  lack  of  full  scientific  certainty should  not  be  used  as  a  reason  for  postponing measures  to  prevent environmental degradation. 

(2) The precautionary principle includes— 

(a) a  careful  evaluation  to  avoid  serious  or  irreversible  damage  to the environment wherever practicable; and 

(b) an  assessment  of  the  risk‐weighted  consequences  of  various options. 

Principle of stakeholder engagement and community participation22 

The  principle  of  stakeholder  engagement  and  community  participation means— 

(a)  taking  into  account  the  interests  of  stakeholders, including transport system users  and  members  of  the  local community; 

(b)  adopting appropriate processes for stakeholder engagement. 

Principle of transparency23 

The principle of transparency means members of the public should have access to reliable and relevant  information  in appropriate forms to facilitate a good understanding  of  transport  issues  and  the  process  by  which  decisions  in relation to the transport system are made. 

5.3 Planning and Environment Act 1987 

The Planning and Environment Act 1987 (P&EA) and the Transport Integration Act 2010 (TIA) are  interface  legislation.   As  interface  legislation,  implementation of this  legislation  is to be coordinated. 

The P&EA establishes the objectives of planning, these are:    

                                                       20  Transport Integration Act 2010 Section 18 21  Transport Integration Act 2010 Section 19 22  Transport Integration Act 2010 Section 20 23  Transport Integration Act 2010 Section 21 

Page 34: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 28 of 162 

 

Objectives 

(a) to  provide  for  the  fair,  orderly,  economic  and  sustainable  use, and development of land; 

(b) to provide  for  the protection  of natural and man‐made  resources and the maintenance of ecological processes and genetic diversity; 

(c) to secure a pleasant, efficient and safe working,  living and recreational environment for all Victorians and visitors to Victoria; 

(d) to  conserve  and  enhance  those buildings, areas or  other  places  which are  of  scientific,  aesthetic,  architectural  or  historical  interest,  or otherwise of special cultural value; 

(e) to  protect  public  utilities  and  other  assets  and  enable  the  orderly provision and co‐ordination of public utilities and other facilities for the benefit of the community; 

(f) to  facilitate development in  accordance with  the  objectives  set  out  in paragraphs (a), (b), (c), (d) and (e); 

(g) to balance the present and future interests of all Victorians. 

5.4 State Planning Policy Framework (SPPF) 

There is a significant amount of State policy that is relevant, both directly and indirectly, to the future of the Punt Road PAO. 

VicRoads, Stonnington City Council and Melbourne City Council all made  reference  to  the SPPF,  some  in  support  for  the  retention  of  the  PAO,  and  some  for  its  removal.    The Committee has also identified additional policy not referred to in submissions. 

The relevant policy is outlined below:  Clause 10.04 ‐ Integrated decision making – identifies that society has various needs and 

expectations  and  that  when  integrating  policy,  conflicting  objectives  should  be balanced  in  favour of net  community benefit and  sustainable development  for  the benefit of present and future generations.  It also emphasises that strategic planning should  be  co‐ordinated  amongst  municipal  planning  authorities  and  other  public bodies  to  achieve  sustainable  development  and  effective  and  efficient  use  of resources. 

Clause 11 – Settlement – emphasises that planning  is to anticipate and respond to the needs of existing and future communities through a range of land uses, as well as the provision of  infrastructure.    In doing so,  it seeks to  integrate transport and  land use (amongst others) emphasising that planning  is to facilitate sustainable development that takes full advantage of existing settlement patterns and investment in transport and other infrastructure.  

Clause  11.04‐3  ‐  A  more  connected  Melbourne  objective  –  seeks  to  provide  an integrated  transport  system  connecting  people  to  jobs  and  services,  and  goods  to market.  The relevant strategies include transforming the transport system to support a more productive central city;  improving access to  job‐rich areas across Melbourne and  strengthening  transport  networks  in  existing  suburbs;  improving  local  travel 

Page 35: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 29 of 162 

 

options to increase social and economic participation; and improving the efficiency of freight networks while protecting urban amenity. 

Clause 12.05‐2  ‐ Yarra River protection objective – seeks to maintain and enhance the natural  landscape  character  of  the  Yarra  River  corridor  in which  the  topography, waterway, banks and  tree canopy are dominant  features providing a highly valued, secluded, natural environment for the enjoyment of the public.  It includes strategies to  strengthen  the  river’s  natural  environment,  heritage  and  overall  health; maintaining  a  sense  of  place  and  landscape;  as  well  as  retaining  and  enhancing people’s enjoyment of the river and its environment.  A key strategy is to protect the river’s  riparian  vegetation,  natural  riverbank  topography  and  flood  management capacity, as well as retaining a dominant and consistent tree canopy along the river corridor and within its broader landscape setting. 

Clause 13.04‐1 ‐ Noise abatement objective – seeks to assist the control of noise effects on sensitive land uses. 

Clause 13.04‐2 ‐ Air quality objective – seeks to assist the protection and  improvement of  air  quality  by  ensuring  land  use  planning  and  transport  infrastructure  provision contributes  to  improved  air  quality  through  improved  transport  accessibility, connections and providing infrastructure for public transport, walking and cycling. 

Clause 15.01‐1 ‐ Urban design objective – seeks to create urban environments that are safe,  functional  and  provide  good  quality  environments with  a  sense  of  place  and cultural identity.  One of the key strategies is to ensure transport corridors integrate land use planning and are developed and managed with particular attention to urban design aspects. 

Clause 15.01‐4  ‐ Design  for safety objective – seeks  to  improve community safety and encourage  neighbourhood  design  that  makes  people  feel  safe.    One  of  the  key strategies  is  to support  initiatives  that provide safer walking and cycling routes and improve safety for people using public transport. 

Clause  15.01‐5  ‐  Cultural  identity  and  neighbourhood  character  objective  –  seeks  to recognise and protect cultural identity, neighbourhood character and sense of place.  Key strategies to achieve this  include ensuring development responds to  its context and reinforces heritage values/built form that reflects community identity; as well as the values, needs and aspirations of the community. 

Clause 15.02‐1  ‐ Sustainable development  ‐Energy and  resource efficiency objective – seeks to encourage land use and development that is consistent with the efficient use of  energy  and  the minimisation  of  greenhouse  gas  emissions.    Key  strategies  to achieve  this  include  the  integration  of  land  use  and  transport  by  supporting  low energy forms of transport, such as walking and cycling. 

Clause 15.03‐1 ‐ Heritage conservation objective – seeks to ensure the conservation of places of heritage significance.  Key strategies include providing for the conservation and  enhancement  of  places  of  cultural  or  social  significance;  encouraging development  that  respects  places  with  identified  heritage  values  and  creates  a worthy legacy for future generations; retaining those elements that contribute to the importance of the heritage place and restoration of contributory elements; as well as ensuring  an  appropriate  setting  and  context  for  heritage  places  is maintained  or enhanced. 

Page 36: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 30 of 162 

 

Clause 15.03‐2 ‐ Aboriginal cultural heritage objective – seeks to ensure the protection and conservation of places of Aboriginal cultural heritage significance.  A key strategy is to provide for the protection and conservation of pre and post‐contact Aboriginal cultural heritage places. 

Clause 17.03‐2 ‐ Tourism in Metropolitan Melbourne objective – seeks to maintain and develop  Metropolitan  Melbourne  as  a  desirable  tourist  destination.    Relevant strategies include maintaining Metropolitan Melbourne's position as a destination in its  own  right  by  developing  city  precincts  and  promenades,  as well  as  improving transport infrastructure. 

Clause  18.01‐1  ‐  Integrated  Transport  ‐  Land use  and  transport  planning  objective  – seeks to create a safe and sustainable transport system by  integrating  land‐use and transport.   Two key strategies  to achieve  this are  to develop  transport networks  to support employment corridors that allow circumferential and radial movements and to plan urban development  to make  jobs and community  services more accessible.  Some of the ways this is to be achieved by: 

Ensuring  access  is  provided  to  developments  in  accordance  with  forecast demand,  taking advantage of all available modes of  transport and  to minimise adverse  impacts on existing transport networks and the amenity of surrounding areas. 

Coordinating  improvements  to  public  transport, walking  and  cycling  networks with the ongoing development and redevelopment of the urban area. 

Concentrating key trip generators such as higher density residential development in and around Central Activities Districts, Principal, Major and Specialised Activity Centres on the Principal Public Transport Network. 

Providing  safe,  convenient  and  direct  pedestrian  and  cycling  access  to  activity centres, public transport interchanges and other strategic redevelopment sites. 

Clause 18.01‐2  ‐ Transport  system objective –  seeks  to  coordinate development of all transport modes to provide a comprehensive transport system.  The key strategies to achieve this include: 

Requiring  transport  system management plans  for  key  transport  corridors  and reserving land for strategic transport infrastructure. 

Incorporating  the provision of public  transport  and  cycling  infrastructure  in  all major new State and local Government road projects. 

Locating  transport  routes  to  achieve  the  greatest  overall  benefit  to  the community and with regard to making the best use of existing social, cultural and economic infrastructure, minimising impacts on the environment and optimising accessibility, safety, emergency access, service and amenity. 

Locating and designing new transport routes and adjoining land uses to minimise disruption of residential communities and their amenity. 

Planning  or  regulating  new  uses  or  development  of  land  near  an  existing  or proposed transport route to avoid detriment to, and where possible enhance the service,  safety and amenity desirable  for  that  transport  route  in  the  short and long terms. 

Encouraging  higher  land  use  densities  and  mixed  use  developments  near principal bus routes and other locations. 

Page 37: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 31 of 162 

 

Ensuring  transport  practices,  including  design,  construction  and management reduce environmental impacts. 

Consider  all modes  of  travel,  including walking,  cycling,  public  transport,  taxis and  private  vehicles  (passenger  and  freight)  in  providing  for  access  to  new developments. 

Clause 18.02‐1 ‐ Movement networks ‐ Sustainable personal transport objective – seeks to promote the use of sustainable personal transport.  Strategies include developing safe  and  attractive  walking  and  cycling  environments  that  are  also  accessible  to footpath‐bound vehicles such as wheelchairs, prams and scooters. 

Clause 18.02‐2 ‐ Cycling objective – seeks to integrate planning for cycling with land use and development planning and encourage alternative modes of travel.  One strategy seeks to ensure bicycle infrastructure is planned to separate cyclists from other road users, particularly motor vehicles, whilst providing the most direct route practical.  It also  seeks  to  link with  and  complement  the metropolitan‐wide  network  of  bicycle routes – the Principal Bicycle Network. 

Clause 18.02‐3  ‐ Principal Public Transport Network objective –  seeks  to upgrade and develop the Principal Public Transport Network and local public transport services in Metropolitan Melbourne  to  connect  activity  centres,  link  activities  in  employment corridors and link Melbourne to the regional cities.  A key strategy is to improve the operation  of  the  existing  public  transport  network with  faster, more  reliable  and efficient on‐road  transport by  improving  the movement, efficiency and reliability of the road‐based public transport through road‐space management measures including transit lanes, clearways, traffic‐light prioritisation and stop design. 

Clause 18.02‐4 ‐ Management of the road system objective – seeks to manage the road system to achieve integration, choice and balance by developing an efficient and safe network  and  making  the  most  of  existing  infrastructure.    Key  strategies  include planning and regulating  the design of  transport routes and nearby areas  to achieve visual  standards appropriate  to  the  importance of  the  route,  including  landscaping.  In addition, it seeks to make better use of roads for all road users through techniques such as  the provision of wider  footpaths, bicycle  lanes,  transit  lanes  (for buses and taxis) and specific freight routes, as well as improving the management of key freight routes  to  make  freight  operations  more  efficient  while  reducing  their  external impacts. 

Clause 18.05‐1 ‐ Freight ‐ Develop freight links objective – seeks to further develop key transport gateways and freight  links and maintain Victoria’s position as the nation’s premier logistics centre.  A key strategy to achieve this is to improve the freight and logistics network to optimise freight handling. 

5.5 Plan Melbourne 

Plan Melbourne outlines the vision for Melbourne’s growth to 2050.  It seeks to define what kind of city Melbourne will be and  identifies the  infrastructure, services and major projects required to underpin the city’s growth.    It  is a blueprint for Melbourne’s future prosperity, liveability and sustainability. 

Plan Melbourne is State policy and specifically referred to in Clause 9 of the SPPF. 

Page 38: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 32 of 162 

 

It recognises that Melbourne  is a  large metropolis, with a population of 4.3 million people, and  is  the  fastest growing  city  in Australia.    It  identifies  that population growth has been profound  with  600,000  new  residents  added  over  the  last  decade  and  that  growth  is exceeding expectations.    It  recognises Melbourne will be a very different city  in 2050 and given  the  rapid  growth  that  has  occurred  over  the  past  decade,  the  city  could  grow  by another 3‐4 million people to be a city of around 7.7 million people by 2051. 

Plan Melbourne seeks  to accommodate  this growth  largely within  the existing urban area; and particularly in locations with good access to services and transport. 

In  planning  for  this  increased  population,  it  recognises  the  city’s  liveability  and competitiveness over the coming decades could be undermined if a number of issues are not addressed.    The  first  issue  identified  is  ‘Congestion’  which  recognises  that  ‘Melbourne’s transport  infrastructure  and  services  are  under  increasing  pressure,  with  congestion increasing on road and public transport systems during peak periods.’ 

Whilst Plan Melbourne seeks to plan for this growth, it recognises that how people live and work  is affected by  changes  in  science,  technology,  communications and  culture, but  that these changes are both difficult to predict and can happen quickly.  It emphasises that based on changes that have occurred over the last 40 years, planning for Melbourne’s future needs to be flexible, ongoing and adaptable. 

It also emphasises the need to make better use of existing assets given the city’s rail, road and associated trunk infrastructure requires billions of dollars of investment to upgrade and maintain each year.    It states  that return on  investment needs  to be maximised  to deliver value to taxpayers and ensure we can provide new infrastructure to meet the requirements of a growing population, stating successful cities respond  to growth constraints by making better use of what they already have. 

In  establishing  a  vision  for Melbourne,  Plan Melbourne  establishes  seven  outcomes  and objectives.  Three of these are directly relevant to the future of the PAO and issues raised in submissions, these include: 

A more connected Melbourne 

Liveable communities and neighbourhoods 

Environment and Water. 

(i) A more connected Melbourne 

A more connected Melbourne  seeks  to provide an  integrated  transport  system connecting people to jobs and services, and goods to market. 

It  recognises  a  key  challenge  for Melbourne  is  the  need  to  ensure  sufficient  commuter capacity on public  transport  and  roads  systems,  and  to ensure  that Victoria maintains  its competitive advantage in freight and logistics. 

This  objective  recognises  that  as  Melbourne  grows,  the  transport  system  will  need  to accommodate an additional 10.7 million daily person  trips by 2050 on  top of  the existing 14.2 million  trips  per  day.    To  accommodate  this,  it  will  be  critical  to  add  links  to  the network, gain greater efficiency out of existing  infrastructure and  increase our  reliance on public transport. 

Page 39: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 33 of 162 

 

Whilst a large focus of this objective is on moving towards a public transport and metro‐style rail system, it recognises the importance and contribution the extensive road system makes in  carrying  trams,  buses,  commuter  cycling,  freight  and  pedestrians,  in  addition  to  the private motor vehicle.    It  recognises  the various networks work  together as an  integrated system with changes and improvements in one part of the system having flow‐on effects to other parts; and that there will be challenges in managing this associated with Melbourne’s growth. 

It  also  recognises  we  will  need  to  use  our  transport  infrastructure  and  services  more efficiently, provide balanced investments across the system, ensure new initiatives represent value for money and deliver maintenance that preserves the long‐term performance of our transport assets. 

The most relevant key directions include: 

Direction 3.1 ‐ Transform the transport system to support a more productive central city –  recognises  that with  the  rapid population growth  in  inner Melbourne, public transport  will  continue  to  be  an  important  means  of  getting  people  around Melbourne, with  trams and buses  sharing  road space with private vehicles.    It also recognises that at the same time, the availability of road space is often connected to the use of clear ways on arterial roads.    It  identifies three key challenges, the most relevant to the future of the Punt Road PAO being the need to improve travel across and within the expanded central city and inner Melbourne. 

Relevant initiatives under this direction include: 

Initiative 3.1.3 – Improve tram travel times, capacity and reliability and extend the tram network  into key urban renewal precincts – recognises the  important contribution  trams play  in  the economy of central Melbourne and  the need  to enhance  this  network  through  improved  travel  times.    It  states  this  will  be achieved by transforming the tram system  into a  light rail system with right‐of‐way. 

Initiative 3.1.4 – Support growing areas of the central city by strengthening bus services to and around central Melbourne – recognises that bus patronage has increased dramatically in response to improved services and that this is expected to continue.   It recognises that as the city develops and demand grows, options to  progressively  upgrade  the  inner‐city  bus  network will  be  examined, with  a focus on increased frequency, reliability, improved travel times and connectivity. 

Direction  3.4  –  Improve  local  travel  options  to  increase  social  and  economic participation  –  recognises  the  importance  of  walking  and  cycling  as  forms  of transport. 

Relevant initiatives under this direction include: 

Initiative 3.4.2 – Create a network of high‐quality cycling links – recognises not only  the  health  benefits  of  cycling,  but  also  that  it  is  a  sustainable  form  of transport.  It recognises there are opportunities to provide dedicated cycle paths as part of new or upgraded road infrastructure, and through the identification of bicycle priority routes. 

Page 40: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 34 of 162 

 

Direction 3.5 –  Improve  the efficiency of  freight networks while protecting urban amenity  –  recognises  the  important  role  freight  plays  to  the  economy  and  that Melbourne  has  a  number  of  competitive  advantages  in  freight,  one  being  good transport links.  It identifies that Plan Melbourne supports three key freight priorities, these being: 

Ensuring  the  ability of businesses  to  access  and  service markets  interstate  and overseas through efficient freight gateways is vital to the economy of the city and state. 

Implementing measures  that enhance  the efficiency of movement of  goods on Melbourne’s  existing  road  and  rail  networks  will  remain  important  to Melbourne’s economic development; and 

Providing  new  infrastructure  capacity  where  bottlenecks  develop,  or  where efficiency measures have been exhausted, will be critical  in  future years as  the size of the freight task grows. 

A relevant initiative under this direction is: 

Initiative 3.5.1 – Improve the efficiency of road freight connections – states the Government  has  a  long‐term  vision  for  the  development  of  an  efficient  and effective road freight network for Melbourne, which not only includes new road infrastructure, but also upgrades to arterial roads. 

Punt Road is identified as being a ‘Principal Freight Network – road.’ 

(ii) Liveable communities and neighbourhoods 

Liveable  communities and neighbourhoods  seeks  to  create healthy  active neighbourhoods and maintain Melbourne’s  identity as one of the world’s most  liveable cities.    It recognises Melbourne  is  known  for  its  well‐preserved  heritage  buildings  and  well‐designed  urban spaces which are considered  fundamental  to Melbourne’s  liveability and sense of  identity; and that more can be done to strengthen protection of this heritage.    It recognises that  it will be  inevitable that during times of growth there will be tension between preserving the best  of  the  past  and  building  for  the  future,  but  that  growth  needs  to  be managed  so Melbourne’s distinctive characteristics and heritage are maintained and liveability enhanced. 

The green  leafy character of Melbourne streets  is also seen as a key feature.   An  identified ‘Solution’  is  to  prepare  a  Distinctive Melbourne  policy  that  specifies  what Melbourne’s distinctive  aspects  are  and  how  they  should  influence  new  development,  and  to  prepare with  VicRoads  and  local  governments,  a  long‐term metropolitan  boulevard  strategy  and implementation  plan  that  identifies  new  boulevard  corridors, which  are  tree  lined major roads. 

The most relevant key directions are: 

Direction 4.6 – Create more great public places throughout Melbourne – recognises the goal to raise the standard of urban design of public places throughout the entire metropolitan  area.    It  recognises  that  streets  (amongst  other  places)  have  the potential to become distinctive and appealing places that can add to the city’s overall character and sense of place and that planning should seek to achieve a consistently high standard of design quality for public spaces. 

Page 41: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 35 of 162 

 

A key initiative under this direction is: 

Initiative  4.6.2  –  Develop  Melbourne’s  network  of  boulevards  –  which recognises  that  Melbourne’s  grand  boulevards  are  a  proud  and  distinctive feature of the city’s urban fabric and will be extended  to transform a network of selected  existing  road  corridors  into  boulevards  across Melbourne,  providing greater  tree  coverage  for  shade  and  enhancing  the  attractiveness  of  major through‐roads. 

Direction  4.7  –  Respect  our  heritage  as  we  build  for  the  future  –  recognises managing the tension between development and conservation  is an  important task.  In doing  so,  it  seeks  to  value heritage when managing growth and  change; and  to respect and protect the city’s Aboriginal heritage. 

(iii) Environment and Water 

Environment  and  Water  seeks  to  protect  natural  assets  to  create  a  sustainable  city, recognising it is defined by the strength, health and beauty of the natural environment and the resilience of the built environment.  It addresses the need to protect and restore natural habitats  in urban areas;  the need  to  improve noise and air quality  to  improve human and environmental  health;  and  the  need  to  integrate  whole‐of  water‐cycle  management  to deliver  sustainable  and  resilient  urban  development.    The  Yarra  River  is  identified  as  a ‘Waterway corridor’. 

The most relevant key directions are: 

Direction 5.2 – Protect and restore natural habitats in urban and non‐urban areas – recognises  that  Melbourne  enjoys  a  rich  natural  amenity  in  its  landscapes  and waterways. 

A key initiative under this direction is: 

Initiative  5.2.2  –  Protect  the  values  of  our  waterways  –  recognises  that increasing urbanisation poses a significant threat to the environmental condition of waterways, which is primarily affected the velocity and quality of stormwater runoff. 

Direction 5.4 – Improve noise and air quality – recognises the need to minimise the air pollution impacts of urban living, including motor vehicle emissions. 

A key initiative under this direction is: 

Initiative 5.4.1 –  Integrate noise and air quality guidelines  into  land use and transport  planning  provisions  –  recognises  that  adopting measures  to  control excessive  noise  through  planning,  building  and  urban  design  will  help  to safeguard community health and amenity. 

5.6 State Strategic work currently underway 

Plan  Melbourne  is  currently  being  ‘refreshed’  and  what  is  being  identified  and  being undertaken as part of this process is relevant to the consideration of the future of the PAO.  This work and its associated implications are discussed below. 

Page 42: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 36 of 162 

 

(i) Plan Melbourne Refresh/Plan Melbourne 2016 

Plan Melbourne  Refresh  is  not  intended  to  be  a wholesale  review  of  all  aspects  of  Plan Melbourne, but rather to ensure its directions are still relevant.  The Plan Melbourne Refresh project will result in an updated strategy Plan Melbourne 2016. 

The Plan Melbourne Refresh Discussion Paper reinforces that Melbourne  is facing some big challenges associated with meeting the needs of an increasing population and reiterates the need to think and act thoughtfully about how to grow and develop the city. 

It reiterates that a key challenge for Melbourne will be the increasing pressure on the city’s transport  network  to  accommodate  7  million  extra  road,  public  transport,  cycling  and pedestrian trips per day on Melbourne’s transport network by 2040.  To accommodate this, it recognises Melbourne needs to double the capacity of its transport system and improve its connectivity, efficiency and supporting investment in transport infrastructure.  It emphasises that adaptive transport planning is vital to respond to Melbourne’s growth patterns as they emerge and change over time. 

Plan Melbourne Refresh recognises that building new transport  infrastructure will be a key part of responding to increased demand, particularly in the fastest growing parts of the city.  To cope,  the existing network will need  to operate more efficiently ensuring  the  transport network supports the key land use directions of Plan Melbourne 2016. 

Plan Melbourne  Refresh  identifies  the  need  to  transform  the  road  and  rail  network  and identifies transit corridors as key transport and land use concepts, reinforcing a commitment to expand the bus network with better facilities and access, along with greater road priority at critical parts of the network.  In doing so, it proposes to include identification of the PPTN in Plan Melbourne 2016. 

Plan Melbourne Refresh recognises that Melbourne’s growth patterns and economic needs will  change  over  time  and  that  successive  governments  will  need  to  respond  to  the challenges  and  opportunities  this  presents  for  the  transport  network.    It  states  Plan Melbourne  2016  will  inform  medium  and  long‐term  transport  options  and  support protection  of  transport  corridors,  which  will  be  guided  by  Victoria’s  transport  planning obligations under  the TIA and  informed by  the advice of  Infrastructure Victoria, which has been established  to advise on  infrastructure  investment and policy directions  that will be reflected in Plan Melbourne 2016. 

The Discussion  Paper  also makes  reference  to  the  importance  of  developing  an  enduring metropolitan  strategy  to  provide  certainty  about  long‐term  strategic  directions  for  sound investment decisions by government and the private sector, highlighting recommendations made by the Plan Melbourne 2015 Ministerial Advisory Committee (MAC) which stated: 

Over a 40 year plan, it is imperative to develop long‐term, visionary plans and (as  necessary)  reserve  transport  corridors,  areas  for  urban  growth,  green wedges,  employment  land,  or  biodiversity  areas,  as  the  Plan  dictates.    This approach was followed for Melbourne in the MMBW 1954 Plan and its 1970s plans. 

What will be required by 2051 needs to be  identified now and set out  in PM Refresh.   The nomination of, say, a  road or  rail project on  the plan does not carry with  it an obligation to build  it now or  in the near future.   However,  its 

Page 43: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 37 of 162 

 

inclusion  in  the  plan  does  set  out  an  intention  and  a  need  to  protect  that option.    In  the  case of  land  components,  this may  involve  land purchase, as and when the opportunity or requirement arises.  While events and technology might  make  changes  necessary  or  beneficial,  the  long‐term  visionary  plan needs  to  be  freed  from  the  budgetary  priorities  and  constraints  of  the government of the day. 

The short term may extend over a ten year period, and involve various levels of project planning and delivery.    It  is really only  in the short term where major capital expenditure needs to be committed.     MAC (2015) report, p.1 

Plan Melbourne Refresh has accepted the MAC’s comments and recognises there is merit in revising Plan Melbourne 2014 to separate the long term plan from the implementation plan to create a more enduring strategy. 

The proposed Punt Road widening has not been  identified as a specific road project  in the Discussion document. 

(ii) Infrastructure Victoria’s 30‐year infrastructure strategy 

As  outlined  in  Plan  Melbourne  Refresh,  an  integral  part  of  meeting  the  transport infrastructural  requirements  to be  included  in Plan Melbourne 2016 will be based on  the advice of Infrastructure Victoria. 

Infrastructure  Victoria  is  currently  in  the  process  of  preparing  a  30  year  infrastructure strategy that will inform Plan Melbourne Refresh, amongst other things. 

Preparation of this strategy has involved three stages, which include: 

Putting  things  into perspective –which provides an overview of Victoria 30 years ago, today and what things might  look  like  in 30 years.   It acknowledges the rapid growth  in both public transport and private vehicle movements since 1986 and recognises greater network capacity,  improved system connectivity and population growth to 9.4 million24 will  drive  even  higher  numbers  of  public  transport  passengers.    It  also  identifies  that innovations such as driverless cars will change how roads are used. 

From the ground up –outlines some of the issues, ideas and opportunities Infrastructure Victoria  will  be  considering  as  it  develops  the  30  year  infrastructure  strategy.    It specifically  identifies  that  in  30  years  time  Victoria will  be  a  very  different  place.    It emphasises that whilst we know some things, there are things we cannot even  imagine that will shape of our society, economy and environment;  just as our society, economy and  environment  will  shape  our  infrastructure  needs.    It  recognises  that  getting infrastructure  right  is  not  easy  and  that  big  infrastructure  projects  require  long  lead times,  cost a  lot of money  and  that using existing  infrastructure better  requires us  to think  in different ways;  accepting  that  getting people  to  agree  is perhaps  the hardest thing of all. 

It recognises that Victoria needs a well‐considered  infrastructure strategy for the short, medium and  long term that factors  in social, economic and environmental  impacts and builds  community  consensus.    It  also  recognises  this will  assist  governments  to make 

                                                       24   From Laying the Foundation 

Page 44: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 38 of 162 

 

informed  decisions  about  the  best ways  to  address  challenges  and make  the most  of opportunities.    It  states  it  will  help  take  the  politics  out  of  infrastructure  planning, providing more certainty for the community and business about our future infrastructure priorities. 

This paper recognises that we are planning for an uncertain future.    It emphasises that whilst we  can be  confident we  know  there will be more people, we don’t  know how many, where they will live and what infrastructure they will require.  It emphasises that population  projections  have  been  consistently  revised  upwards  to  reflect  higher  birth rates and immigration. 

The paper also recognises that  in addition to  increasing population growth, advances  in technology have and will continue to change the way our society and economy function.  Driverless cars were  specifically  identified as one  technological advancement  that may disrupt the way we live and do business.  It emphasises the need to be adaptable to seize technological change and use  it  to our best advantage; and highlights  that uncertainty should not be an excuse for inaction.  On the contrary, it states this is a reason to clearly articulate what we want our future to be, to make decisions based on available evidence and be adaptable in the face of change. 

The paper  identifies  that  this  is  the work being undertaken by  Infrastructure Victoria, looking at both  short and  longer  term  infrastructure  initiatives,  recognising  the  longer term options may be more open and flexible. 

Laying the foundations –sets out what Victoria’s 30 year infrastructure strategy is trying to achieve and identifies what is required to achieve our goals.  It recognises the need to learn from the past, and  in particular states that Victoria’s  infrastructure  landscape  is a result of historical decisions and planning made  throughout  the State’s  relatively  rapid development.  It examines the evolution of planning/infrastructure policy from the 1929 Plan of General Development which identified the need to reduce traffic congestion and recommended  an  underground  rail  network,  through  to  the  1954  Melbourne Metropolitan Planning Scheme Report which  reserved  transport corridors, primarily  for arterial  roads  and  freeways,  to  the  1971  Planning  Policies  for  the  Melbourne Metropolitan Region.    It recognises that although aspects of these plans have not been fully delivered, they have laid the foundation for Melbourne’s subsequent plans. 

Laying  the  Foundations  recognises  that  land  use  planning  and  infrastructure  planning should be closely aligned as land use planning informs infrastructure requirements, while infrastructure enables the achievement of land use objectives.  It recognises the need for both  Plan Melbourne  Refresh  and  this  30  year  infrastructure  strategy  to  inform  each other. 

In  developing  this  strategy,  Infrastructure  Victoria  has  developed  a  series  of  guiding principles  with  one  of  these  relating  to  evidence  required  for  decision‐making.    It recognises that evidence may not exist or be fit for purpose to inform the strategy; and recognises that even the best available evidence will not mitigate uncertainty entirely.  In this  context,  Infrastructure  Victoria  states  it will  seek  to  preserve  options  to  provide more flexibility in future and identify solutions that meet a range of possible needs. 

Page 45: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 39 of 162 

 

It also  states  that,  in  recognising  the  cost of  infrastructure,  it will  seek  to manage  the demands placed on infrastructure and use the assets we already have more efficiently as these can be cheaper and better options.  It states that wherever possible, Infrastructure Victoria will look at non‐build solutions first. 

As  a  case  study,  it  considers  the  potential  impact  of  emerging  vehicle  technology  on infrastructure provision and  recognises  that whilst  the  implications of  this may not be immediately  clear,  they  could  fundamentally  affect  the  way  people  use  Victoria’s transport networks.    It specifically  identifies driverless vehicles as  technology  that may have significant  implications and emphasises the need for planning for the future to be cognisant of what this might mean, how it may contribute to better outcomes and what challenges it may present.  It emphasises that whilst there are still many unknowns, this is not a cause for inaction. 

Some of the questions it identifies emerging transport technologies may present are: 

When?  Gradual adoption or big bang? 

More efficient use of road network?  Road design implications? 

More/lengthier trips by vehicles?  Knock‐on implications for congestion? 

Competition with public transport and other non‐car modes? 

Role in delivery of goods? 

Infrastructure Victoria  released  an  options  paper  titled  ‘All  things  considered’  on  19 May 2016,  and  the 30  year  infrastructure  strategy  is expected  to be  completed by  the end of 2016.    It  is not clear at this stage whether the strategy will assist  in confirming the role of Punt Road in the road network, but the Committee considers that it is possible that project priorities developed  in  the  strategy may have direct or  indirect  impacts on  the Punt Road Hoddle Street corridor. 

5.7 Local Planning Policy Framework 

5.7.1 Stonnington Local Planning Policy Framework  

Stonnington Council submitted the following local policies are relevant to the consideration of the future of the Punt Road PAO. 

Clause  21.02‐3  – Overview  – Key  influences and  challenges  –  identifies  the ongoing  and increasing pressures to accommodate additional development attracted by the City’s  inner metropolitan location and the availability of services and infrastructure.  It also identifies the need  to  uphold  and  restore  the  City’s  key  values  which  include  heritage  buildings,  key landmarks and  residential environs, whilst accepting  change.   How  to optimise  the use of and  access  to  the  public  transport  system,  as well  as  encouraging  sustainable  transport options and managing  traffic  flows and parking on  the City’s  road were, also  identified as challenges. 

Clause  21.03‐  2  –  Vision  –  Strategic  Vision  –  seeks  to  direct  higher  density  housing  to locations with  the  highest  accessibility  to  public  transport  and  services,  including  beside main  roads with Smart buses.    It also  seeks  to ensure key  landmark  features,  such as  the Yarra River frontage, are protected from intrusive development and that all heritage places of  at  least  local  significance  are protected  from  intrusive development.    In  terms of  road infrastructure,  it  seeks  to  significantly  reduce  through  traffic  from within  the  City  and  to 

Page 46: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 40 of 162 

 

reroute  it around the City, resulting  in reductions  in congestion, air pollution and noise.    It also places emphasis on the importance of sustainable personal transport modes. 

The  Strategic  Framework  Plan  identifies  Punt  Road  as  a  ‘Preferred  traffic  route’  and Tram/Bus Priority Route within  the  ‘VicRoads  (Smart Roads) Road Use Hierarchy’.    It  also identifies  the Punt Road Hill  to  the north  (Toorak Road  to  the Yarra River) and Punt Road south  (High  Street  –  Dandenong  Road)  as  areas  which  have  ‘Special  Built  Form considerations’, and the Yarra River as ‘Areas of Natural/Environmental Considerations.’ 

Clause  21.05‐2  –  Housing  –  Location  of  residential  development  ‐  seeks  to  direct  the majority of new housing development to  locations with the highest  level of accessibility to both  an  Activity  Centre  and  the  Principal  Public  Transport  Network,  and  away  from  the residential hinterland.   Given the  identification of Punt Road as a main road and a priority bus  route,  it  is  included within  a  ‘Substantial  change  area’ provided  access  arrangements onto main roads minimises conflicts of movement with vehicle  traffic and public  transport and  does  not  introduce  delays.    It  also  qualifies  that  land  within  a  residential  heritage precinct in a Heritage Overlay, becomes a ‘Minimal Change area’. 

Clause  21.06‐1  –  Built  Environment  and  Heritage  –  Overall  urban  structure  ‐  seeks  to protect and reinforce the key elements of the City’s overall urban structure and character, including  the  Yarra  River.    It  also  seeks  to  reinforce  the  hierarchy  of main  streets  and boulevards with high quality street tree plantings.  It directs higher density development to locations beside the Public Transport Network, as well as Activity Centres. 

Clause 21.06‐1 – Built Environment and Heritage – Significant trees and landscapes – seeks to protect significant trees and the landscape/environmental values of the Yarra River edge and escarpment.   A key  strategy  is  to ensure development and vegetation  removal  in  the sensitive  Yarra  River  environs  area  has  minimal  impact  on  the  defined  landscape  and environmental values. 

Clause 21.07‐2 – Open Space and Environment – Biodiversity ‐ seeks to protect and enhance biodiversity and public amenity through enhancing the municipality’s natural values. 

Clause 21.07‐3 ‐ Significant trees and landscapes – seeks to protect significant trees and the landscape and environmental values of  the Yarra River edge and escarpment.   Two of  the key strategies are to ensure development and vegetation removal in the sensitive Yarra River environs area have minimal impact on the defined landscape and environmental values; and to  protect  significant  trees  on  private  property  to  ensure  overall  quality  and  amenity  of public and borrowed space. 

Clause  21.08  –  Infrastructure  –  Integrated  infrastructure  planning  –  seeks  to  integrate transport  and  land  use  planning  and  development  to maximise  accessibility,  safety  and sustainability of the transport network and the built environment. 

