pepci project permit to work procedure code 3.pdf

Upload: hk

Post on 25-Feb-2018

236 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    1/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 1 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Type of Modification to FEED Deliverables:

    Type 1 FEED without change

    Type 2 FEED + adaptations

    X Type 4 New Document

    01R 17/01/2014 EPCI IFR - Issued For ReviewM. PARIS/Y.

    MOONP.

    VILLAIN

    A.

    POINCHEVAL

    /Y. G KANG

    Rev DateDD/MM/YY

    YY

    STATUS WRITTEN BY(name & visa)

    CHECKED BY(name & visa)

    APPROVED BY(name & visa)

    DOCUMENT REVISIONS

    Sections changed in last revision are identified by a vertical line in the margin

    PRELUDE EPCI

    Floating LNG PROJECT

    Project Permit to Work Procedure

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    2/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 2 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    CONTENTS

    1. SCOPE ............................................................................................................................... 4

    2. PURPOSE .......................................................................................................................... 6

    3. ABBREVIATIONS .............................................................................................................. 7

    4. REFERENCES ................................................................................................................... 7

    5. APPLICATION.................................................................................................................... 8

    6. PERMIT ISSUE................................................................................................................... 9

    7. ROLES AND RESPONSIBILITY ...................................................................................... 10

    7.1 PTW Process Owner ...................................................................................................................................... 10

    7.2 Overall Authority ............................................................................................................................................ 11

    7.3 Delegation ....................................................................................................................................................... 11

    7.4 PTW Authorised Signatories ........................................................................................................................ 12

    7.5 Permit Requestor ........................................................................................................................................... 12

    7.6 Permit Authority ............................................................................................................................................. 14

    7.7 Area Authority ................................................................................................................................................ 15

    7.8 Permit Issuer .................................................................................................................................................. 17

    7.9 Isolation Authority - Authorized Person (Electrical / Mechanical / Inst) .................................................. 19

    7.10 Authorized Gas Tester .................................................................................................................................. 20

    7.11 Permit Holder ................................................................................................................................................. 21

    7.12 Work Party ...................................................................................................................................................... 22

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    3/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 3 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    8. SYSTEM MANAGEMENT ................................................................................................ 23

    8.1 Daily Permit Coordination Meeting .............................................................................................................. 23

    8.2 Facilities .......................................................................................................................................................... 25

    8.3 Documents Required at Site ......................................................................................................................... 25

    8.4 Permit Validity ................................................................................................................................................ 26

    8.5 Archiving of Completed PTW Documents .................................................................................................. 27

    9. LOTO REQUIREMENTS .................................................................................................. 28

    10. RISK ASSESSMENT PROCESS ..................................................................................... 28

    10.1 Overview ......................................................................................................................................................... 28

    10.2 Planning .......................................................................................................................................................... 29

    10.3 Risk Assessment ........................................................................................................................................... 29

    10.4 Toolbox Talk ................................................................................................................................................... 31

    11. RESPONSE TO FACILITY / YARD EMERGENCIES ...................................................... 32

    12. PERMIT AUDITING & SITE INSPECTION ....................................................................... 32

    13. TRAINING, ASSESSMENT AND AUTHORIZATIONS .................................................... 33

    14. PTW NOTIFICATION ....................................................................................................... 34

    15. CONSEQUENCE MANAGEMENT ................................................................................... 35

    16. APPENDIX LIST ............................................................................................................... 35

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    4/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 4 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    1. SCOPE

    The prime objective of the procedure is to ensure that work is properly planned, controlled,

    coordinated and communicated. It is the means of providing written instructions and

    authorization to people carrying out potentially hazardous work, ensuring that the safe

    working requirements and minimum standards for conducting such tasks on Prelude FLNG

    Project Construction, Pre-Commissioning and Commissioning activities until Sail Away are

    complied with.

    This procedure affects all TECHNIP SAMSUNG CONSORTIUM personnel, SUB-

    CONTRACTORS and VENDORS and COMPANY personnel involved in those activities.

    TSC personnel and their respective Subcontractors shall not carry out or be required to

    perform any activity for which they are not competent or which cannot be performed safely.

    This Procedure is a live document which shall be reviewed on a regular basis.

    This Procedure supersedes Construction Permit To Work Procedure ref. 2000-120-G000-

    GE00-G00000-HX-6180-02016.

    The PTW administration is facilitated through a software system that is an electronic work

    control system covering the areas of permit application, risk assessment and review of

    concurrent activities. However this procedure does not describe the electronic systems use.

    Although the PTW administration is by electronic means, final hard / paper copies are used

    for written authorization and displayed at work site. Such software system must be

    understood by all signatories and in Korean and English as a minimum.

    A Permit To Work System is however, only part of an overall work control system which is

    dependent on those who raise permits, those who work under them and those who approve

    them. An effective safe working environment can only be achieved through systematic

    planning, communication, training, checking and implementing control and recovery

    measures, worksite monitoring, inspection upon completion of work and audit of the overall

    processes.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    5/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 5 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    The Permit to Work System shall be adhered to and any noncompliance of the PTW System

    or the Shell Life Saving Rules shall result in a disciplinary action being taken. Refer to

    Article 15 of the procedure.

    A systematic approach to application of the Permit to Work System will involve the following

    activities :

    Accurately specify the work to be performed, expected duration, plus tools and

    equipment to be used

    Accurately specify the location where the work will be performed.

    Specify all precautions to be taken when preparing the worksite and the safe

    working practices while the work is in progress

    Complete the preparatory work, ensuring the facility can be safety worked on and

    verify that all prescribed personal safety requirements are in place. i.e. gas testing

    and equipment isolations.

    Give permission for the work to begin by signing the required declarations on the

    permit form.

    Check job site safety as the work progresses, the validity of permits and

    certificates and adherence to the precautions specified.

    On completion of the work, check that the job site is left in a safe / tidy condition and sign off

    the work permit.

    Note: PTW must be job specific with no multiple jobs being specified, That is, One Permit / One Task.

    It is vital that all supporting documents to a PTW be correctly cross referenced and that permits are

    authorized in relation to other work activities in the same area or on the same equipment.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    6/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 6 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    2. PURPOSE

    The purpose of this procedure is to:

    Clearly define the life cycle of the PTW process and supporting documents to conduct work

    in a safe and practicable manner.

    Ensure that all personnel work under a single PTW system and are trained in its use.

    Specify the Roles and Responsibilities of the various positions within the PTW system.

    Identify the types of work that need to be controlled through a PTW. Ensure that the task is fully considered, the sequence of work decided.

    Define the applicable work scope Hazards and when additional risk assessments are

    required as part of the PTWProcedure.

