Permit Approval Booklet Southern Landing Subdivision Old School Lane (SCR 654) at Cedar Drive (SCR 349A) Town of Millville Sussex County Delaware Tax I.D. 134-12.00-419.00, 419.01 & 419.02 Contents: 1. Permit Expiration List (xx/xx/xx) 2. Town of Millville Preliminary (2/12/19) & Final Approvals (xx/xx/xx) 3. Stormwater Management Approval (3/6/20) and NOI (2/25/20) 4. DelDOT Letter Of No Objection (2/6/20) and Entrance Approval (2/25/20) 5. Sussex County Engineering Sewer Approval (2/7/20) and DNREC Sewer Permit (3/17/20) 6. Town of Millville Engineering Approval (xx/xx/xx) 7. Water Service Approval (2/4/20 Contingent) and Water System Permit (3/26/20) 7. Fire Marshal Site Plan Approval (4/29/19) 8. Sussex County Addressing Subdivision Name Approval (10/29/18) and Street Name Approval (10/29/18) LANDDESIGN, Inc. Attn. Thomas J. Ford III Oak Square, Suite 3 53 Atlantic Avenue Ocean View, De. 19970 302/537-1919; 302/539-0328Fax Updated: April 6, 2020

Upload: others

Post on 30-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

Permit Approval Booklet

Southern Landing Subdivision

Old School Lane (SCR 654) at Cedar Drive (SCR 349A)

Town of Millville Sussex County Delaware

Tax I.D. 134-12.00-419.00, 419.01 & 419.02

Contents:

1. Permit Expiration List (xx/xx/xx)

2. Town of Millville Preliminary (2/12/19) & Final Approvals (xx/xx/xx)

3. Stormwater Management Approval (3/6/20) and NOI (2/25/20)

4. DelDOT Letter Of No Objection (2/6/20) and Entrance Approval (2/25/20)

5. Sussex County Engineering Sewer Approval (2/7/20) and DNREC Sewer

Permit (3/17/20)

6. Town of Millville Engineering Approval (xx/xx/xx)

7. Water Service Approval (2/4/20 Contingent) and Water System Permit

(3/26/20)

7. Fire Marshal Site Plan Approval (4/29/19)

8. Sussex County Addressing Subdivision Name Approval (10/29/18) and Street

Name Approval (10/29/18)

LANDDESIGN, Inc. Attn. Thomas J. Ford III

Oak Square, Suite 3

53 Atlantic Avenue

Ocean View, De. 19970 302/537-1919; 302/539-0328Fax Updated: April 6, 2020

Page 2: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 3: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

Southern LandingPermit Approvals and Expirations Updated: 4/6/2020

Town of MillvilleClient: Miken Builders, Inc.

Town Final Approval Agency: Town of Millville Planning &Zoning

Approval Date: xx/xx/xx Expiration Date: xx/xx/xx

Stormwater Mgmt. Approval Agency: Sussex Conservation District

Approval Date: 3/6/2020 Expiration Date: 3/5/2025

DelDOT LONO Agency: DelDOT

Approval Date: 2/6/2020 Expiration Date: 2/5/2025

DelDOT Entrance Approval Agency: DelDOT

Approval Date: 2/25/2020 Expiration Date: 2/24/2023

Sussex County Sewer Approval Agency: Sussex County Engineering

Approval Date: 2/7/2020 Expiration Date: 2/6/2023

Sanitary Sewer Permit Agency: DNREC

Approval Date: 3/17/2020 Expiration Date: 3/16/2023

Town of Millville Engineering Approval Agency: Town of Millville/ GMB

Approval Date: xx/xx/xx Expiration Date: xx/xx/xx

Water Service Approval Agency: Tidewater Utilities

Approval Date: 2/4/2020 Expiration Date: xx/xx/xx

Water System permit Agency: DE Office of Drinking Water

Approval Date: 3/26/2020 Expiration Date: 3/26/2021

Fire Protection Site Approval Agency: Office of State Fire Marshal

Approval Date: 4/29/2019* Expiration Date: N/A

Street & Subdivision Names Agency: Sussex County Mapping & Addressing

Approval Date: 10/29/2018 Expiration Date: N/A

LANDDESIGN, Inc.

