p.karrivaniaplem foot bridge estimate
TRANSCRIPT
DISTRICT : SRIKAKULAM
CIRCLE : SRIKAKULAM
DIVISION : TEKKALI
SUB-DIVISION : ICHAPURAM
MANDAL : KAVITY
PANCHAYATRAJ ENGINEERING DEPARTMENT
RE-CONSTRUCTION OF FOOT BRIDGE AT P.KARRIVANIPALEM
ESTIMATED COST:-Rs.20.00 lakhs
DETAILED ESTIMATE
Name of the work:-Re-Construction of Foot Bridge at P.Karrivanipalem, Est.Cost:Rs.20.00 lakhs
As per the instructions of the instructions of the Dy.Exe.Engineer,PR,Ichapuram and as per the
request of the Hon'ble M.L.A,Ichapuram, an estimate is prepared for the work"Re-Construction of Foot Bridge at
P.Karrivanipalem",Est.Cost.Rs.20.00 lakhs.
The existing foot bridge,which was constructed about 20 years back, is completely damaged.
Hence the public of Pedda Karrivanipalem village are facing much difficulty to cross the Beelabatti channel to access
their fields located on the other side.The photo graphs of the existing damaged foot bridge are herewith enclosed.
One foot bridge with 1.80m width is proposed on Beelabatti Channel at P.Karrivaniaplem village
to provide access to the villagers to reach agricultural fields on the other side of the channel.The total length of the
proposed bridge is 30m.Both the Hydraulic&Structural designs are herewith enclosed.
As such,an estimate is prepared with the following provisions :-
1.Dismatling of damaged foot bridge.
2.Foundations are taken upto the full scour depth
3.Individual footings are proposed at a depth of 3.00m from Low Bed Level(LBL)
4.Both U/S and D/S aprons are proposed with cut-off walls to protect Channel Bed.
5.Solid circular piers are proposed with 0.50m dia
6.Hammer head type bed blocks are proposed to support the deck slab on piers.
7.T-Beam type deck slab is proposed with effective span of 6.00m
8.Provision is made for wearing coat&Hand rails
9.Sulphate Resisting Cement is proposed along with Epoxy coating to the reinforcement
The estimate is prepared as per the current SSR,i.e.2008-2009 rates and the work will be carried
out as per APDSS after obtaining administrative sanction.
Asst.Executive Engineer Deputy Exe.Engineer
PR(spl),Ichapuram PR,Ichapuram
SPECIFICATION REPORT
As per the instructions of the instructions of the Dy.Exe.Engineer,PR,Ichapuram and as per the
The existing foot bridge,which was constructed about 20 years back, is completely damaged.
Hence the public of Pedda Karrivanipalem village are facing much difficulty to cross the Beelabatti channel to access
their fields located on the other side.The photo graphs of the existing damaged foot bridge are herewith enclosed.
One foot bridge with 1.80m width is proposed on Beelabatti Channel at P.Karrivaniaplem village
to provide access to the villagers to reach agricultural fields on the other side of the channel.The total length of the
The estimate is prepared as per the current SSR,i.e.2008-2009 rates and the work will be carried
SPECIFICATION REPORT
Name of the Work:-Re-Construction of Foot Bridge at P.Karrivanipalem
Rattakanna
HBG Quarry
229/5
1.5Km Ichapuram
223/8 5Km
Edupuram
5.2 Km
0/0
Rajapuram Quarry 15/8 Kavity
Gravel&OTG Ch.Karrivanipalem
3/6
0/0
Sompeta
Assistant Exe.Engineer Deputy Exe.Engineer
PR,Ichapuram PR,Ichapuram
Quarry Chart
Bahuda River
Sand
23/5
Ch.Karrivanipalem
(Proposed bridge
site)
Baruva
Quarry Chart
Name of the work:-Re-Construction of Foot Bridge at P.Karrivanipalem
Est.Cost:Rs.20.00 lakhs
