JAYPEE INSTITUTE OF INFORMATION
TECHNOLOGY, NOIDA
PROJECT MANAGEMENT REPORT
(Even Semester, 2011)
ENTERPRISE RESOURCE PLANNING SYSTEM
FOR
CAPSULE CORPORATION
(D-28,PATPARGANJ INDUSTRIAL AREA,DELHI)
IndranilSen(08102179)
Amber Gupta (08102190)
AbhinavGupta(08102193)
ShishirJain(08102200)
GauravJain(08102270)
Pratik Kalia(08102306)
-
8/6/2019 pd proj (1)
2/14
ACKNOWLEDGEMENT
We would like to express our gratitude to Mrs Swati Sharma, our Project
Management Course lecturer at JIIT University, Noida for developing our
Project Management skills under her guidance. She has provided an invaluable
help with ideas and discussions throughout our entire time working on this
work. It was both an honour and a privilege to work with her. She also
provided help in technical writing and presentation style and we are extremely
grateful for her invaluable guidance in bringing this project to a successful
completion.
-
8/6/2019 pd proj (1)
3/14
1. INTRODUCTION
1.1 Objective of the Project
The objective of the project is to develop a business support system for the Computer
Department atCapsule Corporation that maintains in a single database, the data needed
for a variety ofbusiness functions such as Manufacturing, Transactions, and Customer
Management etc.
The system must be based on a common database and a modular software design. The
commondatabase can allow every department of a business to store and retrieve
information in real time.
Initially, the company was maintaining customer database and transactions database
using excelsheets. It became impossible for company to maintain data using excel sheets
once the customerbase crossed the thousand mark. Hence, a software was needed
which could automate the wholeprocess.
The project will also include the continuous maintenance of the software in case of
problems arisingor changes and modifications to be made in the software to match with
the changes in the companypolicies along with time.
1.2 Project Overview
One of the major objectives of the project is to develop a mod ule for Customer
RelationshipManagement which includes adding customer details, multiple customer
contacts, maintainingcustomer purchases and transactions, sending sms and mails tocustomers.
Another important objective is Employee Management System to store all the
information about theemployees of the company, adding new employees, editing the
information of existing employees,maintaining their pay slips etc.
The project must also provide the solution to keep a record of the vehicles owned by the
company,the number of trips a vehicle makes, the trip details, the details and facility to
add and delete routes.In addition to this a full-fledged record of the number of jars and
dispensers in stock, those on rent,those which are sold and those which are in
maintenance or are discarded must be kept.
As already mentioned, the company was initially maintaining data using excel sheets.
Hence, just toavoid re-inputting of data, the user must have an option of importing data
from excel to Sqldatabase. The user must also have an option of exporting the data from
Database to Excel.
-
8/6/2019 pd proj (1)
4/14
Besides this, just to make the software more secure, the employees of the firm could use
it onlyafter entering their username and password which they could get after making an
account. Thesoftware must divide the users into two types: Admin or Limited. Anyone
must be able to make a Limited Account which provides limited functionalities. In case
the user makes an admit account, itmust not allow the user to log in until and unless it is
activated by the CEO of the company. If theuser forgets the password then the userspassword must be mailed to his/her account on request.
The project will also include the setting up and configuring of the various terminals
(computersystems) all over the company premises with the developed software along
the facility to be interconnectedover LAN (Local Area Network) and share information
with each other and the commondatabase server.There remains a big risk of database
or server crash which may lead to complete loss of theimportant data of the company
hence the software must be equipped with the functionality ofkeeping a database
backup from time to time so that the data can be retrieved in case of emergency.
2. PROJECT ORGANIZATION AND PLANNING
2.1 Project Life Cycle (Process Model)
The project lifecycle will include the following steps:-
1. Requirements specification
2. Analysis and Design
3. Construction (AKA implementation or coding)
4. Integration
5. Testing and debugging (AKA validation)
6. Installation (AKA deployment)
7. Maintenance and Monitoring
-
8/6/2019 pd proj (1)
5/14
The project implementation will be based on the Waterfall Process Model.
