ph electric power industry market and policy assessment
TRANSCRIPT
Philippine Electric Power Industry Market and Policy Assessment
and Analysis of International Markets
Prepared by
Prof. Rowaldo D. del Mundo Ms. Edna A. Espos
With Contribution of
Ms. María Isabel Rodríguez González (former State Undersecretary, National Energy Commission of Chile)
UNIVERSITY OF THE PHILIPPINES – NATIONAL ENGINEERING CENTER
and U.P. Engineering Research & Development Foundation, Inc.
May 2011
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center i
Table of Contents Section Title Page No.
EXECUTIVE SUMMARY ........................................................................................................................... 8
I SUPPLY AND DEMAND ANALYSIS OF LUZON GRID ............................................................. 16
1 THE DEMAND SECTOR ................................................................................................................. 17
1.1 SYSTEM DEMAND OF LUZON GRID ................................................................................................. 17 1.1.1 HISTORICAL DEMAND OF LUZON GRID (MW ............................................................................... 17 1.1.2 ELECTRICITY SALES AND CONSUMPTION IN LUZON (2009) ........................................................ 17 1.1.3 DEMAND DRIVERS OF THE LUZON GRID ...................................................................................... 19 1.1.4 LUZON GRID DEMAND FORECAST (2011-2030) ........................................................................ 20 1.2 LOAD CHARACTERISTICS OF THE LUZON GRID ............................................................................. 22
2 THE SUPPLY SECTOR .................................................................................................................... 26
2.1 POWER PLANTS IN LUZON GRID .................................................................................................... 26 2.1.1 INSTALLED AND DEPENDABLE CAPACITY OF POWER PLANTS ..................................................... 26 2.1.2 PROPOSED POWER GENERATION PROJECTS ................................................................................. 27 2.1.3 OWNERSHIP OF POWER PLANTS AND CONTROL OF IPPA CONTRACTED CAPACITY .................... 29 2.2 WHOLESALE ELECTRICITY SPOT MARKET .................................................................................... 31
3 SUPPLY-DEMAND BALANCE ....................................................................................................... 32
3.1 RELIABILITY PERFORMANCE OF THE GRID ................................................................................... 32 3.1.1 RELIABILITY INDEX AND CRITERIA ............................................................................................... 32 3.1.2 HISTORICAL RELIABILITY PERFORMANCE OF LUZON GRID .......................................................... 34 3.1.3 RELIABILITY PERFORMANCE OUTLOOK ........................................................................................ 34 3.2 REGIONAL PERSPECTIVE OF SUPPLY-DEMAND BALANCE ............................................................ 35 3.3 GENERATION EXPANSION ANALYSIS .............................................................................................. 36 3.3.1 GENERATION EXPANSION METHODOLOGY, CRITERIA, AND SCENARIOS ...................................... 36 3.3.2 EXPANSION PATTERN OF LUZON GRID WITHOUT MALAYA AND LIMAY POWER PLANTS ............ 37 3.3.3 EXPANSION PATTERN OF LUZON GRID WITH MALAYA AND LIMAY POWER PLANTS IN-SERVICE 40 3.3.4 HINDSIGHT GENERATION EXPANSION SCENARIO FOR NATURAL GAS PRICE ............................... 42
II ANALYSIS OF THE POLICY AND REGULATORY FRAMEWORK OF THE PHILIPPINE ELECTRIC POWER INDUSTRY ........................................................................................................... 44
4 THE POLICY FRAMEWORK OF THE PHILIPPINE ELECTRIC POWER INDUSTRY ...... 45
5 ASSESSMENT OF RESULTS OF EPIRA REFORMS .................................................................. 50
5.1 TOTAL ELECTRIFICATION ............................................................................................................... 50
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center ii
5.2 QUALITY, RELIABILITY AND SECURITY OF ELECTRICITY SUPPLY .............................................. 51 5.3 ENHANCED INFLOW OF PRIVATE CAPITAL, PRIVATE OWNERSHIP AND BROADENING OF THE
OWNERSHIP BASE ...................................................................................................................................... 54 5.3.1 PRIVATIZATION OF NPC ASSETS AND IPP CONTRACTS ............................................................... 54 5.3.2 ENHANCED INFLOW OF PRIVATE CAPITAL.................................................................................... 55 5.3.3 BROADENING OF OWNERSHIP BASE .............................................................................................. 57 5.4 GREATER UTILIZATION OF INDIGENOUS AND NEW AND RENEWABLE ENERGY TO REDUCE
DEPENDENCE ON IMPORTED ENERGY ...................................................................................................... 64 5.5 FAIR AND NON-DISCRIMINATORY TREATMENT OF PUBLIC AND PRIVATE SECTOR ENTITIES IN
THE RESTRUCTURING PROCESS ............................................................................................................... 64 5.6 SOCIALLY AND ENVIRONMENTALLY RESPONSIBLE SOURCES OF ENERGY AND INFRASTRUCTURE
65 5.7 EFFICIENT USE OF ENERGY AND DEMAND SIDE MANAGEMENT .................................................. 66 5.8 AFFORDABLE, TRANSPARENT AND REASONABLE ELECTRICITY RATES ..................................... 67 5.9 CONSUMER PROTECTION AND COMPETITION THROUGH A STRONG AND INDEPENDENT
REGULATOR ................................................................................................................................................ 74
6 ASSESSMENT OF INDUSTRY REGULATION ........................................................................... 75
6.1 STRUCTURAL POLICY ...................................................................................................................... 76 6.1.1 VERTICAL SEPARATION OF TRANSMISSION FROM GENERATION AND DISTRIBUTION ................. 76 6.1.2 VERTICAL INTEGRATION OF GENERATION AND DISTRIBUTION ................................................... 76 6.1.3 HORIZONTAL SEPARATION OF GENERATION ................................................................................ 79 6.2 OWNERSHIP ..................................................................................................................................... 85 6.2.1 PRIVATIZATION OF NPC ASSETS AND IPP CONTRACTS ............................................................... 85 6.2.2 DEMOCRATIZATION ....................................................................................................................... 86 6.2.3 OWNERSHIP OF ELECTRIC COOPERATIVES ................................................................................... 87 6.3 LIBERALIZATION AND DEREGULATION ......................................................................................... 90 6.3.1 GENERATION AND ELECTRICITY MARKETS ................................................................................... 90 6.3.2 STRANDED COSTS .......................................................................................................................... 97 6.4 CONDUCT REGULATION ................................................................................................................ 100 6.4.1 RATE SETTING METHODOLOGY FOR TRANSMISSION AND PRIVATE DISTRIBUTION UTILITIES . 100 6.4.2 NEW RATE SETTING METHODOLOGY FOR ELECTRIC COOPERATIVES ........................................ 102 6.4.3 REGULATION OF NON-PRICE CONDUCT: ERC COMPETITION RULES ......................................... 104 6.5 WHOLESALE ELECTRICITY SPOT MARKET .................................................................................. 106 6.5.1 OVERVIEW OF WESM ................................................................................................................. 106 6.5.2 PERFORMANCE HIGHLIGHTS ....................................................................................................... 109 6.5.3 ASSESSMENT OF WESM .............................................................................................................. 114 6.6 SECURITY OF SUPPLY .................................................................................................................... 120 6.6.1 CAPACITY PLANNING AND PROJECT COMMITMENT .................................................................... 121 6.6.2 PLANNING METHODOLOGY AND CRITERIA ................................................................................. 123 6.6.3 PROVISION OF OPERATING RESERVE .......................................................................................... 125 6.6.4 REPLACEMENT POWER FOR MAINTENANCE OUTAGE ................................................................ 126
7 ASSESSMENT OF INSTITUTIONAL GOVERNANCE FRAMEWORK ................................ 128
7.1 OVERVIEW OF INSTITUTIONAL GOVERNANCE ............................................................................ 128 7.2 APPRAISAL OF INSTITUTIONAL GOVERNANCE ............................................................................ 129 7.2.1 CLARITY OF ROLES AND OBJECTIVES .......................................................................................... 129 7.2.2 AUTONOMY .................................................................................................................................. 131
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center iii
7.2.3 PARTICIPATION ............................................................................................................................ 131 7.2.4 ACCOUNTABILITY......................................................................................................................... 132 7.2.5 TRANSPARENCY ........................................................................................................................... 132 7.2.6 PREDICTABILITY .......................................................................................................................... 133
III ANALYSIS OF INTERNATIONAL MARKETS ........................................................................ 134
8 PURPOSE OF ANALYSIS OF COMPARABLE INTERNATIONAL MARKET .................... 135
9 CHILE’S ELECTRIC POWER INDUSTRY ................................................................................. 136
9.1 OVERVIEW OF ELECTRIC POWER INDUSTRY OF CHILE .............................................................. 136 9.2 INDUSTRY RESTRUCTURING AND POLICY REFORMS .................................................................. 140 9.2.1 KEY ISSUES PRIOR TO REFORM ................................................................................................... 140 9.2.2 INSTITUTIONAL BACKGROUND , KEY OBJECTIVES AND ELEMENTS OF THE REFORM ................ 141 9.2.3 POLICY AND REGULATION OF GENERATION ................................................................................ 142 9.2.4 POLICY AND REGULATION OF TRANSMISSION ............................................................................. 149 9.2.5 POLICY AND REGULATION OF DISTRIBUTION .............................................................................. 151 9.3 CHILE’S POST REFORM INSTITUTIONAL GOVERNANCE FRAMEWORK ...................................... 153
10 BRAZIL’S ELECTRIC POWER INDUSTRY ............................................................................ 155
10.1 OVERVIEW OF THE ELECTRIC POWER INDUSTRY OF BRAZIL .................................................. 155 10.2 INDUSTRY RESTRUCTURING AND POLICY REFORM ................................................................. 157 10.2.1 POLICY AND REGULATION OF GENERATION ............................................................................. 161 10.2.2 POLICY AND REGULATION OF TRANSMISSION .......................................................................... 166 10.2.3 POLICY AND REGULATION OF DISTRIBUTION ........................................................................... 169 10.2.4 POLICY AND REGULATION FOR RENEWABLE ENERGY .............................................................. 170 10.3 BRAZIL’S POST REFORM INSTITUTIONAL GOVERNANCE FRAMEWORK ................................. 171
11 KEY POINTS AND LESSONS LEARNED FROM INTERNATIONAL EXPERIENCE ...... 174
12 COMPARATIVE MARKET ANALYSIS: CHILE, BRAZIL AND PHILIPPINES ............... 177
IV PROPOSED REFORMS FOR PHILIPPINE POWER INDUSTRY ....................................... 183
13 POLICY AND REGULATORY REFORMS ............................................................................... 184
13.1 IMMEDIATE REFORMS ................................................................................................................ 184 13.1.1 COMPETITIVE BIDDING OF FORWARD POWER CONTRACTS ....................................................... 184 13.1.2 DEFERMENT OF RETAIL COMPETITION .................................................................................... 184 13.1.3 RESTRUCTURING OF THE OWNERSHIP OF ELECTRIC COOPERATIVES ...................................... 185 13.1.4 LIMITING ERC’S ADJUSTMENT TO INSTALLED GENERATING CAPACITY ................................... 185 13.2 MEDIUM TERM REFORMS .......................................................................................................... 185 13.2.1 PROPER IMPLEMENTATION OF THE PBR RATE-SETTING METHODOLOGY ............................. 185 13.2.2 AMENDMENT OF THE HORIZONTAL SEPARATION POLICY ON GENERATION ........................... 185 13.2.3 INTERCONNECTION OF LUZON, VISAYAS AND MINDANAO ....................................................... 186 13.2.4 STRENGTHENING OF THE WESM ............................................................................................. 186 13.2.5 VERTICAL SEPARATION OF GENERATION AND DISTRIBUTION SECTORS ................................. 186
14 INSTITUTIONAL GOVERNANCE REFORMS ....................................................................... 187
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center iv
14.1 DOE’S ASSERTION OF ITS AUTHORITY UNDER EPIRA ........................................................... 187 14.2 STRENGTHENING OF ADMINISTRATIVE CAPACITY OF ERC THROUGH FINANCIAL AUTONOMY
AND MAINTAINING A BALANCE OF EXPERTISE ...................................................................................... 187 14.3 FLEXIBILITY IN THE REGULATORY PROCESSES ........................................................................ 188
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center v
List of Tables Table No. Title Page No.
Table 1. Annual Peak Demand and Growth Rate of Luzon Grid, 2000-2010 ................................ 17 Table 2. Forecasted Annual Peak Demand (in MW) of Luzon Grid, 2011-2030 .......................... 22 Table 3. Plant Cost Parameters for the Screening Curve ....................................................................... 25 Table 4. Load Category of Luzon Grid, 2010 ............................................................................................... 25 Table 5. Generation Capacity in Luzon Grid According to Plant-Type and Regional Location (in MW) ...................................................................................................................................................................... 26 Table 6. Percentage Dependable Capacity by Plant-Type and Regional Location ...................... 27 Table 7. Capacity of Proposed Power Plants for 2010-2017 Published by DOE ......................... 28 Table 8. Proposed Power Plants for 2010-2017 ....................................................................................... 28 Table 9. Private Ownership of Power Plants and Control of IPPA Contracted Capacities ...... 30 Table 10. Reliability Performance of Luzon Grid, 2000-2010 ........................................................... 35 Table 11. Regional Perspective of Power Supply-Demand Balance of Luzon Grid, 2011....... 35 Table 12. Generation Capacity Expansion Without Malaya and Limay Power Plants (Forecast Demand under Moderate Economic Growth Scenario) .................................................... 38 Table 13. Generation Capacity Expansion Without Malaya and Limay Power Plants (Forecast Demand under Low Economic Growth Scenario) ............................................................... 39 Table 14. Generation Capacity Expansion Without Malaya and Limay Power Plants (Forecast Demand under High Economic Growth Scenario) .............................................................. 40 Table 15. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast Demand under Moderate Economic Growth Scenario) ......................................................................... 41 Table 16. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast Demand under Low Economic Growth Scenario) .................................................................................... 41 Table 17. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast Demand under High Economic Growth Scenario) ................................................................................... 42 Table 18. Generation Capcity Expansion for Hindsight Scenario ..................................................... 43 Table 19. EPIRA Policy and Regulatory Framework ............................................................................... 46 Table 20. Addition to Installed Generating Capacity after 2001 ........................................................ 56 Table 21. Committed Generation Investments as of June 2010 ......................................................... 57 Table 22. Ownership Distribution of Private Generating Plants ........................................................ 59 Table 23. CO2 Emission of Selected Philippine Power Plants (in kTons) ...................................... 66 Table 24. MERALCO Comparative Charges1, 20032-20103 (Pesos) .................................................. 71 Table 25. Brazil Average Electricity Prices, 2010 ..................................................................................... 73 Table 26. Installed Generating Capacities of the San Miguel Group in the Luzon Grid ............ 84 Table 27. Installed Generating Capacities of Lopez and Aboitiz Groups in Luzon Grid ........... 84 Table 28. Investments for New Generation Projects in Chile ........................................................... 148 Table 29. Installed Generating Capacity in Brazil (2001-2010) ...................................................... 155 Table 30. Average Price of Electricity in Brazil (2010) ....................................................................... 157 Table 31. Comparative Analysis of Chile, Brazil and Philppine Power Markets ....................... 177
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center vi
List of Figures
Figure No. Title Page No.
Figure 1. Luzon Grid Energy Sales (MWh) and Consumption by Sector, 2009 ............................ 18 Figure 2. Luzon Grid Energy Sales by Region, 2009 ................................................................................ 19 Figure 3. Luzon Grid Peak Demand, GRDP, Population and Electricity Price (2000-2010) ... 20 Figure 4. Typical One-Day (Hourly) Demand of Luzon Grid ................................................................ 23 Figure 5. Daily Peak Demand (365 days) of Luzon Grid, 2009 ........................................................... 24 Figure 6. Load Duration and Plant Type Screening Curve .................................................................... 24 Figure Figure 7. Variations in Hydro Power generation ....................................................................... 32 Figure 8. Loss of Load Expectation vs. Capacity Reserve of Luzon Grid, 2000-2010 ................ 33 Figure 10. Reliability Performance of Luzon Grid, 2000-2010 ........................................................... 34 Figure 10. Reliability Performance of Luzon Grid With and Without Expansion ....................... 38 Figure 11. National Gross Power Generation By Resource, 2001 and 2009 ................................. 53 Figure 12. Gross Power Generation By Grid and Resource, 2001 and 2009................................. 53 Figure 13. Weighted Average Price of Malampaya Gas (2002-2009, Quarters) .......................... 54 Figure 14. Control of Installed Generating Capacity as of March 2011 , ........................................ 63 Figure 15. Annual Average Effective Rates Rates (2000-2009) ......................................................... 68 Figure 16. NPC Annual Average Effective Rates (2003-2010) ............................................................ 69 Figure 17. MERALCO Average Monthly Generation Cost (2008-2010) .......................................... 72 Figure 18. Chile: Typical Residential Energy Price .................................................................................. 73 Figure 19. Chile: Typical Industrial Regulated Price ............................................................................... 73 Figure 20. Control of 2010 Installed Generating Capacity, Luzon ..................................................... 85 Figure 21. WESM Governance Structure ................................................................................................... 108 Figure 22. Market Transactions (2009,2010) ......................................................................................... 110 Figure 24. Pricing Errors ................................................................................................................................. 111 Figure 24. Price Substitution ......................................................................................................................... 111 Figure 25. Supply and Demand Profile (26 June 2009 to 25 June 2010) .................................... 112 Figure 26. Monthly Outage Rate By Resource (July 2009-June 2010) .......................................... 112 Figure 27. Price Distribution (June 2009 to June 2010) ..................................................................... 113 Figure 28. Market Price Trend (June 2009 to June 2010) ................................................................. 113 Figure 29. HHI Based on Actual Generation Net of Bilateral ............................................................ 114 Figure 30. Combined Pivotal Supplier-Price Setter Index ................................................................. 114 Figure 31. Generation Capacity Plan of DOE PDP .................................................................................. 124 Figure 32. Governance Structure of the Philippine Electric Power Industry ............................ 128 Figure 33. Energy Production in the Chilean National Grids ............................................................ 138 Figure 34. Generation Profile Per Technology in Chile ....................................................................... 139 Figure 35. Chilean Electricity Market Structure .................................................................................... 140 Figure 36. Percentage Change in Distribution Tariffs From VAD ................................................... 153
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center vii
List of Boxes
Box No. Title Page No.
Box No. 1- Forecasting Model for Luzon Grid Peak Demand ............................................................... 20 Box No. 2 - Excerpt, ERC Resolution No. 21 Series of 2005 ............................................................... 93 Box No. 3 - New Rate Setting Methodology for Electric Cooperatives ......................................... 103 Box No. 4 - Excerpt from ERC Competition Rules ................................................................................ 105
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 8
EXECUTIVE SUMMARY1
Objectives of the Study
The paucity of new generation investments despite the EPIRA has led to supply
shortages that conjure unpleasant images of the electricity crisis of the late 1980s to the
early 1990s and increasing calls to amend the law. A number of proposals are now being
considered in and out of Congress – from minor adjustments to drastic overhaul of the
law.
This study is intended to contribute to the debate by offering well-considered proposals
for policy and regulatory reforms to incent generation investments. It is anchored on
the premise that an in-depth analysis of the current state of the industry and its
operating and policy environments are crucial in the design of effective policy and
regulatory responses that could avoid the crisis and the costly IPP route in the 1990s.
Objectives of the Study
The study has several parts. Part I is a market and supply study of the Luzon Grid. Part II
analyzes the policy framework of the Philippine electric power industry, Part III analyzes
the power industry in Brazil and Chile which were chosen as comparators due to their
size and reform’s initial goals. It also includes a set of proposals for policy and regulatory
reforms that were gleaned from the preceding policy analysis. The last part summarizes
the reform proposals for the Philippine Electric Power Industry.
The market analysis of the Luzon Grid aims to establish the opportunities and threats to
new investments in generation capacities. This was achieved by analyzing the demand
and supply sectors, the supply-demand balance situation today and in the future as well
as the network infrastructure for the transmission of electricity in Luzon Grid.
1 This study was prepared by the Energy Advisors of University of the Philippines – National Engineering
Center with funding support from AES. The findings, opinions, conclusions and recommendations are of the authors and not necessarily of the sponsor and UPNEC.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 9
Part II starts with a brief review of the achievements of the industry vis-à-vis the EPIRA’s
declared policy objectives. This is followed by an analysis of its policy framework as laid
down by the EPIRA and the review of the policies of Brazil and Chile. The analysis is
approached from the perspective of policy and regulatory incentive structure. It seeks to
determine whether a robust incentive structure is provided in the EPIRA, i.e., one that
attract sufficient private investment in generation while achieving its economic
efficiency objectives. Economic efficiency refers to allocate, productive and dynamic
efficiency. The strength of the policy and regulatory incentive structure rests on the
design of the structural policy; liberalization; ownership; conduct regulation; and, the
sequencing of policy reform. In network industries that are naturally monopolistic such
as electricity distribution and transmission, the rules that make up the regulatory
incentive structure act as proxies to the disciplines imposed by a fully competitive
market.
An analysis of international markets was undertaken to enrich the study by providing a
model for the design of policy reform under reasonably comparable circumstances.
Aside from having the longest running and most comprehensive electricity reform after
WWII, Chile’s reforms which started in 1982 are widely acknowledged to be highly
successful and a model for developing countries around the world. Chile has been in the
forefront of innovation in the creation of electricity markets. Brazil on the other hand
has the largest electricity market in South America. These two countries have the
highest access rates in Latin America. While Chile’s electricity system shows that
effective competition and privatization is possible in a relatively small market, Brazil’s
illustrate that it is possible in a large developing market. Their combined experiences
and lessons learned are highly instructive for developing countries like the Philippines
that are still grappling with electricity reforms.
A brief review of the state of industry’s institutional governance is made based on the
results of the policy assessment. Corresponding recommendation to address the gaps in
this area are included in the report.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 10
To facilitate the timely completion of the study, the impact analysis for policies and
regulations that require historical data was limited to the Luzon grid. The grid accounts
for 74% of the installed generating capacity nationwide and 72% of its total demand.
The current state of generation in the grid is thus a fair indicator of the strengths and
weaknesses of the current policy framework and of the appropriateness of future policy
interventions.
Findings
The salient findings of the assessment of the policy framework and institutional markets are :
1) The objectives of the EPIRA, as listed in its ‘Declaration of Policy’ have not been
achieved;
2) Critical disincentives to generation investments are embedded in inappropriate
policy designs and gaps in the current policy framework coupled with weaknesses
and errors in their implementation ;
3) The sequencing of policy reform in Chile and Brazil prioritized generation adequacy
over market liberalization . In the interim, pro-competitive regulatory mechanisms
primarily, the public auction of long-term power contracts were put in place to
capture the efficiencies of free market competition; and,
4) Weak institutional governance in the Philippine electric power industry arising from
DOE’s inadequate engagement and ERC’s limited administrative capacity.
Recommendation for Reforms
The reform proposals are intended to remedy the weakness of the incentive structure of
the policy, regulatory and governance framework and address the gaps in the
implementation by the regulator of policies that are set-out in the EPIRA. Except for the
amendment to the horizontal policy on generation and on the guarantee authority of
NEA; these proposals will only require executive and regulatory actions to implement.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 11
The policy and regulatory reform proposals are categorized into immediate (within 6
months) and medium term (from 6 months to 2 years) depending on their urgency and
expected time requirement to implement.
Policy and Regulatory Reforms
a) Immediate Reforms
1 Competitive bidding of forward power contracts
All distribution utilities (PDUs, ECs) should contract for 100% of their energy and
capacity requirements through a competitive public bidding. The utilities (with the prior
endorsement of the ERC and DOE) shall hold yearly public auctions for contracts with a
maximum term of 15 years. Purchases from the spot market shall be limited to 5% of
the DUs’ and generators’ contractual imbalances and shall be subject to the payment of
penalties to be determined by the ERC. Standard contract templates to be drawn up by
ERC and DOE, generators and DUs. Contract quantities shall have priority over spot ones
in case of planned brownouts due to supply shortages (no supply guaranty for
uncontracted energy in case of rationing). A sample contract from the Brazil auction is
attached.
2 Deferment of Retail Competition
Retail competition must be deferred until such time that the vital requirements laid
down in ERC Resolution No. 03, Series of 2007 is achieved:
a) Adequacy of generation, transmission networks , and customer switching systems; and
b) Promulgation by the ERC of all pertinent rules and regulations governing retail
competition and open access. ERC shall determine the timetable with duties and
responsible parties in charge of executing the pending requirements to materialize
RC&OA. Certainty shall be given to the industry in order to allow proper planning.
3 Restructuring of the Ownership of Electric Cooperatives
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 12
ECs may be restructured and consolidated to a small group of equity investors to
strengthen the incentives for productive efficiency. In the interim, the energy
requirements of the ECs should be aggregated by grid and tendered in the auction as
one. Section 30 of the EPIRA shall be amended by Congress to allow NEA to act as
guarantor for the bilateral contract obligations of the ECs, instead of their WESM
purchases.
4 Limiting ERC’s adjustment to installed generating capacity
Adjustment to generating capacity must be limited to permanent derating to avoid the
possible circumvention of the grid limits from the declaration of temporary reductions
in capacity.
b) Medium Term Reforms 1 Proper Implementation of the PBR Rate-Setting Methodology
Proper implementation of the PBR rate-setting methodology for transmission and
private distribution utilities and of the RSEC-WR and proposed PBR for Electric
Cooperatives to improve the utilities’ efficiency and moderate the increases in
electricity rates.
2 Amendment of the Horizontal Separation Policy on Generation
Legislative Amendment of the horizontal separation policy on generation such that the
grid limit is based solely on control of the installed generating capacity. In this regard,
installed generating capacity shall cover IPP capacities whose control were ceded by the
NPC/PSALM to the administrators in the IPPA Agreements.
3 Interconnection of Luzon, Visayas and Mindanao
The Luzon, Visayas and Mindanao grids must be interconnected to mitigate the adverse
effect on energy security of each grid’s high reliance on a single fuel/energy resource.
4 Strengthening of the WESM
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 13
The wholesale spot market must be strengthened to incent new generation investments
by:
a) Reviewing the system operation and network reliability protocols to make them
consistent with consumer valuation;
b) Demand metering to allow consumers to react to changes in the supply and
demand balance;
c) Raising the price cap and sticking to it;
d) Creation of operating reserve, financial hedging, capacity markets and market
for transmission rights to mitigate market risks and solve the ‘missing money’
problem.
5 Vertical Separation of Generation and Distribution Sectors
The generation and distribution sectors must be vertically separated (i.e., remove cross-
ownership) to create robust competition in generation.
Institutional Governance Reforms
The weakness of the institutional governance framework has its roots on: (1) the institutional
paralysis of the DOE; (2) weak administrative capacity of the ERC; and (3) a litigious regulatory
process that does not welcome broad participation and consultations and precludes an effective
appeal mechanism to redress grievances.
1 DOE’s Assertion of its Authority under EPIRA
The DOE must step up into the plate; assert is authority and deliver on its
responsibilities under the law.
2 Strengthening of Administrative Capacity of ERC through Financial Autonomy and
Maintaining a Balance of Expertise
Strengthening the administrative capacity of ERC will require first, financial autonomy
either through an automatic appropriation of its budget or by allowing the agency to
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 14
keep and spend its collections instead of these being remitted to the National Treasury;
and second, maintaining a balance of expertise in the Commission, i.e., finance rather
than accounting (financial policy and strategy is more critical than accounting the
Commission level ); power engineers (not just any engineer); regulatory economists (or
in their absence, micro rather than macro economists); and lawyers. The present
composition of the Commission and its top executive management which is dominated
by lawyers should be restructured to achieve a more balanced composition of these
disciplines. Regulation of infrastructure industries such as the electric power industry is
more about economics rather than law and involves the consideration of the economic,
financial, and technical impact of regulatory decisions rather than on the establishment
and conformity with legal precedents that may be irrelevant to the case on hand. The
current set-up where the Commissioners are appointed by the President need not be
changed. However, the names and the curriculum vitae of candidates should be made
public, e.g., in the newspapers, in the Malacanang and ERC websites so that a public
vetting process takes place before their appointment by the President.
3 Flexibility in the Regulatory Processes
Short of abrogating the quasi-judicial character of the ERC (that will require legislative
amendment); what is required is flexibility in the regulator’s processes that will: (1)
invite broad debate of and meaningful participation by all stakeholders; (2) deepen the
scope of the debate to relevant economic, technical and social issues instead of
confining them to legal procedures and precedents; and (3) provide for an effective
appeal mechanism. On the latter, the ERC could hire more “arbitrators and “conciliators”
akin to those at the National Labor Relations and Conciliation (NLRCC) Board and the
Construction Board rather than requiring all cases to be heard by the Commission and
immediately appealed to the Courts. In addition, a single panel of experts, with a
permanent chair and varying members depending on the issue on hand could be formed
to resolve disputes between the regulator and market agents and among market agents.
The dispute settlement mechanism of WESM, GMC and DMC could be constituted as
sub-groups reporting to this Experts’ Panel when the issues arise from or are within
their jurisdictions.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 15
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 16
I SUPPLY AND DEMAND ANALYSIS OF LUZON GRID
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 17
1 THE DEMAND SECTOR
1.1 SYSTEM DEMAND OF LUZON GRID
1.1.1 HISTORICAL DEMAND OF LUZON GRID (MW
The Annual Peak Demand of the Luzon grid grew at an average annual rate of 3.44%. from
2000-2010 as shown in Table 1. While the first five years (2001-2005) and the second five years
(2006-2010) grew at almost the same pace at 3.40% and 3.47%, respectively , the last five years
showed an increasing trend at 0.36% in 2006 to 8.63% in 2010.
Table 1. Annual Peak Demand and Growth Rate of Luzon Grid, 2000-2010
YEAR Annual GWh
Consumption Growth Rate
Peak MW
Demand Growth Rate
2000 34,679 5,450 - -
2001 38,184 10.11%
3.22%
5,646 3.60%
3.40%
2002 38,387 0.53% 5,823 3.13%
2003 37,535 -2.22% 6,149 5.60%
2004 39,854 6.18% 6,323 2.83%
2005 40,627 1.94% 6,443 1.90%
2006 41,241 1.51%
3.00%
6,466 0.36%
3.47%
2007 43,620 5.77% 6,643 2.74%
2008 44,200 1.33% 6,674 0.47%
2009 44,975 1.75% 7,036 5.42%
2010 48,845 8.60% 7,643 8.63%
Source: 2000-2009 (DOE), 2010 (WESM RTX)
1.1.2 ELECTRICITY SALES AND CONSUMPTION IN LUZON (2009)
The total energy sales and consumption (including own use and system loss) in Luzon account
for 74% of the total Philippines. Visayas and Mindanao has each 13% of the total energy
consumption2.
2 DOE, 2009 Power Statistics
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 18
In Luzon, MERALCO (the single largest distribution utility) accounts for 71% of the total energy
consumption . Its market share (i.e., sales to customers) in 2009 is 61% as shown in Figure 1. The
On-Grid Electric Cooperatives accounts for 11% and another 1% in isolated lated islands which
are served by NPC-SPUG. The Private DUs sales is only 3% while the combined sales to Directly
Connected Customers and Economic Zones is 7%.
Figure 1. Luzon Grid Energy Sales (MWh) and Consumption by Sector, 2009
Figure 2 shows the regional sales of electricity in 2009 to customers of Distribution Utilities (ECs
and PDUs) and to Economic Zones and Directly Connected Customers. Fidty seven percent (57%)
of the total energy sales was delivered to the National Capital Region (NCR). It must noted that
MERALCO’s mega-franchise includes part of Region IV-A (south of NCR) and part of Region III
(north of NCR). Hence, the diffirence between 61% of MERALCO share in the energy sales and
the 57% of energy delivered to NCR accounts for the consumption of the customers in Region III
and Region IV-A.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 19
Figure 2. Luzon Grid Energy Sales by Region, 2009
1.1.3 DEMAND DRIVERS OF THE LUZON GRID
The grid’s peak demand from 2000 to 2010 is plotted with the gross regional domestic product
(GRDP), population and average price of electricity to end-users in Figure 3.3 Population and
GRDP are strongly correlated with demand at 0.9686 and 0.9582 correlation coefficients,
respectively. Demand has low correlation with end-users price (0.7687 correlation coefficient )
which indicates the inelasticity of demand at the regressed price levels. The regression analysis
of demand with both population and GRDP as drivers did not pass the significance of variable
tests (t-stat and p-value) indicating auto-correlation. Thus, the peak demand of Luzon can be
forecasted either by population or GRDP but not by both population and GRDP in the same
regression equation. The sensitivity of the annual peak demand of Luzon Grid to the maximum
daily temperature of Manila was also analyzed for the months of April to June from 2000 to
2010. The analysis showed that the peak demand during summer season has little correlation
with maximum temperature for the same season. The variations of Manila’s temperature
3 The Gross Regional Domestic Product and population of Luzon were obtained by taking the sum total of
the GRDP (population) of NCR, CAR, Region I, Region II, Region III, Region IV-A, and Region V. The GRDP and population of Region 4B (MIMAROPA) were excluded because the provinces and islands in this sub-region are not connected to the Luzon Grid.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 20
Box No. 1- Forecasting Model for Luzon Grid Peak Demand
Forecast Model: L = a + b(GRDP) MAPE 2.37%
a 2663.389855 R^2 0.907542262 t-stat 8.861490813
b 4.83671E-06 adj. R^2 0.895985045 p-value 2.07664E-05
throughout the year is not significant in so far as daily peaks are concerned. The temperature
factor is only significant with respect to the hourly load variations.
Figure 3. Luzon Grid Peak Demand, GRDP, Population and Electricity Price (2000-2010)
1.1.4 LUZON GRID DEMAND FORECAST (2011-2030)
Several regression models were formulated to establish the best forecasting model for the
Grid’s annual peak demand. The model selected for this study is shown in Box No. 1 which is a
simple regression equation with GRDP as variable. The model exibited the highest value of
Adjusted R squared (adj. R^2). It is likewise suitable to forecasting a range of possible economic
growth scenarios. This model passed the t-stat criterion ( less than -2 or greater than 2) and p-
value (less than 0.1) for the GRDP regressor. The Mean Absolute Percentage Error (MAPE) of the
model is 2.37% which is lower than the maximum 3% criterion.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 21
The annual growth rate of the GRDP of Luzon for the period 2000-2010 is 4.88%. The Philippine
GDP growth rate in 2009 was about 1% and in 2010, a hefty 7.3%. Both are aberrations. The
economy was hit hard by the financial crisis in its export markets in 2009 while heavy election
spending in 2010 boosted the economy. With the gradual recovery of the country’s main trading
partners and the added confidence in the country brought about by a change in administration,
the anemic 1% growth is not expected to recur. Thus, the 2010 GRDP was set aside in the
formulation of the forecasting model.
