Page 1: Phase G_2 Quick Installation Guide20100108

HUAWEI TECHNOLOGIES Co., Ltd.

Sudatel Phase G.2Li ShichuangDate: 2010-01-06

Phase G.2 Quick Installation Guide-IBSS+APM30+DBS3900

Page 2: Phase G_2 Quick Installation Guide20100108

IBBS Cabinet Installation

APM30 Cabinet Installation

DBS3900 Installation

RF part Installation

Page 3: Phase G_2 Quick Installation Guide20100108

Site modea IBBS+APM30+DBS3900(900M+1800M)

b BBC+APM30+DBS3900(900M Only)

Page 4: Phase G_2 Quick Installation Guide20100108

Layout

Page 5: Phase G_2 Quick Installation Guide20100108

IBSS Installation

Page 6: Phase G_2 Quick Installation Guide20100108

IBSS installation

a Determining the anchor points and installing the expansion bolt assembly (unit: mm)

According to the Space Requirements of the IBBS, determine the position of the cabinet on the concrete floor.

Use a Ф16 drill bit to drill holes at the marked positions. Ensure that the depth of the holes ranges from 52 mm to 60 mm.Use a cleaner to clean the dust inside and around the holes.Measure the spacing between the holes. If the spacing has an error, relocate and drill another hole before installing the expansion bolt assembly.Align the expansion bolt assemblies with the holes and then use a rubber hammer to strike each assembly until the expansion tube is completely buried into the hole.

Page 7: Phase G_2 Quick Installation Guide20100108

7

Use a level bar to measure the levelness of each section of the base. If necessary, level the baseby adding one or more adjusting pads.

Fixing the baseb

Page 8: Phase G_2 Quick Installation Guide20100108

c Installing the IBBS cabinet

8

Page 9: Phase G_2 Quick Installation Guide20100108

d Cable connections of the batteries

Page 10: Phase G_2 Quick Installation Guide20100108

e Installing TEC AC power cable

12

The power cables for the TEC cooler and the fans The power cables for the TEC cooler and the fans share the LOAD2 terminal on the PDU.share the LOAD2 terminal on the PDU.

The red color cable is already connected during the manufacture.The red color cable is already connected during the manufacture.

Page 11: Phase G_2 Quick Installation Guide20100108

Installing the IBBS External Cablesf

No smoke sensor in Phase G

Page 12: Phase G_2 Quick Installation Guide20100108

g Connect the monitoring cable to APM30

11

Remove the short-circuiting cable from the terminal of the door control cable in the APM30 main cabinet. Connect the cold end terminal on the door control cable (white and green) to the cable terminal.

Door control cable

1. Connect the 2-pin connector on the temperature sensor cable (white and orange) to the Bat 1_TmpBat 1_Tmp socket of the APMI inside APM30 (Temperature Monitor)

2. Connect the white white TEC alarm cable to the E2E2 port;3. Connect the blueblue TEC alarm cable to the E1E1 port ( TEC monitor)

Page 13: Phase G_2 Quick Installation Guide20100108

APM30 Installation

Page 14: Phase G_2 Quick Installation Guide20100108

a

According to the Space Requirements of the APM30, determine the position of the cabinet on the concrete floor.

Determining the anchor points and installing the expansion bolt assembly (unit: mm)

APM30 Installation

Page 15: Phase G_2 Quick Installation Guide20100108

b Fixing the base

c Adjusting the levelness of the base

You should test the levelness in both directions. Check whether the level vial stays in the center of the level, if not, add adjusting pads under the cabinet base to ensure that the cabinet base is kept level after adjustment.

7

Page 16: Phase G_2 Quick Installation Guide20100108

d Installing the APM30

Page 17: Phase G_2 Quick Installation Guide20100108

e Installing the PMU/PSUs

Determine the position for installing the PMU and PSUs . Setting the DIP switch on the PMU

(1100).

Place the PMU or PSUs in the corresponding slot or slots, and then loosen the screws on the handle of the PMU or PSU panel by using a straight screwdriver.

Slide the PSU along the guide rails into the slot and then push the handle in position , Fasten the screws on the handle.

Page 18: Phase G_2 Quick Installation Guide20100108

f Installing the Batteries for the APM30Before installation, set the MCB labeled Bat under the rectifier to OFF to avoid a high current.

Connect the cables to wiring terminals BAT(-) and BAT(+) on the power supply subrack respectively.

14

g Installing the Input Power Cable of the APM30 Power Cabinet

Remove the short-circuiting bars .(Attention)Connect the OT terminals to the AC input wiring terminals labeled L1, L2, L3, and N on the PDU.

Page 19: Phase G_2 Quick Installation Guide20100108

h Installing the Environment/ PMU-HEUM Monitoring Signal Cable

i Installing the Monitoring Signal Cable Between the HPMI and PMU

From From ““RS232/RS422RS232/RS422”” port on PMU panel to port on PMU panel to ““COM OUTCOM OUT”” port on HEUA panel.port on HEUA panel.

From port From port ““COMCOM”” on PMU panel to port on PMU panel to port ““COMCOM”” on HPMI panel .on HPMI panel .