    Specify the minimum Precautions required for the work, based on a Risk Assessment, and

    theHierarchy Of Controls.

    Define additional PPE which must be used to conduct the task

    Specify the preparations and supporting documents required before a PTW can be issued,

    the Controls needed to manage the intended work.

    Provide a means to assess potential conflicts between different work activities (Concurrent

    Work).

    Specify period of validity of permits. There will be no shift handover under a single permit, as

    the Permit Holder will be different and implications of concurrent activities at day and night

    shift have to be re-assessed. Handover in case of continuous activities between Permit

    Holders will take place on site verifying jointly the status of progress and completion of the

    activity..

    All deviations from the PTW Procedure require prior authorization by the PTW Process

    Owner and approved way forward must be clearly communicated. Only exception is in

    Management of change situations, where the process is well described in the Risk

    assessment Procedure, section 4, Management of change.

    Ensure the work is formally communicated between all affected parties.

    Ensure all personnel involved in the work clearly understand the nature of the work, its

    hazards, controls and time restrictions.

    Ensure a formal work completion and hand back procedure is used ensuring the affectedplant and equipment is returned to normal operation.

    Maintained records of and archive closed permits.

    http://void%280%29/http://void%280%29/http://void%280%29/http://void%280%29/
  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    7/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 7 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Delivers continuous improvement of the PTW System and its implementation through

    checks, audits, reviews and revision.

    3. ABBREVIATIONS

    CPY: Company

    CTR : Contractor

    IA : Isolation Authority

    JSA : Job Safety Analysis

    FLNG : Floating Liquefied Natural Gas (facility)

    LOTO : Lock Out Tag Out

    PI : Permit Issuer

    PTW : Permit To Work

    SHI : Samsung Heavy Industry

    SSS : Site Safety Supervisor

    TSC : Technip Samsung Consortium

    RA : Risk Assessment

    SIMOPS : Simultaneous Operations (Conflicting Activities)

    4. REFERENCES

    2000-003-G000-GE00-G00000-HS-6180-00001 Contractor HSSE Management - Level of

    COMPANY Monitoring

    2000-100-G000-GE00-G00000-HX-5798-01552 Project HSSE&SP Plan

    2000-120-G000-GE00-G00000-HX-5880-01556 Construction HSSE Plan

    2000-100-G000-GE00-G00000-HX-6180-01695 Risk Assessment Procedure

    2000-100-G000-GE00-G00000-HX-6180-01692 TBM Procedure

    2000-100-G000-GE00-G00000-HX-5798-01595 External CSU Subcontractor & Vendors HSSE

    management Procedure

    2000-100-G000-GE00-G00000-HX-6180-01593 Onshore CSU HSSE Plan

    2000-100-G000-GE00-G00000-HX-6180-01590 Lockout Tag out Procedure

    2000-120-G000-GE00-G00000-HX-5880-02001 Confined Space Work Procedure

    2000-120-G000-GE00-G00000-HX-5880-02005 Lifting and Hoisting Procedure

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    8/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 8 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    2000-120-G000-GE00-G00000-HX-5880-02007 Radiation Safety Procedure

    2000-120-G000-GE00-G00000-HX-5880-02013 Electrical Safety Procedure

    2000-100-G000-GE00-G00000-HX-6180-01597 CSU Electrical Safety Rules

    2000-120-G000-GE00-G00000-HX-5880-02004 Incident Reporting Procedure

    2000-003-G000-GE00-G00000-HS-6180-00003 Consequence Management Procedure

    2000-100-G000-GE00-G00000-HX-6019-01581 Emergency Response Procedure

    2000-120-G000-GE00-G00000-HX-6180-02010 Scaffolding Management Procedure

    2000-120-G000-GE00-G00000-HX-5880-02015 Working at Heights Procedure

    2000-100-G000-GE00-G00000-CZ-6180-01989 Overriding/By-passing Safety Inhibits

    2000-100-G000-GE00-G00000-HX-6180-01599 TSC HSSE Training Plan

    2000-100-G000-GE00-G00000-CZ-5798-01691 Safety Districts - CSU/Construction Controlled

    Area Mapping

    Respective Shell HSSE&SP Control Framework manuals and Shell Life Saving Rules guide.

    5. APPLICATION

    A Permit To Work provides written confirmation that a risk assessment of the specific conditions

    affecting the work has been carried out and that the appropriate control measures to protect

    personnel and equipment from each of the hazards have been provided. It is a formal agreement

    between the Permit Area Authority and those who will carry out the work, that both the risks and the

    controls that will mitigate them are understood and that the controls will be fully implemented.

    A PTW is required for all tasks listed in Appendix 4. (list to be reviewed on regular basis).

    Depending on the risk two different levels of Risk Assessment and Authorization have been

    established. Level 1 Risk assessment for the high risk activities and Level 2 Risk assessment which

    is contained in the Permit format for the lower risk work. Respectively the permits associated with

    Level 1 and Level 2 RA have different authorization level.

    This system of Risk Categorization is based on the type of activity and the environment to define

    associated risk level to a task. (ref. Appendix 4, Prelude FLNG PTW Scope of application).

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    9/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 9 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    The PTW itself represents a level 2 risk assessment of the activity and is to be supplemented with

    the respective Safe Working Standard for the task. For further detail on the tasks which do not

    require Level 1 risk assessment, but still require PTW, refer to Appendix 4.

    The Project specific procedures as per the Reference Documents section must be complied with and

    the additional requirements associated with each task type factored in the planning, implementation

    and communication stages of the PTW process.

    For all floating crane, diving and rope access activities the method statements, plans and JSA as

    well as the necessary controls and recovery measures shall be agreed with a Company Authorized

    Subject Matter Exerts, e.g. appointed Marine Warranty Surveyor for floating crane lifts; Diving

    Center of Excellence Aberdeen for diving operations; Rope access SME, etc.

    All concurrent activities and interfaces shall be managed by the Area Authorities and final checks and

    arrangements agreed at the Permit Coordination Meeting.

    6. PERMIT ISSUE

    Refer to Appendix 1 for the PTW Flow Diagram.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    10/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 10 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7. ROLES AND RESPONSIBILITY

    7.1 PTW Process Owner

    The PTW Process owner, who is the Prelude FLNG TSC Project HSSE Manager, shall set up a Permit

    To Work (PTW) Procedure that meets the following Shell HSSE&SP Control Framework requirements:

    Identify the types of work that need to be controlled through a PTW.

    Specify that all personnel at a location must work under a single PTW system,

    Define when a Job Hazard Analysis is required as part of the PTW Procedure

    Specify how permits are issued and closed, including for both complete and suspended

    situations, how shift handovers are managed, and the period of validity of permits.

    Specify the authorizations required for deviations from the PTW Procedure in Emergencies.