The continued vulnerability of the economy to external shocks and internal structural problems
indicate a prudent approach in estimating future demand. As such, demand is forecasted
under the low, moderate and high economic growth At 3%, 5%, and 7%, respectively. The
demand forecast for 2011 to 2030 in each of these scenarios is shown in Table 2.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 22
Table 2. Forecasted Annual Peak Demand (in MW) of Luzon Grid, 2011-2030
YEAR Low Economic Growth Moderate Economic Growth High Economic Growth
MW MWh* MW MWh* MW MWh*
2011 7,487 46,742,269 7,581 47,327,033 7,675 47,911,797
2012 7,632 47,645,730 7,827 48,862,040 8,026 50,101,740
2013 7,781 48,576,295 8,085 50,473,797 8,401 52,444,979
2014 7,935 49,534,776 8,356 52,166,142 8,803 54,952,245
2015 8,093 50,522,013 8,641 53,943,104 9,232 57,635,019
2016 8,256 51,538,866 8,940 55,808,914 9,692 60,505,587
2017 8,424 52,586,225 9,254 57,768,015 10,184 63,577,095
2018 8,596 53,665,005 9,583 59,825,070 10,711 66,863,609
2019 8,774 54,776,148 9,929 61,984,979 11,274 70,380,179
2020 8,958 55,920,626 10,292 64,252,883 11,877 74,142,908
2021 9,147 57,099,437 10,674 66,634,182 12,522 78,169,029
2022 9,341 58,313,613 11,074 69,134,546 13,212 82,476,978
2023 9,541 59,564,215 11,495 71,759,929 13,950 87,086,484
2024 9,748 60,852,334 11,936 74,516,580 14,740 92,018,655
2025 9,960 62,179,097 12,400 77,411,064 15,585 97,296,077
2026 10,179 63,545,663 12,887 80,450,272 16,490 102,942,920
2027 10,405 64,953,226 13,398 83,641,441 17,458 108,985,041
2028 10,637 66,403,016 13,935 86,992,168 18,493 115,450,111
2029 10,876 67,896,300 14,498 90,510,431 19,602 122,367,736
2030 11,122 69,434,382 15,090 94,204,608 20,787 129,769,595
* Estimate based on 2009 Load Factor of Luzon Grid (71.26%)
1.2 LOAD CHARACTERISTICS OF THE LUZON GRID
The load characteristic of the grid is also a factor in establishing the most economic mix of
capacity type and energy production of power generation plants. This study used the 2009
Hourly demand of the Luzon Grid obtained from WESM to analyze its load characteristics . The
analysis revealed a 71.26% load factor in 2009.
The typical one-day (hourly) demand is illustrated in Figure 4. The Grid has three peaks
occurring on a typical day: at 11:00AM (morning peak), 2:00PM (afternoon peak), and 7:00PM
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 23
(evening peak). The off-peak demand on a typical day occurs at 4:00AM. From a binomial time-
of-use (TOU) demand point of view, the Grid’s off-peak period is 10:00PM-9:00AM while the
peak period is between 10:00AM and 9:00PM.
Figure 4. Typical One-Day (Hourly) Demand of Luzon Grid
Figure 5 shows the daily peak loads (MW) of the Grid in 2009 . The high peaks occur on
weekdays starting in April and is sustained until September.
In terms of economic dispatch-merit load category, 71.69% of Luzon Grid’s demand is base,
19.08% Intermediate, and 9.23% peaking. The corresponding energy for the load categories are
92.41%, 7.40%, and 0.19%, respectively. These values were obtained from
Figure 6 based on the load duration curve (i.e., the 8760 hourly demand in 2009 arranged in descending order) and plant-type screening curve. The screening curve
was established by plotting the levelized annual generation cost per MW of base load plant (represented by coal thermal power plant), intermediate plant (natural gas combined cycle gas turbine plant) and peaking (diesel) power plant using the plant
cost parameters shown in
Table 3.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 24
Figure 5. Daily Peak Demand (365 days) of Luzon Grid, 2009
Figure 6. Load Duration and Plant Type Screening Curve
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
70,000,000
80,000,000
90,000,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
PH
P/M
W/Y
R
CAPACITY FACTOR
SCREENING CURVE(Levelized Busbar Cost, PHP/MW/YR)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 25
Table 3. Plant Cost Parameters for the Screening Curve
The demand in MW, energy in MWh and load factor for the different load categories for the
Luzon Grid in 2010 is shown in
Table 4. The base load is 5,480 MW ; intermediate at 1,458 and peaking at 705 MW. The
combined energy of the intermediate and peaking loads represent only 7.5% of the total energy.
The intermediate load of Luzon Grid can be categorized as peaking load. The slope of the
levelized generation cost of CCGT which was used to represent the intermediate plant in the
screening curve is high due to its fuel price (US$ per MMBTU) which is about twice the fuel price
of coal for base load plant.4 This implies that the dispatch of power plants in the Grid is not
achieving the optimal mix because the CCGT plants in Batangas contracted by NPC and
MERALCO are base loaded (~80% minimum energy off-take) that translate to about 20% instead
of only 7.5% of the total mix.5
Table 4. Load Category of Luzon Grid, 2010
LOAD
CATEGORY DEMAND
(MW) ENERGY (MWH)
Load Factor (%)
Base 5479.633 44,091,582 91.85%
Intermediate 1458.022 3,531,378 27.65%
Peaking 705.346 90,443 1.46%
TOTAL 7643.000 47,713,402 71.26%
4 The fuel price for CCGT was taken from the estimate of the 2010 price of Natural Gas from Malampaya
which is indexed with international fuel oil. 5 Based on the Power Purchase Agreements of NPC with KEPCO and MERALCO with First Gas that was
approved by ERB/ERC
PARAMETER COAL CCGT DIESEL
Capacity (MW) 300 250 100
Plant Cost (US$/KW) $1,800.00 $900.00 $650.00
Fixed O&M (US$/KW-YR) $63.00 $31.50 $22.75
Var O&M (US$/KWH) $0.00500 $0.00300 $0.01000
Fuel Cost (US$/MMBTU) $5.35 $10.81 $13.28
Heat Rate (BTU/KWH) 9,800 7,800 8,500
Fuel Escalation Rate (% p.a.) 1.00% 2.06% 6.00%
Levelizing Period (YRS) 30 30 30
WACC (% p.a.)
Discount Rate (% p.a.)
FOREX (PHP/US$)
15%
12.00%
P45.00
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 26
2 THE SUPPLY SECTOR
2.1 POWER PLANTS IN LUZON GRID
2.1.1 INSTALLED AND DEPENDABLE CAPACITY OF POWER PLANTS
The installed and dependable power generation capacity (in MW) of Power Plants and
Generating Units in the Luzon Grid are summarized according to plant type (fuel and dispatch-
merit) in Table 5. The list includes the currently mothballed 70 MW Hopewell gas turbine plant
with 30 MW dependable capacity and the 242 MW East Asia/Duracom diesel power plant with
dependable capacity of 200 MW. Not included in the list is the 600 MW Sucat oil-fired thermal
power plant which was retired for economic and environmental reasons. The Sucat plant,
however, could be revived in the short-term (i.e., 2-3 years).
Table 5. Generation Capacity in Luzon Grid According to Plant-Type and Regional Location (in MW)
Notes: (1)Dependable Capacity of Wind Power is considered zero
(2) Small Embedded Power Plants not included
Self-Generation facilities are owned and operated by industrial companies such as the 18 MW
gas turbine of Pilipinas Shell Petroleum Corp. in Tabangao, Batangas and the 24 MW extraction
steam turbine of Petron Corp. in Limay, Bataan. Several cement factories have diesel power
plants such as the 20.4 MW of Solid Cement in Antipolo . The ERC granted Certificates of
Compliance to thousands of self-generation facilities in a list that ran to 140 pages. However,
the list contains stanby generating units of commercial and industrial companies which are
Installed MWDependable
MWInstalled MW
Dependable
MWInstalled MW
Dependable
MWInstalled MW
Dependable
MW
Hydro 1505 1225 764 754 2269 1979
Coal 2004 1958 1875 1492 3879 3450
Geothermal 939 431 939 431
Wind+Bio 8.90 0.93 33 0 42 1
Intermediate NG CCGT 2831 2700 2831 2700
Oil Thermal/CCGT 620 600 620 600
Diesel 242 200 491 341 0 0 734 541
GT 70 30 70 30
Total 321 230.93 4654 4124 6408 5376 11383 9731
South Total Luzon
Plant Type
Base
Peaking
Region NCR North
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 27
technically and operationally speaking not self-generation as they are intended for reliability
back-up during outages in the grid.
Table 6 is a matrix of power generation capacity in the Luzon grid by type, location and share of
dependable capacity. Fifty six percent (56%) of dependable capacity are baseload: hydro,
geothermal and coal thermal plants. Natural gas combine cycle plants that are traditionally
considered as intermediate (mid-merit) plants account for 26% of the dependable capacity. The
share of the peaking plants in the capacity mix is 18%. It should be noted that this includes the
Limay oil CCGT plants and Malaya oil fired thermal plants. These plants were inlcuded in the list
of peaking plants due to the price of their fuel although they were originally designed as
intermediate and base load plants.
Table 6. Percentage Dependable Capacity by Plant-Type and Regional Location
Type \ Region NCR North South
Total Luzon
Base 0.01% 32.71% 27.50% 60.22%
Intermediate 0.00% 0.00% 27.75% 27.75%
Peaking 2.36% 9.67% 0.00% 12.03%
Total 2.37% 42.38% 55.25% 100.00%
In terms of location, the capacity in the National Capital Region (NCR) is almost nil (2%) and is
essentially for peaking only. Forty percent (40%) and fifty eight percent (58%) are located in the
North and South of Luzon, respectively.
2.1.2 PROPOSED POWER GENERATION PROJECTS
Commited Projects
The following are committed power generation projects in Luzon:
a) Rehabilitation of 40.8 MW Bac-Man I-2 Geothermal Power Plant in 2012 by
Lopez Group
b) Rehabilitation of 33.55 MW Bac-Man II-1 Geothermal Power Plant in 2013 by
Lopez Group
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 28
c) Commissioning of of new 600 MW Mariveles Coal Thermal Power Plant in
2013 by GNPower
Proposed Projects Published by DOE
The DOE published , through the PDPs, the proposals of the private sector to put up new
capacity in Luzon. However, these are not really committed projects although in many instances
the proponents informed the DOE that they are “committed” (hence the publication). The
proposed projects that were scheduled for commissioning in 2010 to 2017 are summarized in
Table 7 according to plant type.
Table 7. Capacity of Proposed Power Plants for 2010-2017 Published by DOE
Plant Type Generating Capacity
(MW)
Natural Gas 550
Coal 1,775
Geothermal 150
Large Hydro 530
Wind 415
Proposed Projects Published by NGCP
Some serious proposals but no commitment yet were also submitted to NGCP for Grid Impact
Studies. The list of proposed projects are summarized in Table 8 according to commissioning
year. These proposals were used by NGCP in its Transmission Development Plan (TDP) that was
submittted to ERC for approval and inclusion in their PBR rate setting.
Table 8. Proposed Power Plants for 2010-2017
Commissioning Year
No. of Projects
Generating Capacity (MW)
2011 1 105
2012 10 1001
2013 11 1557
2014 6 173
2015 3 500
2016 - -
2017 2 675
2018 1 300
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 29
Source: NGCP
2.1.3 OWNERSHIP OF POWER PLANTS AND CONTROL OF IPPA CONTRACTED
CAPACITY The ownership and control distribution of the combined private installed generating and IPPA
contracted capacities in Luzon Grid are shown inTable 9. There are three dominant players in
Luzon Grid. These are San Miguel Group, the Lopez group and Aboitiz group that owns or
controls 28.13%, 16.33.53% and 17.36%, respectively of the total installed/contracted capacity
of power plants in Luzon. The market is highly concentrated as these three groups control more
than 70% of the generating capacity in Luzon. The share of others including AES, DMCI and
Quezon Power Phils. are less than 7% each.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 30
Table 9. Private Ownership of Power Plants and Control of IPPA Contracted Capacities
Owner Plant Name Installed
Capacity (MW) %Share of Total
Capacity
A. Lopez Group
1 From Privatized NPC/PNOC Pantabangan-Masiway 112
Bac-Man 150
Total from Privatized
262
2 IPP Plants Sta Rita 1,047
San Lorenzo 549.1
Total IPP Plants
1,596.10
3 IPPA Contracted Capacity
0
Total Lopez Group
1,858.10 16.33%
B. Aboitiz Group
1 From Privatized NPC/PNOC Magat HEPP 360
Tiwi GPP 330
Mak-Ban GPP 410
Ambuklao HEPP 75
Binga HEPP 100
Total from Privatized
1,275
2 IPP Plants
0
3 IPPA Contracted Capacity Pagbilao CFPP 700
Total Aboitiz Group
1,975 17.36%
C. SMC Group
1 From Privatized NPC/PNOC Limay Combined Cycle 655.5
2 IPP Plants
0
3 IPPA Contracted Capacity Sual CFPP 1,000
Ilijan CCGT 1,200
San Roque MHPP 345
Total IPPA
2,545
Total SMC Group
3,201 28.13%
D. AES Masinloc Coal I & II 635 5.58%
E. DMCI Calaca Power Corp 600 5.27%
F. Quezon Power Phil Quezon Power 511 4.49%
G. Other Owners
Angeles Electric Corp Angeles Power Inc 30
Angeles Electric Corp 9
Tarlac Power Corp 18.9
First Cabanatuan Ventures Corp 25.6
Trans-Asia Power Generation Corp 52
Northwind Power Corporation 33
INEC INEC-Agua Grande Mini-HEPP 4.5
SORECO Bicol Hydropower Corp 0.96
Atty Ramon Constancio Cawayan HEPP 448
Barit HEPP 1.8
ISELCO Magat A & B 2.5
Montalban Methane Power Corp 8.19
Phil Power Development Corp MHHP 1.11
Total Other Owners
635.56 5.59%
H. Other IPPAs
Amlan Power Holdings Bakun-Benguet HPP 100.75
Total Other IPPAs
100.75 0.89%
TOTAL PRIVATE
9,516.41 83.63%
TOTAL NPC
1,863.00 16.37%
TOTAL LUZON
11,379.41 100.00%
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 31
2.2 WHOLESALE ELECTRICITY SPOT MARKET
The following excerpts from the assessment report of market results for 2010 show how the
“Big three” of the power industry influence the prices in WESM6:
“Sual CFTPP and Pagbilao CFTPP came out as the two plants with the most number of trading intervals wherein both were setting prices and providing the pivotal supply. There was a significant jump of this measure between 2009 and the first half of 2010. Sual CFTPP was simultaneously setting prices and providing pivotal supply for 7.7% of the time in 2009, and 12.5% of the time in 2010. Likewise, Pagbilao CFTPP was at the same position for 5.5% of the time in 2009, and 13.9% of the time in 2010. This goes to show how critical the market events were during the first half of 2010, especially when prices went up to unprecedented levels.” “The obvious implication is that the potential for market power exercise is higher for plants that are both price setter and pivotal supplier in a trading interval, especially if their exposure in the spot market is also significantly high. This is true if the concerned plants are aware of their advantageous situation and if they have the strategic resolve to exercise those market advantages. The natural gas plants KEPCO Ilijan and Sta. Rita FGPP were also observed to occupy the same advantaged situation although on a lesser extent since a significant portion of their output are contracted.”
“Sual CFTPP is traded by San Miguel Energy Corp. (SMEC) as the Independent Power Producer Administrator (IPPA). The trading participant is fully contracted even if it parlays 48% of its bilateral obligations to the spot market. Pagbilao CFTPP is traded by Therma Luzon Inc. (TLI) with a generating capacity almost equally allocated between the spot market and bilateral contracts market. Even KEPCO Ilijan, traded by PSALM Team 1, has a spot market exposure of 38%. Sta. Rita, owned by First Gas Power Corporation is similarly situated.”
The detailed assessment of WESM is inlcuded in Part 2 (Aanlysis of Policy Framework) of this
Report.
6 From PEMC Report
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 32
3 SUPPLY-DEMAND BALANCE
3.1 RELIABILITY PERFORMANCE OF THE GRID
3.1.1 RELIABILITY INDEX AND CRITERIA
The reliability performance of the generation system, i.,e., the ability of the generation capacity
to meet the demand of the power grid was assessed using probability methods. The reliability
index used to measure the performance of Luzon Grid is the loss-of-load expecation (LOLE)7
because it captures the probabilistic nature of forced outages and its consistency to measure
risks that are associated with variations in capacity, type and number of generating units, the
size of the grid, maintenance of power plants and variations of hydro power generation. Figure
Figure 7 illustrates the variations in hydro power generation in 2009 that was used in the LOLE
calculation. The LOLE is calculated by convolving (i.e., mathematically combining) the
cumulative probability of capacity outages with the demand. In this study, the LOLE of Luzon
Grid was measured in expected number of days in a year (days/year) that there will be a loss of
load. A loss of load will happen if the available generating capacity will not be sufficient to meet
the demand because of the probability of simulataneous outages of generating units of the
power plants.
Figure Figure 7. Variations in Hydro Power generation
7 The power industry has referred to the LOLE as LOLP (loss-of-load probability). Technically
speaking, LOLE is not a probability value but an expected value of probabilistic variable.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 33
The load of the Luzon Grid was represented by its daily peak. Thus, the loss of load in days/year
does not connote a total system blackout for that number of days in a year. It simply means that
the peak load of some days has a chance of exceeding the remaining capacity after the
simultaneous outages of several units. The criteria used in the assessment of reliability
performance of Luzon Grid is one day per year (1 day/year) loss-of-load expectation.8 The use of
deterministic approach is considered by power system relaibility experts as inconsistent
measure.9
Figure 8 shows the relationship of LOLE and the Reserve of the Grid. It can be deduced that with
the current power plant composition (i.e., type, size and number of generating units) and the
load variation curve (i.e., daily peak loads) of Luzon Grid, the necesary reserve that must be
maintained is about 28.7% to meet the maximum one day per year loss-of-load-expectation.
This is higher than the 20.6% operating reserve (spinning and standby) currently used
(apparently based on PDP published) by DOE.
Figure 8. Loss of Load Expectation vs. Capacity Reserve of Luzon Grid, 2000-2010
8 The 1 day/yr LOLE (or LOLP) was used by NPC as reliability criteria in its power development
planning prior to EPIRA. Based on the PEP published by DOE, it appears that the criteria used now in planning are percentage reserve. 9 Billinton, et.al, “Evaluation of Power System Reliability”, IEEE Press,
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 34
3.1.2 HISTORICAL RELIABILITY PERFORMANCE OF LUZON GRID
The reliability performance i.e., LOLE, of the Luzon Grid from 2000 to 2010 is shown in Figure 9.
The LOLE in 2000 and 2001 were more than 10 days per year but the commissioning of new
power plants in 2002 reduced the LOLE to an acceptable level of not more than 1 day per year. It
is noted however that since no power generation capacity were added after 2006, the growth in
demand led to 4 days/yr LOLE in 2010. This means that in year 2010 the reliability criteria was
violated that translated to rotating interruption since there was not enough operating reserve
capacity to secure the Luzon Grid.
Figure 9. Reliability Performance of Luzon Grid, 2000-2010
3.1.3 RELIABILITY PERFORMANCE OUTLOOK
The outlook for year 2011 to 2014 as shown in
Table 10 is not encouraging inspite of the addition in capacity of the 600 MW Mariveles coal
thermal power plant in 2013. The simulation assumed that the Malaya Oil Thermal Plant is
retired from service. This imply that the Malaya thermal plant should not be retired until new
capacities are added in the system.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 35
Table 10. Reliability Performance of Luzon Grid, 2000-2010
Year Capacity (MW Demand (MW) Reserve (%) LOLE (Days/Yr)
2011 9583 7581 26.41% 5.07
2012 9624 7827 22.96% 12.08
2013 9657 8085 19.44% 5.27
2014 9657 8356 15.57% 82.27
3.2 REGIONAL PERSPECTIVE OF SUPPLY-DEMAND BALANCE
From the perspective of regional location of loads and power generation capacity, the matrix of
capacity type and dependable capacity margin shown in Table 11 indicates the mismatch of
capacities and demand. This implies that the transmission network must be robust and its
security concerns must be considered even in the design of the market (i.e., a nodal market
design may not be appropriate).
Table 11. Regional Perspective of Power Supply-Demand Balance of Luzon Grid, 2011
Type Dep. Cap
(MW) Demand
(MW) Margin (%)
NCR
Baseload 1 4,914 -99.98%
Intermediate 0 362 -100.00%
Peaking 30 495 -93.94%
Total 31 5,771 -99.46%
North Luzon
Baseload 2,611 1,114 134.46%
Intermediate 600 82 631.12%
Peaking 341 112 203.62%
Total 3,552 1,308 171.56%
South Luzon
Baseload 2,301 427 438.42%
Intermediate 2,700 31 8472.78%
Peaking 0 43 -100.00%
Total 5,001 502 896.30%
Total Luzon
Baseload 4,913 6,455 -23.88%
Intermediate 3,300 476 593.77%
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 36
Peaking 371 651 -43.01%
Total 8,584 7,581 13.23%
3.3 GENERATION EXPANSION ANALYSIS
3.3.1 GENERATION EXPANSION METHODOLOGY, CRITERIA, AND SCENARIOS
The generation expansion analysis was conducted to establish the additional capacity, timing
and type of power plants needed in the Luzon Grid.
The power system models and methodology for the expansion analysis is summarized as
follows:
a) Load Modeling. The 2009 hourly load of Luzon Grid was used as the load pattern for all years of the planning horizon. The load model was obtained by normalizing the 8760 hourly demand by the peak demand in 2009. The load variations is modified by the hydro power generation;
b) Generating Capacity Outage Probability Modeling. The cumulative value of probability of capacity outage is calculated using recursive algorithm;
c) Probabilitic Reliability Evaluation. The LOLE is calculated for a a given annual peak and set of in-service generating units. If the LOLE exceeds 1 day/year in a given year, a generation capacity will be required;
d) Optimal Capacity Mix Evaluation. The generating capacity type (i.e., base, intermediate or peaking) needed is evaluated using the power plant screening curve which consider the investment, fixed and variable O&M, and production (fuel) costs;
e) Optimal Production Simulation. Based on the available power plants capacity (less capacity on maintenance) the load dispatch for each hour of the 8760 hours in a year are simulated based on merit order
f) Generation Cost Calculation. The annuity of the power plant investment, annual fixed and variable O&M, and annual production costs are added and divided by the annual generation of each power plant.
The plant cost chractersitics of the screening curve (Figure 6) in Table 3 was used in establishing
the optimal expansion pattern of Luzon Grid.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 37
Two (2) scenarios were prepared for the generation expansion analysis relative to the
retirements of existing power plants, particularly of the Malaya and Limay CCGT power plants.
These scenarios were considered because the retirement of the two plants have long been
planned. The study establishes the required expansion pattern with these plants in-service or
out-of-service (i.e., retired). The expansion analysis also pursued three (3) demand growth
scenarios. These are:
a) Moderate economic growth scenario (the GRDP of Luzon will grow 5% annually);
b) Low economic growth scenario (GDRP growth rate of Luzon is 3%); and
c) High economic growth scenario (7% growth rate).
3.3.2 EXPANSION PATTERN OF LUZON GRID WITHOUT MALAYA AND LIMAY POWER
PLANTS
The optimal expansion pattern of Luzon grid with the moderate 5% economic growth driven
demand if Malaya oil thermal and Limay CCGT power plants will be retired is shown in Table 12.
The security of the Grid will be compromised and to meet the reliability criteria of 1 day/year
LOLE, the Grid will require 800 MW of peaking in 2012 and another 900 MW of peaking plants in
2013. The peaking plant requirements is a consequence of the lead time constraints. That is, no
baseload power plant can possibly be commissioned before 2015 if the decision to build will be
made in 2011. The reliability of Luzon Grid generating capacity with and without the expansion
for this scenario is illustrated in Figure 10. The Luzon Grid will require 300 MW of baseload
generating capacities for the years 2015, 2016 and 2017. No intermediate generating capacity
will be needed for the entire planning scenario. This is due to the high price of natural gas in the
country due to its indexation to oil. The economics of power supply implies that the existing
CCGTs in Batangas are more than enough for the next 20 years (assuming that the investment
expansion decision of the generation sector will follow the least cost or optimal mix based on
investment, fixed and variable O&M, and inflating fuel prices).
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 38
Table 12. Generation Capacity Expansion Without Malaya and Limay Power Plants (Forecast Demand under Moderate Economic Growth Scenario)
Figure 10. Reliability Performance of Luzon Grid With and Without Expansion
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 200 800
2014 0 0 900 900
2015 300 0 0 300
2016 300 0 0 300
2017 600 0 0 600
2018 300 0 0 300
2019 300 0 0 300
2020 600 0 0 600
2021 300 0 0 300
2022 600 0 0 600
2023 300 0 0 300
2024 600 0 0 600
2025 300 0 400 700
2026 300 0 200 500
2027 300 0 200 500
2028 600 0 0 600
2029 300 0 300 600
2030 300 0 300 600
TOTAL 6,900 0 2,500 9,400
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 39
Table 13 shows the expansion requirements in the case of a low economic growth scenario (3%
average annual GRDP growth rate) without the Malaya and Limay Power Plants. The peaking
plant requirements in 2012 and 2013 will be 600MW and 700 MW, respectively. This is a
reduction by 200 MW for each year due to the lower demand in this scenario. In addition to
lower capacity requirements to meet the reliability in the immediate scenario, the required
basleoad plants will be 300 MW in 2015 . The next 300 MW will be needed in 2017 instead of
2016 WM.
Table 13. Generation Capacity Expansion Without Malaya and Limay Power Plants
(Forecast Demand under Low Economic Growth Scenario)
On the other hand, if the economic growth of 7% in 2010 is sustained in the future, the Luzon
Grid will require 2,100 MW of peaking plants to ensure the security of the Grid. The base load
capacity addition needed in the Grid, as shown in Table 14, will be 600 MW in 2015 and another
600 MW in 2016.
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 0 600
2014 0 0 700 700
2015 300 0 0 300
2016 0 0 0 0
2017 300 0 0 300
2018 300 0 0 300
2019 0 0 0 0
2020 300 0 0 300
2021 300 0 0 300
2022 300 0 0 300
2023 300 0 0 300
2024 300 0 0 300
2025 300 0 0 300
2026 300 0 0 300
2027 300 0 0 300
2028 300 0 0 300
2029 300 0 0 300
2030 300 0 0 300
TOTAL 4,800 0 700 5,500
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 40
Table 14. Generation Capacity Expansion Without Malaya and Limay Power Plants (Forecast Demand under High Economic Growth Scenario)
3.3.3 EXPANSION PATTERN OF LUZON GRID WITH MALAYA AND LIMAY POWER PLANTS
IN-SERVICE
The previous section indicated the security implications of retiring Malaya and Limay
Plants in the immediate scenario. The optimal expansion patterns of Luzon Grid to meet
day/year LOLE reliability criteria are shown Table 15 to
Table 17.
With moderate demand growth scenario, no additional plants will be required until 2012
provided that rehabilitation of BacMan II-1 unit is completed in 2012 and the maintenance of
power plants are optimally scheduled considering reliability requirements. The grid security
scenario in 2011 and 2012 will be different from 2010 (El Nino year) if the economic growth will
be only a moderate 5%. There is enough intermediate and peaking plants , assuming that the
natural gas CCGTs and diesel plants will be dispatched based on the economic supply mix. The
Luzon Grid will require a total of 7,200 MW of base load plants from 2015 to 2030 if the nat gas
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 500 1,100
2014 0 0 1,000 1,000
2015 600 0 0 600
2016 600 0 0 600
2017 300 0 0 300
2018 600 0 0 600
2019 600 0 0 600
2020 900 0 0 900
2021 600 0 0 600
2022 900 0 0 900
2023 600 0 0 600
2024 900 0 0 900
2025 1,200 0 0 1,200
2026 900 0 0 900
2027 1,200 0 0 1,200
2028 1,200 0 0 1,200
2029 1,200 0 0 1,200
2030 1,200 0 0 1,200
TOTAL 14,100 0 1,500 15,600
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 41
price in the Philippines will continue to be indexed to international Brent oil. In 2015 and 2016,
the Grid will need additional 300 MW each.
Table 15. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast Demand under Moderate Economic Growth Scenario)
Table 16. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast
Demand under Low Economic Growth Scenario)
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 0 600
2014 0 0 0 0
2015 300 0 0 300
2016 300 0 0 300
2017 300 0 0 300
2018 300 0 0 300
2019 300 0 0 300
2020 600 0 0 600
2021 600 0 0 600
2022 300 0 0 300
2023 600 0 0 600
2024 300 0 0 300
2025 900 0 0 900
2026 300 0 100 400
2027 300 0 300 600
2028 600 0 0 600
2029 300 250 0 550
2030 300 0 300 600
TOTAL 7,200 250 700 8,150
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 42
Table 17. Generation Capacity Expansion With Malaya and Limay Power Plants (Forecast
Demand under High Economic Growth Scenario)
The low economic growth scenario shown in Table 15 indicates that even the baseload power
plants must be postponed to 2018 (i.e., if the Malaya and Limay Thermal Plants will not be
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 0 600
2014 0 0 0 0
2015 0 0 0 0
2016 0 0 0 0
2017 0 0 0 0
2018 300 0 0 300
2019 0 0 0 0
2020 300 0 0 300
2021 300 0 0 300
2022 300 0 0 300
2023 300 0 0 300
2024 300 0 0 300
2025 300 0 0 300
2026 300 0 0 300
2027 300 0 0 300
2028 300 0 0 300
2029 300 0 0 300
2030 300 0 0 300
TOTAL 4,200 0 0 4,200
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 0 0
2013 600 0 0 600
2014 0 0 300 300
2015 600 0 0 600
2016 300 0 0 300
2017 600 0 0 600
2018 600 0 0 600
2019 600 0 0 600
2020 900 0 0 900
2021 600 0 0 600
2022 900 0 0 900
2023 600 0 0 600
2024 600 250 0 850
2025 900 250 0 1,150
2026 600 0 300 900
2027 600 250 200 1,050
2028 900 250 0 1,150
2029 600 250 300 1,150
2030 900 250 100 1,250
TOTAL 11,400 1,500 1,200 14,100
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 43
retired). This is the only scenario that shows the condition that should trigger the retirement of
Malaya and Limay plants. In the high economic growth scenario, the Luzon Grid will need 300
MW of peaking plants in 2014 and a minimum of 600 MW baseload plant in 2015.
3.3.4 HINDSIGHT GENERATION EXPANSION SCENARIO FOR NATURAL GAS PRICE
The previous sections has indicated that there will be no adddition of intermediate power plants
(represented by Nat Gas CCGTs). The expansion analysis of this section assumes that the Luzon
Grid is a greenfield in 2011. The 2010 Luzon Grid was assumed to have an optimal mix of base,
intermediate and peaking plants that meets the reliability criteria. The existing renewable
energy-based plants (i.e., hydro and geothermal) are also assumed to be in-service. Table 18
shows how the optimal expansion pattern of base, intermediate and peaking plants will take
place. A series of 600 MW expansion of baseload plants will be followed by a 250 MW of
intermediate. The residual requirements will be provided by peaking plants in 100-300MW
capacity addditions.
Table 18. Generation Capcity Expansion for Hindsight Scenario
YEAR BASE INTERMEDIATE PEAKING TOTAL
2011 0 0 0 0
2012 0 0 100 100
2013 300 0 0 300
2014 300 0 0 300
2015 0 250 0 250
2016 300 0 0 300
2017 300 0 0 300
2018 300 250 0 550
2019 0 0 200 200
2020 300 0 100 400
2021 300 250 0 550
2022 300 0 0 300
2023 300 0 100 400
2024 300 250 0 550
2025 300 0 100 400
2026 300 0 200 500
2027 600 0 0 600
2028 300 250 0 550
2029 300 250 0 550
2030 600 0 0 600
TOTAL 5,400 1,500 800 7,700
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 44
II ANALYSIS OF THE POLICY AND REGULATORY
FRAMEWORK OF THE PHILIPPINE ELECTRIC POWER
INDUSTRY
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 45
4 THE POLICY FRAMEWORK OF THE PHILIPPINE ELECTRIC POWER
INDUSTRY
The policy and regulatory framework of the Philippine electric power industry underwent major
changes over the past twenty-five years. It gained momentum in 2001 when the Government
pushed for extensive reforms through the passage of Republic Act 9136 ‘Electric Power
industry Reform Act’ (EPIRA) . The primary motivations for the reforms were the fiscal deficit
trap created by the contingent liabilities from the IPP take-or-pay contracts that were signed
following the power crisis in the early 1990s and the perceived inefficiencies of the industry.
EPIRA restructured the industry and introduced far-reaching policy and institutional reforms.
Restructuring broke up the National Power Corporation (NPC) into its constituent generation
and transmission components; privatized these assets; established a wholesale power market
and introduced retail competition through a policy of open access to the distribution networks.
The key elements of the policy and regulatory framework created by the EPIRA are
summarized in Table 19.
Institutional reform primarily involved the abolition of the Energy Regulatory Board (ERB) and
the creation, in its place, of the Energy Regulatory Commission (ERC). The ERC, like the ERB is an
independent and quasi-judicial body with broad powers over the industry that revolves around
its exclusive authority to set electricity rates . Its mandate as described in Sec 43 of the EPIRA
are to : (1) promote competition; (2) encourage market development; (3) ensure customer
choice; and (4) penalize abuse of market power.
The responsibility of ensuring the proper implementation of the EPIRA was assigned to the
Department of Energy (DOE). In addition, Section 37 of the EPIRA mandates the DOE to:
a) Ensure the reliability, quality and security of electric power supply;
b) Facilitate/encourage reforms in the structure and operations of distribution utilities;
c) Develop policies and, where appropriate, promote a system of incentives for adequate and reliable electric supply including reserve requirements;
d) Establish the WESM;
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 46
e) Develop policies and programs for energy efficiency;
f) Formulate and implement programs for the development and commercialization of non-conventional energy systems;
g) Encourage private sector investment in the electricity sector; and
h) Promote the development of indigenous and renewable energy sources.10
The DOE Secretary is also directly responsible for total electrification as Chair of the National
Electrification Administration.