The Waterfall Model for Software Development
2.2 Description of the Life Cycle
Requirements Specification: This forms the foundation of the software development
project andneeds a lot of care and attention to be paid. All the designing and planning of
the project is based onthe requirements of the customer. Collecting and analyzing the
requirements takes a goodpercentage of time from the life cycle of the project.The
expenses during this phase include the conveyance charges, telephone charges,stationary andprinting charges.
Analysis and Design:The project derives its form from the design phase. It forms a major
part ofthe project life cycle and consumes a respectable amount of time. However the
cost involved in thisphase is small as compared to its importance in the project life
cycle.
Construction/ Implementation: The construction phase is the soul of the project and
takes themaximum portion of the life cycle. It includes the complete coding of the
software and involvesrigorous work form the programming team. The cost involved is
again nominal.
Integration: This phase involves the linking together of all the modules of the software
developedand the hardware/ external components.
In our project before integration could start we need to setup a database server and the
LAN.
-
8/6/2019 pd proj (1)
6/14
The installation of database server requires a specialist and involves a major part of
the costin the form of buying the high power PC based server.
The setting up of LAN includes the cost of hardware like switches, hubs, cables,
connectors,etc and the raw material like cement, plaster of Paris, wall sockets and cable
holders. It alsoinvolves the cost of unskilled workers to lay down the cables.
Testing and debugging: Once the system is integrated every part needs to be rigorously
tested bythe testing team and the shortcomings detected are removed by the designing
and developmentteam. It constitutes a major part of the project life cycle and is
dedicated to the improvement of theperformance of the software.
Another dimension of the performance of the software i.e. the security analysis of the
softwaredeveloped is also extended with the testing phase.
Deployment: After undergoing the testing and debugging phase the completed software
is deployedin the company along with the add on software to be installed on the
computer systems in thecompany required for the execution of the software developed.
With the end of this phase thesoftware is fully functional.
This phase also includes the activity of training the company employees about the use
andfunctionality of the software developed.
Maintenance and monitoring:This phase includes the monitoring the performance of
thedeveloped software and analyzing and carrying out any modifications or corrections
in the softwareas reported by the users or the project sponsor, keeping in mind the
effect the change has on allother important factors.
2.3 Work Breakdown Structure
2.4 Resource Requirements
Collecting Software Requirements: The phase of collecting requirements of the software
will require a team of skilled professionals and conveyance facilities for the team to go
to the company office to collect the various requirements from different departments.
Analysis, Design and Documentation: We certainly require skilled people to analyze the
collected requirements and other detailed information and to design the software
structure and plan accordingly. We will also need few people proficient in technical
documentation and typist. During this phase the team will require the various modelingsoftware available for software engineering like Rational Rose and Visual Paradigm.
Development: The development phase will require a team of professional programmers
and software packages which provide the platform for the software designing. This
depends on the type of software to be designed and the choice of both the parties the
programmers and the process owner. For example Microsofts Visual Studio for
Windows applications, Java for open source or platform independent applications,
-
8/6/2019 pd proj (1)
7/14
Oracle, MySql or MS Sql for the database backhand and so on.Here for this application
we choose Microsofts Visual Studio 2005 for developing the front end and MS Sql for
the database management. The programmers may also require books and internet for
reference during the development process of the software.
Installation of required Software on existing Systems: Few things like run time
environments,software packages, support systems and add ons like libraries, plugging
etc may be required to beinstalled on the machines for the complete and proper
functioning of the software developed. Hencethis stage of the project will need the
licensed software to be bought and a small workforce to installthese on the systems in
the company office. This team of workers will also need the conveyancefacilities.For this
project we would require Microsoft Dot NET framework 3.0 and windows service pack
2to be installed on all the office machines.
Database Server Setup: During this phase we would require a specialist to setup and
configure thedatabase server and a PC based Database Server with a high speed hard
disk, network card,sufficient amount of RAM and a powerful processor depending upon
the company requirements i.e.number of nodes connected and the number of database
transitions per second. This must beaccompanied with a power backup.
Network Setup: To setup the network we need to have a team of professionals in
networking andsome skilled labor for laying the network cables all around the office
premises along with thehardware like hubs, switches, twisted pair network cable and
connectors. The expenses will involvelabor charge, cost of materials used for laying
down the LAN wire and the cost of other hardware.