Clause  21.08‐2  ‐  Infrastructure  –  Sustainable  transport  –  recognises  the  importance  of sustainable transport options such as walking, cycling and public transport and the need to promote these forms of transport, both as part of development, as well as throughout the City. 

Clause 21.08‐3 –  Infrastructure – Roads and Parking –  identifies  the need  to manage  the high  traffic  volumes,  fast  moving  vehicles  and  traffic  congestion  which  substantially undermine the quality of life in some parts of Stonnington.  In managing the road system, it 

Page 47: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 41 of 162 

 

seeks  to  plan  and manage  the  transport  network  by  supporting  the  existing  hierarchy  of roads  and  promoting  safe  and  efficient  movement,  and  seeks  to  introduce  traffic management measures to significantly reduce traffic through the municipality. 

Clause  22.04  –  Heritage  –  seeks  to  recognise,  conserve  and  enhance  places  in  the  City identified  as  having  architectural,  cultural  or  historic  significance.    It  outlines  the classification  of  buildings  and  the  associated  level  of  significance  allocated  to  each, with ‘Significant’ buildings  being  those  graded  as A1, A2  and B, with C  graded  buildings  being ‘Contributory’. 

Clause 22.19 – Prahran, South Yarra and Windsor Activity Centre Policy –  includes  land at the  intersection of Punt and Toorak Roads as being within the South Yarra Precinct with a Precinct Vision Statement that is: 

A  transformed employment,  living and  tourism hub  founded on high quality, integrated  public  transport  and  pedestrian  links,  convenient  neighbourhood and  distinctive  shopping  and  attractive  networks  of  streets  and  spaces.  Acknowledgement  that  the  redevelopment  of  the  Forrest  Hill  precinct  and nearby  Cremorne  and  Church  Street  Precincts will  change  the  dynamics  of South Yarra. 

This is an area where growth will be focussed, with a focus on incorporating and encouraging sustainable transport options. 

5.7.2 Melbourne Local Planning Policy Framework 

The following Melbourne City Council local policies are also relevant: 

Clause 21.06‐1 – Built Environment and Heritage – seeks to maintain the designated Yarra Corridor as a continuous, high pedestrian amenity focus for the City.  It also seeks to increase the vitality, amenity, comfort, safety and distinctive City experience of the public realm. 

Clause  21.10  –  Infrastructure  –  Open  space  –  seeks  to maintain,  enhance  and  increase Melbourne’s public open space network and promote greening of the City.  Key strategies to achieve this include ensuring there is no net loss of the area of public open space, securing new  public  open  space where  opportunities  arise  and  ensuring  that  development  in  and surrounding  the  City’s  parks  and  gardens  does  not  adversely  impact  on  the  recreational, cultural heritage, aesthetic values or amenity of the open space. 

Clause 21.16‐1 – Other local areas – St Kilda Road and South Yarra – seeks to preserve and enhance the landscape qualities and recreational role of Fawkner Park. 

Clause  21.09‐5  –  Transport  –  Private  Motor  transport  –  seeks  to  reduce  the  negative economic, social and environmental impacts of traffic and parking, particularly on residential areas and parklands. 

5.8 Other relevant policies and strategies 

A number of other strategies were referred to by various parties as  listed  in Section 4.5 of this report.   Reference  is made to these documents as appropriate  in the discussion of key issues in later chapters. 

Page 48: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 42 of 162 

 

5.9 Planning scheme provisions 

5.9.1 Zones 

Land within the study area is included within a number of zones with schedules that provide particular guidance, these include: 

Residential Growth Zone 1 – Key Boulevards 

General Residential Zone 3 – Residential Boulevards and Corridors 

General Residential Zone 9 – Garden River & Garden Suburban Precincts 

General Residential Zone 12 ‐ Inner Urban Precincts 

Neighbourhood Residential Zone 3 – Inner Urban Precincts 

Commercial Zone 1 

Abuts Road Zone Category 1. 

5.9.2 Overlays 

(i) Public Acquisition Overlay 

The purpose of the Public Acquisition Overlay is to: 

To implement the State Planning Policy Framework and the Local Planning Policy  Framework,  including  the Municipal  Strategic  Statement  and  local planning policies. 

To  identify  land which  is  proposed  to  be  acquired  by  a Minister,  public authority or municipal council. 

To reserve land for a public purpose and to ensure that changes to the use or development of the land do not prejudice the purpose for which the land is to be acquired. 

To  designate  a  Minister,  public  authority  or  municipal  council  as  an acquiring authority for land reserved for a public purpose. 

The permit requirements under the PAO are extensive, with almost all buildings, works and subdivision  requiring  a  planning  permit.    Routine maintenance  and  repairs,  however,  are exempt from these permit requirements under General Provision ‐ Section 62.02‐2 Buildings and works not requiring a permit unless specifically required by the planning scheme. 

More substantial buildings and works are not prohibited and  there  is scope  to apply  for a planning permit.   As  ‘Determining Referral Authority’ VicRoads, however, has authority  to direct whether a permit should be issued or not, or require permit conditions. 

Under  the  Decision  Guidelines  of  the  PAO,  a  permit  granted  under  this  clause may  be conditional on: 

The extent of alterations and extension to an existing building and works, and the materials that may be used. 

The location, dimensions, design and material or new building or works. 

The demolition, removal, or alteration of any buildings or works. 

The demolition or removal of buildings or works constructed or carried out in accordance with a permit under this clause. 

No  compensation  being  payable  for  the  demolition  or  removal  of  any building or works constructed under the permit. 

Page 49: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 43 of 162 

 

VicRoads submitted  that ”a PAO  restricts how  the  land may be used or developed, so  that any proposed use or development does not prejudice the purpose for which the land is to be acquired.” 

VicRoads further submitted that25: 

The effect of the PAO is to: 

a) preserve  the opportunity  for  the  land  to be used  for  the  identified public purpose; 

b) reduce the cost of the ultimate land acquisition; and 

c) allow others (owners,  local councils, adjoining  land owners) to plan for the identified conversion of use of the land to that public purpose. 

The PAO along Punt Road preserves  the opportunity  to provide  future public benefits  in  the  form  of  an  improved  transport  corridor,  whether  it  be  the provision of additional traffic  lanes, bus  lanes, cycle  lanes, shared paths, new forms of public transport or otherwise. 

It is not often that section 4(1)(g) of the Planning and Environment Act 1987 is quoted.   The  final objective of planning  in Victoria  is “to balance the present and future interests of all Victorians.”  The PAO is one of the planning scheme tools  that  is  available  to  enable  the  interests  of  future  Victorians  to  be protected. 

This Advisory Committee process squarely raises the issue of how we plan for the  needs  of  future  generations  of  Victorians,  and  how  they  should  be balanced against the interests of current Victorians. 

VicRoads has the power to compulsorily acquire properties within the overlay if required as it  is  the  nominated  acquisition  authority.    The  provisions  of  the  Land  Acquisition  and Compensation Act 1986 and the P&EA provide landowners with access to compensation due to the overlay being in place.  This includes compensation for loss on sale or the refusal of a planning permit by Council if directed by VicRoads as a referral authority. 

It is clear to the Committee that a PAO is intended, in broad terms, to enable a future project to be implemented.  The Committee believes, however, that it is implicit that the imposition of an overlay should be based on the demonstrated needs of an acquiring authority and set aside no more land than that which is reasonably required for that purpose.  This is generally straight  forward  where  a  planning  scheme  amendment  is  being  considered  for  a  new overlay.  In these cases the overlay is defined as the land need for the project, and no more. 

The  difficulty  in  this  case  is  does  the  same  standard  apply?    In  other words,  is VicRoads required to demonstrate that there is a defined project that requires the entire PAO; or is it sufficient to say that there might be a project  in the future so the PAO should be retained “just in case”? 

                                                       25   Document 6 

Page 50: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 44 of 162 

 

Despite the fact that an overlay is already in place along Punt Road, the Committee believes that  it  is necessary as part of this review of the PAO for VicRoads and PTV to demonstrate that the entire extent of the PAO is still required for a legitimate long term option. 

(ii) Heritage Overlays 

The area is affected by a number of Heritage Overlays.  These are discussed in Chapter 9. 

(iii) Other overlays affecting land within the PAO 

Land within the PAO is also affected to varying degrees by the following overlays: 

Design and Development Overlay 1 ‐ Royal Botanic Gardens, City of Melbourne 

Design and Development Overlay 2 ‐ Shrine Vista 

Design and Development Overlay 3 ‐ Yarra River Skyline Area 

Design and Development Overlay 7 ‐ Prahran/South Yarra and Windsor Activity Centre 

Special Building Overlay. 

5.9.3 Particular provisions 

The following particular provisions of the VPP are relevant: 

Clause 52.29 ‐ Land Adjacent to a Road Zone, Category 1, or a Public Acquisition Overlay for a Category 1 Road 

Clause 52.36 ‐  Integrated Public Transport Planning 

Clause  62.02‐2  –  Uses,  Buildings, Works,  Subdivision  and  demolition  not  requiring  a permit. 

Ministerial Directions and Practice Notes 

There are no specific Ministerial Directions or Practice Notes that relate to the consideration of the future of the Punt Road PAO, above the requirements of the TIA and P&EA. 

5.10 Conclusions 

In  coming  to  its  conclusions  in  relation  to  the  PAO,  the  Committee  has  been  guided principally  by  the  legislative  requirements  of  the  TIA  and  the  objectives  of  planning  as defined  in  the P&EA, as  these are  the most  relevant  tests  in considering  the  future of  the Punt Road PAO.    It has  also had  regard  to existing  State policy  and work  currently being undertaken to review this policy, as well as local policy. 

In applying this legislation and policies the Committee has faced a number of key challenges.  The  first  challenge  has  been  balancing  short  term  and  long  term  planning;  and what  the Committee knows, with what the Committee can only anticipate.  

The Committee must balance  shorter  term objectives with  a  longer  term  view  consistent with the approach adopted  in Plan Melbourne, and  in particular consider whether the PAO has a longer term role in meeting the transport needs of Melbourne. 

The other major challenge  for  the Committee  is balancing  the needs of  individual and  the broader  community.    Whilst  the  Committee  must  consider  the  needs  of  the  individual landowners,  it must  also  consider  the  broader  needs  of  the  current  population with  the needs of the future population. 

Page 51: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 45 of 162 

 

As discussed above, the Committee concludes that is necessary as part of this review of the PAO for VicRoads and PTV to demonstrate that the entire extent of the PAO is still required for a long term option.  In order for the Committee to support the full retention of the PAO, it  will  need  to  be  convinced  that  concepts  similar  to  Options  6  or  7  will  ultimately  be required to meet future traffic needs or that  it  is necessary to keep those options open.   If the  Committee  is  convinced  that  a  lesser  option  (in  terms  of  road  cross  section  and acquisition requirement) will adequately serve the future needs, then it follows that the PAO could, and should be reduced to match that required. 

The Committee has sought to balance competing interests of current and future generations in favour of net community benefit. 

Page 52: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 46 of 162 

 

6 The strategic importance of the Punt Road PAO 

6.1 The issue 

Is the retention of the PAO in full or part needed to enable Punt Road to fulfil its long term strategic transport role within the metropolitan context? 

6.2 Evidence and submissions 

There were few individual submitters who addressed the Committee on the appropriateness of  the  retaining, modifying or  removing  the PAO based on  the  legislative  requirements of either the TIA, the objectives of planning as outlined in the P&EA, or the strategic directions contained within  the  SPPF.   Despite  this,  there were many  submitters who made general submissions about the need to examine Punt Road  in the context of the broader transport network and policy, rather than in isolation.  Submitters also emphasised a need to focus on both existing and  future public  transport and other modes of  sustainable  transport  rather than  continuing  to  cater  for  private  vehicles,  with  their  perceived  associated  negative environmental,  social  and  economic  impacts.    Several  submitters  did  make  reference, however, to the LPPF and particularly with regard to the need to protect heritage properties. 

Mr Carassco of Drop Punt and other  submitters  submitted  that good planning has  turned away from creating freeways  in  inner city areas and  is  increasingly returning roads back to landscaping  and  dedicated  places  for  more  sustainable  transport  modes.    They  made submissions  that a proposal  to create a “six  lane  freeway”  through  inner Melbourne  is an outdated approach which is contrary to world’s best practice. 

Ms Murphy  of  Tract  Consultants,  on  behalf  of  the  owners  of  5  Northampton  Place,  did address  the objectives of  the TIA,  stating  retention of  the PAO  is not  consistent with  the objective which seeks to create a sustainable and  integrated mode of transport  in Victoria.  She also submitted that it is not consistent with the fairness objective in the P&EA and does not meet Clause 18 of the SPPF which encourages an  integrated and sustainable transport system that provides access to social and economic prosperity, contributes to environmental sustainability, coordinates reliable movements of people and goods, and is safe. 

Ms Sharp, on behalf of the Stonnington Council, acknowledged there are competing policy objectives in play and submitted that the question before the Committee is one of balancing those interests.  She submitted that on the one hand there is VicRoads, wanting to retain the possibility that the PAO may one day be utilised  for road widening; yet on the other hand there  are  directly  affected  property  owners  and  the  Stonnington  City  Council  who experience the negative impacts associated with ongoing uncertainty regarding the future of the PAO and  the  consequential  impacts of  traffic and parking  in  the  local  street network.  Whilst she accepted that on a first glance the balance may tip in favour of retaining the PAO, when one examines it further she submitted the balance rests with the removal of the PAO.  These factors include: 

how long the PAO has been in place 

that the road has not been widened 

that the last property purchased was 35 years ago 

that there is no funding or political commitment towards widening 

that there is no long‐term strategic plan for Punt Road 

Page 53: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 47 of 162 

 

that improvements can be made within the existing reservation without having to widen Punt Road 

that it is causing planning blight 

that widening would result in the loss of heritage buildings and significant trees; and 

that widening would result in an increase in vehicular traffic and loss of amenity and will impact on west‐east connectivity. 

Ms Sharp submitted that the balance rests with the removal of the PAO.  She also submitted that the onus is upon VicRoads and PTV to demonstrate that the PAO is ‘definitely’ required and not that it would be ‘advisable’ to retain it. 

Ms Forsyth submitted that the fundamental  issue for this Committee to consider  is how to plan  for  the  needs  of  future  generations  of  Victorians,  and  balance  these  against  the interests of current Victorians.   She submitted  that  in addition  to  the  requirements of  the TIA, the Committee should base its decision on the objectives of planning, and in particular the objective which seeks “to balance the present and future interests of all Victorians.”  She emphasised that the SPPF states that where there are competing objectives, these should be balanced in favour of net community benefit and sustainable development for the benefit of present and future generations; and that this is the test the Committee should apply. 

Ms Forsyth highlighted the  future of the Punt Road PAO  is not simply a traffic engineering exercise, but rather raises more significant strategic planning questions.  She submitted that the challenge facing planning for managing growth over the coming decades is well known, and given the growth anticipated in this location we need to take a longer term aspirational and  visionary approach  to growth.    She  submitted  that  the Committee needs  to  consider whether it is desirable from a strategic planning perspective to maintain the opportunity for the widening to occur at some time  in the future, emphasising the exact timing bears  little on the ultimate decision.  She submitted that “if the Advisory Committee forms the view that a widened Punt Road may be needed at some future time – whether it will be in 10 years, 30 years or 50 years – then prima facie the PAO ought to remain.” 

In considering  the Future Transport needs of Melbourne, Ms Forsyth highlighted  that Plan Melbourne  sets  a  planning  horizon  at  2051  and  provides  a  vision  which  allows  us  to contemplate  the  sort  of  city  that  we may  see  at  that  time.    She  highlighted  that  Plan Melbourne  warns  that  the  city  we  enjoy  today  has  been  shaped  by  the  foresight  and planning of earlier generations and that the changes  in the way people  live are difficult to predict  and  happen  quickly,  summarising  that  “we  should  plan  for  the  knowns,  and  be flexible enough to adapt to the unknowns.   So what will the role of Punt Road be  in 2030? 2050? 2070? 2100?   Will  it still function as a preferred traffic route and bus priority route?  Or will it take a new form of public transport?  Will cars be automated?  The fact is that there are many unknowns.   What we can do  is … plan  for  the  things  that we  think are  likely  to happen and preserve the opportunity for flexibility if things change. 

Ms  Forsyth  responded  to  submitters’  accusations  that  VicRoads  is  proposing  a  ‘six  lane freeway’  through  inner Melbourne,  emphasising  that  VicRoads  and  PTV  share  common transportation  objectives  of  less  congestion,  better  public  transport,  better  cycling infrastructure and  improved pedestrian amenity.   She submitted  that  the central question for the Committee  is whether  it  is desirable to retain the PAO  in the  long term to assist  in achieving  these  objectives.    She  submitted  the  PAO  should  be  kept  in  place  to  provide 

Page 54: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 48 of 162 

 

options  for  a  future  integrated  transport  response,  including  one with  a  strong  focus  on public  transport;  and whilst  submitters  have  stated  that widening  of  Punt  Road will  just mean more cars, VicRoads and PTV consider retention of the PAO will also facilitate a modal shift by increasing public transport usage on Punt Road, as well as parallel and cross routes. 

Ms Forsyth submitted the PAO preserves the opportunity to provide future public benefits in the  form of an  improved  transport  corridor, whether  it be  for  the provision of additional traffic  lanes,  bus  lanes,  cycle  lanes,  shared  paths,  new  forms  of  public  transport  or otherwise.   She submitted the appropriately conservative approach to take  is to retain the overlay, considering the potential future broad public benefits to be gained when weighed against  the  largely  localised  negative  effects  of  retention  of  the  overlay.    It  was  her submission that retention of the PAO will achieve a net community benefit by preserving the option for future generations and therefore the PAO should be retained. 

Ms Forsyth emphasised that the concepts presented are not the only concepts available, but rather an indication of what could be achieved.  She urged the Committee to not get caught up  in  the  design  detail  of  the  concepts,  emphasising  the  question  to  be  answered  is  a broader strategic question, not one of detail. 

Ms  Forsyth  also  submitted  that  imposition  of  the  PAO  in  1954  has  and will  significantly reduce the costs of land acquisition if and when the land is acquired for the widening in the future.   She submitted that based on the economic evidence of Mr Kinnaird (which will be discussed later in this report), a significant cost would arise from removing the PAO now and reinstating  it  at  some  time  in  the  future  should  acquisition  be  required  again.    For  this reason, she submitted a conservative approach should be taken to the removal of the PAO in light  of  the  very  significant  costs  to  the  taxpayer  that  could  occur  as  a  result  of underestimating the future transportation needs of the Victorian community. 

In response to submissions from Ms Sharp, Ms Forsyth submitted the test is not whether the Committee is satisfied the PAO will ‘definitely’ be required, but rather, whether on balance and having regard to potential local, regional and state benefits and impacts, it is ‘advisable’ to  retain  the  PAO,  and  Stonnington Council  should  adopt  a more  balanced  and  visionary view. 

Ms Forsyth also relied upon expert town planning evidence from Mr Milner.  In his evidence, Mr Milner stated the original application of the PAO was strategically  justified and that  its retention is also strategically justified.  In saying this, however, he stated there is also a need to consider the future of Punt Road  in the broader and  longer term transportation context and land use vision. 

Mr Milner stated that whilst he accepted recent traffic analysis indicates vehicle movements in Punt Road have decreased, the strategic context of policy and the metropolitan setting of Hoddle Street/Punt Road corridor  indicates a quite different range of  influences are at play which  should  inform  the decision.   He gave evidence  that  the decision  regarding  the PAO should  not  be  overly  influenced  by  recent,  short‐term  traffic  demand  studies,  but  rather should reconcile and plan for the appropriate balance of all these relevant considerations. 

Mr Milner  referred  to  the  SPPF  and  Plan Melbourne  as  supporting  the  need  to  plan  for increased transport to cope with significant population growth, particularly in this inner city location where greater residential densities are to be achieved.  He said this is an important 

Page 55: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 49 of 162 

 

location given the expanded central city because of its location near key activity centres and urban  renewal  areas  where  growth  will  be  accommodated;  and  its  location  near entertainment and  recreational precincts which are proposed  for expansion and will have more  intense  transport  implications, particularly during weekends  and  evenings.   He  also highlighted that Punt Road serves and acts as an  important emergency services corridor to the Alfred Hospital, which  is  a  recognised  State  significant  regional  health  and  education centre in Plan Melbourne. 

Mr Milner concluded that confinement of the review to the removal or retention of the PAO is  too  narrowly  cast  to  appropriately  determine  the merits  of  any  long  term  option  and needs  to  be  considered  in  a  broader more  strategic  land  use  and  transport  context.   He stated that a recommendation to remove the PAO would be premature and fall short of the expectations of the decision making principles of the TIA.  He gave evidence that the future of  the  PAO  requires  integrated  decision  making  by  all  levels  of  government,  relevant stakeholders  and  an  appropriate  triple  bottom  line  assessment  of  the  consequences  of removal and retention of the PAO.  He recommended the PAO be retained until a long term strategy for the corridor has been resolved and that a land use and transport strategy with a 2051 horizon should be prepared.  He accepted short term measures could be implemented that would improve transport efficiency. 

Ms Forsyth also relied upon expert traffic and transport evidence  from Mr Humphreys.    In his evidence, Mr Humphreys  stated  there  is  to be a  “staggering” 218 per  cent population growth up to 2046 within 800m of the corridor alone, with population forecasts of 7.7M to 2051  for metro Melbourne and  forecast  job growth  from 2.2M  to 3.9M.   Recognising  the long  term role  that Punt Road may play  in meeting  the  transport needs of  this population growth, he said the PAO should be retained  in  its entirety  in order to maintain concepts to facilitate that future role. 

In considering the legislative, best practice and policy review, Mr Humphrey concluded that “Overall, there is strong strategic justification within both state and local policy identifying at the very least a need to protect assets such as the Punt Road PAO for the future legacy of the transport network.” 

In considering whether retention of the PAO is appropriate he stated: 

Having reviewed the available information afforded in preparing this evidence, I regard the key question of note with Punt Road  is not whether to maintain the  PAO,  rather,  what  would  be  the  traffic  and  transport  implications  for removing it? 

Punt Road is a key link in the network and is the only north to south preferred traffic Route crossing both  the Yarra River between CityLink  to  the west and Grange Road to the east, a distance of almost 9km.  Both VicRoads and Public Transport Victoria have  identified Punt Road as a traffic and public transport priority route and the need for improvements to it are overdue. 

The strategic benefits of retaining the PAO in my view are quite clear in that it is  critical  to  the management and  improvement of  the  traffic and  transport network.    This  view  is  supported  by  local  and  state  policy  documentation including Plan Melbourne and VicRoads SmartRoads Policy. 

Page 56: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 50 of 162 

 

In his evidence, Mr Humphreys concluded: 

Maintaining  the  PAO  allows  for  a  range  of  future  interventions  to accommodate demand growth  in a  strategically  important part of  the network.    It  is  consistent  with  the  principles  and  intention  of  the Transport Integration Act and I support its retention. 

Removing  the  PAO  means  permanently  losing  the  ability  to  deal adequately  with  future  growth,  or  at  the  very  least  burdens  the community  with  significantly  higher  costs  and/or  lower  amenity outcomes through elevated structures or submerged options (ie tunnels).  This approach  can not be  supported  from a policy perspective against the TIA framework and nor do I support it. 

There  is no case presented  for modifying the PAO at this point  in time.  However,  given  the  nature  of  the  PAO  and  potential  options,  any modifications  are  likely  to  be  minor  in  nature  and  only  able  to  be confirmed  after  the  ultimate  treatment  is  agreed.    I  do  not  support modification of the PAO based on the information available to myself.  

On that basis of the information set out within this report, I am confident that  retention  of  the  PAO  provides  the  greatest  opportunity  to implement improvement works for all modes and meet the future needs of  the continually growing population and economy.   This  includes  the opportunity  to  provide  high  levels  of  public  transport,  pedestrian  and cyclists  facilities,  and  improvements  to  the  traffic  network  for  private vehicles and freight. 

6.3 Discussion 

The Committee agrees with  submissions of VicRoads/PTV and  their expert witnesses who say the future of the PAO needs to be considered both in a strategic context, as well as from a traffic engineering perspective.  The first question for this Committee is therefore whether Punt Road has a strategic role to play in meeting the transport needs of Melbourne. 

In considering  the strategic  importance of Punt Road within  the metropolitan context,  the Committee notes that whilst the widening of Punt Road  is not specifically  identified  in the SPPF or as a major project within Plan Melbourne, it does not consider this means it is not a strategically important project.  This policy is necessarily broad and does not, nor should it, identify every potential road widening that may occur, yet it does recognise Punt Road as a ‘Principal Freight Network – road’.  As part of the ‘Priority Public Transport Network’ (PPTN), it  is  also  proposed  that  Punt  Road  will  be  recognised  within  Plan  Melbourne  2016  by association.  VicRoads SmartRoads policy identifies it as a ‘preferred traffic route’ and a ‘bus priority route’ and  local policy  identifies  it as a ‘Preferred traffic route’.  Punt Road has also been  identified  since 1954 as an  important  transport  corridor and a  reservation/PAO was put in place to protect options for the potential future widening of Punt Road. 

It is clear from this policy framework that whilst Punt Road may not be specifically identified in all State policy, there has been a clear and long standing statement of strategic intent that Punt  Road  will  play  an  important  long  term  transport  role  in  meeting  the  needs  of Melbourne. 

Page 57: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 51 of 162 

 

The  importance of the strategic role of Punt Road  is also supported by the expert evidence of Mr Milner and Mr Humphreys. 

Whilst some submitters and expert witnesses submitted that it should not perform that role and  that  traffic  should  be  redirected  to  other  north‐south  routes  within  metropolitan Melbourne to alleviate the pressure on Punt Road, or that alternate transport modes should be maximised to reduce the role of Punt Road, the Committee consider these submissions fail  to  recognise  that Punt Road has  for many  years been  clearly  identified  as  a  strategic transport asset for metropolitan Melbourne.  The Committee is satisfied that Punt Road has an  identified  significant  strategic  role  to  perform  in  meeting  the  transport  needs  of Melbourne; and that this needs to be considered when making decisions about the future of the PAO. 

The Committee is also aware that land within the PAO is predominantly in private ownership and  that owners have  lived  for over 60  years with  the uncertainty  as  to when or  if  their properties may  be  required  for  road widening  purposes.    The  Committee  is  also  acutely aware that this uncertainty  is causing significant distress for some residents, with 20 of the 135 directly affected property owners making submissions expressing these concerns to the Committee. 

The Committee agrees with  the VicRoads/PTV and Stonnington Council submissions  that a fundamental  issue  for  consideration  is  balancing  the  needs  of  the  individual  against  the needs of the broader community.   The Committee considers  it also extends beyond that to require  a  balancing  of  broader  competing  community  aspirations,  in  particular  transport planning and heritage protection.  In doing so, the Committee agrees with Ms Forsyth that, when balancing the conflicting objectives, the SPPF clearly states they should be balanced in favour of net community benefit and sustainable development for the benefit of present and future generations. 

Whilst Ms Murphy made submissions  that  retention of  the PAO  is not consistent with  the TIA, P&EA objectives and  the SPPF,  through cross‐examination  she acknowledged  she had only emphasised  those  aspects  that  supported her  case and had not attempted  to either outline  or  balance  competing  objectives.    She  accepted  that  a more  full  analysis  of  the objectives and policies would require a balancing of these competing objectives. 

Accepting that Punt Road has an  important strategic role to play  in meeting the  long term transport needs of Melbourne, the critical question for the Committee  is whether the PAO needs  to  be  retained  to  achieve  this  role,  and  ultimately what  achieves  the  greatest  net community benefit. 

VicRoads defined Short‐term as 0 to 5 years, Medium‐term as 5 to 15 years and Long‐term as 15+ years.  The Committee has adopted these timeframes for the purposes of this report.  

The traffic analysis  is based on data projections to 2031.   Various concept options for Punt Road  to  deal  with  projected  traffic  volumes  to  2031  are  discussed  in  Chapter  8.    The Committee needs  to  be  confident  that  options  for  Punt Road  are  capable  of maintaining appropriate levels of service beyond 2031.  Planning in Plan Melbourne extends out to 2050 and  the  Committee  believes  that  future  widening  options  should  plan  for  at  least  this timeframe. 

Page 58: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 52 of 162 

 

The Committee  is aware  that Plan Melbourne, Plan Melbourne Refresh and  Infrastructure Victoria have  all  recognised  that Melbourne will undergo  significant  long‐term population growth,  both metropolitan wide  and  specifically  in  this  location,  and  historically  beyond general  expectations.    Along  with  this  growth  will  come  significant  transport  challenges about how to move people and freight throughout the both broader transport network, as well as around the inner suburbs and central city. 

It is clear there is much we already know and must plan for, but the Committee agrees with Ms Forsyth that there is also much we do not know and cannot foresee, particularly with the rate  of  population  growth  and  technological  advancements  that  are  occurring;  which  is acknowledged  in  both  Plan Melbourne,  Plan Melbourne  Refresh  and  the  strategic  work currently being undertaken by Infrastructure Victoria.  One example of this as raised by both VicRoads and submitters alike was the potential  impact of autonomous vehicles and other transport technologies on the future of transport planning; what will this bring, what are the associated  infrastructure  requirements and what will  this mean  for public  transport?   We don’t know  the answers  to  these questions yet, but autonomous vehicles are  increasingly becoming more likely.  Other unknowns are what improvements are likely to the connecting road network and what are the impacts of these on the function of Punt Road? 

The Committee agrees with Ms Forsyth that to be able to respond to the challenges that will face managing the growth of Melbourne, we need to “adopt a longer term aspirational and visionary approach  to growth.”   For  this  reason,  the Committee agrees with  the VicRoads submissions  and  the  evidence  presented  by  both Mr Milner  and Mr  Humphreys  that  to remove the PAO without an understanding of the potential  long term role of Punt Road  in context of broader metropolitan planning would be inappropriate. 

The Committee considers the PAO is an important piece of community infrastructure already in place.   Planning  for new major  transport  infrastructure projects, and particularly within the  inner city areas,  is extremely difficult and expensive to achieve as  it generally affects a significant number of people and properties.   State policy encourages making  the most of existing  infrastructure,  rather  than  introducing  new  infrastructure.    The  existing  PAO  is identified as land that could be used for future transport infrastructure, and the Committee considers it should only be reduced or removed if it is clear that it is not required in the long term  and  future  transport  needs  can  be met  within  a  reduced  footprint.    This  issue  is discussed in Chapter 8. 

The  Committee  is  aware  that  Infrastructure  Victoria  is  currently  preparing  a  30‐year infrastructure strategy which will define the long‐term infrastructural requirements to meet the needs of Melbourne to 2051.   Whilst no submissions were made to the Committee on the work  being  undertaken  by  Infrastructure  Victoria,  the  Committee  considers  that  this work may help to confirm the longer term role of Punt Road. 

The Committee therefore considers there is value in referring the future role of Punt Road to Infrastructure Victoria to consider in the preparation of the 30 year infrastructure strategy. 

The Committee is aware that affected owners are seeking certainty about the future of the PAO and may consider referral of the Punt Road and the PAO to Infrastructure Victoria to be yet  another  delay,  however,  the  Committee  understands  that  this  work  is  due  to  be completed by the end of 2016, and does not consider this to be unreasonable. 

Page 59: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 53 of 162 

 

6.4 Conclusions 

The Committee concludes that: 

Punt Road currently plays an  important strategic role  in the road network reinforced  in State and local policy. 

The existing PAO should be retained to the extent required to guarantee that Punt Road can continue to fulfil its role in the short, medium and long term. 

Punt Road  is  likely to continue to play an  important strategic role  in Melbourne’s road network, although there are some unknowns about whether that role will change in the longer term. 

The  greatest  net  community  benefit will  balance  fulfilling  this  long  term  role  against minimising the impacts on landowners. 

The Committee also concludes that there is benefit in referring the question of the long term role of Punt Road  to  Infrastructure Victoria  for consideration as part of  the preparation of the 30 year infrastructure strategy. 

Page 60: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 54 of 162 

 

7 Economic issues 

7.1 Broader economic impacts for Melbourne 

(i) The Issue 

What  are  the  broader  economic  impacts  for Melbourne  resulting  from  any  decision  to retain, modify or remove the Punt Road PAO? 

(ii) Evidence and Submissions 

The joint VicRoads and Public Transport Victoria ‐ Part A submission states that: 

The  current  PAO  balances  the  present  and  future  needs  of  all  Victorians ensuring that real options are not built out, resulting in potentially significant economic savings for all future Victorians. 

At the heart of the  issue about the potential future widening of Punt Road  is the role Punt Road currently plays and may play in the future in supporting an efficiently functioning city, both for economic and social purposes. 

VicRoads  noted  that  Punt  Road  plays  an  important  role  in  providing  a  north‐south connection  in the road network for freight and commercial vehicles, as they stated  in their Part A submission: 

With a high proportion of road users undertaking business, delivering  freight and  connecting  with  jobs  and  opportunities  across  Melbourne,  it  is economically  important  to optimise  this  vital  city asset  to  support economic growth and jobs for our state. 

VicRoads stated that in relation to expected population growth, and a proportionate growth in travel demand, in the outer north and across established suburbs in the north, south and east  there will  increased demand  for  travel along and across  the Hoddle Street‐Punt Road corridor that will have significant access implications for the economy.  These include access to employment, education, retail, services and leisure in and around the central city as well as  the  ability  to  bypass  the  city.    They  also  cited  the  role  the  corridor  plays  as  part  of journeys  to  cross Melbourne  to  access  key  freight  and  industrial destinations  such  as  the Port of Melbourne and inner west and outer eastern locations. 

The economic importance of the corridor is reinforced when VicRoads stated 

Protecting and developing the Hoddle Street‐Punt Road corridor (arguably, the most important arterial road for Central Melbourne) is of vital significance for the state.   If the problems facing the corridor are not planned for,  it will  limit the  achievement  of  an  expanded  central  city  and  impact  on  goals  in  Plan Melbourne to create a more connected, liveable and thriving Melbourne. 

In response to a request from the Committee to provide information on the role Punt Road plays in accommodating vehicles that service the local economy, such as localised deliveries and  service  trades, Ms  Forsyth  referred  the  Committee  to  the  advice  from  Arup  which stated: 

Page 61: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 55 of 162 

 

… that commercial vehicles comprise approximately 4.7% of average weekday daily  traffic  along  Punt  Road with  a majority  of  these  vehicles  being  small trucks. 

Ms Forsyth advised, however, that: 

VicRoads  has  not  been  able  to  ascertain  the  percentage  of  trips  that  are undertaken  for  business,  as  opposed  to  private,  purposes  along  Punt  Road.  However,  VicRoads  acknowledges  that  the  number  of  commercial  vehicles shown in [information provided by ARUP] … does not accurately represent the break down between business and private trips given that many of the vehicles which use Punt Road  for business purposes are not  classified as  commercial vehicles. 

In response to a request for information relating to the cost of congestion in Melbourne, she referred the Committee to two more general reports. 

The  first  report  is  the 2015 Federal Government’s Bureau of  Infrastructure, Transport and Regional Economics  (BITRE) report Traffic and congestion cost trends  for Australian capital cities  (an update of earlier  reports) which estimated  the costs of  congestion  for  the eight major Australian cities to be $16.5 billion.  It identified that in Melbourne, the 2015 cost of congestion was estimated to be $4.6 billion and on historical trends, this can be expected to grow by more than double to around $10.2 billion by 2030. 

The report suggests that the actual extent of future traffic congestion will depend on a range of  technical  and  social  factors  and  the  adoption  of  potential  options  for  congestion management,  including  pricing  measures  and  emerging  technologies,  will  need  to  be carefully weighed to achieve the most economically efficient responses. 

The  second  report  is  the  2013  Victorian  Auditor  General  (VAGO)  report  into Managing Traffic Congestion which referred to a 2006 estimate of the economic costs of Melbourne's congestion, prepared by the Victorian Competition and Efficiency Commission (VCEC), to be in the range $1.3 billion to $2.6 billion per year; and that this was likely to double by 2020. 

In relation to the costs of traffic congestion, the VAGO report stated these costs are incurred generally by  the community as a whole and are not paid  for by  the  road users who have caused them. 