Table 19. EPIRA Policy and Regulatory Framework
ISSUE POLICY FRAMEWORK
OWNERSHIP
Privatization of NPC Assets
NPC’s generating , transmission assets and the management and control of the energy output of the IPP contracts are to be privatized according to the guidelines in Sections 47 and 21. NPC prohibited from incurring new obligations to purchase power through bilateral contracts with generation companies or other suppliers.
Transmission Section 45 prohibits generation companies, distribution utilities (DUs) and their subsidiaries or affiliates or stockholder or official and other entities engaged in the generation and supply of electricity within the 4th degree of consanguinity or affinity as specified by the ERC from having direct or indirect interest in TRANSCO or its concessionaire and VICE VERSA. Point-to-point facilities may be developed and owned or operated by a generation company for its exclusive use and for the exclusive purpose of connecting to the transmission system. Ownership of the facilities shall be transferred to TRANSCO at a fair market price in the event that they are required for competitive purposes.
Electric Cooperatives (ECs)
ECs given the option to convert into either (1) stock cooperative under the Cooperatives Development Act or (2) stock corporation under the Corporation Code.
10
EPIRA, Section 37
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 47
ISSUE POLICY FRAMEWORK
Democratization Holdings of persons including directors, officers, stockholders and related interests in a DU (except Electric Cooperatives) and their respective holding companies limited to at most 25% of the voting shares of stocks unless the utility or company holding the shares or its controlling stockholders are already listed in the Philippine Stock Exchange (PSE) , Provided that controlling stockholders of small DUs, i.e. with peak demand of 10 MW or less, who already own the stocks lists in the PSE within 5 years from EPIRA’S enactment. New controlling shareholders to list within 5 years of acquiring ownership and control.
STRUCTURE
Vertical Structure Separation of Transmission and Generation
No explicit policy statement for or against vertical integration of distribution and generation. That integration is allowed may be inferred from Section 45, 6th para, 2nd sentence to wit: “Except as otherwise provided for in this Section, any restriction on ownership and/or control between or within sectors of the electricity industry may be imposed by ERC only insofar as the enforcement of the provisions (i.e., on Cross Ownership, Market Power Abuse and Anti-Competitive Behavior ) of this Section is concerned. Sec 45 limits to at most 50% of total demand that DU can source through bilateral contracts with associated firms except for contracts concluded before the EPIRA
Horizontal Structure As provided in Section 45, no company or related group is allowed to own, operate or control more than 30% of installed generation capacity of a grid and/or 25% of the national installed generating capacity. This restriction does not apply to NPC but applies to IPP Administrators.
LIBERALIZATION
Generation Single buyer arrangement ended . Generation opened to new entrants and de-listed as public utility operation. Franchise requirement lifted.
Wholesale Electricity Spot Market (WESM)
WESM to be established within a year of the law’s effectivity. DUs required to source at least 10% of their demand from WESM in the first 5 years of WESM’s establishment. NEA to act as guarantor of Electric Cooperative’s purchases and for this purpose, its authorized capital stock was increased to PhP 15 Billion.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 48
ISSUE POLICY FRAMEWORK
Open Access and Retail Competition
Within 3 years (5 years for Electric Cooperatives) of the law’s effectivity subject to:
1) Establishment of the wholesale electricity spot market; 2) Approval of unbundled transmission and distribution wheeling
charges; 3) Initial implementation of cross-subsidy removal scheme; 4) Privatization of at least 70% of total capacity of NPC generating
assets in Luzon and the Visayas; 5) Transfer to IPP Administrators of the management and control of
at least seventy percent (70%) of the total energy output of power plants under contract with NPC
Those with monthly average peak demand during the preceding 12 months of at least 1 MW to be opened to generators and retail electricity suppliers; contiguous areas with aggregate demand of at least 750 kW, 2 years after. A gradual reduction of the threshold until it reaches the household demand level following market evaluation by the ERC.
TRANSITION SUPPLY CONTRACTS (TSC)
NPC to file with ERC TSC negotiated with DUs within 6 months of the law’s effectivity. TSC to contain terms and conditions of supply and rate schedule including applicable adjustments and/or indexation formula. TSC terms shall not extend beyond one (1) year from the declaration of open access.
CONDUCT REGULATION
A. PRICE/RATE REGULATION
Generation Generation and retail supply to contestable market to be deregulated upon implementation of retail competition and open access, except as otherwise provided in the law.
Transmission and Distribution
Regulated . ERC directed to establish and enforce rate-setting methodology for transmission and distribution. It was allowed to adopt appropriate alternative forms of internationally accepted rate setting methodology that results in non-discriminatory and reasonable price of electricity.
B OTHER RATE RELATED POLICIES
Mandated Rate Reduction
NPC rates to residential end-users to be reduced by PhP0.30/kWh upon the law’s effectivity.
Lifeline Rates ERC to set rates for marginalized end-users. These lifeline rates are to be exempted from the phase-out of cross-subsidies.
Cross-Subsidies All cross-subsidies to be phased out within 3 years from the establishment of the universal charge.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 49
ISSUE POLICY FRAMEWORK
Universal Charge A universal charge on all end users shall be collected within one year of the law’s effectivity for the following purposes:
Payment for the stranded debt of NPC in excess of the PhP 200 Billion to be assumed by the Government;
Payment for the stranded contract costs of NPC and the distribution utilities from contracts approved by the Energy Regulatory Board as of December 31, 2000;
Missionary electrification;
Equalization of taxes and royalties between indigenous and renewable sources of energy and, imported energy fuels as provided in Section 35;
Environmental charge for watershed rehabilitation and management amounting to PhP 0.0025/kwh;
a charge for the removal of cross-subsidies to be imposed for not more than three years.
Stranded Cost To be paid by end-users through the universal charge. This consists of :
(1) NPC Stranded Debt. Any unpaid financial obligation of NPC in excess of the PhP 200 Billion assumed by the National Government.
(2) NPC Stranded Contract Cost. The excess of NPC’s contracted cost of electricity under eligible IPP contracts over their actual selling price in the market. To be eligible, contracts should have been approved by the ERC by December 31, 2000.
(3) DU Stranded Contract Cost. The excess of the DU’s contracted cost of electricity under eligible contracts over the actual selling price of such contracts in the market. . To be eligible, contracts should have been approved by the ERC by December 31, 2000.
C NON-PRICE CONDUCT
General Prohibitions Section 44 of the law prohibits any person or participant in the electric power industry from engaging in anti-competitive behavior including but not limited to cross-subsidization, price or market manipulation, or other unfair trade practices
Competition Rules ERC directed to promulgate competition rules within one year of the law’s effectivity. The rules are intended to ensure and promote competition, encourage market development and customer choice and discourage/penalize abuse of market power, cartelization and any anti-competitive or discriminatory behavior.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 50
5 ASSESSMENT OF RESULTS OF EPIRA REFORMS
Whether the law has been effective is best examined by comparing the achievements to date
with its objectives. Section 2 ‘Declaration of Policy’ of the EPIRA recites the State’s policy
objectives. These are summarized below to wit:
a) Total electrification;
b) Quality, reliability and security of electricity supply;
c) Enhanced inflow of private capital , private ownership and broadening of ownership base;
d) Fair and non-discriminatory treatment of public and private sector entities in the restructuring process;
e) Socially and environmentally compatible energy sources and infrastructure;
f) Greater utilization of indigenous and new and renewable energy to reduce dependence on imported energy;
g) Efficient use of energy and demand side management;
h) Affordable, transparent and reasonable electricity rates; and
i) Consumer protection and competition through a strong and independent regulator.
5.1 TOTAL ELECTRIFICATION
The DOE targets 100% electrification of barangays by 2008 and 90% of households by 2017.11
Recent DOE statistics report that 99.4% of barangays had been electrified by 200912. The
electrification levels by grid were 99.66 %, 99.53% , 99.67% in Luzon, Visayas and Mindanao
respectively.
The accuracy of this data was challenged during the deliberation of the DOE budget at the
House of Representatives in September 2010.13 A subsequent briefing by NEA to the House’
Committee on Energy on November 2010 confirmed the inaccuracy of the official DOE/NEA
11
DOE Expanded Rural Electrification Program, www.doe.gov.ph 12
Ibid, Power Statistics 13
Philippine Daily Inquirer
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 51
electrification data.14 NEA reported that 31% of the 100,186 sitios nationwide are still not
electrified and set a 100% energization target by 2020.
Neither the DOE nor NEA publish data on the level of household electrification.
5.2 QUALITY, RELIABILITY AND SECURITY OF ELECTRICITY SUPPLY
DOE does not have a working plan or program that will directly address the quality and
reliability of electricity supply. It appears to have left this responsibility to the ERC. ERC has set
systems loss targets but not those of other reliability and service quality indices in the Grid and
Distribution codes. Instead , the latter are merely nominated by distribution utilities and NGCP
whose rates are determined under the Performance Based Regulation (PBR) rate-setting
methodology, based on their performance in the last three years.
While many distribution utilities made significant reduction in systems losses, power losses as a
percentage of total electricity consumption stayed at 12% in 2001 and 2009.15 A thorough
assessment of the EPIRA’s achievements vis-à-vis energy security, reliability and quality is made
in Section 3.6 that shows serious deficiencies in DOE’s planning process.
To ensure energy security, the Department will:16
a) Accelerate the exploration and development of oil, gas and coal resources;
b) Intensify development and utilization of renewable and environment-friendly alternative energy resources/technologies;
c) Enhance energy efficiency and conservation;
d) Attain nationwide electrification;
e) Put in place long-term reliable power supply;
f) Improve transmission and distribution systems;
14
NEA „Briefing for the Committee on Energy‟, November 4, 2010 15
DOE Power Statistics 16
DOE „Philippine Energy Plan‟ 2009-2030
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 52
g) Secure vital energy infrastructure and facilities; and
h) Maintain a competitive energy investment climate.
Apart from the methodologies described in Section 3.6; security of energy supply is also
affected by: (1) fuel diversity , and (2) import dependency. 17 Higher fuel diversity leads to
higher supply security. The risk of supply disruption and price volatility is directly related to the
level of import dependency especially on oil and gas and lately also coal; fuels that have the
greatest price volatility.
Another important indicator is energy efficiency which is measured by energy intensity, i.e.
energy consumption per unit of GDP. These three indicators directly correspond with programs
1 to 3 above.
The national picture however hides the fragile state of the country’s energy security relative to
power generation. This is largely due to the dominance of a single fuel at the grid level and a
pricing policy on key indigenous energy resources that exposes much of power generation to
the volatility of the international price of oil and coal. Figure 11 and Figure 12 reveal over-
reliance in each grid on single resource , i.e., Luzon on natural gas; Visayas on geothermal steam
and Mindanao on hydro resources. Just this year, acute power shortages were experienced in
the Visayas and Mindanao grids when the old geothermal plants in the former had to shut down
for rehabilitation and hydrothermal plants in the latter, due to prolonged drought. The condition
was somewhat eased in the Visayas by the 440 MW HVDC transmission line between Leyte and
Luzon that allowed for limited imports . Mindanao, which is isolated , did not get a similar
reprieve.
17
World Bank “Winds of Change: East Asia‟s Sustainable Energy Future‟ May 2010
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 53
Figure 11. National Gross Power Generation By Resource, 2001 and 2009
Figure 12. Gross Power Generation By Grid and Resource, 2001 and 2009
The price of Natural gas from Malampaya is indexed to the international oil price while that of
geothermal steam from all the steam fields previously held by PNOC-EDC , to the international
price of coal. Consequently, the domestic price of natural gas has followed the trend of, and
had not been spared from the volatility of international oil prices as shown in Figure 13. In a
departure from the past contracts between NPC and PNOC-EDC that indexed the steam price to
0
10000
20000
30000
40000
50000
2002 2009 2002 2009 2002 2009
GW
h
Year
Coal Oil-Based Natural Gas Geothermal
Hydro Wind Biomass
Luzo Visayas Mindanao
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 54
domestic inflation only, the steam sales contract in 2006 between PSALM and PNOC-EDC
indexed the steam price to the international price of coal as well. This indexation could be
behind the nearly 50% increase in steam cost, from PhP 1.7-1.9/kWh in 2008 to PhP
2.8328/kWh in 2009 that the new owners of the Visayas geothermal plants want to recover
from customers in the Visayas Grid.
Source: DOE
Figure 13. Weighted Average Price of Malampaya Gas (2002-2009, Quarters)
5.3 ENHANCED INFLOW OF PRIVATE CAPITAL, PRIVATE OWNERSHIP AND
BROADENING OF THE OWNERSHIP BASE
5.3.1 PRIVATIZATION OF NPC ASSETS AND IPP CONTRACTS
Privatization proceeded at a very slow pace and was hobbled by many issues such as pricing,
and difficulty in securing the agreement of creditors for the transfer of liabilities from NPC to
PSALM. The operation of the transmission assets was finally awarded in 2008 to a private
concessionaire after three failed biddings. Sale of the generation assets only gained momentum
in 2008-2009 and and is now practically complete at 82.6% of total capacity (based on PSALM
plant capacity records; 89% based on ERC plant capacity reports) of total capacity while 80.21
02468
101214
0 4 8 12 16 20 24 28 32 36
Pri
ce (
US$
)
Quarter
US$/GJ US$/MMBTU
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 55
% of the energy output (76.85% based on ERC plant capacity records) 18 of the IPPs have been
transferred to private administrators. Privatization of the remaining IPPs has been derailed by
cases filed in the Supreme Court questioning their Constitutionality and/or consistency with the
policy objectives and guidelines of the EPIRA.
5.3.2 ENHANCED INFLOW OF PRIVATE CAPITAL
New investments in generation by private investors were less than a trickle. The installed generating capacity as of April 2010 was 15,607.8 MW, a mere 2,222.8
increase from 13,385 MW in 2001.19 Of these new investments , 3,780 MW were in 139.1 MW in the Visayas and 265 in MW20. As shown in
Table 20, except for Northwind Power and Montalban LFG which are driven by renewable
energy policy and program of the givernment, those in Luzon were already committed prior to
the EPIRA.
Committed generation investments as of July 2010 as recorded by the DOE were 600 MW in
Luzon, 671 MW in the Visayas and 100.50 MW in Mindanao as shown in Table 21. Their target
completion dates are from March 2010 (for the expansion of Unit I of the CFB Power Plant) to
July 2014 (for the Mindanao 3 Geothermal Power Plant).
Except for a few distribution utilities of local government units, distribution utilities including
the Electric Cooperatives had long been privately owned by the time of the enactment of the
EPIRA. The privatization of Olongapo’s public distribution utility in 2010 completed the
privatization of this sector.
18
The variation in plant capacity records of PSALM and ERC stems from ERC‟s adjustments in installed capacity limit from temporary causes such as outages. On the other hand, there is no baseline record for energy output per se. The baselines used by PSALM/JCPC are a combination of contracted capacities in PPAs and dependable capacities). 19
DOE Power Statistics 2010 20
The discrepancy between the 2010 installed generating capacity and aggregate new investments between 2001-2010 is due to the decommissioning of the Bataan , Manila, Sucat Thermal Power Plants; Cebu II, Aplaya and General Santos Diesel Plants with a combined installed capacity of 1,459.3 MW
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 56
The transfer of the operation of the transmission system to a private concessionaire is expected
to enhance the inflow of private capital for rehabilitation and expansion of the network.
Table 20. Addition to Installed Generating Capacity after 2001
Plant Type Plant Name Owner Installed Capacity
(MW)
Date Commissioned
Luzon
Coal Asia Pacific Energy Corp Non-NPC/IPP 50 2006
Natural Gas Sta Rita Non-NPC/IPP 1,060 Jun 2000/Oct 2011
Natural Gas Ilijan Non-NPC/IPP 1,271 Jun 2002
Natural Gas San Lorenzo Non-NPC/IPP 500 Sept 2002
Hydro San Roque Non-NPC/IPP 345 May 2003
Hydro Kalayaan 3 & 4 NPC-IPP 355 May 2004
Hydro Casecnan Non-NPC/IPP 165 Apr 2002
Hydro Cawayan Non-NPC/IPP .40 Jun 2002
Wind Northwind Power Non-NPC/IPP 33 Jun 2005
Biomass Montalban LFG Non-NPC/IPP 1.0 Jun 2009
Total Luzon 3,780
Visayas
Bunker Fuel Global Business Power Corp (Iloilo)
Non-NPC/IPP 20 Feb 2006
Bunker Fuel Global Business Power Corp (Aklan)
Non-NPC/IPP 12.5 Aug 2006
Bunker Fuel Global Business Power Corp (Aklan)
Non-NPC/IPP 5 Sept 2006
Diesel Guimaras Power Project Trans-Asia 3.4 Apr 2005
Diesel PDPP III (Pinamucan) SPC Power Corp
Non-NPC/IPP 66.4 Transferred 2005
Biomass San Carlos Bioenergy Bronzeaok Phil Inc
8.3 Feb 2009
Biomass First Farmers Biomass Cogen
Non-NPC/IPP 21 Feb 2009
Hydro Sevilla Hydroelectric Plant Non-NPC/IPP 2.5 Nov 2008
Total Visayas
139.1
Mindanao
Diesel PB 104 NPC 32 Sept 2005
Solar Sitio Lomboy, Cagayan Non-NPC/IPP 1 Sept 2004
Coal Mindanao Coal I & II NPC-IPP 232 Sept & Nov 2006
Total Mindanao
265
Source: DOE Power Statistics 2010
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 57
Table 21. Committed Generation Investments as of June 2010
Project Proponent Capacity
(MW) Target Completion
Luzon
2 x 300 MW Coal Fired Power Plant
GN Power 600 4th quarter 2012
Total Luzon 600
Visayas
3 x 82 MW CFB Power Plant Expansion Project
Cebu Energy Development Corp
246 Unit I March 2010 Unit II June 2010 Unit III Jan 2011
Cebu Coal Fired Power Plant KEPCO SPC Power Corp
200 Unit I Feb 2011 Unit II May 2011
2 x 17.5 MW Panay Biomass Power Project
Green Power Panay Phil
35 Unit I 2011 Unit II 2012
Nasulo Geothermal EDC 20 2011
2 x 82 MW CFB Power Plant Panay Energy Development Corp
164 Unit I Sept 2010 Unit II Dec 2010
Total Visayas 671
Mindanao
Sibulan Hydroelectric Power Hedcor Sibulan, Inc 42.5 June 2010
Cabulig Mini-Hydro Power Plant Mindanao Energy Systems Inc
8 June 2011
Mindanao 3 Geothermal EDC 50 July 2014
Total Mindanao 100.50
TOTAL COMMITTED INVESTMENTS
1,317.5
Source: DOE, 16th EPIRA Implementation Status Report (Period covering November 2009-April 2010)
5.3.3 BROADENING OF OWNERSHIP BASE
Generation
Broadening of the ownership base is subject to the installed capacity limits in Section 45(a) of
the EPIRA. The law prohibits the ownership, operation or control by a company or related group
of more than thirty percent (30%) of the installed generating capacity in a grid and/or twenty-
five percent (25%) of the national installed generating capacity. The NPC is exempt from this
prohibition.
Data from the DOE and ERC show that while NPC’s ownership went down from 74% in 2003 to
51.8% in 2010, the government through the NPC owned plants and IPPs retains majority
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 58
ownership of the country’s installed generating capacity in 2010. On a grid basis, government
ownership in 2010 is highest in Mindanao at 85.6% followed by Luzon and Visayas at 53% and 14%
respectively.
The decline in government ownership is primarily due to the sale of NPC owned plants. The
ownership distribution of the private generating capacities, i.e. those not under contract with
NPC are shown in Table 22.
Control of the output of the installed generating capacities remains largely with the NPC except
in Luzon as shown in Figure 14. The San Miguel group now holds nearly 30% (or slightly over 30%
depending on the accuracy of the ERC or DOE data on installed capacities) from its acquisition of
NPC owned plants and administration of the IPP outputs that were transferred to it from PSALM
under the IPP Agreements (IPPA).
Transmission
Broadening of the ownership base of the transmission utility would have been possible by
selling the three grids to three different parties. While the EPIRA does not preclude this option;
the operation of the national network was transferred in 2008 as a whole to a single party on a
concession basis only.
Distribution
Broadening the ownership base of distribution could have been effected by the juridical
separation and sale to different entities of the distribution networks owned by MERALCO but
which had their own franchises prior to the EPIRA. Instead Congress passed a law in 2004
consolidating these franchises into a MERALCO mega-franchise.
Rather than broadening their ownership base, some of the 109 Electric Cooperatives 21may
have to merge to achieve operating efficiency. While DOE has considered this option, it has
proven to be politically difficult to implement.
21
As of end 2010, 10 on-grid ECs , 9 of which are in Luzon had registered with the Cooperative Development Authority. These are Pangasinan I, Pangasinan III, Isabela II, Nueva Vizcaya,
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 59
Table 22. Ownership Distribution of Private Generating Plants
Owner Plant Name Installed Capacity
(MW)
% Share of Total Private
Luzon
A. Lopez Group
1 From Privatized NPC/PNOC Pantabangan-Masiway 112
Bac-Man 150
Total from Privatized 262
2 Others Sta Rita 1,047
San Lorenzo 549.1
Total Others 1,596.10
Total Lopez Group 1,858.10 32.47%
B. Aboitiz Group
1 From Privatized NPC/PNOC Magat HEPP 360
Tiwi GPP 330
Mak-Ban GPP 410
Ambuklao HEPP 75
Binga HEPP 100
Total from Privatized 1,275
2 Others 0
Total Aboitiz Group 1,275 22.28%
C. San Miguel Group Limay Combined Cycle 655.5 11.45%
D. AES Masinloc Coal I & II 635 11.10%
E. DMCI Calaca Power Corp 600 10.48%
F. Quezon Power Phil Quezon Power 511 8.93%
G. Other Owners
Angeles Electric Corp Angeles Power Inc 30
Angeles Electric Corp 9
Tarlac Power Corp 18.9
First Cabanatuan Ventures Corp 25.6
Trans-Asia Power Generation Corp
52
Northwind Power Corporation 33
INEC INEC-Agua Grande Mini-HEPP 4.5
SORECO Bicol Hydropower Corp 0.96
Atty Ramon Constancio Cawayan HEPP 0.448
Barit HEPP 1.8
ISELCO Magat A & B 2.5
MOntalban Methane Power Corp 8.19
Phil Power Development Corp 1.11
Total Other Owners, Luzon 188.008 3.29%
Quirino, Abra, San Jose City, Palawan, Sorsogon II, Negros Occidental. None has converted into Stock Corporations
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 60
TOTAL PRIVATE , LUZON 5,722.61 100.00%
Transmission
Broadening of the ownership base of the transmission utility would have been possible by
selling the three grids to three different parties. While the EPIRA does not preclude this option;
the operation of the national network was transferred in 2008 as a whole to a single party on a
concession basis only.
Distribution
Broadening the ownership base of distribution could have been effected by the juridical
separation and sale to different entities of the distribution networks owned by MERALCO but
which had their own franchises prior to the EPIRA. Instead Congress passed a law in 2004
consolidating these franchises into a MERALCO mega-franchise.
Rather than broadening their ownership base, some of the 109 Electric Cooperatives may have
to merge to achieve operating efficiency. While DOE has considered this option, it has proven to
be politically difficult to implement.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 61
Table 22. Ownership Distribution of Private Generating Plants (cont.)
Owner Plant Name Installed Capacity
(MW)
% Share of Total Private
Visayas
A. Lopez Group
1 From Privatized NPC/PNOC Tongonan I, Palinpinon I & II 305
Unified Leyte 618.4
Northern Negros GPP 49.37
Total from Privatized 972.77
2 Others 0
Total Lopez Group 972.77 54.44%
B. Aboitiz Group
1 From Privatized NPC/PNOC 0
2 Others Cebu Private Power Corp 73
East Asia Limited Corp 50
Total Aboitiz Group 123 6.88%
C Global Business Power Corp
1 From Privatized 0
2 Others Panay Power Corp 108
Cebu Energy Development Corp 167.4
Panay Energy Development Corp
82
Toledo Power Corp 134.75
Total Global Business Power Corp
492.15 27.54%
D Other Owners
SPC Power Corp Bohol DPP, Panay I & II 166.5
BOHECO I Janopol HEPP/Sevilla HEPP 7.5
SAMELCO I Ton-ok Mini HEPP 1
CEBECO I Mantayupan, Matutinao, Basa 1.7
Sta Clara International Corp Loboc HEPP 1.2
SOLECO Henabian MHPP 0.8
Bronzeoak Philippines Inc San Carlos Bioenergy Co, Inc 8.3
ICS Renewables Amlan HEPP 0.8
Enervantage Suppliers Co, Inc Enervantage Bunker C-Fired DPP
11
Total Other Owners, Visayas 198.8 11.13%
TOTAL PRIVATE, VISAYAS 1,786.72 100.00%
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 62
Transmission
Broadening of the ownership base of the transmission utility would have been possible by selling the three grids to three different parties. While the EPIRA does not preclude this option; the operation of the national network was transferred in 2008 as a whole to a single party on a concession basis only.
Distribution
Broadening the ownership base of distribution could have been effected by the juridical
separation and sale to different entities of the distribution networks owned by MERALCO but
which had their own franchises prior to the EPIRA. Instead Congress passed a law in 2004
consolidating these franchises into a MERALCO mega-franchise.
Rather than broadening their ownership base, some of the 109 Electric Cooperatives may have
to merge to achieve operating efficiency. While DOE has considered this option, it has proven to
be politically difficult to implement.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 63
Table 22. Ownership Distribution of Private Generating Plants (cont.)
Owner Plant Name Installed Capacity
(MW)
% Share of Total Private
Mindanao
A. Lopez Group
1 From Privatized NPC/PNOC Mindanao I & II Geothermal Partnership
108.5
Bukidnon Power Corp 1.8
Total from Privatized 110.3
2 Others 0
Total Lopez Group 110.3 24.63%
B. Aboitiz Group
1 From Privatized NPC/PNOC Talomo MHEPP 4.6
Power Barge 117 100
Power Barge 118 100
Total from Privatized 204.6
2 Others DALIGHT Bajada Power Plant 53.5
Cotabato Light & Power Co 9.9
Sibulan A & B 42.59
Total Others 105.99
Total Aboitiz Group 310.59 69.37%
C. CEPALCO Mindanao Energy Systems, Inc 18.9
Bubunuwan Power Co, Inc 7
Solar Photovoltaic 0.95
Total CEPALCO 26.85 6.00%
TOTAL PRIVATE, MINDANAO 447.74 100.00%
Source: Plant name and installed capacity were based on ERC Resolution No 20 Series of 2010 „A Resolution Setting the Installed Generating Capacity Per Grid, National Grid and the Market Share Limitations Per Grid and the National Grid for 2010‟ issued on October 5, 2010. Information on plant ownership partly sourced from DOE 2009 Power Statistics
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 64
Source: ERC and DOE Data
Figure 14. Control of Installed Generating Capacity as of March 2011 ,
Luzon, Visayas and Mindanao
San Miguel
30%Lopez15%
Aboitiz17%
NPC16%
Others22%
Control of Installed Capacity, Luzon
NPC41%
Lopez Group17%
Aboitiz14%
Global Business
Power17%
SPC8%
Others 3%
Control of Installed Capacity, Visayas
NPC83%
CEPALCO1%
Aboitiz16%
Control of Installed Capacity, Mindanao
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 65
5.4 GREATER UTILIZATION OF INDIGENOUS AND NEW AND RENEWABLE ENERGY TO
REDUCE DEPENDENCE ON IMPORTED ENERGY
The reduction in the share of imported energy in the generation mix was mainly due to the
discovery and utilization of natural gas from Malampaya whose share of gross generation
jumped to 32.1% in 2009 from 1.8% in 2001. However, the boost to energy security that could
have resulted from this development was undermined by the indexation of its price to the
international price of Brent oil.
DOE targets the doubling of renewable capacity by 2030. From the results so far, it looks like
only hydro is on track to meet this objective. The contribution of new renewable energy to the
generation mix barely moved: from 0 in 2001 to 64 MW in 2009. Of the ‘old’ renewable energy,
hydro increased by 58% from 3,518 MW in 2001 to 3,291 MW in 2009 while generation from
geothermal was practically maintained: at 1,931 MW in 2001 and at 1,953 in 2009. That said,
the inordinate focus by the government on renewable energy to the point of loading all possible
incentives for investments in the sector is unnecessary and may turn out to be both counter-
productive and financially unsustainable. Hydro and geothermal already account for 33% of
gross generation while natural gas, a clean resource adds another 31% or a total of 64%. In
comparison, countries in Europe that pioneered the adoption of Feed-in-Tariffs (FIT) such as
Germany, Spain and France started with less than 5% RE contribution in their generation mix. As
it is, they have scaled back their FIT while maintaining their 20% RE target for 2020. Massive
fiscal and policy incentives risk the commercialization of renewable resources and technologies
in the Philippines that are on the fringe and could potentially undermine the reliability of the
country’s energy supply. At the same time, fiscal incentives such as tax exemptions strains the
government finances and are thus unsustainable in the long-run.
5.5 FAIR AND NON-DISCRIMINATORY TREATMENT OF PUBLIC AND PRIVATE SECTOR
ENTITIES IN THE RESTRUCTURING PROCESS
No report of discrimination reported.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 66
5.6 SOCIALLY AND ENVIRONMENTALLY RESPONSIBLE SOURCES OF ENERGY AND
INFRASTRUCTURE
A target of 32,000 Gigagrams (32 Metric Tons) cumulative emission avoidance of carbon dioxide
was set in the Philippine Energy Plan (PEP) for 2004-2013. To achieve this, the DOE planned to:
a) aggressively promote Renewable Energy;
b) prioritize the conversion of old and retiring oil and coal-fired power plants to natural gas;
c) strictly implement the fuel quality standards in the Philippine Clean Air Act; and
d) implement energy efficiency and conservation measures.
There is no indication from either the various DOE reports or the DENR on the cumulative
avoided emission performance to date vis-à-vis the target.
Power Generation is a close second to Transport in CO2 emissions. The Philippine National
Communication to the UN Framework Convention on Climate Change disclosed that of the Total
CO2 emission of 50,038 kilo-ton of the energy sector in 1994, 15,888 or 31.7% was from
Transport and 15,508 or 31% from Power Generation. The Carbon Monitoring for Action
(CARMA), estimated the CO2 emission of all Philippine power plants, i.e. grid and off-grid
including embedded plants of industries, at 24,425,721 kTons in 2000 and 33,067,120 in the
current year (as shown in
), a growth of more than twice the 1994 Philippine official figure .22 Of these, 95.6% were from
15 on-grid power plants; 1 from a coal mine and 1 from a mill. At an estimated cost of
$20/tCO223, the external environment cost of the CARMA derived CO2 emission of Philippine
power plants in the current year equals $661,342,400.
22
The CARMA database contains detailed information on the carbon emissions of over 50,000 power plants and companies worldwide. The project is financed by the Confronting Climate Change Initiative at the Center for Global Development, an independent and non-partisan think tank in Washington DC. Emission data for US, Canada, EU and India are based on official reports. Otherwise, emission levels are estimated using a statistical model that was fitted for thousands of reporting plants of these countries. It welcomes comments in its website
23
As estimated in the World Bank Study „Winds of Change: East Asia‟s Sustainable Energy Future‟ May 2010
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 67
Table 23. CO2 Emission of Selected Philippine Power Plants (in kTons)
Power Plant 2000 Current Year
Sual 6582 8181
Pagbilao 3564 4415
Calaca 3121 3851
Masinloc 3032 3766
Quezon Power 2558 3192
Santa Rita 1465 1843
Ilijan - 1435
Mindanao STEAG 0 1268
San Lorenzo 0 881
Naga 648 799
Toledo 604 742
Limay 463 573
Mabalacat Mill 0 494
Malaya 303 240
Semirara 158 194
Power Barge 117 112 139
Total (of 17) 23,345,077 33,067,120
Total (all PH Power Plants) 24,425,721 34,569,282
Source: www.carma.org
5.7 EFFICIENT USE OF ENERGY AND DEMAND SIDE MANAGEMENT
The DOE’s energy efficiency and conservation targets as well as their implementing strategies
keep shifting. From 82.56 MMBFOE (or an average of 8.256 annually) in the 2004-2013 PEP; it
was increased to 23.4 MMBFOE annually for the 2005-2014 planning period; scaled down to 7.5
MMBFOE in 2010 and upped to 9.1 MMBFOE by 2016 in PEP 2007-2016. The target was
changed to 10% energy savings on the total annual demand of all economic sectors in PEP 2009-
2018.
There is limited information available on performance against these targets. It was reported that
in 2006, the recorded energy savings was at 6.1 MMBFOE which was much lower than the 23.4
MMBFOE target at that time.24 Energy labeling and efficiency standards generated 2.03
MMBFOE or 33.3% of total savings achieved. Of this, over half , 1.13 MMBFOE came from the
24
PEP 2007-2016
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 68
CFL project. Power losses as a percentage of total electricity consumption stayed at 12% in 2001
and 2009.25
Among the strategies identified by the DOE in PEP 2009-2018 are:
a) Power Patrol;
b) Partnership for Energy Responsive Companies;
c) Energy Standards & Labeling of Appliance/Equipment;
d) Government Enercon Program;
e) Energy Audit;
f) Energy Use Standard for Buildings;
g) Heat Rate Improvement of Power Plants; and
h) System-Loss Reduction.
In previous PEPs, the strategies also included the aggressive promotion of renewable energy.
The program appears to lack focus (some like the heat-rate improvement and energy building
standards have not been aggressively pursued) and a comprehensive policy framework that will
spell out incentives and penalties for non-compliance. The development of a policy framework
for Demand-Side Management that was assigned to the ERC in the EPIRA has not been started.
The ERC and the DOE had subsequently agreed that the latter will take charge of this but work
on the policy framework has yet to commence.26
5.8 AFFORDABLE, TRANSPARENT AND REASONABLE ELECTRICITY RATES
Whether the electricity rates after the EPIRA are affordable and reasonable is difficult to
evaluate inasmuch as the neither the regulator nor the DOE has determined the tariff level that
is affordable and reasonable tariff. At the same time, the complexity of the new rate setting
methodology for the transmission and distribution utilities and bilaterally negotiated purchase
power contracts tend to obscure the true cost of electricity from the public.
25
DOE Power Statistics 26
From interviews with ERC and DOE officials
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 69
Data from the DOE shows that the effective electricity rates rose by 28.8% from 2003 to 2009.
As shown in Figure 15 and Figure 16, this national average was mirrored in Luzon where
electricity rates increased by 29% during the same period, albeit, with peaks that reached PhP
8.00/kWh that were not experienced in the Visayas and Mindanao grids.
