Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 1 of 12
PDR.12 PRELIMINARY QUALIFICATION & ACCEPTANCE
PLAN
Document number………………………………………………………………………………SKA-TEL-SDP-0000051
Context………………………………………………………………………………………………………………………………SE
Revision……………………………………………………………………………………………………………………………..01
Author…………………………………………………………………………………………………………………..S. Ratcliffe
Release Date………………………………………………………………………………………………………..2015-02-09
Document Classification…………………………………………………………………………………….Unrestricted
Status……………………………………………………………………………………………………………………………Draft
Name Designation Affiliation
Signature & Date:
Signature:
Email:Simon Ratcliffe (Feb 9, 2015)Simon Ratcliffe
Technical Lead
SKA South AfricaSimon Ratcliffe
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 2 of 12
Name Designation Affiliation
Signature & Date:
Version Date of Issue Prepared by Comments
0.1
ORGANISATION DETAILS
Name Science Data Processor Consortium
Signature:
Email:Paul Alexander (Feb 9, 2015)Paul Alexander
SDP Lead
University of CambridgePaul Alexander
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 3 of 12
1 Table of Contents 1 Table of Contents ................................................................................................................ 3
2 List of Figures ..................................................................................................................... 3
3 List of Tables ...................................................................................................................... 3
4 Introduction ......................................................................................................................... 4
5 References ......................................................................................................................... 4
5.1 Applicable Documents ................................................................................................. 4
5.2 Reference Documents ................................................................................................. 4
6 Assumptions ....................................................................................................................... 6
7 Verification Approach .......................................................................................................... 6
7.1 Qualification ................................................................................................................. 7
7.2 Acceptance .................................................................................................................. 7
7.3 Commissioning ............................................................................................................ 7
8 Verification programme ....................................................................................................... 8
8.1 Objectives .................................................................................................................... 8
8.2 Activities ...................................................................................................................... 8
Formal reviews, peer reviews and walkthroughs ................................................................. 9
Verification through testing .................................................................................................. 9
Verification through analysis ..............................................................................................10
Verification through Inspection ...........................................................................................11
8.3 Simulators ...................................................................................................................11
8.4 Test Environments ......................................................................................................11
Build Verification Environment ...........................................................................................11
Development Test Environment .........................................................................................11
Integration Test Environment .............................................................................................12
Volume and Performance Test Environment ......................................................................12
9 Verification Matrix ..............................................................................................................12
2 List of Figures Figure 1: The ‘bathtub’ curve depicting failure rates versus time. ..............................................10
3 List of Tables There are no tables in this document.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 4 of 12
4 Introduction
This preliminary document sets out the approach taken by the Science Data Processor element towards
verification activities. This is primarily concerned with qualifying the design against the allocated
requirements and accepting constructed instances of the SDP sub-elements onto the SKA telescope sites
in preparation for commissioning activities.
This document will be split into a Qualification Test Plan (QTP) and an Acceptance Test Plan (ATP) for the
Critical Design Review (CDR). However, at this stage there is sufficient overlap to justify a single
document that describes the high level philosophy towards verification.
5 References
5.1 Applicable Documents The following documents are applicable to the extent stated herein. In the event of conflict between the
contents of the applicable documents and this document, the applicable documents shall take
precedence.
Reference Number Reference
[AD1] SKA Phase 1 System (Level 1) Requirements Specification
W Turner, Document Number SKA-TEL-SKO-0000008, Dated 15 Sep 14
[AD2] SKA-TEL-SKO-DD-001 SKA1 SYSTEM BASELINE DESIGN
[AD3] MISCELLANEOUS CORRECTIONS TO THE BASELINE DESIGN
[AD4] SKA-TEL-SDP-0000054 - SDP Prototyping Plan
[AD5] SKA-TEL-SDP-0000052 - SDP High-level Risk Register
5.2 Reference Documents
The following documents are referenced in this document. In the event of conflict between the contents
of the referenced documents and this document, this document shall take precedence.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 5 of 12
Reference Number Reference
[RD1] International Standard – Systems and software engineering – Software Life Cycle
Processes ISO/IEC 12207 IEEE Std 12207-2008, Dated 01 Feb 08.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 6 of 12
6 Assumptions
As a preamble to this document, we list the fundamental assumptions that guide our overall approach
to verification. Although this content is repeated and expanded upon in the following sections, it is
summarised here to ease review of the document.
● Functional qualification of the overall architecture will primarily be achieved through testing of
verification requirements against simulators.
● Performance qualification of aspects of the overall architecture may require deferral until real
sky data is available.
● An agile, iterative approach to qualification is taken, to match the proposed software
development methodology.
● Qualification and Acceptance are discussed jointly in this document and are only split in the run
up to the Critical Design Review.
7 Verification Approach
Although it is traditional to follow the “Vee” model as espoused in [RD1], our feeling is that this model is
too restrictive when considering verification of a system such as the SKA as a whole, and indeed the SDP
in specific.
