phoenix convention center phoenix, arizona implementing renewables through your utility innovation...
TRANSCRIPT
Phoenix Convention Center • Phoenix, Arizona
Implementing Renewables Through Your Utility
Innovation Track 10 Partnering with Your Utility To Do Large-Scale Energy Projects
Chandra ShahNational Renewable Energy Laboratory
August 12, 2015
Energy Exchange: Federal Sustainability for the Next Decade2
• Federal Utility Partnership Working Group (FUPWG) - November 3 and 4 in Houston, TX
• UESC Workshop Nov. 5-6 after FUPWG (in Houston)
FUPWG and UESC Workshop
Energy Exchange: Federal Sustainability for the Next Decade
Presentation Overview
• Executive Order 13693 renewable goal overview
• Options for implementing renewable projects through your utility
• Important project considerations
• Utility coordination recommendations for all renewable projects
• Example projects
• Resources
Energy Exchange: Federal Sustainability for the Next Decade
Requirement Electric/Thermal Details
Renewable Goal Electric 10% FY2016-1715% FY2018-1920% FY2020-2125% FY2022-2330% FY2025 and thereafter
“Clean Energy” Goal(renewable & alternative energy)
Electric & Thermal 10% FY2016-1713% FY2018-1916% FY2020-2120% FY2022-2325% FY2025 and thereafter
Definition of “New” for Renewable Energy Certificates (RECs)*
REC definition states that “for the purposes of section 3(d)(iii) and (iv) of this order, were produced by sources of renewable energy placed into service within 10 years prior to the start of the fiscal year”
Executive Order 13693 “Planning for Federal Sustainability in the Next Decade” (March 2015)
*If project RECs are sold, replacement RECs must be purchased that meet the definition
Energy Exchange: Federal Sustainability for the Next Decade
• Revokes various EOs and Presidential Memos - including EO13423, EO13514 and December 5, 2013 Presidential Memo Federal Leadership on Energy Management
• Renewable Priorities (Section 3)(i) installing agency-funded renewable energy on site at Federal facilities and retaining corresponding RECs or obtaining equal value replacement RECs(ii) contracting for the purchase of energy that includes the installation of renewable energy on site at a Federal facility or off site from a Federal facility and the retention of corresponding RECs or obtaining equal value replacement RECs for the term of the contract(iii) purchasing electricity and corresponding RECs or obtaining equal value replacement RECs(iv) purchasing RECs
• Double Bonus Credit for renewable electric energy generated on Federal or
Tribal land/facilities (per EO13693 Implementing Instructions, p. 26)
Executive Order 13693 “Planning for Federal Sustainability in the Next Decade” (March 2015)
Energy Exchange: Federal Sustainability for the Next Decade
Utility Partnership OptionsGovernment Ownership• Utility Energy Service Contract (UESC) with renewable ECM, either stand-alone or
bundled with other ECMs• Project implemented using appropriations, in partnership with the utility
Private Ownership • Utility energy sales agreement • Federal agency hosts renewable project for utility use • UESC with private ownership of renewable ECM
– Must meet OMB title retention requirement
Notes• Fair consideration must be given to each serving utility • All renewable projects (regardless of implementation method) require close
coordination with the utility
Energy Exchange: Federal Sustainability for the Next Decade
Utility Energy Sales Agreement
• Contract with the serving utility – Utility (or renewable developer) constructs, owns, operates & maintains
an on-site renewable project and federal agency purchases the electricity – Utilize FAR Part 41 Utility Service (rather than the UESC authority)
• GSA authority• GSA areawide contract can be used
– Department of Defense can use 10 USC 2922a long term authority
• Contract should specify REC ownership (utility may want RECs for renewable requirement compliance) – If utility keeps RECs, then agency must purchase replacement RECs for
credit towards RE goal
• Renewable project owner can take advantage of available tax incentives
Energy Exchange: Federal Sustainability for the Next Decade
Hosted Renewable Project for Utility Use
• Utility develops renewable project at federal site for utility use, usually for renewable portfolio standard (RPS) compliance– Utility owns, operates and maintains RE project – Real estate agreement– Utility provides payment or in-kind consideration for use of land – In-kind consideration options include energy, RECs, a smaller
