personal protective grounding - training presentation

Upload: irfan-ullah

Post on 14-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    1/31

    1

    Personal ProtectiveGrounding Standard

    Establishing and Ensuring a SafeWork Environment

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    2/31

    2

    Introduction

    The following information is provided as an overview of

    the new Personal Protective Grounding standard.

    The presentation provides key elements of the standard.

    Further details of the standard are listed in the document

    and will require review to ensure all aspects of the

    standard are clear and understood.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    3/31

    3

    Purpose

    The Personal Protective Grounding standard is designed to:

    Prove that the electrical circuit or equipment is in fact

    removed from a dynamic source of electrical energy.

    Provide protection in the case of accidental re-energizationthat may be caused by operator error, contact with

    neighboring circuits, lightning, backfeed, insulator failure,

    etc.

    Provide protection from electrostatic and electromagneticinduction that may be caused by adjacent energized circuits,

    wind or energized equipment.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    4/31

    4

    Regional Responsibilities

    Using the standard each AES Operation must:

    Develop a site specific Program that complies with the

    Personal Protective Grounding standard

    Ensure all applicable governmental regulations regarding

    the Personal Protective Grounding procedures are

    complied with.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    5/31

    5

    Application

    The Personal Protective Grounding standard applies to:

    All work on de-energized circuits of overhead and

    underground transmission and distribution systems, and

    in substations.Exemptions

    Electrical protection and grounding for conductor stringing

    operations is covered in a separate standard.

    Electrical protection for people working around boom-

    equipped vehicles in the vicinity of live circuits is covered

    in a separate standard.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    6/31

    6

    There are a number of Definitions provided in the

    standard to provide explanations for the various

    terms used. The following are some examples:

    Protective Grounding (Earthing) Effectivelyconnecting an electrical circuit or electrical

    equipment to ground/earth potential.

    BondingConnecting all grounds (bonds) to a

    single point to eliminate differences of potential at awork site.

    Definitions of Terms

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    7/31

    7

    Definition of Terms contd

    Bonding Principle Bonds are installed so that a workeris kept in an equipotential zone. A worker must not beable to bridge between a grounded circuit and anyunbonded structure, vehicle, boom, wire or any other

    object that is not tied into the bonded network.

    Grounding Principle Protective grounds are installed toreduce any current flow through a worker to an acceptablelevel by providing a low resistant parallel shunt around the

    worker. If the circuit is, or becomes energized, thegrounds must be large enough to withstand any faultcurrent in the circuit.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    8/31

    8

    Definition of Terms contd

    Bracket Grounding (box grounding) Grounding ateach potential source, not more than 2 miles (3km) oneach side of the work site. Bracket Grounding shall onlybe applied when no possible source of re-energizationmay occur.

    Equipotential GroundingGrounding and bondingtogether all objects, including the structure to a singlepoint to eliminate differences of potential at a work site.

    Grounding Plan An approved written document for

    planning the complete isolation of a circuit and thelocations for the installation of protective grounds.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    9/31

    9

    Guiding Principles and Rules:

    Working on an isolated electrical circuit, or equipmentwithout personal protective grounds, has the potential tokill or cause serious physical harm.

    Proper grounding ensures the correct isolated circuit is

    identified, the circuit is protected from accidentally beingreenergized and high inductive voltage and/or current isreduced to safe levels.

    If a circuit is isolated in order to carry out the work safely,then the circuit must be grounded.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    10/31

    10

    Guiding Principles and Rules: contd

    To be assured that a person will not be exposed to any

    hazardous current or voltage after the protective grounds

    are installed, the installation of the protective grounds

    must comply with the Grounding Principle and the

    Bonding Principle.

    When there is a need for an exception to equipotential

    grounding, such as the installation of bracket grounds, a

    written protective grounding plan must be prepared and

    approved

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    11/31

    11

    Guiding Principles and Rules: contd

    The Grounding Principle

    Protective grounds are installed to reduce any current flow

    through a worker to an acceptable level by providing a low

    resistant parallel shunt around the worker. If the circuit isor becomes energized, the grounds must be big enough to

    withstand any fault current in the circuit.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    12/31

    12

    Guiding Principles and Rules: contd

    To adhere to the Grounding Principle

    The available fault current at each substation and for eachcircuit must be determined so that the correct size groundsets can be specified.

    The ground set specified must be able to withstand thefault current for a time necessary to clear the fault. Theminimum size cable must be # 2 copper.

    The ground sets must be tested at least annually to

    ensure that they will continue to provide a low resistantpath around a worker.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    13/31

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    14/31

    14

    Guiding Principles and Rules: contd

    To Adhere to the Bonding Principle

    Equipotential (single point) grounds or bonds must be

    installed at the point of work so that a person will not be

    subject to any potential difference between any objectsthat can be contacted. The structure must be bonded to

    the grounds.

    Equipotential bonding on underground systems must be

    put in place by working from a ground gradient control matbonded to the equipment or cable.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    15/31

    15

    Requirements

    Each owned and/or operated facility must develop and

    implement a ProtectiveGrounding Program that at a

    minimum contains the following elements:

    Written Program Elements

    Procedural Elements

    Program Administration

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    16/31

    16

    Written Program Elements

    The Protective GroundingProgram must have the followingwritten program elements:

    Be legible, readable, and accessible to all operationspersonnel.