While  the  report does not examine particular  aspects of  the  road network,  it does make observations  about  inner  urban  areas,  such  as  that  covered  by  the  Punt  Road  environs, stating: 

Between 2001 and 2010, Melbourne's population grew by approximately 17 per cent with the majority of that growth, around 63 per cent, occurring in the outer  metropolitan  zone.    In  the  middle  and  outer  zones,  the  percentage growth  in  vehicle  kilometres  travelled  (VKT)  since  2001  has  followed  the percentage growth of these populations very closely—around 25 per cent. 

However,  the  inner Melbourne  zone has experienced a  significantly different trend, where a 25 per cent  increase  in population since 2001 has  resulted  in only a 4 per cent increase in VKT. 

Page 62: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 56 of 162 

 

This shows that population growth in the inner suburbs of Melbourne has a far smaller  impact  on  the  road  network  than  growth  in  the middle  and  outer suburbs.  This is likely to reflect better public transport options and shorter trip lengths in inner areas. 

Despite  this,  information  supplied  by  VicRoads  indicates  that  overall  road congestion  is concentrated  in  inner Melbourne and  the minutes of delay per kilometre travelled is more than twice that experienced on the outer network. 

A  section of  the VAGO  report  focussed on  the  importance of public  transport planning  to achieve mode shift and reduce car dependence.  The reports stated: 

Public transport accessibility is an important factor that influences demand for road use.   Therefore, more explicit consideration of mode shift goals, targets and strategies within tactical plans would provide greater assurance that they are  optimally  focused  and  integrated  with  other  initiatives  to  manage congestion across the transport portfolio. 

The  VAGO  report  provided  a  significant  focus  and  commentary  on  traffic  demand management  in  preference  to  increasing  road  space  supply  as  the  most  economically efficient means of addressing the challenge of traffic congestion. 

In the resource constrained environment facing the State Government, the report indicated that a focus of the supply side “is unlikely to be financially sustainable” so  it concludes the need for agencies “to develop initiatives that effectively mitigate the demand‐side causes of congestion, including both the need for, and cost of, expensive infrastructure solutions.” 

In  relation  to  the  consideration  of  supply  side  solutions  against  demand  management techniques, the VAGO report stated: 

It is generally acknowledged that cities cannot continue to build their way out of congestion and that a greater focus  is needed on helping to meet demand by better managing the assets that already exist. 

Achieving  this  requires  a  focus  on  optimising  the  efficiency  of  existing  road infrastructure.  Important initiatives in this respect include: 

allocating road space to higher priority travel modes that maximise person throughput and the efficient movement of freight 

incident response services and real time traffic management systems, such as  traffic  signalling  and  freeway  management  systems  that  aim  to minimise disruptions to traffic and optimise flow 

ongoing monitoring and evaluation of the operation of the road network. 

The  report acknowledged  that VicRoads was actively working  to  improve  the efficiency of the road network with some encouraging results, however, it recognised that this is limited by “the  lack of clear  system‐wide performance data  for network efficiency and congestion management.” 

(iii) Discussion 

The continuing  important role of Punt road  in providing a key network  link for commercial traffic was  not  contested.   Nor was  the  economic  importance  of  providing  access  to  the 

Page 63: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 57 of 162 

 

Melbourne CBD for employment, education, services, retail and entertainment and  leisure.  It was not suggested that these roles for Punt Road would dramatically change in the future.  VicRoads noted  that heavy  freight vehicles are primarily directed  to  the  freeway network and Punt Road would continue to play only a secondary role  in  freight movement.    In this regard, it is noted that commercial vehicles comprise approximately 4.7 per cent of average weekday daily  traffic along Punt Road with a majority of  these vehicles being small  trucks and medium or large trucks making up only slightly above 1 per cent of total traffic volumes. 

VicRoads did not submit that Punt Road would need to be widened to support any change in road network hierarchy or to support any specific economic direction. 

It  is clear that traffic congestion acts as a major  impediment to the economic efficiency of Melbourne, as  it does  for  cities across Australia.    In addition,  congestion has major  social implications. 

The  VAGO  report  into  managing  traffic  congestion  provided  a  useful  and  quite  recent overview of  the  issues  that affect Melbourne’s  transport system; and why any  ‘first blush’ analysis  concerning  measures  to  relieve  traffic  congestion  through  the  development  of expensive  infrastructure would be misplaced.   A  key  theme  across  the VAGO  report  is  to decrease  traffic  demand  through  a  combination  of modal  shift  to  public  transport;  the implementation of a  range of demand management  strategies  including pricing measures; and optimising the efficiency of existing road  infrastructure through emerging technologies and intelligent transport systems.  Whilst the VAGO report made this as a general point, the Committee believes this applies equally to the Punt Road corridor. 

(iv) Conclusion 

The Committee concludes that: 

Punt role plays an important role in supporting the economic prosperity of Melbourne, in particular through its roles as: 

- A north‐south connector route for private and commercial traffic - A secondary freight route - Access to the Melbourne CBD - A bypass of the central city area. 

There is no evidence that the economic role of Punt Road in Melbourne’s road network is likely to change significantly in the foreseeable future. 

At the broad level, while the economic costs of traffic congestion in Melbourne are very significant  at  over  $4.6  billion  and  likely  to more  than  double  by  2030,  the  limited literature  review  undertaken  by  the  Committee  indicates  that  simply  increasing  road capacity will not address congestion without a range of demand management measures and the use of improved technology and intelligent transport systems. 

7.2 PAO replacement cost 

(i) The issue 

What would be the financial costs of reinstating the PAO in the future if the existing PAO is removed; and how should this be taken  into account  in considering any decision to retain, modify or remove the PAO? 

Page 64: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 58 of 162 

 

(ii) Evidence and submissions 

Ms Forsyth stated in her opening submission that Mr Kinnaird’s evidence demonstrates that there would be a very significant economic cost  imposed upon the Victorian taxpayer  if the overlay was removed and then land had to be acquired in the future … 

Mr Kinnaird’s evidence considered the scenario where the PAO was removed and VicRoads sold the properties they own and recovered the prior compensation paid under the P&EA in respect  of  the  41  properties  affected; making  an  adjustment  for  the  cost  of  selling  the properties.  He estimated that a net amount of $52,220,000 would be realised. 

Mr  Kinnaird  then  estimated  the  theoretical  cost  of  acquiring  the  full  number  of  135 properties  under  the  PAO  again  ‘the  next  day’,  and  concluded  this would  result  in  a  net difference of $215,600,000 in 2016 figures. 

Mr Kinnaird  then calculated  the  future cost of purchasing  the properties  in 2051 with  the cost of capital employed increasing in value by 5.5 per cent annually.  He concluded that in 2051, the estimated cost would be net $1,690,000,000 ($1.69 billion). 

Mr  Kinnaird  then  provided  a  table  which  shows  the  difference  between  the  value  of retaining the PAO and removing it, based on various compensation levels. 

In this table  four different compensation scenarios are modelled that equate to 20, 50, 70 and  90  per  cent  compensation  levels.    The  ‘P&EA  reduction’  relates  to  the  Loss  on  Sale compensation i.e.  The amount of compensation paid for the loss on sale of properties as a percentage of the total compensation entitlement. 

As at 2016 

20 per cent P&EA reduction: $215,600,000  less $200,940,000  $14,660,000 

50 per cent P&EA reduction: $215,600,000  less $176,500,000  $39,100,000 

70 per cent P&EA reduction: $215,600,000  less $160,200,000  $55,400,000 

90 per cent P&EA reduction: $215,600,000  less $143,900,000  $71,700,000 

As at 2051 

20 per cent P&EA reduction: $1,690,000,000  less $1,310,000,000  $380,000,000 

50 per cent P&EA reduction: $1,690,000,000  less $1,150,000,000  $540,000,000 

70 per cent P&EA reduction: $1,690,000,000  less $1,040,000,000  $650,000,000 

90 per cent P&EA reduction: $1,690,000,000  less $940,000,000  $750,000,000 

Mr Kinnaird then assessed the level of redevelopment that would likely occur on the subject properties over  a  35  year  time period  and  the potential  impact on  the  economic  cost of reinstating  the PAO  in 2051.   Based on  a number of  assumptions  concerning  the  level of likely redevelopment, Mr Kinnaird estimated that this could result  in a building value uplift of $82,450,000 by 2051.  This amount would be in addition to the range of 2051 estimates in the above table. 

As outlined above,  several  submissions  from property owners disputed  the  reasoning and conclusions drawn by Mr Kinnaird about the cost to VicRoads of exercising the PAO and also the cost of replacing the PAO if it was lifted then reimposed at a later date. 

Page 65: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 59 of 162 

 

Ms Warwick and Mr Allatson submitted that the 2016 figures are not relevant as VicRoads is not seeking to acquire properties now and “The 2051 figures are more indicative of the likely cost impact.  This is the timeframe set by VicRoads and is far more likely given how long how long it is anticipated VicRoads will take to progress the matter.”  This submission also asserts that  the  final costs  to  the government of  the day are  likely  to be above even  the highest modelled costs because voluntary acquisitions on both sides of Punt Road would need to be factored in. 

The  issues  of  fairness  and  accuracy  of  acquisition  and  property  valuations  as  raised  by several submitters is discussed in more detail in Chapter 13. 

(iii) Discussion 

The  economic  and  valuation  evidence  provided  for  VicRoads  demonstrates  that  under  a range of scenarios, based on differing  levels of prior compensation,  the  total  replacement cost of the PAO varies between $14,660,000 and $71,700,000 in 2016 and $462,450,000 and $832,450,000 in 2051; with the 2051 figures inclusive of the uplifted values due to assumed redevelopment  over  the  intervening  period.    The  various  scenarios  demonstrate  that VicRoads holds significant embedded value as the PAO has been  in place over an extended period of  time, and because prior compensation has been paid on a  third of  the affected properties, the eventual cost to VicRoads of acquiring these properties under the PAO would be mitigated.  By removing the existing PAO, VicRoads would forego this benefit.  Further, in the event of removing or partly removing the PAO, if the property owners of the 41 affected properties repay the prior compensation in line with legislative requirements then they can unlock significant value in their properties. 

The Committee is of the view that if the PAO is relinquished now it will most likely never be recovered due  to  the high  likelihood  that  the  land will be  further developed and become prohibitively expensive to buy back.  The consequence of any decision to remove the PAO is therefore, in the Committee’s view, likely to be final. 

(iv) Conclusions 

The Committee concludes that: 

The existing PAO, including the land already in VicRoads ownership, is a significant public asset. 

Based on evidence provided  to  the Committee,  the  cost of  relinquishing  the PAO and buying it back in the future is prohibitively expensive. 

Any  decision  to  relinquish  all  or  part  of  the  PAO  should  for  all  practical  purposes  be viewed as irreversible. 

Page 66: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 60 of 162 

 

8 Traffic and transport issues 

8.1 The issues 

At the core of the Committee’s task is to examine the implications for Melbourne’s transport system of  removing, modifying or  retaining  the PAO.   The Committee has  considered  the extensive evidence and submissions in relation to the various future concepts for Punt Road and  reached  some  conclusions about  the most appropriate  short, medium and  long  term road layout for Punt Road. 

8.2 The role of Punt Road in the transport network 

VicRoads  SmartRoads  policy  identifies  Punt  Road  as  ‘preferred  traffic  route’  and  a  ‘bus priority route’.  See Figure 3.  Of the routes crossing Punt Road, Toorak Road is identified as a tram and bicycle priority route and a pedestrian priority area, and Commercial Road and High Street are identified as tram, bus and bicycle priority routes. 

 

Figure 3  SmartRoads road use hierarchy 

 

Page 67: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 61 of 162 

 

VicRoads submitted that26: 

The Hoddle Street‐Punt Road corridor is the only major north‐south arterial on the east of an Expanding Central City  that can provide a  strategic bypass of central Melbourne.  Punt Road is identified as a preferred traffic route and bus priority route in the VicRoads Smart Roads hierarchy.  It ought to play a critical role in: 

diverting traffic from going into town and then out again to get across the city by acting as an efficient route for vehicular traffic; 

diverting public transport users from going into town and then out again to get across the city by acting as an efficient route for buses; and 

encouraging  through  traffic  away  from  parallel  roads  and  key  activity centres  such as Chapel Street and St Kilda Road, which are nominated as tram, bicycle and pedestrian priority areas. 

8.3 Comments on the concept options 

The  Committee makes  the  following  comments  on  the  concepts  presented  by  VicRoads, acknowledging that the seven concepts are indicative only and other options and variations are possible. 

Concept 1 involves the implementation of 24 hour clearways on both sides of Punt Road. 

The  Committee  notes  the Government  has  announced  that  it  has  initiated  the  statutory process  to  implement  24  hour  clearways  and  subject  to  the  necessary  approvals,  the clearways should operate from the middle of the year. 

The  Committee  supports  the  introduction  of  the  clearways  and  notes  that  once implemented, they would be expected to be part of any of the concepts suggested. 

Concept  2  has  been  reviewed  by  the  Committee.    It  is  the minimal  improvement  option involving minor changes that can be achieved without any use of the PAO. 

Concept 3 has not been  considered by  the Committee.    It  is not  substantially different  in performance  from Concept  2,  and  although  it may  have  some  operational  advantages,  it does not impact on the PAO. 

Concept 4 has not been considered by the Committee.  VicRoads has discounted the use of a reversible  lane based on  the advice of Arup27.   The Committee agrees  that  the  reversible lane arrangement would have operational challenges with limited benefits. 

Concepts 5, 6 and 7 all involve longer term options utilising part or all of the PAO and have therefore been the main basis of the Committee’s assessment. 

   

                                                       26  Document 2 27  Concept Options Report page 21 

Page 68: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 62 of 162 

 

8.4 Modified Concept 5 

The Committee has also prepared a suggested  Modified Concept 5 for comparison purposes as noted  in  section 4.2  and  shown  graphically  in Appendix E.   The Modified Concept 5  is similar to Concept 5 in that it involves widening at intersections and a four lane cross section midblock,  but  involves much  less  flaring  in  order  to  reduce  land  acquisition  and  reduce impacts on heritage buildings in particular. 

Modified Concept 5 proposes the following variations to the Concept 5 design: 

Generally  contained  within  the  existing  road  reserve  except  at  the major  signalised intersections, similar to Concept 5 but with reduced land acquisition 

Impacts on heritage buildings are avoided with the exception of the Arcadia Hotel on the south east corner of the Punt Road/Toorak Road intersection 

No widening of the Hoddle Bridge 

Provides  for  at  least  two  through  lanes,  plus  one  left  and  one  right  lane  at  all major intersections.   (Concept 5 provides a third shared through and  left  lane at Toorak Road and Commercial Road)  

Similarly  to  Concept  5,  the modified  layout  provides  for  buses  to  share  the  left  lane and/or have a ‘bus jump’ lane at all major intersections 

Allows for improved pedestrian areas at major intersections.  In particular, the modified layout  proposes  widening  at  the  Domain  Road  intersection  to  allow  for  widened footpaths 

Achieves  sufficient  traffic  capacity  to more  than  adequately  cater  for  2031 Base Case volumes 

Requires acquisition of part or all of 54 properties (subject to final design).  Of these, 38 are  relatively  small  acquisitions  not  affecting  buildings  and  16  buildings  would  be affected 

Similarly to Concept 5, the modified layout assumes permanent clearways. 

If the Modified Concept 5 were adopted, the Committee anticipates that the PAO could be removed from the following 81 properties (subject to final design): 

90‐110 Punt Road (11 properties) 

190‐226 Punt Road (13 properties) 

286‐386 Punt Road (36 properties) 

442‐456 Punt Road and 1A Shipley Street (6 properties) 

498‐526 Punt Road and 1A and 2B Gordon Avenue (13 properties) 

49 and 51 Alexandra Avenue (2 properties). 

The Committee has suggested Modified Concept 5 in order to show how some of the issues raised  in  submissions might  be  addressed.    The  drawings  as  shown  in  Appendix  E were prepared after the Hearing and so the parties have not had a chance to comment on them.  The  Committee  is,  however,  comfortable  that  the  Terms  of  Reference  require  the Committee  to  advise  on  “whether  to  retain, modify  or  remove  the  overlay”,  and  in  that context, the Committee believes it is important to explore possible modifications that might be appropriate. 

Page 69: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 63 of 162 

 

In any case, the Committee believes that further design work will be required on whichever future  concept  is  adopted, with  appropriate  consultation  between VicRoads  and  affected landowners. 

8.5 Punt Road traffic performance 

(i) Evidence and submissions 

A summary of which submitters and experts supported which Concepts is provided in Table 4 in Section 8.10 below. 

The Concept Options Report provided an assessment of the traffic performance of the Punt Road corridor based on a Victorian Metroscopic Model (VMM) analysis and using traffic data from  the  Victorian  Integrated  Transport Model  (VITM).    Concepts  1  to  3 were  analysed assuming  a  4  lane  traffic demand  and Concepts  5  to  7  analysed based on  six  lane  traffic demands.  The analysis looked at traffic growth (from existing), travel time and mean speed as indicators. 

VicRoads  submitted  that  the  congested  nature  of  the  existing  road means  that  there  is suppressed demand estimated to be in the order of 5 per cent to 10 per cent, mainly due to limited capacity further north along Hoddle Street. 

The main findings of the Concept Options Report are: 

the  four  lane concepts provide significant travel time  improvements along Punt Road (particularly northbound in the critical morning peak hour) with Concept 2 providing higher average speeds; 

the  six  lane  concepts  (Concepts  5,  6  and  7)  accommodate  a  significantly higher travel demand providing relief to alternative routes (see Section 7.1) with  a marginally  reduced  level  of  performance  along  Punt  Road  when compared to the four lane concepts; and 

Concept  5  (intersection  widening  only)  provides  for  similar  performance when compared to Concept 6 which provides for widening along the length of the corridor. 

The  Options  Report  noted  that  a  substantial  advantage  of  Concepts  5,  6  and  7  is  the flexibility to reallocate road space to public transport (as in Option 7) or to allocate a greater proportion of green time to improve vehicle and public transport conditions on cross routes. 

The report also noted: 

without  improvements  to  the network,  existing  intersections will  become considerably more  congested  in 2031, particularly  the Alexandra Avenue, Toorak Road and Commercial Road intersections; 

Concepts 2 and 3 are able to cater for the forecast growth during the peak hours of between 10% and 15% when compared to the existing conditions and  both  offer  similar  levels  of  traffic  performance  with  this  additional demand; and 

Concepts 5, 6 and 7 are able  to  cater  for  the  forecast growth during  the peak hours of up to 70% when compared to the existing conditions whilst still offering significant improvements in traffic performance. 

Page 70: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 64 of 162 

 

VicRoads and PTV submitted that “Concept Option 5 has the potential to address the short and  medium  travel  demands  for  the  corridor  as  well  as  providing  benefits  across  the surrounding network, particularly  for  trams and buses  on  Toorak Road, Commercial Road and  High  Street.    It  would  ensure  safety  and  operational  improvements  could  be implemented at the three major intersections  …  Both Options 6 and 7 would provide a long term  option  with  better  provisions  for  safety  and  cyclists  than  Option  5.”    VicRoads highlighted  the  need  to  preserve  the  option  for  a  dedicated  bus  lane  on  Punt Road  as  a primary reason for retaining the PAO. 

The Concept Options report assessed Concept 5 as follows:28 

This concept would address the short, medium and long term travel demands for the corridor as well as providing benefits for the surrounding road network.  It also provides benefits  for users crossing the corridor  including pedestrians, cyclists and tram and bus passengers. 

The expert evidence of Mr Kinghorn and Mr Carter was  that Concept 5 was a medium  to long term option “providing benefits for Punt Road and the wider network at all times of the day”.29 

A number of submitters submitted that increasing road capacity will not resolve congestion.  In  response, Mr Kinghorn and Mr Carter gave evidence  that  the  six  lane options  increase throughput on Punt Road,  reducing  traffic  volumes on parallel  roads and  improving  cross road performance. 

A number of submitters including Drop Punt submitted that traffic volumes have declined in recent  years, with  an  18  per  cent  reduction  between  2003  and  2013.    In  response, Mr Kinghorn and Mr Carter gave evidence  that population growth  in Melbourne broadly, and the  local  area more  specifically,  will  drive  demand  up  for  the  Punt  Road‐Hoddle  Street corridor.  They gave evidence that the VITM forecasts showing future increased demand are considered reasonable. 

Drop Punt submitted that Concept 2 performs better than any of the six lane options based on the ARUP traffic analysis provided.  Mr Carrasco presented a comparison of travel times along Punt Road under various concept options.   He submitted that the travel time savings were  very  small  (or  in  some  cases  not  a  saving  at  all) when  comparing  Concept  2  (not widened) to Concept 7 (six lanes with bus lane).  VicRoads responded that such a conclusion fails  to  take  into account  the  substantial network  improvements accruing  to other  routes such as Chapel Street and St Kilda Road.   VicRoads submitted that  it also fails to recognise the significant increase in throughput of the six lane options with subsequent improvements for travel times and reliability for public transport, on Punt Road and on crossing routes. 

Drop Punt submitted that Punt Road north of the Yarra and Hoddle Street will continue to act as the capacity constraint in the corridor and the Committee should have no confidence that  the mooted  Hoddle  Street  improvements will make  any  substantial  difference.   Mr Allatson drew the Committee’s attention to the scope of the Hoddle Street capacity upgrade project  as  shown  in  the  Australian  Infrastructure  Plan30.    That  document  describes  the 

                                                       28   Concept options report page 33 29   Assessment conclusions in expert evidence provided to the Hearing – Document 4 page 25 30   Australian Infrastructure Plan February 2016 – Document 33 

Page 71: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 65 of 162 

 

project  as  addressing  ‘connectivity  between  Eastern  Freeway  and Melbourne  CBD’.   Mr Allatson submitted that the Committee should therefore not expect that the project would assist congestion in the Punt Road section of the corridor. 

Mr Higgs gave evidence that the Punt Road Swan/Street intersection and the section of Punt Road between the Yarra River and Swan Street will continue to act as the most significant constraints on  traffic capacity  in  the corridor.   Mr Higgs’ evidence was  that  the Alexandra Avenue and M1 freeway interchange also provide constraints on capacity in that section and these  constraints will  continue  to  constrain  the  capacity  of  Punt  Road  to  the  south.   He noted  that  any  widening  of  Punt  Road  adjacent  to  Gosch’s  Paddock  is  unlikely  to  be supported by the City of Melbourne. 

Mr Higgs  supported  Concept  5,  arguing  that  the  increased  lane  capacity  at  intersections would provide operational advantages and the opportunity for bus jump lanes: 

The  Arup  Report  provides  Year  2031  level  of  service modelling  for  the  key intersections.   All  concepts  except Concept 1  show  very  satisfactory  level of service for the peak periods. 

In the multi‐criteria analysis the operational outcomes of Concepts 2, 3 and 5 are  similar,  and  Concepts  6  and  7  are  not  rated  significantly  better  than Concept 5. 

In my opinion Concept 5 could provide an advantage  in that bus queue‐jump provision provided that left turn islands with bus stops could be included, in a similar form to that which is already present at Hoddle Street/Bridge Road. 

Concept  5  could  be  further  refined  from  the  layout  shown  in  the  VicRoads Drawings Numbered  668664‐668670 and dated  12/01/11,  through  reducing the  extent  of  the  6  lane  configuration  through  the  intersections  and  thus reducing  the  extent  of  PAO  that  it  would  be  appropriate  to  retain  under adoption of that Concept.31 

Mr Higgs summarised his position: 

In  summary  it  is my  opinion  that  the  PAO  should  either  be  removed  in  its entirety or limited to what would facilitate reasonable designs for intersection capacity enhancements. 

Mr  Tivendale  gave  evidence  that  he  supported  Concept Option  6  as  an  appropriate  long term  treatment  for Punt Road, and  in  response  to questions  from  the Committee,  stated that the PAO should be retained. 

Mr Humphreys evidence primarily  related  to network performance  (discussed  in  the next section) rather  than  the performance of  individual  intersections, but he did comment  that Concepts 5, 6 and 7 would have the benefits of lower signal cycle times, reducing delays for pedestrians  and  crossing  traffic.    He  noted  that  queue  lengths  for  Concept  7 would  be substantially longer than for Concepts 5 and 6 due to the dedication of one lane to bus only.  Mr Humphreys made the assumption that queue  lengths for Concept 5 would be the same as for Concept 6 on the basis that the intersection treatments are identical. 

                                                       31  Mr Higgs’ expert report page 6 

Page 72: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 66 of 162 

 

The City of Melbourne submitted that a 40 km/hr speed limit ought to be imposed along the entire section of Punt Road south of the Yarra River  in order to  improve pedestrian safety.  This position was supported by Mr Tivendale  in evidence called by Melbourne Council and was supported by a number of other submitters  including Ms Chia and Ms Williamson.   Mr Humphreys gave evidence that any extension of 40 km/hr zones outside school times is not likely to be necessary.  He noted (and the Committee agrees) that in any case this is a matter that  does  not  impact  on  the  PAO  and  is  outside  the  gambit  of  the  Committee’s consideration. 

(ii) Discussion  

The Committee agrees with Drop Punt and Mr Higgs that Punt Road north of the Yarra River and the Swan Street  intersection will  likely continue to act as a capacity constraint on Punt Road  south of  the River.    The Committee does not have  any  confidence  that  the Hoddle Street  capacity upgrade project will have  any  significant  impact on  traffic  capacity  at  the southern end of Hoddle Street or the Swan Street intersection.  The Committee agrees with Mr Higgs’ evidence that the M1  interchange will also be a constraint, and additionally, the Committee sees  little  likelihood that the historic Hoddle Bridge would be widened even  in the long term. 

Based on the reports and evidence provided by Arup and the Committee’s own analysis of the SIDRA outputs, the Committee makes the following observations: 

The requirement to provide a significant increase in peak hour capacity along Punt Road is not well founded as there are, and will remain to be, capacity restraints north of the River.    In  fact,  the Committee observes  that under current conditions  in  the AM peak, traffic  queues  regularly  spread  across  the Hoddle  Bridge  such  that  traffic  cannot  exit Punt Road or Alexandra Avenue. 

The provision of 24 hour clearways will give an  increase  in daily capacity for Punt Road and will allow some relief of parallel routes. 

There  is significant congestion at the  intersections with Toorak Road, Commercial Road and High Street during peak periods which restricts the amount   of ‘green time’ able to be allocated to the east‐west flows on Toorak Road, Commercial Road and High Street. 

Flaring of the Punt Road carriageways at its intersections with Toorak Road, Commercial Road  and High  Street would  allow  the  north‐south  capacity  at  these  intersections  to closer reflect the mid‐block capacity. 

Meaningful flaring can be undertaken within the PAO area as demonstrated by Concept 5 and the Modified Concept 5. 

The Committee is not persuaded that the suggested traffic benefits of a full widening as provided in Concepts 6 and 7 would ever be achieved and that significant and meaningful improvement can be obtained by  limiting upgrade works to the flaring of Punt Road at the key intersections. 

The Committee believes that a Modified Concept 5, which restricts the extent of flaring at the key intersections of  Toorak Road, Commercial Road and High Street compared to Concept 5, and which also recognises a desire  to minimise  impacts on buildings within the PAO, would achieve significant benefits overall. 

When  considering  the Modified Concept 5,  the Committee was  cognisant  that  to  fully utilise  the  two‐lane each way midblock  capacity of Punt Road, either  the provision of 

Page 73: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 67 of 162 

 

three stand‐up through  lanes (similar to Concept 5) or the prioritisation of traffic flows (signal linking) would be preferable in each direction at the signalised intersections. 

A review of the traffic predictions and the SIDRA analyses provided by VicRoads showed that  there was  no  need  to  substantially  increase  Punt Road  peak  hour  flows  because sufficient downstream capacity was not available (nor likely to become available).   

The Modified  Concept  5  provides  for  separate  left  and  right  turn  lanes  at  the major intersections  to  allow maximum  flow  from  the  two  stand‐up  through  lanes.    SIDRA analysis of the Modified Concept 5 plans shows that the 2031 Base Case traffic volumes can be accommodated with a good  level of service, although not as well as Concept 5.  The only capacity situation occurs at the Punt Road/Toorak Road intersection where the AM peak period had degrees of saturation approaching 1.0. 

It is significant that the Committee found that the operation of the Punt Road/Alexandra Avenue  intersection  was  unlikely  to  be  a  capacity  constraint  even  with  2031  traffic volumes and beyond.  The current simple traffic signal phasing allows high utilisation of the  existing  lane  configuration  and  capacity  constraints,  particularly  in  the  AM  peak, resulting from a lack of roadspace on Punt Road north of Hoddle Bridge.  The Committee saw  no  benefit  in  changes  to  the  lane  configuration  or  right  turn  arrangements  and further,  did  not  agree  that  any  river  bank  land  should  be  acquired  to  increase  traffic capacity in the future. 

It is appropriate to note that the Committee was concerned that the ARUP traffic model had  allocated  an 80 per  cent  increase  in  traffic  (20,000  vpd  in 2013  to 36,000  vpd  in 2031)  on Alexandra Avenue west  of  Punt  Road.    By  any measure,  this  level  of  traffic would exceed the capacity of that section of Alexandra Avenue and the necessary works to accommodate such an increase would be most unlikely to ever be approved. 

8.6 Broader road network performance 

(i) Evidence and submissions 

The VicRoads Concept Options Report made the following observations: 

Punt Road volumes increase significantly under the six lane concepts when compared  to  the  Base  Case  as  additional  demand  is  attracted  to  the corridor (particularly during the inter peak period); 

volumes  on  parallel  north‐south  roads  such  as  Chapel  Street  reduce providing improved travel times along these corridors with greater benefits associated with the 6 lane scenarios; and 

volumes on east‐west road vary with a minimal change in traffic overall. 

The  VITM  data  provided  by  Arup  shows  that  any  improvements  to  Punt  Road will  draw traffic  from  parallel  routes.    Table  1  is  reproduced  from  the  evidence  statement  of Mr Humphreys.   It shows that Concepts 5, 6 and 7  in particular draw considerably more traffic into  the  Punt  Road  corridor  for  the  benefit  of  St  Kilda  Road,  Chapel  Street  and Williams Road. 

   

Page 74: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 68 of 162 

 

Location  2013 Arup Options (2031) 

Do Nothing  Options 1‐3  Option 5 & 6 Option 7 

Punt Road – South of Toorak Road 

32,000  34,000  30%  65%  64% 

St Kilda Road – South of Toorak Road 

44,000  47,000  1%  ‐3%  ‐2% 

Chapel Street – South of Toorak Road 

17,000  19,000  ‐5%  ‐9%  ‐8% 

Williams Road – South of Toorak Road 

23,000  25,000  ‐6%  ‐10%  ‐10% 

Total  116,000  125,000  7%  13%  13% 

Table 2  VITM Two way estimated daily traffic volumes 2031 

Mr Humphreys gave the following evidence in relation to the VITM outputs: 

Interrogation of the volumes identifies that with the expected population and employment growth, and maintaining  the Punt Road  corridor as  it  currently stands  (i.e.  do  nothing  scenario),  the  north‐south  routes  are  anticipated  to increase  by  approximately  eight  percent.    The  growth  is  expected  to  vary across  each  of  the  four  corridors  of  between  two  and  three  thousand additional vehicles per day. 

It  is  sensible  that Options 5 and 6  from a  strategic  (VITM) perspective have been modelled  as  similar  options  given  that  the  throughput  at  each  of  the intersections would be generally similar to a degree.  I would expect Option 6 may have a marginal higher  level of  throughput given  the  reduced  levels of merging and diverging upstream and downstream of the intersections. 

The  capacity  improvements  provided with Options  5,  6  and  7  show  a  large uplift in throughput as a result of the additional capacity.  In broad terms, an additional  lane on Punt Road would be expected  to provide more  than 50% additional throughput in each direction.  This higher level of throughput in the options highlights that demand in the network exists regardless of the level of capacity  improvement provided.   Whilst the strategic model does not  include the  local street network, the higher  level of demand  increase  in Options 5, 6 and  7  suggests  that  there will also be  increased pressure on  the  local  road network.   This  is on  the basis  that  the  forecast population, employment and educational  increases  in the  immediate vicinity of the corridor (refer to Table 2.1  earlier  in  this  report)  will  create  additional  demand  on  the  local  road network with residents and workers trying to access jobs and housing. 

The  increased  capacity  of  Punt  Road  in  Options  5,  6  and  7 makes  this  an attractive route  for north south movements and  results  in a net decrease on the three competing routes.  There are a number of reason for this in my view with the key reasons being the higher speeds on Punt Road with the increased capacity  as well  as  the  connectivity  that  the  corridor  plays  both  north  and south  of  its  extents  (i.e.  it  is a  continuous  corridor as  opposed  to  the  other three routes). 

Page 75: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 69 of 162 

 

Mr Humphreys also commented on the VMM outputs, noting that the forecast throughput of Concepts 5, 6 and 7 is slightly higher under the VMM (approximately 70 per cent increase in throughput in the peaks compared to 50 per cent under the VITM). 

Mr Humphreys provided the following summary of his evidence in relation to his assessment of the Concept Options: 

The strategic objectives for the Hoddle Street – Punt Road corridor (as detailed in  the  Arup  Report)  include  the movement  of  people  along  and  across  the corridor,  improving travel times and reliability  for bus services as well as the local  amenity  and  priority  of  sustainable  transport.    The  options  reviewed allow  for a  staged approach  (if  required)  to progressively construct  capacity improvements  at  the  key  intersections  (Option  5),  followed  by  midblock improvements (Option 6) and the introduction of high capacity lanes or public transport lanes (Option 7). 

Without  improvements  to  the  corridor,  increased  congestion  will  have  an impact on both car  travel and public  transport with  travel  times making  the services  unreliable  and  unattractive.    Further,  the  current  congestion  and provision of north‐south priority along punt road also  impacts on  intermodal connectivity between buses, train and trams. 

The  information  provided  by  VicRoads,  PTV  and  Arup  have  confirmed  that from a traffic and transport perspective each of the options provide benefit to the Punt Road corridor as well as the wider and localised transport network. 

The VicRoads and PTV position that the corridor should have a focus on both passenger  vehicle  throughput  as well  as  public  transport  is  supported  and should be planned for.  In the short term, Option 5 and 6 provide outcomes for traffic that will benefit all modes and the network up to 2031.   Beyond 2031, transport  solutions  will  be  required  so  that  more  people  can  be  moved efficiently, as such  I am satisfied that Option 7 will provide the best outcome for the transport network. 

On  this  basis  Mr  Humphreys  concluded  that  the  PAO  should  be  retained  because “maintaining  the PAO allows  for a  range of  future  interventions  to accommodate demand growth  in a strategically  important part of the network.”32   He added the qualification that he had  “not  investigated  in great detail as  to whether  or not  the PAO  could be modified which is due to the fact that options are preliminary in nature and would require more detail and documentation prior to finalising on and exact layout and alignment.” 

Stonnington Council  submitted  the Committee  should  consider  that  the PAO has been  in place  for  62  years  but  that  the  road  has  not  been widened  in  that  time  and  there  is  no funding or political commitment to widen it.  Council submitted that there are other options to improve the operation of Punt Road within the existing road reserve.  Council submitted that  the  traffic  engineering  justification  for  the  retention  of  the  overlay  is  far  from conclusive. 

                                                       32   Mr Humphreys evidence page 33 

Page 76: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 70 of 162 

 

Stonnington Council resolved to seek the removal of the PAO partly on the basis of  ‘recent and  proposed  improvements  to Melbourne’s  road  network  and  public  transport network’.  Stonnington  Council  submitted  that  the  following  projects  ought  to  be  considered  in  a broader network analysis: 

The Melbourne Metro Rail Project 

The proposed merging of Tram Routes 8 and 55 to establish Route 58 

The proposed downgrading traffic function of St Kilda Road 

The immediate rebranding of Bus Route 246 as a SmartBus 

The proposed (rail) grade separations; and 

Car  parking  policies  that  actively  seek  reduction  in  car  parking  and ownership. 

Melbourne  Council  also  pointed  to  a  number  of  initiatives  introduced  over  the  past  two decades that have reduced the attractiveness of driving to the City, including parking levies, speed  restrictions,  tram  superstops and other  traffic  limitations.   A number of  submitters including  Mr  Cleaver  (who  appeared  at  the  Hearing  with  Ms  Oldfield)  and  Ms  Dwyer submitted that ride sharing services will also have a substantial impact in reducing traffic in the future.  Drop Punt also submitted that the majority of traffic on Punt Road is bound for the  City  and  that  a  number  of  demand  management  measures  can  be  employed  to discourage traffic into the City. 