renewable project for agency use, electrical infrastructure, energy security benefits such as right of first refusal in case of grid outage
Energy Exchange: Federal Sustainability for the Next Decade
Partnering to Respond to Utility Renewable/REC RFP• Utility issues renewable/REC RFP• Site seeks industry partner to respond to RFP • Industry partner responds to RFP (may be joint bid with federal site)• Could be electricity contract and/or real estate agreement • Utility will own the RECs (replacement REC purchase required for E.O. 13693
renewable goal)• Examples: Brookhaven, Ft. Carson, NREL• Cons
– Tough to predict timing of utility requirements – Team must be ready to spring into action
Utility RFP Federal Site hosts third party owned and
operated RE resource
Developer constructs RE resource on Federal
land/building and sells RECs/renewable energy to
utilityRECs/renewable energy
Energy Exchange: Federal Sustainability for the Next Decade
Utility Partnership Advantages/Challenges
Advantages Challenges Utility and federal agency have
existing relationship
Investor-owned utilities are eligible for investment tax credit and possibly other tax incentives
Utility may provide electricity at a pre-existing tariffed rate
Utility involvement could streamline interconnection process and reduce associated costs. May result in other benefits such as no stand-by charges
Possible use of areawide contract
Utility may be interested in purchasing all or excess power
Relatively new contracting method
Third party ownership required for tax benefit
Public Utility Commission approval may be required
Some utilities may not be willing to offer this service
Energy Exchange: Federal Sustainability for the Next Decade
Project Considerationsand Utility Coordination
Energy Exchange: Federal Sustainability for the Next Decade
Project Considerations
• Site and agency approval requirements• Real estate agreement options include easement, lease or
license– Utilities generally prefer an easement – FAR Part 41.501c4 (52.241-5 Contractor’s Facilities), which provides
for a license, may be used
• Compliance with National Environmental Policy Act (NEPA), National Historic Preservation Act (NHPA), etc.
• Electrical considerations• Glint/glare if near an airport• Others
Energy Exchange: Federal Sustainability for the Next Decade
Utility Coordination (regardless of implementation option)• Contact the utility early in the process and periodically
throughout project development. Discussion topics include: – Interconnection process and requirements – application and study
requirements, the time required for study completion, costs (application fee, study fees, possible equipment upgrade costs) and the current queue for interconnection study completion
– Interconnection agreement – legal review template agreement early in process, contact FEMP for assistance
– Renewable system tie-in options– Available incentives – Applicable policies such as net metering, feed-in tariff, virtual net
metering/community renewables – Utility rate impacts – possible tariff change, standby charges, etc.– Demand charge impacts if project goes down
• Best to be very conservative with demand charge reduction estimates (10% recommended)
Marine Corps Logistics Base Barstow Wind Project
1.5 MW wind turbine $4.6 million cost financed by Southern
California Edison $6.1M total, minus $1.5M rebate
$515k annual savings 15 year term
Example: UESC (gov’t ownership)
Energy Exchange: Federal Sustainability for the Next Decade
• Partnership with Tucson Electric Power (TEP), who will fund, own and operate the approximately 22 MW DC PV project– Subcontract with industry partner E.ON for the system’s design,
engineering, procurement and construction management
• Utilizes existing GSA areawide contract
• TEP will provide electric service at Arizona Corporation Commission approved rates
• 30 year easement
Fort Huachuca, Arizona
Energy Exchange: Federal Sustainability for the Next Decade
• NEPA completed March 2014
• Interconnected with TEP-owned Fort Huachuca substation
• April 25, 2014 ground-breaking ceremony
• November 2014 operational
• http://www.armyeitf.com/downloads/fort_huachuca_factsheet.pdf
Fort Huachuca, Arizona
Energy Exchange: Federal Sustainability for the Next Decade
• 50 MW biofuel-capable plant at Army Schofield Barracks in Hawaii
• Partnership with Hawaiian Electric Company (HECO)– Construction, ownership, operation and maintenance of plant