    Specify that permits be retained for a period defined by legislative requirements or the criticality of

    the permit, and in any case for not less than three months.

    Define the Permit To Work Form to be used

    As process owner of the PTW System, he/she is responsible for:

    Ensuring that at all time work is executed in compliance with Prelude FLNG Project HSSE rules

    and procedures.

    Ensuring that appropriate PTW trainings are given to all workers as per their level of implication

    within the PTW system.

    Performing competence assessment on the PTW signatories.

    Assigning HSSE personnel to monitor, audit and inspect the work done under PTW system.

    Ensuring HSSE attendance and input to daily PTW Coordination meeting(s).

    Ensuring the PTW system and associated procedures are regularly reviewed, audited and revised

    including lessons learnt for continuous improvement.

    Maintaining an evergreen list of those signatories as well as clear organizational structures with

    clear mapping out of the Area Authorities for the Construction and CSU activities respectively and

    the Areas physical boundaries (ref. to Safety Districts - CSU/Construction Controlled Area

    Mapping Procedure)

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    11/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 11 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.2 Overall Authority

    The Overall Authority, who is Prelude FLNG TSC Executive Project Director bears the overall

    accountability for establishing and maintaining a Permit To Work system ensuring that any work

    performed is done in a safe manner. This person shall have an overview of all operations under way

    and to avoid hazards caused by simultaneous activities. He/she is responsible for ensuring the

    effectiveness of the PTW system, by appointing (written delegation) an appropriate responsible person

    (or people) with sufficient authority (i.e. Area Authorities) to carry out this function on his behalf. The

    Overall Authority can delegate his/her responsibilities to Area Authorities but remains accountable for

    the actions performed by his/her delegate(s).

    Overall Authority is responsible for:

    Ensuring the safe performance of the work conducted for the Prelude FLNG Project

    Assigning sufficient resources to ensure the effective implementation of the PTW procedure at

    worksite.

    Appointing in writing nominated individuals to act as Authorized Competent Persons (Area

    Authorities, Permit Requestors, Permit Issuers, Permit Holders and other Specialist Signatories

    together with their specific authorities, roles and competence requirements).

    Ensuring that appropriate level of risk assessment is performed, the hazards associated with the

    work are identified and adequate control measures required to reduce the residual risk to ALARP

    (As Low As Reasonably Practicable) are clearly described on the PTW.

    Participating in and reviewing incident and audit findings and ensures correctives actions are

    closed out.

    7.3 Delegation

    The Process Owner and Overall Authority shall appoint in writing, a named competent delegate, in

    case of absence.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    12/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 12 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.4 PTW Authorised Signatories

    The Authorities PTW Signatories mentioned here after must be adequately trained, assessed as being

    competent and officially appointed to the role (Cf. Appendix 5 Authorized Signatory Certificate) by

    the Overall Authority:

    Permit Requestor

    Permit Holder

    Permit Authority

    Area Authority

    Permit Issuer

    Isolation Authority (ref. to LOTO Procedure for the specific Authorized Signatory

    Certificate)

    Authorized Gas Tester

    The PTW Process owner will maintain an evergreen list of those signatories as well as clear

    organizational structures with clear mapping out of the Area Authorities for the Construction and CSU

    activities respectively and the Areas physical boundaries.

    7.5 Permit Requestor

    He/she :

    May or may not be the Permit Holder.

    Is Not allowed to issue permits for themselves

    Applies for the Permit To Work via the computerized system and prepares the risk

    assessments, isolation design (when applicable) and other supporting documents and

    preparatory information the Permit Authority requires to endorse the Permit.

    Completes Section 1 of the Permit to Work Template using computerized system by

    identifying Type of Work, Exact Work Location, Subsystem, Equipment tag numbers, Task

    Details, Equipment Isolation requirements, Equipment to be used, and expected start and

    duration times. In that way he/she communicates to the Permit Authority the nature and

    scope of the work and special tools involved.

    Gets involved in the tasks Risk Assessment and makes sure the control and recoverymeasures specified are reflected in the Permit application and that the Level 1 Risk

    Assessment enclosed to the permit is the approved& final version.

    http://void%280%29/http://void%280%29/
  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    13/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 13 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    The computerized system will automatically define :

    o The applicable Hazards for the particular work type, Section 2 of the PTW

    o Set the Minimum Controls, inclusive of PPE requirements in Sections 3 and 4 of

    the PTW

    o Detail the Supporting Documents required, section 5 of the PTW

    o Nominate the Permit Authorization Level, Section 6 of the PTW

    The requester is to double check all automatic minimum requirements set for the work scope

    and manually add any additional precautions if necessary for the actual work being applied

    for.

    The Permit Requestor should also ensure any supporting documents as identified are

    supplied with the PTW application.

    After the PTW has been Electronically Authorized, the Permit Requestor is required to print

    out a hard copy of the Permit and submit it along with all supporting documents to the Permit

    Issuer for review at the next Daily Permit Coordination Meeting or at least one day before

    work is planned to be performed.

    The Permit Requestor shall work with appropriate Isolation Authority/ies to jointly prepare the

    isolation design and Isolation Summary sheet to confirm isolation points specified will enable

    safe execution of work. (for further details refer to LOTO Procedure).

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    14/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 14 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.6 Permit Authority

    He/she :

    Is responsible for the effective operation of the PTW process at the work site. Depending

    upon the classification of the work being conducted the required Level of Authorization will

    change in line with this PTW procedure, Authorization Responsibility Matrices and Shells

    HSSE&SP CF Framework.

    Note: Permit Authority is not the Permit Issuing Authority. His authorization is a pre -requisite

    for the permit application to be elevated to the respective Area Authority attention for final

    approval.

    Work CategoryAutorisation

    Level

    Construction CSU

    SHI Subcontractor TSC Subcontractor

    Level. 1

    A

    Department

    Vice President

    Site

    Representative

    Specified

    discipline CSU

    Superintendent

    Site

    Representative

    BDepartment

    General Manager

    Site

    Representative

    Specified

    discipline CSU

    Superintendent

    Site

    Representative

    Level.2

    CDepartment

    Manager

    Site

    Representative

    Specified

    discipline CSU

    Superintendent

    Site

    Representative

    DDepartment

    Senior Foreman

    Site

    Representative

    Specified

    discipline CSU

    Superintendent

    Site

    Representative

    Depending on the work categorization the applicable Permit Authority shall review the

    content of the PTW and confirm that the following is provided;

    o Description of work

    o Exact work location (area plot plan)

    o Tools and equipment to be used

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    15/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 15 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    o Expected start date and duration of work

    o Hazards have been identified

    o An appropriate level of risk assessment

    o Precautions and controls specified to enable work to be performed safely

    o Supporting documents (section 5) incl. supporting drawings and procedures.