While acknowledging that the precise effect of each of these projects  is difficult to predict, Stonnington  Council  submitted  that  these  projects  are  more  likely  to  assist  mode  shift towards public transport and lessen the traffic load on Punt Road in the longer term. 

In response, VicRoads submitted  that  the VITM model does account  for Melbourne Metro and car parking policies.  VicRoads submitted that simply rebranding the 246 bus route as a SmartBus would not  increase capacity without moving the bus more quickly and  increasing reliability, both of which would be achieved through  increasing the traffic capacity of Punt Road.  VicRoads also pointed out that any downgrading of St Kilda Road would be supported by an upgrade of Punt Road. 

Stonnington Council submitted that the traffic analysis: 

does  show  that  time  savings  along  Punt  Road  will  not  be  significantly improved  by  road  widening  and  that  intersectional  changes  (which  can primarily  be  provided  within  the  existing  Punt  Road  reservation  and  land outside the PAO) create immediate benefits. 

The  Committee was  not  provided with  any  definitive  evidence  about whether  increased capacity  would  be  required  in  the  Punt  Road  corridor  beyond  2031.    The  argument  of VicRoads and PTV was that additional capacity may be required so therefore the PAO should be retained.  Evidence and submissions were presented in relation to the likelihood of future demand management measures such as congestion tax, CBD parking restrictions etc. and the expectation  that  this would  reduce  traffic on Punt Road.   Counter  to  this,  the Committee received  information on overall projected population  increases  in Melbourne and the  likely localised development and population increase in the vicinity of the Punt Road corridor.  Mr Humphreys’  evidence  assumed  that  this  would  likely  result  in  increased  traffic  demand beyond 2031, but he acknowledged that this was a broad assumption rather than as a result 

Page 77: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 71 of 162 

 

of  detailed  analysis.    The  Committee  cannot  draw  any  conclusion  about whether  traffic demand will continue to increase beyond 2031. 

(ii) Discussion 

The Committee notes  that  the VITM analysis shows  that Concept 5 has similar benefits  to Concepts 6 and 7 in terms of the ability to absorb higher traffic throughput and hence relieve parallel routes such as St Kilda Road, Chapel Street and Williams Road. 

The Committee agrees that some upgrading of Punt Road  is  justified to cater for projected future traffic volumes, allow for improved conditions for crossing traffic and public transport and to relieve congestion, particularly outside of peak times,  on parallel routes. 

The Committee does believe that Concepts 2 or 3 are adequate as  long term solutions and believes that an upgrade to the Concept 5 or the Modified Concept 5 will be required in five to ten years’ time.   This would necessitate the retention of part of the overlay, but only to the extent  required  for  the proposed  intersection widening.   The Committee believes  that Concept  5 would  provide  an  appropriate  level  of  service,  but  does  not  believe  that  the extent of widening proposed  is necessary.   The Committee  is confident  that  the Modified Concept 5 will function adequately. 

The modified Concept 5 retains the right turns from Punt Road as well as providing for bus priority.  Using the 2031 Base Case volumes, it achieves a good level of service. 

It  reaches  capacity, even  retaining  turn movements, with  about half  the  additional  traffic (base  case  to  concept 5, 6, 7).   Alternatively,  it provides additional  capacity  for east‐west movements when catering for the base case volumes. 

We are confident it will work well because: 

it  provides  significantly more  capacity  for  Punt  Road  traffic  than  existing  volumes which are restricted north of the river (or alternatively provide better for east‐west movements), 

it retains the ability for all turns which can be restricted in the future if necessary to provide additional through capacity, and 

it is conducive to signal linking.  

Whilst the Modified Concept 5 will not provide the same through traffic capacity as Concept 5, the Committee believes that this is an appropriate concession in minimising the impact of the widening and limiting acquisition. 

The additional capacity provided by allowing separate left and right turn lanes can be shared by additional traffic on Punt Road as well as extra “green time” for the major cross streets.   

The Committee does not believe that provision of additional through capacity on Punt Road (over  and  above  that  achievable  by  the  Modified  Concept  5)  is  warranted  because  of upstream/downstream  restrictions  in  adjacent  sections.    The  additional  capacity provided off‐peak  by  the  introduction  of  24  hour  clearways  and  the  localised  flaring  at  the major intersections will  see  the  daily  capacity  along  Punt  Road  under  the Modified  Concept  5 effectively match that of Concept 5. 

Page 78: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 72 of 162 

 

The  Committee  believes  that  its  Modified  Concept  5  provides  an  appropriate  balance between widening Punt Road and meeting the demands for future capacity in the corridor. 

A key question for the Committee is: should the PAO be retained in case it might be needed in the future?  The difficulty for the Committee is that no traffic modelling was done beyond 2031, so there is a level of uncertainty associated with drawing conclusions about the most appropriate  longer term solution.   Even  if modelling had been done beyond 2031,  it would have been based on uncertain assumptions.  It comes down to a question of the level of risk that can be assigned to each possible outcome. 

On one hand the conservative approach could be taken, and on the basis that future traffic volumes are unknown  it would be reasonable to conclude that the PAO should be retained ‘just in case’.  This would be the low risk approach from a transport planning viewpoint and is  the  approach  supported  by  Mr  Humphreys  and  quite  understandably  supported  by VicRoads in its role as the State’s transport planner.  Mr Humphries evidence is that “Option 7 will provide  the best outcome  for  the  transport network”.   The Committee accepts  that Options 6 and 7 may well provide the best outcome to preserve options for providing higher levels of traffic capacity.   However, for the reasons set out above, the Committee does not accept that increased capacity is required, or that it is necessarily desirable. 

The Committee agrees that some degree of caution is warranted, but believes that it is in a position  to  provide  advice  based  on  broader  consideration  of  the  issues  and  drawing  on reasonable assumptions about likely transport policy influences into the future.  

For  the  reasons  set  out  above,  the Committee  believes  that  the Modified Concept  5 will provide a satisfactory level of performance from a traffic and transport viewpoint, and at the same time is at the low end of the risk scale. 

The Committee believes that this approach is low risk based on the following assumptions: 

Issues limiting future traffic volumes: 

Further  demand management measures  are  likely  to  be  employed  to  further  restrict vehicle access and parking in the Melbourne CBD 

The  sports  and entertainment precinct  is  likely  to have  less  rather  than more parking provision in the future, with patrons encouraged to use public transport 

Public  transport  upgrades  including  Melbourne  Metro  and  SmartBus  will  encourage mode shift from private vehicles to public transport 

Government  policies will  continue  to  encourage mode  shift  from  private  vehicles  to public transport 

Alternative  transport modes  such  as  ride  sharing will make  at  least  a  small  positive contribution to reducing traffic volumes 

Even if traffic does grow by 50 to 65 per cent, the VITM analysis shows that the corridor can cater for these volumes without the need for a six lane road33 

Capacity constraints 

Punt Road north of the Yarra River and the intersections with Swan Street will continue to be a capacity constraint on  the Punt Road corridor and  the scope  to overcome  this 

                                                       33  See Table 1 

Page 79: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 73 of 162 

 

constraint is limited (The Committee believes that this will continue to be the case even if continuous flow lanes are introduced to improve capacity at Swan Street). 

Widening of Punt Road  into Gosch’s Paddock to upgrade the M1  interchange  is unlikely to be supported 

Widening of the Hoddle Bridge is unlikely to be supported (on heritage and visual impact grounds) 

Widening of the Alexandra Avenue  intersection  is unlikely to be supported  if  it  impacts on the River environs. 

The Committee acknowledges that population growth, both more broadly across Melbourne and  locally, works against some of  these  factors  that would otherwise  reduce  traffic.   The Committee  is confident, however, that Punt Road with a four  lane cross section mid‐block, widening at key intersections and appropriate signal linking will more than adequately cater for the traffic needs of the corridor well beyond 2031. 

VicRoads,  supported  by Mr Humphreys  accepted  that  Concept  5 would  be  a  satisfactory treatment based on 2031 traffic projections, but, based on his assumption that traffic would continue to grow beyond that date, favoured preserving the ability to scale up to the higher capacity  Concepts  6  or  7  in  the  longer  term.    The  Concept  Options  Report  and  traffic engineering expert evidence  from Mr Kinghorn and Mr Carter  referred  to Concept 5 as a medium to  long term option, and Mr Higgs  favoured Concept 5  (or similar) as a  long term solution. 

The Committee  is not  convinced  that  traffic volumes would  increase  considerably beyond 2031, and was not presented with any definitive expert evidence to the contrary.   For the reasons set out above, the Committee believes that traffic volumes are likely to be contained and not increase significantly beyond 2031 volumes. 

(iii) The future role of Punt Road  

As noted above,  the Committee believes  that reducing  the PAO  is at  the  lower end of  the risk scale.  It is fair to say, however, that this is based on the Committee’s understanding of the  issues  and  a  number  of  assumptions  about  what might  unfold  in  the  future.    The Committee therefore believes it is important to list the assumptions it has relied upon. 

The  Committee  has  based  its  conclusions  on  the  following  assumptions  about  the  future strategic role of Punt Road between Union Street and the Yarra River: 

Punt Road will continue to act as an urban arterial road and will not become a freeway 

A primary function will be as a key north‐south bypass of the Melbourne CBD 

Punt Road will continue  to  function as an access  route  to  the Melbourne CBD and  the Yarra Park sporting precinct, and as a local access road 

Punt  Road will  continue  to  provide  regionally  important  access  to  hospitals,  schools, recreation, employment and business 

Government policies will continue to attempt to manage traffic demand  in the corridor and encourage mode shift from private vehicles to public transport 

The ability to increase capacity north of the Yarra River is limited, and this section of Punt Road and the Swan Street/Punt Road intersection will continue to act as critical capacity constraints in this part of the corridor 

Page 80: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 74 of 162 

 

Bus services will continue to operate along Punt Road, but there will be limited demand for  new  services  along  the  route,  apart  from  increasing  the  frequency  of  the  existing service. 

These  assumptions  are  based  on what  is  known  or  can  be  reasonably  predicted  by  the Committee at the time of preparing this report.  In the event that these assumptions change substantially,  and  this may  be  informed  by  the work  of  Infrastructure  Victoria,  then  the future  options  for  Punt  Road  should  be  reviewed  and  the  PAO  should  also  be  further reviewed. 

The  Committee  has  given  some  consideration  to  scenarios  that  could  challenge  these assumptions and makes the following comments: 

   

Page 81: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 75 of 162 

 

Scenario  Committee comment 

Significant major arterial road upgrades on either end of Punt Road require it to carry substantially more traffic. 

Given constraints on existing arterials this is considered unlikely. 

Punt Road north of the Yarra River and Hoddle Street would continue to act as the capacity constraint unless significantly upgraded. 

Significant upgrade in capacity to Punt Road north of the Yarra River and Hoddle Street. 

Given spatial constraints and the high cost of upgrade, this is likely to be limited in effect. 

The road corridor is required for additional public transport capacity. 

Unlikely given the extent of parallel services that better serve demand for travel to and from the City. 

The expansion of the existing bus service is likely to be limited given its ‘niche’ market. 

Major development of the Yarra Park sporting precinct. 

Unlikely to be done with additional car parking provision. 

Access is likely to rely on public transport access. 

New technologies dramatically change traffic demands or require road space to implement. 

Most initiatives (e.g. ride sharing) are aimed at reducing traffic on the roads.  It is not clear whether driverless cars would increase or decrease traffic. 

There are no new technologies that were brought to the Committee’s attention that would require additional road space. 

Government policies on restricting demand on CBD traffic and parking change 

The Committee believes that policies are likely to be more restrictive in favour of shifting more demand to public transport 

Table 3  Scenarios that could affect Punt Road south of the Yarra River 

In  summary,  this  ‘risk  analysis’  shows  that  there  are  no  future  scenarios  that  cause  the Committee to doubt its assumptions about the future role of Punt Road. 

The most likely of these future scenarios is if future works increase the capacity of Punt Road and Hoddle Street north of the Yarra River.  Whilst the cost of this would likely be high given the  spatial  constraints,  it  is  likely  that  some  increase  in  capacity will be achieved  through initiatives  such  as  the  continuous  flow  lanes  recently  announced.    This may  result  in  an increase in demand on Punt Road feeding into the higher capacity north of the River.  If this scenario does arise,  it may not be desirable to further widen Punt Road south of the Yarra (beyond two through lanes each way) in order to restrict demand on the additional capacity north of the Yarra.  In other words it may not be desirable to remove the congestion on Punt Road north simply to see it return by widening Punt Road south. 

In any case, the Committee believes that any increase in capacity north of the Yarra is likely to be limited and, at best, just means that flows through the Alexandra Avenue intersection and over the Hoddle Bridge will be freed up, allowing a widened Punt Road  (to the extent proposed) to operate closer to optimal capacity. 

Page 82: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 76 of 162 

 

8.7 The public transport impacts 

(i) Evidence and submissions 

The  Concept  Options  Report  noted  that  travel  speeds  improve  for  six  land  concepts (Concepts 5, 6 and 7) with consequent improved reliability for on road public transport.  The reliability of public  transport on other parallel routes  (Chapel Street, Williams Road and St Kilda Road) can also be expected  to  improve as congestion  is  relieved.   The concepts  that provide  four  lanes  with  24  hour  clearways  (e.g.  Concepts  1,  2  and  3)  will  also  provide benefits  (of  a  lesser degree)  for  traffic  and public  transport during  the middle of  the day both along Punt Road and also on the surrounding road network. 

The Concept Options Report noted: 

The concepts that provide for six  lanes along Punt Road provide considerable flexibility in terms of the operation of the network.  For example, the capacity that  is added  to Punt Road under  the  six  lane  concepts  could be utilised  to provide a balance of  improved north‐south  travel as well as promoting east‐west  travel  across  the  corridor  for  key  public  transport  movements.  Alternatively, there would be opportunities to provide added public transport or bicycle priority on parallel routes such as Chapel Street and St Kilda Road as a result of the reduction in traffic demands on these routes. 

Mr Humphreys summarised the VITM estimates of public transport patronage  in his expert report.  He noted that the six lane options (Concepts 5, 6 and 7) could be expected to attract an  increase  in patronage of 22 per cent over  the  ‘do‐nothing’ scenario.   VITM predicts no additional demand generated by Concept 7 (exclusive bus lane) compared to Concepts 5 and 6,  however Mr Humphreys  gave  evidence  that  the  introduction  of  SmartBus  bus  priority measures and increased reliability would be likely to increase patronage considerably. 

VicRoads  and  PTV  submitted  that  the  Route  246  bus  service, which  operates  along  Punt Road‐Hoddle Street from St Kilda Junction to Clifton Hill, is an important service, providing a cross town linkage and connections to a range of employment, education, sporting and retail destinations.  The service currently caters for approximately 1.5 million passenger boardings per annum.  VicRoads submitted that the route reduces the need for users to travel in to the City and out again to reach their destination.   Current trip times and reliability on the 246 route are highly variable with travel times from St Kilda Junction to Clifton Hill varying from as low as 18 minutes off peak to as high as 40 minutes during the peak.  The service operates every  ten minutes during  the peak.   PTV advised  that  it  is  intended  to ultimately  increase frequency to five minutes  in the peak.   PTV and VicRoads submitted that  it  is  important to protect options to improve public transport travel times and reliability and encourage mode shift from private vehicles to public transport. 

Ms Murphy, on behalf of the residents of Northampton Place, supported  improvements to route 246, although, as pointed out by VicRoads, does not support a separate bus  lane or bus jump lanes. 

Other  submitters,  including Drop  Punt,  submitted  that  the  route  246  bus was  of  limited value, effectively running parallel to the Sandringham rail  line along the Punt Road section.  Drop Punt also submitted that other major destinations within the Punt Road corridor such 

Page 83: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 77 of 162 

 

as Wesley College and the Alfred Hospital ere well served by tram routes along St Kilda Road.  Drop Punt submitted that upgrading the 246 route does not justify the economic, social and environmental cost of widening Punt Road. 

Mr and Mrs Allatson submitted that the  likelihood of a significant modal shift to the route 246 bus  is highly questionable.   They submitted that the majority of vehicle traffic on Punt Road is destined for the City and so the 246 bus does not provide a substitute for such trips. 

In  response,  PTV  provided  more  detailed  information  on  route  246  boardings34,  and highlighted  boarding  numbers  supporting  the  importance  of  the  route  in  accessing  the Richmond Railway Station, Swan Street and  the Alfred Hospital and other key  stops along the route. 

There  was  general  agreement  from  all  parties  that  use  of  public  transport  should  be prioritised over use of private cars.  VicRoads, PTV and Melbourne Council all submitted that increased  road  capacity  (through widening  or  other  improvements)  ought  to  be  used  to improve  conditions  for  public  transport  along  and  across  Punt Road.   Melbourne Council submitted  that  care needed  to be  taken  to  ensure  that  additional  road  capacity was not simply  taken up by more car  trips and planning should ensure  that public  transport  is  the main beneficiary.  Melbourne Council submitted that “it supports an ultimate solution which includes a bus/multi passenger vehicle lane.”35 

(ii) Discussion 

The Committee believes that Concept 5 and the Modified Concept 5 provide the opportunity for bus  jump  lanes and would  improve bus reliability considerably.   The ability for buses to utilise the left‐turn approach lane and be provided with a bus‐stop on the departure side of the  intersection  is  a  significant  benefit  operationally.    The  Committee  believes  that  the Modified Concept 5 is as effective as Concept 5 in this regard. 

The Committee was not convinced that an exclusive bus lane (Concept 7) is justified for such small bus numbers.   Even  in  the  future at  five minute headways,  there would only be 12 buses per hour in each direction. 

The  Committee  agrees  that  the  scope  for  substantial mode  shift  to  the  route  246  bus  is limited.    The  route  fills  a  niche market  for  users with  destinations  in  the  corridor  but  is limited in its long‐term appeal given the parallel train and tram routes and the fact that the majority of private vehicle trips along Punt Road will not easily substitute to the bus route (or other public transport mode introduced along Punt Road) along the corridor. 

   

                                                       34  Document 45 35  Melbourne Council submission – Document 13 

Page 84: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 78 of 162 

 

8.8 Cycling and pedestrian impacts and opportunities 

(i) Evidence and submissions 

Cycling 

Punt  Road  is  not  included  on  VicRoads'  SmartRoads  as  a  preferred  bicycle  route.    The Melbourne  and  Stonnington  Bicycle  Plans  do  not  show  Punt  Road  as  a  preferred  bicycle route.   Alexandra Avenue  (riverside path), Toorak Road, Commercial Road and High Street are all shown on SmartRoads as priority cycle routes. 

Melbourne City Council  submitted  that  long  term planning  should  consider provisions  for cycling, perhaps considering that powered assisted bicycles may have more of a role  in the future.  This position was supported in evidence by Mr Tivendale. 

Pedestrians 

The City of Melbourne and City of  Stonnington  submissions  raised  concerns  about  longer pedestrian crossing times if Punt Road was widened. 

Mr Humphreys,  in his evidence, agreed  that  it would  take  longer  for pedestrians  to  cross Punt Road but noted that signal cycle times would be reduced with all options that upgrade capacity,  hence  reducing  overall  delays  for  pedestrians.    He  also  noted  that  widened intersections  would most  likely  create  opportunities  to  stage  pedestrian movements  on traffic islands. 

38 of the 121 submissions received identified concerns about pedestrian safety, particularly for school children, and broader pedestrian amenity.    In many cases  it was submitted that pedestrian  safety  is  already  an  issue  in  Punt  Road  and  that  the  road  widening  options presented would  exacerbate  the  problem.    A  common  theme was  the  large  number  of school children who regularly need to cross Punt Road to access schools on the west side, and concerns about traffic throughput increasing risk, as would increased crossing times for a widened road. 

The submission from Ms Bilu refers to 6,554 school children who regularly cross Punt Road throughout the day to attend schools and use local amenities. 

The  City  of  Melbourne  made  submissions  and  introduced  expert  evidence  regarding pedestrian safety and amenity. 

While  there appeared  to be common ground between  the Council and VicRoads around a number of matters, the Council made the following statement regarding pedestrians in their submission: 

…. the analysis of the pedestrian usage of Punt Road falls well short of what ought to be expected and that more work ought to be done to ensure that any proposal  improves  the  safety  of  pedestrians  and  improves  the  pedestrian experience within the corridor. 

Mr Tivendale gave evidence in relation to pedestrian issues as follows: 

The northern end of Punt Road has very narrow (in some cases no) footpaths.  In  every  case  this  is  because  lane  width  for  private  vehicles  has  been considered  to be more  important  than adequate  space  for pedestrians.   An 

Page 85: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 79 of 162 

 

example from the south western side of the intersection of Domain Road and Punt  Road  is  shown  below.    This  footpath  does  not  meet  the  minimum standard endorsed by the City of Melbourne and is likely to be non‐compliant with the Disability Discrimination Act. 

As the intensity of residential development, commercial activity and schools in the surrounding area increases the demands on the footpath space across the whole area are increasing.  In particular there is significant need for residents on  the western  side of Punt Road  to  cross  the  road  for  their daily  shopping needs  and  residents  on  the  eastern  side  of  the  road  often  need  to  cross  in order to access education and recreation facilities (Fawkner Park and Botanic Gardens in particular). 

A  number  of  submitters,  including Drop  Punt  submitted  that widening  Punt  Road would create pedestrian  safety  issues, especially  for  school  children.   VicRoads  strongly disputed this,  submitting  that  utilising  the  PAO  creates  the  opportunity  to  design  wider,  more pedestrian friendly areas.   Ms Murphy, on behalf of the residents of 5 Northampton Place, submitted that additional vehicle traffic would increase risk for pedestrians.  She advocated for  improvements to pedestrian  infrastructure  in the  local area to encourage  local trips by foot instead of short car trip. 

The VicRoads 2012 Punt Road Study noted that: 

Pedestrian  activity  is  particularly  pronounced  at  the  Punt  Road/Moubray Street/Greville  Street  intersection  (during  school  start  and  finish  times)  and Punt  Road/Toorak  Road  intersection, with  high  pedestrian  volumes  causing delays to turning traffic. 

Crash  data  included  in  the  2012  report  for  the  period  between  1  January  2005  and  31 December 2009 noted that there were 135  injury crashes reported for Punt Road and that pedestrian  injuries represented 19 or 14 per cent of these crashes.   The report then made the comment that a “median could reduce the number of pedestrian and head‐on crashes”.    

Page 86: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 80 of 162 

 

In relation to walking and cycling, the Background Report noted: 

Any widening of Punt Road to six lanes should help facilitate enhanced bicycle and pedestrian provisions, and associated safety and amenity for these users, on the road network in the surrounding area and along Punt Road. 

In their Part A submission to the Committee, VicRoads stated: 

VicRoads and PTV accept that the implementation of any of the options needs to  be  thoroughly  considered  from  the  perspective  of  both  pedestrian  safety and amenity. 

The  submission  acknowledged  that  “a  widened  Punt  Road  would  increase  the  walking distance to cross the road; however this could be mitigated through the provision of a wide central median to protect pedestrians”. 

The  VicRoads  submission  also  stated  that  there  would  be  improved  outcomes  for pedestrians from additional elements of the road and traffic designs for the various Options including  banning  right  hand  turns  and  reducing  traffic  signal  cycle  times  at  key intersections.    VicRoads  do  not  contemplate  pedestrian  overpasses  in  the  short  term because  it would require additional  land acquisition and substantial service relocation that could only be designed when an ultimate road configuration is known. 

The  road widening  options  allow  improved width  of  footpaths  and  improved  pedestrian amenity through landscape enhancements. 

The expert evidence statement from Mr Kinghorn and Mr Carter advised: 

During any future design stages to develop a specific proposal for the corridor it is expected that the government agencies would work with the schools and the local community to improve the safety of pedestrians. 

(ii) Discussion 

Cycling 

Cycling on Punt Road  is currently severely  limited by  the  lane widths, high  levels of  traffic and  the physical difficulty of  traversing  the Punt Road hill  from Domain Road  to  the Yarra River. 

The provision for cyclists along Punt Road is unlikely to be achieved in a safe manner without the provision of a dedicated  facility.   This  is an  impractical proposition within  the corridor and there was no argument for such a proposal at the Hearing. 

The Committee believes that planning for cycling on Punt Road, particularly north of Domain Road,  should  not  be  a  priority.    Planning  should  provide  for  the  bicycle  priority  routes crossing Punt Road  at Alexandra Avenue  (riverside path),  Toorak Road, Commercial Road and High Street.    

Page 87: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 81 of 162 

 

Pedestrians 

The  issues of pedestrian safety and amenity were  raised as concerns  through a significant number of submissions and in expert evidence. 

Any final design for a road, even if the PAO is removed, would need to carefully consider the range  of  factors  that  impact  on  pedestrian  volumes  and  behaviours.    The  Committee believes  that  VicRoads  understands  the  priority  that  must  afforded  to  a  high  level  of pedestrian amenity  in developing any  final design  for Punt Road and  its  intersecting  road network. 

Pedestrian movements  along  Punt  Road  are  restricted  by  the  narrow  footpath widths  at some locations and the relatively ‘hostile’ environment so close to high traffic volumes.  This is particularly  the case at Domain Road where sub‐standard  footpath widths as  low as 1.2 metres create an uncomfortable environment for pedestrians.  The Modified Concept 5 plan includes a minor widening  in  the vicinity of Domain Road  to  facilitate  the widening of  the footpaths at this location. 

The Committee believes  that  any  long  term plans  should provide  for higher  standards of pedestrian  safety  by  providing  properly  proportioned  pedestrian  areas.   More  generous footpath  widths  that  comply  with  contemporary  standards  should  be  planned  for,  with safety barriers where appropriate. 

8.9 Impact on local streets 

Stonnington  Council  submitted  that  the  proposed  turn  bans  at  Toorak  Road,  Commercial Road  and  High  Street  would  potentially  cause  intrusion  of  traffic  into  local  streets  and necessitate  the  implementation  of  local  traffic  management  measures.    VicRoads acknowledged that local traffic intrusion is a possible side effect, and agreed that it may be necessary for Council to address any unintended impacts. 

The Committee notes however, that some of the proposed concept options provide for left and right turns at all the major intersections and therefore would not cause traffic intrusion into local streets. 

The long term management of Punt Road may involve limitation to access from local streets and restrictions on future development, however these matters have not been addressed by the Committee and are  left to the relevant planning authorities.   Local street access  issues should be carefully assessed before implementing any turn bans or other access restrictions on Punt Road or crossing roads. 

8.10 Summary of parties preferred position 

Table 4 below summarises  the position of  the submitters and  traffic experts  in  relation  to the preferred medium to long term options: 

   

Page 88: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 82 of 162 

 

Party  Medium term   Long term 

VicRoads and PTV  Concept 5  Concepts 6 or 7 

Melbourne City Council  Concept 5  Concepts 6 or 7 

Stonnington City Council  No widening  No widening 

Drop Punt and the majority of other submitters  Concept 2  No widening 

Mr Kinghorn and Mr Carter expert evidence  Concept 5  Concepts 6 or 7 and possibly 5 

Mr Higgs expert evidence  Concept 5  Concept 5 

Mr Tivendale expert evidence    Concept 6 

Mr Humphries expert evidence  Concept 5  Concept 6 or 7 

Table 4  Submitter’s and expert’s preferred concepts medium and long term 

There seemed to be general support from all parties to the Hearing that permanent 24 hour clearways (Concept 1) are a good  initiative, and there was general support for other minor improvements that could be achieved within the existing road reserve (Concept 2). 

8.11 Conclusions 

In  relation  to  the  traffic  and  transport  issues,  the  Committee  draws  the  following conclusions: 

The  short  term  introduction of Concepts 1  and 2  are  supported.    Substantial off‐peak capacity  improvements and  congestion  relief  can be achieved  through  clearways,  turn bans and other minor lane realignments. 

Concepts 3 and 4 were not considered in any detail by the Committee.  Concept 3 (with a narrow  central  median)  would  appear  to  provide  no  substantial  advantages  over Concept  2.    Concept  4  (reversible  fifth  lane) would  have  operational  challenges with limited benefits, and was abandoned by VicRoads prior to the Hearings. 

The Committee  is generally  supportive of Concept 5  (involving  substantial  intersection upgrades  and  four  lanes  midblock),  however  believes  that  the Modified  Concept  5, substantially  reducing  land  acquisition  and  not  widening  the  Hoddle  Bridge,  would achieve a similar level of corridor performance. 

The Committee was not convinced that the current traffic capacity constraints in Hoddle Street north of  the Yarra River can be  resolved and  that Punt Road between  the River and Swan Street will continue to be the main constraint on traffic. 

The Committee was not convinced that upgrading of  the Punt Road/Alexandra Avenue intersection or widening of  the Hoddle Bridge  is warranted.    This  is borne out by  the traffic  analysis  provided  to  the  Committee  which  shows  that  the  Alexandra  Avenue intersection will function satisfactorily under projected 2031 volumes. 

The Committee prefers a Modified Concept 5 that provides for additional lanes and bus priority  at each of  the major  intersections, minimises  land  acquisition  and  removal of houses, and restricts the demolition of heritage buildings to only one property. 

Although  some  expert witnesses  supported  the  retention of  the  PAO  to  preserve  the option of increasing capacity in the future, the Committee was not convinced that there was compelling evidence that a full six lane widening of Punt Road (Concepts 6 and 7) is 

Page 89: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 83 of 162 

 

justified.   Traffic projections provided to the Committee extended to 2031 and showed that Concept  5  provided  an  adequate  level  of  service  and  substantially  greater  traffic throughput,  thereby  alleviating  parallel  routes  and  providing  for more  reliable  traffic flow (for private vehicles and public transport) along and across the Punt Road corridor. 

Based  on  the  evidence  and  submissions,  the  Committee was  not  convinced  that  the merits  of  Concepts  6  or  7  (essentially  marginally  better  traffic  speeds)  justified  the extensive additional land acquisition. 

The Modified Concept 5 is the Committee’s preferred treatment for Punt Road. 

The  risk of  the Modified Concept 5 not adequately  catering  for  traffic demand on  the Punt Road corridor at least until 2031 is considered low.   

Based on its assessment of available traffic projection data, and assumptions in relation to  likely  future policy  influences,  including demand management and  improvements to the public  transport  system,  the Committee believes  that  the Modified Concept 5 will adequately cater for traffic demand in the Punt Road corridor well beyond 2031. 

The Committee was not  convinced  that  an  exclusive bus  lane  (Concept  7)  is  justified.  Even in the future at five minute headways, there would only be 12 buses per hour in the peak in each direction. 

The  design  of  future  road  widening  should make  provision  for  improved  pedestrian facilities, particularly at locations such as Domain Road were the current footpath widths are sub‐standard and at locations where high pedestrian volumes are experienced. 

Local  street  access  issues  should  be  carefully  assessed  before  implementing  any  turn bans or other access restrictions on Punt Road or crossing roads. 

Page 90: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 84 of 162 

 

9 Heritage issues 

9.1 The issue 

Whether the heritage value of properties within the PAO is an impediment to any potential widening of Punt Road; and whether the PAO is having an impact on heritage properties? 

9.2 Background 

There are 42 properties affected by the PAO that are also included within a Heritage Overlay (HO).  Of these, three have individual HO’s and the remainder are included within a precinct based HO.  A map showing the location of these properties is included in Appendix F. 

Individually listed buildings 

The  individually  listed buildings are Fawkner Mansion at 250 Punt Road, Prahran  (HO448  ‐ Level A1 Significance and includes tree controls and the iron palisade fence), Bendale at 446‐448 Punt Road, South Yarra (HO449 ‐ Level A2 Significance and includes controls in relation to the front fence) and 424 Punt Road, South Yarra (HO463 ‐ Level A2 Significance). 

Heritage precincts 

The remainder of the heritage properties are identified for the contribution they make to six heritage precincts, but have not been  identified as having  individual heritage  significance, including the A1  listed  ‘Shan Teng’; which  is Mr Allatson and Ms Warwick’s property.   The level of significance for these properties (apart from those identified as vacant) is: 

A1 ‐1 property 

A2 ‐ 16 properties 

Level B – 17 properties 

Level C – 1 property 

Ungraded (vacant) – 4 properties. 

Note  that  the exact number of properties affected  is open  to  interpretation and may vary slightly form the information tabled by VicRoads and Stonnington Council.  Any variation can be explained by differences in assumptions about subdivision or consolidation of lots. 

Heritage significance of buildings affected by the PAO 

In order  to understand  the  significance of  these buildings,  it  is necessary  to  consider  the significance classifications referred to.  This explanation is found in the Stonnington Heritage Policy36 which states: 

Gradings frequently applied in the City are: 

A1 Buildings – are of national or state importance, irreplaceable parts of Australia’s built form heritage. 

A2 Buildings – are of regional or metropolitan significance, and stand as important  milestones  in  the  architectural  development  of  the metropolis. 

B  Buildings  – make  an  architectural  and  historic  contribution  that  is important within the local area. 

                                                       36   Clause 22.04 Stonnington Planning Scheme 

Page 91: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 85 of 162 

 

C Buildings – are either  reasonably  intact  representatives of particular periods or styles, or they have been substantially altered but stand in a row  or  street  that  retains  much  of  its  original  character  and  are considered to have amenity or streetscape value. 

Significant  buildings  be  defined  as  A1,  A2  and  B  graded  buildings.  Contributory buildings be defined as C graded buildings. 

Of  the 42 heritage properties within  the PAO,  three are considered  individually significant with  one  of  those  recognised  as  having  State  significance,  39  are  considered  significant within the precinct with one of those being of State significance for the contribution it makes to the precinct; and the remaining being of regional or local significance. 

The Committee  is  aware  of  only  two  trees  identified  as  having  heritage  significance,  and these are the two liquidambar trees located at the front of the Fawkner Mansions. 

9.3 Evidence and submissions 

There were many submissions37 which raised concern about the impact the PAO is having on heritage  properties,  submitting  it  is  leading  to  the  deterioration  of  these  buildings,  and ultimately the loss of significant heritage values in the area and Melbourne.  The submitters also raised concern that any potential road widening would directly  impact on 42 heritage properties, some which have A1 and A2 heritage significance; as well as significant trees. 

The submissions emphasised that heritage properties “are an important visual reminder and record of Melbourne’s architectural history and the evolution of  life  in this city.   The  loss of these  places  can  never  be  recovered38”.   Mr  Carrasco  submitted  that  in  the  twenty  first century, many cities are jealously guarding their cultural and architectural heritage primarily for its own sake, but also as a major draw card for international tourism.  He submitted that “one of the reasons Melbourne is not more of a tourist destination is that the extraordinary Victorian era architecture  it once had has  systematically been wiped out  for  short  sighted endeavours such as widening roads39”. 

Particular  reference was made  to  two significant properties which are considered of State Significance.  These include Shan Teng40, which the Committee was advised is an A1 heritage home built in 1926 by Australian Architect Arthur Purnell, and includes a distinctive ‘temple‐style’ roof which was a tribute to his love of oriental architecture; and Fawkner Mansions41, which is the oldest residential flats in Stonnington, and one of the oldest in Victoria, built in Melbourne in 1910. 

The  owners  of  Shan  Teng, Mr  Allatson  and Ms Warwick,  acknowledged  they  bought  the property with the full knowledge that  it was  included within the PAO, but did so based on advice from VicRoads that the widening was unlikely to proceed.  They submitted that they have significantly  renovated  the property since purchasing  it, however,  the  roof  is beyond repair  and  maintenance  and  in  need  of  specialist  restoration  which  would  cost approximately  $200,000.    They  explained  how  they  had  sought  and  received  in‐principle 

                                                       37  Submissions 8, 10, 44, 54, 59, 63, 67, 70, 77, 86, 95, 97, 98, 99, 101, 105, 112, 115, 119 and 121. 38  Submission 10 ‐  Mr Bilu and Submission 59 ‐ Ms Berry 39  Submission 63 – Mr Carrasco 40  490‐492 Punt Road, South Yarra 41  250 Punt Road, Prahran 

Page 92: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 86 of 162 

 

support  for a heritage grant  to  restore  the  roof, however, because of  the PAO  they were disqualified. 

Mr Heydon submitted that his dwelling  is one of five early Howard Lawson buildings along Punt  Road  which  is  significant  as  it  was  a  precursor  for  Lawson’s  future  dramatic development  of  Alexandra  Avenue.    He  emphasised  the  importance  of  retaining  these properties. 