and a 46 kV sub-transmission line to connect plant to HECO grid – 10.3 acre land lease – 2.5 acre interconnection easement on Schofield Barracks and
adjacent Wheeler Army Airfield
Schofield Generating Station Project
Energy Exchange: Federal Sustainability for the Next Decade
• Army benefits:– Help achieve Army goals of producing renewable energy on Army-
owned real property– Enhance energy security for Schofield Barracks, and adjacent sites
Wheeler Army Airfield and Field Station Kunia
• HECO benefits:– Quick-start facility – Help maintain grid stability– Contribute to grid reliability and continuity if:
1) Tsunami/other natural disaster, due to location away from the shoreline2) Man-made threat, since located within a secured military installation
– Progress towards Hawaii’s Renewable Portfolio Standard
Schofield Generating Station Project
Energy Exchange: Federal Sustainability for the Next Decade
• Environmental Impact Statement (EIS) in progress– Will satisfy both federal National and Hawaii Environmental
Policy Acts (NEPA and HEPA)– Will integrate National Historic Preservation Act Section 106
consultation and public participation requirements – January 17, 2014: Notice of Intent published in Federal Register– Jan. 17- March 2, 2014: Scoping period– April 24, 2014: Draft EIS issued – April 24- June 8, 2015: 45 day public comment period
• http://www.garrison.hawaii.army.mil/schofieldplant/
Schofield Generating Station Project
Energy Exchange: Federal Sustainability for the Next Decade
• BNL serves has PV array host• BP is solar project developer• 20-year contract between solar developer and utility for
purchase of 100% of output and RECs• 20-year easement between BNL and solar developer• In-kind consideration - small PV project & research • Peak capacity 32 MW AC, ground-mounted• Annual Energy Output 44 million kWh• 200 acres of land, ~160,000 panels• Crystalline solar PV modules• Energize date November 2011
DOE Brookhaven
Energy Exchange: Federal Sustainability for the Next Decade
• Partnership between NASA and Florida Power & Light
• MOU signed December 2007• EUL signed June 2008• 10 MW FPL-owned PV project
– Output feeds into FPL transmission system– Substation expansion required
• In-Kind Consideration - 990 kW NASA-owned PV – Based on appraised value– FPL construction– Output feeds into NASA-owned
distribution system
• 130 mph wind standard
NASA Kennedy Space Center and Florida Power & Light
23
Project SummaryNellis AFB PV Array II
Hybrid Power Purchase Agreement and Enhanced Use Lease Local utility company (NV Energy) will build, own, and operate
solar PV array Anticipate 19 MW PV array on leased area of 122 acres
Will purchase approx 55% of total production at existing tariff rate All power will flow through the Nellis AFB Power not used by Nellis AFB will go to the grid
NV Energy will own/sell Renewable Energy Certificates (RECs) Contemplated lease (payment in kind) is secondary substation
Will afford Nellis with much needed energy resiliency/mission assurance by providing redundant primary electric feed to base
Will provide secondary output path to solar PV generating plant by two distribution feeders that will connect to existing substation
Lease signed 1 Mar 15
24
Project SummaryNellis AFB PV Array II
Collaborative effort between Nellis AFB (99 ABW), Air Combat Command (ACC), Air Force Civil Engineer Center (AFCEC), and Air Force General Counsel (SAF/GCN) 99 ABW conducted National Environmental Policy Act process, gained
acceptance from with other agencies, and coordinated with NV Energy ACC evaluated economic viability, mission impact/encroachment issues,
and provided expertise for PPA AFCEC provided overall project oversight and served as liaison with
senior AF leadership for execution and scheduling AFCEC and SAF/GCN led real estate actions and lease development
Energy Exchange: Federal Sustainability for the Next Decade
David McAndrew: 202-586-7722, [email protected] Chandra Shah: 303-384-7557, [email protected]
GSA Areawide Contract Information: http://www.gsa.gov/portal/content/184635
FEMP Trainings: http://apps1.eere.energy.gov/femp/training/
FEMP Project Funding Web Site: www1.eere.energy.gov/femp/financing/mechanisms.html
Renewable Project Financing Mechanisms:http://energy.gov/eere/femp/financing-mechanisms-federal-renewable-energy-projects
UESC Resources (some information applicable to other utility partnerships): http://www1.eere.energy.gov/femp/financing/uescs_resources.html
Resources