Source: DOE EPIRA Reports 2007 Rates are estimate
Figure 15. Annual Average Effective Rates Rates (2000-2009)
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
National 4.69 5.47 5.18 5.51 5.59 6.80 6.90 6.88 5.77 7.25
Luzon 4.82 5.62 5.31 5.71 5.90 7.29 8.05 8.03 6.40 7.73
0123456789
Pe
so/k
Wh
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 70
Figure 16. NPC Annual Average Effective Rates (2003-2010)
The analysis of MERALCO’s 2010 billing statements in Table 24 indicates that generation and
transmission costs were behind the rate increases. Generation charges increased by an average
of 30% ; transmission by 48%. Distribution had no contribution because MERALCO’s 2003
unbundled charges continued to apply until 2010 when the ERC finally allowed the utility to
implement its approved rates under the Performance Based Methodology (PBR) . Tariffs are
certain to increase more with the implementation of MERALCO’s PBR rates where the
distribution charges alone are on average, 60.5% higher than their 2003 level.
The rise in MERALCO’s generation costs in 2008 to 2010 as shown in Figure 17 were caused by
the increasing prices of its 3 main suppliers, namely: IPPs, WESM, and NPC. WESM average
prices per kWh were at PhP 7.79 in 2010, PhP2.86 in 2009 and PhP4.87615 in 2008. Average
price of NPC were at its highest in 2010 at PhP 5.24/kWh and lowest in 2008 at PhP3.97/kWh.
Purchases from the IPPs had lower price fluctuations than those from WESM and NPC at an
average of PhP4.6/kWh during the 3 year period with its highest average at PhP/4.71/kWh in
2008.
0
1
2
3
4
5
6
2003 2004 2005 2006 2007 2008 2009 2010
Pes
o/k
Wh
Year
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 71
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 72
Table 24. MERALCO Comparative Charges1, 2003
2-2010
3 (Pesos)
Service Generation (per kWh)
4
Transmission (per kW except
residential)5
Distribution (per kWh)
6
Distribution (per kW)
6
Supply & Metering
(per customer/ month)
6
Residential 201-300 KWh
2003 3.4029 0.9605 1.6471 5
2010 4.2874 1.28 2.23 25.95
Change 25.99% 33.26% 35.39% 419.00%
General Service IS Small
2003 3.4029 258.31 0 141.87 973.07
2010 4.2874 376.5898 0.0259 247.87 1,309.79
Change 25.99% 45.79% 0.7472 34.60%
INDL IS Large Secondary
2003 3.4029 290.11 0 119.4 973.07
2010 4.2874 433.898 0.0259 247.87 14,382.97
Change 25.99% 49.56% 1.076 1378.10%
Comm NIS Large Below 13.2 Kv
2003 3.4029 294.57 0 112.94 973.07
2010 4.2874 469.2007 0.0259 188.56 14,382.97
Change 25.99% 59.28% 0.6696 1378.10%
Comm NIS Very Large 13.8/13.2 kV
2003 3.4029 300.1 0 123.27 1,096.34
2010 4.2874 469.2007 0.0259 188.56 31,509.08
Change 25.99% 56.35% 0.5297 2774.02%
Industrial IS Large 34.5 kV
2003 3.4029 311.4 0 124.62 1,096.34
2010 4.2874 503.5579 0.0259 188.56 31,509.08
Change 25.99% 61.71% 0.5131 2774.02%
Industrial IS Extra Large 115 kV
2003 3.4029 326.12 0 112.76 973.07
2010 4.2874 421.2338 0.0259 151.69 31,509.08
Change 25.99% 29.17% 0.3452 3138.11% 1 Excludes VAT, Energy Tax, Lifeline rate subsidy, special discount, power factor adjustment, power act reduction
2 Based on ERC Order of May 2003 on ERC Case No 2001-900 & 2001-646 „Re Application for Approval of Revision of
Rate Schedules and Appraisal of Properties With Prayer for Provisional Authority‟ and „In the Matter of the Application for Approval of the Revised Rate Schedule in Compliance with Section 36 of Republic Act No 9136 and ERC Order Dated October 30,2001 and for Approval of Appraisal of Properties, With Prayer for Provisional Authority: MERALCO, Applicant‟ 3 Based on MERALCO Summary Schedule of Rates Effective December 2010 Billing Month
4 MERALCO average generation cost in 2009 and ERC approved generation rates in 2003
5 MERALCO average transmission charges in 2010
62010 Distribution charges
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 73
Figure 17. MERALCO Average Monthly Generation Cost (2008-2010)
The typical residential energy price and typical industrial regulated price in Chile are shown in
Figure 18 and Figure 19, respectively. For the residential customers, generation rate (energy +
power) is approximately PhP 5.59/kWh while distribution is approximately PhP 1.72/kWh. For
industrial customers, the generation rate comprises of an energy charge of approximately PhP
4.8/kWh; a power charge of approximately PhP43/kW at off-peak or at PhP 365.5/kW at peak
hours. The distribution charge is approximately PhP 64.5/kW. The transmission charge is
approximately 10% of the combined energy and power charge.
It will be noted that while the generation charge in the MERALCO franchise area is lower than in
Chile; the distribution charges for both residential and industrial customers are much higher.
For the typical residential customers , MERALCO’s distribution charge (exclusive of supply and
metering) are at PhP2.23/kWh vs. PhP 1.72/kWh for Chile. For industrial customers, MERALCO’s
lowest charge , i.e., for Extra Large Industrial Customers is 2.35x that of Chile.
Brazil‟s average tariffs are shown in Table 25. They are lower than MERALCO‟s charges for all
customer classes.
0
2
4
6
8
10
12
0 4 8 12 16 20 24 28 32 36
Ph
P/kW
h
Month
NPC WESM NPC & WESM IPPS AVERAGE
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 74
Figure 18. Chile: Typical Residential Energy Price
Figure 19. Chile: Typical Industrial Regulated Price
Table 25. Brazil Average Electricity Prices, 2010
Type of
customer Average Tariff
(US$/MWh) (PhP/kWh)
Residential 153.49 6.68
Industrial 108.55 4.72
Commercial 147.60 6.42
Typical Residential
Energy Price
Typical Residential
Energy Price
Typical Industrial Regulated PriceTypical Industrial Regulated Price
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 75
5.9 CONSUMER PROTECTION AND COMPETITION THROUGH A STRONG AND
INDEPENDENT REGULATOR
Consumer protection and the development of effective competition primarily depend on the
strength of the incentives for them in the policy framework and secondarily only on the strength
and independence of the regulator. The policy review that follows show that existing policies
such as vertical integration between generation and distribution and the improper sequencing
of reforms dulls competition and consequently, consumer protection. Since regulation only
implements policy, any shortcomings on the regulation side is normally corrected by policy
reform. However, there is strong evidence from this assessment and that of the policy
framework that the regulator, by its own omission and/or commission may have further
weakened consumer protection and competition. Examples of these are in the implementation
of the grid limits on generation capacity ; the implementation of the PBR for transmission and
distribution; and the fatally flawed Competition Rules and Complaints Procedures. At the same
time, the regulator is viewed as having taken its independence too far; to the point of making
coordination difficult with other agencies.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 76
6 ASSESSMENT OF INDUSTRY REGULATION
The industry’s regulatory system consists of the regulatory policy directions laid down in the
EPIRA and its Implementing Rules and Regulations (IRR) and the rules and regulations issued by
the regulator to carry them out. The assessment of these regulatory policies will focus on the
strength of their incentives to primarily, attract sufficient private investment in generation in the
Luzon grid and secondarily, contribute to economic efficiency.
A robust regulatory incentive structure aligns the regulatory objectives of economic efficiency
with the profit objective of the regulated firms. Economic efficiency refers to productive
efficiency, dynamic efficiency and allocative efficiency. Prices at marginal cost of production
(which includes a normal mark-up) are allocatively efficient. Those above and below are not. The
former diverts money from more productive activities while the latter leads to wasteful
consumption, insufficient private investment and government subsidies that crowd out other
essential public services such as education and health. Economic efficiency is induced by
effective competition which compels firms to eliminate slack, innovate, and adopt new
processes over time. However, the policy choice is not as straightforward in an industry such as
the electric power industry that is characterized by market power or, the ability to set price
above the marginal cost of production,. In this situation, economic efficiency is brought about
by a policy mix of market competition where it is possible and the regulation of sectors/activities
that are not competitive.
The rules that make up the regulatory incentive structure are intended to act as proxies to the
disciplines imposed by a fully competitive market that are largely absent from utility/network
industries. The principal objective of regulation is thus to ensure that utilities are provided
sufficient incentives to invest, increase their efficiency and reduce costs while maintaining or
improving the quality of service to their customers. A sound regulatory incentive structure
strikes the right balance between ensuring financially viable firms and low electricity rates. It
does not underwrite the financial viability of any particular entity if its viability is being
undermined by risky financial decisions or poor management performance. Neither does it
impose low rates that fail to recover the prudent and reasonable costs of the regulated entities.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 77
As in other network industries, the strength of the regulatory incentives in the electric power
industry rests on the structural policy adopted; liberalization; ownership; conduct regulation;
and the sequencing of policy reforms.
6.1 STRUCTURAL POLICY
6.1.1 VERTICAL SEPARATION OF TRANSMISSION FROM GENERATION AND
DISTRIBUTION
Transmission was vertically separated from generation and distribution. Section 45 of the
EPIRA27 prohibits generation companies, distribution utilities or their respective subsidiaries or
affiliates or stockholders or officials or other entities engaged in these businesses within the
fourth civil degree of consanguinity or affinity from holding any direct or indirect interest in
TRANSCO or its concessionaire and vice versa.
The need for close coordination between transmission and generation favors vertical integration.
However, this policy would restrict competition in generation. To promote competition between
embedded and independent generators, the transmission company could be required to
undertake competitive tendering for additional generating capacity and provide third-party
access to independent generators. However these alternatives will require a strong regulator;
one with not only the adequate powers but the capacity to monitor and ensure that
transactions are arms-length and that the transmission company does not discriminate against
independent generators. Vertical separation is the most radical policy alternative but offers the
most prospect for the horizontal separation and liberalization of generation. Given the EPIRA’s
policy mandate to open generation to competition and to sell-off the generating assets of NPC,
vertical separation of transmission from generation and distribution was the logical policy choice.
6.1.2 VERTICAL INTEGRATION OF GENERATION AND DISTRIBUTION
27
Section 45 is on Cross Ownership, Market Power Abuse and Anti-Competitive Behavior
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 78
There is no categorical policy statement favoring vertical integration between distribution and
generation in the EPIRA. Instead, it is implied in paragraph 3 of Section 45 c) that prohibits ERC
from imposing restrictions on ownership and control outside those required to enforce the
provisions on competition, market abuse and anti-competitive behavior of this Section. Thus,
while a finding of anti-competitive conduct and/or violation of competition rules can force de-
integration; vertical separation is not an ex-ante policy . The relevant sentence in paragraph 3
reads:
“Except as otherwise provided for in this Section, any restriction on ownership
and/or control between or within sectors of the electricity industry may be
imposed by ERC only insofar as the enforcement of the provisions of this Section
is concerned”.
To avoid abuse of market power, Section 45 limits to 50% of its total demand the amount of
energy that a distributor can source from bilateral supply contracts with an associated firm
except for those contracts concluded before the EPIRA. A distributor is also obliged under
Section 2328 to “supply electricity in the least cost manner to its captive market” which is akin to
the economic sourcing obligation imposed in other regulatory jurisdictions abroad.
Except for the reduction of transaction cost, there is hardly any economic justification for
vertical integration. There is very little economies of scope between distribution and generation.
In contrast, the downside risk of anti-competitive conduct by the integrated utility and
disincentive to new entrants are very high. Vertical integration could lead to uneconomic
sourcing where the distributor favors its own generation over cheaper competitors, exclusionary
conduct and discriminatory access terms to the network. To limit the harm to competition, the
vertically integrated utility is: a) subjected to regular audit; b) required to undertake competitive
tendering for its energy requirement and to strictly comply with its economic sourcing
obligation; and c) required to provide non-discriminatory access to the network. These
safeguards usually require a complicated regulatory oversight to succeed including a skillful and
vigilant regulator. Despite these safeguards, regulating a vertically integrated utility is a tough
28
Section 23 is on Functions on Distribution Utilities
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 79
challenge to even the most skillful regulator because the former has both the incentive and the
ability to circumvent nondiscrimination rules which are against their self-interest, not the least
due to information asymmetry. Thus, vertical separation is the better policy choice in regulatory
jurisdictions with limited administrative capacity.
The challenge of regulating a vertically integrated utility is especially difficult in the Luzon grid
where nearly 70% of electricity demand is supplied by a single distributor, MERALCO. With its
dominance of the grid’s distribution network and electricity supply, the utility can single
handedly influence the entry and profitability of competing generation investments as well as
the end-user price of electricity. MERALCO ceased buying from NPC and defaulted on its
contract obligation when its affiliate generators came on stream in 2003. A compromise
settlement amounting to PhP13 Billion, down from the original disputed amount of PhP30
Billion, was eventually reached by the two parties with the approval of the regulator. But
instead of paying the penalty itself, the regulator allowed MERALCO to pass on and collect the
settlement charge from its customers. 29 A study conducted in 2008 by the University of the
Philippines using an optimization model found that MERALCO had violated its economic
sourcing obligation by sourcing higher priced energy from its affiliates which caused end-user
prices to be PhP 0.62/kWh higher than would have been the case had the utility bought from
non-affiliated generators instead.30
Ex-post de-integration is difficult to achieve because it threatens to harm private stockholders
who can be expected to legally challenge a policy re-direction. Again, this will be particularly
difficult in Luzon because of MERALCO’s affiliation with generating plants. While the Lopez
group has largely divested from MERALCO its place has been taken over by San Miguel Energy
Corporation. SMEC owns 27% of MERALCO and now accounts for nearly 30% of Luzon’s
generating capacity.
29
On appeal from the Office of the Solicitor General, the Court Appeals recently ruled that NPC does not have the authority to enter into a settlement 30
Del Mundo Rowaldo, et al „Analysis of Power Supply Purchases of MERALCO for the Year 2007 and 1
st Quarter of 2008‟
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 80
A policy of vertical separation need not be an all or nothing agenda. Since some distribution
utilities had integrated to generation under the current policy framework; a standstill
agreement may be enforced. That is, distributors need not divest from generating plants that
supply their load requirement provided that: a) no new additional investments will be made; b)
all bilateral power purchase contracts will undergo competitive public tenders; c) economic
sourcing obligation will be strictly complied with; and, d) violation of any one of these conditions
and/or the competition rules will result in forced divestment.
6.1.3 HORIZONTAL SEPARATION OF GENERATION
EPIRA’s Mandate
A policy of horizontal separation of generation was mandated in the EPIRA in order to promote
competition and prevent the abuse of market power. An alternative policy option, i.e., vesting
contracts is not provided in the law.31 Vesting contracts has the advantage of promoting scale
economies while curbing abuse of market power by requiring dominant generators to dedicate
a prescribed portion of their capacity to designated end-users at regulated prices pending the
achievement of effective competition in generation. However, the regulator’s inability to
correctly implement horizontal separation does not bode well for its ability to grapple with the
complexities of vesting contracts. Besides, technological developments in generation have
brought down the minimum efficient scale in generation; e,g., it is exhausted at 300-400 MW in
CCGT plants.
The policy directive for Horizontal separation is provided in Section 45 of the EPIRA. This policy
prohibits the ownership, operation or control by any company or related group of more than
thirty percent of the installed generating capacity of the grid and/or twenty-five percent of the
national installed generating capacity. Rule 11 Section 4(a) of its IRR added IPP Administrators
among those covered by the prohibition and clarified that the prohibition applies either “singly
31
Vesting contracts are bilateral electricity contracts that are imposed by the regulator on large incumbent utilities in order to curb their market power and promote efficiency and competition in the market. With these contracts, the generators are required to sell a specified amount of electricity at a specified price to distribution companies for the benefit of primarily, the captive customers and at times, also to serve a part of the contestable customer demand.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 81
or in combination.” Such restrictions do not apply to PSALM and NPC while their assets are
being privatized.
Related group is defined in Section 45a) as including “a person’s business interests, including its
subsidiaries, affiliates, directors or officers or any of their relatives by consanguinity or affinity,
legitimate or common law, within the fourth civil degree.”32
Rule 11 Section 4 of the IRR prescribes a methodology for crediting the capacity of a generating
facility with different owners or where it is owned, operated or controlled by different persons,
viz:
“(b) The capacity of such facility shall be credited to the entity controlling the
terms and conditions of the prices or quantities of the output of such capacity
sold in the market in cases where different entities own the same Generation
Facility.
In cases where different Persons own, operate or control the same generation
facility, the capacity of such facility shall be credited to the Person controlling the
capacity of the Generation Facility” (underscoring supplied)
Control of the output, i.e., the installed generating capacity is the key determinant of market
power. Either by oversight or by design, the Rules extends the prohibition to a Person/group
that owns, operates or controls the facility but does not control the prices and/or the level of its
output that is sold in the market. This is the situation of the owners and operators of IPP plants
whose capacities are, with few exceptions fully contracted to the NPC. Under the current rules,
they will be credited with capacities that they do not control and will unnecessarily be
prevented from investing in additional generating capacities once they have reached the limit.
This logic appears to have guided the ERC in its implementation of the policy , albeit, one that
violates the law.
Implementation by the Regulator
In 2005, the ERC through Resolution No. 26 Series of 2005 came out with the guidelines for
determining and crediting the installed generating capacity in a grid. The guidelines amend the
32
EPIRA, Section 45a)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 82
law and explain why the ERC has not found any company or group to have violated the limits ;
why the Lopez’ group acquisition of Unified Leyte in 200733 and its subsequent purchase of
Tongonan I and the Palinpinon plants in 2009 were allowed to proceed notwithstanding that
these caused the group to breach the 30% grid limit ; and the San Miguel group’s plans to
invest in more power plants in the Luzon grid.
Section 4 of the ERC guidelines reads:
“Section 4. Crediting of Generating Capacity
In crediting generating capacity of a generation facility in favor of one or more persons or entities, which own, operate, or control such generation facility, the following rules shall be observed:
a. If different entities own the same generation facility, the capacity of such facility shall be credited to the entity controlling the terms and conditions of the prices or quantities of the output sold in the market. b. If an entity owns the generation facility and some other entity or entities operate or exercise control over such facility, pursuant to a maintenance or operating contract, lease, assignment, joint venture agreement , or any other similar arrangement, the capacity of such facility shall be credited to the entity or entities controlling such capacity, to the extent subject of its or their control, and not to the entity owning the generation facility. c. Consistent with the foregoing, in the case of NPC and its independent Power Producers (IPPs), it is the control and not the ownership of the power plants which determines who should be credited with the total capacity under contract as it is NPC that actually controls the quantity (dispatch level) generated from the subject power plants and the price of electricity offered to the market. Thus, NPC will be credited the contracted capacity while the remaining capacity not under contract will be credited to the owner of the plant or the entity exercising control over such remaining capacity, in accordance with the preceding rules.”
Section 4 c) above is inconsistent with the law and its IRR. The language of the latter is such that
the cap separately and equally applies to ownership as well as to the operation or control of the
installed generating capacity. Moreover, Section 4(c) of Rule 4 of the IRR only applies to a
generation facility with different owners or one which is owned, operated or controlled by
separate entities.
33
With the purchase, the Lopez group breached the grid limit
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 83
Based on ERC’s data as of October 4, 2010 the Lopez group at that time owned, operated and
controlled 54.4% of the installed generating capacity in the Visayas grid. 34 Nearly 69% of this or
668 MW represents the installed generating capacity of Unified Leyte that the group acquired
when the government decided to sell its remaining majority stake in PNOC-EDC. While the
capacities of the plants are covered by a PPA contract and controlled by NPC; ownership, control
and operation of the facility is with the Lopez group. The capacities can only be credited to NPC
had the facilities been owned by different entities or had they been owned, operated or
controlled by different persons. Since neither of these conditions applies in this case; the Lopez
group is caught by the general prohibition against ownership, operation or control of more than
30% of the installed generating capacity limit in a grid and more than 25% of the national grid
limit. Had control of the installed generating capacity been the criterion regardless of who owns
and operates the facility, the share of the Lopez group of the grid’s installed generating capacity
in October 2010 would have been reduced to 20.7% in October 2010 and 17% in March 2011.
The remaining capacity owned, operated and controlled by the Lopes group in the Visayas are
those of the Tongonan I, Palinpinon I and II geothermal plants which were previously owned by
NPC and were bought by the group from PSALM in 2009. Unlike Unified Leyte, their capacities
are not under covered by a PPA with NPC. Because of this, ERC correctly credited their
capacities to the Lopez group.
With respect to the IPPs that are now under administration, it is clear from Section 31 of the law
that the management and control of the energy output of the plants will be transferred to the
Administrator. This is confirmed in the IPPA Agreements. For instance, Annex 5 to Section B –
Delivery of Power and Energy of the IPPA Agreement for the Sual Coal Fired Power Plant
between PSALM and San Miguel states that:
“2. The Administrator shall be entitled to the management and control of the Capacity of the Units and shall pay the Monthly Payments in respect of, inter alia, such rights”.
34
ERC „Resolution No 20, Series of 2010: A Resolution Setting the Installed Generating Capacity Per Grid, National Grid and the Market Share Limitations Per Grid and the National Grid for 2010‟, Oct 4, 2010
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 84
Like Unified Leyte, these facilities are exclusively owned, operated and controlled by the IPPs.
However, since their capacities are now controlled by the administrator by virtue of the IPP
Agreement the administrators are caught by the general prohibition against the control of the
installed generating capacity in excess of 30% of the grid total and/or 25% of the national grid.
But as in the case of Unified Leyte, the ERC wrongly credited these capacities to the NPC in line
with Section 4c) of its Resolution No. 26 Series of 2005.
Resolution No. 26 further complicates the determination of a breach by defining installed
generating capacity in a manner that could not have been remotely envisaged in the law.
Section 2 of Resolution 26 acknowledges that the installed generating capacity is its maximum
output or nameplate rating. However, in determining the installed capacity of each plant the
guidelines adjusts the same by netting out: a) permanent reductions; b) temporary reductions
due to plant shut down in the preceding 12 months; and, c) temporary reductions due to
transmission constraint that are expected in the next 12 months from the determination. As a
consequence, the installed generating capacity of each company/related group as well as the
total for each grid as determined by the ERC fluctuates yearly as revealed in a review of its
annual determinations from 2005 to 2010.
These adjustments are not provided in the law where the limitation strictly applies to installed
generating capacity. While the adjustment for permanent reduction or derating may be
reasonable; adjustment for temporary reduction is much more problematic and should never be
allowed. Aside from complicating the determination of a breach, i.e., a company may be in
breach one year and not in the following year; it can be used to circumvent the grid limits and
nullify its objective to prevent the abuse of market power by those who may be inclined to do
so.
ERC’s unilateral adjustments to the installed generating capacity makes it difficult to ascertain
whether or not a company/related group whose share is in the border of 30% is still within the
limit. A case in point is the San Miguel group. Table 26 shows disparate data from ERC, PSALM,
and DOE on installed generating capacities now owned, operated and/controlled by the group.
The group is well within the limit based on ERC’s data but is close to breaching it based on
DOE’s. Note that DOE’s data are based on nameplate rating.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 85
Table 26. Installed Generating Capacities of the San Miguel Group in the Luzon Grid
Plant Installed Generating Capacity (MW)
Status ERC 2010 PSALM DOE
Limay CGCT 603.5 620 620 Owned, operated and controlled
Sual 218 1,000 1,294 IPPA; capacity controlled
Ilijan 36.3 1,200 1,271 IPPA; capacity controlled
San Roque 66 345 345 IPPA; capacity controlled
Total San Miguel 923.8 3,165 3,530
Total Luzon Grid 10,839 NA 11,863
San Miguel share (%) 8.5 NA 29.75 Source: ERC Resolution No. 20 Series of 2005 ; PSALM’s declared capacities of generating plants transferred to administrators; DOE List of Generating Plants in 2009.
The installed capacities in Luzon that are controlled by the Lopez and Aboitiz groups are shown
in
Table 27 Unlike in the San Miguel group’s , there is only a slight difference between the
capacities recorded by the ERC and the DOE. Figure 20 shows that San Miguel has the biggest
capacity from the point of view of control if the IPPA contracted capacity is included in its
capacity credit.
Table 27. Installed Generating Capacities of Lopez and Aboitiz Groups in Luzon Grid
Group/Plant
2010 Installed Generating Capacity (MW) Status
ERC DOE
Lopez Group
Pantabangan-Masiway 112 112 Owned, operated and controlled
Bac-Man 36 150 Owned, operated and controlled
Sta Rita 1,036 1050 Owned, operated and controlled
San Lorenzo 526 500 Owned, operated and controlled
Total Lopez Group 1,710 1,812
% to Luzon 15.77 15.27
Aboitiz Group
Magat HEPP 360 360 Owned,operated and controlled
Tiwi GPP 169.1 275.69 Owned, operated and controlled
Mak-ban GPP 281.25 458.43 Owned, operated and controlled
Ambuklao HEPP 0 75 Owned, operated and controlled
Binga HEPP 100 100 Owned, operated and controlled
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 86
Pagbilao 700 728 IPPA; capacity controlled
Total Aboitiz Group 1,610.35 1,997.12
% Luzon 14.85 16.83
Total Luzon 10,839 11,863
Figure 20. Control of 2010 Installed Generating Capacity, Luzon
6.2 OWNERSHIP
The main policy mandates on ownership are on the privatization of NPC’s assets and IPP
contracts and democratization. While the law did not directly address the ownership of Electric
Cooperatives; that issue will be examined in this study because of its relevance to the question
of incentives and generation investments in the Luzon grid.
6.2.1 PRIVATIZATION OF NPC ASSETS AND IPP CONTRACTS
EPIRA privatized the transmission and generation assets of NPC including its IPP contracts. NPC
is allowed to generate and sell electricity from the unsold generating assets/IPP capacity only
and is prohibited from concluding power purchase contracts with other generators or suppliers.
San Miguel
30%Lopez15%
Aboitiz17%
NPC16%
Others22%
Control of Installed Capacity, Luzon
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 87
It must conclude transition supply contracts with distribution companies which shall be
assignable to its successor generating companies.35
There was no need for a similar policy mandate for distribution utilities which were already
privately owned, with the exception of 2 LGU owned utilities that were subsequently sold to
private investors.
6.2.2 DEMOCRATIZATION
The law limits to at most 25% of the voting shares of stock of a distribution utility that may be
held by Persons, including directors, officers and stockholders and related interests unless the
utility or its controlling shareholders are already listed in the Philippine Stock Exchange (PSE) . It
requires the controlling shareholders of small distribution utilities to list in the PSE within 5
years from the time they acquire ownership or control and mandates generation companies and
distribution utilities to sell to the public at least 15% of their common shares.
Section 28 explains that the 25% limit and the requirement to list are “in compliance with the
constitutional mandate for dispersal of ownership and de-monopolization of public utilities...”.
It does not provide any economic efficiency justification for this intrusion into corporate
structure and control of private companies. The biggest motivator or incentive in private
companies is control. Unless there is compelling evidence that such limitation yields significant
economic efficiencies; a better policy course would be to create vibrant financial markets and to
remove legal and economic barriers to entry into the electric power industry.
Democratization is not a Constitutional mandate. The State is only directed to “encourage
equity participation in public utilities by the general public”.(underscoring supplied)36. As for
monopolies, the Constitution mandates the regulation or prohibition of monopolies when
required by public interest. Generation is no longer a monopoly while transmission and
distribution are regulated natural monopolies. Monopolization, which describes an
35
Sec 67 36
1987 Philippine Constitution, Art XII(11)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 88
action/conduct of a monopolist to exclude potential competitors is covered by the prohibitions
in Section 45 of the law.
6.2.3 OWNERSHIP OF ELECTRIC COOPERATIVES
There are 120 ECs nationwide. Of these, 55 operate in Luzon including 12 off-grid. Their
aggregate electricity sales in 2009 was 5,430,395 MWh or 14.3% of total electricity sales in
Luzon that year with a peak demand of 1,272 MW which was 18% of the grid wide peak.
Because of their predominantly residential and small commercial consumer base, ECs are
expected to continue as retail suppliers to most end-users in these markets even with retail
competition. In Luzon, only 3 ECs (INEC, ISELCO, SORECO) have embedded generating plants
with combined capacities of 8 MW.
ECs are non-profit and non-stock institutions that are exclusively owned by all their consumers.
Their operating, maintenance, capital expenses (equal to 5% of operating revenue in tariff
allowance) and taxes are fully funded by the consumers through the tariffs. Because consumers
provide funding for capital investment and debt service, the tariff does not provide for
depreciation and return on investment.
PSALM’s statements of account as of December 31, 2010 showed 16 Luzon ECs with power bill
payables of more than 60 days; accrued VAT remittances and accumulated interests including
restructured accounts . Except for Batangas II Electric Cooperative (BATELEC-II), all the ECs
experienced negative operating margins in 2010 as reported in NEA’s annual financial statistics.
The average collection efficiency of the Luzon ECs is around 94%. Despite this, 22 on-grid ECs
incurred net losses in 2009 and 17 in 2010. They accounted for 46% and 42% of total energy
purchases of the Luzon ECs in 2009 and 2010, respectively. The on-grid ECs that incurred losses
include 11 of the biggest in terms of yearly electricity sales, i.e.; over 100,000 MWh . Three-
Pampanga II and III and Albay Electric Cooperatives are among those with huge arrears with
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 89
NPC/PSALM and are being closely monitored by NEA. Due to their size, the thirteen are able to
collect annual reinvestment allowance ranging from PhP 30 Million to PhP 79 Million. 37
which rules out lack of investible funds as the cause of their financial difficulties.
Among the policy measures taken by the government to strengthen the ECs since the enactment
of the EPIRA were:
a) Loan Condonation. Section 60 of the EPIRA directed PSALM to assume all
outstanding financial obligations that were incurred by the ECs for rural
electrification. But in exchange, the ERC was directed to reduce their tariffs by an
amount corresponding to the loans condoned over a period of five years. The
reduction ranged from PhP0.25 – PhP0.40/kWh which further strained the ECs’
finances.
b) Investment Management Contracts Scheme (IMC). The program was conceived for
ECs whose operating and financial performance could be turned-around with
management expertise from the private sector but with low investment
requirement. During the long gap between project conceptualization and
implementation however, the financial condition of the eight pilot ECs had
deteriorated to the point of requiring massive capital infusion. Few private investors
were willing to join a scheme that will require them to invest their own capital
without the management control that was retained by the EC Board of Directors. In
the end, two contracts were signed. These collapsed prematurely because of inter-
alia; the contracts strayed from the program’s guiding principles; weak project
oversight by the DOE and resistance from the EC stakeholders. 38
c) New Rate-Setting Methodology. The ERC introduced a new rate setting
methodology in 2009 for on-grid ECs. This would have increased the tariffs of 56 by
as much as 64% and reduced those of rest. The stiff opposition to tariff reduction
moved the ERC to maintain the tariffs of those affected at their old levels. The new
37
NEA „Status of Financial and Technical Operation as of December 31, 2009‟ 38
Based on the program evaluation of a member of this study team who was contracted by the DOE to conduct a third-party review of the IMC.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 90
methodology allows the ECs to collect additional contribution from the members to
fund capital deficiency through existing legal procedures.
d) Option to Convert into Stock Corporations under the SEC or Stock Cooperatives
under the CDA. Only 10 ECs converted to stock cooperatives; 9 of them in Luzon.
None has converted into stock corporations. The poor uptake is partly due to
resistance from the EC management and employees (and even from some NEA
officials/employees); reluctance of some ECs to lose NEA’s authority to discipline
and remove undesirable Board members that would result with conversion to stock
cooperatives and the lack of technical and financial capability of the Cooperative
Development Authority (CDA) to support their operations. ECs that joined the CDA
were mainly motivated by the continuing tax exemption available from membership
that had expired for those with NEA.
These measures do not directly address the possible link between the ECs’ ownership structure
and their operating efficiency. It is generally the case that privately owned firms are more
productively efficient than State Owned Enterprises (SOEs) because of their exclusive focus on
profitability. The Board of Directors appoints and monitors the performance of the managers to
induce them to behave in the owners’ interest. In companies with dispersed ownership such as
public companies, the threat of capital market disciplines such as takeover, regulatory
monitoring of their corporate practices makes up for weaker shareholder control and discourage
costly managerial discretion.
ECs are privately owned by all their consumers. However, they lack the tight control over
management and single-minded focus on profitability that characterizes their PDU counterparts.
Instead, their current ownership and management structures have strong built in disincentives
for productive efficiency, namely: (1) wide ownership dispersal (many consumers do not even
know that they own the utility) without the strict discipline imposed by capital markets ; (2) the
absence of a profit motive; and (3) politicization of the Board of Directors that owe their loyalty
to their political sponsors rather than to the owners that they are supposed to represent.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 91
Two benchmarking studies on the ECs technical efficiency showed efficiency scores that were far
behind the efficient cost frontier. Both studies excluded power cost from the cost drivers and
included the size of the franchise area. Their findings suggest large potential for cost savings by
reducing productive inefficiencies. The first study conducted in 2004 covered 105 ECs.39 With
data on the ECs’ operations from 1990-2002, the study employed Stochastic Frontier Analysis
(SFA) and Data Envelopment Analysis (DEA) to calculate their relative efficiencies. It found that
on average, the ECs were 34% away from the frontier under the SFA and 42% under the DEA.
The second study was conducted in 2006 and employed DEA only with data sets from 2001-
2005.40 It excluded all 21 off-grid ECs and 31 on-grid ECs with incomplete data sets.41 Over half
of the on-grid ECs excluded were in the bottom-half of the efficiency ranking in the first study.
The study recorded a lower average inefficiency score of 19%.
Mitigating the damage on the ECs productive efficiency may require the consolidation of their
ownership to a small group of equity investors – preferably consumers of the EC, whose profit
motive coupled with effective regulatory restraint could induce productive efficiency. The
process will necessarily involve valuation of the business as a going concern; buying out the
existing owners-consumers and registration either as Stock Corporations or Stock Cooperatives.