S.No Description of item Nos Quantity Rate Per
Length Bredth Depth
1 Dismantling clearing away and carefully stacking materials useful for reuse for Brick masonry
including all labour charges etc.complete
For columns 1X8 0.90 2.00 2.40 34.56 192.24 1.00Cum
Construction of Foot Bridge:-
2 Earth work exacavation and depositing on bank with an initial lead and lift in loamy&clayey soils
like Black Cotton soils,red earth etc complete including dewatering below low water level
for foundations of PIERS&APRONS
Piers 1X6 3.00 3.00 3.00 162.00Cum
D/S Cut off walls 1X1 30.00 0.90 1.20 32.40Cum
U/S Cut off walls 1X1 30.00 0.90 1.20 32.40Cum
D/S Apron 1X1 30.00 3.00 0.75 67.50Cum
U/S Apron 1X1 30.00 3.00 0.75 67.50Cum
361.80Cum 327.16 1.00Cum
3 Providing aprons with jeddy stone of 450mm to 600mm size including cost,seinorage and
conveyance of all materials including all labour charges etc.complete
D/S Apron 1X1 30.00 3.00 0.45 40.50Cum
U/S Apron 1X1 30.00 3.00 0.45 40.50Cum
81.00Cum 789.22 1.00Cum
4 Cement Concrete(1:4:8) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
Piers 1X6 3.00 3.00 0.30 16.20Cum
D/S Cut off walls 1X1 30.00 0.90 0.15 4.05Cum
U/S Cut off walls 1X1 30.00 0.90 0.15 4.05Cum
D/S Apron 1X1 30.00 3.00 0.15 13.50Cum
U/S Apron 1X1 30.00 3.00 0.15 13.50Cum
51.30Cum 2776.29 1.00Cum
5 Cement Concrete(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges for
Approach slab 1X2 3.6 2.00 0.15 2.16Cum
Aprons 1X2 30 3.00 0.15 27.00Cum
29.16Cum 4629.85 1.00Cum
6 Cement Concrete(1:3:6) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
D/S Cut off walls 1X1 30.00 (0.75+0.30)/2 1.05 16.70Cum
U/S Cut off walls 1X1 30.00 (0.75+0.30)/2 1.05 16.70Cum
33.39Cum 3947.18 1.00Cum
7 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all
materials and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for foundations of piers including bailing out of water and formation of bunds for
diversion of water,if necessary etc.complete
Rectangular portion 1X6 2.50 2.50 0.30 11.25Cum
Trapezoidal portion 1X6 (2.5+0.7)/2 (2.5+0.7)/2 0.10 1.54Cum
12.79Cum 6531.19 1.00Cum
8 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
DETAILED-CUM-ABSTRACT ESTIMATE
Measurements
S.No Description of item Nos Quantity Rate Per
Length Bredth Depth
Measurements
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for piers,hammer head bed blocks including bailing
out of water and formation of bunds for diversion of water,if necessary etc.complete
Piers (22/28)*6 0.50 0.50 6.12 7.21Cum
Hammer head bed blocks 1X6 0.50 (1.2+0.5)/2 0.60 1.530Cum
8.736Cum 6685.39 1.00Cum
9 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for bed blocks,backing walls,bearing pedastals including bailing
out of water and formation of bunds for diversion of water,if necessary etc.complete
Bearing pedastals 1X6 0.83 0.42 0.15 0.314Cum
0.314Cum 6592.87 1Cum
10 Supplying and fixing of fully moulded type Neoprene Rubber Bearing of 500X320X84mm size
including the cost and conveyance of bearings and labour charges for fixing the same in position
confirming to specifications stipulated in specification for bridges and road works of MOST
drawings.
Piers 1X6 63.00 22.00 6.10 50727.60cc
50727.60cc 0.70 1.00cc
11 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Beams of bridge.
Main beam 1X1 30.00 0.30 0.750 6.750Cum 7867.59 1Cum
12 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Super structure DECK SLAB.