Permit Contact History

Page 4: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 5: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 6: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 7: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 8: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 9: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 10: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 11: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 12: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 13: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 14: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 15: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

February 06, 2020 Mr. Jamie Whitehouse, Director Sussex County Planning & Zoning Commission Sussex County Administration Building P.O. Box 417 Georgetown, Delaware 19947 SUBJECT: Letter of No Objection to Recordation

Southern Landing Tax Parcel # 134-12.00-419.01, 134-12.00-419.00 SCR349A-CEDAR DRIVE SCR654-OLD SCHOOL LANE Millville, Baltimore Hundred, Sussex County

Dear Mr. Whitehouse:

The Department of Transportation has reviewed the Site Plan, dated April 1, 2019 (last revised January 29, 2020), for the above referenced site, and has no objection to its recordation as shown on the enclosed drawings. This "No Objection to Recordation” approval shall be valid for a period of five (5) years. If the Site Plan is not recorded prior to the expiration of the "No Objection to Recordation”, then the plan must be updated to meet current requirements and resubmitted for review and approval.

This letter does not authorize the commencement of entrance construction. Entrance

plans shall be developed in accordance with DelDOT's Development Coordination Manual and submitted to the Development Coordination Section for review and approval.

This “No Objection to Recordation” letter is not a DelDOT endorsement of the project

discussed above. Rather, it is a recitation of the transportation improvements, which the applicant may be required to make as a pre-condition to recordation steps and deed restrictions as required by the respective county/municipality in which the project is located. If transportation investments are necessary, they are based on an analysis of the proposed project, its location, and its estimated impact on traffic movements and densities. The required improvements conform to DelDOT’s published rules, regulations and standards. Ultimate responsibility for the approval of any project rests with the local government in which the land use decisions are authorized. There may be other reasons (environmental, historic, neighborhood composition, etc.) which compel

Page 16: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

Southern Landing Mr. Jamie Whitehouse Page 2 February 06, 2020

that jurisdiction to modify or reject this proposed plan even though DelDOT has established that these enumerated transportation improvements are acceptable.

If I can be of any further assistance, please call me at (302) 760-2266.

Very truly yours,

Susanne K. Laws Sussex County Review Coordinator

Development Coordination cc: Michael Cummings, Miken Builders

Ray Blakeney, Land Design, Inc. William Kirsch, South District Entrance Permit Supervisor Rusty Warrington, Sussex County Planning & Zoning Jessica L. Watson, Sussex Conservation District Gemez W. Norwood, South District Public Work Manager Jennifer Pinkerton, Chief Materials & Research Engineer Chris Sylvester, Traffic Studies Manager Linda Osiecki, Pedestrian Coordinator John Fiori, Bicycle Coordinator Mark Galipo, Traffic Development Coordination Engineer Tim Phillips, Maintenance Support Manager Dan Thompson, Safety Officer North District Jared Kaufman, DTC Planner James Kelley, JMT Todd Sammons, Subdivision Engineer

Kevin Hickman, Sussex County Reviewer

Page 17: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

February 25, 2020

Mr. Ray Blakeney

Land Design, Inc.

Oak Square Suite 3

Ocean View, Delaware 19970

SUBJECT: Entrance Plan Approval Letter

Southern Landing

Tax Parcel #134-12.00-419.01, 134-12.00-419.00

SCR349A-CEDAR DRIVE

SCR654-OLD SCHOOL LANE

Millville, Baltimore Hundred, Sussex County

Dear Mr. Blakeney:

The Department of Transportation has reviewed the Commercial Entrance Plans dated

July 11, 2019 (last revised January 30, 2020) for the referenced project and determined that they

are in general conformance with the Department’s current regulations, specifications and

standard details. By signing and sealing the plan set, the developer’s engineer is responsible for

accuracy of content. Any errors, omissions or required field changes will be the responsibility of

the developer. This plan approval shall be valid a period of three (3) years. If an entrance permit

has not been obtained within three years, then the plans must be updated to meet current

requirements and resubmitted for review and approval.

This letter does not authorize the commencement of entrance construction. The

following items will be required prior to the permit being issued. A pre-construction

meeting may be required as determined by the South District Public Works office.

1. A copy of the recorded Site Plan which is consistent with the DelDOT “No Objection

to Recordation” stamped plan and all appropriate signatures, seals, plot book and

page number.

2. Three (3) copies of the approved entrance plans.

3. Completed permit application.

4. Executed agreements (i.e. construction, signal, letter).

5. An itemized construction cost estimate.

6. A 150% security based upon an approved itemized construction cost estimate and W-

9 form (if providing escrow).

