PAYBAST CO. ( PJS )
PREQUALIFICATION DOCUMENT
MAY 2015
TABLE OF CONTENTS: PAGE
1 – GENERAL INFORMATION 1
2 – SERVICES AND FIELD OF ACTIVITIES 2
3 – ORGANIZATION CHART AND COMPANY STRUCTURE 3
3-1 – MEMBERS OF THE BOARD 3
3-2 – OTHER MANAGEMENT TEAM MEMBERS 3
3-3 – COMPANY KEY PERSONNEL 4
3-4 – ORGANIZATION CHART 5
3-5 – AWARDS 6
4 – EXPRIENCES : 8
4- 1 – MANAGERS EXPERINCES 9
4- 2 – COMPANYS REFRENCES 20
5 – QUALITY MANAGEMENT 22
6 – COPMANY RESOURCES : 24
6 – 1 – MANPOWER 25
6 – 2 – CONSTRUCTION EQUIPMENT AND MACHINERY 26
,
1-GENERAL INFORAMTION :
COMPANY NAME : PAYBAST
TYPE OF CPMPANY : PRIVATE JOINT STOCK
DATE OF ESTABLISHMENT : 1991
REGIS. CODE AND PLACE. : 87716 – TEHRAN - IRAN
PAID CAPITAL : 1/000/000/000 IRANIAN RIALS
COMPANY ADDRESS : NO 22, 4TH FLOOR,
MANSOOR ALLEY,
MOTAHHARI ST., VALI ASR
AVE., TEHRAN, IRAN
PHONE NO. : ( +98) 88726729 – 32
FAX NO. : ( +98) 88726728
E – MAIL ADDRES : [email protected]
WEB SITE : WWW.PAYBASTCO.COM
1
2- SERVICES AND FIELD OF ACTIVITIES :
SERVICES OFFERED BY PAYBAST :
●PROJECT EVALUATION.
●CONSTRUCTION DETAIL ENGINEERING
●PROCUREMENT SERVICES
●CONSTRUCTION AND PRECOMMISSIONING
●ASSISTANCE TO COMMISSIONING AND START - UP
FIELD OF ACTIVITES:
•OIL, GAS AND PETROCHEMICAL COMPLEXES
•PIPELINES, WATER AND SEWAGE TREATMENT PLANTS AND
NETWORKS
•STEEL AND CONCRETE INFRASTRUCTURES
•POWER PLANTS, FOOD INDUSTRIES AND INDUSTRIAL COMPLEXES
•RESIDENTIAL AND ADMIN. BUILDINGS.
2
3 – ORGANOZATOIN CHART AND COMPANY STRUCTURE:
PAYBAST HAS BEEN ESTABLISHED BY A GROUP OF MANAGERS,
HAVING VALUABLE EXPERINCES IN INDUSTRIAL PROJECTS.
THE AIM OF THE COMPANY IS TO BUILT UP DYNAMIC ORGANIZATION
AND UPDATE KNOWLEDGE FOR PROVIDING SERVICES WITH HIGH
QUALITY IN PROJECTS.
“SATISFACTION OF THE CLIENT IS THE MAIN AIM OF COPMANY “
MEMBERS OF THE BOARD, MANAGEMENT AND KEY PERSONAL OF THE
COMPANY ARE AS FOLLOWS :
3 – 1 - MEMBERS OF THE BOARD
M . SANADZADEH : CHAIRMAN
E . ROSHAEIAN : VICE CHAIRMAN
GH. KARIMI : MANAGING DIRECTOR
F . ZAHEDI : TECHNICAL & ENG . MANAGER
3 – 2 – OTHER MANGEMENT TEAM MEMBERS :
M . KASIRZADEH :PROCUREMENT MANAGER
3
Boa
rd O
f Dire
ctor
s
H.S
.E M
anag
erM
anag
ing
Dire
ctor
QA
/ Q
C M
anag
er
Pro
cure
men
t M
anag
erE
ngin
eerin
g M
anag
erP
roje
cts
Dire
ctor
Fin
anci
al A
nd
Adm
inis
trat
ion
Man
ager
Pro
ject
M
anag
ers
Adm
inis
trat
ion
War
ehou
seF
inan
cial
3-4
–C
om
pan
y O
rgan
izat
ion
Ch
art
5
3–5– AWARDS :
6
7/1
7/2
7/3
4 – EXPRIENCES :
4-1- MANAGERS EXPERIENCES
4-2- COMPANYS REFRENCES
8
,
,
4-1- MANAGER’S EXPERIENCES
9
PERIOD COMPANY
PAYBAST CO.