Deck slab 1X5 6.00 1.80 0.175 9.450Cum 7404.99 1Cum
13 VRCC(1:1:2) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for wearing coat
Over Deck slab 1X5 6.00 1.80 0.080 4.320Cum 7585.18 1Cum
14 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for hand rails&hand posts
Over Deck slab 1X5 6.00 ---- ---- 30.00m
30.00m 1404.74 1.00m
15 Cost supply and fabrication charges of steel including cost of binding wire and all labour charges etc.complete
11000Kg 62.40 1Kg
16 Providing expansion joints including cost and conveyance of all materials from approved
source to site fabricated with 2 Nos.MS angles of size 75X75X6mm for 7.5m 1 No.MS plate
of 140X6mm for 7.5m 200 Nos.of 12mm dia MS iron anchor bars of 30.6 Cms and
nuts including welding of MS plate and MS angles and also welding MS anchor bars and
fitting with anchor bolts and nuts including all labour charges for cutting,fixing and painting
the exposed faces of MS angles with anti corrosive paint including 4% TOT
1X4 ---- ---- ---- 4Nos 2097.20 1Nos
17 Drilling of 150mm dia conformatory bore holes below water level in all types of soils at each
pier and abutment locations to required depth(excluding refusal strata) including transport
of boring craft and all other accessories to site,providing boring platform,drilling,insertion of
150mm dia MS casing pipe for collection of disturbed/undisturbed soil samples at 1.50m
interval or at the change strata for conducting various tests as per specifications,removing
S.No Description of item Nos Quantity Rate Per
Length Bredth Depth
Measurements
casing pipe after completing boring works,incidental royalties etc.complete as per MOST
technical specification No.2400
1X4 15.00 ---- ---- 60.00m 650.00 1.00m
18 Provision for Caution Boards. --------------LS--------------------
19 Provision for Price escalation&Variation of rates@10% --------------LS--------------------
20 Provision for engaging technical [email protected]% --------------LS--------------------
21 Provision for [email protected]% --------------LS--------------------
22 Provision for Q.C.Inspection [email protected]% --------------LS--------------------
23 Provision for investigation [email protected]% --------------LS--------------------
24 Provision for preparation of detailed estimate@1% --------------LS--------------------
25 Provision for unforeseen items --------------LS--------------------
TOTAL
Assistant Exe.Engineer Deputy Exe.Engineer
PR,Ichapuram PR,Ichapuram
Est.Cost:Rs.20.00 lakhs
Amount
6644
118367
63927
142424
135006
131796
83508 12.79Cum 100 1278.6
DETAILED-CUM-ABSTRACT ESTIMATE
Amount
58406 8.736Cum 200 1747.26
0.314Cum 200 62.748
2068
35509
53106 6.750Cum 200 1350
69977 9.450Cum 150 1417.5
32768 4.320Cum 200 864
3 200 600
42142
686396
8389
Amount
39000
10000
171279
42392
9420
9454
9454
18841
19727
2000000
Name of the work:-Re-Construction of Foot Bridge at P.Karrivaniaplem
Est.Cost:-Rs20.00 lakhs
S.No Description of item Name of the quarry Initial Conveyance Seinorage Blasting Machine Deduct Total
MR CT Total Cost charges crushing stacking
charges
1 Gravel Rajapuram 8.80 0.00 8.80 56.00 148.00 20.00 0.00 0.00 (-)11.00 213.00
2 Sand for filling Bahuda River 11.30 0.00 11.30 60.00 166.00 36.00 0.00 0.00 (-)11.00 251.00
3 Sand for Mortar Bahuda River 11.30 0.00 11.30 175.00 166.00 36.00 0.00 0.00 (-)11.00 366.00
4 Rough stone OTG for revetment Rajapuram 8.80 0.00 8.80 95.00 168.00 45.00 0.00 0.00 (-)17.40 290.60
5 40mm HBG metal-SS5 J.L.Kota 23.50 0.00 23.50 500.00 257.00 45.00 70.00 0.00 (-)17.40 854.60
6 20mm HBG metal-SS5 J.L.Kota 23.50 0.00 23.50 845.00 257.00 45.00 70.00 211.25 (-)17.40 1410.85
7 Jeddy stone for aprons 450 to 600mm size Rajapuram 8.80 0.00 8.80 156.00 168.00 45.00 0.00 0.00 (-)17.40 351.60
Certified that the above leads are correct to the best of my knowledge
Assistant Exe.Engineer Deputy Exe.Engineer
PR,Ichapuram PR,Ichapuram
Lead in Kms
LEAD STATEMENT
DESIGN OF FOOT BRIDGE
Name of the work:-Re-Construction of Foot Bridge at P.Karrivanipalem
Est.Cost:- Rs.20.00 lakhs
S.No Quantity Description Rate Per Amount
1 Dismantling clearing away and carefully stacking materials useful for reuse for Brick masonry
including all labour charges etc.complete
1.00Cum Dismantling 187.00 1.00Cum 187.00