    The written program must identify the position in theoperation that is ultimately responsible for theimplementation and maintenance of the operationsProtective Grounding Procedure.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    17/31

    17

    Written Program Elements

    Written program elements contd:

    The written program must clearly and specifically outlinethe scope, purpose, responsibility, authorization, rules,and techniques to be applied to the use of Protective

    Grounding and the measures to enforce compliance withthe program.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    18/31

    18

    Procedural Elements

    The Protective GroundingProgram must have the followingprocedural elements:

    Arranging for De-energization of the Circuit - Theprocedure must have the requirement that a circuit isguaranteed to be isolated and remain isolated and thattags and/or locks are on isolation points as per the AESOperations lock out/ tag out procedure.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    19/31

    19

    Procedural Elements

    Procedural element contd:

    Determining Suitable Grounding Location(s) - Grounds

    must be placed at the point of work in an Equipotential

    Zone configuration.Bracket grounding does not adequately protect workers

    from accidental re-energization. Bracket grounding shall

    only be applied when there is no possible source of re-

    energization. Bracket grounding requires the preparationof a grounding plan approved by a supervisor.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    20/31

    20

    Procedural Elements

    Procedural element contd:

    Determining the Proper Grounding Assembly or Set -

    The grounding set must be large enough to carry the full

    fault current available at the work location, to ground andstay intact until the circuit protection opens.

    Each AES Operation must determine the fault current

    availability for the circuits to be worked on. Circuits that

    require ground sets larger than the minimum establishedsize (# 2 copper) must be determined and the ground set

    requirements specified for each of these circuits.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    21/31

    21

    Procedural Elements

    Procedural element contd:

    Choosing the Most Effective Ground Electrode -The

    grounding set must be large enough to carry the full fault

    current available at the work location, to ground and stayintact until the circuit protection opens.

    Each AES Operation must determine the fault current

    availability for the circuits to be worked on. Circuits that

    require ground sets larger than the minimum establishedsize (# 2 copper) must be determined and the ground set

    requirements specified for each of these circuits.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    22/31

    22

    Procedural Elements

    Procedural elements contd :

    Connecting to the Ground Electrode - The connectionto the ground electrode must be made before any otherconnections and must be removed last.

    Establishing a Bonded Work Zone at the Work Site -Grounds must be installed to establish the bond betweenthe ground electrode and the structure. To keepeverything in the work zone bonded, any wires or winchcables brought into the work zone need to be bonded to

    the same ground electrode.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    23/31

    23

    Procedural Elements

    Procedural elements contd:

    Establishing a Bonded Area on the Ground - Workers

    on the ground that are handling conductors are outside of

    the bonded zone and need to use rubber gloves or inmore hazardous situations, work from ground gradient

    mats.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    24/31

    24

    Procedural Elements

    Procedural elements contd:

    Testing the Circuit to be Grounded to Verify Isolation -

    The AES Operation must use an approved potential tester

    to verify that the circuit is isolated. Buzzing or teasing isnot a reliable method to distinguish between induction or

    static charges and dynamically alive circuits.

    Ensuring Low Resistant Connections - The conductor

    and the inside of the ground set conductor clamps mustbe clean. The ground set must be visually checked,

    maintained and tested at least annually.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    25/31

    25

    Procedural Elements

    Procedural elements contd:

    Installing the Ground Clamps on the Phase

    Conductors - All personnel must be either completely in

    or completely out of the planned bonded work zone beforeinstalling the protective grounds.

    Live line or Hot Stick tools must be used and proper eye

    protection must be worn when installing ground clamps.

    The proper sequence for installing the conductor clampsshould be specified in the Protective Grounding Program.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    26/31

    26

    Procedural Elements

    Procedural elements contd:

    Removing Grounds - Grounds should be removed in the

    reverse order to which they were installed.

    In high induction areas, removing the grounds caninterrupt current and drop voltage. Therefore, live line

    tools must be used and eye protective must be worn when

    removing grounds.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    27/31

    27

    Procedural Elements

    Procedural elements contd:

    Preparation of a Protective Grounding Plan - Each

    AES Operation should prepare a protective grounding

    plan where bracket grounding is used to protect theworker. See Appendix A of the Standard for an example

    of a protective grounding plan.

    The plan needs to show the extra steps taken to ensure

    that the risk of accidental re-energization from dynamicsources is as low as reasonably achievable.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    28/31

    28

    Program Administration

    The Protective GroundingProgram must have the

    following program administrative elements:

    Enforcement - of the AES Standard and Program

    Clearly Defined Roles Responsibilities - for those

    positions involved in protective grounding.

    Inspections - Inspection of the application of grounds by

    Operations Supervisory staff.

    Audits - Annual audits to determine the effectiveness of

    the Protective Grounding program.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    29/31

    29

    Program Administration

    Program administrative elements contd:

    Training - All employees that install, remove and inspect

    grounds must be trained and knowledgeable on

    grounding and bonding principles, procedures forinstallation and removal of grounds and testing and

    maintenance procedures.

    Maintenance - At least annually, ground sets must be

    inspected, maintained and tested with a ground set tester.

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    30/31

    30

    Conclusion

    Applying the Personal Protective Grounding standard willallow a Region, facility, work group or contractors to worksafely and be protected from hazardous energy sources ifimplemented correctly

    The Region must ensure proper implementation of aPersonal Protective Grounding program

    Employees must ensure individual Personal ProtectiveGrounding responsibilities are complied with to protect

    themselves and others when working in a hazardousenergy work environment

  • 7/27/2019 Personal Protective Grounding - Training Presentation

    31/31

    31

    Key To Successful Personal

    Protective Grounding

    Everybody working together to

    establish a trusted and safe work

    environment.