Placing Curing Good concrete is concrete that has been placed, compacted and cured properly. In simple terms, poor compaction and poor curing – singly or together – produce poor concrete with lower strength and lower durability. By following the procedures below, you will ensure the concrete has the potential to achieve its design strength. Before any concrete is placed, rigid, level and clean formwork must be in position and accessible. And you must have all the right equipment ready. If the truck mixer cannot discharge directly into the forms, you will need skips, barrows or pumps. And you will also require pokers, external vibrators or vibrating beams to compact the concrete after placing. Check what testing is required. (See Site Sampling and Testing poster. ) Place the concrete carefully in a series of layers of roughly equal depth – normally 300-500 mm – and compact each layer with a vibrator. Never let the mix pile up in large heaps or sloping layers. Deep beams and columns With deep walls and columns, don’t let the concrete free-fall more than about one metre unless the mix has been designed to be dropped. Instead, use ‘letterboxes’, a tremie pipe or a pump for placing. Ensure that poker hoses and power lines are long enough to reach the work. To avoid tie-bolts, lift the poker out and re-insert. With small columns, it is tempting to pour the concrete in faster than it can be compacted. So use a banker board and shovel, and lower the poker down before adding each 300 mm depth of concrete. Generally, small columns will not have enough room for more than one poker to be used and it is even sensible to use a single poker for larger columns, removing and re-inserting as necessary. Slab formwork Slab formwork should be overfilled by around 15 mm to allow for settlement. Experience will dictate how much surcharge is needed, depending on the thickness of the slab. However, if light mesh is required near the top of the slab, do not overfill. Instead, tamp the concrete to mesh level with a notched beam, and then lay the reinforcement, cover with more concrete (including a little surcharge), compact and finish. Never tread on the mesh. Compacting All fresh concrete contains tiny bubbles of air. If nothing is done to get rid of them, the resultant blowholes or honeycombing weaken the finished concrete and make it less able to resist water penetration. They can also reduce the bond between the concrete and reinforcement. In general, concrete in the truck has an air content of around 20% and this needs to be reduced to between 2% and 5%, depending on the mix, by vibration. Every 1% of trapped air reduces the concrete strength by about 6%, so proper compaction is vital. There are three main types of compacting equipment – poker vibrators, external vibrators and vibrating beams. When is compaction complete? Compaction is complete when bubbles stop rising to the surface When using a poker, you can also tell by the fact that the sound of the poker stops changing. And with non-air-entrained concrete, a glistening film of mortar on the surface is another good sign In general, vibrate a bit longer than you think necessary – except for slabs and high- workability mixes, where excessive surface mortar may result Poker vibrators Pokers vary in diameter and length. Since the poker must be able to fit easily between the reinforcement, the spacing will sometimes decide what size of poker is needed. The larger the vibrator, the greater the area it can vibrate and therefore the greater the allowable spacing between successive vibrator positions. Generally the spacing should be around four to six times the poker diameter. Insert the poker so that it penetrates 100mm into the previously compacted layer underneath. Try not to let it touch the formwork or reinforcement. If high-quality finishes are called for, use a rubber-tipped vibrator to prevent formwork ‘burns’. Never use a poker to make concrete flow as segregation may result. Once air bubbles stop rising, take the poker out and re-insert at the next position, making sure the areas overlap. If in doubt, vibrate a little longer. External vibrators When reinforcement is too congested or access too difficult for pokers, external vibrators offer a solution, but formwork will need to be strong enough to withstand the intense vibration. External vibrators are extremely noisy, so wear ear protectors. Compact in 300 mm layers and, where possible, finish the top 600 mm with a poker. Watch out for grout loss through joints, loose vibrators and formwork instability. Vibrating beams Although slabs up to 100 mm thick can be tamped by hand, a vibrating beam drawn across the surface will do the job much better. Slabs thicker than 150 mm should always be compacted by vibrating beams and their edges finished with pokers. With deep slabs and heavily reinforced slabs, start by compacting with pokers and finish with a vibrating beam. Don’t stand on the reinforcement unless it is supported by spacers or stools to stop it bending or moving. With a double vibrating beam, make sure there is a surcharge in front of both beams. One pass should be enough, as further passes may bring excess cement laitance to the top. Remember All compaction equipment must be well maintained, with bearings greased and