Page 18: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

Southern Landing

Mr. Blakeney

Page 2

February 25, 2020

7. A letter of source of materials, work schedule, list of subcontractors, emergency

telephone numbers and names of contact persons.

Please contact the South District Public Works office (302) 853-1340 concerning any

questions you may have relative to the aforementioned required items.

Sincerely,

Susanne K. Laws

Sussex County Review Coordinator

Development Coordination

cc: Michael Cummings, Miken Builders

Deborah Botchie, Millville Town Manager

Jamie Whitehouse, Sussex County Planning & Zoning Commission

Rusty Warrington, Sussex County Planning & Zoning

Jessica L. Watson, Sussex Conservation District

Gemez Norwood, South District Public Work Manager

James Argo, South District Project Reviewer

William Kirsch, South District Entrance Permit Supervisor

Robert Bragg, South District Subdivision Manager

Jerry Nagyiski, Safety Officer Supervisor

Chris Sylvester, Traffic Studies Manager

Jennifer Pinkerton, Chief Materials & Research Engineer

Linda Osiecki, Pedestrian Coordinator

John Fiori, Bicycle Coordinator

Mark Galipo, Traffic Development Coordination Engineer

Tim Phillips, Maintenance Support Manager

Dan Thompson, Safety Officer North District

Jared Kaufman, DTC Planner

James Kelley, JMT

Todd Sammons, Subdivision Engineer

Kevin Hickman, Sussex County Reviewer

Page 19: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 20: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 21: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 22: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 23: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 24: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 25: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 26: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 27: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 28: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 29: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

From: Tawanda Priester <[email protected]> To: Byron Jefferson <[email protected]> Cc: Tom Ford <[email protected]>; [email protected] <[email protected]> Sent: Tue, Feb 4, 2020 11:31 am Subject: RE: Plan Review #4 for Southern Landing To:you + 2 more Details

Plan Approval App rev.10 form.... (49 KB)

Byron, At this time, TUI has no further comments. Prior to final approval, the following open items must be completed:

1. WSA agreement must be executed between TUI and the developer and the income liability taxes must be paid. To initiate the process, the developer should contact Kirsten Higgins at [email protected] or by phone at 302-747-1325. 2. DelDOT permit must be completed. Please contact Josh Turner at [email protected] to electronically submit the DelDOT permit.

Once the open items are completed, the following documentation may be submitted for final approval:

1. Completed plan approval application, signed and dated. Attached is the latest application. 2. Hard copies of all permits. 3. One hard copy of the recorded record plat for the subdivision with book and page. 4. Three copies of final plans sealed by a professional engineer registered in the State of Delaware. Final plans should include: cover sheet, utility plans, profiles, water details, and water notes. 5. Electronic files on CD:

a. Final water utility plan in full .dwg format (AutoCAD 2018 or earlier versions) and in .pdf format. b. Recorded record plat in .pdf format.

Thank you, Tawanda Priester Staff Engineer

Page 30: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 31: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 32: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 33: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 34: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 35: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 36: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 37: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 38: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 39: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

October 29, 2018

LANDDESIGN Attn: Ray Blakeney RE: Proposed Subdivision Name(s) I have reviewed the name(s) submitted for your proposed subdivision Southern Landing, which is located in Town of Millville (134-12.00-419.00 & 419.01). In reviewing the proposed name(s) the following has been approved for this subdivision:

SOUTHERN LANDING

Should you have any questions please contact the Sussex County Addressing Department at 302-853-5888 or 302-855-1176.

Sincerely,

Terri L Dukes

Terri L. Dukes Addressing Technician II CC: Christin Headley Planning & Zoning

Page 40: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance
Page 41: Permit Approval Booklet Southern Landing...Jan 30, 2020  · This letter does not authorize the commencement of entrance construction. Entrance plans shall be developed in accordance

LANDDESIGN Attn: Ray Blakeney

RE: Southern Landing I have received proposed street name(s) for the new subdivision, Southern Landing, located in Town of Millville. In reviewing the proposed street name(s) the following have been approved:

Sweetgrass Ln

Use only approved road names that you have written confirmation for or you will be required to rerecord. Each street name is to be used only once.

Upon final approval of Southern Landing please forward a copy of the recorded site plan to my attention. Our office would appreciate a digital copy if at all possible for the purpose of addressing. Should you have any questions, please contact the Sussex County Addressing Department at 302-855-1176. Sincerely,

Terri L.Dukes Terri L.Dukes Addressing Technician II CC: Christin Headley Planning & Zoning