plan- x1 meeting no. 4 – 27/04/10 at ncra auditorium, pune gmrt servo system plan x1 target...
TRANSCRIPT
Plan- x1 meeting no. 4 –27/04/10 at NCRA Auditorium, Pune
GMRT SERVO SYSTEM PLAN X1 TARGET implements :
1a) Brushless drives1b) PC-104 Servo computer
1c) Generic antenna Controller unit (GACB)1d) Solid state interface logic– SSI
1e) Feed position system – 6U04/19/23 1dec 2008
04/19/23 dec 2008 2
Brushless drive … work planned for 2k8-9
04/19/23 dec 2008 3
• One antenna system testing with test setup (simulating the actual dual drive of either azimuth or elevation axis) in progress in LAB.
…..Completed in MTAC period 2010 both in: a) position loop mode b) Velocity loop mode. Overall position accuracy matches with the test report of
Leopold •
• Installation and commissioning on antenna by end 2008
…….Documentation / computation of test plots/results in progress to arrive at performance parameters like a) bandwidth b) resonant frequency• Two more antenna systems procurement, testing and installation by March 2009……. Purchase order placed in feb 2010 for 4 more systems
Brushless drive … work planned for 2k10-11
• Test Large test setup by interfacing SSC to BLDC and later with PC-104
• On successful completion of the above, test antenna - C04 with BLDC + PC-104
• Leave the unit at C04 for Observation and feedback from Engineering group / GTAC users.
• Assemble one antenna bldc system in a 19” rack for minimising RFI emanating from the drives.
• Test / Measure the RFI after the rack is assembled and submit for acceptance and approval for mass production
Block Diagram ….BLC configured in position loop
Position Error in arcsec with i522=0.1cts/ms pr 6.66 rpm
-3
-2.5
-2
-1.5
-1
-0.5
0
0.5
1
1.5
2
2.5
0 1 2 3 4 5 6 7 8 9 10
Time(Sec)
Po
siti
on
Err
or
in a
rcse
c
Posn.error = +/- 1.6sec
Block Diagram ….BLC configured in velocity loop
Summary of load velocities for different scale factors in Algorithm
Analog i/p – to ADC
Velocitycmd.Scale factor
Load vel.In cnts/sec
Load vel. In deg/min
RemarksVelocity error
10 V 5 350 2
10 V 63 4500 30 +/- 0.02 ‘sec/s
10 V 100 7500 50
LoadVelocity (deg/min) with ADC=10V(10V=32767cts or 2200 rpm) and Cmdvel Scaling factor(P9)=63
-40
-20
0
20
40
60
80
100
0 0.2 0.4 0.6 0.8 1 1.2 1.4
Time(sec)
Lo
adve
loci
ty(d
eg/m
in)
Velocity Error in arcsec/sec with P9=63 and ADC=10V
25.11
25.112
25.114
25.116
25.118
25.12
25.122
25.124
25.126
0 0.2 0.4 0.6 0.8 1 1.2 1.4
Time(sec)
Velo
city
Err
or in
arc
sec/
sec
Gear box being hauled up to the setup
04/19/23 12dec 2008
Generic Antenna Board Functional Block Diagram
PC104 Master PC104 Slave104 lines in
Parallel
Addr/data busbuffers
Addr/data busbuffers
CPLD 2
CPLD 1
AIPsection
DIP section
Encoder Interface
AOPsection
DOP section
SPIInterface
QUADUART
CANcontroller
K/B,mouse
VGA USB
TCP/IP
3 x RS232
RS422/RS485
BLDC Drives
PMDC Drives
Field Sig.
FieldSig.
FieldSig.
Sensors
Front Front PanelPanel
(Maintena(Maintenance)nce)
RS232
Add. lines Data lines
Generic Antenna Controller – GAC plan status and projections – 2k10-11
• 1. Generic Antenna Controller Board FY 2009-10 : Work done : • Specification on a new integrated Generic antenna Controller board is
finalisedthis year and a detailed design exercise was undertaken in active collaboration with BARC's Control and Instrumentation division.• The design has been completed and frozen.
• PCB layout work with a vendor is in progress currently. It is expected to finalize the layout work by Sept 2010.
• The boards are expected to be populated by Oct 2010 and tests would start in
Oct2010. Antenna tryouts are likely by the end of this financial year.
04/19/23 dec 2008 14
Solid State Interlocks – SSI plan status and projections – 2k10-11
• FY 2009-10 : Work Done :
• --- SSI systems were installed on ----- antennas in this financial• years, taking number of antenna with SSI to 22 including 1 prototype • board. In addition, work was undertaken to get fresh PCBs ready for• 10 antennnas and the population of these PCBs is in progress. It is• expected to get 10 systems ready and tested in the coming financial• year and install at least 08 systems on antennas, subject to availabilty• of antennas during GTAC cycle.
04/19/23 dec 2008 15
PC-104 • FY 2009-10 : works planned / done
• Development of Graphic user Interface – GUI developed for monitoring, data logging from antenna base.
• Make RFI measurements and Cabinet vendor identification in progress
• Performance checks after installation for one GTAC cycle
compensator extensively tested at C02, Antenna test plan report generated to validate the code during the antenna installation,added a state machine “calibrate”
04/19/23 dec 2008 16
Pc-104 works planned 2k10-11
• Extensive testing from CEB thro’ ABC• Performance evaluation of pc-104 during
GTAC observation….2 weeks• Interfacing with BLDC at Rayshed/JOgshed
with simulated load• Actual interface with BLDC at antenna base
and control from CEB• Make RFI enclosure
Budget Utilisation in Lakhs(Rs) & proposed
Activity Plan 2k9-10 Actual Plan 2k QTY
10-11 Rs Lacs
BLDC 5 ants(150.00)
4 ants(145.78)
6 # ( 250.00 )
PC-104 &GACB
30 & 5 ants( 25.00)
Prototype( 2.04)
10 # 5 # ( 30.00 )
BL Drive ( indig) --------- ----------- 2 nos ( 20.00)
Lab eqp . (10.00) ( 4.70)
Fps – 6U &Angle enc.
10ants &5#( 10.00 )
10ants ( 6.90)
10 ants5 #
( 10.00 )
SSI 15 ants 22ants( 2.00 )
08 ants ( 2.00)
Lightning protection
---------- 01 ant(4.00 )
------ NIL
DC ServoMotor magnet
5 nos ( 10.00 )
--------- 5 # ( 10.00 )
Thank you 04/19/23 April 2010 19