Ms Phillips also highlighted  that  there are number of dwellings on  the Punt Road Hill  that were once previously occupied by significant Australian artists or leading Melbourne citizens, some which had already been demolished.   She submitted that “bulldozing more historical homes that add value and enrichment to our society is short‐sighted and neglectful.” 

A number of submissions also raised concern that any proposed road widening would result in the removal of significant vegetation; and in particular mature trees, which would result in the loss of heritage values, as well as visual amenity. 

The submissions emphasised that not only would any potential widening of Punt Road have a  direct  impact  on  these  properties,  but  so  does  retention  of  the  PAO,  as  it  acts  as  a disincentive for property owners to either restore or maintain their properties because they are unsure whether they will ever be acquired for road widening purposes, and if so when.  They  also  raised  concern  that  if  they were  to undertake  any  restoration or maintenance, whether they would be compensated for this if and when the property was acquired.  They emphasised this has  led many people to almost abandon their heritage properties,  leaving them to fall into disrepair and almost neglect. 

Mr  Kelder  also  submitted  the  PAO  has  unintentionally  preserved  a  unique  collection  of heritage buildings along Punt Road. 

Melbourne City Council  submitted  that new Aboriginal Heritage  sites had been  identified since the 2010 Heritage Study, which was not reflected in the Arup Report. 

Ms Forsyth stated that VicRoads acknowledges that widening of Punt Road will result in the demolition of buildings which are recognised as having heritage significance, but submitted that conflict between the retention of the heritage fabric and the provision of infrastructure is  one  of  the  natural  tensions  that  arises  in  planning.    She  submitted  that  the  heritage impacts are not overwhelming having regard to the  fact that there  is only one  individually listed A1 graded building within the overlay; and even that building has not been accepted for registration on the Victorian Heritage Register. 

In terms of Aboriginal cultural heritage, Ms Forsyth submitted that whilst part of the PAO is within 200 metres of a waterway and therefore of cultural heritage sensitivity,  it has been significantly disturbed and is therefore not of cultural heritage significance. 

In his evidence, Mr Milner acknowledged the potential road widening would affect heritage properties  and  accepted  these  are  legitimate  concerns,  but  said  this  is  one  of  the many issues  that  needs  to  be  considered  in  the  choice  of  options  and  determining where  the greatest community benefit lies. 

Page 93: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 87 of 162 

 

9.4 Discussion 

The impact of road widening options on heritage properties 

Whilst  it would be the Committee’s preference that no heritage properties be  impacted by any  future  road  widening,  the  Committee  agrees  with  Mr  Milner’s  evidence  and  Ms Forsyth’s  submissions  that  one  of  the  challenges  of  planning  is  balancing  competing objectives,  and  two  of  these  objectives  are  protecting  heritage  values  and  the  need  to provide infrastructure to meet the needs of both present and future generations. 

Whilst  the  conservation  and  enhancement  of  buildings  which  are  of  architectural  or historical interest is an objective of planning, so too is the need to protect public utilities and other  assets;  to  enable  the  orderly  provision  and  co‐ordination  of  public  utilities  and facilities for the benefit of the community; and ultimately, the need to balance the present and future interests of all Victorians. 

The  SPPF42  clearly  states  that  conflicting  objectives  should  be  balanced  in  favour  of  net community  benefit  and  sustainable  development  for  the  benefit  of  present  and  future generations. 

Concepts  1  –  4  would  have  the  least  impacts  as  they  would  not  affect  any  properties; Concept 5 would affect nine heritage properties and five heritage buildings and Concepts 6 and 7 would affect 40 heritage properties and 34 heritage buildings.   

The Modified Concept 5 would affect seven heritage properties and one heritage building, the Acadia Hotel.   

Clearly,  Concepts  6  and  7  would  have  the  greatest  impact  on  heritage  properties  and buildings, with Concept 5 and  the Modified Concept 5 having a  relatively minor effect by comparison.  The most significant difference between Concept 5 and the Modified Concept 5 is that Concept 5 requires the demolition of the Fawkner Mansions, whereas the Modified Concept 5 does not. 

If part or all of the PAO is required to facilitate road widening, the Committee is satisfied the improvements  to  be  achieved  to  the  overall  transport  system would  likely  outweigh  the potential  impacts  on  heritage  properties,  and  would  therefore  have  a  net  community benefit. 

In  terms  of  the  Modified  Concept  5,  whilst  the  Fawkner  Mansions  would  not  require demolition, the removal of the two liquidambar trees and the front fence would be required.  Whilst these are the only two trees along Punt Road with heritage significance, based on the Committee’s  inspection, they appear to be significantly compromised as a result of pruning around power  lines.    The Committee  considers  that  it may be  an  acceptable outcome  to remove  them;  however,  the  Committee  acknowledges  this would  need  to  be  considered further  in  the detailed design of  this option.   The Committee  recognises  that  this balance could  change  with  the  passage  of  time;  and  such  an  assessment  would  need  to  be undertaken at the time when a definite proposal is being considered. 

Based  on  the  limited  significance  of  the  heritage  properties  affected  by  the  PAO,  the Committee believes  that,  regardless of which  road widening concept  is ultimately chosen, 

                                                       42  Clause 10.04 – Integrated decision making 

Page 94: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 88 of 162 

 

the balance is likely to be in favour of widening the road.  In other words, the significance of the  heritage  properties  in  Punt  Road  is  not  such  that  it would  outweigh  the  community benefit of widening  such an  important  road.   The Committee  therefore does not consider the potential  impact on  the heritage properties  is a determinative matter  in deciding  the future  of  the  PAO  at  this  time,  and  the  decision  should  be  made  based  on  other considerations. 

Impact of the PAO on heritage properties 

As it is the role of this Committee to consider whether the PAO should be retained, modified or  removed,  the other question  for  this Committee  is whether  the PAO  itself  is having an adverse  impact  on  these  heritage  properties,  as  opposed  to  the  road  widening  options presented. 

The Committee notes the concerns raised by submitters related to owners’ unwillingness to invest  in renovating or maintaining these properties, not knowing whether they would one day be demolished to make way for a road widening.  The Committee does not consider this issue,  however,  is  exclusive  to  heritage  properties  as  it was  a  common  theme  amongst submissions. 

In terms of direct impacts, the Committee agrees with Mr Allatson and Ms Warwick, that for them  the  PAO  has  had  a  direct  impact  on  their  ability  to  fund  the  restoration  of  the significant roof using grant money.  Whilst the Committee empathises with Mr Allatson and Ms Warwick,  and  accepts  that  this  is  a  direct  impact,  it  considers  this  to  be  a  relatively isolated case. 

The Committee also agrees with the submissions made by Mr Kelder that the PAO may have also  had  an  unintentionally  positive  impact  on  these  heritage  properties  by  limiting  new development  along Punt Road,  thereby preserving  these heritage buildings.    If  it had not been  for  the PAO, given  the Residential Growth Zone  (RGZ) on  the  land and  the  strategic directions  in  the  Stonnington  Planning  Scheme,  the  Committee  considers  it  likely  there would have been more significant redevelopment along the east side of Punt Road resulting in  the  demolition  of many  of  these  heritage  dwellings.    For  this  reason,  the  Committee considers  that  any  potential  road  widening  is  not  the  only  potential  threat  to  the preservation  of  these  heritage  properties;  and  considers  potential  redevelopment  could have  an  equally  significant  impact  and  potentially  a  more  immediate  impact  than  any proposed road widening. 

The Committee considers  it  important  to  recognise  that not only are  the owners of  these dwellings acting as custodians of a future community asset, they also have the dual role of also acting as custodians of properties with heritage significance.  For this reason, if part or all  of  the  PAO  is  not  intended  to  be  used  in  the  short  or medium  term,  but  rather  is identified as a  long  term strategic option,  the Committee considers  it  important  to enable owners  to maintain  these  properties  to  ensure  they  do  not  fall  into  disrepair;  therefore ensuring these heritage values are not lost. 

In  these  circumstances,  the  Committee  considers  that  a more  co‐operative  arrangement between VicRoads and the owners of properties identified as long‐term could provide more certainty  for owners and VicRoads, and ensure  that  these heritage  values are maintained and enhanced in the meantime. 

Page 95: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 89 of 162 

 

In  terms  of  Aboriginal  Heritage,  based  on  Ms  Forsyth’s  submission,  the  Committee  is satisfied that the area within the PAO which is likely to have the greatest sensitivity has been altered to such an extent that there are unlikely to be any sites of significance. 

9.5 Conclusions 

The impact of road widening options on heritage properties 

The  Committee  concludes  that  whether  any  future  impacts  on  heritage  properties associated with a widening of Punt Road would be acceptable needs to be assessed once a preferred option is selected.  This would require an assessment of whether the greatest net community benefit for present and future populations is achieved by the protecting heritage properties or providing improved transport infrastructure, or a combination of both.  That is a decision for a later date. 

The Committee is satisfied, however, that improvements to the transport system associated with  the Committee’s Modified Concept 5 are  likely  to have a net community benefit and justify the relatively minor impacts on the heritage properties. 

If some properties are identified as required to be retained in the PAO long term (15+ years), the Committee considers that VicRoads should adopt a more flexible arrangement towards allowing restoration of heritage properties within the PAO.  The Committee believes it would be helpful to develop guidelines to clearly identify the range of works that may be permitted and any conditions that would apply, to facilitate the protection and enhancement of these values in the meantime. 

Impact of the PAO on heritage properties 

The Committee also concludes  that  the PAO may be having a positive  impact on heritage properties  within  the  PAO  as  it  is  indirectly  protecting  these  sites  from  further,  more substantial development. 

Page 96: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 90 of 162 

 

10 Environmental issues 

10.1 Impacts on the Yarra River 

(i) The issue 

Do the potential impacts on the Yarra River and its environs create an impediment to future road widening? 

(ii) Evidence and submissions 

The Drop Punt submission stated that: 

The  Yarra  River  will  be  heavily  polluted  by  freeways  run‐off  and  debris, including motor oil, chemical  from  tyres, petrol and diesel  fuel  leakage  from the extra freeway lanes on Hoddle and Swan Street Bridges. 

A number of individual submissions picked up on the themes of pollutant run‐offs and debris as advanced in the Drop Punt submission. 

The City of Stonnington submission stated that: 

A  key  natural  feature  of  the  City  of  Stonnington  is  the  Yarra  River  which provides opportunities for increased biodiversity, riparian habitat linkages and community interaction with a natural environment. 

The  submission  then  detailed  the  range  of  policy work  and  adopted  strategies  both  at  a State and local government level to protect and improve the river.  The Council summarised their position in relation to the river when it stated: 

Council  submits  that  although  the  final  and  detailed  layout  of  the  various options is not decided, it can be safely assumed that any degradation or loss of native  vegetation  and  open  space  or  significant  trees  along  the  Yarra River and private properties in Punt Road is inconsistent with Council’s policies 

The City of Melbourne raised concerns over  impacts on the river and  its biodiversity values through  the  potential  widening  of  Alexandra  Avenue.    The  expert  evidence  statement regarding  open  space  issues  by  Mr  Shears  addressed  the  issue  of  the  potential  road widening impacts: 

This  concept proposes acquisition of public  land between Alexandra Avenue and the Yarra River to facilitate a displaced right turn from Alexandra Avenue into Punt Road.    I do not  consider  the widening of Alexandra Avenue  to be appropriate because this concept would lead to a loss of open space along the natural banks of the Yarra River. 

The green space of the Yarra River reserve  is a significant  landscape element and recreational area of the Yarra River corridor.   This road treatment would negatively affect the function and amenity of the Capital City Trail, one of the city’s primary recreational walking and cycling routes.  This area of river bank is  also  one  of  the  few  places where  people  can  get  close  to  the  river  and engage with it. 

Page 97: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 91 of 162 

 

It would also  seriously degrade  the general amenity and environment along the river bank and detrimentally affect the biodiversity role of the Yarra River corridor.  This section is the only side of the Yarra that has a green bank, and reducing this would have serious environmental implications. 

For its part, VicRoads did not make detailed submissions regarding the potential impacts on the  river  environment  that  may  result  from  any  proposed  intersection  treatment  that widens Alexandra Avenue  to  the east of Punt Road,  submitting  the proposed  intersection design is only conceptual at this stage.  VicRoads’ preferred position is that the PAO remain in place to allow future road widening on Alexandra Avenue to take place on the south side, that  is,  the  side  covered  by  the  PAO.    VicRoads  maintained  in  its  submission  that  the Alexandra  Road/Punt  Road  intersection  treatment will  need  to  occur  irrespective  of  any widening of Punt Road. 

VicRoads sought to address the concerns expressed by the City of Melbourne by  indicating that  retention of  the PAO would offer greater protection  from  future pressure  to use  the river bank to accommodate a widened road; stating: 

In so  far as the City of Melbourne’s argument about the  importance of open space  is  concerned,  it  is  important  to  retain  the  PAO  in  the  vicinity  of Alexandra Avenue / Dobson Street in order to maximize the opportunity for a solution that minimises  impacts on public open space.    In other words,  if the PAO was removed, then the cost of acquiring  land to the south of Alexandra Avenue would increase, and therefore so would the pressure to utilize the river bank. 

Once  again,  VicRoads will work with  the  council  at  the  relevant  to  time  to determine the most appropriate treatment for that intersection having regard to both transport and public space objectives.  However, the impacts on public open space are not a reason to remove the PAO.   The evidence points to the contrary. 

There was  no  submission  or  evidence  regarding  how  an  expanded  river  crossing may  be achieved if the PAO were exercised. 

(iii) Discussion 

The fact that Punt Road crosses the Yarra River over the existing Hoddle Bridge creates the potential for impacts on the river and its environs. 

The Committee notes that Concepts 5, 6 and 7 propose to widen the river crossing, however, the precise nature of how this would be achieved (for example, a widening of the heritage Hoddle Bridge or a  separate bridge) was not detailed.   These  three Concepts also  include proposals  for separating  turning  traffic between Punt Road and Alexandra Avenue, east of Punt Road,  to  improve  intersection  functionality.    This  is described  as  a  ‘continuous  flow intersection’.  On the preliminary designs provided, these separating traffic solutions would necessitate  the widening  of  the Alexander Avenue  road  east  of  Punt  Road  to  potentially encroach on the immediate environs of the river and could result in vegetation removal. 

A  further  supplementary  concept  to  some  of  the  Concepts  initially  advanced,  but subsequently withdrawn by VicRoads, provided for the widening of Alexander Avenue west 

Page 98: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 92 of 162 

 

of Punt Road and the construction of a new bridge  just east of the existing historic Morrell Bridge. 

The Committee notes the potential intersection treatment that affects Alexandra Avenue is only broadly  conceptual  at  this  stage, however,  the preliminary design  clearly  appears  to impact  on  the  river  bank  environment.    Despite  comments  that  the  PAO  reservation,  if retained, would alleviate pressures for the river bank to be used for a future road widening it is evident that the preliminary design for the ‘continuous flow’ concept extends significantly further east along Alexandra Avenue, well past where the PAO ends.  Therefore, in the view of the Committee there would be continued pressure to encroach on the river bank which the Committee considers to be highly undesirable. 

The recent changes to the State Planning Policy Framework supports the stronger protection of the Yarra River and its riparian environment and any proposal to affect the river bank to accommodate a widened road would be at odds with the  improved river protection and so would have  to have a very high  standard of  justification.   For  this  reason,  the Committee would  not  be  supportive  of  any Option which  sought  to  encroach  further  north  into  the Yarra  River  embankment  that  would  lead  to  removal  of  vegetation  or  compromise  the cycling/pedestrian pathway along the river. 

Further,  as  discussed  elsewhere  in  this  report,  the  Committee  is  not  convinced  that increasing  traffic  capacity  through  the  Alexandra  Avenue/Punt  Road  intersection  is warranted. 

The Committee notes that the main  impacts regarding a widened Alexandra Avenue would be outside the PAO reservation and so does not fully form part of the Committee charter to review the Punt Road PAO.   However, the  interrelationship between a potentially widened Punt  Road  and  the  concept  for  widening  Alexandra  Avenue  to  deal  with  overall  traffic congestion are evident. 

The Committee does not consider that the additional run‐off created by an expanded Punt Road  to  six  lanes  instead  of  the  current  four  lanes  could  not  be  adequately  dealt with through the final design process. 

(iv) Conclusion 

The  Committee  concludes  that while  there may  some  issues  regarding  additional  run‐off from  a widened  road  the  impacts  are not  so  significant  as  to be  a  substantive  reason  to remove or modify the PAO. 

The  Committee  does  not  support  any  concept  that  adversely  affects  the  banks  or  the riparian environment of the Yarra River. 

   

Page 99: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 93 of 162 

 

10.2 Air quality and noise 

(i) The issue 

Do the potential impacts regarding air quality, noise and vibration create an impediment to future road widening? 

(ii) Evidence and submissions 

The Christ Church Grammar School raised concerns about “the  increased pollution/noise  in the area that would result as a direct consequence of an increase in traffic on Punt Road and the  risks  that  this  raises  for  the  safety  and  wellbeing  of  our  School  community.”    The submission referred to classrooms that face onto Punt Road and their concern for students and teachers arising from increased air pollution; and damage to school buildings that would result  from  air  borne  pollution.   Mrs  Jones,  the Headmistress,  submitted  the  school  had measurements  for  air  pollution  that  showed  the  levels were  already  close  to  risk  levels, although  these  measurements  were  not  tabled;  and  not  subsequently  received  by  the Committee. 

Tract  Consultants,  on  behalf  of  residents  of  5  Northampton  Place,  South  Yarra,  made submissions in relation to noise, pollution and vibration stating: 

Residential  areas  in  proximity  to  Punt  Road  are  currently  subject  to  traffic vibration  impacts,  noise  and  pollution.    The  substantial  increase  in  traffic anticipated  under  Concept  Options  5‐7  will  generate  increased  noise  and emissions that would further  impact residents of the area, particularly during the construction phases. 

The counter approach is articulated in the Public Transport Guidelines for Use and Development 2008 (State Government of Victoria): 

“Designing our towns and activity centres to accommodate public transport services,  infrastructure and  facilities will have additional benefits  such as reducing air and noise pollution and road traffic congestion, so as to create more vibrant, walkable town centres”. 

There is little acknowledgement in the available material of the impact on air quality associated with  increased vehicle movements  in this highly residential location.   The expert evidence statement from Mr Milner simply puts faith  in ‘future  technologies’  to  address  this  important  planning  consideration.    The (subject  properties)  are  each  fully  attached  along  their  sides  and  rear boundaries.  This means that the properties that face west have no alternative means of ventilation, aside from their Punt Road frontage. 

The submission from Dr Lovell questioned the lack of data held by VicRoads in relation to air quality  along Punt Road.   Regarding  the use of  the Air Quality  Screening  Tool  (AQST), Dr Lovell  queried  the  inputs  concerning  traffic  volumes  and  suggested  that  there would  be value in having an independent expert evaluate VicRoads’ AQST modelling and the validity of the inputs assumptions and the application of the tool. 

The Drop Punt submission addressed the negative health impacts for the community and the contribution to air pollution that would arise from a widened road.  The submission referred 

Page 100: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 94 of 162 

 

to  a  2005 World  Health Organization  (WHO)  report  into  the  health  effects  of  transport‐related air pollution being  similar  to  the death  rate of  the  road  toll  in Europe.   The WHO report  was  said  to  have  made  references  to  urban  development  in  Australia  and  the transport  impacts on public health,  including exposure  to particle matter which has been associated with increases in mortality and cardiovascular and respiratory diseases. 

The  City  of  Stonnington  submission  identified  the  significant  detrimental  impact  on  the community arising from a 65 per cent increase in traffic volumes under the Option 7 in terms of: 

a) Additional noise created by more vehicles; 

b) Extended periods of noise  created by more  vehicles utilising  the  road  for longer periods due to the increased capacity and potential efficiency; 

c)  Air quality resulting from the increased traffic; 

… 

The City of Stonnington queried the rigour in the modelling in the Air Quality Screening Tool used  by  VicRoads  in  demonstrating  that  air  quality  in  a  widened  Punt  Road  would  be satisfactory, using the gradient in Dobson Street as an example. 

VicRoads  made  substantial  submissions  regarding  air  quality  and  noise.    It  provided  a detailed account of the methodology that had been used to assess air quality  issues under the various Concepts, excepting the discarded Concept 4, advising: 

The  VicRoads  Air  Quality  Screening  Assessment  Tool  (AQST)  has  been developed in consultation with the Environment Protection Authority to assess road projects for compliance against the State Environment Protection Policy (Air Quality Management)  (SEPP(AQM))  using  a worst  case  approach.    The tool  is used to determine whether the air quality component of the project  is satisfied or alternatively whether further evaluation in the form of detailed air quality impact assessment is warranted. 

VicRoads submitted that the screening tool had assessed the six Concepts, on a worst‐case basis, and after applying a range of reasonably conservative assumptions, stated: 

In conclusion, the Air Quality Assessment predicts that air quality effects from the  Project's  operational  phase will  be  below  the  intervention  level  criteria specified in SEPP (Air Quality Management). 

In  additional  documents  supplied  to  the  Committee  regarding  air  quality,  VicRoads acknowledged  that motor  vehicle emissions  are  the  largest  contributor  to  air pollution  in Melbourne.  It stated that at the planning stage: 

Each road project is required to characterise the influence of traffic generated emissions on the near‐road environment, taking into account the relationships of meteorology and traffic type, volume and speed. 

VicRoads provided the single page summary report sheet from the AQST Workbook for each of the 6 assessed concepts that ranged from traffic increases of 30 per cent by 2031 (1, 2 and 3),  60 per  cent  (Option  5)  and  65  per  cent  ‐  70 per  cent  (Concepts  6  and  7).   All  sheets 

Page 101: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 95 of 162 

 

demonstrated  an  Assessment  Status  of  Pass  on  a  Fail/Pass  scale  for  the  six  Concepts assessed. 

VicRoads responded to the Committee’s request for  information on existing conditions and trends in air quality and noise caused by traffic on Punt Road, or comparable arterial roads, by advising that the monitoring of air quality is undertaken by the EPA, but assessing trends over time “is a complex area and is beyond the scope of VicRoads’ capacity at this Committee hearing.” 

In  reply,  VicRoads  dismissed  any  comparison  between  air  pollution  in  Francis  Street, Yarraville and a widened Punt Road, identifying the low level of truck traffic in Punt Road as a major difference. 

In relation to noise, a number of submissions raised concerns over the problems of increased noise  levels arising  from a widened Punt Road.   This was often  raised  in association with anticipated  increased  levels  of  airborne  pollution.    Comments  included  concerns  that increasing  road  capacity  would  “only  achieve  minor  travel  time  improvements,  but  will expose nearby residents to increased noise and air pollution …” 

The VicRoads submission noted  that “Punt Road  is already a noisy  road,” however, stated that owners bought with the knowledge that the property they were buying was on a major road.  VicRoads accepted that if the road is widened under Concepts 5, 6 or 7, properties on the east side would be potentially exposed to traffic noise by the removal of buildings under the  PAO,  but  submitted  that  if  that were  the  case,  the  VicRoads Noise  Reduction  Policy would apply, which states: 

Where  arterial  roads  or  freeways  are  built  on  new  alignments,  or  where existing  arterial  roads  or  freeways  are widened  by  two  or more  lanes  and buildings  previously  protected  from  traffic  noise  are  exposed  by  removal  of buildings  required  for  widening,  the  traffic  noise  will  be  limited  to  the objectives  set  out  below  or  the  level  that would  have  prevailed  if  the  road improvements had not occurred, whichever is the greater. 

VicRoads advised  it has not undertaken any modelling to determine  if any noise mitigation measures  would  be  required  and  advised  that  this  would  done  at  the  time  of  detailed design.    The  range of mitigation measures  include  acoustic walls or noise  attenuation on individual buildings. 

VicRoads stated that because most of the buyers have purchased their properties since the PAO was put  in place they are aware of the  long term strategic plan for the road.   Further, there  would  be  opportunities  for  redeveloped  properties  under  a  future  widened  road option to have a design response to the new acoustic environment. 

(iii) Discussion 

The Committee notes  the processes utilised by VicRoads  in  the preliminary assessment of likely  motor  vehicle  emissions  through  the  VicRoads  AQST  under  the  various  Concepts considered and consequent negative impacts for air quality.  The Committee is satisfied that air quality issues would be properly investigated and responded to at the final design stage for any proposed road project and can be adequately resolved.  While there was substantial anecdotal  evidence  about  the  increased  levels  of  air  pollution  that would  result  from  a 

Page 102: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 96 of 162 

 

widened Punt Road, even with views that the existing levels are above acceptable standards, there was no evidence before the Committee that the  impacts from  increased traffic flows would impair air quality to negatively affect public health. 

The Committee does not believe that there was sufficient adverse evidence to suggest that the  potential  for  increased  air  pollution  from  a widened  Punt  Road  should  result  in  the removal of the PAO on this ground. 

The  Committee  accepts  that  Punt  Road  is  noisy  although  the  low  level  of  heavy  vehicle traffic  does mean  the  noise  environment  is  generated mainly  from  light motor  vehicles.  There has been no suggestion  that  the  role of Punt Road will change  from  that of arterial road  and  so  it  will  remain  a  heavily  used  thoroughfare  with  associated  noise.    The Committee  notes  that  the  evidence  provided  by  VicRoads  shows  that  there  will  be  an increase  in  Punt  Road  traffic  as  a  result  of  the  introduction  of  clearways  that will  likely increase the ‘base level’ of noise and vehicle emission. 

It  is further noted that VicRoads has a clear obligation to ensure that with the advent of a widened  road  that  it  has  a  responsibility  to  implement  noise  attenuation  measures  to respond to increased noise impacts. 

(iv) Conclusion 

The Committee concludes  that VicRoads can satisfactorily  respond  to additional noise and air quality issues that might arise from a widened Punt Road and so this does not represent a reason to remove the PAO. 

10.3 Stormwater management 

(i) The issue 

Do the impacts of stormwater management create an impediment to future road widening? 

(ii) Evidence and submissions 

Some  references were made  in  submissions  regarding  increased  stormwater  that would result  from a widened Punt Road and  its effective  future management.   No evidence was introduced that specifically dealt with the issue of stormwater. 

(iii) Discussion 

The Committee does not consider stormwater management as an issue that might affect any decision  regarding  the  future  of  the  PAO.    The  Committee  is  confident  that  stormwater management would be fully and properly taken into account in the engineering assessment in any final design process for a widened road. 

(iv) Conclusion 

The Committee concludes the stormwater management  is not as an  issue that might affect any decision regarding the future of the PAO. 

Page 103: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 97 of 162 

 

10.4 Tree removal 

(i) The issue 

Does the potential removal of trees create an impediment to future road widening? 

(ii) Evidence and submissions 

A  number  of  submissions  from  local  property  owners  and  residents,  as well  as  the  two Councils,  raised  concerns  regarding  tree  removal  and  the  loss  of  mature  trees  and established gardens that would occur as a result of  the widening of Punt Road. 

The Drop Punt submission stated: 

Throughout the  length of Punt Road east, there are many significant, mature trees, some aged 100 years or more.  The trees provide: 

a calming, friendly ambiance to neighbourhood; 

filter air and noise from the  road traffic emissions; 

essential shade and shelter to pedestrians 

The  submission  from Ms  Bilu  referred  to  “40 magnificent  trees  of  significant  age/or  size along the east‐side of Punt Road and many wonderful established gardens.  Uprooting trees and gardens to replace them with concrete and tar (will) adversely impact on the community spirit and have detrimental effect on the air, noise, light and temperature of the local area.” 

The  City  of  Stonnington  drew  the  Committee’s  attention  to  local  policies  in  its  Planning Scheme regarding  ‘Biodiversity’ and  ‘Significant trees and  landscapes’ that  identified a  ‘key issue’ of “Acknowledging  the  importance of significant  trees  in both  the public and private realm  for  their  contribution  to  habitat  and  amenity”  and  include  strategies  that  seek  to protect  significant  trees  on  private  property  and  opportunities  to  increase  and  replace significant  trees.   Council  advised  that  a  Significant Tree Register has been established  as part of the implementation of the strategies and specifically identified the two Liquidambar trees  in the grounds of the Fawkner Mansions heritage property.   Further, Council referred to  its  Street  Tree  Strategy  ‘Turning  over  a  new  leaf’  that  looked  at  street  trees  within Stonnington, yet did not identify any priority street trees in Punt Road.  The Council advised that  the  current  uncertainty  around  the  PAO  has  meant  the  Council  has  not  invested resources  in  the  street environment,  including  street  tree planting,  that may be  removed with a future widening of Punt Road. 

The City of Melbourne’s horticultural evidence from Mr Shears addressed the  loss of street trees on Punt Road, and other adjoining cross streets, that would result from proposed road widening options and which may  limit potential  street  tree planting  if  the already narrow footpaths are further narrowed. 

In  relation  to  street  trees and  landscaping opportunities  for a  future Punt Road, VicRoads stated  that “There are  some  scattered  trees on  the eastside of Punt Road within  the  road reserve  and  limited  plantings  within  private  property  boundaries.    …    There  is  little opportunity for roadside  landscaping along the existing Punt Road due to the narrow width of the existing reserve and narrow shared path on either side.”  It advised that as there is no road widening proposed under Concepts 1, 2 and 3 there would be “little or no landscaping opportunities” if any of these Concepts are adopted.  VicRoads advised Concept 5 would only 

Page 104: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 98 of 162 

 

allow  some  landscaping  improvements  around  the  approaches  to  intersections,  but  no improvements are possible  in the midblock areas, whereas Concepts 6 and 7 offer the best options for landscape improvements, stating: 

A more  substantial  landscaped  centre median  and wider  roadside width  on both sides of Punt Road  is potentially achievable  for concepts options 6 & 7.  These additional landscaping areas would create opportunities for significantly enhanced  landscaping  improvements  from  the existing conditions potentially including boulevard treatment. 

In relation to trees and vegetation within the PAO, VicRoads stated “There are a number of small, medium and large trees within the public acquisition overlay, the majority of which are located on private property”.  The Concepts that do not utilise the PAO would not impact on these trees, however, Option 5 would result some trees being removed as this option only upgrades major  intersections, whereas Concepts 6  and 7  “would  result  in  the majority of these trees within the PAO being removed as they would not be suitably  located within the future central median or roadside verges, nor would they be likely to survive construction.” 

(iii) Discussion 

The Committee agrees that the current street environment along Punt Road, particularly on the east side, presents poorly and the absence of street trees contributes to this quite stark, unadorned  urban  environment.    The  narrowness  of  the  footpaths  provide  limited opportunities  to  undertake  street  planting  in  the  existing  road  reservation,  however, certainty  regarding  the  future of  the PAO would enable Stonnington Council  to undertake landscape  improvements  including  street  tree  planting  and  enhanced  public  amenity facilities. 

In  relation  to  trees  and  other  vegetation  in  private  gardens,  whilst  the  Committee acknowledges how strongly submitters value  the direct and  indirect benefit of  these  trees and  gardens  and  that  some  of  these  trees  have  been  identified  on  the  Significant  Tree Register, the Committee does not consider the future of these trees would be a determining factor when considering the future of the PAO. 

The  Committee  acknowledges  the  two  Liquidambars  located  on  the  Fawkner  Mansions heritage property are also on the Significant Tree Register, however, considers the future of these trees is a heritage consideration and has been discussed in Chapter 9.   

Whilst  the  loss  of  established  and  mature  trees  would  be  regrettable,  the  ability  to undertake new plantings and landscape improvements in a widened road reservation would also  provide  a  community  benefit  over  time.    The  Committee  considers  that  one  of  the significant  advantages of Concepts 6  and  7  is  that  they provide  space  for  the planting of street  trees  along  the  Punt  Road  corridor  which  could  lead  to  significant  streetscape improvements.  The Committee is not convinced, however, that this is sufficient justification alone to adopt these concepts. 

As an aside, several submissions referred to the need to retain a significant European tree on the west side of Punt Road at the  intersection of Alexandra Avenue.   The Committee notes that this tree is not within the PAO and is unaffected by any formal concepts placed before the Committee and therefore makes no further comment about it. 

Page 105: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 99 of 162 

 

(iv) Conclusion 

The Committee concludes that the future of these trees would not be a determining factor when considering the future of the PAO. 

10.5 Impacts on Fawkner Park 

(i) The issue 

Do the potential impacts on Fawkner Park create an impediment to future road widening? 

(ii) Evidence and submissions 

The  City  of Melbourne  raised  issues with  any  incursion  into  Fawkner  Park  that might  be necessitated  by  the  introduction  of  the  proposed  ‘jug  handle’  turn  (left  turn/U  turn manoeuvre)  designed  to  remove  northbound  right  turns  from  Punt  Road  at  key intersections. 

In his expert evidence statement and confirmed at the Hearing, Mr Humphreys for VicRoads stated  by  that  “an  alternative  design  is  possible  and  achievable,  which  could  result  in Fawkner Park land not being required.” 

In  their  submission,  the City of Melbourne acknowledged  this evidence when  they  stated “there may  not  be  need  for  the  road  options which  show  intrusion  into  Fawkner  Park  to affect that park”. 

In addition, the Council’s expert evidence by Mr Shears stated it is “clear that any proposal for works to Punt Road ought to be formulated without impacting on the City’s valued open space”.  The Council submission also referred to the concession under cross examination by Mr Milner, who provided expert planning evidence for VicRoads, “that there would be a very strong justification required to support an intrusion into existing public open space”. 

(iii) Discussion 

The Committee notes that there would be no open space lost through any of the presented concepts as  they  impact on  the PAO.   The only potential  impact on  the quantum of open space was the design implications of the ‘jug handle’ turn indicatively proposed on the west side of Punt Road.   

The Committee agrees with  the expert  traffic opinion presented  that  the design  could be modified to eliminate the need to impact on Fawkner Park.  While this matter is technically outside the consideration of the PAO, it nonetheless potentially impacts on the road design solutions that utilise the PAO, yet this will be a matter for any detailed design phase. 

(iv) Conclusion 

In conclusion,  the Committee considers  that any potential  impacts on Fawkner Park are a matter for the detailed design phase of any future option and are not determinative when considering the future of the PAO. 

   

Page 106: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 100 of 162 

 

10.6 Summary of conclusions on environmental issues 

The range of environmental issues in this section of the report associated with any proposal to widen  Punt  Road would  need  to  be  carefully  considered  in  any  final  design  solution, however,  the  Committee  believes  that  these  issues  can  be  adequately  resolved  to meet adopted standards for noise, pollution and environmental impacts. 

In assessing the environmental issues in relation to its consideration of the PAO the question for  the  Committee  is whether  there  is  any  compelling  evidence  that  the  PAO  should  be removed  or modified  because  of  the  environmental  issues  covered  in  this  section  of  the report.  The Committee does not believe that this is the case and that a diligent design for a widened road can effectively deal with the range of environmental issues. 

Page 107: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 101 of 162 

 

11 Social issues 

11.1 Fairness and equity 

(i) The issue 

Is retention of the PAO is fair and equitable? 

(ii) Evidence and submissions 

Mr Heydon, Mr Carrasco, Ms Warwick, Mr Allatson and others submitted that retention of the PAO was not fair to the existing land owners.  The issues of fairness primarily related to the length of time the PAO has been in place with no firm plans to widen the road; that living with  uncertainty  is  intolerable;  they  were  unable  to  get  approvals  to  undertake maintenance, repairs and renovations which meant they are unable to maintain homes in a liveable state; and are disinclined  to  invest  in  their properties not knowing  the  future and are unsure whether they would receive adequate compensation. 

Mr Carrasco on behalf of Drop Punt submitted that “simply keeping the overlay  in place  is just maintaining the same festering state of uncertainty and  limbo that the community has unfairly  endured  for  the  last  sixty  years.”    He  submitted  the  PAO  has  blighted  the surrounding  area, with buildings  failing  into disrepair  and empty unkempt blocks of  land; and  if  left  unused  for  another  sixty  years, would  constitute  a  gross misuse  of  a  planning instrument, which is manifestly unjust and contrary to the principles of natural justice. 

Mr  Heydon  submitted  the  overlay  was  never  intended  to  be  there  so  long  and  many residents are unable to improve or even maintain their homes because of the overlay. 

Many  submitters  also  said  that  as  VicRoads  had  not  acquired  their  properties,  they  are unable to access compensation and unable to sell their properties as people are unwilling to buy land within the PAO due to the uncertainty around the future of these sites, which they submit is manifestly unfair. 

