5/12/2016 1 and Superstructure Bridge Slide Michigan M-100 Presented by: Donald Yetter, PE, SE - AECOM Picture here Photo by MDOT Photography Unit and Project overview Considerations for ABC Proposed bridge Temporary substructure and approach slab Sliding operations Construction Lessons learned OUTLINE

Upload: others

Post on 26-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

1

and

Superstructure Bridge Slide – Michigan M-100Presented by: Donald Yetter, PE, SE - AECOM

Picture here

Photo by MDOT Photography Unit

and

• Project overview• Considerations for ABC • Proposed bridge• Temporary substructure and approach slab• Sliding operations• Construction• Lessons learned

OUTLINE

Page 2: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

2

and

• Potterville, MI• ADT – 5400• Overall project consisted of

replacing 3 bridges along M-100 (other 2 were stage constructed)

PROJECT OVERVIEW

Grand Rapids Lansing

Detroit

and

Emergency Services

CN/GTW RR

Project Location

Interchange

Page 3: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

3

and

• 3-span steel superstructure• Constructed in 1940• Reinforced concrete stub

sill abutments and steel bent piers on spread footings

• 157’ long with a clear roadway width of 40’

EXISTING BRIDGE

Photo by AECOM

Photo by AECOM

and

• MDOT and city officials didn’t want extended bridge closure• Part width construction not feasible• Emergency services located on the opposite side of tracks

from the majority of city• 4.5-mile detour (20 for trucks) w/ at-grade crossing• Minimize user delay costs due to detours• Space available adjacent old Bridge to build new one

CONSIDERATIONS FOR ABC

Page 4: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

4

and Photos by MDOT Photography Unit

1. Build New Bridge on Temporary Frames

3. Build Permanent Abutments 2. Remove Existing Bridge

OVERALL SEQUENCE

and

• Slide-out to temporary location• Slide-in from temporary location • Build in temporary location on west side versus east

- Extensive utilities on east side

ABC OPTIONS

Photo by AECOM

Page 5: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

5

and

gas telephonefiberoptic electrical

Existing Bridge

New Bridge in Temporary Location

and

• Single span steel superstructure• 107’-6” span on a 37.6° skew• Full height concrete abutments on steel H-piles• 44’-0” clear roadway width and 10-foot shared-use walkway• Temporary alignment located 76’-5” west and parallel to the

existing alignment

PROPOSED BRIDGE

Horizontal Beam Seat

Page 6: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

6

and

• Foundation Alternatives - concrete; micro-piles; vs. driven steel pile

• 2 rows HP 14 piles (pre-bored some)• Frame braced in each direction with

channels and angles• Field welded connections• Longitudinal triple W18x76 beam was

the main load carrying member• Wire face MSE wall behind frames

used to retain road fills

TEMPORARY SUBSTRUCTURE

Abutment Frame

New Superstructure

Guide Rail

Temp. MSE Wall

Temp. Approach Slab

and

Photo by MDOT Photography Unit

Existing Bridge

Temporary Substructure

Temporary MSE Wall

Page 7: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

7

andAll photos by MDOT Photography Unit

TEMPORARY SUBSTRUCTURE & MSE WALL CONSTRUCTION

and

Photo by MDOT Photography Unit

Triple Beam Support for Guide Rail

Page 8: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

8

and

• C10x30 used to guide the steel rollers• Welded to top of triple beam and bolted to top of concrete

abutment• Drop-in span used to span the gap between the temporary

and permanent abutments

TEMPORARY SUBSTRUCTURE

Drop-in Span

Guide Rail

and

Photo by AECOM

Guide Rail

Photo by MDOT Lansing TSG

Drop in Span

Supported on New Footing

Page 9: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

9

and

• Concrete approach slab tied to temporary abutments

• 2” open joint at each abutment• Level with bottom of deck

APPROACH SLAB (Temporary Roadway)

