pheasant flight pen construction
TRANSCRIPT
Flight Pen ConstructionFlight Pen ConstructionBy Chris TheisenBy Chris Theisen
OUR GOAL:OUR GOAL: Build 24 acres of pens in 5 months
1,045,440 square feet1,045,440 square feet 1900 posts to put in the ground1900 posts to put in the ground 4 ½ miles of wire to stretch4 ½ miles of wire to stretch 11 ½ miles of cable to run11 ½ miles of cable to run 2 ½ miles of trench to dig2 ½ miles of trench to dig 20,000 staples to pound20,000 staples to pound ½ million rings to install½ million rings to install 1 ½ miles of water line to hang1 ½ miles of water line to hang 150 gates to build and hang150 gates to build and hang
Before you do anything…Before you do anything………Look at the layout – make plans for the Look at the layout – make plans for the
future future
……Plan on expanding even if you don’t Plan on expanding even if you don’t have any plans to do sohave any plans to do so
……Research and ask questions – there are Research and ask questions – there are a lot of ideas out therea lot of ideas out there
Site PreparationSite Preparation It’s easier before the pens go upIt’s easier before the pens go up
Know the entire layout of the pens Know the entire layout of the pens before doing ANYTHING.before doing ANYTHING.
Important part of the process – DON’T Important part of the process – DON’T overlook itoverlook it
Don’t overlook the roads
Start by pounding the postsStart by pounding the posts
Hang the cable…
…Then you can stretch the wire
WIRE INSTALLATIONWIRE INSTALLATION Efficient, Simple, and ReliableEfficient, Simple, and Reliable
Work smart, not hardWork smart, not hard
Efficiency saves moneyEfficiency saves money
Don’t give up on initial ideas – Don’t give up on initial ideas – improve upon themimprove upon them
Beveled so wire does not get caught
One person can put wire on the pipe with the rollers
Flatbed allows us to carry multiple rolls
Hinged so pipe can lay on the rollers
Plate with bearings underneath
7 minutes to 7 minutes to installinstallone roll of wireone roll of wire
Run the division fences firstRun the division fences first
Then run the perimeter wireThen run the perimeter wire
Stretch the wire tightStretch the wire tight
DIGGING TRENCHESDIGGING TRENCHESMany different ideas and approachesMany different ideas and approaches
trenchertrencher Excavator Excavator shovelshovel
Come up with a different ideaCome up with a different idea
Transition from 6’ division fence to 7’ laneTransition from 6’ division fence to 7’ lane
Stretch the lane wire last
Easier to install gates BEFORE fence and netting are up
Joyce Hangers for Headers
Lane GatesLane Gates
Channel iron to support kick boards
NETTINGNETTING
Differences in Knotted vs. Woven netsDifferences in Knotted vs. Woven nets
Differences in Nylon vs. Polyethylene Differences in Nylon vs. Polyethylene netsnets
Important to get 1Important to get 1stst net up square net up square
Run the water line
Notice water line on outside of penNotice water line on outside of pen
Plant pens BEFORE pens are finishedPlant pens BEFORE pens are finished
Add feeders BEFORE installing the nettingAdd feeders BEFORE installing the netting
October 15th, 2006October 15th, 200624 Acres of pens – complete!24 Acres of pens – complete!
Remember…Remember…Improve on existing procedures Improve on existing procedures
Keep an open mindKeep an open mind
Talk to people – get their inputTalk to people – get their input
Work smart – not hardWork smart – not hard