    When the Permit Authority is fully satisfied the information listed above has been provided

    he/she will endorse the PTW electronically using the HSSE PTW Computerized system

    (section 6).

    Ensures the appropriate actions and communications have been taken to notify of planned

    energisation of equipment prior to approval of the PTW, i.e. Livening Up Notices Issued

    and approved and PTW Notifications as described in section 14 of this procedure.

    It is to be noted that a Notification System for high risk activities shall be followed. (ref. to section 14 for

    further clarification).

    No permit can be printed out, unless it has been authorized electronically by the designated Authority

    level. Once authorized the Permit and supporting documents need to be submitted to the Permit

    Issuer for and further endorsement by the applicable Area Authority at the Daily Permit Coordination

    meeting.

    7.7 Area Authority

    The Area Authority is responsible for managing all activities occurring within their area of

    responsibility.

    He/she :

    Is responsible for the safe control of work activities within their area.

    Communicates clearly his/her expectations to the Permit Requestors and Permit Holders in

    that respect.

    Review all Supporting documents as submitted for permitting the activities within their area.

    He/ she has the ultimate authority to reject a permit if not satisfied with the controls specified

    in the respective Level 1 Risk Assessments.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    16/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 16 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Reviews and approves isolation summary and certificate for the job to proceed under the

    PTW. He/ she has the authority to request discipline input and review prior to approving of

    isolation certificate.

    Attends the Daily Permit to Work Coordination meeting to discuss and agree the following

    days activities are safe to proceed and that any conflicting activities and the isolation

    requirements to perform the work have been identified. .

    The Area Authority will sign section 7 of the PTW providing he/she is satisfied that the work

    can safely go ahead within his/her area of responsibility handing over responsibility of PTW

    coordination to the Permit Issuer.

    Ensuring work site inspections are carried out before, during and after the completion of each

    task.

    Report to the Permit Issuer, as well as PTW Overall Authority for any non-compliances or

    issues he could not resolve on the site.

    Stops work and withdraws Permit/s until safety issues are resolved and communicates this

    back to the Permit Issuer.

    Report incidents and GSR/ LSR breaches. Participate in the investigations

    Specify the controls required for the work, based on a risk assessment, and the hierarchy of

    controls

    Specify the operational preparations required before a PTW can be issued, including:

    o Isolation of the work area from hazards including all potential sources of energy,

    conforming to safe isolation-Lock Out Tag Out;

    o Hazard freeing and confirmation that either the hazards have been removed to

    acceptable levels or the appropriate controls are in place to manage them;

    o the controls needed to manage the potential interaction between different work

    activities (simultaneous/concurrent activities);

    o the controls needed to manage the temporary overriding or bypassing of safety

    devices.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    17/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 17 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.8 Permit Issuer

    The Permit Issuer is a key position and coordinates the PTW flow and approval process (See

    Appendix 1 for the simplified PTW process flow diagram).

    Once the PTW and controls are approved by the applicable Area Authority at the Permit to Work

    Meeting, the PI will manage the PTW process, including issuing Isolation Confirmation Certificate for

    commencement of Isolation / De-isolation and ensuring Initial Gas testing requirements are

    completed.

    After all necessary PTW approvals / endorsements have been completed, the work scopes and

    isolation requirements agreed, the Permit Issuer will issue the Isolation Confirmation Certificate to

    an Approved Isolating Authority to conduct / perform the Isolation / De-isolation scope.

    In addition the PI will ensure that all isolations / de-isolations are in place by reviewing the Isolation

    Confirmation Certificate for correct completion and sign off when returned.

    The PI will not issue the PTW to the Permit Holder, for commencement of work until he / she is fully

    satisfied that all Isolations and initial gas testing requirements have been completed and verified and

    the work site is safe for the work to commence. Initial Gas testing should be performed immediately

    prior to work being approved by the Permit Issuer.

    Full coordination and control of this paperwork flow and approval process is the sole responsibility of

    the Permit Issuer or his delegate.

    He/she :

    Acts as the Gate Keeper for the Permit to work process ensuring all permits have the

    appropriate signatures and supporting documents.

    Coordinates the daily Permit Coordination Meeting and ensuring permit applications to be

    discussed at the meeting are accompanied by all required supporting documentation.

    Maintains a PTW wall plan (visual display of all permits per areas for the day) of all activities on

    the facility by area and advertising of potential conflicts.

    Escalates conflicting concurrent activities and simultaneous work, prompts Area Authorities in

    reviewing with all related parties at the PTW Coordination meetings for resolution and issuepermits accordingly.

    Maintaining a daily record of all issued PTWs.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    18/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 18 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Issuing to key personnel daily the PTW summary list and list of suspended permits.

    Obtaining the necessary Authorisations / Endorsements. When one or more Specialist

    Signatory is needed, issue the permit only after the specialist(s) has signed the permit

    supporting documents.

    Issuing the permits to the appropriate Permit Holders.

    Transfers PTW supporting documents from an expired PTW to a new PTW using the

    supporting document unique numbers where necessary.

    Maintains a copy of all permits in the PTW office - suitably displayed and arranged.

    Manages the issuance and revalidation of Night / Dayshift Permits

    Coordinates the De-isolation for Test process

    Coordinates the overall PTW, LOTO and Gas Testing process.

    Makes Sure that Permits are signed off by the authorised only. And that the telephone

    numbers of Permit Holder, Area Authority & PI are clearly visible on the Permit.

    Ensures all keys to locking devices used for isolations are kept in an appropriate lock box in

    the PTW office and maintain a log when padlocks and keys are issued for personnel use.

    Maintains the Livening Up Notification register.

    Maintains the Management of Change register, as per the Project Risk assessment procedure,

    Section 4, ref. 2000-100-G000-GE00-G00000-HX-6180-01695.

    Communicates PTW Notifications. Inform all people who may be affected by the work.

    Maintains an up to date list of Authorised Competent Persons in the PTW Coordination Office

    together with all the related Authorised Signatories.

    Not issue the PTW to the Permit Holder, for commencement of work until he / she is fully

    satisfied that all Isolations and initial gas testing requirements have been completed and

    verified and the work site is safe for the work to commence. Initial Gas testing should be

    performed immediately prior to work being approved by the Permit Issuer.

    Archives and files Closed out PTW documents and supporting information. Permit Issuer signs

    off section 9 and 13 of the permit.

    Makes available at least two copies of the permit. One must be at the work site with the Permit

    Holder and one at the PTW office, so that the status of the permits in any area can be readily

    assessed.