6.3 LIBERALIZATION AND DEREGULATION
6.3.1 GENERATION AND ELECTRICITY MARKETS
Generation was immediately opened to competition, de-classified as a utility and exempted
from the franchise requirement by the EPIRA. The wholesale and retail electricity markets were
liberalized. A wholesale electricity spot market (WESM) was created: WESM Luzon and WESM
39
Lavado, Rouselle „Benchmarking the Efficiency of Philippine Electric Cooperatives Using Stochastic Frontier Analysis and Data Envelopment Analysis‟, 2004. The study states that 119 ECs were covered but only 105 , 6 of them off-grid are in the data sets. 40
NEA/UPNEC/EC-ASEAN Energy Facility „Performance-Based Regulation for Electric Cooperatives in the Philippines Technical Report 2: Efficiency Benchmarking of Philippine Electric Cooperatives for Performance –Based Regulation‟, 2006 41
Off-grid ECs do not have substations or have small substations only. They were removed to avoid distorting the efficiency results.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 92
Visayas went live in June 2006 and in December 2010 respectively. Retail competition will
commence as soon as prior-conditions are achieved, namely: (a) establishment WESM; (b)
approval of unbundled transmission and distribution wheeling charges; (c) initial
implementation of the cross subsidy removal scheme; (d) privatization of at least 70% of the
total capacity of generating assets of NPC in Luzon and Visayas; and, (e) transfer of the
management and control of at least 70% of the total energy output of power plants under
contract with NPC to the IPP Administrators. All these conditions have been met. Generation
rates and retail supply are to be deregulated when retail competition sets in. These radical
policy reforms were intended to attract private investments in generation, induce competition
and create an efficient domestic electricity market.
The immediate removal of the legal barriers to entry and the operation WESM in 2006 failed to
attract the expected high level of new investments in generation. From 2002 to 2009 only 33
MW from new investments that were committed after the EPIRA was passed were added to the
generating capacity in Luzon; 66.4 MW in the Visayas and none in Mindanao. An additional 600
MW is expected to come on-stream in Luzon by 2013; 671 MW in the Visayas and 100 MW in
Mindanao.
To understand the underinvestment requires an appreciation of the allocation of the risks
associated with large, sunk and long-term investments in power plants in a single buyer
regulated environment and in a liberalized, deregulated environment. In the former, the
customer bears all the risks as in the case of the IPP contracts signed by NPC. In the other, the
risks are internalized and borne by the investor. In order to commit, the investor must have a
sufficient degree of certainty on the recoverability and profitability of such investments. In the
first place, project finance has to be raised and the financiers have to be assured of payment
before extending financing. The collapse of the US wholesale electricity markets in 2001
practically dried up financing for merchant plants without long-term contracts.
Given these altered environment decisions to invest are more than ever based on long–term
fundamentals, market design, market structure and policy support that mitigate such risks; not
on short-term price spikes such as those that occasionally obtain in the spot market. Since
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 93
radical policy reforms especially one attended by a change-over from subsidized government
utilities to privately owned profit maximizing utilities inevitably result in a period of uncertainty
and price increases; credible government commitment to the reforms or at least refusal to slide
back to populist policies and regulatory capacity to deal with the complexities of new market
designs and processes and the problems that these create are critical to the decision to invest.
Unfortunately, these were mostly lacking in the wake of the EPIRA and continue to be so.
Industry participants, consumers and observers alike are dismissive of the regulator’s technical
and administrative capacity and the DOE has mostly conceded to the ERC even in those areas
where it is supposed to lead.42 Concerns over political intervention in regulatory decisions were
raised when the then President ordered the NPC/ERC to cap the PPC of IPP contracts at PhP0.40
less than a year into the EPIRA following consumer protests over increased electricity prices.43
The credibility of the reform process was then undermined by missed timelines for major policy
initiatives laid down in the law, which were unrealistic to start with.
The Spot Market and Generation Adequacy
Under idealized conditions, competitive wholesale electricity markets send out efficient price
signals that attract a mix and amount of new generation investments consistent with reliability
criteria. Experience around the world had shown otherwise. The principal cause appears to be
the “missing money” or net revenue gap, i.e.; the net revenues earned in energy markets over
time fail to cover the capital cost of generating electricity.44 This gap is in turn attributed to, in
order of importance: (a) system operation protocols and behavior of the system operator to
maintain network reliability and prevent network collapse that depress wholesale prices in
times of scarcity or hides the marginal social cost of voltage reduction; (b) inelastic prices caused
by the consumers’ inability to react to changes in the supply and demand balance; and (c) price
caps, must–offer obligations and other regulatory interventions in the market to prevent abuse
42
Based on interviews conducted by a member of the study team for an ADB study on the Philippines‟ regulatory policies in the energy sector 43
NPC‟s unbundled generation rate has 3 components: fuel, PPC and basic charge. IPP contracts were split into PPC – that was capped by the President and amortization of capacity fees which falls under the basic charge. 44
For a discussion of the „missing money‟ problem, refer to Cramton Peter and Steven Stoft „The Convergence of Market Designs for Adequate Generating Capacity, White Paper for California Electricity Oversight Board, March 2006
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 94
of market power.45 Some policy proposals had been advanced by noted international regulatory
experts that in combination, will close the revenue gap and incent new investments.46 These
include: (a) the adjustment of reliability rules and protocols that were a legacy of vertically
integrated utilities to make them consistent with consumer valuation; (b) improved market
design such as raising the price cap; (c) forward energy hedging contracts; and (d) forward
capacity markets. These proposals are difficult to implement and get right. They will not
happen overnight especially not in the Philippines where a liquid and complete capital markets
have yet to come out despite years of effort and with its fragile regulatory institutions.
Physical Contracts and Generation Adequacy
The current supply shortage compels the adoption of solutions that will induce investment in
new generating capacities at the soonest possible time even at the expense of postponing some
of the efficiency gains from liberalizing the electricity markets. Effective competition and
economic efficiency can hardly be expected to materialize with supply shortages even in
liberalized electricity markets, anyway.
Under current conditions, forward power purchase contracts for physical delivery has the most
potential to incent new investments. It minimizes market risk that then allows investors to raise
project finance. ERC Resolution No 21 Series of 2005 [Box No. 2] requires DUs to sign bilateral
supply contracts but fails to specify the quantity to be contracted, the duration of the contract,
when the contract must be entered into and the penalty for non-compliance. Compliance had
been spotty due to these and because the DUs are increasingly averse to being locked in long-
term contracts that are often one-sided in favor of the supplier. In addition, long-delays in the
approval and ex-post arbitrary changes to the contract terms by the regulator alter their
carefully negotiated financial structures and deter prospective investors.
Box No. 2 - Excerpt, ERC Resolution No. 21 Series of 2005
45
Joskow Paul „Competitive Electricity Markets and Investments in New Generating Capacity The New Energy Paradigm‟ Oxford University Press, 2007 46
Ibid
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 95
WHEREAS, to ensure that there will be sufficient supply of electricity in preparation for the
implementation of the wholesale electricity spot market, a bilateral contract should be entered into by
and between the distribution utilities and power suppliers to obtain generation and/or ancillary
services of a given type, quantity, duration, timing and reliability over a contractual term
NOW WHEREFORE, BE IT RESOLVED…. All DUs are hereby directed to enter into future bilateral power
supply contract with power producers to be subjected to a review by the Commission
To incent investment, the requirement for bilateral contracts must:
a) be mandatory;
b) prescribe the duration of the contracts such as say for the next 10 to 15 years;
c) mandate immediate compliance;
d) require 100% coverage of forecast load requirement; and
e) impose stiff penalties for non-compliance.
To capture some of the efficiencies of competition, purchase contracts should be publicly
auctioned instead of negotiated bilaterally between the DU and the supplier. The regulator can
draw-up, with inputs from stakeholders , and prescribe the use of a standard contract that will
protect the interest of both the supplier and buyer in the transaction. The contract shall also
provide for the carve out of a portion of the capacity contracted, e.g., in an amount equal to the
size of the DUs contestable market, from the coverage of the contract without giving rise to
stranded costs when retail competition is declared. The general framework of the auction shall
be akin to the Chilean framework as follows:47
1 Distributors shall be 100% contracted at all times.
2 Contracts shall be for 10-15 years;
47
A detailed description of the Chilean auction framework is provided in Part II of this Study and in Moreno, R et. Al, Auction Approaches of Long-Term Contracts to Ensure Generation Investment in Electricity Markets: Lessons from the Brazilian and Chilean Experiences, Energy Policy (2010), doi:10.1016/j.enpol.2010.05.026
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 96
3 Each distributor shall draw up its own criteria , and auction its own
requirements subject to the approval by the regulator ;
4 Distributors can aggregate and simultaneously auction their requirements;
The advantages of public auction over bilaterally negotiated contracts are:
a) It captures some of the efficiencies of liberalized markets through the process of
competing for the market;
b) Transparency and efficient price discovery;
c) Minimizes regulatory opportunism because price caps per technology are set ex-
ante;
d) Ensures that small buyers can contract efficiently because under the system, the
aggregated load is bidded out by technology instead of by prospective buyer; and
e) Removes self-dealing by integrated utilities by requiring them to auction off all their
requirements .
Retail Competition and Generation Adequacy
Retail competition as directed by the EPIRA shall commence upon the implementation of open
access. Electricity end-users with a monthly average peak demand of at least 1 MW for the
preceding 12 months shall be immediately allowed to choose their supplier; those with 750 kW,
two years after. The threshold shall be subsequently lowered until it reaches the household
demand level.
The 1 MW and 750 kW thresholds appear to be arbitrary. More than this, postponing retail
competition is inevitable under current conditions. First, there cannot be meaningful customer
choice with supply shortage although large industrial customers may have some advantage.
Second, the conditions necessary to facilitate actual entry by competing suppliers and customer
switching , moderate the advantage of incumbents, and for the efficient working of the retail
market are still absent. These conditions were precisely recognized by the ERC as “vital
requirements” prior to declaring retail competition and open access in ERC Resolution No. 3 ,
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 97
Series of 2007 titled “ A Resolution Indicating the Timelines for Full Retail Competition and Open
Access in Luzon”. Paragraph 1 of the Resolution describes these vital requirements as:
“the adequacy and establishment of all necessary in infrastructures including
but not limited to: transmission networks, generation supply and the customer
switching systems, and the promulgation by the ERC of all pertinent rules and
regulations governing Retail Competition and Open Access”.
The conditions necessary to encourage customer switching, facilitate entry of competing
suppliers and the smooth working of the retail market should include:
a) Publication by the ERC of the full list of contestable customers at least 3 years before
retail competition sets in to give new entrants time to market and build new
capacities, where so desired . The lists submitted by the DUs are reportedly covered
by a non-disclosure agreement. The customers came about as a result of the DUs’
monopoly positions; not through their own marketing efforts, hence, problems of
incentive and confidentiality do not arise from the publication of the list. Non-
disclosure impedes entry, maintains the incumbents’ advantage and runs counter to
the law’s objective to create retail competition.;
b) A requirement for DUs to provide their contestable customers with complete energy
information (e.g. hourly meter reading data). These data are not currently provided
by the DUs who inform their customers of their aggregate monthly energy data and
peak demand for the month;
c) Completion by the ERC of the rules and guidelines for the smooth working of the
retail market, such as on:
i. the settlement of imbalances, line rentals, and net settlement surplus
between DUs and Retail Electricity Suppliers (RES);
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 98
ii. the performance of duties and responsibilities of the Philippine
Electricity Market Corporation as the Central Registry Body for Retail
Electricity Supply;
iii. the settlement of disputes for Contestable Customers;
iv. the standards for the metering facilities for Contestable Customers, the
responsibilities and standards of performance of the DU as the meter
service provider therefor, and the rates for such services;
v. amendment of ERC Res. No. 20, series of 2005 to provide for the
imposition of VAT by Retail Electricity Suppliers;
vi. The installation of WESM compliant metering to all Contestable
Customers (capable of tracking energy transactions in each WESM
interval for purposes of billing and for the settlement of imbalances, line
rentals and net settlement surplus); and
vii. The installation of the IT platform for the B2B infrastructure required for
the business processes which ERC prescribed in the rules for Uniform
Business Practices .
The Philippines will not be the first country/jurisdiction to postpone retail competition because
the necessary conditions for it to function particularly inadequate generation, were absent.
Latin American countries followed a much slower pace than that envisioned in the EPIRA and do
not foresee retail competition at the household level.
6.3.2 STRANDED COSTS
Section 32 of the EPIRA allows NPC to recover stranded contract costs and stranded debts and
DUs to recover stranded contract costs through a universal charge on all end-users. Two
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 99
petitions for the recovery of NPC’s stranded costs were submitted by PSALM to the ERC in 2009.
The first petition is for the recovery of stranded debts estimated at PhP 471 Billion over 17 years
at PhP 0.30/kWh. The second is for the recovery of estimated stranded contract costs
amounting to PhP 22.2 Billion over 5 years at a rate of PhP0.0920/kWh. The petitions are still
under review by the ERC. No DU has filed a petition.
As defined in Section 32, NPC’s stranded debts are any amount of its unpaid financial
obligations net of the PhP200 Billion assumed by the government. Stranded contract costs are
the excess of the contracted cost of electricity under NPC’s and the DUs’ IPP contracts that were
approved by December 21, 2000 over their actual selling price in the market. Market refers to
the wholesale electricity spot market (WESM). In 2007, the ERC issued the ‘Rules for Recovery of
NPC Stranded Contract Costs and Stranded Debts Portion of the Universal Charge’.
Outside the Philippines, the term stranded costs refer to those costs incurred by a utility that
were previously recovered under a regulated regime but can no longer be recovered with the
advent of competition and the removal of price controls.48 These costs were approved or
imposed by the regulator in order to improve the service or hold down rates. Since the new
entrants are not burdened by these costs, competition could result in lower prices and/or the
departure of the utility’s wholesale customers for other suppliers offering lower prices. Either of
these developments mean that the utility will not be able to earn enough revenue to recover its
long-term investments and other costs, which are then stranded. Only generation costs are
stranded . Transmission and distribution costs are not because their tariffs remain regulated.
The bulk of stranded costs consists of generation-related assets; long-term contracts for power
or fuel and regulatory assets that regulators would have eventually allowed the utility to recover
through its regulated rates. The latter includes deferred income tax liabilities, deferred
operating expenses, deferred taxes, unamortized debt expenses, and costs associated with
issuing or reacquiring debt. While there is no agreement, stranded costs are either borne by the
utilities’ departing customers, the remaining customers, or by the shareholders. While the
philosophical debate on recovery has not been settled, the idea that some compensation must
48
See for example Baumol William J and J. Gregory Sidak „Stranded Costs‟ Harvard Journal of Law and Public Policy, Vol 18(3) Summer 1995
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 100
be made had gained ground. The arguments for compensation are premised on economic
efficiency, legal and political considerations the latter to the effect that compensation has to be
made to stop powerful losers from impeding efficient policies.
Applying the internationally accepted definition of stranded cost means that:
a) Only NPC’s generation-related costs are strandable and may be recovered.
Transmission debts absorbed by PSALM do not qualify;
b) Costs that were previously disallowed by the regulator cannot be recovered;
c) Only those approved generation costs that are stranded by deregulation or the
removal of price controls may be recovered;
d) Of NPC’s total generation costs; only those debts and contract costs assignable to
enery traded in WESM , i.e., the spot market volume may qualify for stranded cost
recovery. The amount of stranded costs here shall be the difference between the
assignable costs/debts and trading revenue. However, this does not consider the
possibility that losses were caused by a deliberate strategy to bid low even if
NPC/PSALM could have bidded higher, rather than by market forces;
e) Debts and contract costs assignable to capacities/energy traded or sold outside of
WESM cannot claim stranded costs because their prices continue to be regulated by
the ERC. The TOU prices in the TSC were set by the ERC and prices in the bilateral
contracts will continue to be regulated until open access sets in. Losses incurred
from One-Day Power Sales and similar schemes are business losses , not losses from
deregulation and competition;
f) Debts and contract costs assignable to privatized generating assets cannot be
recovered; except those costs stranded in the WESM prior to privatization; and
g) Debts and losses caused by reasons other than deregulation such as politically
mandated reductions in rates and/or subsidies cannot be recovered.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 101
Of the total energy traded by the NPC in 2008, only 22% was spot sales. By proportion, only
around PhP0.02/kWh can be claimed as stranded cost if recovery is phased over 5 years as
proposed by NPC. The data provided by NPC do not permit a similar approximation of the
stranded debts assignable to WESM trades.
NPC’s debts are not stranded debts. Many reasons had been given for these debts among them,
subsidized tariffs, regulatory disapprovals for recovery through the approved tariffs,
management inefficiency including “bad” deals, and losses from NPC’s privatization especially
those involving the Administration of IPP contracts. Recovering these debts from the
consumers is without precedent in countries that had similarly privatized their state-owned
electricity assets.
6.4 CONDUCT REGULATION
6.4.1 RATE SETTING METHODOLOGY FOR TRANSMISSION AND PRIVATE DISTRIBUTION
UTILITIES
Transmission tariffs and those of private distribution utilities (PDU) were set through the cost of
service methodology (locally known as Return on Rate Base (RORB) before the EPIRA. The law
allows ERC to adopt other appropriate or internationally accepted rate-setting methodologies
that ensure a reasonable price of electricity and promotes efficiency. The ERC chose to apply
the Performance Based Rate (PBR) methodology, specifically its CPI-X formula to transmission
and PDU tariffs starting in 2003 and 2005 respectively.
In the CPI-X formula, the efficient cost of the utility is pre-determined. Tariffs are increased by
inflation (CPI) but the increase is abated by efficiency savings (X) which is the calculated cost
reduction during the current period from the preceding period. This methodology is most
appropriate where there is potential for large efficiency gains or productive efficiency unlike
the cost of service methodology which assumes that there is not much scope for efficiency
improvement in historical costs. It relies on financial incentives and disincentives to lower
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 102
costs; improve service; and a more rational allocation of risks and rewards between the utility
and the utility’s customers. Its main characteristics are: 1) the linking of regulated rates to
efficient costs and de-linking them from the individual utility’s cost; 2) the reward/penalty
structure; 3) a longer regulatory lag that incent the utilities to cut costs because savings do not
immediately lead to tariff cuts; 4) performance standards so that service quality is not sacrificed
in the cost-cutting effort. The adoption of this formula abroad especially in the UK led to large
efficiency gains and tariff reductions particularly in the first 10 years.
The new ERC methodology is not PBR, much less its CPI-X variant. It is not also an internationally
accepted methodology. It is still RORB with a twist: costs are based on forecasts instead of
historical costs which justifies the consumers’ complaints that they are now financing the
investments and paying the utilities profits on it too; and for nothing. Not surprisingly, it has
resulted in sustained tariff increases rather than deep tariff cuts that characterized its
introduction abroad.
What separates ERC’s new methodology from the true CPI-X formula are:
a) Unbroken cost-price link. Tariffs for the first regulatory period were based on the
utility’s historical cost and for the subsequent periods, on the utility’s own forecast.
The cost forecasts are upwards, never downwards. In contrast, the recoverable
costs in other regulatory jurisdictions are benchmarked to the efficient cost of a
Reference Utility such as in Brazil ,Chile and in other Latin American countires
and/or derived in combination with benchmarking methodologies such as the DEA
and SFA;
b) ‘X’ does not represent productivity gains. There is no prior determination of the
utility’s efficient cost and productivity targets. Thus the “X” or efficiency factor was
0 in the first year of the first regulatory period and a pure mathematical number
that equates the Present Value (PV) of forecast real revenue to the PV of forecast
nominal revenue, in the succeeding periods;
c) No tariff increase abatement by productivity savings. The automatic yearly rate
increases arising from the application of the inflation factor are not abated;
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 103
d) Short regulatory lag. The regulatory lag is shortened to one year since the utility’s
cost and tariffs are reviewed and adjusted yearly. This should have been a
disincentive but is not, since there is no requirement to cut cost;
e) No performance standards. Performance targets have not been set by the ERC
except for distribution systems loss. The utilities’ performance in the most recent 3
years and their own targets are used instead. The utilities are granted an additional
amount in their approved revenue requirement to be used to achieve these targets
or to pay the corresponding penalties to the consumers.
f) Overly generous valuation of the rate base. The rate base is valued by the Optimized
Replacement Cost Method (ODRC) before the start of each regulatory period and
indexed to inflation within the period. This results in excessive gains to the utilities
especially considering that the return on rate base and depreciation account for
55% to 65% of their revenue requirement. Absolute valuation such as through the
ODRC should be limited to the time before a new rate setting methodology is
applied. Thereafter, the rate base should simply be rolled-forward to the succeeding
regulatory period , adjusted for the value of new investments and indexed to
inflation.
6.4.2 NEW RATE SETTING METHODOLOGY FOR ELECTRIC COOPERATIVES
A new methodology was adopted in 2009 that replaced the cash-flow methodology that was
previously used to set the tariffs of the ECs. As shown in Box No. 3, tariffs are group tariffs and
are neither based on the utility’s own historical nor forecast cost but are derived through a
formula that starts from the average operating revenue requirement of the group where the EC
has been assigned. The new methodology is highly arbitrary and has no precedent in the
Philippines or elsewhere. The ERC is now preparing to again change the methodology to one
that is PBR based. The deficiencies found in the PBR for transmission and the PDUs are also
present in the proposed methodology as observed from its latest draft.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 104
Box No. 3 - New Rate Setting Methodology for Electric Cooperatives
1) Classify ECs into groups according to identified cost drivers,
2) Calculate operating cost per kWh for Distribution, Supply, Metering (DSM) in 2000 by adjusting
each EC’s DSM unbundled DSM in 2000 by the CPI and the average wage increase. Deduct 5% to
net out other revenue income that were included in the 2000 tariff. Set DSM/kWh , the Initial
Standard Tariff (IST) at the median of the groups 2008 operating cost,
3) Calculate Operating Revenue Requirement (ORR) of each group by multiplying the IST by each
group’s 2007 average kWh sale . The derived ORR becomes the basis for calculating the rates per
customer class,
4) Functionalize ORR by using the ratio of each group’s Distribution, Supply and Metering costs to
total cost in 2000,
5) Allocate the functionalized ORR by non-coincident demand for distribution and by the number of
customers for supply and metering
6) Convert the functionalized ORR per customer class to peso.kWh by:
a) Dividing the distribution ORR by the average kWh sales (kW for >240v consumers)
b) Dividing supply revenues vy the average kWh sales (for 220/240v, 10/30 and >240 customers,
divide average number of customers of the group to derive corresponding fixed peso per
customer per month charge)
c) For Residential customer metering charge: first calculate the gross revenue from the
PhP5.00/month metering charge (an arbitrary charge included in the 2000 unbundling
decision) then divide the same by the average kWh sales to arrive at the variable peso/kWh
metering charge. For 220/240v, 10/30 and >240v customers, divide the functionalized
metering per customer class ORR by the average number of customers per month
d) Set the reinvestment fund, i.e. EC consumer-members’ contribution to capital expenditure at
22% of the group’s 2008 median ORR/kWh
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 105
7) Fund capital deficiency with additional contribution of members, to be collected through existing
legal procedures.
Source: ERC ‘Rules for Setting Electric Cooperatives’ Wheeling Rates’ Sept 2009
6.4.3 REGULATION OF NON-PRICE CONDUCT: ERC COMPETITION RULES
Section 45 of the EPIRA directs ERC to formulate rules and regulations to encourage market
development and customer choice and discourage/penalize abuse of market power,
cartelization and any anti-competitive behavior. It specifies that the rules shall define the
relevant markets for purposes of establishing abuse or misuse of monopoly or market position.49
ERC issued the Competition Rules in 2006. The rules cover: 1) prohibited agreements; 2)
prohibition on the misuse of market power ; 3) acquisitions, mergers and consolidations; 4)
clearances and authorizations; 5) disclosure of information; and, 6) penalties. Oddly, it contains
two definitions of ‘market’ as shown below:
“means a market in the Philippines in which electricity or other goods or services
that are directly or indirectly related to or used in connection with the generation,
transmission, distribution or sale of electricity are, or may be, supplied or
acquired” (Definitions)
“ A market includes one in which goods or services, and other goods and
services that are substitutable for, or otherwise competitive with, the first
mentioned goods or services, are or may be supplied or acquired” (Rule 18 (2)
on Interpretation and Application)”50
49
EPIRA Section 45 50
ERC Competition Rules and Complaint Procedures
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 106
The first defines an economic market; not an anti-trust market. The second does embrace the
concept of substitutability, a critical element in market definition, but only refers to the product
market and excludes the geographic market. Section 3 of Rule 18 states that the geographic
area will be considered in determining substitutability but still neglects to define the geographic
market.
Correct market definition is at the heart of competition or anti-trust law. Market power, abuse
of market power, market share and similar competition concepts are all relative to the market.
The Rules also do not clarify these concepts as shown in Box No. 4. As it is, ERC’s Competition
Rules falls short of providing a workable and legally enforceable framework for the evaluation of
anti-competitive conduct. This in turn raises concern over the regulator’s ability to discharge its
responsibility to protect consumers and to create a competitive power market.
Box No. 4 - Excerpt from ERC Competition Rules
Rule 5 – Misuse of Market Power
Section 1. Prohibition. A Person that has a substantial degree of power in a Market shall not misuse
that power. In this Rule, a reference to power is a reference to market power. (NB the Rules does not
define market power)
Section 2. Degree of power; Factors: Without prejudice to the preceding paragraph, a Person is to be
taken to have a substantial degree of power in that Market if:
(a) an Affiliate of a Person has, or two more Affiliates of a Person; or (b) a Person and its Affiliate, or a Person and two or more of its affiliates, together, have a
substantial degree of power in a Market
Section 3. Misuse of power; Factors. In determining whether or not a Person has misused its power in
a Market, the following factors, among others, shall be considered:
(a) that Person would have acted in the way it did, whether or not it had a substantial degree of market power; and
(b) the Person was reasonably justified in using its power in the way it did.
Section 4. Use/Misuse of power; How done. The circumstances in which a Person uses or misuses its
power in a Market may include where that Person:
(a) does an act; or (NB ‘act’ is not described or defined anywhere in the Rules) (b) refuses to do, or intentionally refrains from doing, an act; or (c) makes it known that an act will or will not be done; or (d) refuses to do an act, or to offer to do an act, except on a condition or conditions; or
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 107
(e) makes it known that an act will not be done, except on a condition or conditions; or (f) makes it known that an act will only be done on a condition or conditions.
Source: ERC Competition Rules and Complaint Procedures
6.5 WHOLESALE ELECTRICITY SPOT MARKET
6.5.1 OVERVIEW OF WESM
Objectives and Operating Features
WESM was established to create a fair, transparent and reliable trading environment that will
attract investments and encourage healthy competition that will ultimately lead to cheaper
electricity for all consumers by:
a) Providing incentives for the cost-efficient dispatch of power through an economic merit system while guaranteeing the security and reliability of the power system;
b) Create reliable price signals to assist participants in weighing investment options; and,
c) Provide and maintain a fair and level playing field for suppliers and buyers of electricity.
WESM’s establishment is one of the pre-conditions for open access and retail competition . The
market price in WESM shall be the basis for the determination of the stranded contract cost; i.e.,
the variation between the market price and the contracted price of the quantities transacted in
the market.
Trial Operations Program (TOP) was launched in Luzon in April 2005 and was completed in
December as the last stage of preparation for its commercial operations. A TOP for Visayas was
also launched on October of the same year . Commercial operations in Luzon commenced in
June 26, 2006; in the Visayas, on December 2010.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 108
WESM is a bid-based energy market only that operates as a gross pool.51 Bilateral contract
quantities transacted in the pool can be settled outside the market. Locational Marginal pricing
(LMP) is applied where settlement is based on the marginal value of all electricity produced
and consumed by time and location at all nodes.
Entities directly connected to the grid are not allowed to inject or withdraw without registering
in the WESM.
Participants
As of December 2010, there were 99 direct and indirect trading participants comprising of 30
generators, 45 distribution utilities and 24 bulk users. The National Grid Corporation of the
Philippines (NGCP) is the network service provider and the system operator (SO) at the same
time. It is also the metering service provider pending the designation of the ERC of separate
metering service providers. Ancillary service providers will be registered prior to the start of
trading of reserves in the market.
Governance
a. Regulatory Oversight
Both the DOE and the Energy Regulatory Commission have regulatory oversight of the WESM.
Together with the Philippine Electricity Market Corporation (PEMC), the three form the WESM
Tripartite Committee as a venue for coordination as illustrated in Figure 21.
The DOE was tasked under the EPIRA to establish the WESM and formulate the WESM rules,
together with electric power participants. It was also mandated by EPIRA to form the
autonomous group market operator (AGMO) thru the creation of PEMC to establish, govern
and initially operate the WESM. To date, the DOE continues to facilitate the development of the
market thru its involvement in the WESM – as part of the DOE Steering Committee and the
Philippine Electricity Market Board.
51
The market is technically an exchange, not a pool, in the absence of side payments.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 109
The ERC approves the Price Determination Methodology that sets out the principles for the
pricing of electricity at the spot market, the market fees to recover the cost of administering and
operating WESM, and the administered price determination methodology for pricing of WESM
transactions in times of market suspension and intervention. It also sets the criteria for WESM
membership and the performance standards based on the Grid code. As the industry regulator,
its power and authority extends to the enforcement of the rules and regulations, investigation
and action against any WESM participant that violates any law, rule or regulation and impose
fines and penalties for any non-compliance with or breach of the EPIRA, IRR and rules and
regulations in the market.
Source; WESM
Figure 21. WESM Governance Structure
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 110
b. Market Governance
PEMC was incorporated to perform the functions of the autonomous group market operator
(AGMO) as stated in the EPIRA IRR. It functions as the governance arm of the WESM and is
tasked to handle its initial operations until the appointment of the independent market
operator (IMO).
The PEMC Board together with the various WESM committees perform the governance
functions of the PEMC. During the transition period to the selection of the IMO, the PEM Board
is chaired by the Secretary of the DOE. The Secretary also appoints members of the Board. After
the transition period, the Chairman of the Board will be elected by the independent members,
while members will be elected by PEMC members.
6.5.2 PERFORMANCE HIGHLIGHTS
The ensuing review of the market’s performance is based on the results of the Luzon market
operations from July 2009 to June 2010 (and for the full year 2010 when data allows). This
period is a better indicator that those of prior periods because it was at this time that more
private participants entered the market, thus, loosening the control of NPC/PSALM following
the privatization of NPC generating plants and the transfer of IPP energy outputs to private
administrators. The market highlights are: 52
a) Negligible increase in spot quantity accompanied by substantial increase in spot
market value from 2009 to 2010 (Figure 22);
b) High occurrences of pricing errors due to contingency violation of N-1 contingency
and HVDC related concerns. Real-time prices were applied at 60.2% of the time only
(Figure 23);
52
WESM, „Market Governance Updates‟, 4th WESM Annual Participants‟ Meeting, 12 August
2010
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 111
c) Frequent price substitution (Figure 24 and Figure 25) ;
d) Tight supply condition from the Malampaya shutdown; simultaneous occurrences of
forced and scheduled outages; and capacity gap from low capacity offered (Figure
26);
e) Wide price variability ranging from 0 to negative bids (14.5%) to above 10,000
(10.6%) and clustering at the 0-5000 level (61%) (Figure 27 and Figure 28);
f) Highly concentrated when measured on the basis on the actual generation of major
participants net of bilateral contract quantities; (Figure 29);
g) High risk for the exercise of market power by Pivotal Supplier and Price-Setters with
large uncontracted capacities , e.g. (Pagbilao and Kepco Ilijan) (Figure 30);
Source: PEMC
Figure 22. Market Transactions (2009,2010)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 112
Source: PEMC
Figure 23. Pricing Errors
Source: PEMC
Figure 24. Price Substitution
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 113
Source: PEMC
Figure 25. Supply and Demand Profile (26 June 2009 to 25 June 2010)
Source: PEMC
Figure 26. Monthly Outage Rate By Resource (July 2009-June 2010)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 114
Source: PEMC
Figure 27. Price Distribution (June 2009 to June 2010)
Source: PEMC
Figure 28. Market Price Trend (June 2009 to June 2010)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 115
Source: PEMC
Figure 29. HHI Based on Actual Generation Net of Bilateral
Source: PEMC
Figure 30. Combined Pivotal Supplier-Price Setter Index
6.5.3 ASSESSMENT OF WESM
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 116
The market results paint a disturbing picture of a market that is unlikely to deliver on its
objectives to incent efficient generation investments and create efficient price signals without
radical changes in its current architecture and rules. The assessment of the market will
therefore focus on the required adjustments of its architecture and rules as indicated in the
foregoing market results.
Market Architecture
Market architecture refers to the design of component submarkets. They are anchored on the
market structure and are designed prior to the market rules.
The Philippine electricity market is characterized by: (1) tight supply and demand situation ; (2)
increasing dominance of a few large generating groups; and (3) severe transmission constraints
in many zones/nodes. Its operating environment includes political leaders that are inclined to
intervene in the market to deflect mass opposition to high electricity prices.
The tight supply and demand situation means that uncontracted generators possess a high
degree of market power and can exploit this market power through capacity withholding or
excessive price bids. Among the pivotal suppliers and price setters in 2009-2010; Pagbilao’s
uncontracted capacity were approximately 50% while those of Sta Rita and Ilijan were
approximately at 38%. It is interesting to note that these plants are also controlled by the 2 of
the 3 largest groups: the Lopez and Aboitiz groups , respectively. To manage this, there should
be: (a) as an interim measure, high level physical contracting, say, 100% for loads and
consequently, generators ; and b) in the medium term , the introduction of a long-term financial
forward market (forward, futures, swaps, options) that will curb the exploitation of market
power by generators and shield trading participants from spot price volatility. Pending the
operation of the financial hedging market, the spot market is best designed as a balancing
market only to fulfill the contractual commitments of generators and possibly, distributors as
well. This solution is also likely to scale-down government intervention in the market. A
financial capacity market should be created in the longer term with a corresponding
requirement imposed on distribution utilities and large users to contract for a prescribed
percentage of their peak capacity requirements.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 117
Tight capacity constraints also require the operation of a contract operating reserve market to
maintain system security and reliability and to encourage investments in additional generating
capacity. The pricing of operating reserves is discussed under Market Rules.
Transmission upgrades are critical to relieve transmission congestion. As it is, the market is
characterized by wide price separations among nodes that are only partly managed by the
collection of Settlement Surplus. In the longer term, a sub-market for Transmission Rights (TR)
must be created to manage the trading participants’ exposure to nodal price risks. It can also
do away with Administered Prices, or Price Substitution in cases of transmission congestion.
TRs could be physical or financial (although FTRs classified as options - no payment when the
flow is reversed, are equivalent to physical transmission rights). The market operator (MO) can
periodically auction TRs. Pending the full liquidity of the market, the minimum price of the TRs
can be set by the MO and/or approved by the ERC based on estimates of cost from congestion
and losses.