Page 20: Phase G_2 Quick Installation Guide20100108

““COM INCOM IN”” port on the HEUA panel and the other end to the port on the HEUA panel and the other end to the ““MON1MON1”” port on the BBU.port on the BBU.

j Installing the BBU Monitoring Signal Cable

Page 21: Phase G_2 Quick Installation Guide20100108

NOTE

The mapping between the cables and the cable holes at the bottom of the cabinet for IBBS.

Power CablePower Cable1、Power cable between IBBS and APM30 ------------------35mm^22、PGND cable for IBBS ------------------------------------------25mm^23、Power cable for TEC -------------------------------------------2.5mm^24、PGND cable for APM30----------------------------------------16mm^2

Page 22: Phase G_2 Quick Installation Guide20100108

Installing the BBU in the APM30

Page 23: Phase G_2 Quick Installation Guide20100108

Installing the BBU in the APM30Installing the BBU Casea

Installing the BBU Cablesb

6

PDU

Slide the BBU case along the guide rails into the 2 U space closely under the PDU. Then, fasten the four M6 screws.

External power supply

External alarm device

Monitoring signal cable

Alarm cable

BSC

E1cable

CPRI signal cable

E1 transfer cable

Power cable

Cable connections of the BBU

External monitoring device

Page 24: Phase G_2 Quick Installation Guide20100108

Installing the BBU CablesbInstall the power cable. Connect the OT terminal of the power cable to the LOAD terminal on the APM30H, and then fix the 3W3 connector of the power cable to the PWR port on the BBU.

Install the CPRI optical cable. Connect one end of the optical cable to the CPRI0, CPRI1, or CPRI2 port on the GTMU panel of the BBU and the other end to the CPRI_W port on the RRU.

a. Insert the optical module into the CPRI0, CPRI1, or CPRI2 port, and then turn outwards the puller on the optical module.

b. Insert one end of the CPRI optical cable into the optical module, and then lead the CPRI optical cable out of the cabinet along the right side of the cabinet.

c. Wrap the fiber tail with the winding pipe.

Optical modulePuller

Connect the BBU power cable to the 12 A12 A LOAD terminal.

Connect the RRU power cable to one of the LOAD4 to LOAD9 terminals.

Winding pipe

The TX port on the BBU is connected to the RX port on the RRU ; the RX port on the BBU is connected to the TX port on the RRU.

7

Page 25: Phase G_2 Quick Installation Guide20100108

b ground the shielding layer of the RRU power cableb

Use the grounding clip to ground the Use the grounding clip to ground the shielding layer of the RRU cable shielding layer of the RRU cable inside the APM30.inside the APM30.

Page 26: Phase G_2 Quick Installation Guide20100108

Reference

41

Add two OT terminals to the end of the power cable connecting to the RRU.

Making OT Terminals by Using a Cable Peeler (Recommended)

The assembling of OT terminals to the power cable must be complete before the RRU is installed on a metal pole.

-48V DC power cable -48V DC power wire

GND wire

Shielding layer

OT terminals

Determine lengths of power cables for different operations according to the scales on the inner side of the cover plate of the cabling cavity.

Based on the determined length, remove the jacket and shielding layer off the power cable.

Add an OT terminal to each wire.

Strip a 15 mm jacket off the power cable to reveal the shielding layer of the power cable

Remove the jacket from each wire.

Page 27: Phase G_2 Quick Installation Guide20100108

Reference

Making OT Terminals at the Input End of the Power Cable by Using a Knife

Warning: Do not damage the shielding layer of the power cable when cutting around the jacket.

OT terminal on the shielding layer

Lead the wires with shielding layers through heat-shrinkable tubes

Wrap the PVC insulating tape at the conjunction where the three wires meet

Page 28: Phase G_2 Quick Installation Guide20100108

RRU Installation

Page 29: Phase G_2 Quick Installation Guide20100108

a Preparing for the Installation

Fixture assembly for installing the RRU Front of the RRU

Back of the RRU

Cover plate Attachment

plate

Main fixture

Auxiliary fixture

Dual-nut bolt assembly

Installing the DC RRU3008

Top view

Angle steel

Page 30: Phase G_2 Quick Installation Guide20100108

b Installing the RRU on the Pole

1. Install the main fixture.

Contact piece

1. When installing the main fixture, ensure that the arrow on the main fixture is upward. 2. When installing the main fixture, ensure that the contact piece on the fixture is fixed.

It is recommended that the bottom of the highest main fixture be 1200 mm to 1600 mm above the ground for easy maintenance.

Arrow

2. Install the auxiliary fixture between the nuts of the dual-nut bolt assembly on the main fixture.

TIP: You may fit one end of the auxiliary fixture on one dual-nut bolt assembly and then the other end on the other dual-nut bolt assembly during the installation.

Ensure that the arrow on the auxiliary fixture is upward.

Installation position for the auxiliary fixture

Installing the DC RRU3008

Page 31: Phase G_2 Quick Installation Guide20100108

Installing the DC RRU3008 3. Use an adjustable wrench to tighten the nut until the fastening torque is 35 N•m to 40 N•m. In this way, the main and auxiliary fixtures are secured on the pole.

