Primavera PERT Master –

The Risk Analysis Tool

Page 2: PERT Master - Risk Analysis Tool

Presentation Agenda• What is PERT Master ?• Project Risk Management Concepts• Introductory Demonstrations– Importing from Primavera– Quick Risk Templates– Running a Risk Analysis– Risk Register with schedule

• Advanced Risk Management– Schedule cost loading techniques– Probabilistic cash flow and profitability breakeven

04/28/23

Page 3: PERT Master - Risk Analysis Tool

What is PERT Master ?

• PERT Master Focus– Specialist in Project Risk Management– Full Lifecycle risk solution– Faithful to project scheduling

• PERT Master Vision– “Improved decision making

through project intelligence”

04/28/23

Management Reserve

Mitigation Cost/Effort

Contingency

Budget / Schedule Estimate

Maximize Profit

Tota

l Pro

ject

Cos

t

“Strategic Decisions”

“Maximize Return”

“Proper Allocation”

“Minimize Uncertainty”

Page 4: PERT Master - Risk Analysis Tool

Life Value Proposition

04/28/23

•High estimate uncertainty•Little Known about risk events

SANCTION

Alternative selection (rig

A/B/C, own)

-15% to +30% Estimate

Capital Investment risk

analysis

PHASE 2

FEED Front End Engineering

Design

+/-10% Estimate

Schedule based cost risk analysis

PHASE 3

Execution Detailed Eng. &

Procurement

+/- 3% Estimate

Risk event / register analysis

PHASE 4

Opportunity (e.g. oil field)

Wild Guess (WAG)

Operations Detailed Eng. &

Procurement

No Estimate Uncertainty

Risk event monitoring

PHASE 1 PHASE 5

Market/Investment risk analysis

“DOING RIGHT PROJECTS” “DOING PROJECTS RIGHT”PLAN YOUR WORK WORK YOUR PLAN

•Estimate uncertainty – Low•Discrete risk events

Page 5: PERT Master - Risk Analysis Tool

Life Value Proposition

04/28/23

•High estimate uncertainty•Little Known about risk events

SANCTION

Alternative selection (rig

A/B/C, own)

-15% to +30% Estimate

Capital Investment risk

analysis

PHASE 2

FEED Front End Engineering

Design

+/-10% Estimate

Schedule based cost risk analysis

PHASE 3

Execution Detailed Eng. &

Procurement

+/- 3% Estimate

Risk event / register analysis

PHASE 4

Opportunity (e.g. oil field)

WAG

Operations Detailed Eng. &

Procurement

No Estimate Uncertainty

Risk event monitoring

PHASE 1 PHASE 5

Market/Investment risk analysis

“DOING RIGHT PROJECTS” “DOING PROJECTS RIGHT”

PLAN YOUR WORK WORK YOUR PLAN

•Estimate uncertainty – Low•Discrete risk events

CORPORATE REVENUE ANALYSIS

PORTFOLIO ANALYSIS PROJECT ANALYSIS

Page 6: PERT Master - Risk Analysis Tool

Risk Vs Schedule

• Realistic /Most Likely

• Aggressive / Optimistic

• Cautious / Pessimistic

• Scale to Fit

04/28/23

Page 7: PERT Master - Risk Analysis Tool

Types of Risks• Uncertainty

– PERT Master handles uncertainty by using three point

estimate distributions minimum, most likely and maximum

• Risk Events

– PERT Master handles risk events by using risk register to

enter possible events along with estimates of each one’s

probability and potential impacts on duration, cost and

project quality

04/28/23

Uncertainty + Risk Events = Total Risk Exposure

Page 8: PERT Master - Risk Analysis Tool

Types of Risk - Uncertainty

04/28/23

Duration/Cost

E.g. How long does it take to do wiring?

Page 9: PERT Master - Risk Analysis Tool

Types of Risk

04/28/23

Activity A

?Activity C

Activity BE.g. Do we need to replace old wiring?

Page 10: PERT Master - Risk Analysis Tool

Branching – Probabilistic & Conditional

04/28/23

Scenario: Renovate the Premises– Remove wiring (50% probability)– Repair wiring (40% probability)– Install new wiring (10% probability)

Page 11: PERT Master - Risk Analysis Tool

Template Quick Risk

04/28/23

Page 12: PERT Master - Risk Analysis Tool

Types Of Risks - Risk Events

• Single Impact

• Series of Impact

• Multiple exclusive impacts

• Multiple impacts to multiple activities

04/28/23

Page 13: PERT Master - Risk Analysis Tool

Risk Register

04/28/23

Page 14: PERT Master - Risk Analysis Tool

Risk Register

04/28/23

Page 15: PERT Master - Risk Analysis Tool

Monte Carlo Simulation

04/28/23

7 8 9 10 11 12 13 14 15 16 17Min Likely Max

• Range forms an envelope• One segment is selected for each envelope• Hidden critical paths revealed

Page 16: PERT Master - Risk Analysis Tool

Monte Carlo Simulation

04/28/23

7 8 9 10 11 12 13 14 15 16 17Min Likely Max

• Range forms an envelope• One segment is selected for each envelope• Hidden critical paths revealed

ITERATION

123456789

10 DAYS9 DAYS

14 DAYS17 DAYS

11 DAYS7

DAYS10 DAYS

12 DAYS6 DAYS

Page 17: PERT Master - Risk Analysis Tool

PERT Master Risk Analysis Methodology• Risk Ready State

– Schedule : Sound logic– Scheduling errors

• Risk Inputs– Estimate Uncertainty: “Quick Risk”– Risk Events: risk register

• Risk Impacts– Map risks to tasks

• Risk Analysis– Monte Carlo Simulation– Risk hot spots

04/28/23

Page 18: PERT Master - Risk Analysis Tool

PERT Master Risk Analysis Methodology

• Risk Response– Determination of Contingency– Mitigation Scenarios– Probabilistic cashflow

04/28/23

Page 19: PERT Master - Risk Analysis Tool

Plan Validation: Schedule Check

04/28/23

Page 20: PERT Master - Risk Analysis Tool

Initial Risk Inputs – Quick Risk Analysis

04/28/23

Page 21: PERT Master - Risk Analysis Tool

Accuracy with Ease

04/28/23

Page 22: PERT Master - Risk Analysis Tool

Risk Outputs