pcapp monthly status briefing november 2011

17
Monthly Status Briefing November 2011

Category:

Business


2 download

TRANSCRIPT

Page 1: PCAPP Monthly Status Briefing November 2011

Monthly Status Briefing November 2011

Page 2: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Project Background

The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in mortar rounds and artillery projectiles stored at the U.S. Army Pueblo Chemical Depot (PCD).

Neutralization followed by biotreatment is the technology selected by the Department of Defense to destroy the Pueblo chemical weapons stockpile.

The Program Manager, Assembled Chemical Weapons Alternatives (ACWA), headquartered at Aberdeen Proving Ground, Maryland, is responsible for managing all aspects of the safe and environmentally sound destruction of the chemical weapons stockpiles in Colorado and Kentucky.

The Bechtel Pueblo Team (BPT) is a partnership of Bechtel National, Inc., URS, Parsons, and Battelle Memorial Institute. The BPT functions as the systems contractor selected to design, build, systemize, pilot test, operate, and close the PCAPP.

2

Page 3: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Bechtel Pueblo Team

Project management Business services Safety and quality

Systemization Pilot testing Operations Closure

Process design Process equipment

fabrication Support to systemization

and operations

Environmental permitting and compliance

Laboratory management Pilot testing

Design/engineering Procurement/subcontracting Construction

Systems Contractor

Teaming Subcontractors

3

Page 4: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Staffing

Bechtel Pueblo Team non-manual: 586

– Pueblo: 578 (180 local hires)

– Other locations: 8

Construction Workers: 840

– Bechtel direct-hire craft workers: 666

– Subcontractor personnel: 174

4

Page 5: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Employment Opportunities

5

Hotline

(719)549-4003

Website

http://pueblo.bechtel.com

Page 6: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Safety

As of October 2011, PCAPP Project staff accomplished:

243 Safe Work Days

1,515,851 Safe Work Hours

6

Page 7: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Destruction Technology

7

Page 8: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Pueblo Chemical Agent-Destruction Pilot Plant—Site Plan

8 8

Page 9: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

PCAPP Site Overview

1

2

3

4

Enhanced Reconfiguration Building

Automated Guided Vehicle Corridor

Agent Processing Building

Biotreatment Area

Northwestern Corner - Observation Point

1

2 3

4

5

Agent Filtration Area

9

6

7

Munitions Service Magazine

Control and Support Building

5

6

7

8 Munitions Service Magazine corridor

8

Page 10: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Construction Status – In Progress

Enhanced Reconfiguration Building– electrical conduit, cable & wire pulling, equipment setting and terminations, installation of robotics and conveyors in the explosion and vapor containment rooms

Agent Processing Building– electrical conduit, cable and wire pulling, process piping, electrical and mechanical equipment setting

Balance of Facilities–cable raceway, underground duct banks, pipe rack piping and supports, various mechanical equipment setting; final site grading is complete

Control and Support Building– completing facility control/power system testing, including prep for beneficial occupancy in November

Medical Facility— completing final permanent power terminations and exterior final grading; starting furniture installation to support beneficial occupancy in November

Brine Reduction System—platform steel, tank/vessels placement and specialty coatings are complete; installing vendor supplied piping and instrumentation

Immobilized Cell Bioreactors—electrical and piping bulk installation and equipment insulation

Filter Press Building— building installation complete; starting mechanical, electrical and piping commodities

10

Page 11: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Systemization

Utility Building 480V Substation

Agent Processing Building (APB) 480V substation

APB Non-Essential motor control center power

APB essential motor control center power

Control and Support Building essential motor control center power

Agent Filtration Area (AFA) instrument air

AFA plant air

Utility Building essential motor control center power

BTA Essential motor control center

AFA critical power panels monitoring houses

Control and Support Building (CSB) Non-Essential power panels

NETA (International Electrical Testing Association) testing for power calibration

13.2 kV Switchgear

Utility Building Critical power panels

BTA Critical power panels

CSB Critical power panels

11

As the project transitions from construction to systemization, the following systems have been turned over to the start-up group to begin the systemization process:

To learn more about Systemization, watch the video at http://www.pmacwa.army.mil/info/video/systemization_yt.html

Page 12: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Systemization (cont.)

12

APB Critical Power Panels

HVAC exhaust filter units 07 thru 16, common ductwork, and stack

BTA 480V Substations

Agent Filtration Area (facility)

Plant Air System—Enhanced Reconfiguration Building (ERB) Distribution

Site Water: Existing potable water pumps and tie-ins

Existing Potable water pumps and tie-ins

2 ERB Non-essential Motor Control Centers (MCC’s)

2 ERB Essential MCC’s

1 BTA Non-essential MCC’s

1 BTA Essential MCC’s

Standby diesel generator 1A

Standby diesel generator 1B*

ERB 480V Substation*

To learn more about Systemization, watch the video at http://www.pmacwa.army.mil/info/video/systemization_yt.html

*Newly added

2 ERB Critical Power Panels*

CSB Facility Protection Controller*

AFA Facility Protection Controller*

HVAC Hot Water Distribution to APB*

Page 13: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Agent Processing Building

13

Taken from the upper level processing room, this photo shows one of the agent reactor tanks. The motor, visible on top, will turn the agitators inside the tank.

Page 14: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Pipe Rack

The pipe rack now encases the Immobilized Cell Bioreactors (left). In the distance, the Brine Reduction System evaporator can be seen.

14

Page 15: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Biotreatment Area

15

The Brine Reduction System includes an evaporator (tall tower) and filter press steelwork on the right.

Page 16: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

FEMA/Army VIP Tour

16

Bechtel Pueblo Team Project Manager Doug Omichinski (right) gives a tour of the PCAPP site on Nov. 3 to members of the Federal Emergency Management Agency, Colorado Division of Emergency Management, and the local emergency services bureau.

Page 17: PCAPP Monthly Status Briefing November 2011

OPSEC Completed 10 November 2011

Contact Information

17

Pueblo Chemical Stockpile Outreach Office

104 West B Street 719-546-0400

Tom Schultz

PCAPP Public Affairs Specialist

Bob Kennemer

Community Outreach Manager

Sandy Romero

Bechtel Communications Manager

U.S. Army Pueblo Chemical Depot

45825 Highway 96 East 719-549-4135

Chuck Sprague

Public Affairs Officer

Ken Roque Deputy Public Affairs Officer