All submitters acknowledged they bought their properties with the full knowledge that the PAO was in place, but submitted that when making enquiries to VicRoads about the future of the PAO they had been repeatedly advised VicRoads had no immediate plans to widen Punt Road; and that it was unlikely to ever occur due to a lack of funds and political will. 

For  these  reasons,  it was  submitted  that  retention  of  the  PAO was  unfair  to  the  current landowners and should be removed.   

Ms Forsyth submitted  that a PAO  is a  legitimate planning  instrument used  to  identify  that land is to be acquired for a public purpose. 

In response to submissions that some people did not understand the full implications of the PAO, she submitted it is incumbent upon prospective purchasers to fully research the impact of  development  controls  on  a  property  prior  to  the  purchase  of  land  and  to  seek  advice where they are unclear of the implications; but that this is not justification to the remove the overlay. 

Ms  Forsyth  also  submitted  the  statutory  framework  for  compensation  puts  in  place  a mechanism to financially compensate landowners for the impacts of the PAO and that if they 

Page 108: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 102 of 162 

 

have  been  compensated  for  loss,  or  bought  their  properties  knowing  that  the  land was affected by a PAO, how can it be said that it is unfair to those property owners to keep the reservation in place until it is needed? 

She emphasised that land within the PAO is not a ‘wasteland’ as it continues to be used for legitimate beneficial purposes. 

(iii) Discussion 

The Committee  considers  the questions of  fairness and equity are  important  issues when considering the future of the PAO. 

It was clear through the presentations to the Committee that the PAO is causing significant distress to a number of land owners.  The Committee does not consider, however, that the questions of  fairness and equity are  resolved by simply  removing  the PAO,  they are much broader  than  the effect on current property owners and have community‐wide and  inter‐generational implications. 

In considering this issue, the Committee has referred to the TIA and the P&EA, as well as the SPPF which provide the following guidance on equity and fairness as follows: 

The  TIA43  identifies  equity  as  one  of  the  key  decision making  principles  stating  “The principle of equity means … equity between generations by not compromising the ability of future generations to meet their needs.” 

The P&EA44 identifies fairness as an objective of planning stating planning is “to provide for the fair, orderly, economic and sustainable use, and development of land” and it also states that planning is to “balance the present and future interests of all Victorians.” 

The SPPF45  recognises  that  society has various needs and expectations and  that when integrating  policy  it  is  necessary  to  “balance  conflicting  objectives  in  favour  of  net community benefit and  sustainable development  for  the benefit  of present and  future generations.” 

It  is  clear  that  both  the  legislation  and  the  SPPF  place  greater  emphasis  on  balancing fairness,  equity  and  the  needs  of  both  the  present  and  future  community,  than  just  the individual.  That is not to say that fairness to an individual is not a consideration, but that it needs  to  be  weighed  against  the  broader  net  community  benefit  and  equity  for  future generations.  This is a fundamental challenge of planning. 

The  Committee  also  recognises  that  all  but  three  of  the  135  land  owners  bought  their properties with the full knowledge of the PAO; knowing these properties may be acquired at some time  in the future for road widening; and would most  likely have paid a market rate that  reflected  the PAO.    It may be  that  some people were  advised  that VicRoads had no plans to widen to the road and that there was no funding to purchase properties, however, it appears that this was a risk that purchasers were prepared to accept.  That does not mean retention of the PAO is unfair. 

In response to suggestions that the length of time the PAO has been in place is an abuse of this planning  tool and  therefore unfair,  there  is no suggestion  in  the purposes of  the PAO 

                                                       43  Section 17(b) 44  Section 4 45  Clause 10.04 ‐ Integrated decision making 

Page 109: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 103 of 162 

 

that the overlay is intended to be a temporary measure.  Its intention is to implement policy and  identify  land  that may  be  acquired  for  a  public  purpose,  and  if  land  is  identified  as having a  long  term public purpose,  then  it  is  reasonable  to expect  that  the PAO will be  in place  for  a  long  time.    As was  expressed  by  the Ministerial  Advisory  Committee  to  Plan Melbourne Refresh: 

… What will be required by 2051 needs to be identified now and set out in PM Refresh.   The nomination of, say, a  road or  rail project on  the plan does not carry with  it an obligation to build  it now or  in the near future.   However,  its inclusion  in  the  plan  does  set  out  an  intention  and  a  need  to  protect  that option. … 

Overlays  that  restrict  development,  such  as  a Heritage Overlay,  Special  Building Overlay, Land Subject  to  Inundation Overlay and  the PAO are  implemented  to  identify  the  location and extent of a special  feature and  to control development.   They are not  intended  to be temporary overlays and do not have sunset clauses, they are applied  in perpetuity or until the special feature no longer applies and they are removed. 

The Committee considers that  if there  is a clear commitment by the Government to utilise the PAO in the long term, then retention of the PAO to the extent required is not a misuse of a planning tool and is not unfair.  However, if there is no such commitment, and the PAO is being retained ‘just in case’, then the Committee agrees this would be unfair. 

In relation to submitter concerns that as a consequence of the PAO they have been unable to undertake  routine  repairs  and maintenance  to  their properties,  Section  62.02‐2 of  the VPP – ‘Buildings and works not requiring a permit unless specifically required by the planning scheme’ ‐ clearly states repairs and routine maintenance to an existing building or works are exempt  from  the  permit  requirements  of  the  PAO.    The  existence  of  the  PAO  does  not prevent  owners  from  undertaking  routine  repairs  and  maintenance,  and  there  are  no internal controls.  The Committee does not accept claims that the PAO is preventing people from making their homes liveable or undertaking maintenance. 

Where  the  issue  becomes  more  contentious  is  where  owners  wish  to  undertake  more substantial buildings  and works,  including  renovations.   Under  the provisions of  the PAO, there  is  the  scope  to  apply  for  a  planning  permit  to  undertake  these  works;  and  as  a ‘Determining  Referral Authority’ VicRoads  has  the  ultimate  authority  to  direct whether  a permit should be issued or not. 

Concerns were raised that VicRoads would not allow more substantial buildings and works to properties within the PAO, and where permits were granted, they were subject to Section 173 Agreements which directed  that no  compensation would be payable  for  these works and that they need to be removed before acquisition of the property.  The Committee notes this approach is consistent with the PAO Decision Guidelines.  The Decision Guidelines state that  a  permit  granted may  be  conditional  on  “The  demolition  or  removal  of  buildings  or works constructed or carried out in accordance with a permit under this clause” and that “No compensation  being  payable  for  the  demolition  or  removal  of  any  buildings  or  works constructed  under  the  permit.”    The  intention  is  to  manage  the  future  compensation obligations of the purchasing authority. 

Page 110: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 104 of 162 

 

As these are standard conditions for a PAO and form part of the Victoria Planning Provisions, the Committee does not consider them unreasonable conditions to be placed on any permit issued,  or  any  Section  173  Agreement  that  is  registered  against  title,  particularly  for properties  that  are  to  be  acquired  within  the  short  to  medium  term.    Therefore  the Committee does not generally consider them unfair. 

Where the Committee considers these conditions and Section 173 Agreements may become unfair, however, is where the PAO is in place for a very long time and is intended to preserve a long term option, to which there is no real commitment. 

People who occupy dwellings on land which may be required for a long term public purpose are  in  effect  the  custodians  of  this  land  until  such  time  as  it  is  required  for  the  public purpose.   Whilst  the  Committee  can  see  the  need  to manage  development  in  order  to manage future compensation, these residents still need to live in these properties and they need  to  be  able  to  adapt.    To  not  let  them make  any  improvements  above  and  beyond routine  repairs and maintenance  is, particularly over a 60  year period or  longer  is,  in  the Committee’s opinion, neither fair nor reasonable. 

The Committee does not, however, see this as justification for the removal of the PAO, but rather the need for VicRoads to adopt a more flexible approach with regards to properties identified as a  long term public asset which enables people to adapt; and at the same time manage VicRoads future compensation obligations. 

The Committee notes these are not mandatory conditions, they are discretionary, therefore VicRoads has the ability to vary them.  The Committee considers that for properties that may be  identified  for  long  term acquisition  (15+ years)  that VicRoads should enter  into a more cooperative arrangement with landowners which enables them to undertake more extensive works to their properties, whilst also managing its future compensation obligations.  It may be an arrangement where people can undertake more extensive works accepting they will receive  no  compensation,  or  they  undertake  more  modest  works  and  receive  more compensation.   The Committee can see a situation where both concepts could work and  it may require a tailored approach, although the Committee recognises that this raises  issues beyond the Punt Road PAO that need to be considered. 

The Committee considers that this would require VicRoads to develop a policy position on this and prepare clear guidelines. 

The Committee  considers  that  this approach would enable  landowners  to make  informed decisions about what  investment they are prepared to make to these properties based on the an understanding of if, and when, they are likely to be acquired. 

(iv) Conclusion 

The Committee concludes that the application of the PAO is not inherently unfair. 

The  Committee  has  also  concluded  that,  whilst  it  may  be  appropriate  to  limit  the development of land through conditions on a permit and a Section 173 Agreement for land that is to be acquired in the short to medium term, that greater flexibility should be given to people who own land which has been identified as a long term acquisition option. 

Page 111: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 105 of 162 

 

11.2 Certainty 

(i) The issue  

The need to provide property owners with certainty about the future of the Punt Road PAO. 

(ii) Evidence and submissions 

A majority of  the written submissions and presentations  to  the Committee  raised concern that the PAO has been in place for sixty years and there are still no plans to either widen the road or acquire any of the properties and that this has led to significant uncertainty for land owners in terms of whether the widening will ever occur, and if it is to occur, when and what properties will be affected.  Submitters asked if it is not to be widened for some time what works they can undertake to their properties and what compensation is likely to be payable to them and  for what?   The bulk of submitters state this uncertainty  is untenable and not only causing significant stress to people, but it also leading to properties being neglected and even abandoned, which  is  leading  to planning blight.    It was  submitted  that  removing  the PAO would resolve this uncertainty, giving residents an opportunity to get on with their lives and improve their properties. 

Mr Allatson submitted that 60 years  is an unconscionable period of time for the owners of properties  to  live with uncertainty of  the overlay being  retained  ‘just  in case’.   He said he needed to be able to invest in his home to make it safe and liveable. 

Mr Allatson submitted that VicRoads had,  in the past, advised  landowners that  it would be highly  unlikely  that  Punt  Road  would  ever  be  widened.    He  provided  in  his  submission (Document 41) a copy of minutes of a meeting with VicRoads officers dated 19 October 2006 which  indicated  that  VicRoads  officers  said  “no  one  wants  to  widen  Punt  Road.    The Government  doesn’t want  to widen  Punt  Road.   We want  to make  the  public  transport system  work  effectively.    Our  priorities  are  facilitating  public  transport  and  maximising safety.” 

Mr Carrasco on behalf of Drop Punt submitted that “simply keeping the overlay  in place  is just maintaining  the  same  festering  state  of  uncertainty  and  limbo  that  community  has unfairly  endured  for  the  last  sixty  years.”   He  submitted  the  only  actions  consistent with providing  certainty  is  either  to  lift  the  PAO  or  to  action  it  in  its  entirety,  or  a modified version, and to acquire the affected properties. 

Mr Wilson  submitted  that maintaining  the overlay will  simply perpetuate  the uncertainty and confusion for property owners and residents  in these areas, emphasising that overlays such as this are not intended to, and should not, remain in place indefinitely. 

Ms  Sender  made  submissions  about  the  adverse  effects  of  chronic  uncertainty,  stating people need  certainty  in  their  lives  so  that  they  can make plans  for  themselves and  their families going  forward.    She  submitted  that people  living on or near Punt Road  for many years have  feared  the compulsory acquisition of  their properties and  this can also  lead  to trauma  associated with  battling  to  obtain  fair  compensation  and  the  struggle  to  relocate themselves  to  somewhere  affordable.    She  submitted  the  state of  the houses  along Punt Road seems to reflect the despair of owners, who are unwilling to repair and beautify their homes if they are uncertain whether they can stay in them. 

Page 112: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 106 of 162 

 

In  response  to  concerns  about  a  lack  of  certainty, Ms  Forsyth  submitted  the  PAO  is  the instrument  to  enable  the  identification  of  land  which  is  “proposed  to  be  acquired  by  a Minister, public authority or municipal council”, and therefore whilst the PAO remains in the planning  scheme,  there  is  certainty  the  land  has  been  earmarked  for  acquisition,  and property owners ought to proceed on that basis.  She submitted that a natural consequence of  buying  land  within  the  PAO  is  that  there  will  be  uncertainty  about  the  timing  of acquisition stating that is the nature of the instrument, but she submitted if owners feel the property  is no  longer of value  to  them, or saleable,  they are able  to make submissions  to VicRoads to purchase their properties. 

In conclusion, Ms Forsyth submitted that whilst many people said 60 years is too long for the PAO  to be  in place,  the TIA and P&EA  require decision makers  to  take account  for  future generations  and whilst  60  years may  seem  long  to  an  individual,  “it  is  a  relatively  small period of time in the context of a city.” 

(iii) Discussion 

The Committee can understand an owners’ desire to have certainty about the future of their property, however, when purchasing a property affected by a PAO,  there will always be a level of uncertainty. 

The Committee agrees with Ms Forsyth’s submissions that the PAO itself provides certainty in that it clearly identifies there is an intention to acquire land that has been identified for a future public purpose.  Having the PAO in place is a clear statement to anyone who seeks to purchase these properties that part of this  land may be acquired  in the  future  for a public purpose.  The issue of certainty, particularly when the PAO has been in place for a long time, is whether it is still required, and if so, when is it likely to be purchased and what can they do to the property until then. 

Regardless of the extent of the Overlay ultimately retained, the Committee considers there is still a need to improve certainty for residents and considers there are a number of ways in which this can be achieved, as discussed below. 

A clear statement of intent supported by policy 

If  it  is  accepted  that  Punt  Road  is  to  play  a  significant  long‐term  role  in  the  transport network,  then  the  Committee  considers  this  should  be  reflected  in  the  Victorian Infrastructure Strategy and Plan Melbourne 2016. 

An indication of future timing 

The  timing associated with  the potential acquisition of  land was  identified as a  significant issue. 

The Committee considers the identification of Punt Road PAO in terms of short, medium and long  term  acquisition  priorities would  assist  both  owners  and  VicRoads  to  gain  a  better understanding of timing and what compensation rights/obligations they have. 

This will not only assist owners and prospective purchasers with a better understanding of when  the  land  is  likely  to be acquired  to enable  them  to make  informed decisions about whether to buy or sell property, but  it will also enable them to make decisions about what 

Page 113: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 107 of 162 

 

investment they are prepared to make to these properties based on the an understanding of when they are likely to be acquired. 

It will also assist VicRoads to make appropriate funding arrangements for the acquisition of these properties. 

The Committee recognises these should be  indicative timeframes, but considers this would go a long way towards providing some certainty for all parties. 

The Committee also considers that this approach would enable to sequenced acquisition of land with greater priority given to the acquisition of medium priority properties over longer term priorities. 

Indication of works that can be undertaken under the PAO 

As discussed in Section 11.1, the Committee considers there is scope for VicRoads to adopt a more  flexible  arrangement  with  regards  to  works  owners  could  undertake  to  their properties, particularly properties identified as longer term acquisition priorities. 

The Committee can see benefit in VicRoads developing guidelines about the type of works it will allow and under what conditions, such as: what can be done?; will it need to be removed at the owners expense when the property is acquired?; what works will compensated?; and what will not? 

The Committee considers guidelines would provide owners and prospective purchasers with greater  certainty  to  assist  in making  informed  decisions  about what  investment  they  are prepared to make in their properties; and whether to buy or sell them. 

The  Committee  considers  the  use  of  section  173  agreements  is  both  important  and appropriate as it ensures the conditions of the permit are reflected on the property title so that  any  prospective  purchaser  is  aware  of  the  obligations  associated with  owning  these properties.   The section 173 agreement  itself  is a means of providing certainty, particularly to prospective property owners. 

Compensation process and the amount payable 

In  relation  to  the  compensation  likely  be  paid,  the  Committee  notes  that  compensation payable  is based on  the  Land Acquisition and Compensation Act 1986.    It  also notes  that VicRoads  provides  a  brochure  on  the  VicRoads  website  entitled  ‘Land  acquisition  and compensation.    General  Information  for  Property  Owners’  which  outlines  the  general acquisition process. 

The Committee is satisfied there is clear process in place to deal with compensation and that if  residents  are  unsure,  they  can  contact VicRoads  to  examine  this  further.    The  issue  of compensation is discussed in more detail in Chapter 13. 

Consistent advice from VicRoads about the future of the PAO  

Many  submitters  stated  that  VicRoads  has  provided  inconsistent  advice  to  both  existing landowners and prospective purchasers about  future of  the PAO, and  that has been both misleading and further fuelled uncertainty surrounding the future of Punt Road. 

Given  the  age  of  the  PAO,  the Committee  considers  that  people may well  have  received differing verbal advice from VicRoads as to the future of the PAO. 

Page 114: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 108 of 162 

 

In  situations  like  this,  clear  and  consistent messages  are  essential  to  ensure  all  parties receive the same information. 

The Committee considers the PAO  itself  is the first clear  indication that  land  is  intended to be acquired for a public purpose.  That is the purpose of the PAO.  The Committee is satisfied the PAO adequately alerts people to the fact that there is an intention to acquire either part or  all  of  these  properties  for  future  public  purposes  and  that  this  is  then  reflected  in  a Section 32 Statement prepared as part of any property sale. 

The Committee considers  the VicRoads website would benefit  from a Punt Road PAO Fact Sheet which simply and concisely outlines the strategic context of Punt Road, the purpose of the PAO, the proposed stages of work and the owner’s rights and obligations. 

The  Committee  considers  this would  be  a  relatively  simple  task  to  complete  and  ensure consistent advice is provided to all parties. 

(iv) Conclusions 

The  Committee  concludes  there  is  a  need  to  provide  both  owners  and  prospective purchasers with greater certainty  in relation  to  the Punt Road PAO, but does not consider the removal of the PAO is necessarily required to provide that certainty. 

The  Committee  concludes  that  greater  certainty  would  be  provided  to  owners  and prospective purchasers by the following actions: 

Identify the future role of Punt Road and the priority for any upgrade of Punt Road in the Victorian Infrastructure Strategy and Plan Melbourne 2016. 

Define the PAO required for the future widening of Punt Road according to  its priority, that being short (0‐5 years), medium (5‐15 years) and long term (15+ years). 

VicRoads  to  adopt  a more  flexible  arrangement with  regards  to works  owners  could undertake  to  their  properties,  particularly  properties  identified  as  long  term  priorities and develop guidelines to clearly identify the range of works that may be permitted and the conditions that would apply. 

VicRoads  should  continue  to  apply  section  173  Agreements  to  ensure  prospective purchasers  clearly understand  the  rights  and obligations  associated with  an  individual property within the PAO. 

VicRoads should give priority to acquiring properties that are identified as required in the short and medium term, or at least give these property owners the option of acquisition. 

VicRoads  should  prepare  a  Punt  Road  PAO  Fact  Sheet  which  simply  and  concisely outlines the strategic context of Punt Road, the purpose of the PAO, the proposed stages of work and the owner’s rights and obligations. 

   

Page 115: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 109 of 162 

 

11.3 Impacts on the community 

(i) The issue 

Whether the potential widening of Punt Road would have a detrimental impact on the local community? 

(ii) Evidence and submissions 

There were many  submissions which  raised  concern  that  the  potential widening  of  Punt Road would lead to community dislocation. 

These  concerns generally  related  to an  impression  that  the  future widening of Punt Road would be  in the  form of a  ‘six  lane  freeway’ that would create a hard and tangible barrier between east and west of Punt Road, making pedestrian access across Punt Road extremely difficult.  The impacts identified related to the difficulties that would be experienced by local residents  to  cross  a  widened  road  to  access  open  space,  schools,  shops  and  other community services. 

Mr Heydon submitted “The social impacts would be negative and lasting.  A six lane road in this neighbourhood would rip the heart from Melbourne’s finest region and would divide the locale  in  two,  creating  an  ugly,  noisy,  dangerous  barrier  between  the  Royal  Botanical Gardens, Fawkner Park and the CBD and the residents east of Punt Road.” 

Mr  Carrasco  submitted  a  Hoddle  Highway  would  destroy  the  amenity  of  an  extremely integrated  area of Melbourne,  including  South  Yarra, which  is  known  as one of  the most liveable suburbs in Melbourne. 

Ms  Allatson  submitted  that widening  of  Punt  Road would  divide  the  community,  leaving those on the east side separated from the significant open space to the west.  She submitted that a freeway in this location, would mean people no longer feel connected to the Botanical Gardens, The Shrine of Remembrance, the Sidney Myer Music Bowl, the Tan and the Yarra River. 

Mr  Allatson  and Ms Warwick  submitted  that  the  threat  to  desecrate  these  suburbs  has devastated local residents and are united them in their resolve to protect and preserve their vibrant, warm  spirited  community.    They  submitted  that  these  suburbs  are  the model  of sustainable community living, not only for the services and amenities that are available, but also because of  the  strong  sense of  inclusiveness.   They  submitted  that crisscrossing Punt Road  is  part  of  their  daily  life  to  share  and  utilise  local  amenities,  however,  crossing  a ‘freeway’ will become a mental obstacle to crossing Punt Road. 

Ms Widmer  submitted  that  the  brutalising  effect  of  road widening  and  increased  traffic damages  the  quality  of  community  life  and  disconnects  people  from  their  place  in  a community which ultimately decreases social cohesiveness as citizens feel threatened by the scale of the road which could lead to withdrawal and social isolation.  Road widening creates a  physical  and  psychological  division  and  both  sides  of  the  road  become  a  non‐liveable community and neighbourhood. 

Ms Forsyth emphasised that VicRoads is not proposing to construct a freeway through inner Melbourne,  but  rather  seeking  to  preserve  the  long  term  option  to widen  Punt  Road  to accommodate not only cars, but also public transport and other more sustainable transport 

Page 116: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 110 of 162 

 

options.  She also emphasised the concepts presented are not final concepts, but rather an illustration  of what  can  be  achieved,  and  as  such  the  final  design  details  have  not  been resolved at this stage.   She acknowledged there would be a need to refine the final option and  issues  such as  the  interface with adjoining properties and appropriate crossing points would be issues considered at that stage. 

Ms Forsyth also submitted that Punt Road is a four lane, busy congested road which already exists.    She  submitted  that  the  redesign  of  Punt  Road  could  improve  the  situation, particularly  if  an  option  such  as  Concept  7  were  developed  which makes  provision  for landscaping along street edges and medians strips. 

(iii) Discussion 

Much of  the  community’s  concern  relates  to  the  assumption  that  any  future widening of Punt Road would be in the form of a freeway. 

Whilst Punt Road may have been  identified as a  ‘future  freeway’  in 1969, and one of  the concepts prepared by VicRoads as part of this exercise is for a 6 lane road, it is important to recognise  that  none  of  the  proposals  are  for  a  freeway  or  a  highway.    Similarly,  the Committee  does  not  consider  a  freeway would  be  an  appropriate  traffic  solution  in  this location for many reasons, one of which would be the impact on the community. 

The  Committee  agrees  that  Punt  Road  is  already  a  major  arterial  road  which  carries significant  traffic  and  that  crossing  it  at  peak  times  already  presents  challenges  to pedestrians accessing facilities and services on either side of Punt Road.  In the Committee’s view,  however,  a widened  Punt  Road would  not  act  as  an  impenetrable  barrier  denying access to open space or other community services to the west for residents who live on the east side. 

The Committee  is satisfied  that, as  the concepts presented are not  final concepts and any future road widening will need to undergo a detailed design phase, there is the opportunity to design  the  road and  intersection  treatments  to ensure  that pedestrian movements are adequately addressed and to ensure people have reasonable access to the range of services and  facilities  in  the  area.    The  Committee  is  confident  these  issues  could  be  adequately addressed through the future design process. 

Committee  therefore  does  not  consider  that  community  impacts  are  determinative  in relation to whether the PAO should be retained, modified or removed. 

(iv) Conclusion 

The  Committee  considers  that  community  access  arrangements  can  be  adequately addressed in detailed design. 

Page 117: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 111 of 162 

 

12 Impacts on strategic growth objectives 

(i) The issue 

How does a decision to retain, modify or remove the PAO on Punt Road impact on the future strategic growth objectives at both a State and local level? 

(ii) Evidence and submissions 

A  number  of  submissions  raised  concerns  that  the  future  of  Punt  Road  should  not  be considered in isolation, but rather as part of a strategic exercise that considers this location in the context of the broader land use planning for the local area and Melbourne. 

Ms Sharp submitted that the PAO  is  impacting on Stonnington Council’s ability to meet  its strategic growth targets as some of the land which fronts onto Punt Road which is affected by this PAO, is also included within the Residential Growth Zone and the General Residential Zone. 

Melbourne  City  Council  submitted  that  if  the  PAO  is  retained,  the  rear  of  dwellings  and buildings  that  currently  back  onto  the  properties  directly  facing  Punt  Road  would  then directly  interface with Punt Road.   He submitted this  is a replication of what has happened on the Nepean Highway and Alexander Parade where the buildings do not front the street, creating a poorly designed street interface and having a significant detrimental effect on the corridor.   This  interface treatment should be considered  in design concepts and any future built form guidelines for the corridor. 

Glossop Town Planning, on behalf of a number of submitters, similarly submitted that some land on the eastern side of Punt Road is currently in the Residential Growth Zone, which is a relatively  scarce  resource  in  the  City  of  Stonnington,  and  that  the  PAO  makes  the development of this  land unlikely,  leading to broader  implications for housing diversity and affordability within Stonnington.  Glossop Town Planning submitted that there needs to be a clear plan  for Punt Road and  that  it  is unacceptable  to continue  to reserve  land without a clear, funded and sustainable solution for the future of Punt Road. 

Alfred Health supported the retention of the overlay because it preserves an opportunity to enhance traffic flow through a very congested area.   Alfred Health emphasised the overlay needs  to  be  considered  in  a  broader  strategic  context  to  determine  how  Victorians  can access areas such as the Alfred Medical Research and Education Precinct, which is identified in Plan Melbourne as a State significant health and education precinct. 

Alfred Health submitted that a planning strategy should be prepared that identifies how this precinct could attract other health services to co‐locate in this precinct.  It emphasised that any consideration about what to do with Punt Road, that does not consider how to maximise the  benefits  that  the  Alfred  precinct  brings, may  result  in  lost  opportunity  that  will  be difficult to re‐capture.  It submitted that any decisions about the future of Punt Road should only be considered in the context of a broader strategy for the area. 

Mr Kelder submitted that  if the PAO was  lifted this would open  land up for redevelopment and urban renewal, and that a levy should be implemented so that developers can fund and make  improvements  to  the  streetscape, wider  footpaths,  underground  infrastructure  and 

Page 118: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 112 of 162 

 

planting.   He submitted removal of  the PAO should be seen as an opportunity  to enhance the area for local residents and the established community. 

Mr Woodford submitted demolition of homes on the east side of Punt Road would expose the  sides  of  houses  currently  in  side  streets  to  the  new  Punt  Road  creating  an  ugly streetscape when viewed from Punt Road. 

Ms Forsyth submitted that VicRoads has not explored the possibility of a planning strategy for  land along  the Punt Road corridor as  it does not consider  that  is  the  role of VicRoads, however,  she  submitted  VicRoads would  not  be  opposed working with  the  Councils  and other relevant government agencies on such strategies, if and when appropriate. 

In his evidence, Mr Milner stated that whilst the original proposal to acquire land along Punt Road  was  a  significant  strategic  planning  decision  demonstrating  a  well  founded appreciation of  the  land and  transport  issues  to be  faced by a growing city; and provided leadership and vision regarding the structure and form of the future urban, what is missing is a clearly articulated longer‐term vision for the form and composition of the road space and its integration with the land uses and development that adjoins it. 

Mr Milner  accepted  that  if  the PAO was  taken up  in  its entirety,  the  residual  land would present a significant  range of difficulties  for how  it could be developed and accessed.   He identified  some of  the  issues  that would need  to be addressed  include marginal  slivers of residual  land with no evident  capacity  for beneficial use,  leaving  land with no  alternative means of access except via Punt Road, properties  that  leave a building or dwelling at  the new  interface with Punt Road and buildings bisected but not entirely  included within  the reservation and exposing the rear boundary of properties as the new street frontage to Punt Road.   He highlighted  the widening  of Brighton Road  provides  a  useful  insight  about  the issues that need to be addressed as part of any road widening. 

He  emphasised  that  transport  and  strategic  land  use  planning  need  to  be  integrated  to provide  guidance  on  the  preferred  future  boundaries  of  land  uses,  development  and conceptual  urban  design  outcomes.    He  gave  evidence  that  this would  contribute  to  an enhanced  public  domain  amenity  in  Punt  Road  and  an  overall  improvement  in  the functionality and appearance of the road. 

(iii) Discussion 

The  Committee  agrees  with  submissions  that  the  PAO  raises  significant  issues  beyond transport implications alone, and raises significant land use planning considerations as well, both at a State and local level. 

Alfred Health raises a significant issue.  The Alfred Medical Research and Education Precinct located  in  the  corner of Punt and Commercial Roads  is  identified  in Plan Melbourne as a health and education precinct of State significance.  The strategic direction contained in Plan Melbourne  is  “To  improve access  to health and/or  education  services and  to  improve  job choices  in  these  industries  for  Melbournians.    As  a  significant  generator  of  skilled employment,  activity  and  visitation,  these  precincts  will  support  ancillary  health  and/or education, retail, commercial, accommodation, services, housing and public transport.  They may anchor activity centre development ……    In established Melbourne, they may currently stand  alone  and  there will  be  opportunities  to  diversify  the  uses  around  these  precincts.”  Whilst strategic work relating to the development of this precinct has not been undertaken, 

Page 119: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 113 of 162 

 

it may have implications for the Punt Road corridor and should be considered in a strategic context. 

Stonnington  Council  and Glossop  Town  Planning  submitted  that  the  PAO  is  impacting  on Council’s ability to achieve its strategic residential growth objectives.  Whilst the Committee accepts this may be occurring, it does not consider the implications of that to be significant.  Whilst land south of Domain Road is predominantly included within the Residential Growth Zone  and  identified  as being  a  substantial  change  area,  it only  applies  to  allotments  that have direct abuttal  to Punt Road,  and does not extend  further east.   As  identified by Mr Milner  in  his  evidence,  if  the  PAO  were  to  be  removed,  these  properties  would  prove attractive  for redevelopment and have the potential achieve higher density and yield than currently exists, however, he  identified  that “shallower and narrower  lots, complicating or frustrating  site  assembly  and  consolidation”  could  limit  redevelopment  to  two  or  three storey town houses, rather than the four storeys as anticipated in the RGZ.  He also said that if  the  PAO  were  to  be  taken  up  in  its  entirety,  the  residual  land  would  also  present  a significant  range of difficulties  for how  this  land  could be effectively used and developed.  The growth that could be accommodated along the Punt Road RGZ is also insignificant when compared  to  growth promoted within  the Principal Activity Centres  located  along Chapel Street. 

Whilst the Committee agrees the PAO does impact on the potential redevelopment of these Punt  Road  properties,  it  does  not  consider  that  removal  of  the  PAO  would  enable  the redevelopment  of  these  properties  to  the  extent  that  they  would  make  a  significant contribution to Stonnington’s housing supply. 

The  zoning  of  the  land  does,  however,  raise  a  number  of  issues  relevant  to  traffic management  along  Punt  Road  that  the  Committee  considers  needs  to  be  explored.    For example,  if the PAO was to be removed and  land abutting the road  is to be developed for more  intensive  residential  development,  the  Committee  considers  this  raises  an  issue  in terms of car parking and direct vehicular access to Punt Road.  The Committee considers that direct vehicular access  to Punt Road would not be appropriate and  could have  significant impacts on traffic flows and safety, particularly at peak periods.  Similarly, as identified by Mr Milner, if the PAO is utilised for widening purposes, there is a need to address the interface treatments and to determine what to do with remaining parcels of land. 

Whilst the Committee accepts this  is not a determining  factor, the Committee agrees with Mr Milner’s evidence and submissions that emphasise the need to for an integrated land use and transport strategy, and sees benefit in such a strategy being prepared whether the PAO remains,  is  modified  or  is  removed.    The  Committee  considers  the  responsibility  for preparing this should  lie with the Stonnington and Melbourne City Councils  in consultation with VicRoads. 

The Committee considers that such a strategy would also assist in providing some certainty about  the  future  redevelopment  options  associated  with  properties  and  identifying  the issues that need to be addressed.    

Page 120: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 114 of 162 

 

(iv) Conclusions 

The  Committee  concludes  the  PAO  does  not  have  a  significant  impact  on  the  City  of Stonnington’s ability to accommodate future residential growth. 

The Committee concludes there  is a need to prepare an  integrated  land use and transport strategy  which  examines  the  development,  access  and  interface  issues  associated  with development  along  Punt  Road,  irrespective  of  which  widening  concept  is  adopted  and whether the PAO remains or is removed. 

Page 121: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 115 of 162 

 

13 Other issues raised in submissions 

A wide  range of other  issues were  raised  in  submissions.    In  this Chapter  the Committee assesses some of the more major  ‘other’  issues and provides commentary and conclusions on the considerations relevant to a decisions to remove or retain the PAO. 

13.1 The cost of property acquisition and property values 

(i) The issue 

Has the cost of property acquisition been fairly and accurately assessed? 

(ii) Evidence and submissions 

There were several submissions concerning the effect of the PAO on local property values. 

In relation to the effect of the PAO, Ms Forsyth made the point  in her opening submission that: 

Applying a PAO can be a disbenefit to owners of property directly affected by the PAO (eg because they are restricted in the manner in which they can deal with their properties).  However, individual property owners affected by a PAO are  compensated  for  their  losses  under  the  provision  of  the  Planning  and Environment Act 1987  (Part 5)  (eg  loss on sale compensation) and under the Land Acquisition and Compensation Act 1998 (upon acquisition). 

Ms Forsyth relied upon the evidence of Mr Kinnaird, a Certified Practising Valuer, in relation valuation and economics issues. 

Mr Kinnaird undertook an indicative desktop valuation estimate of each affected property as at the 20  January 2016.    In his evidence statement, Mr Kinnaird advised that  if the PAO  is retained and VicRoads acts on purchasing the properties: 

The  cost  of  acquiring  the  market  value  of  the  properties  not  owned  by VicRoads  as  at  2016  is  $160,197,000  based  on  the  assumption  that  the compensation  paid  for  the  loss  on  sale  properties  equates  to  70%  of  the compensation entitlement.  The cost based on 50% and 90% P&EA reduction is $176,500,000 and $143,900,000 respectively. 

(As previously mentioned  the  ‘P&EA  reduction’  relates  to  the  Loss  on  Sale  compensation i.e.   The amount of compensation paid for the  loss on sale of properties as a percentage of the total compensation entitlement.) 

In response to a request from the Committee, Mr Kinnaird provided supplementary advice which stated that if the rate of prior compensation was in fact 20 per cent, this 2016 figure would have been $200,940,000 creating a higher  level of overall compensation payable by VicRoads. 

Mr Kinnaird also provided estimates of the future cost of compulsory acquisition in 35 years time based on a 5.5 per  cent annual  real annual growth  rate after adjusting  for  inflation.  These estimates were $1,150,000,000  (at 50 per cent P&EA reduction), $1,040,000,000  (at 70 per cent P&EA reduction) and $940,000,000 (at 90 per cent P&EA reduction).  If a 20 per cent P&EA reduction level was applied then the figure would be $1,310,000,000. 

Page 122: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 116 of 162 

 

Several submitters contested VicRoads’ economic analysis. 

The submission  from Ms Warwick and Mr Allatson maintained  that  the 2016  figures were not  relevant  as VicRoads will  not  purchase  properties  now  and  so  the  figure  for  2051  of $1.31 billion (using the 20 per cent prior compensation level) is more likely.  Ms Warwick and Mr Allatson also believed that, in addition to the compensation payable for properties within the  PAO,  voluntary  acquisitions  would  be  offered  to  other  affected  properties  and substantially  increase  the  total compensation  figure.   Therefore  it would be misleading  to use  the 2016  figures as  indicating “affordability  to  the  taxpayer” as  the actual  real cost of acquisition would be much higher.   The submission from Ms Warwick and Mr Allatson also stated  that  the  current  value  ascribed  to  VicRoads  properties  of  $50.56 million,  rising  in value  to  $329.34  million  at  a  projected  annual  increase  of  5.5  per  cent,  represents  a significant public asset that sits dormant. 