( SHARE HOLDER &MEMBER
OF THE BOARD )
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION SITE MANAGER
KOTAM GOSTAR CO.
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
39,000,000,000 RIALS.
KIMIA GHARB GOSTAR CO.
M.SANADZADEH, MECHANICAL ENGINEER ( B.S. FROM TEHRAN UNIVERSITY )
PROJECT
PROJECT
ERECTION OF EQUIPMENT & PIPING OF
C2 RECOVERY PLANT- PARS
PETROCHEMICAL COM. -ASSALUYEH
40,000,000,000 RIALS.
(SHARE HOLDER & MEMBER
OF THE BOARD )
4 - EXPERIENCES
4-1- MANAGERS EXPERINCES
POSITION
ERECTION OF MECHANICAL WORKS OF
GOLPAYEGAN PETROCHEMICAL
COMPANY (GBPC)
PROJECT
2005 - NOW
PROJECTS & POSITIONS
HEAD OF MECHANICAL DEPARTMENT
2002-2005
MECHANICAL , ELECTRICAL &
INSTRUMENT WORKS OF CITRIC ACID
FACTORY- KERMANSHAH
2002-2003
GBPC
SITE MANAGER
2004-2006
2003-2004
HAMPA(PPC)
10,000,000,000 RIALS
SITE MANAGER
,
10
PERIOD COMPANY
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
16,000,000,000 RIALS.
PIPING & INSULATION OF HYDROGEN
UNIT -BANDAR ABBAS REFINERY
NIRO- VA - TAVAN CO.
ERECTION OF MECHANICAL , ELECTRICAL
& INSTRUMENT WORKS OF MONTAZER
GHAEM COMBINED CYCLE POWER PLANT
PROJECT
KOTAM GOSTAR CO.
PROJECT MANAGER
2000-2002
SITE MANAGER
1998-2000
1996-1998
N.I.E.O.C
M.SANADZADEH, MECHANICAL ENGINEER ( B.S. FROM TEHRAN UNIVERSITY )
PROJECTS & POSITIONS
MAPNA CO.
22,000,000,000 RIALS
1998-2002
SITE MANAGER
1996-1998
MAPNA CO.
28,000,000,000 RIALS.
ERECTION OF MECHANICAL , ELECTRICAL
& INSTRUMENT WORKS OF SHAHID
RAJAEI COMBINED CYCLE POWER PLANT
11
PERIOD COMPANY
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
PROJECTS & POSITIONS
M.SANADZADEH, MECHANICAL ENGINEER ( B.S. FROM TEHRAN UNIVERSITY )
1994-1996 SAHAND AZAR .CO.
1990-1993
SITE MANAGER
1994-1996
WATER ORGANIZATION OF TEHRAN
3,000,000,000 RIALS.
SITE MANAGER
PROJECT1988-1990 IRAN NATIONAL STEEL GROUP
1990-1993 ATMOSPHERE CO.
1980-1988AHWAZ PLANING AND BUDGET
ORGANIZATION
EMERGENCY WATER PIPELINE OF
GHAZVIN
ERECTION OF MECHANICAL ,ELECTRICAL
& INSTRUMENT WORKS OF COOLING
SYSTEM OF SHAHID RAJAEI POWER
PLANT
MANAGER OF HYDRULIC & PENUMATIC
MAINTENANCE
PIPE MANUFACTURING FACTORY
TAVANIR CO.