    Liaises directly with Area Authorities for any PTW issues as required.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    19/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 19 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.9 Isolation Authority - Authorized Person (Electrical / Mechanical / Inst)

    Reference the Prelude Project LOTO Procedure and Electrical Safety Rules for further clarification.

    He/she :

    Conducts the isolation scope on the Permit Issuer request as detailed on the isolation

    certificate and associated supporting marked up drawings.

    Shall effect all isolations in the correct order to maintain the safety and equipment integrity.

    Shall work directly with and support Permit Requestor in the preparation of the Isolation design

    and ICC.

    Ensures that isolation will be completed as per Prelude Project Lock Out Tag Out Procedure

    2000-100-G000-GE00-G00000-HX-6180-01590.

    Ensures that all components are fully isolated, locked off and tagged using only approved

    devices.

    Confirms the isolations are in place, their integrity proven and completes all sections of the

    Isolation Certificate before returning it signed to the Permit Issuer.

    Upon the Permit Issuer request conducts de-isolation and confirms the de-isolations are fully

    completed, all locking devices removed and tags collected.

    The IA shall complete the isolation confirmation certificate and return to the permit office with

    the recovered tags.

    Ensures Isolation integrity is regularly monitored.

    Communicates with all the affected parties to ensure that the isolation procedure is effectively

    implemented.

    Communicates effectively with other work parties involved in the work.

    Supervises others who may assist in applying / removing isolations.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    20/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 20 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.10 Authorized Gas Tester

    He/she:

    Conducts Initial Gas Testing for Confined Space entry as defined and record the results in

    Section 8 of the PTW. Initial testing must be performed immediately before the Permit Issuer

    issues the permit for work commencement.

    Monitors the work site on commencement of work and retesting and recording of results in

    Section 11 of the PTW, at the frequency specified on the PTW. Note: Minimum requirementshall be as specified in the Confined Space Procedure and confirmed at the Permit to Work

    Coordination meeting and take into account Confined Space Category, type of work and work

    durations..

    Ensures the Gas testing equipment is fully calibrated, certified and working prior and after

    conducting the tests.

    Records the readings and signing the PTW document as formal record.

    Stops work & evacuates all personnel should the atmosphere measurement be outside of the

    safe range (Refer to Confined Space Work Procedure 2000-120-G000-GE00-G00000-HX-

    5880-02001)

    Informs the Permit Holder and Permit Issuer to suspend the permit.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    21/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 21 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    7.11 Permit Holder

    Responsible for the actual work being performed, under the conditions set out on the Authorized

    and Approved Permit to Work. The Permit Holder may be the person carrying out the task or

    Supervising a group of people carrying out a task. The Permit Holder can be responsible for more

    than one task at any one time, providingthe tasks can be safely managed concurrently & sufficient

    supervision is ensured.

    He/she:

    Participates in the task risk assessment

    Accepts the permit to Work from the Permit Issuer prior to commencing actual work, by

    endorsing Section 9 of the PTW.

    Understands the controls and ensures they are in place before work starts

    Checks that all LOTO isolations have been implemented as per the Lockout Tag out

    Procedure prior to proceeding with the work.

    Ensures that Works Party understands what, where, and how work is to be performed.

    Ensures that the Work Party use proper tools and equipment for the job. Ensures the

    equipment is fit for purpose and fit for service.

    Leads the Toolbox Meeting with work party and has all team members sign their declaration

    in Section 10 of the PTW.

    Ensure a copy of the PTW and Supporting documents are clearly displayed at the work site.

    Actively supervises the task.

    Ensures Gas testing is performed by the AGT as per PTW requirements.

    Ensures that only the work covered within the scope of the PTW is undertaken and nodeviation takes place.

    Ensures the crew members are fit for work and that they have passed necessary project

    specific training.

    Ensures the work site is kept in a clean and safe condition, both during and upon completion

    of the task.

    Ensure that a detailed handover of the status of the task is conducted at end of shift or

    completion of work with the Area Authority and Permit Issuer, by signing off Section 12 of the

    PTW.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    22/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 22 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Confirms completion and notifies the Permit Issuer upon completion of the work and makes

    sure all tools and equipment are removed from the job site.

    Hands the PTW and all supporting documents back to the Permit Issuer for close out or

    carry over as required.

    Ensure a copy of the PTW and Supporting documents are clearly displayed at the work site.

    Suspends the permit and stops work if the conditions change and inform permit issuer.

    When in doubt consults with the Permit Issuer and or Area Authority.

    7.12 Work Party

    The work party members have a crucial part to play in the process by:

    Actively participating in the Toolbox Talk (TBT) to ensure they understand the Hazards and

    control measures associated with the task

    Actively participating in the identification of any additional Hazards and Control measures

    required at the work site.

    Ensuring safe access and egress to the worksite is maintained at all times.

    Keeping the work place tidy, free of debris / waste and ensuring materials are stored correctly.

    Signing onto the PTW confirming their understanding and acceptance of the PTW

    requirements.

    Stopping the work at any time if they are concerned about safety.

    Identifying any lessons from the task and informing the, Permit Holder and Permit Issuer for

    future reference.

    Complying with the applicable SHI Golden Safety rules, Shell Life Saving Rules.

    Intervening to stop any unsafe act during the execution of the work. Reporting any unsafe conditions/actions, near misses or incidents.

    When in doubt, consult the Permit Holder.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    23/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 23 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    8. SYSTEM MANAGEMENT

    8.1 Daily Permit Coordination Meeting

    The daily Permit Coordination meeting is MANDATORY and provides the Site Management Team

    with the opportunity for

    A daily overview of all ongoing and planned work under the control of a PTW and to review

    compliance with the agreed plan.

    Identifying and preventing potentially conflicting activities

    Area Authority will endorse any new PTWs and by doing so agrees to the timeframes and

    any concurrent activities are controlled in their area of responsibility.

    It is vital that all permits submitted to the meeting via the Permit Issuer for approval have all

    supporting documents to enable a thorough review of work scope and are discussed in relation to

    other work activities in the same area or on the same equipment.

    Note: Meeting timing may need to be adapted during the different project phases.

    By 2:30pm on D-1, all permits shall be endorsed by the Permit Authority in the electronic PTW

    system. This will allow for the Permit Issuer to prepare the summary and the permits for the daily

    coordination meeting and analyze the data.

    The PTW Coordination meetings will take place daily at 4:30pm at the Permit coordination office.

