Introduction

Specsavers Optical Group Ltd is the world’s largest optical retailer.

With turnover now exceeding £1b, over 800 stores in the UK and a further 500 across the globe, the move to Solent Business Park was essential to the company’s plan to support its rapid global expansion.

Having completed Specsavers’ 36,000 ft2 Shared Services facility in Nottingham, Paragon was retained to undertake the design and fit-out of Forum 6, a 38,000 ft2 Grade A office block.

Prior to selecting the building, Paragon advised Specsavers on its suitability. As part of the evaluation, the existing mechanical and electrical installation was assessed before recommendations were presented and subsequently implemented as part of the fit out.

Paragon was tasked with creating an inspiring interior that would compliment the building architecture and attract the right staff for Specsavers’ aggressive growth.

Following an intensive consultation period, the design was agreed, the project was started and the fit-out was completed within 12 weeks to the agreed budget.

The Forum 6 fit-out was created within an overriding ethos of best value for Specsavers, whilst perfectly illustrating its commitment to providing its staff with quality office accommodation.

Page 4: Pig Specsavers 12pp 2010 Email

Client

Specsavers Optical Group LtdIT/Support Services

Page 5: Pig Specsavers 12pp 2010 Email

Location

Forum 6

The Forum

Solent Business Park

Whitely

Hampshire

PO15 7PA

Page 6: Pig Specsavers 12pp 2010 Email

Project Size

38,000 ft2

Project Value

£2.1m

Page 7: Pig Specsavers 12pp 2010 Email

Timescales

Off-site

Design, procurement and mobilisation 10 weeks

On-site

Project management, construction and fit-out 12 weeks

Page 8: Pig Specsavers 12pp 2010 Email

Scope of Works

Space planning

Detailed design

Partitions and doors

Suspended ceilings

Floor coverings

Decoration

Joinery and feature items

Upgrade of existing cooling capacity

Upgrade of existing fresh air provision

Upgrade of existing mains power by 750 kVA

Data centre

Furniture

Page 9: Pig Specsavers 12pp 2010 Email

Client Contacts

Nick James – Director of Group Services

[email protected]

Hugo Lord – Property Director

[email protected]

Specsavers Optical Group Ltd,

La Villiaze,

St. Andrews,

Guernsey,

GY6 8YP.

Tel: 01481 236 000

Page 10: Pig Specsavers 12pp 2010 Email
Page 11: Pig Specsavers 12pp 2010 Email

“Paragon’s consultation throughout the property acquisition phase of this project has been crucial. They not only understood the needs of the business from a space-optimisation perspective, which helped us to be far more accurate with our search but also from the organisational and strategic perspective of the business going forward. This is a property acquisition to meet the growing demands of the business, not only in the UK, but internationally. Paragon’s fit-out is going to offer us the space to expand our IT facility, and create additional space to meet the growing demands of the business as we continue to expand our operations around the world.”

Hugo LordProperty Director

Page 12: Pig Specsavers 12pp 2010 Email

Paragon Interiors Group Plc

Nottingham OfficeParagon House | Orchard Place | Nottingham Business Park | Nottingham | NG8 6PX

t: 0115 951 9512 f: 0115 951 9513

Manchester OfficeBelvedere Building | Booth Street | Manchester | M2 4AW

t: 0161 235 0800

w: www.paragoninteriors.biz