35,000,000,000 RILAS.
8 YEARS
1988-1990
I.N.S.G
……………..
30,000,000,000 RIALS
LOCAL PROJECTS
MECHANIC ENGINEER
12
DATE COMPANY
PAYBAST CO.
SHARE Holder & MEMBER OF
THE BOARD
POSITION
PROJECT
KOTAM GOSTAR CO. DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
PROJECT
DURATION
CLIENT
AMOUNT
OF
CONTRACT
15,000,000,000 RIALS.
4 - EXPERIENCES
4-1- MANAGERS EXPERINCES
PROJECTS & POSITIONS
E.ROSHAEIAN, CIVIL ENGINEER ( B.S. FROM SHIRAZ UNIVERSITY)
HEAD OF CIVIL DEPARTMENT
94,000,000,000 RIALS
2003-2005
BASTAB BANA CO.1999-2002
IRAN KHODRO SAZEH
10,000,000,000 RIALS
CONSTRUCTION OF INDUSTRIAL
FOUNDATIONS OF IRAN KHODRO
COMPANY-TEHRAN
PROJECT MANAGER
2001-2002
2005 - NOW POSITION
2003-2005
KIMIA GHARB GOSTAR CO.
PROJECT MANAGER
MAROON PETROCHEMICAL COMPLEX
,(MPC) CONSTRUCTION OF CONTROL
ROOM , SUBSTATION & WAREHOUSE
CONSTRUCTION OF CIVIL WORKS OF
CITRIC ACID FACTORY- KERMANSHAH
2002-2003
MPC
SITE MANAGER
,
13
DATE COMPANY
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
40,000,000,000 RIALS.
CONSTRUCTION OF UTILITY BUILDINGS
OF BANDAR ABBAS REFINERY
TOTAL FINA ELF
1996-1999
10,000,000 USD
SIRRI A & E FIELD DEVELOPMENT
PROJECT
CONSTRUCTION MANAGER
TABRIZ PETROCHEMICAL CO.
25,000,000,000 RIALS.
MAHSHAHR ECONOMIC ZONE CO.
REINFORCING OF FOUNDATIONS OF
PETROL STATION AND ENTRANCE
SQUARE OF MAHSHAR SITE
SITE MANAGER
10,000,000,000 RIALS.
1999-2000
UNDER GROUND PIPING AND CIVIL
WORKS OF COOLING WATER , POWER
PLANT AND WASTE WATER PLANT
PROJECTS & POSITIONS
E.ROSHAEIAN, CIVIL ENGINEER ( B.S. FROM SHIRAZ UNIVERSITY)
1992-1993 SHANGARF CO.
PROJECT
1992-1993
N.I.E.O.C
SITE MANAGER
1993-1996
PROJECT
1999-2002
CONSTRUCTION MANAGER
1997-1999 JAHANPARS CO.
PROJECT
BASTAB BANA CO.
1993-1997 RADIRA CO.
PROJECT
14
DATE COMPANY
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT
OF
CONTRACT
PROJECT
1985-1988 JASK COMPANY
CONSTRUCTION OF CIVIL WORKS AND
FOUNDATION OF 133 MB OIL STORAGE
TANKS -ESFAHAN REFINERY PLANT
CONSTRUCTION OF MAIN ROAD
BETWEEN "CHENAR SHAHIJAN" AND
"DOGONBADAN"
N.I.O.C
1985-1986
200,000,000 RIALS
400,000,000 RIALS
SITE MANAGER
PROJECT
PROJECTS & POSITIONS
E.ROSHAEIAN, CIVIL ENGINEER ( B.S. FROM SHIRAZ UNIVERSITY)
1990-1993
1,000,000,000 RIALS.
ARAK REFINERY
SITE MANAGER
CONSTRUCTION OF RESIDENTIAL CAMP
FOR "BELELI"COMPANY IN ARAK
REFINERY
1986-1988
ROAD MINISTRY
1990-1992 BELELI.CO.
