peter ross - ldo group & lake coal
TRANSCRIPT
LakeCoal – Chain Valley Operation 1
Chain Valley
LONGWALL OPERATION
LakeCoal – Chain Valley Operation 2
• Chain Valley
Colliery(CVC) is located
on the southern shores
of Lake Macquarie in
Central NSW;
• CVC commenced
production in 1962 to
supply the neighbouring
Vales Point Power
Station.
• Current owners acquired
80% of CVC in 2009 and
the remaining 20% in
2010.
Background
Background
LakeCoal – Chain Valley Operation 3
Background
LakeCoal – Chain Valley Operation 4
Background
• 2010 decision to take the mine from bord and pillar to
miniwall method of mining;
• Chinese manufacturer selected;
• September 2011 Miniwall mining commenced at CVC
with a 61.25m face;
• June 2012 extended to 86.2m face adding an additional
14 roof supports and AFC components;
LakeCoal – Chain Valley Operation 5
Our Challenges
• Difficult conditions with
significant strata issues;
• Place change method
of mining;
• Constrained underground
coal clearance system;
• Limited reserves / life;
• Inadequate ventilation infrastructure;
• Aging infrastructure and equipment;
• Transportation of coal (truck haulage).LakeCoal – Chain Valley Operation 6
What we put in place
• Introduction of continuous miners with on-board bolters;
• Improved strata
management
systems – support
optimisation
strategies, secondary
support regime,
routine geotechnical
mapping and
monitoring;
LakeCoal – Chain Valley Operation 7
LakeCoal – Chain Valley Operation 8
What we had
What we have now
Where we are now –
Longwall Mining
Longwall Supplier Selection
• Developed a close relationship
with a Chinese manufacturer for
the supply of mechanical and
structural components of a
longwall mining system.
• The main drivers for this liaison
were:
Price, Availability and
Design-build to mine requirements
LakeCoal – Chain Valley Operation 9
Build
• Business risk assessment
undertaken on utilising unproven
Chinese equipment in Australia.
• Use of Chinese motors that
required IEC approval.
• During build process audits and
design verification undertaken
by a third party.
• Supports tested to consol 30K
cycles with an exceptional
outcome – previously never undertaken in ChinaLakeCoal – Chain Valley Operation 10
Where we are now –
Longwall Mining
Specifications
LakeCoal – Chain Valley Operation 11
Where we are now –
Longwall Mining
Component Comment
Width 61.25m – 86.2m
Shearer manufacturer Bucyrus
Type Electra EL 2000 DERDS
Drum dia MG – 2m / TG – 2m
Cutting height/method/
web depth
3.2 – 3.5m / Uni-di / 750mm
Install power 1275 kW
Roof support manufacturer SIWEI
Specifications
LakeCoal – Chain Valley Operation 12
Where we are now –
Longwall Mining
Component Comment
Type/Number of Supports 2-leg chock shield / 38-52
Yield load/working
range/control
800 t 1.8 – 3.9m / Tiefenbach
Face conveyor
manufacturer
IMM, SGZ800/200 twin
inboard
Chain speed &
manufacturer
1.2 m/s – Parsons
Motors 1 x 250 kW
Beam stageloader IMM, SZZ800 / 200, 200 kW
Coal crusher IMM, PLM 2000, 200 kW
Coal clearance (to surface) Conveyor / 600tph
• 61.25m Longwall commenced MW Block 1 in September
2011 – 10 months from conception to implementation.
• In June 2012 block 3 was extended to 86.2m adding an
additional 14 roof supports and AFC components.
Chain Valley is the first
underground mine to
implement and successfully
complete a Chinese
manufactured longwall in
Australia!
LakeCoal – Chain Valley Operation 13
Where we are now –
Longwall Mining
Longwall Production
LakeCoal – Chain Valley Operation 14
Where we are now –
Longwall Mining
Year Retreat (m) Production (t)
2011 ^ 691 228,456
2012 1,791 710,295
2013 1,407 652,654
2014 2,372 1,115,277
2015 2,345 1,091,986
2016 * 2,198 1,020,520
* Forecast^ Miniwall production commenced 27/9/11
Total retreat (m) 10,804
Total production (t) 4,819,188
Average Face Utilisation 82%
Longwall Shear Rate
LakeCoal – Chain Valley Operation 15
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16 Jul-16
Target (1.3 shears/hr)
Where we are now –
Longwall Mining
Production
LakeCoal – Chain Valley Operation 16
* End of year projection
YearTotal
Production (tonnes)
Manning Tonnes/Man
2009 581,354
2010 556,530
2011 686,700
2012 1,076,933 186 5,790
2013 923,273 203 4,548
2014 1,368,270 165 8,293
2015 1,343,377 154 8,723
2016 1,326,000* 122 10,869
Where we are now –
Longwall Mining
• Secured sub-lease with neighbouring collieries
enabling:
• An increase in current reserves in both the GNS and
Fassi Seams from 25 Mt to 75 Mt;
• Accessibility to Mannering Colliery pit top and coal
clearance system;
• Link Road Project (LRP) linking Chain Valleyand
Mannering underground workings.
LakeCoal – Chain Valley Operation 17
Where we are now –
CVC Extension
LakeCoal – Chain Valley Operation 18
Where we are now –
CVC ExtensionLRP Plan
• Post LRP
• Increase in annual production;
• Increase of underground coal clearance capacity;
• Modern and reliable trunk and drift belt system;
• Higher surge capacity;
• Direct overland conveyor to Power Station;
• Utilisation of Power Station stockpile for truck loading
for export.
LakeCoal – Chain Valley Operation 19
Where we are heading
• Moonee / Newvale area
• Secured sub-lease over Newvale area
• Granted EL over Moonee area;
• Combined additional reserves ~37Mt.
• Rail loop
• Expansion of existing VPPS rail unloading facility to
allow rail haulage to Port;
• Development of a private land haul road from current
stockpile areas to proposed rail loader
• Additional Longwall
• Allowing increase in production to ~3Mtpa
LakeCoal – Chain Valley Operation 20
Where we are heading