Integration: The integration part would involve all the modules to be linked together
forming thecomplete system. For this we would require the specialists of every module
to work together andintegrate the modules.
Testing:All testing sessions including oper ational testing, integration testing, application
testingand security analysis will require skilled testing team and the documentation
team to keep a recordof the problems encountered and the changes that the project
needs to undergo. It would alsorequire some end users to use the software and give the
feedback. Some automated testing andanalysis software would be required by the team.
Monitoring and Maintenance: This phase will require the users to send in a report or
feedback viaemail or on a telephonic conversation else a face to face meeting. The
designing and developmentteam along with the documentation team would be involved
in bringing out any further changes andmodifications according to the users demand.
3. BUDJETING AND COST ESTIMATION
-
8/6/2019 pd proj (1)
8/14
Materials (Hardware)
1. Storage Media:
CD/DVD - 50* (Rs10) = Rs 500
Pen Drives 10* (Rs 400) = Rs 4000
2. Network Hardware:
Switches (24 port) 2* (Rs 6000) = Rs 12000
Hub (4 port) 5 * (Rs 200) = Rs 800
LAN Cord (cat 5) 200 Meters * Rs 10 = Rs 2000
Connectors (RJ 45) 100 (Male-Female Pairs) * Rs 5 = Rs 500
3. Database Server (IBM):- Rs 54,000
Raw Material for Laying Network Cable
1. Cement:- Rs 200
2. Plaster of Paris:- Rs 200
3. Cord Holder:- Rs 8 per meter * 50 = Rs 400
4. Wall Sockets:- Rs 10 * 50 = Rs 500
Expenses
1. Conveyance Charges Rs 60 per trip to the company office per person.
10 members * 20 trips during project *60 = Rs 12000
2. Telephone Charges 10 members *200 calls/month *5 months * Re 1/call = Rs 10000
3. Internet Connection Charges Rs 700 per month* 5 months = Rs 3500
4. Electricity Charges Approx Rs. 3000 per month* 5 months = Rs 15000
Software: Microsoft Dot NET framework 3.0 Rs 6000
Stationary and Printing Charges
1. Stationary:
A4 sheets 10 packs * Rs 130 =Rs 13 00
Files/Folders 30 * Rs 15 = Rs 450
Pens 50 * Rs 9 = Rs 450
-
8/6/2019 pd proj (1)
9/14
Staplers and paper pins Rs 250
2. Printing:
A4 sheets 10 packs * Rs 130 = Rs 1300
Printing Cost Rs 0.30 * 5000 = Rs 1500
Wages and Salaries (Table)
Total Estimated Budget for the Project = Rs 2286850
In Words: Rupees Twenty Two Lakhs Eighty Six Thousand Eight Hundred and Fifty
Only.
No. of
Persons
Salary Time
Duration
Total
Salary
Project Manager 1 25000/Month 5 Months 125000
Network Specialist 1 20000/Month 5 Months 100000
Database Server
Specialist
1 20000/Month 5 Months 100000
Analysis And DesignTeam
6 18000/Month 5 Months 540000
Skilled Programmers 10 15000/Month 5 Months 750000Testing Team 10 10000/Month 5 Months 300000
Documentation Team 4 10000/Month 5 Months 200000
Semi-Skilled
Persons(Installation)
3 6000/Month 5 Months 36000
Unskilled
Workers(Cable)
6 150/Day 5 Months 9000
Total Salary 2160000
-
8/6/2019 pd proj (1)
10/14
RISK ANALYSIS
Types of Risks
1. Project specific risk: The cost of materials may rise which would eventually lead to an
overall higher cost of project development. Hence some reservoir of resources is needed
to be maintained and included in the budget.
2. Competitive risk: Alternative offer or software in the market might attract the
company due to lower cost of development and so the demand will reduce. There is also
a possibility that another project company offers attractive features. In such a case the
profits might be at stake.
3. Market Risk: If capital for project is acquired on loan, and interest rate increases due
to certainmacroeconomic variations, then there is a risk that overall cost will increase.