Market Rules
a) Dispatch Schedule
The current bid-based dispatch schedule is inconsistent with the tight supply situation in the
market. It is a disincentive to generation investments and invites gaming to recover capacity
costs and start-up costs. A cost-based dispatch would have been more appropriate . The current
price distribution in the market shows that many generators are unable to recover their capacity
and start-up costs from their spot transactions . This is likely to result in very high bids in an
attempt to compensate for losses in the spot market. Markets that adopted cost-based dispatch
at the early stages of their operations include Singapore and the PJM . Cost-based dispatch
continues to apply in Chile, Brazil and Argentina.
b) Pricing Errors Notice (PEN) and Market Re-Runs
Real time market outcomes applied 60.2% of the time only. This was attributed mainly to the
high frequency of pricing errors although there were also price substitutions and other
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 118
administered prices imposed by the regulator. When PEN occurs, ex-ante prices are re-run
using ex-post re-run prices. This induces generators to withhold some capacity from the market
because the ex-post prices, by including the must-run units, are almost always lower than the
ex-ante prices. A solution would be to use ex-ante input data instead of the ex-post prices for
the ex-ante re-runs.
c) Must-Run-Units
(i) Dispatch
The planned reserve and energy co-optimization should be implemented without delay. The
current practice of constraining off individual units to provide reserves and interrupting loads to
achieve supply and demand balance could lead to regular under-generation.
(ii) Pricing
Must – Run (MR) contracts are ‘out of market’ arrangements that are necessary for the system
to withstand various contingencies, particularly security and reliability that are beyond the
control of a single generation firm. Must-run generators must therefore be compensated for
their ‘above-market’ costs when they are forced to operate even when the market price is
below their operating costs. These costs include fixed operating costs (that may be scaled
according to contribution to system reliability) ; opportunity cost from foregone energy or
ancillary service revenue; and start-up costs . At the same time, the contract
price/remuneration must be so designed to curb the possible exercise of large market power
held by the units providing the service. This requires that : (1) the opportunity cost not be linked
to market outcomes ; (2) the must-run energy requirements be announced prior to running the
Day-Ahead dispatch schedule; and , (3) Prior to their dispatch as MRU, Must – Run generators
must choose between their declared MR variable compensation or the market price. There
cannot be a “higher of the 2” choice to prevent the MRU from leveraging its market power to
raise prices in the energy or reserve market.
The compensation of MR units have to be formalized in a contract between the SO and the
generators. The contract shall be negotiated and approved by the regulator. It shall contain the
agreed fixed payments regardless of whether or not they are called to run (or scaled down
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 119
according to their contribution) and the generators’ variable compensation when they are called
to run. This variable compensation should at least be equal to the marginal cost of providing the
service.
The current Settlement Procedure of Must Run Units of PEMC53 neither guarantees fixed
payments nor de-link the MRU’s variable compensation to market outcomes. MRUs are paid a
Generation Price Index (GPI) which is simply the average market payment during the relevant
trading interval(s) . Instead of fixed payments, an MRU has to apply for additional
compensation to cover fuel and variable operating and maintenance cost (to include start-up
cost and shut-down costs) if these were not covered in the GPI settlement. Thus, the GPI
settlement could either under compensate or over compensate the MRU its opportunity cost
depending on the market outcome .
d) Regulatory Intervention
(i) Market Intervention and Market Suspension
The WESM Manual on Administered Price Determination Methodology of October 2010
describes the conditions for SO intervention and market suspension by the ERC. Intervention or
suspension occurs when the grid is in extreme state condition arising from: (a) an emergency; (b)
a threat to system security; or, (c) an event of force majeure. It also sets-out the price
determination methodology when market intervention or suspension occurs.
Only the ERC can suspend market operations and when any of the following conditions obtain:
(a) natural calamities; and, (b) declaration of national/international security emergency by the
President. The SO can intervene in the market in an emergency, i.e.; where a situation exists
that has an adverse material effect on electricity supply or which poses as a significant threat to
system security.”54
It is unclear whether prior market suspensions or interventions were mainly motivated by
threats to system security or influenced by high prices. Despite the non-inclusion of “high prices”
53
PEMC „WESM Manual: Management of Must-Run Units” Issue 4, 28 February 2007 54
WESM Rules 6.3.1.1
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 120
as a condition for market intervention, the definition of emergency in clause 6.3.1.1 of the
WESM Rules leaves enough flexibility for the SO and/or ERC to intervene in the market in the
event of high prices. The clause defines emergency as “existence of a situation which has an
adverse material effect on electricity supply or which poses as a significant threat to system
security. The phrase “has an adverse material effect on electricity supply” is ambiguous enough
to allow for such a flexibility. Market suspension or intervention due to high prices curtails real
market price formation that is essential to signal the need for generation investment and dulls
the incentive for such investments. At the very least, the regulatory price cap should be allowed
to work and must be hit in emergency situations caused by insufficient supply. On the other
hand, extra-ordinary price spreads caused by transmission congestion should be addressed by
Transmission Rights instead of market intervention.
Force majeure events are those enumerated in clause 6.7.2 of the WESM Rules: a) major
network trouble that caused partial or system-wide blackout; b) market system hardware or
software failure that makes it impossible to receive or process market offer/bid information or
dispatch the system in accordance with the WESM Rules; and, c) any other event, circumstance
or occurrence in nature of, or similar in effect to any of the foregoing.
(ii) Administered Price Determination
The Administered Price for generators for each generator node shall be the load-weighted
average of the ex-post nodal energy price and metered quantity of the 4 most recent same-day,
same hour trading intervals that have not been administered. In case they were administered,
they will be replaced with prices that have not been administered for the most recent earlier
same or similar day. If prices in these same-day, same hour trading intervals reflect constraint
violation coefficient prices or are subject of a pricing error, the WESM Manual for the
determination of price substitutes for pricing error shall apply.
The base period for determining the settlement amount is too short . An alternative would be
the average of the corresponding prices for the 30 days preceding the market intervention or
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 121
suspension. The methodology for price substitution in cases of pricing errors was previously
addressed.
6.6 SECURITY OF SUPPLY
Security of supply refers to the adequacy of capacity to supply demand and the reliability of
the generation and delivery systems that should result in affordabale rates to end-users55. The
adequacy of supply can be measured in terms of the timely availability of capacity while
reliability is best measured in terms of the risk of interruptions of end-users due to the outages
in the supply (generation) and delivery (transmission and distribution) systems.
The unbundling of generation, transmission, distribution and supply in the restructured power
industry also unbundled the responsibilities for demand forecasting, capacity planning and
project commitment in each sector. The Department of Energy forecasts the demand by Grid
(i.e., Luzon, Visayas and Mindanao Grids) and prepares indicative generation plan in accordance
with the mandate of EPIRA that liberalized the generation sector of the power industry. Unlike
before (i.e., prior to EPIRA) where the National Power Corporation prepared a committed plan,
the private sector is expected to submit to DOE its proposed generation projects with targets or
committed commissioning dates. The Philippine Grid and Distribution Codes prescibe the
forecasting and capacity planning for transmission and distribution networks. The transmission
and distribution utilities prepare the Transmission Development Plan (TDP) and Distribution
Development Plan (DDP), respectively wherein the first five (5) years are committed while those
beyond five years are indicative. From the operational perspective, the transmission company is
mandated by EPIRA to ensure the security of supply (i.e., to ensure that there is adequate
reserve to respond to the outages of generation facilities. The TDP and DDPs are consolidated by
DOE together with the generation plan to form the Power Development Plan.
55
Energy security, according to the International Energy Agency (IEA) is characterized by the energy supply and delivery system that is (a) adequate, (b) Reliable, and (c) affordable. The European Commission defines it as “Uninterrupted physical availability of energy products on the market, at a price which is affordable for all consumers (private and industrial)”
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 122
6.6.1 CAPACITY PLANNING AND PROJECT COMMITMENT
The DOE has a well defined process and timeline in preparing the Power Energy Plan (PEP)
which contains the Power Development Plan (PDP) as mandated by EPIRA (Sec. 37). The PEP
planning process starts in January of each year with the review of the implementation of the
previous year’s plan and in updating policy directions and government commitments. In
February, DOE conducts sectoral planning and coordination meetings internally together with
the attached agencies (i.e., NPC, TRANSCO, PNOC, NEA and PSALM56) to set the key planning
parameters and formulate the initial sectoral simulations. Sectoral public consultations are held
in March to solicit issues and concerns as well as regional and provincial plans. A strategic
planning workshop within the DOE is held in June to present the assessment and draft sectoral
plans/programs with the end-view of resolving conflicting policies. By the first week of July, the
Energy Plan which integrates and harmonize the energy sub-sector assessment, plans and
programs inlcuding supply-demand outlook, investment requirement and legislative agenda is
formulated by DOE. The energy plan is presented within the “Energy Family” and later to the
public for review and comments. The DOE finalizes the Energy Plan by end of July. The final
version of the annual Philippine Enery Plan is submitted to the Office of the President and
Congress on or before September 15.
The planning process for the generation sector assumes that the private sector will respond and
commit to build the generation capacity based on the demand-supply outlook indicated in the
Power Development Plan (PDP). The annual PDP published by DOE since 2001 indicated that
there are enough “committed” generation capacity that will be commissioned to meet the
supply requirements. However, these “commitments” did not translate to actual additional
installed capacity according to the timeline or expected commissioning year. A gap exists
between the generation capacity planning of DOE and the commitment of private generation
developers to build power plants.
Except for a few ECs and PDUs, most of the DUs did not sign bilateral contracts before the
expiration of their TSCs with NPC. Those that signed after a long process of negotiation have
56
Planning documents from DOE indicates that PSALM is considered as an attached agency although by law it is an attached agency to the Department of Finance as it is chaired by the Secretary of DOF
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 123
signed short term (1-3 years) contracts with the new owners of NPC power plants and the IPPAs.
It is also noted that even MERALCO which represent about 70% of the market in Luzon did not
sign new bilateral contracts. Apparently, the Philippine WESM does not really provide an
effective signal to Generators to commit in building power plants for new/additional capacity.
After four (4) years of commercial operation of Luzon WESM that has been indicating the tight
supply situation, there has been no response to the need of the market as no merchant power
plant has been committed by any GENCO. A new capacity which will most likely be added in the
Grid (based on the stage of plant construction) that can be considered as the only real
committed plant by the private sector is covered by long-term contracts, after it was able to
convince small DUs to aggregate their demand.
Based on the contracting and WESM experiences so far, it can be concluded that under the
current capacity planning and project commitment process in the generation sector, the only
modality to ensure the timely availability of new capacity additions is to pursue medium to long-
term (i.e., at least ten years) power supply contracting between GENCOs and DUs.
Unfortunately, the GENCOs perceive the power supply contract approval in ERC as a big risk.
This is evident in the power supply contracts submitted by the DUs to the ERC which include
provisions like “...If the ERC will not approve the Power Supply Agreement, the supplier will not
be obligated to supply...” and “...If the ERC approved a different rates, the Supplier will not be
obligated to supply if the the approved rates will not be financially viable”. The financial closure
with lenders for project financing is now very much dependent on the regulatory approval of
the power supply contracts by the ERC. This issue can be addressed by a government-enabled
and regulator-backed competitive selection process through power supply auctions with a pre-
approved template of power supply contract so that the results of competitive selection process
or auction are not subjected to additional regulatory review.
As to the transmission and distribution sectors, the eventual commitment to build network
capacity is not problematic since the regulatory process assures the investors of recovery and
returns for their investment.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 124
6.6.2 PLANNING METHODOLOGY AND CRITERIA
The other issue in ensuring security of supply is related to the planning methodology and criteria
used by the respective planners in generation, transmission and distribution. It can be gleaned
from the PDPs published by the DOE that it adopted a deterministic methodology in generation
capacity planning. As shown in Figure 31, the capacity reserve requirements correspond to the
Operating Reserve criteria of the transmission utility (NGCP) which is based on the single outage
contingency criteria, a deterministic approach. Billinton57 emphasized the deficiency of the
deterministic approaches and the need for adopting probabilistic methods in reliability risk
assessments of power systems. Hence, the probabilistic methodology are used all over the
world even by developing countries. The deterministic approaches do not provide consistent
risks assessment because of the probabilistic nature of load variations and forced outages of
plant equipment. In addition, the reliability risks are dependent on the number, type and
capacities of the equipment as well as the size of the power system. For example, the U.S. and
European power systems can adequately address the reliability risks even with less than 10%
reserve margin for an expected one loss of load in ten years while the Luzon Grid will require
30% reserve margin for a one loss of load in one year58.
57
R. Billinton, et. al., “Applied Reliability Assessment in Electric Power Systems”, 1991, IEEE Press. 58
R. del Mundo, Development of Models and Methodology for Optimizing Power System Reliability, University of the Philippines Diliman, 1991
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 125
Source: DOE PDP
Figure 31. Generation Capacity Plan of DOE PDP
It must be noted that prior to EPIRA, the National Power Corporation prepared generation plans
that meets the one day per year (1 day/yr) loss-of-load expectation (LOLE also called loss-of-
load probability or LOLP ) reliability criteria in compliance with the government (NEDA) directive
to adopt the results and recommendations of the value of loss-of-load and power system
reliability study59. Thus, DOE appeared to have digressed when the generation planning was
assigned to them as a consequence of the EPIRA reforms.
The operational reliability criteria for the determination of ancillary services is deficient from the
point of view of capacity planning. It does not take into consideration the scheduled
maintenance outages of power plants. Based on the Open Access Transmission Service (OATS)
and the Ancillary Service approved by the ERC for NGCP, the levels of reserve correspond to
frequency regulating (2.8%), spinning or contingency (10.3%) and dispatchable back-up (10.3%)
which totals 23.4% ; the level of required reserve margin in the DOE PDP as shown in Figure 31.
59
U.P. National Engineering Center, “Optimal Power Supply Reliability for the Philippines”, NEDA TDI No. 53, 1991
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 126
The DOE must use a higher reserve level for the reliability criteria. Based on the 1991 study on
the optimal reliability for Luzon Grid when the demand was about 3,000 MW, the 1 day per year
LOLP correspond to 30% reserve margin. By this time (with about 7,000 MW demand), the
reserve margin would correspond to 25-28% reserve margin. It would be best if a Value of Loss-
of-Load (VoLL) study is conducted which is useful in setting the optimal reserve requirement for
capacity planning and in operating reserve planning. In must be noted that the VoLL is also
required under the WESM Rules which unfortunately is still missing since day 1 of the operation
of WESM.
Pagobo and del Mundo60 reported in their study on the application of probabilistic approach to
establishing spinning reserve for the Luzon Grid that the optimal spinning reserve (for year
2007) should have been only 85% of the reserve requirement established using the
deterministic single outage contingency (i.e., 10.3% of the peak demand). There is therfore an
opportunity to reduce the cost of ancillary services if a probabilistic approach is used. The value
of loss of load used by Pagobo and del Mundo is the inflation-adjusted cost of power
interruptions to industrial consumers in Luzon established in 1991 by del Mundo. It is therefore
recommended that the DOE or NGCP conducts an update to the value of loss of load study in
1991. It is further recommended to the NGCP to adopt the probabilistic approach methodology
in the determination of operating reserves. The ERC can require the NGCP to undertake this in
its submission for the approval and inclusion of rates for ancillary service.
6.6.3 PROVISION OF OPERATING RESERVE
The Operating Reserve (Spinning and Stand-by) is included in the Ancillary Services provided by
NGCP as the System Operator (SO) in accordance with the Philippine Grid Code. These reserves
address the security concerns resulting from forced outages of generating units. While it is clear
that NGCP is responsible for the provision of these reserves, the WESM Rules61 provides that it
60
G. Pagobo, “A probabilistic approach in scheduling spinning reserve based on FOR of Generating Units and the Value of Loss of Load”, MSEE Thesis (2009), University of the Philippines *Prof. R. del Mundo served as MS Thesis Adviser] 61
WESM Rules clause 3.3.3.2 specifies that “The System Operator shall arrange for the provision of adequate ancillary services for each region either: (a) By competitive tendering process, administered by the Market Operator, whereby a number of Ancillary Services Providers can provide a particular category
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 127
must be procured either through contracting or spot market to be administered by the Market
Operator (MO). In the meantime that it is not yet adminstered by the MO, the SO sourced it
from NPC and other interested GENCOs. The experience of TRANSCO then and now NGCP in the
provision of operating reserve indicated that the the actual reserve that were provided are less
than the required level approved by ERC. The experience in 2010 is a classic case of this
problem. There were interruptions due to forced outages of some power plants. To address the
problem of deficient Operating Reserve, the ERC must impose corresponding penalty to the
System Operator if the required reserve was not met or provided by the System Operator.
With regards to the administration of the MO for the procurement of the reserve, the Market
Rules, assumes that the market will automatically provide the reserve. To ensure the security of
the Grid, it is necessary to issue a clear policy that will mandate the System Operator to source
the operating reserve through long-term bilateral contracts (say 90% of required reserve) and
source only a limited amount from the spot market (say 10%). This is similar to the mandate of
the DUs to source 10% from WESM for balancing supply and demand purposes because the
security of supply is supposed to be ensured by new capacities resulting from long-term bilateral
contracts for 90% of the demand. The premise of this policy recommendation emanates from
the fact that trading of energy in WESM did not produce new investment for generation
capacity and so it cannot be relied upon for the Operating Reserve. The long-term contract will
provide security while the short-term trading in WESM of the balancing requirement could
achieve lower cost of ancillary service.
6.6.4 REPLACEMENT POWER FOR MAINTENANCE OUTAGE
The replacement power for generating units maintenance (scheduled) outages are not included
in Operating Reserve because EPIRA envisioned that the Wholesale Competition market design
(with WESM) will automatically lead to “Full Requirements” power supply contract (as opposed
of ancillary services; or (b) By negotiating contracts directly with an Ancillary Services Provider who is a Direct WESM Member, where only one Ancillary Services Provider can provide the required ancillary services; or (c) Where applicable, by competitive spot market trading in accordance with clause 3.3.4.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 128
to the (Generaing Plant-contingent PPA).62 Unfortunately, the contracts signed by DUs with
GENCO’s for new generating capacities (e.g., GNPower in Luzon and KEPCO and SALCON in the
Visayas) indicated that the GENCO’s are excuse to supply during plant outages (maintenance or
forced) as well as with some new owners of the privatized NPC plants. There is no security
problem for the forced outages because it is covered by Ancillary Services. However,
maintenance outage allowances in these contracts creates a risk for the DUs as they face either
high market price or even lack of supply for the replacement power. Unfortunately, in the same
contract, the GENCO’s have taken advantage of the market design wherein they can supply from
other power plants or from WESM (at their discretion). This is a clear case of selective
application of contract provisions from “Purchasing Agency or Single Buyer Market” model to
“Wholesale Competition” market model. The power purchase agreement (PPA) of IPPs is
applicable basically to a the Single Buyer market since as the Single Buyer has the portfolio of
power plants to manage forced and maintenance outages. The PPA which is plant-contingent
contract does not work to multiple-buyer market. This may apply to MERALCO because it is
virtually a Single Buyer in Luzon because of its market share. But this will definitely not work in
the context of small private DUs and Electric Cooperatives. The DOE or ERC must issue a policy
directive or rules and regulation that power supply contracting under EPIRA shall be “Full
Requirements” contracts and “Plant-Contingent” contracts are not allowed.
62 “Full Requirements” contracts obliged the seller (GENCO) to supply 24/7 the buyer (DUs) in
accordance with the agreed demand specified in the contract. The seller is not obliged to supply its customers from its generating plants. Plant-Contingent Power Purchase Agreements (PPA) of IPPs obliged the seller to supply only from the seller‟s Power Plants. Hence, they are excuse during maintenance outages.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 129
7 ASSESSMENT OF INSTITUTIONAL GOVERNANCE FRAMEWORK The preceding review of the achievements of the EPIRA and the assessment of industry
regulation do not paint a flattering picture of the state of the industry’s regulatory governance.
The core contents of regulatory governance are: (1) the objectives and functions of regulation ;
and, (2) the specific institutional framework or the design aspect of regulation. The first was
reviewed in Sections 2 and 3 of this report. This part will assess the second.
7.1 OVERVIEW OF INSTITUTIONAL GOVERNANCE
The immediate institutional governance framework of the Philippine electric power industry
comprise of: (1) the ERC, as the regulator; (2) the DOE , as the policy body; and (3) Congress
through the Joint Congressional Power Commission as the oversight body. Decisions of the ERC
can only be appealed to the Court of Appeals and ultimately, to the Supreme Court. This
structure is presented in Figure 32 below.
Figure 32. Governance Structure of the Philippine Electric Power Industry
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 130
7.2 APPRAISAL OF INSTITUTIONAL GOVERNANCE
The study applies the criteria developed by Stern and Holder for the assessment of the
performance of regulatory systems in the developing countries in Asia.63 The criteria include:
a) Clarity of Roles and Objectives;
b) Autonomy;
c) Participation;
d) Accountability;
e) Transparency; and
f) Predictability.
7.2.1 CLARITY OF ROLES AND OBJECTIVES
This refers specifically to the clarity of the roles and responsibilities between the policy making
and regulatory agencies. Clarity is essential to enhance accountability and predictability in the
regulatory process.
The EPIRA clearly delineates the roles of the DOE and ERC. The latter has exclusive authority
over rates and as detailed in Section (43) has principal responsibility for consumer protection by
promoting competition; encouraging market development; ensuring customer choice and by
penalizing abuse of market power . The DOE is mandated to ensure the proper implementation
of the EPIRA. In addition, Section (37) mandates it to:
a) Ensure the reliability, quality and security of electric power supply;
b) Facilitate /encourage reforms in the structure and operations of distribution utilities;
c) Develop policies and, where appropriate, promote a system of incentives for
adequate and reliable electric supply including reserve requirements;
63
Stern John and Holder Stuart “Regulatory Governance: Criteria for Assessing the Performance of Regulatory Systems, An Application to Infrastructure in Developing Countries of Asia”, May 1999
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 131
d) Establish the WESM;
e) Develop policies and programs for energy efficiency;
f) Formulate and implement programs for the development and commercialization of
non-conventional energy systems;
g) Encourage private sector investment in the electricity sector; and
h) Promote the development of indigenous and renewable energy sources.64
The DOE Secretary is also directly responsible for total electrification as Chair of the National
Electrification Administration.
Notwithstanding the clear delineation in the EPIRA, the DOE largely relinquished its role, leaving
most matters in the hands of the industry participants and to the ERC. The associated
consequence was that the ERC did not have much policy guidance for its regulatory decisions
and attempted to fill the void by regulation. A specific example is the adoption of the new rate
setting methodology for the ECs. The new methodology is an attempt to address the chronic
financial instability of the ECs in the absence of effective DOE policy initiatives to stabilize their
financial situation. With respect to the encouragement of private sector investments; the
Department has not gone beyond the customary investment missions and fiscal incentives when
it could have initiated an in-depth examination that could have led to the identification of
weaknesses in the contracting process as a disincentive to investments. The DOE points to a
number of factors as being constraints on its ability to effectively perform its responsibilities
under the EPIRA.65 These factors include the ERC’s insistence on its independence which
constraints the DOE from taking the initiative to design policy and undertake programs to
address the industry’s problems; (a view, incidentally, shared by many in the industry), limited
in-house capability (based in large part on its lack of funds to hire additional staff) and the
reported lack of police power to enforce its decision to undertake non-price regulation that are
64
EPIRA, Section 37 65
Based on interviews by a member of the study team with DOE officials for a prior ADB study
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 132
outside the ERC’s authority notwithstanding Section 37 (p) and (q) that explicitly vest the
Department with such powers.66
7.2.2 AUTONOMY
This pertains to autonomy from political interference and equally importantly, to security of
tenure and financial autonomy. The ERC does not enjoy financial autonomy because its budget
must be approved by Congress through the regular budgetary process. Almost 65% of its budget
are for salary and personnel expenses. This does not leave much for staff training and to raise
salaries to the level of the regulated utilities’ to attract high quality staff and reduce employee
turn-over. Instead, the agency is dependent on external consultants that are mostly packaged
with the technical assistance provided by bilateral and multilateral agencies. The annual
appropriation may be augmented if its collection from supervisory, licensing and other fees
exceed its revenue target that is set by the government; e.g.; at PhP300 Million for 2009. This
process has resulted in a perverse incentive to collect varied and increasing fees from industry
participants that are eventually passed on to the consumers.
The ERC is an independent body that is legally free from government interference. The
Commissioners have security of tenure. The prevailing opinion is that it has taken its
independence to the extreme, i.e.; in a manner that precludes coordination with other
executive agencies and meaningful consultations with industry stakeholders.
7.2.3 PARTICIPATION
Meaningful participation by all stakeholders is required to improve the quality of regulatory
decisions and to increase the likelihood of support from the regulated entities, consumers and
the general public. The ERC’s process achieves the opposite effect and is costly to both the
utilities and the consumers. It is a litigious/rule making approach that requires petitioners and
oppositors to hire lawyers; limits the participants to petitioners, accredited oppositors and
66 Sections 37 (p) and (q) authorizes the Department to “formulate such rules and regulations as may be necessary to implement the objectives of this Act” and “exercise such other powers as may be necessary or incidental to attain the objectives of this Act”.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 133
intervenors; and, limit itself to considering the ‘facts’ of the case and avoids the consultative
and iterative approach adopted in other jurisdictions (e.g. UK, Australia, UK) where debates are
encouraged and a broad range of comments are invited and heard. The ERC claims that its
process is called for by the quasi-judicial nature of its decisions notwithstanding that other
quasi-judicial entities in the country and in the United States (from where the process was
borrowed) undertake wide ranging and non-legal consultations . Aside from being the result of
the regulator’s narrow interpretation of the quasi-judicial process, the litigious process could
be a reflection of its limited capacity to undertake comprehensive economic and technical
evaluations to support its decisions.
7.2.4 ACCOUNTABILITY
Accountability depends on the availability of an effective mechanism to challenge regulatory
decisions. The current appeal mechanism – where appeals could be decided by the ERC and/or
the courts anywhere from 1 to 5 years does not induce accountability.
7.2.5 TRANSPARENCY
A transparent regulatory framework requires the regulator to explain and justify its decisions
and processes in a manner that leads to a clear understanding by all participants of the rules of
the game.
Section 21 of the EPIRA on Reportorial Requirements requires the DOE to submit to the Joint
Congressional Power Commission (JCPC) a semi-annual report on the law’s implementation.
The ERC’s report to the DOE is submitted to and integrated by the DOE in this report. The final
report is published in the DOE website.
The ERC also prepares an Annual Report that is published on its website. The Annual Report and
the report to the JCPC detail its accomplishments in the past year and the related pending issues
concerning its ongoing work. Feedbacks to the DOE and ERC reports are seldom received from
the JCPC.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 134
The ERC’s decision-making process is fairly transparent as the regulator regularly publishes on its
website its rules and decisions with their corresponding reasons. However, stakeholders,
particularly consumers, complain that the attachments to rate applications that provide the
basis for the rate petitions are not published in the website and are not easily accessible at the
ERC contrary to the latter’s claim that they can be easily reproduced for a fee. Even the utilities
complain that they are not given access to the ERC’s computations/calculations that form the
basis of the rate decisions and adjustments in the terms of the power supply contracts that are
submitted for approval.
7.2.6 PREDICTABILITY
A predictable regulatory framework precludes regulatory opportunism and/or sudden changes
in the over-all legal framework. It does not necessarily mean being welded to set legal
precedents to the exclusion of unique economic and technical factors attendant to a case.
Industry stakeholders and observers claim that ERC decisions are either too predictable or too
unpredictable. Decisions on tariffs, capital expenditure and similar issues are criticised for
failing to take into account differences in operating situations of the utilities. For instance,
stakeholders observed that the ERC appears to have a pro-forma decision where only the
numbers and the name of the utility are changed (and, in one or two rate decisions, it even
neglected to change the name). On the opposite end, generators and distribution utilities
cannot predict how the ERC will rule on their power supply contracts. It was also observed that
the decisions and/or rules are rarely accompanied by considerations/evaluations of their
economic, financial and technical merits.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 135
III ANALYSIS OF INTERNATIONAL MARKETS
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 136
8 PURPOSE OF ANALYSIS OF COMPARABLE INTERNATIONAL
MARKET
The analysis of international markets is intended to enrich the study by providing a model for
the design of policy reform and empirical evidence for or against certain policies under
reasonably comparable circumstances. To that end, the study analyzes the experiences of Chile
and Brazil with respect to the:
a) Characteristics and issues of the industry prior to reform;
b) Institutional framework including legacy economic policies and political structure;
c) Approach to and design of the reform;
d) Key elements of the reform process as regards to incentives and governance;
e) Defining features and characteristics or best practices; and
f) Policies to address specific issues relating to generation investments.
Aside from having the longest running and most comprehensive electricity reform after WWII,
Chile’s reforms which started in 1982 are widely acknowledged to be highly successful and a
model for developing countries around the world. Chile has been in the forefront of innovation
in the creation of electricity markets. Brazil on the other hand has the largest electricity market
in South America. Capacity addition had lagged behind demand growth before the reforms.
These two countries have the highest access rates in Latin America. From a policy and regulatory
perspective, it is helpful to have a good understanding of how their energy sector copes with
such an increase in demand. While Chile’s electricity system shows that effective competition
and privatization is possible in a relatively small market, Brazil’s illustrate that it is possible in a
large developing market. Their combined experiences and lessons learned are highly instructive
for developing countries like the Philippines that are still grappling with electricity reforms.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 137
9 CHILE’S ELECTRIC POWER INDUSTRY
9.1 OVERVIEW OF ELECTRIC POWER INDUSTRY OF CHILE
Chile’s power sector is organized in four (4) grid systems, namely:
a) Sistema Interconectado Central (SIC), the Central Grid, which serves over 90% of the
population and covers more than 40% of the country’s area;
b) Sistema Interconectado Norte Grande (SING), the Northern Grid, which is mainly
thermoelectric and serves mostly the mining industry in the region that accounts for 98%
of the system’s demand ;
c) Aysén and Magallanes Grids, which are both located in the extreme south of the country
and serve the remote areas. The combined capacity of both grids represents about 1%
of Chile’s total generation capacity .
The power sector consists of four private players that interact in the supply chain: Generation,
Transmission, Distribution Companies, and Clients. Generation companies produce the energy
using different sources (hydroelectric, coal, gas, diesel, wind ) that are sold to distribution
companies and non-regulated clients or consumer with consumption greater than 2,000 kW.
Regulated clients are obliged to buy electricity from a distribution company while non-regulated
clients can buy power and energy from any generation or distribution company.
The structure of the installed capacity is shown in Figure 33. The hydro capacity is very variable
due to periodic draughts. During very wet years such as in 2002, the energy supplied reaches
53% of the national load. During dry years such as in 1999 , it supplies only about 36% . The
generation profile per technology is shown in Figure 34.
An independent entity, the Economic Dispatching Center (CDEC) coordinates the operation of
the systems. CDEC ensures the efficiency, security and sufficiency of the power supply in
compliance with applicable regulations. It also calculates the payments between generation,
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 138
transmission and distribution companies. Its board is composed of the representatives of the
generation and transmission companies and non-regulated clients.
Figure 35 illustrates the structure of the Chilean electrical market.
SIST
EMA
INTE
RC
ON
ECTA
DO
CEN
TRA
L
SIST
EMA
IN
TER
CO
NEC
TAD
O
DEL
NO
RTE
GR
AN
DE
AM
BO
S SI
STEM
AS
(SIC
+ S
ING
I)
0%
10%
20%
30%
40%
50%
60%
70%
80%
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 (*)
Part
icip
ació
n de
l tot
al g
ener
ado
Ener
gía
gene
rada
(G
Wh)
EMBALSE PASADA GAS
GNL CARBON-PETCOKE CARBON
DESECHOS DIESEL FUEL
DIESEL-FUEL EOLICA Participación Carbón
Participación Hidroeléctrico Participación Gas Natural Participación Diesel
0%
10%
20%
30%
40%
50%
60%
70%
80%
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 (*)
Part
icip
ació
n de
l tot
al g
ene
rado
Ener
gía
gene
rada
(G
Wh)
EMBALSE PASADA GAS GNL
CARBON-PETCOKE CARBON DESECHOS DIESEL
FUEL DIESEL-FUEL EOLICA Participación Carbón
Participación Gas Natural Participación Diesel
0%
10%
20%
30%
40%
50%
60%
0
10,000
20,000
30,000
40,000
50,000
60,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 (*)
Part
icip
ació
n de
l tot
al g
ener
ado
Ener
gía
gene
rada
(G
Wh)
EMBALSE PASADA GAS
GNL CARBON-PETCOKE CARBON
DESECHOS DIESEL FUEL
DIESEL-FUEL EOLICA Participación Carbón
Participación Hidroeléctrico Participación Gas Natural Participación Diesel
Legend Gas Natural- Natural Gas
Carbón – Coal
Biomasa - Biomass
Eólica – Wind Power
Embalse – Hydro (reservoir)
Pasada- Hydro (run of the river)
Derivados del Petroleo – Oil Derivatives
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 139
Source: CNE
Figure 33. Energy Production in the Chilean National Grids
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 140
Figure 34. Generation Profile Per Technology in Chile
Pasada13 MW
0.4%
Carbón1,138 MW
31.8%
Gas Natural2,074 MW
58.0% Diesel131 MW
3.7%
Derivados del Petroleo217 MW
6.1%
CAPACIDAD INSTALADA SING
Pasada1,592 MW
10.8%
Embase3,706 MW
25.2%
Eólica81 MW
0.6%
Biomasa
58 MW0.4%
Carbón2,137 MW
14.5%
Gas Natural5,050 MW
34.3%
Diesel
1,707 MW11.6%
Derivados del Petroleo389 MW
2.6%
CAPACIDAD INSTALADA TOTAL
Pasada1,580 MW
14.2%
Embase3,706 MW
33.2%
Eólica81 MW
0.7%
Biomasa58 MW
0.5% Carbón
999 MW9.0%
Gas Natural2,976 MW
26.7%
Diesel
1,576 MW14.1%
Derivados del Petroleo172 MW
1.5%
CAPACIDAD INSTALADA SIC
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 141
Figure 35. Chilean Electricity Market Structure
9.2 INDUSTRY RESTRUCTURING AND POLICY REFORMS
9.2.1 KEY ISSUES PRIOR TO REFORM
The difficulty of securing project financing in the 1930s caused the industry to stagnate. The
government took up the slack left by weak private sector interest and eventually ended up
controlling the industry by the 1970s. A non-adjustable pricing scheme was established. The
resulting prices did not cover operating costs much less the capital costs of the investments. The
losses of the vertically integrated electricity companies were simply absorbed by the State.