    The Daily Permit Coordination meeting will be chaired by the Permit Issuer for Construction Areas

    and the Permit Issuer for Commissioning areas. The daily Permit Coordination meeting shall beattended by the following persons or endorsed delegates as a minimum :

    Construction Leads (COMPANY)

    Construction Area Authorities

    Construction Permit Issuer

    Construction HSE Team Focal Points

    CSU Permit representative (if required)

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    24/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 24 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    When first area will be transferred from Construction to CSU, following attendees will also be

    attending:

    CSU Area Authorities

    CSU Permit Issuer

    CSU HSE Team Focal Point

    The Permit Issuers for Construction and Commissioning respectively will prepare the daily agenda for

    the meeting to include a listing of all permits (Construction and CSU) being requested for the following

    day grouped and sorted by specific location and their status.

    The agenda of the meeting should be pre-agreed and standard and should include but is not limited to:

    Discussions of problems with work preparation. Suspended and withdrawn permits list form

    previous day.

    Ongoing / continued work scopes and transfer of supporting documents

    Unplanned work.

    Temporary/ Emergency changes.

    PTW Notifications.

    Systematic review of Permit to Work scopes by geographic work areas checking for

    potential clash of concurrent activities or SIMOPS, e.g. working on the same pieces of

    equipment / process.

    Review and approve LOTO requirements (Elec/Mech/Inst)

    Coordination issues shall be resolved at this forum. The Permit Issuer will bring all submitted permits

    to the meeting for review and will ensure they have all supporting documents attached in advance.

    At the conclusion of the Daily Coordination Meeting an approved listing of Permits approved by the

    Area Authorities for issue the next day will be produced as well as the list of the rejected permit

    applications and distributed to attendees of the meeting.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    25/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 25 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Any Deviation of PTW application scheme will have to be formally approved by the following people :

    - Permit Authority

    - Affected Area Authorities

    8.2 Facilities

    The PTW coordination meeting shall be held in an area as near to the central issue point as is

    possible so that an overview of ongoing and potentially conflicting activities can be viewed and

    assessed.

    A dedicated PTW facility will be created that will house all permits and accommodate the daily

    Coordination meeting. This facility should include a visual wall plan where work activities are

    illustrated by permit type.

    It should be equipped with air conditioning; radio and telecommunications; printer/s and PCs as

    required for facilitating the PTW process.

    The evergreen list of PTW signatories as well as clear organizational structures with clear mapping

    out of the Area Authorities for the Construction and CSU activities respectively and the Areas physical

    boundaries will be visibly displayed at the PTW offices. (ref. Safety Districts - CSU/Construction

    Controlled Area Mapping Procedure)

    8.3 Documents Required at Site

    Minimum requirements are :

    Copy of the PTW

    Copy of all supporting documents

    Copies of drawings to support isolation schemes

    It is the responsibility of the Permit Holder to ensure that a copy of these documents are clearly

    displayed at the work site, or as close as practicable.

    The Permit Issuer will maintain a second copy (Master Copies) suitably available in the Permit to

    Work Coordination Office.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    26/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 26 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    8.4 Permit Validity

    All permits are valid for a 12 hour shift, inclusive of lunch and rest breaks. Should a permit be

    requested which extends beyond a 12 hour shift then this needs to be clearly identified and justified

    before approval will be given at the Permit Coordination Meeting.

    Application for the extension shall take place at the Permit office the same day by 14:30hr.

    It is the Permit Requestors and Permit Holders responsibility to ensure the fitness for work of the

    workers during such extensions is robust. They must make sure compensation in rest is taking place in

    accordance with the local labor law and the regulations.

    Permits will not be extended for periods over 14hrs, except for critical test that cannot be interrupted.

    Night shift permits should be submitted to the Permit Issuer one whole day prior to the work being

    performed.

    Where work carries over to the next day, a new PTW will be required and all supporting documents

    transferred from the old permit to the new permit prior to authorisation and issue.

    For CSU activities in CSU controlled areas, PTW validity can be up to 7 days after Permit Authority

    and Area Authority approval.

    The old and new PTW documents will be cross referenced in Section 13 of the PTW form and all

    supporting documents will be carried forward with their unique number on the new permit. A review of

    isolations and supporting documents is conducted to ensure the previous controls remain suitable for

    the new permit activities should they differ.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    27/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 27 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    When work is completed and the work site has been left in a clean and safe condition and all

    temporary signs, barriers etc have been removed:

    The Permit Holder ensures the work party participants are informed and no further work is to

    be undertaken.

    The Permit Holder returns the PTW and supporting documents to the Permit Issuer at the

    Permit Coordination Office.

    The Permit Holder will sign off the PTW in section 12 of the permit noting either Work

    Complete or Work Incomplete.

    The status is fully discussed between both the Permit Holder and Permit Issuer, so that the

    supporting documents can be transferred to a new PTW or the permit to work closed out as

    appropriate.

    The permit Issuer will then complete Section 13 of the Permit to work and make any necessary

    arrangements for either.

    Transfer of supporting documents to a new PTW for continuation on the following day

    Arrange for de-isolation if work is fully complete

    Close out all documents as required and file in archive.

    8.5 Archiving of Completed PTW Documents

    Permits and associated supporting documents shall be retained for a period defined by legislative

    requirements and in any case for not less than three months.

    Note: Where a reported incident has been associated with any work performed under a PTW, the

    Permit To Work Process Owner should retain the paper copies and all supporting documents to

    facilitate a complete review.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    28/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 28 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    9. LOTO REQUIREMENTS

    For a full detailed description of Lock out Tag Out, ref. the Project LOTO Procedure, 2000-120-G000-

    GE00-G00000-HX-6180-001590 .

    10.RISK ASSESSMENT PROCESS

    10.1 Overview

    Safe management of work includes:

    Planning

    Risk Assessment

    Approval and Communication

    Execute Work and Review

    There are two levels of risk assessment in the PTW process:

    1. Level 2 Risk Assessment for lower risk Tasks Simple format of check boxes on the PTW

    form to identify hazards, controls and PPE requirements.

    2. Level 1 Risk Assessment for High risk Tasks Formal qualitative assessment using a specific

    form (ref. Appendix 2, Risk Assessment Template) which must be submitted with the PTW

    application as a supporting document and approved by the Area Authority. In some cases a

    Jointly (TSC/CPY) revised and signed off Safe Working Standard can also be accepted as

    Level 1 Risk Assessment, to acknowledge prior experience / SHI standards for the task.

    Tasks requiring PTW and Level 1 or Level 2 Risk Assessment respectively are listed in Appendix 4 of

    this document.

    The Project specific procedures as listed in the Reference documents are the minimum requirements

    for safe execution of the work and must be complied with at all times.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    29/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 29 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    10.2 Planning

    Safe planning of work involves:

    1. Define the task and its operation via a Method Statement

    2. Visit the worksite (Permit Requestor/ Permit Holder / Area or Permit Authority / Isolation

    Authorities) for field verification. Adjust the method statement and JSA as necessary.