Photos by MDOT Photography Unit

Completed Bridge in Temporary Location

and

• Synchronous vertical jacks placed under each end diaphragm

• End diaphragms designed for 1/16” deflection• Superstructure lifted and rollers placed under

each beam• Superstructure lowered onto rollers• Jacks and rollers located in the channel guide in

front of permanent bearings so no conflict occurred

LIFTING SUPERSTRUCTURE FROM TEMP. BEARINGS

Page 10: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

10

and

LIFTING SUPERSTRUCTURE FROM TEMP. BEARINGS

and

Place jacks under end diaphragm

Photo by MDOT Photography Unit

Retract jacks

Photo by AECOM

Raise each end of bridge

Photo by AECOM

Photo by MDOT Photography Unit

LIFTING SEQUENCE

Photo by MDOT Photography Unit

Attach Rollers to Beams

Photo by MDOT Photography Unit

Roller

Page 11: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

11

and

• Steel rollers versus PTFE pads• Rollers with horizontal guide wheels for fascia girders• Larger top plate with slotted holes to allow for more

construction tolerance• Cushion pad used• Variable filler plate• Designed for µ=0.07

ROLLER SYSTEM

Girder

Fill PlateThickness Varies

by Beam

Elastomeric Pad

Guide WheelRoller

and

Photos by MDOT Photography Unit

Guide Wheel (Fascia Girder)

Roller

Elastomeric Pad

Fill Plate

ROLLER SYSTEM

Fascia GirderInterior Girder

Page 12: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

12

and

ROLLER SYSTEM

and

• Independently controlled double-acting horizontal jacks at fascia girders

• Jacks attached to saddle assembly• Saddle assembly connected to guide channel by means

of (3)-7/8”ø pins

SLIDING OPERATIONS

Insert Pins between Saddle & Guide Rail

Page 13: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

13

and

Photo by MDOT Photography Unit

Photo by AECOM

Photo by MDOT Photography Unit

SLIDING OPERATIONS

Pins

Clevis

and Construction Sequence before Slide

Page 14: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

14

and Slide Sequence

and

Permanent Approach Slabs

Before Slide

After Slide

• Early strength concrete used to allow traffic as soon as possible• Cast-in-place

Sleeper SlabExpansion

Joint

Mechanical Splicer

C.I.P. Approach Slab

Expansion Joint

Page 15: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

15

and

• Roller system with horizontal guide wheels worked well• Actual µ=0.034 to overcome static friction• Use conservative loads in design • Draw everything in plan and elevation views at all the stages

of construction• Measure, measure, measure – perhaps survey multiple times

with different methods to ensure everything will fit• Account for construction tolerances wherever possible

- Holes for push cylinder saddle pins could have been bigger

- Or better shop QC when drilling holes in saddle & guide rails

OBSERVATIONS & LESSONS LEARNED DEBRIEFINGS

and

Photo by MDOT Lansing TSG

Proactive Railroad Engagement Provided Value Tight Tolerances

Parapet MisalignmentFaster Cylinder Retraction PreferredPhotos by AECOM

Page 16: Photo by MDOT Photography Unit - SEAOI€¦ · • Traffic shifted: August 14, 2015 • Road closed: Friday, Nov. 13 at 7 PM • Vertical jacking: Friday, Nov. 13 at 11 PM • Bridge

5/12/2016

16

and

• Let project: December 5, 2014• Start construction: March 18, 2015• Traffic shifted: August 14, 2015• Road closed: Friday, Nov. 13 at 7 PM• Vertical jacking: Friday, Nov. 13 at 11 PM• Bridge slide: Saturday Nov. 14 1 AM -10 AM

(slid ~100’ in 9 hours)• Pour approach slabs: Saturday Nov. 14 at 2 PM• Road opened to traffic: Monday, Nov. 16 at 6 PM

TIMELINE

and

Photo by MDOT Photography Unit

Questions