Tariffs were eventually allowed to rise between 1974 and 1980. This stabilized the financial
situation of the State companies but was by itself insufficient to solve the problems that plagued
the industry; namely:
a) Inefficiency. Being state companies, their structures were large, complex and
somehow difficult to control. The investments were planned according to technical
criteria that often neglected economic considerations;
b) Flawed Pricing Policy. Tariffs were not based on the efficient cost of delivering the
service but on actual cost incurred by the utilities. The lack of a standard and
uniform rate setting methodology led to differential pricing among the utilities and
discrimination among client categories. High inflation in the seventies resulted in
Transferencias aCosto Marginal
Empresa
Distribuidora
Empresa
Distribuidora
ClienteLibre
ClienteLibre
Cliente ClienteCliente Cliente
G G
CDEC
Marginal Cost Transfers
Distribution
Company
Distribution
Company
Free
clientFree
client
Free client FreeClientRegulated Client
Node Price
Node price
Free price
Node Price
SPOT MARKET
Zona
Concesión
Free
PriceFree
Price
Regulated Client
Node Price
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 142
tariffs that were far below the amounts needed to recover investments. The Tariff
Commission progressively lost its influence over the tariff setting process and the
task of conducting pricing studies was eventually taken over by the National
Commission on Energy.
c) Huge Financial Drain on the State Coffers. By 1979, the State owned 90% of
generation, 100% of transmission and 80% of distribution. The losses incurred by
the State-owned power companies meant that minimal funds were left to maintain
and provide quality service to the industry’s customers.
9.2.2 INSTITUTIONAL BACKGROUND , KEY OBJECTIVES AND ELEMENTS OF THE
REFORM
Reforms were started in 1982 and carried out in a dictatorial regime thus limiting consultation
and opposition from affected stakeholders such as the remaining private operators, prospective
investors and consumers.
The principal reform objective was to privatize the industry. The process was strongly influenced
by the prevailing market ideology of the University of Chicago whose disciples were the prime
mover of the reform process. The reform succeeded in creating a vibrant private industry but
left lingering structural and institutional weaknesses that remain to be addressed.
Those weaknesses are partly explained by the origins of the reform, such as the decisions on
privatization as well as price risks that mainly represent the national electrical system. The
energy price risk is directly related to the highly varying hydrology. Frequent droughts also
caused huge increases in marginal costs due to the need to replace the hydro power with high-
cost generators such as diesel.
One major factor to consider in the privatization effort is the presence of ENDESA, the largest
generating company of the system plus the water rights that were granted to it. This company
also has ownership links to one of the biggest distributors in the country. A really powerful
entity was created against whom others, particularly new entrants were at a competitive
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 143
disadvantage. Due to the importance and size of ENDESA, it is very difficult to legislate on
topics that could go so far as to harm it.
The General Law of Electric Services that was passed in 1982 unbundled and privatized the
industry. The law introduced a liberalized market in generation and third-party access to the
transmission network, setting up a system operator to coordinate the operations of competitive
generators. The privatization process began in the 80s and was completed in 1998 when the last
state-owned utility was privatized.
From the beginnings of the reform, the main investment incentive element has been the
establishment of prices that reflect the true costs of providing the service. This was
complemented by the provision of a transparent and stable regulatory framework for the
industry.
The regulatory commission, National Commission of Energy (CNE) that was created in 1978 was
charged with the development of a regulatory environment conducive to the efficient
development of the industry and to prepare for its privatization. CNE was provided with wide
government support. Its managing board is comprised of 7 of the 21 state ministers, namely: the
Secretary of Defense, of Treasury, of Economy, of Planning,, of Mining, the Presidency
Spokesman and the presiding minister of the board who is a member of the armed forces.
9.2.3 POLICY AND REGULATION OF GENERATION
The policy and regulatory framework for generation are contained in two laws, as follows:
a) General Electric Services Law or DFL N°4 from 2004, LGSE (for its Spanish
acronym); and
b) ERNC Law or Law N°20257 which requires that 10% of consumed energy comes
from renewable sources.
DFL N°4 Law grants private generators complete freedom in their investment and marketing
decisions within the pre-established rules. Any generator with more than 9 MW of installed
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 144
capacity has the right to access the Energy Spot Market and can buy and sell energy regardless
of its installed generating capacity. There is no electricity broker in Chile’s electric power
market.
Generation companies have two kinds of incomes for its business: Capacity Payment and Energy
Income.
The capacity payment is calculated on a monthly basis (US$/kW/month) as the base payment
plus the fixed operation costs of a reference gas turbine. This payment is calculated by CNE and
applies to the firm power available from a unit to cover the 8 peak load hours of the winter
period. The winter period goes from April 1st to September 30th. The capacity to be considered
for capacity payments is calculated taking into account the availability of each unit:
a) For hydro units, it considers the power they are able to supply during 8 hours per
day in the winter period of the driest hydrologic condition registered in the past 40
years. As a result of this calculation, the capacity finally paid (firm capacity) varies
between 50% and 70% of the installed power for these types of units;
b) For thermal units, calculation takes into account typical unavailability values. The
capacity paid (firm capacity) varies between 70% and 85% of the installed power;
c) Thereafter, each calculated firm capacity is adjusted by a unique coefficient in a
way that the sum of all the firm capacities will be equal to the peak load forecasted
for the year. These calculations are performed ex ante, at the beginning of every
year by CDEC, therefore the firm power of each unit is independent of its real
production during the year;
d) The power withdrawn by the generators in the peak load period to meet their
contracts is compared with the firm power of its units. If there is a deficit, the
generator is seen as a buyer of this power in the spot market in that year and has to
pay the power deficit in 12 monthly payments. If the generator had surplus power,
then it is considered as a power seller in the spot market and receives every month
the appropriate payment. The balance of purchases and sales of firm power is
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 145
performed at the beginning of the year based on estimations of its withdrawals at
the peak load hours. This balance is recalculated once the peak load has happened
and then a re-settlement is performed;
The Energy incomes come from different sources:
a) Energy sales to the Spot Market;
b) Energy sales to distributors companies through open and competitive bids;
c) Energy sales to non-regulated costumers, by means of freely established contracts for consumers with demand over 2000 kW; and
d) Energy sales by means of freely established contracts with others generation companies;
Energy Sales to the Spot Market
The Spot market operates as a balancing market for generators only. Distribution companies
and non-regulated costumers do not have access to the Spot Market and can only buy energy
through supply contracts.
Generators are allowed to sell their uncontracted capacities and to buy for their contracted
commitments. The spot market price or the hourly marginal cost are the variable costs of the
most expensive unit in operation. In the event of energy shortage or rationing, the marginal cost
becomes the default cost of the system.
The market is operated by the Economic Dispatch Centers (CDECs). Each CDEC plans the
operation of their respective systems in the medium and short term; draws up the real time
dispatch schedule of the generating units; determines the system’s marginal cost and makes up
the payments between generators companies.
The generation units’ dispatch are centrally planned by each CDEC using optimization models to
get the lowest operational cost of the system subject to security and quality of service
restrictions. Each hydroelectricity generator informs the CDEC of the dam levels and tributary to
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 146
its run by the river plants. Thermoelectric generators are required to report their operating
costs. The reported costs could be audited by the CDEC. The CDEC calculates weekly or at any
time that it is necessary, the value of water levels at the dam and determines the hourly
dispatch for the following day and by block for the incoming week. It then determines the hourly
energy Spot Price of the system or the system marginal price (SMP) and calculates the energy
transfers between generators that is valued at the Spot Price. The pay settlements are made
directly between the generation companies without the intervention of the CDECs. Generators
are paid only when they are dispatched. Payments represent the difference between energy
withdrawn for the generators’ contract commitments and the energy sold to the market.
Energy sales to distribution companies
Distribution companies must contract for the requirements of the regulated market, i.e. those
with demand lower than 2000 kW. The energy tariff for this market was historically regulated
and fixed at the node price. However since 2010, the energy and power prices had been
determined by auction where the distribution companies bid the required supply for their
regulated customers’ consumption. The tenders are public, open, non-discriminatory,
transparent and are supervised by the regulator, CNE, the Fuel and Electricity Superentindence –
SEC and the Economic Prosecutor.
The main characteristics of the auction are:
a) The bidding terms are developed by the distribution companies subject to the
approval of the CNE. The quality and safety conditions of service will be unique to all
the bidders who can offer special qualities of service or additional benefits in the
provision of energy tendered;
b) The contract duration must be specified in the bidding document and shall not
exceed 15 years. Offers of supply for periods less than or greater than those
indicated in the bid terms are not accepted. CNE prescribes the maximum amount
of energy that a distributor can contract in each contract and the maximum amount
to be contracted per year.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 147
c) While bidders can bid any price, contract prices are capped at the current node
price plus 20%. If the bid fails, a rebidding can be held 30 days later at which time
the CNE may authorize an increase of up to 15% of the price cap. The node price is
the price at the date of the tender.
d) The bidder should show the change from their base bid price from the application
of the price indices. The indexing mechanism should reflect the variation of the
investment cost of the generating units. The allowable indices are pre-defined and
are common to all bidders. Bidders are free to assign the weight factors for each
index in their bids;
e) The contract is awarded to the bidder offering the lowest price of energy;
f) Prices obtained in the bids are established through a decree that contains the basic
price and the indices for the duration of the contract;
g) The indexed bid price is passed on by distributor to its final customers. The pass-
through price of each distribution company cannot be higher or lower than the
average price of all contracts in force ±5%; and
h) In the event that a vendor submits an average price that exceeds the 5% limit, the
average price of the distributor is adjusted downwards to this limit. The difference
in revenue generated by the adjustment will be prorated among all regulated
customers in the distribution systems. The resulting reassessments will be settled
between the distributors.
Energy sales to non-regulated costumers
Sales to customers with more than 2000 kW of demand are not subject to price controls.
Generally, clients with less than 20 MW demand are still supplied by distribution companies.
The competition for non-regulated customers is tough.
The prices for non-regulated customers were previously lower than regulated prices. This
changed in the last 4 years because of higher spot market prices that were passed on by the
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 148
generation and distribution companies to their non-regulated costumers. This pass through
system will be allowed until 2013 when the prices in the Power Purchase Agreements will be
actualized with the variations of coal prices and CPI, among others.
Energy sales to other generation companies
Generation companies contract with other generators to mitigate their risks. For example, a
generation company with a high hydro percentage in its generation mix and a high contract
volume could enter into a contract with a thermoelectric generator for back-up capacity in order
to reduce its costs in the event of non-favorable hydrological conditions such as drought.
Contracts between generators are expected to increase with the passage of the Non
conventional Renewable Energy (ERNC) Law in 2010 . Non-RE generators are expected to
contract for the 10% RE obligation mandated by the law.
Policy and Regulatory Incentives for Generation
The CNE prepares an indicative plan for generation expansion for the next ten years. This plan is
critical to new generation investments because the inclusion of a proposed power generation
project facilitates the obtaining of the project finance. This plan was the reference point for the
calculation of node prices prior to the adoption of the auction system for supply contracts.
A specific investment incentive mechanism that was in place since the beginning of the reform
until the year 2004 was the “failure cost”. This was the price for the energy transfers between
generators in cases where the installed generation capacity was insufficient to supply the total
demand of the system and was fixed by the regulator. This mechanism was intended to
incentivize generation adequacy by equating prices to the scarcity cost or its economic costs.
Generators in deficit who had to buy energy from others with surplus capacity had to pay at
these high prices thus encouraging investments in backup generation. Nevertheless, this
mechanism was not enforced during the energy deficit period that was caused by extreme
drought. This motivated a modification of the law to harden the terms of the obligation but had
an unwanted effect: the generating companies avoided signing supply contracts with the
distributors because of a negative risk evaluation. This situation was aggravated by the
curtailment in the supply of natural gas from Argentina that caused uncertainty over the choice
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 149
of generation technology to invest in. The crisis motivated another amendment to the law that
obliged distribution companies to auction long-term contracts for their energy requirements.
This competitive tendering process has proven to be more effective in attracting new generation
investment than the Indicative Generation Plan.
Before 2005, the generators were not interested in contracts with distributors as the investment
in coal, wind, hydro or geothermal plants were threatened by the possibility of recovery of the
gas importations from Argentina. Assuming this was the case, then the non-gas plants would not
have been competitive and the regulated prices would have gone down (as the regulated prices
were then calculated as the weighted average of the marginal costs for the next 48 months).
The success of the auctions implemented in 2005 in enhancing the generators’ investment is
due to the indexation system. In that system, the generators can choose an indexation based on
combinations of the fuel price variations and the CPI.
The indexation system resulted to a huge improvement in the investments generating a large
portfolio of projects as summarized in Table 28.
Table 28. Investments for New Generation Projects in Chile
TECNOLOGY QUANTITY POWER
PROJECTS MW Coal Thermal plants 29 7600
Hydro Power Plants 38 12100
Wind Power plants 18 1260
Geothermal Plants 14 540
TOTAL 21500
It has to be noted that not all those projects have been constructed nor are currently being
constructed as the legal and environmental processing is extensive and complex. This
significantly affects the timing of the projects, sometimes causing indefinite postponement. This
situation specially affects coal plants as well as the hydro plants with reservoirs.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 150
Prior to the implementation of the auction system, there were no generation deficits due to the
contribution of small investors that installed emergency generation equipment (diesel engines
and turbines). Those investors were motivated by the capacity payments and the possibility of
obtaining high marginal prices (which actually happened in the period previous to the
international economical crisis). The downside was high electricity prices because of the high
cost of operating these plants.
9.2.4 POLICY AND REGULATION OF TRANSMISSION
The transmission system in Chile is divided into 3 categories: the Trunk System, Sub-
transmission System and the Additional System. The Additional System is composed of the
transmission facilities, lines and power substations that are primarily intended to transmit
electricity to non-regulated costumers and other end-users for which the generators are
allowed to inject energy to the interconnected system without being part of the Trunk System.
DFL N°4 mandates open access to the transmission system. However, open access to the
Additional System is limited to the transmission facilities that use national properties. The
transmission charges for the Trunk and Sub-transmission systems are determined by the CNE
and valued by the CDECs who inform the companies of the amounts that they must pay. Tariffs
are fixed for a 4-year period. Payments for the use of Additional system lines are negotiated
between the owner and the user.
The law limits the participation of generators, distributors and consumers in the ownership of
the trunk system. The individual participation, directly or indirectly, of companies operating in
any other segment of the electrical system or of users who are not subject to price fixing in the
main transmission system may not exceed eight percent (8%) of the total investment value of
the main transmission system. In addition, the sum of the individual participation of generators,
distributors and non-regulated costumers in the ownership of the trunk transmission system
shall not exceed forty percent (40%) of the total value of the trunk system.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 151
The income that transmission companies receive for their existing installations corresponds to
the annuity of the investment value (AVI) plus operating, maintenance and administration costs
(COMA). The annuity of the investment value of existing facilities is calculated using a discount
rate of 10% in real terms (before taxes) and an economic life of 30 years.
Payment for new facilities in the trunk systems is equal to the bid of the winning bidder in a
competitive tender. The expansion of existing facilities is assigned to their respective operators
and is paid as a function of their declared investment value during the bidding for their
construction.
For the Sub-transmission systems, the Annual Investment Value (AVI) and the Annual Operation
and Maintenance Costs (COMA) are determined in quadrennial for each demand adapted
system.
The privatization of the transmission sector acted as a catalyst for new investment that was
reinforced by a tariff process that ensured cost recovery and a fair return on investments.
Both the Trunk and Sub-Transmission systems are subject to price controls. Prices are
determined in quadrennial studies that consider demand projections and new generation
investments. The study, which is undertaken by private and independent consultants determine
the tolls to be paid for the use of the facilities; which power lines or substations shall be
upgraded; and/or, if new facilities are needed. The toll is a function of the level of investments;
the operation and maintenance costs of the facilities, with a 10% average cost of capital over an
economic life of 30 years.
These studies are reviewed and approved by a special commission whose members are drawn
from the electricity industry and from the government. The construction of facilities that are
declared as essential for the operation of the transmission systems goes through an
international tender. The tolls to be paid for the use of the new facilities are based on the
results of the bidding processes.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 152
9.2.5 POLICY AND REGULATION OF DISTRIBUTION
The authority to construct and operate a public distribution network is granted through an
indefinite nature concession that obliges the concessionaire to provide service to anyone who
requests for it. The concession could be terminated in case of repeated poor service.
Distribution companies must have supply contracts with generators to supply their regulated
customers for at least the next three next years. This contract is the result of the bidding process
explained previously in this document.
The electricity tariff that apply to regulated customers consists of the prices of energy and
power that unifies generation (energy and power), transmission (high voltage line and
substation use) and distribution (medium and low voltage line and substation use) costs. The
distribution charge is determined by the Distribution Annual Value (VAD). The VAD is calculated
as the capital, operating and maintenance costs of an efficient distribution utility, with density
characteristics comparable to the utility to whom the distribution charge will apply. Therefore,
the distribution tariff under this methodology is de-linked from the utility’s own and actual cost.
The capital cost is determined as the new replacement value of the efficient comparable model
and the monthly payment is calculated based on a 30 years economic life and 10% real annual
cost of capital. The operation and maintenance costs are based on effective management and
administration costs while overhead costs; on the number of customers of the company model.
There are different types of cost considered in the VAD calculation:
a) Administrative costs due to the existence of the client. This is a fixed monthly fee,
regardless of user consumption;
b) Cost for energy consumption. Each kWh consumed by the customer requires the
company distributor to purchase a kWh plus the corresponding distribution losses;
c) Cost of peak power consumption. Each KW consumed by the customer requires the
distribution company to buy that KW plus distribution losses corresponding to the
system generator;
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 153
d) Cost per customer power demand in the local peak demand hours of the system.
This cost refers to the required capacity of facilities to cope with customer
consumption that coincides with peak demand. This requires the distribution
company to expand its substations, lines and transformers, high and low voltage to
cater for every additional KW customer demand for peaking power; and
e) Cost per customer power demand during off-peak hours. This has no impact on
investments at substations, transformers and lines away from client but nonetheless
affects the investments on facilities that that are near the clients and are more
specific to their demand behaviour.
The CNE hires one or several consulting firms to carry out the study while distribution
companies undertake the same study with consultants chosen by them, but approved by the
CNE. The results are weighted 1/3 for the study of distributor and 2/3 for the study of the CNE.
Tariffs are indexed through formulas that run for 4 years.
The VAD calculation mechanism generated the results in Figure 36 based on a reference study
conducted by the Pontifícia Universidad Católica de Chile (2009).
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 154
Figure 36. Percentage Change in Distribution Tariffs From VAD
9.3 CHILE’S POST REFORM INSTITUTIONAL GOVERNANCE FRAMEWORK
The Ministry of Energy was recently created. It is the agency responsible for the development of
plans and policies for energy sector including forecasting the demand and domestic supply of
energy. Other institutions that have key governance roles are:
a) National Energy Commission, CNE (for its Spanish acronym). It is the entity
responsible for setting all electricity prices except those in the non-regulated retail
market. The CNE is under the Ministry of Energy.
b) Fuel and Electricity Superintendence, SEC (for its Spanish acronym). It is the entity
responsible for ensuring the correct operation of the electricity, gas and fuel
services in terms of security, quality and price. It oversees the proper
implementation of the framework laws for these industries.
c) Economic Dispatch Centers, CDEC ((for its Spanish acronym) 67 CEDCs are
independent entities that are responsible for the optimal operation of each
interconnected electrical systems, called Economic Dispatch Centers. They are also
responsible for the valuation of the energy and power transfers between generation
companies and for the calculation of the transmission lines toll to be paid by the
companies. Their Boards are made up of the representatives of generators
companies, transmission companies and non-regulated customers. By their sheer
number and by the manner of selection of representatives that is biased for the
bigger companies; generation companies particularly the big ones have a large
influence over the decisions of the Board. The inclusion of non-regulated costumers
adds transparency to the decisions and actions of the CDECs .
d) Experts Panel. The panel was an offshoot of the amendment of the Electricity Law in
2004. It consists of 2 lawyers and 5 engineers or economists who are appointed for
67
There are two CDEC in Chile, CDEC-SIC that rules the Central Interconnected System, an CDEC-SING in charge of the operation of the Big North Interconnected System.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 155
6 years who are selected by the members of the Chilean Court of Free Competition.
Their work is to resolve differences arising between the authority and the electricity
market agents in connection with the application of the rules set out in the
Electricity Act and its Regulations. The Expert Panel also solves the differences
between the wholesale electricity market agents who are members of CDEC.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 156
10 BRAZIL’S ELECTRIC POWER INDUSTRY
10.1 OVERVIEW OF THE ELECTRIC POWER INDUSTRY OF BRAZIL
Generation
The Installed generation capacity and peak load of Brazil from 2001 to 2010 is shown in Table
29. The generation system in Brazil in 2010 has an installed capacity of 112,400 MW . Total
energy generation in 2010 was 475,104 GWh ; contracted import capacity at 5,850 MW ; and,
a maximum demand at 68,307 MW.
There were 2,336 generating plants in 2010. Of these 72% (80,637 MW) of installed capacity
was hydro, 19% (21,003 MW) thermal , 7% (7,826 MW) biomass (mainly sugarcane bagasse),
2% (2,007 MW) nuclear power and 927 MW wind power. It is notable that 79% (89,390 MW) of
generating capacity is from renewable energy . An additional 18,000 MW of generating capacity
is expected to operate in 2010 to 2011.
Table 29. Installed Generating Capacity in Brazil (2001-2010)
Year Peak Load
(MW)
Installed Capacity
(MW) Reserve
2001 55,099 74,877 36%
2002 50,757 80,315 58%
2003 53,515 85,857 60%
2004 56,795 90,679 60%
2005 59,103 92,865 57%
2006 61,782 96,295 56%
2007 64,371 100,352 56%
2008 65,586 102,949 57%
2009 67,442 106,570 58%
2010 70,954 112,400 58%
The National Interconnected System (SIN) is a system of large hydrothermal base that is
predominantly hydro and with multiple ownership. The SIN consists of four major subsystems:
South, Southeast / Mid-West (the largest in the country for its application and serves the
region’s largest population and industrial production centers ), North and Northeast. All the
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 157
hydro power systems are allowed to maintain a large energy storage capacity during the wet
years in anticipation of the dry years. The interconnections between the subsystems allow joint
optimization of the generation in different watersheds, thus leveraging on their hydrological
diversity. Current configuration allows the SIN to carry all the power generated in any of the
subsystems to the demand centers.
The system in the Amazon where energy demand is about 3% of the country is not yet fully
inter-connected to the SIN. However, the interconnection in 2001 of the capital city of Manaus
substantially reduced the number of non-interconnected systems and confined them to those
that are scattered in the Amazon region.
The system in the central Itaipu on the border with Paraguay with a demand of 14,000 MW has
a frequency conversion capability that allows Brazil to purchase power from Paraguay at 50 Hz .
There are also interconnections with Paraguay for 50 MW; with Argentina for 2050 MW; with
Venezuela for 200 MW (not integrated into the national grid in Brazil) and Uruguay for 70 MW.
Energy Import Contracts were signed with Argentina and Venezuela in addition to the
agreement to purchase power from the central Paraguay binational Itaipu dam.
Transmission
The current transmission system in Brazil has more than 95,000 km of power lines greater than
or equal to 230 kV and a transformer capacity higher than 206,000 MVA. The predominance in
the system of hydro generation located at long distances from the load centers requires a large
and complex transmission. The transmission system has voltage levels of 230, 345, 440, 500, 600
(DC) and 765 kV. The federal government maintains an important role in the sector through its
ownership of most of the basic grids.
Distribution
Brazil currently has about 70 distribution companies. A large number of major distribution
companies have private equity. However, some of the states of the federation maintain
ownership of distribution companies. System losses in Brazil range between 8% and 45% in 2008.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 158
The average sales price of electricity in Brazil in 2008 was approximately US$131.88/MWh. The
residential, industrial and commercial sectors registered average sales prices of US$153.49;
US$108.55 and US$147.60 per MWh, respectively. The average prices in 2010 is shown in Table
30.
Table 30. Average Price of Electricity in Brazil (2010)
Type of customer Average Tariff
(US$/MWh)
Residential 153.49
Industrial 108.55
Commercial 147.60
10.2 INDUSTRY RESTRUCTURING AND POLICY REFORM
During the 70s, all the companies in generation, transmission and distribution of electricity were
owned either by the federal or provincial governments. During the 80s and the 90s, Brazil
suffered a hyper-inflation process that, together with the freezing of the electrical tariffs
resulted to a debt of US$ 50,000 MM between the generators and distribution companies. That
debt was partially cancelled by the federal government in 1993. By then, the Brazilian state had
suffered the consequences of a severe economic crisis as a result of the high external debt. In
1995 during Fernando Cardozo’s government, it was decided to initiate reforms using other
countries such as Chile, England and Colombia as benchmarks.
The modernization of the Brazilian electric sector began in 1995 through the publication of the
Law on Public Service Awards (8.987 Act) and regulations related to the electricity market
specifically the 9.074 Act. The regulatory body was created in 1996 through the 9427 Act. In
2004 the Brazilian Government decided to make modifications in the operating model of the
sector through the enactment of Laws 10847 and 10848.
The key issues that led to the reform were:
a) High disinvestment in the electricity sector in the 1970-1990 period;
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 159
b) Financial and technical inability by the state to provide the necessary system expansions due to the external debt crisis experienced by Brazil in the eighties;
c) Dominance of state electricity companies resulting in the need to increase the participation of the private sector;
d) Poor quality of service that showed in frequent blackouts; and
e) Low tariff levels from inefficient subsidies.
Law No. 8987 of 1995, known as the "Law on Public Service Awards” and the Sector Law No.
9047 of 19/5/1995 introduced profound and important changes, namely:
a) Opening up the industry to private investors;
b) Bidding for new generation projects;
c) Creation of the Independent Power Producer;
d) Open access to transmission and distribution systems;and,
e) Freedom for large consumers to choose their energy suppliers.
Decree No. 1717 of 1995 established the conditions and enabled the extension and
consolidation of public service concessions and approved the plans for the conclusion of the
suspended work on 22 power generation projects with a combined 10,100 MW of generating
capacity.
Decree No. 2003 of 1996 established the "Regulation of the Operation of Independent
Producers and Self-producers.”
Other laws were passed in 1997 as follows:
a) Law No. 9433, which instituted the National Water Resources Policy and created
the National Water Resources Management;
b) DNAEE (former regulator) Resolution 466, which consolidated the General
Conditions of Supply of Electricity and harmonized it with the Consumer Protection
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 160
Code (Law No. 8078, of 1990);
c) Resolution MME (Ministry of Mines and Energy) 349, which approved the Internal
Regulation of the ANEEL established Control DNAEE management ; and
d) Decree 2410, which provided for the calculation and collection of the annual audit
of public services by all concessionaires.
Major policy reforms were made in 1998 with the publication of Provisional Measure No. 1531,
which authorized the Executive to restructure ELETROBRÁS and its subsidiaries, the most
significant of which were:
a) Authorizing the gradual withdrawal of the State from the electricity business;
b) Guaranteeing the General Reversion Reserve (RGR) until 2002 to continue the
investments in Electrobrás (Centrais Eletricas Brasileiras SA);
c) Since 2003, concessionaires or authorized may negotiate the amount of energy
with gradual reduction, the annual ratio of 25% of amounts relating to the year
2002;
d) Authorizing the separation of FURNAS into two companies: one each in generation
and transmission;
e) Authorizing the separation of ELETROSUL into two companies: one each in
generation and transmission;
f) Authorizing the separation of ELETRONORTE into five companies: two generation
companies, one transmission and one distribution in the isolated systems of Manaus
and Boa Vista, one for generation in Tucurui, and another for transmission;
g) Authorizing the separation of CHESF into three companies: two in generation and
one in transmission;
h) Authorizing ELETROBRÁS to retain stakes in the generating companies to be created
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 161
from the separation of FURNAS, ELETROSUL, ELETRONORTE and CHESF.
In summary, the policy reforms in 1997 resulted in the following:
a) Unbundling (Generation, Transmission and Distribution);
b) Open access to transmission and distribution systems;
c) Creation of a short-term energy market and of the Mercados Atacadista de Energia (MAE) that was responsible for settlements in this market;
d) Creation of an independent Regulatory Body;
e) Re-definition of operating organisms of the system, with the participation of agents in the system;
f) Definition of traders companies and free consumers;
g) Tender for new generation projects.
The key elements of reform that were intended to incent investments in the industry by the
private sector were the :
a) Creation of a stable legal and institutional framework through laws and decrees
that permits and facilitates private sector participation in the electricity industry;
b) Privatization of distribution companies . The privatization of these non-profitable
companies provided greater security to generation investors because it allowed for
a better functioning of the long-term power markets; and
c) Adjustment of the tariffs to end-users through the removal of subsidies.
The immediate results of the reforms highlighted the importance of private participation in the
generation and distribution of electricity. From virtually zero in 1995 , private ownership rose to
3% in the generation and 32% in distribution in 1997. Between 1998 and 2000 US$ 10 Billion
was invested in the electric system by private companies. During this period, the government
successfully tendered 10,000 MW of new hydropower generating capacities. The tender for the
generation plants owned by the federal government was however stopped by the political
opposition.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 162
10.2.1 POLICY AND REGULATION OF GENERATION
The central regulatory policy for generation is the requirement imposed on distribution
companies and large consumers to enter into long-term contracts with generators . This policy
is mainly intended to incent investments in new generating capacities.
Distribution companies are mandated to sign contracts for 100% of their energy requirements.
Contracts must be signed for energy to be supplied by existing plants one year before they are
required; three to five years before for energy to be supplied from new plants that are still to
be built. Generators must have backup power capacity to secure their supply contracts. There
are no additional charges for generation capacity. Large consumers (Contestable Consumers)
also must contract 100% of energy requirements.
The policy reforms in 2004 created three electricity markets, namely:
a) Regulated contracting market for contracts between generation companies and
distribution companies for the demand of the regulated markets;
b) Free contracting market for bilateral contracts between generators, importers or
traders and large consumers and exporters; and
c) Energy spot market, where the Chamber of Electric Energy Commercialization (CCEE)
calculate the amounts and price differences between contracted and consumed
energy.
Regulated Contracting Market
Distribution companies must secure their energy requirements through contracts in the
Regulated Contracting Market (ACR). ANEEL is responsible for the regulation, organization and
conduct of the bidding process directly or through the Chamber of Electric Energy
Commercialization (CCEE).
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 163
The winning companies at the auction are those that offer the lowest price per MWh to supply
the distribution companies. Regulated Market Contracts are signed between the winning
generators and distribution companies.
The main design elements of the auction are:
a) Total energy purchases must be made through auction based on the lowest price
method;
b) Procurement is carried out jointly by distributors through the pooling of their energy
requirements in order to obtain economies of scale in contracts associated with
new generation projects in addition to spreading the risks;
c) Auctions are held separately for new power plants (supply to the expansion of
demand) and for existing plants, both by tender.
There are three types of auctions. Given that “A” represents the starting year for energy supply,
the auctions that are held are:
a) Auctions (A - 5) performed in the fifth year preceding the year A;
b) Auctions (A - 3) made in the third year preceding the year A;
c) Auctions (A - 1) made in the year preceding the year to start of supply.
Auctions (A-5) and (A-3) are made for the purchase of power from new generation projects and
(A-1) for the purchase of energy from existing plants. Additionally ANEEL may conduct
Adjustment auctions in order to supplement the supply for distribution companies to at most
1% of their demand. Finally, there are auctions for energy from renewable sources and for
backup energy. Sellers in this market must have physical support for their contracted energies
from their own plants or through contracts with other generators or electricity traders.
Every year until the first of August the distribution companies, energy traders , and large
consumers must submit their forecast demand for the next five years to the Ministry of Mines
and Energy . The Ministry determines the sum of the demands of distribution companies and
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 164
that are to be auctioned (A-5) in the regulated contracting market. The energy needs of other
agents are met in the free contracting market.
Distribution companies can change their forecast for the year A, three years before the supply
will be required. The limit of this change is 2% of the load. The Ministry determines the total
amount of these requirements and may hold an auction (A-3).
Distribution companies can make a new forecast a year before the year A, limited to 5% of its
market for the replacement of contracts that are about to expire. The Ministry determines the
amount of the new demand and may hold an auction A-1. The amount of energy that the
distribution companies can buy from this auction is limited 1% of their total contracted load.
The duration of contracts with new power plants (auctions (A-5) and (A-3)) is at least 15 years
and a maximum of 30 years counted from the start of supply. For contracts with existing plants
(auctions (A-1)) the duration is at least 5 years and a maximum of 15 years. For supplies from
other sources; the contract duration is between 10 and 30 years .
In addition to the regular auctions , Setting auctions may be held for energy requirements within
four months after the auction with supply period of up to two years. These are for energy
requirements that were not forecasted or caused by unexpected situations that could not be
included in the A-5 and A-3 auctions. Setting auctions cannot involve more than 1% of the
energy tendered in the regular auctions and are held in the same year as the A-5 and A-3
auctions.
Generation projects identified by the Energy Research Company (EPE) and approved by
resolution of the National Energy Policy Council (CNPE) are considered priorities for their
strategic and public interest and are included in the auction (A-5) and (A-3).
To increase the security of supply, reserve power auctions are held to sell backup power from
generation centrals hired by the Chamber of Electric Energy Commercialization (CCEE) for this
purpose.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 165
Generation companies can contract for either energy or availability. Energy is a classical contract
in which the generator assumes the risks of not being able to supply the energy (when this
happens, the generator will have to assume the costs of buying the energy in the spot market).
In such energy contracts, the generator assumes also the risk associated with increasing fuel
prices. As for the availability contract, there is a minimum availability to be met by the generator
and in the case of non-performance, there are penalties to be paid by the generator. However,
the distributor assumes the costs of buying in the spot market or the risk associated with the
prices of fuel. In energy contracts, generation companies assume the risk of generating energy
in the contracted amount. In availability contracts, the risk in the amount of energy generated
belongs to the distribution companies that sign the contract. The Ministry is opting for
availability contracts for thermic central where distribution companies assume the payment of
fuel.
Free Contracting Environment
Consumers with demand exceeding 3 MW that were connected after July 1995 and the
consumers with supply voltage exceeding 69 kV and connected prior to this date can buy their
energy from any supplier.
Consumers with demand exceeding 500 kW can buy power from the local distribution
concessionaire at regulated rates . Alternatively, they are free to enter into power purchase
contracts with small generators particularly small hydropower, biomass thermal or wind.