PROJECT
SITE MANAGER
15
DATE COMPANY
PAYBAST CO.
SHARE HOLDER &MEMBER
OFTHE BOARD
POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
POSITION
DURATION
CLIENT
KOTAM GOSTAR CO.
AMOUNT OF
CONTRACT
( SHARE HOLDER & MEMBER
OF THE BOARD )POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
1999-2001
FALEGH SANAT CO.
37,000,000,000 RIALS (6.2 M USD)
4 - EXPERIENCES
4-1- MANAGERS EXPERINCES
PROJECTS & POSITIONS
1997-2005
2005 - NOW
PROJECT
G.B.P.C
GH.KARIMI, CIVIL ENGINEER ( M.S. FROM TEHRAN UNIVERSITY )
CONSTRUCTION OF STEEL STRUCTURE,
MECHANICAL & ELECTRICAL WORKS OF
AMIR KABIR CANE SUGAR FACTORY -
AHWAZ / IRAN
CONSTRUCTION OF MECHANICAL,
ELECTRICAL & INSTRUMENTATION WORKS
OF ARDABIL AVIATION FUEL FACILITIES /
IRAN
CONSTRUCTION OF MECHANICAL,
ELECTRICAL & INSTRUMENTATION WORKS
OF "GHAED BASIR" PETROCHEMICAL
COMPLEX GOLPAYGAN / IRAN
PROJECT
PROJECT
CONSTRUCTION OF CIVIL WORKS OF
CITRIC ACID FACTORY- KERMANSHAH / IRAN
G.B.P.C
2003-2005
134,000,000,000 RIALS (19.1 M USD)
POSITION
PROJECT
KIMIA GHARB GOSTAR CO.
2002-2003
39,000,000,000 RIALS (5.6 M USD)
MANAGING DIRECTOR (Please refer to
www.paybastco.com)
PROJECT MANAGER
PROJECT MANAGER
PROJECT MANAGER
PROJECT MANAGER
2001-2003
8,500,000,000 RIALS (1.3 M USD)
,
16
DATE COMPANY
POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
POSITION
DURATION
CLIENT
AMOUNT OF
CONTRACT
37,000,000,000 RIALS (17.9 M USD)
SITE MANAGER
1991-1992
2,500,000,000 RIALS (2.5 M USD)
MANAGER OF SITE ENGINEERING
OFFICE
1987-1990
NATIONAL IRANIAN GAS CO.
NATIONAL IRANIAN GAS CO.
7,500,000,000 RIALS (9.4 M USD)
GH.KARIMI, CIVIL ENGINEER ( M.S. FROM TEHRAN UNIVERSITY )
OFFSHORE FACILITIES OF TAHERI PORT AND
CONDENSATE TANKS
CONSTRUCTION OF WATER TREATMENT
AND WATER RESERVOIRS OF JAM - TOHID
TOWN / IRAN
UNDER GROUND PIPING, CIVIL & MECHANICAL
WORKS OF COOLING WATER PLANT, POWER
PLANT, WASTE WATER PLANT, STEEL STORAGE
TANKS & AUXILIARY BUILDINGS
(ROOM/SUBSTATIONS/PUMP HOUSED) OF TABRIZ
PETROCHEMICAL CO-TABRIZ / IRAN
1986-1996
PROJECTS & POSITIONS
PROJECT
PROJECT
PROJECT
TABRIZ PETROCHEMICAL CO.
SITE MANAGER
RADIRA CO.
1993-1997
17
PERIOD COMPANY
POSITION
DURATION
CLIENT
POSITION
DURATION
POSITION
DURATION
CLIENT
POSITION
DURATION
CLIENT
4 - EXPERIENCES
4-1- MANAGERS EXPERINCES
1996-JUNE
2006
4-1- F.ZAHEDI,INDUSTRIAL ENGINEER ( B.S. FROM ELM-O-SANAT UNIVERSITY )
PROJECTS & POSITIONS
2006 -SUNE
NOW
PAYBAST CO. (SHARE HOLDER
& MEMBER OF THE BOARD)POSITION TECHNICAL & ENG. MANAGER
JAHANPARS ENG. & CONS. CO.