Uncertainty Factors
1. Server down: Higher load on the server may lead to the temporary delays in the
project at different stages of development and operation.
2. Internet: Internet connection with limited connectivity or lower speed than that
required may lead to the extension of project life cycle.
3. Electricity: Electricity related problems or any discrepancy in the back- up system
provided for the electricity supply system may delay the progress of project.
4. Accidents: Personal safety at the project development site is very necessary. Skilled
or semi skilled all laborers and technicians should be having their insurance. In addition
to this proper ambience must be provided to the specialist developers in order to
extract maximum work from them.
-
8/6/2019 pd proj (1)
11/14
5. Project Monitoring and Control
Continuously monitor and Analyze project variables: The key project variables will be
identified to be monitored at least weekly to ensure that their progress/status is in
accordance with their associated plan (i.e., project management plan, configuration
management plan, quality assurance plan).
The issues taken care would be: tasks starting and ending as planned, deliverables with
content and quality level required, level of effort as planned, milestones being met when
planned, risks as recorded applying the Risk Management Process.
The needed data would be provided through measurement activities, periodic team
reviews, and risk assessment events. In addition, the scope of work will be assessed
with respect to sponsor-initiated requirement changes to determine if the scope of
work has deviated from established agreements.
Team Meetings: The team meetings will be regularly scheduled to keep all the team
membersinformed about the current status of the work and to plan for the upcoming
project tasks defined inthe documented project plan. All the teams would be required to
inform everyone about theindividual tasks accomplished and project risks.
Revise the Course of plans: If the need of any corrective measure is determined as a
result of theanalysis and team meetings, the team would be required to analyze the
effect of the change on thecost, schedule, requirements and the stakeholders and try to
find out the best possible solution afternegotiation and approval form the senior
management and the project sponsor.
Initiate and track changes (Control):- The required changes and modifications will be
done in theplan and the design of the project. The changes and modifications would be
recorded and noteddown by the documentation team for future planning activities. The
project manager would beresponsible to keep a track that the required modifications
are properly
-
8/6/2019 pd proj (1)
12/14
PERT Chart Analysis of the Project
Activity Description Normal Time
NormalCost
CrashCost
CrashTime
CrashCost Per
Day
A Collecting
Requirements
15 40000 45000 12 1666.66
B Making The SRS 7 28850 30000 6 1150
C Analysis And Design 15 380000` 400000 12 6666.66
D Documentation 7 25000 28000 6 3000
E Development 60 700000 750000 55 10000
F Prototyping 7 25000 26000 5 500
G Installation of
Required Software on
Existing Systems
3 60000 62000 2 2000
H Database Server Setup 5 220000 230000 4 10000
I Hardware & Network
Setup
10 340000 350000 9 10000
J Operational Testing 7 75000 78000 5 1500
K Integration 10 95000 100000 8 2500
L Integration Testing 7 78000 80000 6 2000
M Application Testing 10 95000 100000 9 5000
N Security Analysis 5 125000 130000 5 -
117 2286850 2409000
-
8/6/2019 pd proj (1)
13/14
Activity on node Network Diagram
-
8/6/2019 pd proj (1)
14/14
The Slack Time for each activity are as follows:
Activity Slack Time (Days)
A 0
B 0
C 0
D 73
E 0
F 55
G 45
H 45
I 56
J 56
K 0
L 3
M 0
N 5
Hence the Slack Time is 0 for the activities on the critical path (A-B-C-E-K-M).
One day can be deducted from activity B with an increase in the cost by Rs 1150.00.
A deduction of up to 3 days from activity A will lead to an extra cost of Rs. 5000 (at the
rate of1666.67 Rs. per day).
If more than 4 days are required to be reduced, then activity K can be taken into
consideration afteractivity B and A. For activity K the increase in cost is Rs. 2500 per
day for a period of maximumtwo days.
Activity M, activity C and activity E follow in the crashing process with an extra cost of
Rs. 5000for a period of 1 day, Rs. 6666.66 per day for a period of maximum 3 days and
Rs. 10000 per dayfor a period of maximum 5 days respectively.