The top down approach to development is likely to be followed fairly closely, and certainly the element
level of the SKA will do so with some rigour. However, at the lower levels it is felt that a more agile
approach to development and testing, and by extension verification, is needed.
The main aim for adopting an alternate approach is to allow testing that is both iterative and crosses the
traditional horizontal boundaries in the “Vee” approach. For instance, the LMC sub-element is likely to
provide a simulation capability, with limited functionality, at a very early timescale. This will be
integrated into a testing loop with other sub-elements at multiple levels to support component testing.
These types of prototyping activities [AD4] will take place throughout the SDP consortium, and are an
essential input into the design process. This deep embedding of prototyping into the design phase will
be fully documented in the Qualification Test Plan (QTP).
These activities will form a critical part of the evolution of the SDP design from PDR to CDR phase,
culminating in the Qualification Test Report, which proves that the proposed design meets the
requirements specification.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 7 of 12
Verification is also closely tied to the management of risk [AD5], and many of the risk register items will
be explicitly retired only when the design components underlying the risk have been appropriately
verified.
7.1 Qualification
The purpose of qualification is to ensure that the proposed design meets the requirements that specify
the design. This happens at multiple levels, with a cascaded, hierarchical approach to the process.
The first step in the qualification process is to establish a set of verification requirements, which provide
coverage of the requirements assigned to a particular function. These verification requirements are
categorised by the method of verification, with those to be verified by test forming the backbone of the
qualification process.
The QTP will describe in detail the formal process for arriving at a fully qualified SDP element.
7.2 Acceptance
The purpose of acceptance testing is to ensure that a component, be it hardware or software, meets the
set of requirements that specify the particular component. In many circumstances, tests similar to those
used for qualification of the design can be used, although the stakeholders are generally different.
Typically acceptance marks the formal handover of a component from the developer to the client. This
may be an internal handover in the case of integrated components and can be quite lightweight, and
automated, in this scenario.
Once the individual components have been accepted, the formal process of verifying the emergent
behaviour of the integrated system commences.
7.3 Commissioning
Acceptance testing only proves that the component meets the requirements specified on it, it does not
guarantee that the component will perform acceptably once integrated into the operational system.
This is one reason why it is essential to have strict control of interfaces, as this significantly mitigates the
commissioning risk. Once any initial issues have been dealt with, a number of softer operational tasks
are performed:
● Handover of documentation and training material.
● Direct training of operational staff.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 8 of 12
● Side by side operations.
At the conclusion of side-by-side operations, the commissioning team will take operational responsibility
to evaluate the final performance of the component. The SDP team, particularly QA, will be readily
available through this period to address any concerns and bugs that may be found.
For the SDP in particular, early commissioning will be a critical activity as it will mark the first time in
which the full performance can be adequately evaluated although it may be possible to gain an early
indication of system performance by deploying with simulated inputs on representative hardware in
large national facilities ahead of time (assuming representative hardware may be found). This is
described in Volume and Performance Tests below.
8 Verification programme
The SDP Element verification shall be risk-driven. High risk areas shall be identified at the time of the
requirements review and a plan shall be proposed for mitigating these risks. These risk mitigation
activities shall be described in the SDP element development plan and the prototyping plan [AD4]. The
risks will drive the verification activities performed on the SDP element.
8.1 Objectives
The objectives of the risk driven approach are to ensure that:
● Identification of risk, with mitigation through the verification function;
● The appropriate level of risk based verification is performed, under the guiding principle that the
verification is carried out at the earliest possible point in the lifecycle thereby reducing costs;
● To ensure that the design is proven to meet the qualification criteria, and is able to be deployed
to the production phase with a low risk of integration;
● To drive down technical/technology risks of the project;
8.2 Activities
Verification activities will include:
a) Formal reviews, peer reviews and walkthroughs;
b) Verification through testing of qualification models, including horizontal and vertical prototypes;
c) Verification through analysis by means of modelling and simulation;
d) Inspection of products and assemblies.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 9 of 12
A subset of verification activities will form the basis of the Qualification Test Plan, where the results of
the verification activities will be captured in a Qualification Test Report after successful execution.
Formal reviews, peer reviews and walkthroughs
Key artefacts will be subjected to peer reviews and walkthroughs before being formally reviewed e.g.
requirements specification, design documents. The risk driven approach will dictate the type of review
performed on each artefact produced during the pre-construction phase. Code is treated as an artefact
and will likewise be subjected to reviews.
Verification through testing
Qualification models will be subjected to a range of tests including unit tests, component tests,
integrated SDP tests, hardware verification tests, regression tests and volume & performance tests
during the pre-construction phase.
Unit Tests
Each SDP component shall be sufficiently covered by unit tests to ensure the units within the
component are ready for component testing. Unit tests across all components will be executed on a
regular basis to ensure the integrity of the component is maintained, with quick identification and
correction of defects at this level.
Component Tests
Requirements allocated to each SDP component must be covered during component testing. SDP
components will be tested by simulating external interfaces. Component tests will be executed on a
regular basis to ensure integrity of the component is maintained, with quick identification and
correction of defects at this level.