The submission  from Dr Lovell and Ms Gartland held that Mr Kinnaird had misrepresented the economic  cost of  retaining or  removing  the PAO,  claiming  that  the  value of VicRoads owned land should not be factored in.  Dr Lovell and Ms Gartland further submitted that, for the 75 properties where no  compensation has been paid,  these properties  should not be taken  into  account  because  “They  would  have  to  pay  full  compensation  for  these  75 properties  should  they  compulsorily  acquire  them  in  2016,  2051  or  at  some  other  date.  Therefore  the  retention  or  removal  of  the  PAO  is  irrelevant”.    In  relation  to  the  cost  of removing  and  then  reinstating  the  PAO,  the  submission  stated  “Removing  the  PAO immediately  presents  a  potential  opportunity  cost  to  the  Government  of  approximately $22M only and not $267.8M as presented by Mr. Kinnaird in his evidence.” 

Ms Hocking’s submission claimed that regarding the cost of removing the PAO “This is not a $650m decision, based on Urbis figures it is: $55m for full PAO removal, less than $30m (for) a midblock removal.” 

The  Drop  Punt  presentation  stated  that  “Investigations  show  most  compensations  are between  20%  and  25%.    Not  90%,  grossly  underestimating  the  payout  required.”    The presentation used a  simplified example  to demonstrate how  the percentage  level of prior compensation can be ascertained.  At the Hearing, Mr Carrasco for Drop Punt stated he had undertaken title searches for 12 of the 41 properties that have had prior compensation paid and that these showed that compensation at the time of purchase was between 20 per cent and 25 per cent. 

In their reply submission, VicRoads rejected the assertion by Drop Punt that it is a “relatively simple process to arrive a precise value of compensation as a proportion of the unaffected value of properties  today.”   VicRoads maintained  that  the equation used  in  the Drop Punt presentation does not apply unless the whole of the property is affected by the PAO; and it does not take into account the values placed on the land as compared to any building on the land.  As VicRoads submitted, title information does not reveal the sale price of the property at  the  relevant  time.   To support  the complexity of understanding  the percentage  level of prior  compensation  for  Loss on Sale, VicRoads  referred  to  the  supplementary  information provided by Mr Kinnaird where he demonstrated  in  the worked example  that  the Loss on Sale would have been only 16 per cent if it applied to the entire property, but 78 per cent if considered against only that part of the land affected by the PAO.  In this case, the balance of 22 per cent would be paid as compensation when the property is compulsorily acquired. 

Page 123: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 117 of 162 

 

VicRoads held  that  the Drop Punt analysis of  the percentage  levels of prior compensation was not substantiated as the 12 titles that Drop Punt referred to in their presentation were not  tabled, and neither  the percentage of  the  land affected by  the PAO nor  the sale price could in any event be determined from the title, and therefore concluded: 

Accordingly,  the submission  is unsubstantiated and  runs counter  to both  the example given by Mr Kinnaird and Mr Kinnaird’s evidence about his experience with more recent loss on sale cases with which he is familiar. 

In her submission to the Committee, Ms Bilu provided the background to the purchase of a property  in  Punt  Road  covered  by  the  PAO  that  indicated  that  the  previous  owners  had spent $300,000 renovating the property but after having the property on the market  for a year  they  had  dropped  the  price  by  some  $200,000  to  enable  a  sale.    The  drop  in  price brought the property within an acceptable price range for Ms Bilu but after purchasing the property she became aware of the uncertainty associated with the PAO “with other residents living in fear for 30 years or more, not being able to renovate or repair their houses, for fear of losing their money.” 

Ms  Gartland  referred  to  the  difficulty  associated with  a  sudden  need  to  sell  a  property covered  by  the  PAO  “if  that  had  happened  to  be  at  a  time when media  attention was focussed  on  the  Punt  Road  corridor,  I would  have  struggled  to  realise  an  adequate  sale price.” 

In relation to the effect on property values, the Drop Punt presentation to the Committee stated  that  “two  identical  properties  (were)  recently  transferred  before  and  after media speculation about PAO review process.”  It was asserted that the prices obtained for the two properties varied by over $500,000. 

In response to the Drop Punt example, Ms Forsyth responded in her reply submissions that: 

350 Punt Road sold for $1.5m in 16 May 2015 and 344 Punt Road was sold for $950m  on  December  2015.    But  of  course  there  is more  to  any  sale  that whether  the properties  look broadly comparable  from  the public  realm.   The real  estate  brochures  from  those  sales  clearly  show  that  the  higher  value property  has  been  recently  renovated  to  a  high  level,  and  has  on  site  car parking. 

and 

The  brochure  for  350  Punt  provides  an  interesting  example  of  a  property where there has been recent investment in the maintenance of the property. 

(iii) Discussion 

The Committee did not receive information that definitively calculated the cost to VicRoads of  acquiring  land  under  the  PAO  because  to  do  so would  require  a  detailed  property  by property  analysis  of  each  property’s  market  value,  a  knowledge  of  what  part  of  each property would be required  for the road widening  (which can only be  fully known when a final design is completed) and what level of prior compensation has been paid on each of the 41 properties where Loss on Sale has been paid.  The costs of land acquisition in 2016 figures has been estimated by Mr Kinnaird, using a number of assumptions,  to be  in  the range of $143,900,000  to  $176,500,000.    This  range  is  based  on  the  assumptions  that  the 

Page 124: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 118 of 162 

 

compensation paid  for  the  loss on sale properties equates  to 90 per cent and 50 per cent respectively under the P&EA reduction.  If the reduction is 70 per cent of the compensation entitlement  then  the  cost  to  VicRoads would  be  $160,197,000.   While  submissions  from property owners asserted that lower prior compensation levels of 20 per cent to 30 per cent reflect  local  experience,  the  Committee  is  unable  to  reach  any  firm  conclusion  as  no documentary  evidence  was  provided.    The  Committee  therefore  has  no  firm  basis  to question Mr Kinnaird’s assumptions. 

It was apparent to the Committee through statements by property owners and others that property prices are adversely affected by the existence of the PAO, as would be expected.  Equally,  it  is clear that the existence of the PAO was known or this  information was readily available to prospective buyers. 

The Committee was presented with  information  that  indicates  that properties  covered by the PAO have continued to be sold over the years, demonstrating that a market does exist for  such  properties.    At  the  same  time,  the  Committee  also  accepts  that  the market  for properties covered by the PAO will be affected from time to time by express knowledge or speculation about how imminent and how far reaching the implementation of the PAO may be.   However,  in  the Committee’s  view  this  is  not materially  different  from  a  number  of other  market  factors  that  may  influence  potential  purchasers  about  whether  to  buy property. 

Several  submitters  raised  an  expectation  that  in  addition  to  the  cost  of  compulsory acquisition  of  properties  covered  by  the  PAO,  if  a widened  road  project  proceeds  there would also be voluntary acquisitions offered for other properties indirectly affected and that this would  increase  the overall  cost of  the project.   The Committee  received no evidence that this would occur so cannot comment on this matter.  Even if there are additional costs the Committee has no basis  to  conclude  that  this would  influence any decision  to  retain, remove or modify the PAO. 

(iv) Conclusion 

The Committee acknowledges  there  is no certainty about  the value of prior compensation paid and this will affect the ultimate compensation payments that VicRoads would  incur  in exercising its rights in relation to the PAO and the economic benefits held by VicRoads in the PAO.    The  Committee  relies  on  Mr  Kinnaird’s  expertise  and  knowledge  of  the  land acquisition compensation system and that the prior compensation levels under Loss on Sale payments are at the higher levels he modelled. 

13.2 Compensation 

(i) The issue 

Are adequate compensation provisions in place for land owners subject to acquisition? 

(ii) Submissions and evidence 

Ms Forsyth made  submissions  regarding  the compulsory  land acquisition process and also referred the Committee to information that VicRoads makes available to affected parties to their assist understanding of the process.  Compensation for land covered by the PAO that is compulsorily  acquired  is determined by  the  Land Acquisition and Compensation Act 1986 

Page 125: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 119 of 162 

 

(LACA)  and  the P&EA;  and  that  the  compensation  legislation under  the P&EA  also makes provision for Loss on Sale compensation for those whose properties are affected by a PAO; but that it is limited to those who were owners prior to it being reserved under the PAO.  In certain  situations where a property  is  sold, before ultimate acquisition occurs, a claim  for Loss On Sale can be made which provides for a level of compensation if the owner sells land at a lower price than he or she might reasonably have expected to get if the land or part of the land was not reserved by the PAO. 

Ms Forsyth advised that: 

Approximately 41 properties within the Punt Road PAO have been paid  ‘Loss on Sale’ compensation.  The most recent payment being made this year (2015) with another claim for ‘Loss on Sale’ currently being assessed. 

In his expert evidence, Mr Kinnaird advised  that some $2,418,155 compensation has been paid under the P&EA for these 41 properties, including $960,000 for a claim that has still not been  finalised.   He advised VicRoads owns 19 properties and  the balance of 75 properties have not had compensation paid and, notably, all but three properties of the 75 properties are not eligible  for Loss of Sale compensation because they were purchased after the PAO was in place. 

Regarding  the  impacts on owners of property within  the PAO, Ms  Forsyth  advised  in her opening submission: 

It is important to recognise that landowners who have been compensated, or have purchased the property with notice of the overlay, may gain significant economic advantages  if the overlay  is removed.   While they may have to pay back  loss  of  sale  compensation,  that  amount  is  usually much  less  than  the compensation  that was  paid when  one  takes  account  of  the  time  value  of money.    It  is  common,  therefore,  that  not  only  is  there  opposition  to  such instruments being applied  in the first place, but also that there  is subsequent pressure to remove them from the land over time. 

Further, in relation to the issue of fairness of the compensation system she submitted: 

In  respect  of  the  fairness  argument,  the  statutory  framework  for compensation  puts  in  place  a  mechanism  to  financially  compensate landowners  from  the  impacts  of  the  PAO.    If  people  have  already  been compensated for  loss, or bought their properties with notice of the PAO, how can it be said that it is unfair to those property owners to keep the reservation in place until it is needed? 

The submission from Ms Warwick and Mr Allatson raised concerns over the time effects on the compensation system because of the extended period of time of 62 years that the PAO has been in place.  They maintained that the fairness of the compensation: 

In  the  short  to medium  term  ... may well provide adequate  recompense  for loss or for limiting development opportunity.  However, clearly, this diminishes over time and there must be a point arrived at when compensation ceases to have the effect intended. 

Page 126: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 120 of 162 

 

The example  is cited of $14,000 paid as compensation  in 1970 equates  to a present  value  of  $155,772  (RBA  FVM)  or  $156,454  (ABS  CPI)  in  2015  ie  45 years  after  compensation  was  paid.    $156,000  would  be  considered inadequate compensation for inner‐city Melbourne real estate in 2016. 

Ms Warwick and Mr Allatson concluded that: 

It cannot be considered reasonable, or realistic, to expect that the architects of Victoria’s  compensation  legislation would have envisaged over 60 years ago that  a  fair  and  reasonable  compensation  arrangement  entered  into  in  the previous century between  the Government of  the day and  the  then property owner would  remain  in  place,  retain  relevance  and  still  satisfy  the  tests  of fairness or reasonableness 45 years later (in the above example) or longer. 

The Drop Punt presentation at  the Hearing acknowledged  that Loss on Sale compensation does provide some mitigating effect on the impact on properties however: 

Over  time,  original  compensation  amount,  even  with  indexation  holds  no relationship to the compensation percentage claimed by the authority. (Drop Punt emphasis) 

The Drop Punt presentation maintained that VicRoads does not contribute to maintenance or improvements yet still retains its ‘cut’ and that the introduction of a depreciation element into the compensation regime would ensure that authorities do not simply sit on properties for  unreasonable  periods.   Drop  Punt  believed  that  the  prior  compensation  value  should begin to depreciate after 5 years and be fully extinguished after 10 years. 

(iii) Discussion 

The  compensation  for properties  acquired, or  the prior  compensation on  Loss on  Sale,  is governed by well tested  legislation and  it  is not the role of this Committee to comment  in depth about the compensation system.  However, in the case of the Punt Road PAO that was first put in place some 62 years ago and, when adding the additional planning horizon of 35 years  to 2051 used by VicRoads  in  this matter,  this  then  takes  the potential period  to 97 years  that  the  PAO may  be  in  place  before  it  is  acted  on.    A  question  then  arises  as  to whether this creates issues of fairness regarding the adequacy of the compensation system. 

The Committee  agrees with Ms  Forsyth’s  submission  regarding  the  compensation  system when  she  stated  “If  people  have  already  been  compensated  for  loss,  or  bought  their properties with  notice  of  the  PAO,  how  can  it  be  said  that  it  is  unfair  to  those  property owners to keep the reservation in place until it is needed?” 

Further, the Committee notes that hardship provisions exist under the compensation regime to allow VicRoads to purchase land if the seller can demonstrate an inability to sell is a direct result of the PAO; and this inability to sell will cause significant hardship. 

The  Committee  considered whether  there  needs  to  be  some mechanism  for VicRoads  to periodically review and ‘refresh’ a PAO after the passage of an extended period of time.  Ms Forsyth considered that “it  is appropriate that there  is a periodic review when the PAO has been in place for an extensive period of time, to ensure the PAO retains its relevance.”  While the Committee agrees with this proposition what constitutes “an extensive period of time” becomes potentially difficult to determine when one considers the wide range of situations 

Page 127: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 121 of 162 

 

and purposes where PAOs are in place and the clear need for government to sometimes take the very  long term view of ensuring proper provision  is made for nominated  infrastructure to  be  developed  at  an  indeterminate  date  in  the  future.    However,  this  is  a matter  for VicRoads to give further consideration to. 

The  Committee  has  no  information  to  base  an  opinion  about  the  correct  level  of  prior compensation actually paid under  the P&EA by VicRoads  in  respect of various properties.  While Mr Kinnaird modelled 50 per cent, 70 per cent and 90 per cent, local property owners maintained the figure to be closer to 20 per cent.  It was put to the Committee by VicRoads' counsel  that  the  lower  figure  as  advanced  by  local  property  owners  represented  a misunderstanding of  the way  the LACA prescribed  formula worked.   The Committee notes Mr  Kinnaird’s  expertise  and  experience  regarding  the  compulsory  land  acquisition compensation system and so has confidence in his written evidence that the higher levels of 50 per cent, 70 per cent and 90 per cent that were modelled are realistic. 

There  was  no  evidence  presented  that  disputed  or  raised  substantive  issues  about  the principle  of  compulsory  acquisition  of  property  to  enable  major  infrastructure  projects.  Equally,  the  provisions  of  the  legislation  for  compensation  that  compensated  property owners at market values were not disputed, however as outlined above, the effects of the extended time period that the PAO has been in place was raised as having potential impact on the value of compensation. 

(iv) Conclusion 

In the Committee’s view the compensation system for compulsory land acquisition appears adequate  and  well  tested  and  provides  no  basis  to  call  into  question  the  removal  or modification of the PAO. 

The  Committee  agrees  that  VicRoads would  be well  served  to  consider  a mechanism  to undertake a periodic review when a PAO has been in place for an extensive time.  While the period of 62 years that the Punt Road PAO has been in place does appear to be long or even excessive, when  taking  the  very  long  term  view  about  city  shaping  infrastructure,  such  a timeframe may well not be unreasonable. 

13.3 Streetscape design 

(i) The issue 

What impact would a potential road widening have on the Punt Road Streetscape? 

(ii) Evidence and submissions 

There were multiple submissions that raised concerns about the impact that road widening would have on the Punt Road streetscape. 

Mr Carrasco, on behalf of Drop Punt, raised concern that the ‘Hoddle Highway’ would leave an  ugly  scar  through  the  middle  of  Melbourne’s  most  liveable  suburb  and  would  run contrary to what many cities with a global profile are doing; which is to focus on sustainable streetscapes to improve amenity for locals and visitors alike and to reclaim areas dedicated to the car for landscaping purposes.  He also said that removal of the PAO would enable the restoration of the original tree lined boulevard. 

Page 128: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 122 of 162 

 

Similarly Mr Heydon submitted the widening of Punt Road could create a ‘big ugly road’.  He submitted that “South Yarra is one of the most liveable, attractive and finest suburbs in the world.  To take Hoddle Street, one of the Melbourne’s ugliest and most congested roads, and duplicate it through South Yarra and Prahran is poor planning.” 

Mr Allatson and Ms Warwick submitted  that bulldozing 140 properties on  the east side of Punt Road, 40 of which have heritage significance, will not only wipe out an important part of  Melbourne  architectural  history,  but  will  also  replace  the  friendly  neighbourhood landscape with boundary and cyclone fences and freeway sound barriers.  He submitted that retaining the PAO will result in many of the historical homes becoming derelict and beyond preservation, with many of  the VicRoads properties already demonstrating how  the entire area will deteriorate becoming graffiti covered and rubbish dumps.   They submitted that a ‘freeway’ will become unsightly. 

Mr  Tivendale,  who  was  called  to  give  evidence  by  Melbourne  City  Council,  said  that Victorians have come to expect a high  level of urban amenity from public spaces  including roads,  and  the  desire  to  see  more  grand  boulevards  created  has  been  supported  by successive metropolitan  strategies.   When  asked  by  the  Committee whether  he  thought Punt Road could or should be a significant metropolitan boulevard, he agreed and said the PAO should be retained to achieve that purpose. 

Ms Forsyth emphasised that VicRoads is not proposing to construct a freeway through inner Melbourne,  but  rather  seeking  to  preserve  the  long  term  option  to widen  Punt  Road  to accommodate not only cars, but also public transport and other more sustainable transport options. 

She also  submitted  that whilst  there  is  some vegetation along Punt Road,  there  is  limited opportunity  for  roadside  landscaping  along  Punt  Road  due  to  the  narrow  width  of  the existing reserve and narrow shared path on either side, however, this is not due to the PAO.  Similarly, she said the dominance of high front fences, which detracts from the visual appeal of  the  corridor,  is  also  not  a  function  of  the  PAO,  but  rather  as  a  result  of  the  existing function of Punt Road as an arterial road. 

Ms Forsyth submitted that whilst Concepts 3 and 5 provide some opportunity for planting, Concepts  6  and  7  provide  for  a  more  substantial  landscape  centre  median  and  wider roadside  widths  on  both  sides  which  she  submitted  would  create  opportunities  for significantly enhanced landscaping improvements, including boulevard treatments. 

(iii) Discussion 

The  Committee  finds  submissions which  consistently  refer  to  the  PAO  being  retained  to enable the construction of a freeway to not only be exaggerated, but also misleading.   The Committee accepts that none of the concepts presented by VicRoads proposes to construct a freeway along Punt Road. 

Whilst submitters have  raised concerns  that a  road widening could significantly  impact on the  streetscape,  the  Committee  considers  the  Punt  Road  streetscape  is  already  seriously compromised, not only because of the high  front  fences, condition of the buildings on the eastern side of Punt Road and unmaintained vacant VicRoads sites, but also because of the narrowness of the footpaths which provide no scope for streetscape planting, as well as the 

Page 129: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 123 of 162 

 

significant amount of service  infrastructure  that exists such as power poles, bus stops and street signs. 

The  Committee  considers  there  is  a  clear  need  and  scope  for  significant  streetscape improvements along Punt Road, both now and as part of any future road widening. 

Whilst Punt Road is not identified as a boulevard in Plan Melbourne, the Committee agrees with Mr  Tivendale’s  evidence  that  any  option  which  seeks  to  widen  Punt  Road  should incorporate  streetscape  improvements  including  extensive  tree  planting,  improved footpaths and a rationalisation of infrastructure and signage that will ensure that any future road design contributes to the liveability of this area. 

(iv) Conclusions 

The Committee concludes there  is a need to make significant streetscape  improvements to Punt Road and considers that provision should be made for this in any future widening plans. 

13.4 Implications of emerging technologies 

(i) The issue 

What  impact will  emerging  technologies  have  on  the  future  transport  planning  for  Punt Road? 

(ii) Evidence and submissions 

Ms Allatson and Mr Cleaver both submitted that transport technology is changing, including the  introduction of autonomous vehicles, and questioned what  impact this would have on the future transport planning.   Mr Cleaver suggested that  it could reduce the need for the private motor vehicles and that services such as Uber could provide a cheap and affordable alternative to public transport. 

Ms  Forsyth  provided  the  Committee  with  information  on  Intelligent  Transport  System solutions as examples  that could assist with  the safe and efficient operation of Punt Road and the surrounding network, which  included CCTV monitoring, TRANSnet, Smart Bus Lane enforcement, Tram Security Cameras, etc.   She also provided a copy of a conference paper prepared  by  Peter Davidson  and Anabelle  Spinoulas  entitled,  ‘AUTONOMOUS VEHICLES  – WHAT COULD  THIS MEAN  FOR  THE  FUTURE OF  TRANSPORT?’  to  assist  the Committee  to understand what  implications autonomous vehicles  could have on  the  future of  transport and  transport  planning.    She  emphasised  this  paper  does  not  represent  the  opinions  of VicRoads/PTV, but was provided as information only. 

(iii) Discussion 

Whilst it could be questioned what relevance autonomous vehicles have to the future of the Punt  Road  PAO,  as  an  emerging  technology  it  is  important  to  understand  the  potential impacts they may have on both the way we live and operate as a society, as well as how we get around and what infrastructure may be required to support this new technology. 

In  addition  to  the  information  provided  by  VicRoads,  the  Committee  notes  that Infrastructure Victoria  has  specifically  identified  the  potential  impact  of  emerging  vehicle 

Page 130: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 124 of 162 

 

technology as a significant  issue that needs to be considered.   The Laying the Foundations report prepared states: 

Even when we know the nature of an emerging technology, the implications of its use may not be  immediately clear.   There  is a  range of emerging vehicle technologies  that  could  fundamentally  affect  the way  people  use  Victoria’s transport networks.  In particular, driverless vehicles and ride sharing are two interrelated  technologies  that  may  change  the  way  people  get  around.  Driverless  vehicles  could  offer  an  opportunity  for more  efficient  and  safer roads, while  ride  sharing  could  provide more  flexible  transport  options.    In combination, they could enable people to avoid the major cost of owning their own vehicle, while having the convenience of an automatic transport option to take them from point A to point B.  …  But in planning for the future, we must be cognisant of what new technologies might mean  in the Victorian context, how they can contribute to better outcomes and what challenges they might present.    There  are  still  a  lot  of  unknowns  about what  these  technologies might mean for Victoria (see figure 1), but this is not cause for inaction. 

Some of the questions it identifies emerging transport technologies may have are: 

When?  Gradual adoption or big bang? 

More efficient use of road network?  Road design implications? 

More/lengthier trips by vehicles?  Knock‐on implications for congestion? 

Competition with public transport and other non‐car modes? 

Role in delivery of goods? 

Both Plan Melbourne and  Infrastructure Victoria recognise  that whilst we can plan  for  the things that we know, there are many things that we do not know and that we must maintain flexibility to be able to respond. 

Similarly, the information provided by VicRoads states that whilst autonomous vehicles have long been  in the realm of science fiction, recent progress means that driverless cars will be on our streets in the relatively near future stating.  The information states that whilst there are  still  many  issues  to  be  considered,  in  terms  of  transport  planning  into  the  future, autonomous vehicles should be considered as they are  likely to have significant  impacts on travel  behaviour  and  road  network  operations  with  some  car  companies  having  fully operation models within the next 5‐10 years and predict that vehicles without a legal driver will be possible by 2050. 

The paper prepared by Mr Davidson and Ms Spinoulas says: 

Autonomous  vehicles  are  an  emerging  technology  that  is  likely  to  have significant  impacts  on  travel  behaviour  and  road  network  operations  in  the medium  to  long  term.   Autonomous vehicles will  improve safety on  roads as they more closely observe their surroundings using technologies such as radar, lidar, GPS, and  computer  vision;  these  driver‐less  cars will be  able  to  travel closer  together  and  operate  at  higher  speeds,  thus  increasing  capacity  on roads.   However,  the  improved  comfort; ability  to better use  the  time while travelling;  and  reduced  complexity  of  parking will make  road  based  travel more attractive.  This is likely to increase trip making and increase average trip lengths.  The extra demand pressures could be exacerbated by the use of cars 

Page 131: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 125 of 162 

 

to  auto‐chauffeur  people,  reducing  parking  requirements  but  increasing counter peak traffic flows.   The relative attractiveness of public transport will also be altered; on the one hand the improvements to car travel will make PT relatively  less attractive; on the other hand autonomous vehicles could make PT more responsive and affordable … 

The paper concluded that: 

The big gains  in autonomous vehicles will  come  in  later  stages – when  they can operate without occupants, allowing automatic chauffeuring and shared vehicles;  and  when  they  can  rely  on  instant  communications  with  a  fully autonomous vehicle fleet to increase speeds and reduce vehicle spacing.  …. it is likely that the long term picture for a shared, fully autonomous fleet, is very good  –  with  very  low  congestion,  minimal  new  infrastructure  and  high productivity.    A  fully  shared  fleet  could  completely  transform  our  cities, allowing  higher  densities  and  improved  mobility,  and  freeing  up  a  huge amount  of  space  in  our  houses,  our  yards,  our  streets,  and  in  our  urban centres.  … 

The  difficulty with  this  is  that  things will  get much worse  before  they  get better.   There will be strong demand  for new  infrastructure  to deal with  the large  growth  in  travel  demand,  and  likely  increased  mode  share  to  car.  However  the  economic  lifetime  of  much  of  the  new  infrastructure  will  be limited, as  the new world of  shared autonomous vehicles will not  require  it.  This  is  an  important  planning  challenge,  and  clear  insight  into  the  likely trajectory of change is crucial. 

The potential impacts of emerging technologies are an illustration of the need to ensure that as a city we have the flexibility to respond to changes such as this. 

(iv) Conclusion 

The  Committee  is  unable  to  draw  any  conclusions  in  relation  to  the  impact  of  emerging technologies,  other  than  to  recommend  that  the  likely  implications  be  considered when deciding the future of the PAO. 

13.5 The suggested tunnel option 

(i) The issue 

A number of submissions  raised  the option of a  tunnel as an alternative  to widening Punt Road.  A tunnel option was not advanced by VicRoads as one of their potential concepts and so  the Committee did not consider  this matter  in any detail.   VicRoads provided a general response to the tunnel option. 

(ii) Evidence and submissions 

Ms Bilu’s submission stated: 

A tunnel is the overwhelmingly preferred long‐term option for Punt Road (the outcome of the VicRoads public forums, both  in person and online,  in August 

Page 132: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 126 of 162 

 

2015).   Yet, VicRoads has chosen to  ignore the people of Melbourne and has not scoped or costed a tunnel for this review. 

The submission from Ms Warwick and Mr Allatson advised: 

At the community drop‐in  forums, predominately attended on the south‐side of the Yarra by residents from our community group, the tunnel was again the most  favoured  long‐term  solution.    It  was  however,  quickly  dismissed  by VicRoads as being too expensive. 

At the Hearing Ms Warwick and Mr Allatson presented their view: 

It  is  disappointing  that  a  number  of  experts  addressing  the  Panel  have dismissed  tunnels  as  a  reasonable  and  viable  option.    They  have  relied  on some form of VicRoads assessment, which VicRoads has refused to release, of the cost of construction, being allegedly ten times the cost of road widening.  No evidence has been presented by either VicRoads or  its experts  to confirm this  ‘costing’  or  to  indicate  the  cost‐benefit  of  tunnels within  a Melbourne context. 

This  submission disputed  the opinion offered by Mr  Tivendale  in his  traffic evidence  that tunnels have not been economically viable because a narrow cost‐benefit analysis does not take  broader  benefits  such  “reduced  delay  and  improved  productivity,  or  the  benefits  of improved amenity and streetscape above ground.  These benefits are consistently referenced in  the  international  literature,  as  is  how  cities  are  improving  the  economics  of  tunnel construction and operation”.   The submission supplied a detailed overview of  international cities that have used or are building tunnels to alleviate traffic congestion. 

The Committee notes  that VicRoads consultation  involved online engagement, community drop‐in sessions and council workshops.    In relation to what the report describes as Out of scope  feedback,  the  following  feedback  was  provided  in  relation  to  a  tunnel  or  grade separation: 

There  was  support  for  a  tunnel  underneath  the  existing  Punt  Road alignment.  Participants suggested that this solution would ease congestion and cause fewer disruptions to residents and properties on Punt Hill 

Many participants suggested  that grade separations at major multi‐nodal intersections would  improve  traffic  flows  for public  transport and private vehicles and reduce waiting times. 

In  the  2012  Punt Road  Study,  the  economic  assessment  referred  to  the  broad  costing  of $450 million to $500 million plus a $50 million contingency to construct a 6 lane road option that uses the full PAO and made the comment in relation to a tunnel: 

Although  the  cost  of  Option  1  (the  6  lane  road  option  in  that  report)  is relatively high,  it  is  far  less  than a new  tunnel which appears  to be  the only other option for increasing north‐south capacity within the sub region. 

In their Part A Submission, VicRoads stated: 

There were a number of comments received regarding either tunnelling under the  existing  Punt  Road  alignment  or  lowering/raising  of  Punt  Road  (grade separation). 

Page 133: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 127 of 162 

 

However  it  is  noted  that with  only  15‐20%  vehicles  travelling  the majority length  of  the  Hoddle‐Punt  Corridor,  it  is  expected  there  would  still  be  a significant  traffic  demand  on  the  surface  road  network.    Therefore,  the problem  still  needs  to  be  addressed:  ‘how  do we  get  the most  out  of  the existing network’.  Though no investigations have been undertaken looking at these  suggestions of a  tunnel,  land may  still be  required within  the existing PAO and beyond to facilitate such a tunnel, for example: construction (cut and cover), interchanges and ventilation stacks. 

Furthermore, road tunnelling  is far more costly than surface road works, and would be  likely  to  result  in  such a proposal being  less economically  justified than a surface improvement. 

The written expert traffic evidence for VicRoads did not address the tunnel option. 

(iii) Discussion 

The tunnel option has not been put  forward by VicRoads as an option  for consideration  in the Committee’s assessment of the future role of the PAO.    It has not been  investigated  in any  detail  for  the  Committee  to  offer  any  informed  response.    A  range  of  community responses to the range of consultation opportunities considered it as an option. 

For completeness, even  if VicRoads dismissed a  tunnel option at  the outset because of an unacceptably high cost, it may have assisted the community’s broader understanding of the issues to have received some order of magnitude of cost for a tunnel, possibly as a multiple of the highest cost surface option, even at a desktop level. 

(iv) Conclusion 

The Committee considers that detailed consideration of a tunnel option is outside the scope of the Committee’s terms of reference, and therefore makes no further comment. 

Page 134: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 128 of 162 

 

14 Findings and recommendations 

14.1 Findings 

The  Committee  has  weighed  the  evidence  and  submissions  received;  and  makes  the following findings: 

Strategic context 

1. The Punt Road PAO was put in place in 1954 to provide for a future major arterial road along the corridor.  The PAO was retained through the 1970s and 1980s with the long term  intent of providing  the  future  F2  Freeway.   The  full  freeway network plan has long  since  been  abandoned,  and  there  are  no  current  plans  in  any  Melbourne transport plans to widen Punt Road. 

2. Punt  Road  is,  and  will  continue  to  be,  an  important  north‐south  arterial  link  in Melbourne’s road network and its efficient operation contributes to the economic and social wellbeing of the city. 

3. In relation to the strategic role of Punt Road, the Committee concludes that: - Punt Road is likely to continue to play an important strategic role in Melbourne’s 

road network, although there are some unknowns about that role  in the  longer term. 

- The  greatest  net  community  benefit will  balance  fulfilling  this  long  term  role against minimising the impacts on landowners. 

- The existing PAO  should be  retained  to  the extent  required  to  guarantee  that Punt Road can continue to fulfil its role in the short, medium and long term. 

Fairness and certainty 

4. The  existence  of  the  PAO  has  created  uncertainty  for  property  owners  over  a  long period of time, particularly in terms of their ability to confidently invest in maintaining or developing their properties.   The Committee accepts that the ongoing uncertainty and  lack of  a  clear plan  for  the  future of Punt Road  is  causing distress  for property owners. 

5. The retention of  the PAO  is not unfair or  inequitable where  it  is  intended  to protect land  to be  acquired  for  a  committed public  infrastructure project, even over  a  long period  of  time,  however,  if  there  is  no  commitment  to  a  defined  project,  then  the Committee considers the PAO should be removed. 

Traffic and road network capacity 

6. The  2013  VAGO  report,  Managing  Traffic  Congestion  found  that  increasing  road capacity will not on  its own address  the high  cost of  congestion without a  range of demand  management  measures.    The  Committee  agrees  that  a  range  of  traffic management measures  should  be  applied  in  the  Punt  Road  corridor,  not  just  road widening. 

7. The capacity of Punt Road needs to be upgraded  in the short term to relieve existing congestion issues, and further upgraded to some degree in the medium and long term to fulfil  its role  in the network, relieve other parallel north‐south routes and  improve 

Page 135: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 129 of 162 

 

public transport operation along and across the Punt Road corridor.  A key question for the Committee is the extent of upgrade required in the longer term. 

8. The Committee was not provided with any definitive evidence about whether  traffic volumes would  increase  in  the  Punt  Road  corridor  beyond  2031.    The  argument  of VicRoads was that additional capacity may be required so therefore the PAO should be retained.    Evidence  and  submissions were presented  in  relation  to  the  likelihood of future  demand  management  measures  such  as  a  congestion  tax,  CBD  parking restrictions  etc.  and  the  expectation  that  this  would  reduce  traffic  on  Punt  Road.  Counter to this, the Committee received  information on overall projected population increases  in Melbourne and the  likely  localised development and population  increase in the vicinity of the Punt Road corridor.  The Committee believes that while there may be  growth  in  local  traffic  demand,  it  is most  likely  that  growth  in  corridor  traffic demand  would  be  limited  given  the  demand  management  policies  expected  to continue and the capacity constraints elsewhere in the corridor. 

Heritage 

9. While  there  are  two  ‘highly  significant’  and  a  small  number  of  ‘locally  significant’ properties  affected  by  the  PAO,  the  Committee  is  not  convinced  that  the  heritage significance  of  buildings  along  Punt  Road  is  a  determining  factor.    If  there were  a compelling  case  for  widening  Punt  Road,  the  Committee  is  of  the  view  that  the properties affected could be acquired in the broader community interest.  That said, if there are workable long term options that avoid heritage properties then it is desirable to follow that path. 

Environment 

10. Impacts on open space and vegetation, along with noise and air pollution impacts are important considerations for the more detailed design and construction phase of any project, but are not determinative at the broad planning stage and decisions regarding the future of the PAO should be made on other grounds. 

Assessment of concept options 

11. In  relation  to  the  Concept  Options  presented,  the  Committee  draws  the  following conclusions: 

- The short term introduction of Concepts 1 and 2 are supported.  Substantial off‐peak  capacity  improvements  and  congestion  relief  can  be  achieved  through clearways, turn bans and other minor lane realignments. 

- Concepts  3  and  4  are  not  supported.   Concept  3  provides  no  real  advantages over  Concept  2.    Concept  4  (reversible  fifth  lane)  would  have  operational challenges with  limited benefits, and was abandoned by VicRoads prior  to  the Hearings. 

- The  Committee  is  generally  supportive  of  Concept  5  (involving  substantial intersection  upgrades  but  four  lanes  midblock),  however,  believes  that  the Modified Concept 5, substantially reducing land acquisition and not widening the Hoddle Bridge, would achieve a similar level of corridor performance. 

- The  Committee  notes  the  improvements  proposed  to  the  Swan  Street intersection, but  is not convinced that the current traffic capacity constraints  in 

Page 136: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 130 of 162 

 

Punt  Road  ‐ Hoddle  Street  north  of  the  Yarra  River  can  be  fully  resolved  and believes that Punt Road between the Yarra River and Swan Street will continue to be the main constraint on traffic. 

- The  Committee  was  not  convinced  that  the  upgrading  of  the  Punt Road/Alexandra  Avenue  intersection  or  the widening  of  the  Hoddle  Bridge  is warranted.   This  is borne out by the traffic analysis provided to the Committee which shows  that  the Alexandra Avenue  intersection will  function satisfactorily under projected 2031 volumes. 