Add [email protected]% 5.24
TOTAL 192.24
2 Cement Mortor (1:3) (1:5) (1:6)
1.00Cum Cost of sand 366.00 366.00 366.00
7200/1MT Cost of SR Cement 3456.00 2073.60 1728.00
1.00Cum Mixing charges 28.00 28.00 28.00
3850.00 2467.60 2122.00
3 Cement Concrete(1:4:8) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 40mm HBG metal 854.60 1Cum 786.23
0.46Cum Cost of sand 366.00 1Cum 168.36
166.00Kg Cost of cement 7200.00 1000Kg 1195.20
1.00Cum Labour charges 505.88 1Cum 505.88
1.00Cum Machine mixing charges 45.00 1Cum 45.00
Add [email protected]% 75.62
2776.29
4 Cement Concrete(1:3:6) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
0.92Cum Cost of 40mm HBG metal 854.60 1Cum 786.23
0.46Cum Cost of sand 366.00 1Cum 168.36
221.00Kg Cost of cement 7200.00 1000Kg 1591.20
1.00Cum Labour charges 505.88 1Cum 505.88
1.00Cum Centring charges 700.00 1Cum 700.00
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Vibrating charges 43.00 1Cum 43.00
Add [email protected]% 107.51
3947.18
5 Rough stone packing for revetment with concrete grouting using CC(1:2:4) using 300mm size Rough
stone including cost and conveyance of all materials and all labour charges etc.complete.
1.10Cum Rough stone 300m for revetment 290.60 1Cum 319.66
1.00Cum Labour charges 383.96 1Cum 383.96
0.25Cum CC(1:4:8) 4343.74 1Cum 1085.94
Add [email protected]% 19.73
1809.28
6 Cost supply and fabrication charges of steel including cost of binding wire and all labour charges etc.
complete
1.00Kg Cost and supply of Fe415 Steel 51.70 1.00Kg 51.70
1.00Kg Fabrication charges 9.00 1.00Kg 9.00
Add [email protected]% 1.70
TOTAL 62.40
7 Earthwork excavation and depositing on bank with an initial lead of 10m and lift of 2m in loamy and clayey
soils in wet and slushy conditions including shoring,shuttering and bailing out of water
1.00Cum Earth work excavation 37.50 1.00Cum 37.50
1.00Cum Add 50% for foundation excavation 18.75 1.00Cum 18.75
DATA SHEET
S.No Quantity Description Rate Per Amount
1.00Cum Add Bailing out water(2 to 3m) deep 80.00 1.00Cum 80.00
1.00Cum Shuttering charges of materials 15.00 1.00Cum 15.00
1.00Cum Shoring charges including cost of materials85.00 1.00Cum 85.00
1.00Cum Fixing charges for shuttering,shoring&strutting 62.00 1.00Cum 62.00
1.00Cum Seinorage Charges 20.00 1.00Cum 20.00
Add [email protected]% 8.91
327.16
8 Cement Concrete(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges for Approach Slab
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
331.00Kg Cost of cement 7200.00 1000Kg 2383.20
1.00Cum Labour charges 449.20 1Cum 449.20
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 160.00 1Cum 160.00
Add [email protected]% 126.10
4629.85
9 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all
materials and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for foundation including
bailing out of water and formation of bunds for diversion of water,if necessary etc.complete
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 700.00 1Cum 700.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 177.89
6531.19
10 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all
materials and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for piers,abutments,hammer head bed blocks and return walls including
bailing out of water and formation of bunds for diversion of water,if necessary etc.complete
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 850.00 1Cum 850.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 182.09
6685.39
11 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all
materials and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for bed blocks,backing walls,bearing pedastals including bailing
out of water and formation of bunds for diversion of water,if necessary etc.complete
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 760.00 1Cum 760.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 179.57
6592.87
S.No Quantity Description Rate Per Amount
12 Supplying and fixing of fully moulded type Neoprene Rubber Bearing of 500X320X84mm size
including the cost and conveyance of bearings and labour charges for fixing the same in position
confirming to specifications stipulated in specification for bridges and road works of MOST
drawings.