4. Install the RRU on the main bracket. When you hear a click, you can infer that the RRU is in position.

The screw is a non-fixed one and can be neglected during the installation.It is only used when the RRU is removed.

The RF port at the bottom of the RRU does not have load bearing capacity. Do not place the RRU on the ground on its bottom during the installation.

Fasten the two dual-nut bolt assemblies alternatively. After the brackets are secure, use a tape to measure the spacing between the main bracket and the auxiliary bracket at the two sides and ensure that the spacing is the same.

Page 32: Phase G_2 Quick Installation Guide20100108

Opening and Closing the Cover Plate of the RRU Cabling Cavity

17

n Installing the RRU Cables

Installing the DC RRU3008

Cable trough for the power cable

Cable trough for the optical cable

Cable trough for alarm cable

Waterproof filler

Cover plate of the cabling cavity

Cabling cavity

Cabling Cavity of the RRU

① Open the cover plate of the RRU cabling cavity.

② Close the cover plated of the RRU cabling cavity.

1. The screw on the cover plate is tightened until the fastening torque is 14 kgf•cm.2. The screws on the cover plate are tightened in the order shown in the preceding figure.

14kgf•cm

Page 33: Phase G_2 Quick Installation Guide20100108

n Installing the RRU Cables

Installing the DC RRU3008

Cable Connections of RRU

CPRI optical cable

Shielding layer of the power cable

Power cable

First wrap the joint with the waterproof tape, and then wrap the joint with the PVC insulating tape.

Grounding boltOT terminalPGND cable

RF jumper

The RRU power cable is connected to 20A 20A LOAD terminals of PDU in APM30.

Page 34: Phase G_2 Quick Installation Guide20100108

RF Part Installation

Page 35: Phase G_2 Quick Installation Guide20100108

1 Assemble the Antenna

a Assemble the support

b Fix the support onto the antenna

1. The antenna described in this guide is an 800MHz directional antenna of Huawei. For installation of other antennas, see the relative manuals.

2. The assembly of three antennas is complete on the ground.

Fix the upper support

Fix the lower support Finished

Page 36: Phase G_2 Quick Installation Guide20100108

Wrap three layers of waterproof tape

Wrap three layers of insulation tape

Fix the cable ties

1. When wrapping the tape, ensure that the upper layer covers more than 50% of the lower layer.

2. Before wrapping the waterproof tape, stretch the tape till the width of the tape becomes 1/2 of the original. Stretch each layer of the waterproof tape and wrap each layer around the jumpers tightly.

2 Connect Jumpers to the Antenna

a Connect jumpers

1. Use six jumpers with fixed length.

2. (Optional) If no jumper with a fixed length is available, cut a jumper into proper lengths and fix DIN male connectors to both ends of the jumpers.

b Stick color rings

c Seal the connectors

1. Ensure that the color rings are in the correct direction and positions. Wrap the jumpers with 2 or 3 layers of tape to make the color rings. The distance between neighboring color rings is 10 mm to 15 mm.

2. Stick the first color ring at the position 200 mm away from the jumper connector.

Optional

Finished

Page 37: Phase G_2 Quick Installation Guide20100108

3 Lift the Antenna

1. Installers A and B climb onto the tower. Installer B fixes the fixed pulley onto the support of the tower platform and puts the lifting rope through the fixed pulley.

2. Installer D uses plastic bags or tape to wrap the jumper connectors and then coils the jumpers. Fasten the lifting rope to the upper support of the antenna and the traction rope to the lower support.

3. Installer C pulls down the lifting rope, and installer D pulls the traction rope outwards to prevent the antenna from hitting the tower.

4. Installers A and B hold the antenna and unfasten the ropes.

5. After three antennas are lifted onto the platform, do not remove the fixed pulley, because the feeder needs to be lifted later.

Page 38: Phase G_2 Quick Installation Guide20100108

4 Install the Antenna

a Install the antenna on a pole

b Make the waterproof curve of jumpers

c Adjust the antenna azimuth

Page 39: Phase G_2 Quick Installation Guide20100108

4 Install the Antenna

d Adjust the tilt angle of the antenna

Method 1: Using the scale on the upper support

Method 2: Using the inclinometer

Method 3: Rotating the gear wheel on the antenna (only for the RET antenna)

Page 40: Phase G_2 Quick Installation Guide20100108

Distinguishing Cables & Cables fixing

Blue, two ringsBlue, one ring3Yellow, two ringsYellow, one ring2Red, two ringsRed, one ring1

1800M Power cable/Fiber900M Power Cable/Fiber Sector

1. Use the cable fixing clip to fix the RRU power cable and fiber cable

2.2. 1 M fix one time1 M fix one time

Page 41: Phase G_2 Quick Installation Guide20100108

Note

Seal the APM30 and IBBS holes to protect the water and dust.Seal the APM30 and IBBS holes to protect the water and dust.

Page 42: Phase G_2 Quick Installation Guide20100108

Sudatel Phase GLi shichuang