everything cleaned after use Double-check the security of connections on all air lines and power lines Clear moisture out of air lines before connecting Have a standby vibrator and alternative power supply available Don’t leave pokers in the same spot for too long and switch them off as soon as they are out of the concrete ‘Curing’ is important to preventing concrete from drying out too soon. Well cured concrete is stronger, more resistant to chemical attack and traffic wear, and more watertight. It also withstands freezing and abrasion better. Most curing is done by using polythene sheeting or a sprayed membrane. Leaving the formwork in place is also possible, except for slabs, where the large surface area will soon dry if left unprotected. Curing should always start before the concrete begins to dry out. Covering with polythene sheeting Airtight polythene sheeting is an efficient way of preventing moisture loss. It should be placed on a slab as soon as the concrete is hard enough to prevent surface damage or marking. Exposed edges and corners must be fixed down well to keep out wind and draughts. With columns and beams, the sheeting should be tied with tape or cord. If possible, water-spray the concrete the next day and reseal the polythene. If the slab has a special finish – such as texturing – support the sheeting on lightweight frames to stop it damaging the surface, making sure that all edges are sealed. Applying a sprayed membrane Sprayed membranes are designed to form a superficial seal on the concrete, preventing water evaporating. Be careful when selecting a suitable product, as some prevent subsequent adhesion of screeds or applied finishes. In general, membranes should be applied to damp, not wet, surfaces as they can be absorbed and cause discolouration. If the The first rule of working with concrete is to be protected. Ensure that the personnel are wearing adequate safety equipment If fresh, wet concrete touches the skin, it can cause alkali burns – some of which, don’t cause pain immediately – or dermatitis. The longer the skin is in contact with the concrete, the worse the injury will be. So, protect yourself by wearing safety goggles, waterproof gloves, a sturdy jacket, waterproof trousers and long boots. If concrete does contact your skin, wash surface has dried, dampen it before spraying. For even coverage, apply in two directions at right-angles, with the spray head about 300 mm from the surface. With slabs, a portable walkway may be needed to avoid damage to the concrete surface. immediately and thoroughly with clean water. If your eyes are affected, seek medical help immediately. Remove and wash any protective clothes or boots that become impregnated with fresh concrete, but making sure you wash yourself first. Lifting Fresh concrete is heavy, with a barrow load weighing over 100 kg. So carrying just a small volume may cause physical injury. Follow Health & Safety regulations so that you can place, compact and finish the work before it sets without straining yourself. Poor compacting = poor concrete lower strength lower durability blowholes honeycombing Poor curing = poor concrete lower strength lower durability dusty surface weaker surface All advice or information from The Concrete Centre is intended for use in the UK only by those who will evaluate the significance and limitations of its contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting from such advice or information is accepted by The Concrete Centre or its subcontractors, suppliers or advisors. Readers should note that publications from The Concrete Centre are subject to revision from time to time and should therefore ensure that they are in possession of the latest version. www.concretecentre.com © British Ready Mixed Concrete Association and published by The Conrete Centre on behalf of BRMCA. Produced and printed by The Book on the Wall Company, Kent Edited by A F G Lewis TCC/03/41 May 2008 SAFETY A practical guide for site personnel Placing, compacting and curing concrete Problems to avoid Plastic settlement and voids After concrete is placed and vibrated,‘bleed’ water rises to the surface and the concrete ‘settles’. If this settling is restrained by reinforcement or prestressing ducts, a surface crack may form along the reinforcement.To counter this, one answer is to place concrete up to the underside of the ducts, wait half an hour, re-vibrate and then continue placing and compacting. Re-vibration is fine as long as concrete is still workable enough.To assess this, insert a poker and if it sinks into the concrete and leaves no hole when removed, the concrete can be re-vibrated. In general, the top 600 mm of columns and walls can be re-vibrated between 30-60 minutes after main compaction finishes. Cold joints in mass concrete If freshly placed concrete is left too long before the next layer is placed on top or alongside, the layers may not bond properly, resulting in a weak ‘cold joint’.To help prevent this, place concrete in the sequence shown. Don’t let concrete harden too much before it is covered by the next layer and always re-vibrate before placing the adjacent fresh material. If void formers are to be surrounded by concrete, drill small holes at regular intervals in the former soffit to let air escape.