PROJECT DARQUAIN FIELD DEVELOPMENT PROJECT
HEAD OF PLANNING & TECHNICAL OFFICE FOR
SUPPORTING FOLLOWING PROJECTS: AMAK
PROJECT SIRRI A & E FIELD DEVELOPMENT
BORZOYEH PETROCHEMICAL COMPLEX
PROJECT GACHSARAN GAS INJECTION PROJECT
PROJECT
PLANNING & PROJECT CONTROL MANAGER
1992-1996OIL INDUSTRIES ENG. & CONS.
CO. (OIEC)
PROJECT BANDAR ABBAS REFINERY
N.I.O.C SOUTH FIELD
N.I.O.C
1992-1996
SITE MANAGER
2003-2006
ENI IRAN BV
1998-2000
SITE MANAGER
1996-1998
TECHNICAL OFFICE MANAGER
,
18
PERIOD COMPANY
POSITION
DURATION
CLIENT
POSITION
DURATION
POSITION
DURATION
1986-1989MINISTRY OF REUOLATIONARY
GAURDSPROJECT FABRICATION OF ONSHORE STRUCTURE
1989-1990
PROJECT ESFAHAN REFINERY LUB OIL COMPLEX
PLANNING MANAGER
MINISTRY OF ROAD LOCATION YASOUDJ CITY
1989-1990
1986-1989
4-1- F.ZAHEDI, INDUSTRIAL ENGINEER ( B.S. FROM ELM-O-SANAT UNIVERSITY )
PROJECTS & POSITIONS
PLANNING SUPERVISOR
PREVENTIVE MAINTENANCE PLANNING ENG.
1990-1992CHAGALESH / FOOSTER
WEELER JOINT VENTURE
N.I.O.C.
1990-1992
19
4-2- COMPANYS REFRENCES
20
,
PROJECT NAME : METHANO UNIT OF VENIRAN APADANA PETROCHEMICAL
CLIENT : VENIRAN APADANA PETROCHEMICAL
PROJECT DESCRIPTION : EXECUTION OF CONCRETE PIPE RACK OF
METHANO UNIT OF VANIRAN APADANA
PETROCHEMICAL
PROJECT DURATION : 12 MONTHS
START DATE : FEBRUARY 2015
MAJOR QUANTITIES OF THE WORK:
CONCRETE : 15,000 M3
FORMWORK : 40,000 M2
REBAR : 2,500 TON
21/1
21/2
PROJECT NAM : PHASE12, SOUTHPARS OFFICES AND OBSERVATION
GALLARY POWER & WATER SYSTEM
CLIENT : PETROPARS
PROJECT DESCRIPTION : MATERIAL PROCURMENT, CONSTRUCTION &
ERECTION OF POWER & WATER SYSTEM FOR
PROJECT OFFICES & OBSERVATION GALLARY
PROJECT DURATION : 5 MONTHS
START DATE : DECEMBER 2014
MAJOR QUANTITIES OF THE WORK:
CABLE PULLING : 13,300 M
ERECTION & COMMISSIONING & MODIFY
OF POWER DISTRIBUTION PANNEL : 10 SET
POLTETHILEN PIPING : 500 M
ERECTION & COMMISSIONING
OF TRANSFORMER : 1 SET
21/3
21/4
PROJECT NAME : SIRAF METHANOL UNIT
CLIENT : SIRAF ENERGY
PROJECT DESCRIPTION : CIVIL WORKS OF SIRAF METHANOL UNIT
PROJECT DURATION : 15 MONTHS
START DATE : OCTOBER 2013
(Due to client financial & Technical problems project has stopped)
MAJOR QUANTITIES OF THE WORK:
EXCAVATION : 45,000 M3
BACKFILL : 70,000 M3
CONCRETE : 30,000 M3
FORMWORK : 92,000 M2
REBAR : 2,400 TON
21/5
PROJECT NAME : EXPANSION AND UPGRADING SHAZAND
ARAK REFINERY