Law 10.848 of 2004 created the Free Contracting Market. In this market, customers conclude
bilateral contracts freely with generators, traders and importers. Free Customers should be free
agents of CCEE. They can be represented for the purposes of accounting and settlement by
other agents of that chamber that means that some agents can act in the name of others
(through a power of attorney). This is due to the fact that some free agents do not have enough
technical knowledge or economical resources to manage their contracts so they could associate
and/or be represented by third parties. It is estimated that 25% of the country's current demand
are from free customers.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 166
A consumer in the free contracting market who wishes to revert to the distribution company in
his/her area for the supply electricity must advise of its intention to do so 5 years in advance.
Energy Spot Market
The short term energy market in Brazil can be defined as a generators’ pool. The transactions
and prices not covered by the long term contracts are resolved in this pool. The participants in
the spot markets are generators, distributors, traders and free customers.
The Differences Settlement Price (PLD), is used to value energy transactions in the short-term
markets and is the difference between contracted amounts and quantities currently generated
and consumed. The PLD is derived by the national system operator ONS (Operador Nacional do
Sistema Electrico) with the use of power system operation optimization models. There are two
models, the NEWAVE model with five years horizon and monthly simulations and DECOMP
model with 12 months horizon. The models find the optimal solution using the reservoirs, taking
into account the benefit of present water use and the expected future benefit of storing water,
reducing fuel costs and future failure.
The PLD is determined weekly for each of the three load steps and for each submarket (North,
Northeast, Southeast / Mid-West and South). It is equal to the marginal cost, but must be within
floor and ceiling prices that in 2010 were at US$ 7.2 MWh and US$ 350 MW Respectively.
When the level of hydropower reservoirs in each region is below the safety limit, the ONS
activates the Risk Aversion curve and prioritizes the entry of thermal and other energy imports
even if the marginal cost of hydro generation obtained from the models is less than the cost of
these resources. In this case the PLD is equal to the "cost risk", i.e. the price of more expensive
energy resources dispatched.
The calculation of the PLD has no transmission constraints within each submarket. As such,
energy is assumed to be equally available in all points of the sub-market and the price is unique
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 167
within each submarket. In contrast, the PLD calculation takes into account transmission
constraints between the various submarkets.
The calculation of the PLD is based on ex-ante dispatch ,i.e.; prior to the real operation of the
system.
The settlement of the income of hydropower in the spot market is done through the Energy
Reallocation Mechanism (MRE). The MRE is based on the concept of Assured Energy of
hydroelectric plants. The Assured Energy of each hydropower plant is determined by ANEEL by a
method of energy allocation to be supplied by the set of hydro plants with a defined probability
of occurrence. The MRE assures that all hydro plants receive a minimum income whose
calculation depends on its Assured Energy regardless of actual energy production. In other
words, hydro plants act as an energy pool to compensate those plants that produce under their
assured energy.
If there is secondary energy source in the system, the energy generated over the total
committed energy is allocated between the hydro generators in the proportion of their
committed energy.
10.2.2 POLICY AND REGULATION OF TRANSMISSION
Transmission concessionaires are responsible for the maintenance and availability of their
facilities. The facilities are operated by the ONS. There is open access to the transmission lines
subject to the payment of transmission charges and compliance with operational and
contracting procedures.
Transmission system planning is performed centrally by the Energy Research Company (EPE).
The main studies are contained in the Ten-Year Energy Plan (PDE) and cover a 10 year horizon
for the generation and transmission systems and a 5 year horizon for the Transmission
Expansion Program (PET) .
Transmission facilities are classified as:
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 168
a) Basic Grid (trunk grid): voltage installations greater than or equal to 230 kV;
b) Border: transformer facilities with voltage greater than or equal to 230 kV that
feeding network with lower voltage distribution at 230 kV; and
c) Other transmission facilities (DIT) at any level of voltage for the exclusive use or
shared use of generators or exclusive use of free-choice consumers.
The new facilities needed for the expansion of the Basic grid are tendered through an auction
while the reinforcements in the existing concessions are approved by ANEEL.
Transmission concession contracts are generally signed for thirty-year periods. Contracts define
the pay revisions every four years and annual rate adjustments according to the IPCA index
(Indice General de Precios al Mayor –General Index for Wholesale prices).
For the purposes of remuneration, the Backbone facilities are divided into: (a) Current Facilities;
(b) New Facilities Authorized; and (c) New Facilities Tendered.
The remuneration for current facilities consists of the depreciation expense allowance and
return on assets that are based on the regulated rate of return. The revenue associated with
these facilities for most companies were defined in 1999 and is subject to adjustments
according to the IGP-M index until 2015 at the expiration of their concession contracts.
New transmission facilities are authorized by specific resolution of ANEEL. Their payment
includes an allowance for depreciation and return on investments on new and replacement
facilities as recommended by the EPE or the ONS to increase transmission capacity or system
reliability. The annual remuneration is calculated as an authorized investment annuity in the
form of a regulated rate of return that is reviewed every four years.
The construction and maintenance of new assets for existing transmission systems is awarded
through an auction. The annual income allowed (RAP) to the transmission agent is based on its
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 169
bid and is paid for a period of 30 years with adjustments as provided in the concession contract.
ANEEL determines the maximum values for the acceptable RAP in the tenders.
ANEEL employs the Capital Asset Pricing Model (CAPM) to calculate the return on equity
component of the regulated rate of return. Allowable leverage is 63.55% for both existing
companies and for new entrants. The real rate of return in domestic currency after tax that was
adopted in the second tariff review cycle (2009-2013) was 7.24% for companies existing in 1999,
and for projects tendered for construction since 2000. The regulated rate of return is updated
every five years (the fifth, tenth and fifteenth year) . It was adjusted in 2010 to 6.00% in real
terms and after tax.
Payments are based on the efficient cost of an efficient transmission company that is derived by
ANEEL taking into account the actual conditions in the geographic area of the concession. The
costs covered in the payments include the operation and maintenance of electrical networks,
commercial management, direction and management. The methodology for the second periodic
review of cost was approved by the Normative Resolution 386 of December 15, 2009, where
operational costs were determined based on benchmarking methods.
The transmission usage fees or tariffs (TUST) are set by ANEEL. The fee structure provides
locational signals and imposes higher charges on those using the system in greater proportion.
TUST had two components starting in July 2004. These are:
a) The TUSTRB, for facilities of the basic grid with voltage less than 230 kV, which is
calculated by the Investment Cost Relating Pricing (ICRP) nodal methodology, and;
b) The TUSTFR, for the transformer facilities with voltage greater than or equal to 230
kV, and feeding distribution networks with voltage less than 230 kV, and for other
DIT’s transmission facilities that are shared by distribution concessionaires.
The TUST is calculated from the Nodal Program simulation and computational system. Rates are
based on the use of the grid and demand at each node depending on the intensity of use for the
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 170
injections or withdrawals of power. Charges are based on the long-run marginal costs (LRMC) to
inject to or extract 1 MW from the grid. The methodology considers the minimal total
investment cost of an ideal grid and assumes that network expansion and re-routing of
transmission lines are performed continuously. As the amount of remunerations calculated by
the nodal method does not allow the full recovery of network investments, a constant
adjustment factor, R $ (reais) per MW is added to the rates.
Small hydropower (PCHs) and generation projects that use alternative energy sources (such
solar, biomass, wind and CHP) with power less than or equal to 30 MW have the right to a
discount of at least 50% on transmission and distribution tariffs for the energy commercialized.
The exact percentage is determined in their authorizations.
Resolution No. 267, a legislation that was passed in June 2007, changed the calculation of the
TUST for new companies that participate in the generation auctions. For energy auctions ANEEL
publishes a set of TUST for the new installations with direct connection to the basic network not
being in commercial operation.
10.2.3 POLICY AND REGULATION OF DISTRIBUTION
Distribution concessionaires cannot participate or own shares directly or indirectly or perform
activities in generation and transmission in the same way that generation concessionaires
cannot be controlled by distribution concessionaires. Distributors can sell energy to free
consumers except for those located in its franchise area where rates and terms applied to
regulated captive customers are used. These restrictions do not apply to distribution companies
in isolated systems, or in their own market for market smaller than 500 GWh per year.
Distributors are allowed to charge their customers for energy costs that are up to 3% higher
than the contract price in the energy auction. Subcontracting for energy supply is not allowed .
A distributor that is in deficit must buy power in the short term market subject to the payment
of penalties.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 171
Distribution tariffs reflect the prudent cost of investments required to deliver the service and to
comply with the requirements of the concession contract such as on service quality. Eligible
assets determined for a reference network are initially valued at their replacement cost
according to a price database maintained by ANEEL and are thereafter adjusted based on a
productivity index. The prices in the ANEEL database are the average prices in the last four years
by type of equipment on actual purchases made by the concessionaire. The replacement value
of assets is then multiplied by a factor called “exploitation index”. The index reflects the degree
to which assets are currently employed and removes the value of not used or not useful assets,
e.g. those oversized from the valuation of the rate base.
Operating costs, maintenance, administration and commercial management are de-linked from
actual costs incurred and are instead calculated by ANEEL by the Reference Network
methodology. An optimal capital structure that was derived from empirical data from
comparable electricity distribution companies in Brazil, Argentina, Chile, Australia and Britain is
used in the WACC . This structure allows for 57.16% of debt . The rate of return in real terms is
9.95% after tax.
The pricing methodology is a Wholesale Price Index (WPI) – X price cap. Concessions that were
signed with power distributors from 1995 provided for initial rates and adjustment mechanisms
in the periodic rate revisions, extraordinary rate revisions and annual rate re-adjustment. Rate
Review occurs every four years.
10.2.4 POLICY AND REGULATION FOR RENEWABLE ENERGY
Generating capacity from renewable energy increased by 5,200 MW in the period 2004-2009.
These were mainly from two resources: bioelectricity cogeneration from sugarcane bagasse, and
small hydro from plants with capacities of less than 30 MW. These plants have been
participating in the energy auctions carried out by distribution companies to supply their loads;
competing with traditional generation companies. In the last two years, 800 MW of wind power
were in operation and under construction. An additional 1,800 MW of new capacity was
contracted in the 2009 auction.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 172
The biggest obstacle to the construction of these plants has been the inability of the existing
regional grids to accommodate new power injections. It thus became necessary to plan grid
reinforcements. To this end, a new regulatory design known as the IGC Scheme was agreed
between ANEEL and the RE investors. The agreement calls for:
a) Generators to hire a technical team to plan the integration network in cooperation
with EPE. The planning of the integration network would be carried out on a least-
cost basis through the use of an optimization model to optimally locate the IGC
facilities and minimize investment costs. The proposed plan would be subject to
ANEEL´s approval;
b) Generators to pay for 100% of the IGC costs plus the basic grid tariff (TUST); and
c) Distribution companies to (exceptionally) waive their right to build the IGC assets
and an auction will be held for the right to operate and maintain the IGC facilities.
As agreed in the IGC scheme, generators will pay for all integration network construction and
maintenance costs. Because the network had a tree structure, it was easy to calculate the
fraction of each generator’s injection that would flow across each circuit. This allowed the
application of a MW-mile scheme where each generator pays for the cost of each circuit in
proportion to its use.
ANEEL held an auction in 2010 to grant the concession of the ICG facilities that will be used to
integrate about 1,800 MW of Wind Power in the northeastern and southern regions of Brazil.
10.3 BRAZIL’S POST REFORM INSTITUTIONAL GOVERNANCE FRAMEWORK
The governance framework set up by the reform comprised of three institutions: the system
operator (ONS), the regulator (ANEEL) and a body responsible for the settlement of short-term
market called “Mercado Atacadista de Energía” (MAE). They are guided and assisted by other
agencies that are involved with the electric power industry.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 173
MAE is supervised by the Ministry of Energy and Mines. It is however a non-profit private
institution,. The President of its Governing Council is designated by the Ministry. The President
also has veto power.
The formulation , implementation and monitoring of the electricity sector policies are the
responsibilities of the Ministry of Mines and Energy (MME) under the guidelines of the National
Energy Policy Council (CNPE). CNPE is chaired by the Mines and Energy Minister. Its principal
duty is to recommend to the Brazilian President energy policy, the bidding of special projects
in the electricity sector and the definition of safety criteria for electricity supply. Within the
Ministry's structure is the electrical energy secretary whose key responsibilities include to
coordinate ; provide guidance and control the Ministry´s actions with respect to the politics of
power sector; security of supply under the established quality standards; continuity and safety;
and, the definition of fair rates for consumers and one which encourages medium and long
term investments.
Electric Energy National Agency (ANEEL) is the regulatory body. It is responsible for developing
regulations and legislation; for the auction of generation and transmission projects and for the
power supply of distribution companies.
The Energy Research Company (EPE) is a state-owned enterprise in charge of research and
studies of the energy sector planning. The company draws up every year the electrical system
expansion plan for the next 5 years.
The National Electric System Operator (ONS) is responsible for coordinating and controlling the
operation of the national grid; implementing an optimization of energy resources; ensuring
security of supply and service quality standards taking into account the conditions imposed for
multipurpose water reservoirs and the limitations of the generation and transmission systems .
The Chamber of Electric Energy Commercialization (CCEE) is an association of electricity market
players and institutions. Its main function is to register and manage the electricity supply
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 174
contracts signed between generation companies, trading companies, distribution companies
and large users. The most important activity carried out by the CCEE is the calculation and
payment of the spot market prices.
The Monitoring Committee Electricity Sector (CMSE) is an institution whose function is to
analyze the continuity and quality of power supply in a five years period, and develop preventive
measures and actions on the demand side and generation system.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 175
11 KEY POINTS AND LESSONS LEARNED FROM INTERNATIONAL
EXPERIENCE
The policy and regulatory reforms in Chile and Brazil had many aspects in common. Among the
most important are:
a) Vertical Disintegration of activities where competition between players could be
possible (i.e. power generation and commercialization) and the regulated activities
(i.e. distribution and transmission);
b) Both countries actively fostered competition in generation and commercialization
activities in order to reduce electricity prices to the consumers;
c) Requirement for distribution utilities and large users to sign bilateral contracts for
100% of their forecast demand through auctions in order to incent generation
investments;
d) The creation of wholesale spot market that is primarily a balancing market for
generators and distributors (plus traders and free customers in Brazil) for their
contractual commitments. In these markets the dispatch is based on the variable
operating costs of thermoelectric generation units and on the water’s opportunity
cost for dammed hydro generation plants;
e) Decentralization of the investment decisions for the expansion of the transmission
grids and new generation capacity;
f) Tariffs related to the usage of transmission and distribution grids are benchmarked
to the cost of an efficient utility, the reference network, and de-linked from the
utilities own cost;
g) Open access to transmission and distribution networks is guaranteed by law, once
the security and reliability conditions are met. Access tariffs are regulated; and
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 176
h) Strong and comprehensive institutional governance framework that clearly allocates
responsibilities for policy, planning, regulation and dispute resolution among
government and non-government organizations.
However there are also differences between the two reform processes, the following being the
most notable:
a) In the Chilean case, power sector privatization was directed at Chilean investments,
however during the 90’s some companies were bought by international companies.
In Brazil national and international companies participated in the privatizations;
b) In Brazil, the regulator conducts three types of bids for distribution companies
depending on when the supply is needed. In Chile, distribution companies set their
own bidding terms but each bid must be approved by the regulator;
c) Brazil permits big end users to participate as agents in the electricity market. They
can buy in the wholesale market their requirement for the short and long term. In
Chile, end users have no access to the wholesale energy market. They have to buy
energy and power from a generation or distribution company; and
d) Brazilian methodology for the calculation of the regulated transmission tariff is
based on the long term marginal cost. In Chile the tariff calculation is based in the
short term marginal cost and the market agent’s use of the grid.
The following highlights the weaknesses of the Chilean regulation reforms:
a) In the beginning Transmission and Generation were not separated. This caused
innumerable problems and a great barrier to the entry of new players in the
electricity market. This weakness was overcome some year later by the Chilean
antimonopoly organism who decreed that both activities shall be separated;
b) The huge participation of the principal generation company of the system, ENDESA
plus the problem that most of the water usage rights are owned by this company.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 177
This problem has not been solved; the only partial solution has been a tax for the
unused water rights;
c) Vertical integration between the principal generation company and the biggest
distribution company. This problem still persists but its adverse effects have been
softened by the open bids for the distribution companies’ supply;
d) Absence of a regulatory mechanism for the quick resolution of disputes leading to
proceedings/litigation of issues that could not be addressed properly by
authorities and to the extent that the authority could not act in properly during
the supply crisis. This problem was superseded with the creation of the “Experts
Panel” that solves the conflicts between market agents;
e) State entities in charge of the definition and implementation of energy policies, and
the regulation and supervision of the electricity sector activities were weak. These
problems were gradually addressed by initially, giving more authority to the
superintendent’s office and later, by the creation of the Ministry of Energy;
f) Privatization did not promote investment in power generation as has been proven in
Chile. The growth in generation capacity was not sufficient to fulfill demand growth
and the supply security needed. This lack of investment is in part explained by the
dominant position of the biggest generation company, which is primarily
hydroelectric and owns most of the generation water rights, who has extra profits
with the delay of generation project; and
g) Usually the investments in generation respond to energy prices and supply crisis.
The bids for distribution companies’ supply and new mining projects have worked as
incentive for new power generation.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 178
12 COMPARATIVE MARKET ANALYSIS: CHILE, BRAZIL AND PHILIPPINES
The power markets of Chile, Brazil and the Philippines are compared in Table 31 below.
Table 31. Comparative Analysis of Chile, Brazil and Philppine Power Markets
Market Feature Chile Brazil Philippines
Promulgation of Reforms
Main reform in 1982. In 2005 the distribution bids were imposed
1995 and 2001 2001
Policy and Planning
Ministry of Energy Fuel and Electricity Superintendence
National Energy Policy Council (CNPE); Ministry of Mines and Energy; Energy Research Company; Monitoring Committee for the Electricity Sector
JCPC Department of Energy
Regulator Comisión Nacional de Energía , CNE
Electric Energy National Agency (ANEEL)
Energy Regulatory Commission (ERC)
Dispute Resolution
Independent Experts Panel
Appointment of Dispute Resolution Administrator and Panel Group; disputes can be raised in court
ERC subject to recourse to the court Sectoral Dispute Resolution Mechanisms in WESM, GMC, DMC
Designation Process of Regulator
Selected by Senior Public Management System and approved by the President
Proposed by the President and approved by Senate
Appointed by the President
Regulated Activities
Transmission, distribution. Generation through auctions
Transmission, distribution. Generation through auctions
Transmission & Distribution Generation until retail competition and open access declared
Types of Power Markets
Bilateral contracts through auctions(distributors and free users100% contracted); Centralized SPOT Market (short-term marginal cost based dispatch pool, “SMP”)
Bilateral contracts through auctions (distributors 100% contracted; Capacity contract optimization model and Spot market based on long run marginal cost (“LRMC”)
Negotiated bilateral contracts; Centralized SPOT Market (bid price-based dispatch gross pool)
System Operator
Economical Load Dispatching Center (Centro de Despacho Económico de Cargas, CDEC)
National Operator of the Electrical Systema (Operador Nacional do Sistema Eléctrico, O N S.)
National Grid Corporation of the Philippines (NGCP)
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 179
Market Feature Chile Brazil Philippines
Market Operator
Private. Centro de Despacho Económico de Cargas, CDEC (membership from generation, distribution and free users)
Private. Chamber of Electric Energy Commercialization (CCEE)
Philippine Electricity Market Corporation (PEMC) pending selection of IMO.
Peak Demand SIC: 6200 MW SING: 1900 MW
70, 954 MW 9,472 in 2009 (Country) 7,643 MW (Luzon Grid - 2010)
Major Players in Generation (by % of total demand)
SIC: ENDESA COLBUN AES GENER
SING: E-CL(SUEZ AES GENER: GAS ATACAMA: Others
ELECTROBRAS, the state company is the major generator and distributor
Luzon: SMC Group Lopez Group Aboitiz Group NPC/PSALM
Visayas: NPC/PSALM Global Business Power Lopez Group
Mindanao: NPC/PSALM Aboitiz Group CEPALCO
Existence of Supply Sector
generators and distributors
Generators , distributors, traders
Distributors; and with retail competition, generators, retail electricity suppliers
Free clients or Contestable Market
Those with demand of at least 2 MW . No provision for retail competition at household level
Demand >3 MW. No provision for competition at household level
Open Access and Retail Competition is yet to be implemented. Thresholds are 1
st, consumers with
demand of 1 MW and above; 2
nd, 750 kW and
above 2 years after with possible aggregation; 3
rd,
all consumers 7 yrs after 2
nd stage.
Type of Pool
Balancing Market. Generators only
Net Pool. Generators, distributors, traders and free customers for energy requirements not covered by long-term contracts
Gross pool
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 180
Market Feature Chile Brazil Philippines
Method of Settlement in Spot Market
Direct settlement between generators based on SMP and net balance calculated by CDECs. SMP based on variable cost of most expensive generator dispatched. Thermoelectric generators required to submit operating costs that could be audited by CDECs.
Differences Settlement Price (LPD) determined by ONS. PLD subject to floor and ceiling: US$ 7.2 /MWH and US 350 MW in 2010 respectively
Net settlement at nodal prices using the differencing model
68 .
Generators bid Prices for each hour.
Dispatch Centralized at the lowest cost, independently of the contracts
Economic dispatch submit to optimization model
Central scheduling and dispatch using optimization model, independently of the contracts
Capacity charge
Capacity is remunerated only in peak hours (note that auction price is node price + 20% and bid awarded to lowest energy price)
Lowest capacity charge in the auction
No Capacity Remuneration in WESM; capacity charge included in negotiated bilateral contracts
Degree of Privatization (in Generation)
100% 10% 85% of the total capacity of generating assets in Luzon and Visayas
Existence of Subsidies
None Residential customers Missionary customers from universal charge; lifeline customers (with consumption of 100 kWh and below) as well as senior citizens are subsidized by non-lifeline and non-senior citizen customers
Presence of Dominant Power Player
ENDESA controls more tan 40% of SIC generation E-CL controls about 50% of the generation of SING
ELECTROBRAS , the state company is the dominant player in generarion and distribution
MERALCO (the largest DU controls nearly 70% of the Luzon grid)
Market Share of DUs (based on demand)
75% del SIC 10% del SING
70% 99% Luzon; 96% Visayas; 85% Mindanao
68
For a settlement system that works on a differencing basis, each exit point from the transmission network is assigned to a standard retailer, and that retailer has the prima facie responsibility for payment for all energy that passes through that exit point. That energy is purchased at the appropriate reference node pool price multiplied by the loss factor appropriate to the exit point.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 181
Market Feature Chile Brazil Philippines
Number of Customers in the market
More than 4 million More than 40 million More than 5 million
Generation Barriers
For hydro the main barrier is the control of water usage rights by the largest generation company (ENDESA). For Thermoelectrics the main barrier are environmental approvals, people opposition and availability of assured Natural Gas. For small projects the main barrier is the lack of transmission infrastructure.
Environmental licensing process still complex; availability of acquisition of natural gas
Complex and multifarious authorization and permitting requirements including health, safety and environmental clearance is still required from government agencies. Highly concentrated Distribution Market with a single DU accounting for ~70% of the main grid.
Participation of Generators in the Market
Without restriction Without restriction No Single company, related group or IPP Administrator allowed to own, operate or control more than 30% of installed generating capacity in a grid and/or 25% of installed generating capacity
Driver of Growth in Generation
Contracts with distribution companies (Public bidding process) and non-regulated customers.
Auctions in the regulated and in the free market
None
Transmission Expansions
New works are open and competitive to any operator. Expansion of existing works are compulsory for the owner
Expansion of the system through auctions
Expansion planned & carried out by the National Grid Corporation of the Philippines (NGCP)
Regulatory reform and restructuring in the three countries were motivated by a common need
to create an efficient electric power industry. Their broad policy and market architectures and
institutional governance frameworks are similar: liberalization of generation; regulation of
network services; creation of wholesale and retail markets; and the creation of separate policy
and regulatory institutions. They also face the same challenge from dominant utilities. However,
the detailed policy, regulatory and institutional market designs markedly varies between Chile
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 182
and Brazil on the one hand; and the Philippines in the other. These differences may well explain
the performance of the markets in the three countries, specifically, on generation investments.
Chile and Brazil have achieved generation adequacy; the Philippines has not and is instead facing
supply shortages particularly in the Luzon and Mindanao grids. Market size and privatization do
not appear to explain these differences. The power markets of Chile and the Philippines are
comparable in size and both countries have actively pursued privatization. Brazil on the other
hand has a large market and the government continues to hold ownership interests in most of
the country’s distribution utilities and generating plants. While these disparate achievements
could be partly because the two comparator countries, particularly Chile implemented drastic
reforms much earlier than the Philippines that gave them a lead time to assess the effectiveness
and re-calibrate their policies; it also signals the need for an in-depth examination and
adjustments of the policy and institutional design in the latter.
The distinguishing feature of Chile’s and Brazil’s markets is the sequencing of policy reforms that
prioritize the achievement of generation adequacy over wholesale and retail competition.
Distributors and large users are required to contract for 100% of their forecasted demand and
sign long-term contracts from the public auctions that are managed by the regulator. The
regulator sets the price caps and approves the terms (actually draws up the bidding terms in
Brazil) of the auction. The system has greatly reduced market risk and the risk of regulatory
opportunism which provides a strong incentive for generation investments. Since generators
and other suppliers must compete to supply under strict bidding terms including a price cap that
is set before the auction ; consumers benefit from the efficiency of competition, albeit, from
competition for the market, rather than competition in the market. The exercise of market
power by dominant generators and/or distributors is curtailed because both are required to
contract by auction.
As a result of the 100% bilateral contract requirement, the wholesale spot market in Chile is a
balancing market for generators only while that in Brazil is a net pool for energy requirements of
distributors, generators , traders, and large users that are not covered by these long-term
contracts. At the same time, both Brazil and Chile have placed higher thresholds than the
Philippines for initial retail market contestability at over 3 MW and 2 MW respectively and have
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 183
not mandated contestability at the household levels. In contrast, bilateral contracts in the
Philippines are bilaterally negotiated and are predominantly for 1-3 years only. Distributors and
eventually, contestable market customers will be allowed to secure their energy supplies from
the spot market subject only to the distributor’s compliance with their economic sourcing
obligation under the law.
Construction of new transmission facilities in Chile and Brazil are awarded by auction for which
tariffs, like those of distribution, are benchmarked to the cost of an efficient utility or the
“reference network”. Again in contrast, the Philippine PBR methodology for setting
transmission and distribution tariffs does not de-link tariffs from the utilities’ own cost.
The institutional governance structures in Chile and Brazil are characterized by the clear
delineation of oversight, policy, planning and regulatory responsibilities among separate
agencies that coordinate closely to ensure the efficient operation of the industry. They also
include dispute resolution mechanisms separate from the regulator to facilitate prompt conflict
resolution between the regulator and market agents and among market agents. Expert and
arbitration panels whose members are drawn from the private sector provide a ready
mechanism for the prompt resolution of disputes.
Institutional governance of the Philippine electric power industry to date has been marked by
the virtual withdrawal of the DOE from the scene and the regulator’s insistence on its
independence to the extent of making coordination difficult with other agencies. The JCPC is
perceived by industry stakeholders to be largely passive. The laws creating WESM, the Grid
Management Committee (GMC) and Distribution Management Committee (DMC) all provide for
the creation of Dispute Resolution Mechanisms . Apart from catering only to their respective
concerns; those of the GMC and DMC have yet to be activated. A dispute resolution mechanism
that will mediate all types of conflicts between the regulator and market agents and among all
market agents outside the concerns in WESM and the technical concerns covered by the GMC
and DMC have not been created.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 184
IV PROPOSED REFORMS FOR PHILIPPINE POWER
INDUSTRY
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 185
13 POLICY AND REGULATORY REFORMS
The preceding analysis of the industry’s policy framework and international markets points to a
need for a number of policy and regulatory forms, many of which are urgent. These reforms are
categorized into those that needs to be implemented immediately and in the medium term (1 to
3 years) on the strength of their potential to incent new generation investments and are listed
by their order of importance. Except for the amendment of the horizontal policy and the scope
of NEA’s guarantee provision that require legislative enactment, the foregoing requires no more
than executive/regulatory actions to implement.
13.1 IMMEDIATE REFORMS
13.1.1 COMPETITIVE BIDDING OF FORWARD POWER CONTRACTS
All distribution utilities (PDUs, ECs) should contract for 100% of their energy and capacity
requirements through a public bidding. Therefore the utilities (with the prior endorsement of
the ERC and DOE) shall hold yearly public auctions for contracts with a maximum term of 15
years. Purchases from the spot market shall be limited to 5% of the DUs’ and generators’
contractual imbalances and shall be subject to the payment of penalties to be determined by
the ERC. Standard contract templates to be drawn up by ERC and DOE, generators and DUs .
Contract quantities shall have priority over spot ones in case of planned brownouts due to
supply shortages (no supply guaranty for uncontracted energy in case of rationing). A sample
contract from the Brazil auction is attached .
13.1.2 DEFERMENT OF RETAIL COMPETITION
Retail competition must be deferred until such time that the vital requirements laid down in ERC
Resolution No. 03, Series of 2007 is achieved:
c) Adequacy of generation, transmission networks , and customer switching systems; and
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 186
d) Promulgation by the ERC of all pertinent rules and regulations governing retail
competition and open access. ERC shall determine the timetable with duties and
responsible parties in charge of executing the pending requirements to materialize
RC&OA. Certainty shall be given to the industry in order to allow proper planning.
13.1.3 RESTRUCTURING OF THE OWNERSHIP OF ELECTRIC COOPERATIVES
ECs may be restructured and consolidated to a small group of equity investors to strengthen the
incentives for productive efficiency. In the interim, the energy requirements of the ECs should
be aggregated by grid and tendered in the auction as one. Section 30 of the EPIRA shall be
amended by Congress to allow NEA to act as guarantor for the bilateral contract obligations of
the ECs, instead of their WESM purchases.
13.1.4 LIMITING ERC‟S ADJUSTMENT TO INSTALLED GENERATING CAPACITY
Adjustment to generating capacity must be limited to permanent derating to avoid the possible
circumvention of the grid limits from the declaration of temporary reductions in capacity.
13.2 MEDIUM TERM REFORMS
13.2.1 PROPER IMPLEMENTATION OF THE PBR RATE-SETTING METHODOLOGY
Proper implementation of the PBR rate-setting methodology for transmission and private
distribution utilities and of the RSEC-WR and proposed PBR for Electric Cooperatives to improve
the utilities’ efficiency and moderate the increases in electricity rates.
13.2.2 AMENDMENT OF THE HORIZONTAL SEPARATION POLICY ON GENERATION
Legislative Amendment of the horizontal separation policy on generation such that the grid limit
is based solely on control of the installed generating capacity. In this regard, installed generating
capacity shall cover IPP capacities whose control were ceded by the NPC/PSALM to the
administrators in the IPPA Agreements.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 187
13.2.3 INTERCONNECTION OF LUZON, VISAYAS AND MINDANAO
The Luzon, Visayas and Mindanao grids must be interconnected to mitigate the adverse effect
on energy security of each grid’s high reliance on a single fuel/energy resource.
13.2.4 STRENGTHENING OF THE WESM
The wholesale spot market must be strengthened to incent new generation investments by:
e) Reviewing the system operation and network reliability protocols to make them consistent with consumer valuation;
f) Demand metering to allow consumers to react to changes in the supply and demand balance;
g) Raising the price cap and sticking to it;
h) Creation of operating reserve, financial hedging, capacity markets and market for transmission rights to mitigate market risks and solve the ‘missing money’ problem.
13.2.5 VERTICAL SEPARATION OF GENERATION AND DISTRIBUTION SECTORS
The generation and distribution sectors must be vertically separated (i.e., remove cross-
ownership) to create robust competition in generation.
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 188
14 INSTITUTIONAL GOVERNANCE REFORMS
The weakness of the institutional governance framework has its roots on: (1) the institutional
paralysis of the DOE; (2) weak administrative capacity of the ERC; and (3) a litigious regulatory
process that does not welcome broad participation and consultations and precludes an effective
appeal mechanism to redress grievances.
14.1 DOE’S ASSERTION OF ITS AUTHORITY UNDER EPIRA
The institutional paralysis of the DOE is self-inflicted and stems from its misreading of, rather
than an actual downgrading of its role under the law. There are anecdotal evidences to support
the view that the mass exodus of its staff after the EPIRA was caused more by frustration over
the perceived diminution of its role rather than from low salaries. The DOE must step up into
the plate; assert is authority and deliver on its responsibilities under the law.
14.2 STRENGTHENING OF ADMINISTRATIVE CAPACITY OF ERC THROUGH FINANCIAL
AUTONOMY AND MAINTAINING A BALANCE OF EXPERTISE
Strengthening the administrative capacity of ERC will require first, financial autonomy either
through an automatic appropriation of its budget or by allowing the agency to keep and spend
its collections instead of these being remitted to the National Treasury; and second,
maintaining a balance of expertise in the Commission, i.e., finance rather than accounting
(financial policy and strategy is more critical than accounting ); power engineers (not just any
engineer); regulatory economists (or in their absence, micro rather than macro economists); and
lawyers. The present composition of the Commission and its top executive management which
is dominated by lawyers should be restructured to achieve a more balanced composition of
these disciplines. Regulation of infrastructure industries such as the electric power industry is
more about economics rather than law and involves the consideration of the economic, financial,
and technical impact of regulatory decisions rather than on the establishment and conformity
with legal precedents that may be irrelevant to the case on hand. The current set-up where the
Commissioners are appointed by the President need not be changed. However, the names and
Philippine Electric Power Industry Market and Policy Assessment and Analysis of International Markets
Final Report
University of the Philippines – National Engineering Center 189
Malacanang , DOE and ERC websites so that a public vetting process takes place before their
appointment by the President.
14.3 FLEXIBILITY IN THE REGULATORY PROCESSES
Short of abrogating the quasi-judicial character of the ERC (that will require legislative
amendment); what is required is flexibility in the regulator’s processes that will: (1) invite broad
debate of and meaningful participation by all stakeholders; (2) deepen the scope of the debate
to relevant economic, technical and social issues instead of confining them to legal procedures
and precedents; and (3) provide for an effective appeal mechanism. On the latter, the ERC could
hire more “arbitrators and “conciliators” akin to those at the National Labor Relations and
Conciliation (NLRCC) Board and the Construction Board rather than requiring all cases to be
heard by the Commission and immediately appealed to the Courts. In addition, a single panel of
experts, with a permanent chair and varying members depending on the issue on hand could be
formed to resolve disputes between the regulator and market agents and among market agents.
The dispute settlement mechanism of WESM, GMC and DMC could be constituted as sub-groups
reporting to this Experts’ Panel when the issues arise from or are within their jurisdictions.
******