Hardware Verification Test
Hardware components typically follow a ‘bathtub’ curve of failure rates versus time (see Figure 1).
Hardware components will undergo a ‘burn-in’ test to eliminate early component level failures.
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 10 of 12
Figure 1: The ‘bathtub’ curve depicting failure rates versus time.
Hardware verification may in some cases seek to verify the electromagnetic interference and
electromagnetic compatibility requirements of the SDP element.
Integrated SDP Tests
Integrated SDP tests will be performed against a full simulated system to cover SDP functionality across
multiple components and exercise the full SDP subsystem in a “true-to-life” framework. Integrated SDP
tests will be logged against the set of SDP requirements to ensure coverage of the requirements.
Integrated SDP tests will cover the bulk of the qualification tests required to ensure conformance with
the requirements.
Regression Tests
Functional tests will be scripted where possible such that a set of automated regression tests can be
executed before and after changes are introduced to a test environment. An automation framework is
proposed to be used to facilitate regression testing.
Volume and Performance Tests
Volume and performance tests will be conducted on representative hardware to ensure conformance
with performance requirements. Simulators will be used to scale inputs to the required levels. Volume
and performance tests will be logged against the set of performance requirements to ensure coverage
of requirements.
Verification through analysis
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 11 of 12
Verification through analysis includes sampling and correlating measured data and observed test results
with calculated expected values to establish conformance with requirements.
Qualification models and prototypes will be subjected to verification by analysis where verification
through testing is not possible.
Verification through Inspection
Verification through inspection involves the evaluation by observation and judgment accompanied by
the physical act of measurement or gauging to assess conformance with specified requirements.
8.3 Simulators
Simulation will play an essential role in both qualification and acceptance verification. Particularly as
part of an integrated, hierarchical testing framework, simulators of components that have multiple
dependencies will provide much more robust testing than would otherwise be possible.
Ideally, the SDP would like to completely isolate all external dependencies into simulators. This would
mean at least simulating the following interfaces:
● SDP-TM
● SDP-CSP
Such capabilities will be of use to the other party in the interface as well, and so opportunities for co-
development are clear.
8.4 Test Environments
Build Verification Environment
Responsible for building SDP element components and performing build verification tests. Automated
unit and component level tests will be executed on this environment to perform regular checkpoints on
the integrity of the current build. A minimal hardware specification is used for this environment.
Development Test Environment
A test environment for ad-hoc integration (functional) testing of units and components. This
environment allows development teams to test new units\components at a high-level without going
through the rigours of a configuration management process. This environment is also used for
Document No: SKA-TEL-SDP-0000051 Unrestricted
Revision: 01 Author: S. Ratcliffe
Release Date: 2015-02-09 Page 12 of 12
reproducing\troubleshooting defects not evident at a unit level. A minimal hardware specification is
used for this environment.
Integration Test Environment
A test environment used to perform functional integration testing of SDP units and components. This
environment is formally controlled using change control and configuration management processes.
Representative hardware is used for this environment.
Volume and Performance Test Environment
A test environment used to test non-functional requirements such as performance, capacity, resource
usage, and availability. This environment is formally controlled using change control and configuration
management processes. Representative hardware is used for this environment.
9 Verification Matrix
The verification matrix will detail each verification requirement placed on the SDP at all levels. It will list
the requirement under verification and the verification method.
This will be developed early on in the CDR process once the top-level requirements and design have
been signed off at PDR.
PDR12PreliminaryQualificationandAcceptanceplan(1)EchoSign Document History February 09, 2015
Created: February 09, 2015
By: Verity Allan ([email protected])
Status: SIGNED
Transaction ID: XJEEYGIF2I443AX
“PDR12PreliminaryQualificationandAcceptanceplan (1)” HistoryDocument created by Verity Allan ([email protected])February 09, 2015 - 2:51 PM GMT - IP address: 131.111.185.15
Document emailed to Simon Ratcliffe ([email protected]) for signatureFebruary 09, 2015 - 2:52 PM GMT
Document viewed by Simon Ratcliffe ([email protected])February 09, 2015 - 2:58 PM GMT - IP address: 66.249.93.195
Document e-signed by Simon Ratcliffe ([email protected])Signature Date: February 09, 2015 - 3:00 PM GMT - Time Source: server - IP address: 196.24.41.254
Document emailed to Paul Alexander ([email protected]) for signatureFebruary 09, 2015 - 3:00 PM GMT
Document viewed by Paul Alexander ([email protected])February 09, 2015 - 6:41 PM GMT - IP address: 131.111.185.15
Document e-signed by Paul Alexander ([email protected])Signature Date: February 09, 2015 - 6:41 PM GMT - Time Source: server - IP address: 131.111.185.15
Signed document emailed to Verity Allan ([email protected]), Paul Alexander ([email protected]) andSimon Ratcliffe ([email protected])February 09, 2015 - 6:41 PM GMT