Upload: lekien

Post on 20-Dec-2016

265 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Placing, compacting and curing concrete

Placing

Curing

Good concrete is concrete that has been placed, compacted and cured properly. In simple terms, poor compaction and poor curing – singly or together – produce poor concrete with lower strength and lower durability. By following the procedures below, you will ensure the concrete has the potential to achieve its design strength.

Before any concrete is placed, rigid, level and clean formwork must be in position andaccessible. And you must have all the right equipment ready. If the truck mixer cannot discharge directly into the forms, you will need skips, barrowsor pumps. And you will also require pokers, external vibratorsor vibrating beams to compact the concrete after placing.

Check what testing is required. (See Site Sampling and Testing poster.)

Place the concrete carefully in a series of layers of roughly equaldepth – normally 300-500 mm – and compact each layer with avibrator. Never let the mix pile up in large heaps or sloping layers.

Deep beams and columnsWith deep walls and columns, don’t let theconcrete free-fall more than about one metreunless the mix has been designed to bedropped. Instead, use ‘letterboxes’, a tremiepipe or a pump for placing.

Ensure that poker hosesand power lines arelong enough to reachthe work.

To avoid tie-bolts, liftthe poker out and re-insert.

With small columns, it is tempting to pourthe concrete in faster than it can becompacted. So use a banker board and shovel, and lower the poker down beforeadding each 300 mm depth of concrete.

Generally, small columns will not haveenough room for more than one poker to beused and it is even sensible to use a singlepoker for larger columns, removing and re-inserting as necessary.

Slab formworkSlab formwork should be overfilled by around15 mm to allow for settlement. Experience will dictate how much surcharge is needed,depending on the thickness of the slab.However, if light mesh is required near the topof the slab, do not overfill. Instead,tamp the concrete to mesh level with anotched beam, and then lay the reinforcement,cover with moreconcrete (includinga little surcharge),compact and finish.Never tread on the mesh.

CompactingAll fresh concrete contains tiny bubbles of air. If nothing is done to get rid of them,the resultant blowholes or honeycombingweaken the finished concrete and make it lessable to resist water penetration. They can alsoreduce the bond between the concrete and reinforcement.

In general, concrete in the truck has an aircontent of around 20% and this needs to bereduced to between 2% and 5%, dependingon the mix, by vibration.

Every 1% of trapped air reduces the concretestrength by about 6%, so proper compactionis vital.

There are three main types of compactingequipment – poker vibrators, external vibrators and vibrating beams.

When is compaction complete?Compaction is complete when bubbles stoprising to the surface

When using a poker, you can also tell by thefact that the sound of the poker stopschanging. And with non-air-entrained concrete,a glistening film of mortar on the surface isanother good sign

In general, vibrate a bit longer than you thinknecessary – except for slabs and high-workability mixes, where excessive surfacemortar may result

Poker vibratorsPokers vary in diameter and length. Since thepoker must be able to fit easily between thereinforcement, the spacing will sometimesdecide what size of poker is needed. The largerthe vibrator, the greater the area it can vibrateand therefore the greater the allowablespacing between successive vibrator positions.

Generally the spacingshould be around four to six times thepoker diameter.

Insert the poker so that it penetrates 100mminto the previously compacted layerunderneath. Try not to let it touch theformwork or reinforcement. If high-qualityfinishes are called for, use a rubber-tippedvibrator to prevent formwork ‘burns’. Neveruse a poker to make concrete flow assegregation may result.

Once air bubbles stop rising, take the pokerout and re-insert at the next position, makingsure the areas overlap. If in doubt, vibrate alittle longer.

External vibrators When reinforcement is too congested oraccess too difficult for pokers, external vibrators offer a solution, but formwork willneed to be strong enough to withstand theintense vibration. External vibrators areextremely noisy, so wear ear protectors.

Compact in 300 mm layers and, where possible, finish the top 600 mm with a poker.

Watch out forgrout lossthrough joints,loose vibratorsand formworkinstability.

Vibrating beamsAlthough slabs up to 100 mm thick can betamped by hand, a vibrating beam drawnacross the surface will do the job much better. Slabs thicker than 150 mm shouldalways be compacted by vibrating beams and their edges finished with pokers.

With deep slabs and heavily reinforced slabs,start by compacting with pokers and finishwith a vibrating beam. Don’t stand on thereinforcement unless it is supported by spacers or stools to stop it bending or moving.

With a double vibrating beam, make surethere is a surcharge in front of both beams.One pass should be enough, as further passesmay bring excess cement laitance to the top.