13440 50*32*8.4cc provisional rate 1.10 1.00cc 14784.00
Add VAT@4% 591.36
15375.36
13 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for Beams of bridge.
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 2000.00 1Cum 2000.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 214.29
7867.59
14 VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for deck slab of bridge.
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 1550.00 1Cum 1550.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 201.69
7404.99
15 VRCC(1:1:2) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for wearing coat
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
662.40Kg Cost of cement 7200.00 1000Kg 4769.28
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 160.00 1Cum 160.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
Add [email protected]% 206.60
7585.18
16 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for hand rails&hand posts
0.92Cum Cost of 20mm HBG metal 1410.85 1Cum 1297.98
0.46Cum Cost of sand 366.00 1Cum 168.36
445.00Kg Cost of cement 7200.00 1000Kg 3204.00
1.00Cum Labour charges 894.96 1Cum 894.96
1.00Cum Machine mixing charges 45.00 1Cum 45.00
1.00Cum Centring charges 2200.00 1Cum 2200.00
1.00Cum Vibrating Charges 43.00 1Cum 43.00
S.No Quantity Description Rate Per Amount
Add [email protected]% 219.89
8073.19
Per RM 1404.74
17 Providing aprons with jeddy stone of 450mm to 600mm size including cost,seinorage and
conveyance of all materials including all labour charges etc.complete
1.10Cum Cost of Jeddy stone 351.60 1Cum 386.76
1.00Cum Labour charges 380.96 1Cum 380.96
Add [email protected]% 21.50
789.22
18 Providing expansion joints including cost and conveyance of all materials from approved
source to site fabricated with 2 Nos.MS angles of size 75X75X6mm for 7.5m 1 No.MS plate
of 140X6mm for 7.5m 200 Nos.of 12mm dia MS iron anchor bars of 30.6 Cms and
nuts including welding of MS plate and MS angles and also welding MS anchor bars and
fitting with anchor bolts and nuts including all labour charges for cutting,fixing and painting
the exposed faces of MS angles with anti corrosive paint including 4% TOT
1Rmt Provisional rate 2097.20 1Rmt 2097.20
19 Providing 100mm dia AC pipe for weep holes at 1m c/c in both horizontal and vertical
directions so that the weep holes in each horizontal row staggered from the weep holes
lying immediately above and below for abutmentys and wing walls including cost and
conveyance of AC pipe and labour charges for cutting to required length,placing the pipe
with a slope of 1:20 towards retaining face etc.complete for finished item of work
1Rmt Cost of 100m AC pipe Cl-15 167.35 1Rmt 167.35
Add CED@12% 20.08
Add [email protected]% 5.25
Add Conveyance @6% 10.04
Add for cutting&positioning 1.58
204.30
20 Drilling of 150mm dia conformatory bore holes below water level in all types of soils at each
pier and abutment locations to required depth(excluding refusal strata) including transport
of boring craft and all other accessories to site,providing boring platform,drilling,insertion of
150mm dia MS casing pipe for collection of disturbed/undisturbed soil samples at 1.50m
interval or at the change strata for conducting various tests as per specifications,removing
casing pipe after completing boring works,incidental royalties etc.complete as per MOST
technical specification No.2400
1Rmt Provisional rate 650.00 1Rmt 650.00
Assistant Exe.Engineer Deputy Exe.Engineer
PR,Ichapuram PR,Ichapuram
VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials
VRCC(1:11/2:3) Controlled concrete mix using 20mm HBG chips including cost and conveyance of all materials