    3. Discussing SIMOPS potential at the daily permit Coordination meeting.

    10.3 Risk Assessment

    The electronic PTW system will automatically designate when a Level 1 risk assessment is required,

    by the work type selected at Permit application by the Permit Requestor.

    However the auto selection of Hazards and controls by the electronic system is a minimum

    requirement only and additional controls must be selected manually by the Permit Requestor and

    approved by Permit Authority and the Area Authority depending upon the actual work to be

    performed. The additional selection could also be a Level 1 Risk Assessment as per Permit

    Requestor, Permit Authority or Area Authority.

    Depending the activity and location, several document may be requested by the Permit Issuer :

    Method Statement / Detailed Procedure.

    Level 1 Risk Assessment; Job Safety Analysis; Safe Working standards

    Material Safety Data Sheet (MSDS). PEFS, Marked-up Drawings.

    Isolation details.

    Crane Inspection Certificate, including load test.

    Rigging Certificates.

    Competent Person Certificates.

    Rigging / Lifting Plan.

    Rescue Plan.

    Layout plans.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    30/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 30 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    The intention of the risk assessment is to reduce the risks to As Low As Reasonably Practicable

    (ALARP).

    If ALARP cannot be demonstrated, the work should not proceed and alternative methods of work or

    additional controls must be applied.

    For further detail on risk assessment refer to Project specific procedure, ref. 2000-100-G000-GE00-

    G00000-HX-6180-01695.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    31/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 31 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    10.4 Toolbox Talk

    ALL work shall proceed only after a Toolbox Meeting (TBM) has been conducted by the Permit

    Holder.

    Subjects which must be covered include:

    1. Work scope & supporting documents (Isolation schemes, method statements and lift plan for

    example)

    2. Hazards identified in the Level 1 or 2 risk assessment

    3. Control which must be put in place and verification that they are in place

    4. Any additional Hazards as identified on suite by the work party (situational awareness)

    5. Any additional controls required

    6. Communication protocols during the task

    7. Access and egress and Emergency procedures

    8. Reporting of incidents / problems

    9. PPE Required

    10. Tools required

    11. Housekeeping and general waste management

    12. Potential Conflicts / SIMOPS

    13. Work Party Responsibilities

    14. Level of Supervision required

    15. Should the conditions change report to Permit Holder

    16. Experience / Qualifications of Work Party, for task allocation

    The Permit Holder shall ensure that the work crew fully understands of the TBM content.

    Following the TBM, the work party must sign onto the PTW in Section 10, to confirm they fully

    understand and willingness to comply with the instructions and controls to safety complete the task.

    The TBM shall be repeated for any new work party member joining after the pre-start TBM.

    For further detail on TBM, refer to 2000-100-G000-GE00-G00000-HX-6180-01692, TBM procedure.

    Area Authority, HSSE representative and Project Management will perform regular audits of the

    PTW system and include TBM attendance.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    32/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 32 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    11.RESPONSE TO FACILITY / YARD EMERGENCIES

    It is the responsibility of the each of the Project personnel to raise the alarm if an emergency

    situation is spotted, e.g. in case of fire, personnel injured or in acute health condition; man

    overboard; major incident, etc. The individual should raise the alarm as soon as aware of the

    situation by notifying his/ her supervisor/ permit holder or an HSSE representative; call the Yard

    emergency number, or directly activating the sound alarm.

    In the communication he/she should be explicit on the location; the situation and contact.When the Prelude Facility emergency alarm is sounded all work must stop immediately, personnel

    must make the work area safe and proceed to their assigned project muster point.

    When the All Clear is given, work that was being carried out under the Permit to Work must not

    restart until the job has been released by the Area Authority. Its the responsibility of the Permit

    Holder to liaise with the Area Authority before recommencing work.

    12.PERMIT AUDITING & SITE INSPECTION

    Auditing is an integral part of managing the Permit to Work System. It is a documented activity that

    verifies that the requirements of the system :

    Have been established

    Have been documented

    Are effective

    Corrective action has been initiated when required.

    It is the responsibility of the TSC SSS to attend daily (every shift) to the Level 1 Permits and verify

    compliance with the specified controls at the start of work in their assigned areas. They must report

    to the Permit Issuer on all issues and non-compliances identified and suspend the permits until

    compliance restored.

    TSC/CPY HSSE and Project management shall conduct a regular walkthrough of the workplace

    carrying out general checks on the status of PTW compliance. To this end a PTW Inspection check

    sheet has been established, refer to Appendix 6, and a target for documented verification frequency

    established.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    33/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 33 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Monthly review and analysis of the findings will be conducted by the PTW Process owner and shared

    with the PTW Authorized signatories.

    A bi-annual in depth review will be carried out to confirm compliance with this procedure and identify

    areas for improvement. This review will be performed by a Joint HSSE Team/Construction

    Leads/CSU leads.

    13.TRAINING, ASSESSMENT AND AUTHORIZATIONS

    The signatory authorities of the PTW shall only be assigned to personnel who:

    Have received appropriate training, as per the TSC and CSU HSSE & SP Plans and

    HSSE & SP TRAINING PLAN GOC, ref. 2000-100-G000-GE00-G00000-HX-5798-01599

    (To be updated) and have been assessed competent in accordance with the requirements of

    project Specific PTW Procedure, the PTW referenced procedures and TSC Training

    Standards.

    Have been authorized and appointed to the applicable PTW role in writing And have

    accepted the responsibilities and duties the role entails.

    Additional communication and training shall be conducted when material changes to the procedure

    are made based on incident investigation or change of scope/interfaces and shall be recorded. An

    authorization may be withdrawn if a particular authorization is no longer relevant to a person's duties

    or if the person consistently fails to fulfill the role responsibilities.

    A PTW Authorized Certificate, as per the role of the person shall be issued to each person appointed

    to an authorized PTW signatory level, nominated by the Relevant Production division or CSU division

    and endorsed by the Overall Authority to demonstrate the level of authorization achieved. Refer to

    appendix 5.

    Each Training Learning Outcome shall include:

    Competency Assessment Criteria for each Learning Outcome depending their involvement in

    the PTW system (i.e. specific training and evaluation for PTW roles list en chapter 7 to be in

    place).

    Documented evidence of the assessment process

    A documented process for recognized prior learning and current competence and

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    34/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 34 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    An assessment for competence that is documented in writing.

    All authorizations, training and competency assessment shall be recorded and Documented in an

    auditable manner. An evergreen list will be maintained by the PTW Process Owner.

    Records of all assessments, authorizations, Initial and Refresher Training Courses shall be retained

    by the TSC Training dept.

    A listing of all authorized persons shall be permanently displayed in the Permit to Work coordination

    offices.