- The Committee was not provided with compelling evidence to support the need for a  full  six  lane widening of Punt Road  (Concepts 6 and 7)  in  the medium or long  term  future.    Traffic  projections  provided  to  the  Committee  extended  to 2031  and  showed  that  Concept  5  provided  an  adequate  level  of  service  and substantially  greater  traffic  throughput,  thereby  alleviating  parallel  routes  and providing for more reliable traffic flow (for private vehicles and public transport) along and across the Punt Road corridor. 

- Based on  the evidence presented,  the Committee was not  convinced  that  the merits of Concepts 6 or 7  (essentially marginally better  traffic  speeds)  justified the extensive additional  land acquisition and  impact on heritage properties that would result. 

- The Committee was not  convinced of  the merits of providing  a dedicated bus lane  (Concept 7),  for  such a  small number of buses on  the  route.    (6 per hour currently, expected to increase to 12 per hour in the peak). 

The Committee’s preferred response 

12. The Committee has  shown a Modified Concept 5  for consideration  that provides  for additional  turn  lanes  and  bus  priority  at  each  of  the major  intersections, minimises land  acquisition  and  removal  of  houses,  and  restricts  the  demolition  of  heritage buildings to only one property.   The Modified Concept 5 would require acquisition of part or all of 54 properties  (subject to  final design).   Of these, 38 are relatively small acquisitions not affecting buildings and 16 buildings would be affected.    If Concept 5 were modified in the manner shown, the Committee anticipates that the PAO could be removed  from  81  properties  (subject  to  final design)  as  listed  in  Section  8.4  of  this report. 

13. The Committee  is firmly of the view that the Modified Concept 5 (which needs to be refined through more detailed design) would provide for adequate corridor capacity in the medium term and well beyond 2031.  The Committee’s believes that the Modified Concept 5 will achieve good levels of service and more than adequately cater for 2031 Base Case  traffic projections, and more  so  if permanent clearways and  signal  linking are implemented. 

14. The Committee has suggested Modified Concept 5  in order to show how some of the issues raised in submissions might be addressed.  The Committee is conscious that the modified layout was not produced until after the Hearing, and so has not yet been fully ‘tested’.    However,  the  issues  that  have  prompted  the modified  layout  were  well canvassed in submissions and at the Hearing.  The Committee believes that modifying Concept 5  in the way shown would resolve the vast majority of concerns raised with the Committee, whilst still providing adequate future traffic capacity.  The Committee 

Page 137: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 131 of 162 

 

acknowledges  that  further design work will be  required whichever  future  concept  is adopted, and any change to the PAO will require a planning scheme amendment. 

15. The Committee’s  findings  are based on  the  following  assumptions  about  the  future strategic role of Punt Road between the Yarra River and Union Street: 

- Punt Road will continue to act as an urban arterial road and will not become a freeway 

- A primary function will be as a key north‐south bypass of the Melbourne CBD - It will also continue to function as an access route to the Melbourne CBD and the 

Yarra Park sporting precinct, and as a local access road - It  will  continue  to  provide  regionally  important  access  to  hospitals,  schools, 

recreation, employment and business - Government policies will continue  to attempt  to manage  traffic demand  in  the 

corridor and encourage mode shift from private vehicles to public transport - The  capacity  to  increase  capacity  north  of  the  Yarra  River  is  limited,  and  this 

section of Punt Road and the Swan Street/Punt Road  intersection will continue to act as the capacity constraints in this part of the corridor 

- Bus services will continue to operate along Punt Road, but there will be  limited demand for new services along the route other than increasing the frequency of the existing service. 

16. The above assumptions are based on what is known or can be reasonably predicted by the  Committee  at  the  time  of  preparing  this  report.    In  the  event  that  these assumptions  change  substantially,  and  this  may  be  informed  by  the  work  of Infrastructure Victoria, then the future configuration options for Punt Road should be reviewed and the PAO should also be further reviewed. 

The future of the Public Acquisition Overlay 

17. The TIA and Plan Melbourne both make it clear that land should be preserved for the implementation of future transport projects.  If the widening of Punt Road appeared as a clear priority in strategic planning documents or a Metropolitan Transport Plan then the advice of the Committee would be clear.    It would be to retain  land required  for the project  in  the  form  identified.   The  fact  that no such  reference exists makes  the Committee’s task more difficult. 

18. The  Committee  could  have  taken  the  conservative  view  proposed  by  VicRoads  and recommend that the PAO should be retained on the basis that it may be required.  On the other hand,  it  could be  argued  that  the need  for  the PAO has not been  clearly demonstrated and therefore the PAO should, at least in part, be relinquished.  The fact is that the PAO already exists, and as such represents a substantial community asset that should not be relinquished  lightly.   The Committee  is of the view that  if the PAO were  relinquished  now  it  would  most  likely  never  be  recovered  due  to  the  high likelihood  that  the  land  would  be  further  developed  and  become  prohibitively expensive  to  buy  back.    The  consequence  of  any  decision  to  remove  the  PAO  is therefore, in the Committee’s view, likely to be final. 

19. The Committee has concluded that if the role of Punt Road remains as it is today, there is no need to upgrade the capacity to a six lane road.  Demand management measures, improvements  in  public  transport  services  and  new  technologies  can  reasonably  be 

Page 138: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 132 of 162 

 

expected  to  limit  traffic  growth  on  Punt  Road.    If  the  role  of  Punt  Road  changes considerably  so  that  it  acts  as  a more  substantial  private  vehicle,  freight  or  public transport  route,  then  there  is an argument  to  retain  the PAO  to provide  for such an upgrade.  The Committee thinks this is highly unlikely. 

20. The Committee is aware, however, that Infrastructure Victoria is currently preparing a 30 year infrastructure strategy for Victoria that will review infrastructure priorities.  It may be that the strategy will provide more guidance on the future role of Punt Road.  The Strategy is due for release by the end of 2016 and it may be prudent to wait for its release before making final decisions on the Punt Road PAO. 

21. The Committee finds that any widening of Punt Road (and use of the PAO) should be limited to be consistent with the assumed constraints that exist, notably: 

Hoddle  Street  and  Punt  Road  north  of  the  Yarra  River will  continue  to  be  the capacity constraints on the corridor 

The widening of the Hoddle Bridge is unnecessary and unlikely to be supported in the foreseeable future 

It is desirable to limit impacts on heritage buildings 

It is desirable to limit the extent of the PAO and the degree of land acquisition for reasons of cost, impact on properties and improving certainty for landowners. 

22. On  balance,  the  Committee  therefore  recommends  that  the  PAO  be  modified  to provide only the  land required  for a road  layout design based on a modified  form of Concept  5.    The  Modified  Concept  5  as  shown  in  Appendix  E  has  substantial advantages  in terms of reduced  impact on heritage properties (as shown  in Appendix F), and requires less overall land acquisition than other concepts reviewed. 

Implementation 

23. The Committee acknowledges that the Modified Concept 5 as shown in Appendix E is a preliminary functional layout only.  It is envisaged that VicRoads would further develop and  refine  a  design, more  accurately  define  the  revised  PAO  required,  and  seek  a planning  scheme  amendment  to  formally  revise  the  PAO.    The  PAO  should  not  be removed  from  the  remaining  properties  until  this more  detailed  design  and  formal planning process is carried out. 

24. Irrespective of  the  final extent of  the PAO,  the Committee believes  that  there are a range  of  measures  that  VicRoads  should  adopt  to  provide  landowners  with  more certainty.  These include to: 

Define  the PAO  required  for  the  future widening  of  Punt  Road  according  to  its priority, that being short (0 to 5 years), medium (5 to 15 years) and long term (15+ years). 

Adopt a more flexible arrangement with regards to works owners may undertake to  their properties, particularly properties  identified as  long  term priorities, and develop guidelines  to clearly  identify what may be permitted and  the conditions that would apply. 

Give priority to acquiring properties that are identified as required in the short and medium term, or at least give these property owners the option of acquisition. 

Page 139: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 133 of 162 

 

Prepare  a  Punt  Road  PAO  Fact  Sheet  which  simply  and  concisely  outlines  the strategic context of Punt Road,  the purpose of  the PAO,  the proposed  stages of work and the owner’s rights and obligations. 

25. Once the future of the Punt Road PAO is resolved there will be a need to bring urban planning  in  the  corridor  into  step.    The  Committee  recommends  that  the  Cities  of Stonnington  and Melbourne,  in  consultation  with  VicRoads  and  other  agencies  as required,  should develop an  integrated  land use and  transport  strategy  for  the Punt Road corridor that addresses: 

The impact of future road widening on the development potential of land abutting Punt Road 

Restrictions  on  direct  property  access  to  Punt  Road  for  future  development  in favour of access via other roads 

Preferred  urban  design  outcomes,  including  improved  pedestrian/bicycle  access and landscaping. 

14.2 Recommendations 

Based on these findings, and in response to the Terms of Reference, the Committee makes the following recommendations: 

The Public Acquisition Overlay 

A Public Acquisition Overlay should be  retained  to  the extent  required  to ensure 1.that Punt Road can continue to fulfil its role in the short, medium and long term. 

On  the  basis  of  the  evidence  and  submissions  provided  to  the  Committee  in 2.relation  to  traffic demand and  the  future  role of Punt Road  in  the  road network, the Committee recommends: a) VicRoads develop a more detailed design layout that generally accords with 

the Modified  Concept  5  as  shown  in  Appendix  E, minimising  impacts  on heritage properties and minimising overall land acquisition whilst providing for a safe and functional design 

b) The Punt Road Public Acquisition Overlay should be modified to provide for a  road  layout  generally  in  accordance with  the design based on Modified Concept 5. 

The Committee notes  that  Infrastructure Victoria  is currently preparing a 30 year 3.Infrastructure  Plan  for  Victoria,  and  recommends  that  the  Committee’s assumptions regarding the future strategic role of Punt Road are confirmed before a final decision to remove the balance of the Punt Road Public Acquisition Overlay. 

If  the Committee’s assumptions are confirmed,  then  the Committee  recommends 4.removal of the balance of the Public Acquisition Overlay not required to implement the final approved road configuration. 

Other actions recommended for Stonnington and Melbourne Councils  

The Cities of Stonnington and Melbourne,  in consultation with VicRoads, develop 5.an  integrated  land  use  and  transport  strategy  for  the  Punt  Road  corridor  that addresses: 

Page 140: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 134 of 162 

 

The  impact of  future  road widening on development potential of  land abutting Punt Road; 

Restrictions  on  direct  property  access  to  Punt  Road  for  future development in favour of access via other roads; and 

Preferred  urban  design  outcomes,  including  improved pedestrian/bicycle access and landscaping. 

Other actions recommended for VicRoads 

In order to improve certainty for landowners, VicRoads should: 6.

Define  the Public Acquisition Overlay  required  for  the  future widening of  Punt  Road  according  to  its  priority,  that  being  short  (0‐5  years), medium (5‐15 years) and long term (15+ years). 

Adopt a more flexible arrangement with regards to works owners could undertake to their properties, particularly properties  identified as  long term priorities  and develop  guidelines  to  clearly  identify  the  range of works that may be permitted and the conditions that would apply. 

Give priority  to  acquiring properties  that  are  identified  as  required  in the short and medium term, or at least give these property owners the option of acquisition. 

Prepare a Punt Road Public Acquisition Overlay Fact Sheet which simply and concisely outlines the strategic context of Punt Road, the purpose of the Public Acquisition Overlay, the proposed stages of work and the owner’s rights and obligations. 

Page 141: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 135 of 162 

 

15 Response to Terms of Reference 

Paragraph 28 of the Terms of Reference set out the outcomes required of the Committee’s report: 

a summary and an analysis of the submissions received and a  list of those consulted 

an analysis of the issues identified by the Committee 

recommendations to retain, modify or remove the overlay 

any other related matters that the Advisory Committee sees fit. 

The following table provides a summary of where these matters are addressed in the report: 

ToR Requirement  How addressed  Reference 

Summary of submissions and those consulted 

List of submitters 

List of parties to the Hearing 

Summary of issues raised 

Appendix A 

Appendix B  

Section 2.1 

Analysis of issues identified 

Legislative and strategic context 

The strategic importance of Punt Road 

Economic issues 

Traffic and transport issues 

Heritage issues 

Environment issues 

Social issues  

Impacts on strategic growth objectives 

Other issues raised in submissions 

Chapter 5 

Chapter 6 

Chapter 7 

Chapter 8 

Chapter 9 

Chapter 10 

Chapter 11 

Chapter 12  

Chapter 13 

Recommendations on whether to retain, modify or remove the overlay 

Findings  

Recommendations  

Summary 

Chapter 14 

Chapter 14 

Executive Summary 

Other matters  The Committee has made comment on a range of other matters throughout the report and in the Findings.  Of particular note are: 

Fairness and equity 

Certainty 

Impacts on the community 

The cost of property acquisition 

Compensation 

Recommendations have been made in relation to improving certainty for landowners  

  

 

Chapter 11 

Chapter 11 

Chapter 11 

Chapter 13 

Chapter 13 

Recommendation 6 

Table 5  Response to Terms of Reference 

 

Page 142: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 136 of 162 

 

Appendix A  Submitters to the Advisory Committee 

No.  Submitter 

1  Marcelle Damicoucas 

2  George Damicoucas 

3  Daniel Lehrer 

4  Deborah Claydon 

5  Luyi Chen 

6  Kay Elizabeth Martin 

7  Linley O'Neill 

8  Ursula Anne O'Connor 

9  Yos Bilu 

10  Vivian Bilu 

11  Jay Wilson 

12  Ondine Childs 

13  Ann Oldfield 

14  Laurel Kanost 

15  Rebecca Cleaver 

16  Fiona Chin 

17  Warrick Paddon 

18  Harrison Cleaver 

19  Rita Price 

20  Ursula Wertheim 

21  Effie Tsarprias 

22  Spiros Polimenakis 

23  Maria Polimenakis 

24  Thomas Price 

25  Simone Heydon 

26  Marc Corley 

27  Alfred Health 

28  David Howell Williams 

29  Melvyn Soo 

30  Terence Bartels 

31  Michael Wall 

Page 143: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 137 of 162 

 

No.  Submitter 

32  Linda Wilson 

33  Barbara Chia 

34  David Brockway 

35  Sarah Overliese 

36  Naomi Eros 

37  Grant Edhouse 

38  Abi O'Neill 

39  Richard William Wortley Lovell 

40  Nick Heydon 

41  Bernard Corr 

42  Krassin Pty Ltd 

43  Wani Wall 

44  Christine Sender 

45  Clare Kelder 

46  Mike Gould 

47  Felicity Gould 

48  William Bateman 

49  Carmel Bateman 

50  Shem Kelder 

51  Lisa Godinho 

52  Zebe Haupt 

53  Zane Haupt 

54  Jule Langhammer 

55  Lily Feiner 

56  Michelle McClurg 

57  Arthur Rabavilas 

58  Angela Bromilow 

59  Jennifer Berry 

60  Jennifer Berry 

61  Jennifer Berry 

62  Jennifer Berry 

63  Drop Punt 

 

Page 144: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 138 of 162 

 

No.  Submitter 

64  Bernadette Peace 

65  Rosie Currell‐Paynting 

66  David Graham 

67  Zoe Nicole Allatson 

68  Martin Karpowicz 

69  Hayley Margaret Patricia Guest 

70  Simon Allatson and Susie Warwick 

71  Brian Stanley Hauser 

72  Natalie Doherty 

73  Jeremy Wright 

74  James McDonald 

75  Fatima Hussein 

76  Ahmed Hussein 

77  Jenny K Phillips 

78  Margaret Perkins 

79  Pearl Perkins 

80  Ellen Creswell 

81  Suzanne Keogh 

82  Di Nash 

83  Debra Mathias 

84  Catherine Buckmaster 

85  David Sargentson 

86  Carl Hamilton on behalf of No 4 Gordon Grove Pty Ltd 

87  Annette Pearse 

88  Tom Cooper 

89  Trent Schmidt 

90  Mardi Doherty 

91  Helen Doherty 

92  Brian Doherty 

93  Ross Doherty 

94  Liz Doherty 

95  Wendy Widmer 

 

Page 145: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 139 of 162 

 

No.  Submitter 

96  Sophie Cooper 

97  City of Stonnington 

98  Alexandra Ashton 

99  Alexandra Ashton on behalf of Body corporate of 1 Greville Street 

100  City of Melbourne 

101  Steven Woodford 

102  Angela Katrina Bexon 

103  Christ Church Grammar School 

104  Lynne Davies 

105  Glossop Town Planning on behalf of 484‐486 Punt Road, South Yarra; 262A Domain Road, South Yarra; 1A Gordon Grove, South Yarra; 255 Domain Road, South Yarra 

106  Stephen Langhammer 

107  Peter Kamberis 

108  Paola Teresa Rossetti 

109  Peter Aulich and Louise Sweetland‐Aulich 

110  Shirley Ellen Williamson 

111  Peter Cotter 

112  Angela A Wood 

113  Vanessa Forrest 

114  Karen Grant 

115  Tract on behalf of residents of 5 Northampton Place, South Yarra 

116  James Gilchrist 

117  Tristan Quinn 

118  Edmund Carew 

119  Jermain Koh 

120  Barbara Kelly 

 

Page 146: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 140 of 162 

 

Appendix B  Parties to the Hearings 

Submitter  Represented by 

VicRoads  Ms Juliet Forsyth of Counsel instructed by Mr Rory O’Connor of Norton Rose Fulbright who called the following expert witnesses: ‐ Mr Paul Carter and Mr Jonathon Kinghorn on 

Transport ‐ Mr Reece Humphreys on Traffic Engineering 

and Transport ‐ Mr Rob Milner on Planning ‐ Mr Andrew Kinnaird on Economic/valuation 

Melbourne City Council  Ms Sarah Porritt of Counsel and calling expert evidence from ‐ Ms Knowles Tivendale on Traffic and Transport ‐ Mr Ian Shears on Open Space 

Stonnington City Council  Ms Jane Sharp of Counsel 

Residents of 5 Northampton Place  Tract Consultants 

Ms Jenny Phillips   

Ms Ann Oldfield   

Mr Peter Aulich and Ms Louise Sweetland‐Aulich   

Christ Church Grammar School   

Ms Hayley Guest   

Ms Linda Wilson   

Mr Barbara Chia   

Drop Punt  Mr Andrew Carrasco and others 

Ms Paula Dwyer and Mrs Georgie Hockings  A number of property owners, and calling expert evidence from: ‐ Mr Jim Higgs on Traffic Engineering 

Mr Jay Wilson   

Ms Vivian Bilu   

Mr Yos Bilu   

Mr Richard Lovell and Ms Kerry Gartland   

Ms Shirley Williamson   

Mr Nick Heydon and Ms Simone Heydon   

Ms Angela Wood   

Mr Simon Allatson and Ms Susie Warwick   

Ms Zoe Allatson   

Mr Brian Hauser   

Page 147: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 141 of 162 

 

Appendix C  Document list 

No.  Date  Description  Presented by 

1  09/02/16  Stonnington City Council meeting agenda for 8 Feb 16 and relevant attachments 

Stonnington City Council /  Ms Porritt 

2  09/02/16  VicRoads’ submission documents  VicRoads / Ms Forsyth 

2.1  09/02/16  Planning Maps and Aerials  VicRoads / Ms Forsyth 

2.2  09/02/16  Extracts from relevant legislation and Stonnington Planning Scheme: 

Clause 45.01  ‐ Public Acquisition Overlay Stonnington Planning Scheme 

Sections 98‐99 Planning and Environment Act 1987 

Sections 6‐13 Transport Integration Act 2010 

Clause  18  ‐  State  Planning  Policy  Framework  ‐ Transport, Stonnington Planning Scheme 

VicRoads / Ms Forsyth 

2.3  09/02/16  Extracts from VicRoads Part A submission: 

Figure 3: Preferred Traffic Routes 

Figure 4: Road Use Hierarchy Map  

Extract from ARUP Options Report: 

Figure 14: Network Strategy {Traffic) 

VicRoads / Ms Forsyth 

2.4  09/02/16  Submission from Public Transport Victoria dated 5 Feb 16  VicRoads / Ms Forsyth 

2.5  09/02/16  VicRoads Bicycle Network Plans and Fact Sheets  VicRoads / Ms Forsyth 

2.6  09/02/16  VicRoads Air Quality information sheet and screening tool workbook extracts for options 1‐7 

VicRoads / Ms Forsyth 

2.7  09/02/16  VicRoads Traffic Noise Reduction Policy (2005)  VicRoads / Ms Forsyth

2.8  09/02/16  Plan Melbourne and Plan Melbourne (Refresh) extracts  VicRoads / Ms Forsyth 

2.9  09/02/16  Report on Advances and Trends in Traffic and Transport  VicRoads / Ms Forsyth 

2.10  09/02/16  Department of Treasury and Finance Ministerial Briefing dated 19 Jan 15 (Extracts) 

VicRoads / Ms Forsyth

2.11  09/02/16  Punt Road clearways ‐ notice to residents and media releases dated 1 Feb 16 

VicRoads / Ms Forsyth

Page 148: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 142 of 162 

 

No.  Date  Description  Presented by 

2.12  09/02/16  Aboriginal and European Cultural Heritage (Maps, Citations, Reports) 

VicRoads / Ms Forsyth

2.13  09/02/16  Streamlining Hoddle Street Initiative ‐ Information & Hoddle Street Study, VicRoads (October 2015) 

VicRoads / Ms Forsyth

2.14  09/02/16  VicRoads  SmartRoads brochure (July 2011)  VicRoads / Ms Forsyth

2.15  09/02/16  VicRoads Traffic Monitor 2012 ‐ 2013  VicRoads / Ms Forsyth

2.16  09/02/16  VicRoads Memorandum ‐ modification of the PAO (February 2016) 

VicRoads / Ms Forsyth 

2.17  09/02/16  Punt Road Community Engagement Report, Capire (December 2015) 

VicRoads / Ms Forsyth 

3  09/02/16  Expert witness report: Milner (10 Consulting Group)  VicRoads 

4  09/02/16  Hard copy of Kinghorn & Carter (Arup) overheads  VicRoads 

5  09/02/16  Expert witness report: Kinghorn & Carter (Arup)  VicRoads 

6  10/02/16  VicRoads submissions    VicRoads /Ms Forsyth 

7  10/02/16  Hoddle Street – Punt Road Corridor Investigations Report  VicRoads 

8  10/02/16  Expert witness report: Humphreys (GTA)  VicRoads 

9  10/02/16  Table & graph of Punt Road Peak Hour traffic volumes  VicRoads 

10  10/02/16  SmartBus – Estimated patronage fact sheet  MCC 

11  11/02/16  Expert witness report: Kincaid (Urbis)  VicRoads 

12  11/02/16  Melbourne City Council reference documents – summary  MCC 

13  11/02/16  Melbourne City Council submissions and relevant attachments 

MCC / Ms Porritt 

14  11/02/16  Evidence statement: Shears (MCC)  MCC 

15  11/02/16  Shears PowerPoint presentation slides ‐ hardcopy  MCC 

16  11/02/16  Evidence statement: Tivendale (Phillip Boyle & Assoc.)  MCC 

17  11/02/16  Tivendale PowerPoint presentation slides ‐ hardcopy  MCC 

18  16/02/16  Supplementary submission to matters raised by Committee 

VicRoads 

19  16/02/16  Aerial photograph of 440 Punt Road  VicRoads 

20  16/02/16  Stonnington supporting documents folder  SCC / Ms Sharp 

21  16/02/16  Stonington City Council submissions  SCC / Ms Sharp 

22  16/02/16  Submission by residents of 5 Northampton Place  Ms Murphy (Tract) 

23  18/02/16  Submission by Jenny Phillips  Jenny Phillips 

Page 149: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 143 of 162 

 

No.  Date  Description  Presented by 

24  18/02/16  Submission by Ann Oldfield  Ann Oldfield 

25  18/02/16  Submission by Louise Sweetland  Louise Sweetland 

26  18/02/16  Drop Punt submission slides ‐ hardcopy  Drop Punt,  Mr Carrasco 

27  18/02/16  Buildings of Architectural and Historical Importance  Drop Punt 

28  18/02/16  Paper – The Local Community  Drop Punt 

29  18/02/16  Paper – Easy Access to Green Space  Drop Punt 

30  18/02/16  Documentation for film  Drop Punt,  Mr Heydon 

31  19/02/16  Submissions by Paula Dwyer  Dwyer, Ms Hocking 

32  19/02/16  Expert witness report: Higgs (TTM)  Dwyer, Ms Hocking 

33  19/02/16  Australian Infrastructure Plan  VicRoads 

34  19/02/16  Submission by Vivian Bilu  Vivian Bilu 

35  19/02/16  Submission by Yos Bilu  Yos Bilu 

36  19/02/16  Submission by Jay Wilson  Jay Wilson 

37  19/02/16  Submission by Kerry Gartland  Kerry Gartland 

38  19/02/16  Submission by Richard Lovell  Richard Lovell 

39  19/02/16  Submission by Shirley Williamson  Shirley Williamson 

40  19/02/16  Stonnington City Council Delegates reports  SCC / Ms Sharp 

41  19/02/16  Submission by Simon Allatson and Susie Warwick  Simon Allatson & Susie Warwick 

42  19/02/16  Submission by Zoe Allatson  Zoe Allatson 

43  19/02/16  Submission by Nick and Simone Heydon  Nick & Simone Heydon 

44  19/02/16  VicRoads closing submission  VicRoads/  Ms Forsyth 

45  19/02/16  Government data: boardings and alightings for Bus 246  VicRoads 

46  19/02/16  Real estate brochures  VicRoads 

 

Page 150: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 144 of 162 

 

Appendix D  Terms of Reference  

Page 151: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

1 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

 

Terms of Reference 

Punt Road Public Acquisition Overlay Advisory Committee Advisory Committee appointed pursuant to Part 7, Section 151 of the Planning and Environment Act 1987 to report and recommend on whether to retain, modify or remove the Public Acquisition Overlays affecting Punt Road within the City of Stonnington. 

Version: Revised 11 August 2015 

Name 

1. The  Advisory  Committee  is  to  be  known  as  the  “Punt  Road  Public  Acquisition  Overlay  Advisory Committee’ 

2. The Advisory Committee  is to comprise three members with strategic planning, road and transport planning, traffic engineering and land use economics skills. 

Purpose 

3. The purpose of  the Advisory Committee  is  to  review  the  future of  the  Public Acquisition Overlay (overlay) affecting properties within the City of Stonnington on the east side of Punt Road along the 2.6 kilometres between Alexandra Avenue, South Yarra and Union Street, Windsor (Attachment) by seeking  input  from  affected  landowners,  stakeholders  and  agencies  and  to  recommend  to  the Minister for Planning whether to retain, modify or remove the overlay. 

Background 

4. Punt Road/Hoddle Street is one of Melbourne’s busiest and most congested key arterial roads.  Punt Road/Hoddle  Street  links  Clifton  Hill/the  Eastern  Freeway  in  the  north  with  St  Kilda Junction/Dandenong Road  in the south and provides regional road access to many State significant facilities. 

5. Punt Road is a declared State arterial road and is used by around 33,000 vehicles per day1.  It forms a boundary between the Cities of Melbourne and Stonnington.  

6. This  review  relates  to Punt Road  south of  the Yarra River within  the City of  Stonnington which  is narrower than Punt Road/ Hoddle Street north of the Yarra River. 

7. The  original  1954  planning  scheme  identified  the  intention  to widen  the  east  side  of  Punt  Road between Alexandra Avenue, South Yarra and Union Street, Windsor.   A 20 metre wide overlay  for proposed  road widening affecting 140 properties  is  included  in  the Stonnington Planning Scheme.  The overlay also affects 49 and 51 Alexandra Avenue, South Yarra (refer attachment). 

8. The purpose of a overlay is: 

“To implement the State Planning Policy Framework and the Local Planning Policy Framework, including the Municipal Strategic Statement and local planning policies. 

                                                       1 Source: VicRoads two way traffic count Punt Road (South Yarra) between Alexandra Avenue and Domain Road 2013) 

https://www.vicroads.vic.gov.au/traffic‐and‐road‐use/road‐network‐and‐performance/road‐use‐and‐performance 

Page 152: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

2 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

To  identify  land which  is proposed to be acquired by a Minister, public authority or municipal council. 

To reserve land for a public purpose and to ensure that changes to the use or development of the land do not prejudice the purpose for which the land is to be acquired. 

To designate a Minister, public authority or municipal council as an acquiring authority for land reserved for a public purpose.” 2 

9. VicRoads has the power to compulsorily acquire properties within the overlay if required as it is the nominated acquisition authority.  The provisions of the Land Acquisition and Compensation Act 1986 and the Planning and Environment Act 1987 provide landowners with access to compensation due to the overlay being  in place.   This  includes  compensation  for  loss on  sale and  refusal of a planning permit by council if directed by VicRoads as a referral authority.  

10. VicRoads has purchased a small number of affected properties and no funding has been allocated for construction of the road widening to date.  

11. The Government wishes  to provide  certainty about  this matter as  some affected property owners wish to plan for the future of their properties and are concerned about whether the road widening will be going ahead. 

Method 

12. The Advisory Committee must undertake the review in accordance with the following four stages but may inform itself in any other way it sees fit: 

Stage 1: VicRoads Background Report 

13. VicRoads has been requested to prepare a background report to provide base  information to assist with this review.  The background report will include information about: 

the history of and background to the road widening/ the overlay 

detailed mapping of the overlay 

the  current  and  projected  traffic  volumes  for  all modes  of  transport,  including  pedestrian, cyclist, car, heavy and public transport along and near Punt Road 

the current and projected regional road and transport network operation 

the current and possible future configurations of Punt Road with and without the overlay 

the current land use and built form of land subject to the overlay 

the current public transport along and crossing Punt Road 

the current planning controls 

the benefits (advantages) and costs (disadvantages) of retaining the overlay 

the benefits (advantages) and costs (disadvantages) of removing the overlay, including possible alternate road and transport network response 

whether any modifications to the overlay are necessary. 

14. This report must be made public and be available on the Department’s website. 

   

                                                       2 Clause 45.01 Stonnington Planning Scheme 

Page 153: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

3 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

Stage 2: VicRoads Options Report 

15. VicRoads is preparing an Options Report that will expand on the Background Report by including traffic modelling and projections for various future options along Punt Road. 

16. This report must be made public and be available on the Department’s website prior to commencing Stage 3. 

Stage 3: Request for Submissions 

17. Following  the  release  of  the  Options  Report,  the  Advisory  Committee must  invite  and  consider submissions from: 

all  landowners  along both  sides of Punt Road between Alexandra Avenue,  South  Yarra  and Union Street, Windsor 

the Cities of Stonnington, Melbourne, Yarra and Port Phillip 

relevant agencies (including VicRoads, Public Transport Victoria, the Department of Economic Development, Jobs, Transport and Resources, and Heritage Victoria) 

any other persons or organisations that the Advisory Committee see fit 

18. The Department of Environment,  Land, Water and Planning will assist  the Advisory Committee  to notify  these  persons  and organisations by  letter  and  through  advertisements  in  local newspapers circulating in the area.  Planning Panels Victoria will receive and store all submissions. 

Stage 4: Public Hearing 

19. The Advisory Committee must hold a public hearing inviting submitters to present their submissions.  In holding  the public hearing,  the Advisory Committee  is bound by  the  rules of natural  justice but may regulate its own proceedings by: 

Limiting the time for presentations by persons or organisations appearing before it 

Prohibiting or regulating cross examination. 

20. The  conduct  of  the  public  hearing must  be managed  by  the  Chairperson.    The  Chairperson may regulate  proceedings  in  a manner  that  he/she  considers  appropriate  to  best  allow  the  Advisory Committee to inform itself, and may give directions as to the conduct of the public hearing. 

21. In scheduling the public hearing, the Advisory Committee must provide any submitter a reasonable opportunity to make submissions on a public hearing matter, having regard to both its task and time requirements under the Act. 

22. The form of the presentation of any submissions which the Advisory Committee will be provided with may be the subject of direction by the Advisory Committee. 

23. Questioning of submitters and any expert witnesses must be controlled, and conducted primarily, by the Advisory Committee.   At  its discretion  the Advisory Committee may accept questions  received either verbally or  in writing  from participants at  the public hearing.   The Advisory Committee may prohibit or regulate such cross‐examination if it considers that it is necessary or appropriate to do so in order to assist it to undertake its task. 

24. VicRoads must be given an opportunity to respond to submissions made during the public hearing at the conclusion of the public hearing. 

Stage 5: Advisory Committee Report 

25. In  considering whether  to  recommend  retaining, modifying or  removing  the overlay,  the Advisory Committee must consider: 

   

Page 154: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

4 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

the VicRoads background report 

the VicRoads options report 

the views of submitters included in their submissions and stated at the public hearings 

relevant documents  including the Stonnington Planning Scheme, the Network Operating Plan for Stonnington,  the Principle Bicycle Network, public  transport strategic plans, and heritage reports. 

the effect on the long term planning and operation of the arterial road system in the region for all users. 

26. The Advisory Committee may operate with a quorum of at least two members, one of whom must be the Chairperson. 

27. The Advisory Committee may ask the Minister for Planning to vary these terms of reference prior to submission of its report. 

Outcomes and Timing 

28. The Advisory Committee must submit a written report to the Minister for Planning, including: 

a summary and an analysis of the submissions received and a list of those consulted 

an analysis of the issues identified by the Committee 

recommendations to retain, modify or remove the overlay 

any other related matters that the Advisory Committee sees fit. 

29. The indicative timelines for the review are: 

Stage  Indicative Timeline 

1. Advisory Committee receives VicRoads Background Report for public release 

Date of release Expected mid August 2015 

2. Advisory Committee receives VicRoads Options Report for public release 

Date of release Expected October 2015 

3. Request for submissions issued  + 1 month 

4. Public hearing commenced  + 1 months 

5. Advisory Committee Report sent to Minister for Planning  + 3 months3 

Submissions and the Advisory Committee report will be public documents 

30. The  Advisory  Committee  must  retain  a  library  of  any  written  submissions  or  other  supporting documentation provided to it in electronic form. 

31. Any written  submissions or other  supporting documentation provided  to  the Advisory Committee must be available for public inspection in electronic format until the submission of its report, unless the Advisory Committee specifically directs that the material is to remain ‘in camera’. 

32. The full report and recommendations of the Advisory Committee will be made public along with the decision of the Minister for Planning. 

                                                       3 The Advisory Committee must submit  its written report with recommendations to the Minister for Planning as soon as practicable but no  later 

than 40 business days from the completion of its hearings. 

Page 155: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

5 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

Fees 

33. Fees for the Advisory Committee will be set at the current rate for a panel appointed under Part 8 of the Planning and Environment Act 1987. 

34. The costs of the Advisory Committee and any necessary research will be met by the Department of Environment, Land, Water and Planning. 

Project Manager 

35. Department  of  Environment,  Land,  Water  and  Plan  and  Planning  Panels  Victoria  will  provide administrative  and professional  support  to  the Committee.   The Advisory Committee may engage additional  administrative  and/or  professional  support  if  required  with  the  prior  approval  of  the Deputy Secretary Planning, Department of Environment, Land, Water and Planning. 

36. Day  to  day  liaison  for  the  Advisory  Committee will  be  through  Greta  Grivas  of  Planning  Panels Victoria on telephone 03 8392 6393 and e‐mail [email protected]

37. Day  to day  liaison  for  the Department of Environment, Land, Water and Planning will be  through Andrew  Widdicombe,  Principal  Project  Manager  on  telephone  03 9094 8442  and  e‐mail [email protected]

 

 

Page 156: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

6 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

Attachment:  Maps showing Public Acquisition Overlay along Punt Road (Stonnington Planning Scheme) 

 

Page 157: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

7 of 7  Punt Road Public Acquisition Overlay Advisory Committee  Terms of Reference 

 

 

 

Page 158: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

 

Page 152 of 162 

 

Appendix E  Modified Concept 5  

Page 159: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 153 of 162 

 

 

Page 160: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 154 of 162 

 

 

Page 161: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 155 of 162 

 

 

Page 162: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 156 of 162 

 

 

Page 163: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 157 of 162 

 

Appendix F  Heritage map 

Page 164: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 158 of 162 

 

 

Page 165: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 159 of 162 

 

 

Page 166: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 160 of 162 

 

 

Page 167: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 161 of 162 

 

 

Page 168: Planning and Environment Act 1987...good urban design outcomes, enhanced public transport usage, improved pedestrian safety and experience and consideration of impacts on sites of

Punt Road Public Acquisition Overlay  Advisory Committee Report  30 May 2016 

Page 162 of 162