pitfalls of ineffective change management - gnwtwarehouse.pws.gov.nt.ca/pdf/pmc/pmc...
TRANSCRIPT
FACT OR FICTION Contractors like changes Contractors make $$$ (gouge)
on changes Productivity impact (?) can be
quantified on each change Contractors make money on the
markup in change orders
SUPERIOR SCOPE MANAGEMENT
NO CHANGES PAYING / RECEIVING THE RIGHT
AMOUNT SPEEDY DECISIONS & RESOLUTION
NO SURPRISES
SUPERIOR SCOPE MANAGEMENT
Evaluate the contract Identify the change Notify parties of the change Document the change Prepare the change request Resolve the change request
Six Steps for Successful Change Order Management Katherine Molly - Cost Engineering - April 2007
Opinion from
19 41.30%0 0%
14 30.43%13 28.26%
Totals 46 100%
1.) Make up of Group Do you work for a: Responses
Owner organization – buyer of serviceEngineering organization – design of serviceContractor organization – builderFirm that consults to one or more of the abov...
Inflation
Totals
2.) Inflation in Claim What is the general level of inflation in claims? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Inflation
6 13.64%18 40.91%12 27.27%
8 18.18%0 0%
Totals 44 100%
2.) Inflation in Claim What is the general level of inflation in claims? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Inflation Extras
Totals
3.) Inflation in Extras What is the general level of inflation in extras? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Inflation Extras
7 15.56%23 51.11%
9 20%6 13.33%0 0%
Totals 45 100%
3.) Inflation in Extras What is the general level of inflation in extras? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Claim Prep
Totals
Responses
AgreeSomewhat AgreeSomewhat DisagreeDisagree
4.) Claim Submissions are well prepared
Claim Prep
3 6.67%11 24.44%22 48.89%
9 20%Totals 45 100%
Responses
AgreeSomewhat AgreeSomewhat DisagreeDisagree
4.Claim Submissions are well prepared
CHANGE ORDER
COST COMPONENTS Elements
DIRECT COST IMPACT ON SCOPE INDIRECTS
Easy to quantify Causes
argument
WHEN DOES 10% MARKUP
COVER THE COSTS OF: - CHANGE ORDER
PREPARATION - FIELD OVERHEADS
- HOME OFFICE OVERHEADS
EXTRA WORK BREAK-EVEN POINT
0
100
200
300
400
500
0 500 1000 1500 2000
OVERHEAD AND FEE
DIRECT COST VALUE OF CHANGE
?
CHANGE ORDER PREPARATION
ESTIMATING PURCHASING CLERICAL ADMINISTRATION COORDINATION SUB-TRADES CONSULTANTS SITE
FIELD OVERHEADS
FIELD COORDINATION
TEMPORARY FACILITIES
ADMINISTRATION MEETINGS CORRESPONDENCE COST CONTROL
HOME OFFICE OVERHEADS UTILITIES BUILDING COMPUTERS ADMINISTRATION MANAGEMENT FINANCING INSURANCE BONDING EXTENDED WARRANTY BUSINESS DEVELOPMENT
General Conditions
Supervision Temporary Facilities Field Support Temporary Utilities Construction Equipment Special Conditions
SCHEDULE
CHOICES SILENCE NO EFFECT IF AUTHORIZATION TO
PROCEED BY ……….. WILL PROVIDE EFFECT ON COMPLETION
OF THE WORK ON COMPLETION OF THE PROJECT
OR ALLOW 2 DAYS FOR EVERY CHANGE
Contractor Original Estimate
Hours
Contractor Original Estimate
Hours
Change Order Hours
Inefficient Hours
Under Estimated Hours on Original Contract Work + Contractor
Inefficiency
Impact of Change Orders
Dire
ct F
ield
Lab
or H
ours
0 100 Construction Phase (% Complete)
Inefficient Hours
Design and/or Fabrication error
Crews tries to make it fit Crews stands down waiting for direction /
clarification Foreman seeks direction from Engineer
and tries to get crew working productively
Demob to an other work face When direction is received remob to initial
work face
According to Construction Industry Institute (CII) Study (1995):
“generally … projects with a high % change
experience lower craft productivity than projects with little or no change”
IMPACT OF CHANGES ON LABOUR PRODUCTIVITY
• 5 - 10%
As a ratio of Completed Cost to Original Cost Estimate (U.S. Studies 1974-1985)
Construction Industry Institute Survey 1995 where Change = Increase in Scope
• up to 9% (Design-Build projects)
• up to 15% (Design-Bid Build projects)
Normal ?
40 45 50 35 30 25 20 15 10 5 0 0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
Construction Change (%)
Con
stru
ctio
n Pr
oduc
tivity
Rat
io
Construction Industry Institute Study 1995*
“Quantitative Effects of Project Change”, CII - Publication 43-2, May 1995
• 1) The number of change orders issued was not an
accurate indication of productivity loss
• 2) The average size of change orders was also not correlated with productivity loss.
• 3) There was a high degree of correlation between loss of labor productivity and the percentage of change orders hours to total contract hours.
LEONARD STUDY This study determined that:
% Change orders = Actual Contract Hours = Total Actual Hours less Change Order Hours and less Unproductive Hours due to Contractor Inefficiencies
Change Order Hours Actual Contract Hours
X 100
Effect of Change Orders on Civil and Architectural Work
0
10
20
30
40
50
60
0 10 20 30 40 50 60
Loss of Productivity (%)
% Change Orders
Changes only Plus 1 major cause Plus 2 major causes
0
10
20
30
40
50
60
0 10 20 30 40 50 60
Leonard (1988) - Effect of Change Orders on Electrical and Mechanical Work
Loss of Productivity (%)
Changes only Plus 1 major cause Plus 2 major causes
% Change Orders
Impact on Spent Contract Hours
Spent CH 1,000 Extra 200 Total 1,200
Spent CH 1,000 Productivity 180 Extra 200 Total 1,380
Leonard (1988) vs. Ibbs (1995, 2005) Electrical and Mechanical Work
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
Leonard - Changes only Leonard - Plus 1 major cause
Ibbs (2005)
Ibbs and Allen (1995)
Leonard - Plus 2 major causes
0.00
1.20
1.00
0.80
0.60
0.40
0.20
Construction Productivity Index
% Change Orders
Quantity of Change vs Impact (based on manhours)
-5%
0%
5%
10%
15%
20%
25%
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
Change Hours as % of Base Project Hours
Impa
ct a
s %
of T
otal
Act
ual H
ours
Productivity Improvement
CII
Electrical Contracting Foundation
Quantity of Change vs Impact (based on manhours)
-5%
0%
5%
10%
15%
20%
25%
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
Change Hours as % of Base Project Hours
Impa
ct a
s %
of T
otal
Act
ual H
ours
Mechanical Contracting Foundation
Productivity Improvement
Leonard
CII
COMMENT
Lost productivity associated with the cumulative effect of changes is one of the most difficult claims to quantify thoroughly and persuasively (even for the very experienced) . Productivity losses can impact both the changed work and the unchanged (base contract) work. There is no universally accepted method available at this time to quantify the cumulative losses. Current methods are subject to scepticism and criticism.
Constructin Claims Seminar Revay and Associates Limited
CHANGE QUOTATION The price quoted is only for the direct
cost of the change. We reserve the right to seek compensation for the
impact on contract work and / or the cumulative effect of changes when
these costs (if any) can be quantified.
The Great Debate
Owners
Absolutely refuse to accept
qualification
Contractors
Need to qualify so as to preserve their right to
discuss productivity