    For Isolation authorities training and competency requirements refer to Isolation Lock out/ tag out

    Procedure, ref. 2000-100-G000-GE00-G00000-HX-6180-01590

    14.PTW NOTIFICATION

    A notification system for high risk activities will be established to advise personnel of activities

    affecting an area, examples of high risk activities are;.

    Pneumatic pressure testing

    High pressure nitrogen / helium leak testing

    Module lifts

    Non routine complex lifts

    Electrical switchboard energization

    Boiler start up / firing

    Steam blowing

    Compressor mechanical runs (air / nitrogen)

    Radiation (ND Testing)

    Typhoon preparedness

    Other activities as defined by Area Authorities

    This is applicable to all Project activities in GOC day shift, extended shift, night shift, weekends and

    holiday periods.

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    35/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 35 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Those will be communicated via e-mail 24 hours in advance to the respective site representatives;

    HSSE, Construction and Commissioning Managers. in the TSC and Company organization and a

    notice board in the respective offices.

    The notification shall contain a brief description of scope, location, potentially affected area/s, timing

    and person in charge of the work with contact telephone number.

    15.CONSEQUENCE MANAGEMENT

    Consequence management will be applied to those who work without a valid permit, when a permit is

    required and those who break any of the Shell Life Saving Rules, SHI Golden Safety Rules as per

    the Project HSSE Consequence management Procedure, Ref.2000-003-G000-GE00-G0000-HS-

    6180-00003 03A.

    16.APPENDIX LIST

    Appendix 1 Permit To Work Flow Diagram

    Appendix 2 Permit to Work Template (Korean and English Versions)

    Appendix 3 Risk Assessment template

    Appendix 4 Application scope and permit authorities

    Appendix 5 PTW Authorized Signatories Certificates

    Appendix 6 PTW Inspection check sheet

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    36/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 36 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Appendix 1 : Permit To Work Flow diagram

    Job Planning

    Assess Work Scope Requirements and Construction

    methodology/ sequence.

    Minimize risk by selecting a safer methodology.

    Complete Level 1 Risk

    Assessment

    With HSE and Peer Support

    High Risk

    Activity

    Identify SWS or generic Job Safety

    Analysis for the task at hand or

    conduct Level 2 RA

    Draft PTW

    Including All Supporting Documents,

    L2RA, Isolation Summary and Marked

    Up Drawings

    Verify / Approve

    Ensure Hazards

    and Controls are

    Suitable

    AuthorisePTW

    Issue Isolation

    CetificateIf

    Required`

    Isolation Certificate Authorised

    By Approved Authority

    Isolations Implemented

    and Verified

    All Locks and Tags in place

    Confined

    Space

    Entry

    Gas Testing and Entry Logs

    Perform Initial Gas Test

    IssuePermitTo Work

    Work in Progress

    Work Site Managed by Permit Holder

    Work Complete

    Work Site Left in a Safe and Tidy Condition

    PTW Signed OFF

    Issue Isolation

    Cetificate for De-

    Isolation if

    Required

    De-IsolationAuthorised

    By Approved Authority

    All Isolations Removed and

    Verified

    All Locks Removed and Tags

    Returned with Certificate

    Work Permitand Certificates

    Closed

    All Documents Archived

    No

    Yes

    No

    No

    No

    Yes

    Yes

    No

    Yes

    Yes

    WHO / WHAT

    Permit Requester Bitmap

    Subject Matter Expert (if required)

    1)Planning of Work Scope

    2) Assess Hazards

    3) Completes PTW ready for Submission

    4) Completes L2RA if required

    5) Completes Isolation Summary Sheet

    6) Provides Marked Up Drawings

    D -X

    D -3

    D -1

    D

    D

    D

    D + X

    Permit Approval

    1)Review and Verify Work Scope

    2) Assess Identified Hazards

    3) Review Proposed Controls

    Permit Issuer Isolation

    1) Authorized PTW

    2) Issues Isolation Cert to Authority

    3) Verifies isolations are completed

    Isolation Authority

    1) Completes All Listed Isolations

    2) Ensures Locks and Tags are fitted

    3) Returns Signed Isolation Cert`

    Permit Issuer - Approves Initial Testing

    1) Confirms Control In place

    2) Notifies Emergency Response Team

    3) Issues CS Permit to AGT

    Approved Gas Tester

    1) Confirms Gas Detector Operation

    2) Conducts Initi al Gas Test

    3) Records Readings

    4) Ensures Signage is Posted at Entry

    5) Returns CS Permit to Permit Issuer

    Permit Issuer

    1) Holds Permit Awaiting Issue

    2) Assesses Concurrent Activities

    3) Discusses Permit Requirements

    Permit Holder -Work In Progress

    1) Accepts Responsibility for the Work

    2) Ensures all Isolations are In Place

    3) Conducts Toolbox Talk with Work Party

    4) Ensures Work Procedures are Followed

    5) Monitors Site and Concurrent Act ivities

    6) Ensures Work Site is Left Safe and Tidy

    Permit Holder - Work Complete

    1) Ensures All Work has been Completed

    2) Returns PTW upon completion of Scope

    3) Signs PTW as Work Complete

    Permit Issuer - Work Completed

    1) Ensure Permit Holder Sign OFF PTW

    2) Defines De-Isolation Authority

    3) Issues De-Isolation Cert to Authority

    De-Isolation Authority

    1) Completes All Listed De-Isolations

    2) Ensures Locks and Tags are Removed

    3) Returns Signed De-Isolation Cert

    4) Returns All Tags with De-Isolation Cert

    Permit Issuer - De-Isolation Completed

    1) Verifies All De-Isolations are Complete

    2) Files all Documents to Historic Archive

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    37/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 37 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Appendix 2. Permit to Work Template (Under revision to be adapted for both construction and CSU phases)

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    38/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 38 of 55

    Prelude FLNG Project Project Permit To Work Procedure

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    39/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 39 of 55

    Prelude FLNG Project Project Permit To Work Procedure

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    40/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 40 of 55

    Prelude FLNG Project Project Permit To Work Procedure

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    41/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00G00000 PP 0000 01697

    Security Classification COMPANY Document number Doc Class: 2

    RESTRICTED Project IDOriginator

    CodePlant Code

    Main Unit Code(Parent)

    Unit Code(Child)

    Discipline Doc TypeSequential

    No. Rev Page

    ECCN

    CodeEAR99 2000 100 G0000 GE000 G00000 HX 6180 01697 01R 41 of 55

    Prelude FLNG Project Project Permit To Work Procedure

    Appendix 3 Risk Assessment Template

  • 7/25/2019 pEPCI Project Permit to Work Procedure code 3.pdf

    42/55

    TSC Document number

    Project n Area-Unit CodeDoc.type

    Materialcode

    SequentialNo

    60869M GF00