Remember

• All compaction equipment must be wellmaintained, with bearings greased andeverything cleaned after use

• Double-check the security of connectionson all air lines and power lines

• Clear moisture out of air lines beforeconnecting

• Have a standby vibrator and alternative power supply available

• Don’t leave pokers in the same spot fortoo long and switch them off as soon asthey are out of the concrete

‘Curing’ is important to preventing concretefrom drying out too soon. Well cured concreteis stronger, more resistant to chemical attackand traffic wear, and more watertight. It alsowithstands freezing and abrasion better.

Most curing is done by using polythene sheeting or a sprayed membrane. Leaving theformwork in place is also possible, except forslabs, where the large surface area will soon dry if left unprotected.

Curing should always start before the concretebegins to dry out.

Covering with polythene sheetingAirtight polythene sheeting is an efficient wayof preventing moisture loss. It should beplaced on a slab as soon as the concrete ishard enough to prevent surface damage ormarking. Exposed edges and corners must befixed down well to keep out wind anddraughts.

With columns and beams, the sheeting should be tied with tape or cord. If possible,water-spray the concrete the next day andreseal the polythene.

If the slab has a special finish – such as

texturing – support the sheeting onlightweight frames to stop it damaging the surface, making sure that all edges are sealed.

Applying a sprayed membraneSprayed membranes are designed to form asuperficial seal on the concrete, preventingwater evaporating. Be careful when selecting a suitable product, as some prevent subsequent adhesion of screeds or applied finishes.

In general, membranes should be applied todamp, not wet, surfaces as they can beabsorbed and cause discolouration. If the

The first rule of working with concrete is to

be protected.

Ensure that the personnel are wearing

adequate safety equipment

• If fresh, wet concrete touches the skin, it cancause alkali burns – some of which, don’t

cause pain immediately – or dermatitis.

• The longer the skin is in contact with theconcrete, the worse the injury will be. So,protect yourself by wearing safety goggles,waterproof gloves, a sturdy jacket,waterproof trousers and long boots.

• If concrete does contact your skin, wash

surface has dried, dampen it before spraying.For even coverage, apply in two directions atright-angles, with the spray head about 300 mm from the surface.

With slabs, a portable walkway may be needed to avoid damage to theconcrete surface.

immediately and thoroughly with cleanwater. If your eyes are affected, seekmedical help immediately.

• Remove and wash any protective clothesor boots that become impregnated withfresh concrete, but making sure you washyourself first.

• Lifting Fresh concrete is heavy, with abarrow load weighing over 100 kg. Socarrying just a small volume may causephysical injury. Follow Health & Safetyregulations so that you can place,compact and finish the work before itsets without straining yourself.

Poor compacting =

• poor concrete

• lower strength

• lower durability

• blowholes

• honeycombing

Poor curing =

• poor concrete

• lower strength

• lower durability

• dusty surface

• weaker surface

All advice or information from The Concrete Centre is intended for use in the UK only by thosewho will evaluate the significance and limitations of its contents and take responsibility for its useand application. No liability (including that for negligence) for any loss resulting from such adviceor information is accepted by The Concrete Centre or its subcontractors, suppliers or advisors.Readers should note that publications from The Concrete Centre are subject to revision from timeto time and should therefore ensure that they are in possession of the latest version.

www.concretecentre.com

© British Ready Mixed Concrete Association and published by The Conrete Centre on behalf of BRMCA. Produced and printed by The Book on the Wall Company, Kent Edited by A F G Lewis TCC/03/41 May 2008

SAFETY

A practical guide for site personnel

Placing, compactingand curing concrete

Problems to avoidPlastic settlement and voids

After concrete is placed and vibrated, ‘bleed’ water rises to the surface and the concrete ‘settles’. If this settling is restrained by reinforcement or prestressing ducts, a surface crack may form along the reinforcement. Tocounter this, one answer is to place concrete up to the underside of the ducts, wait half anhour, re-vibrate and then continue placing and compacting.

Re-vibration is fine as long as concrete is still workable enough. To assess this, insert a pokerand if it sinks into the concrete and leaves no hole when removed, the concrete can be re-vibrated. In general, the top 600 mm of columns and walls can be re-vibrated between

30-60 minutes after main compaction finishes.

Cold joints in mass concrete

If freshly placed concrete is left too long before the next layer is placed on top or alongside, the layers may notbond properly, resulting in a weak ‘cold joint’. To help prevent this, place concrete in the sequence shown.

Don’t let concrete harden too much before it is covered by the next layer and always re-vibrate before placing the adjacent fresh material. If voidformers are to be surrounded by concrete, drill small holes at regular intervals in the formersoffit to let air escape.