CLIENT : CONSORTIUM OF SAZEH , ODCC AND
SEI COMPANIES
PROJECT DESCRIPTION : EXECUTION OF REMAINING A/G PIPING
WORKS IN UNIT 45
PROJECT DURATION : 18 MONTHS
DATE OF PROVISIONAL
ACCEPTANCE : May 2013
MAJOR QUANTITIES OF THE WORK:
SUPPORT WEIGHT : 285 TON
PIPING : 55,000 IN-DIA
PAINTING : 24,500 M2
BUILDINGS & SITE : 1,950 M2
ELECTRICAL / INSTRUMENT CABLING : 39,000 M
INSTRUMENT DEVICE : 50 SET
21/6
21/7
4-2- COMPANYS REFRENCES
• PROJECT NAME : GAS TURBINE GENERATORUNIT 4&5 OF
IRAN LNG
• CLIENT : NEYR-PERSE COMPANY
• PROJECT DESCRIPTION : ERECTION AND PRE-COMMISSIONING
OF GAS TURBINE GENERATOR
UNIT 4 & 5 OF IRAN LNG.
• ROJECT DURATION : 8 MONTHS
• DATE OF PROVISIONAL
ACCEPTANCE : March 2011
• MAJOR QUANTITIES OF THE WORK:
• ALL RELATED WORKS OF GTG 160 MW : 2 SET
21/8
,
PROJECT NAME : phase 12- south Pars – Epc1 – Construction of NIB
CLIENT : NASR Consortium
PROJECT DESCRIPTION : Construction of industrial steel structure and
building consist of civil, electrical, mechanical work
for Main Workshop, Lorry & Car maintenance ,
Substation, Pipe rack, Concrete, Dyke, Sleepers,
Ditch, Culvert, …
PROJECT DURATION : 14 MONTH
DATE OF PROVISIONAL
ACCEPTANCE : March 2011
MAJOR QUANTITIES OF THE WORK:
BUILDING : 14,000 m2
CONCRETE : 14,000 m3
FORMWORK : 31,000 m2
REBAR : 1,200 ton
STEEL STRUCTURE ERECTION ; 1,400 ton
SAND BLAST & PAINTING : 25,000 m2
21/9
21/10
21/11
PROJECT NAME : Condensate Tanks EPC1 – phase 12
CLIENT : Consortium NASR
PROJECT DESCRIPTION : Mechanical Erection Sand blast painting &
Hydro test of 4 Tanks With 100,000 m3 Capacity,
One Tank with 23000 m3 Capacity & 5 utility tanks
PROJECT DURATION : 15 MONTH
PROGRESS : 98 %
MAJOR QUANTITIES OF THE WORK:
TANK ERECTION : 8,800 TON
SAND BLAST & PAINTING : 120,000 m2
21/12
21/13
21/14
PROJECT NAME : LIGHT NAPHTA HAYDROTREATING &
ISOMERIZATION PROJECT (joint with Radira)
CLIENT : CHAGALESH CONSULTING ENGINEERS
PROJECT DESCRIPTION : CIVIL, MECHANICAL, ELECTRICAL &
INSTRUMENT WORKS OF LNHAIP
PROJECT DURATION : 22+18 MONTH
DATE OF PROVISIONAL
ACCEPTANCE : March 2011
MAJOR QUANTITIES OF THE WORK:
CONCRETE : 22,000 m3
FORMWORK : 40,000 m2
REBAR : 2,500 ton
C.S. PIPING : 197,000 in-dia
EQUIPMENT ERECTION : 5,400 ton
STEEL STRUCTURE ERECTION : 1,100 ton
ELECTRICAL / INSTRUMENT CABLING :459 km
INSTRUMENT DEVICE : 2,900 set
SAND BLAST & PAINTING : 31,000 m2
PIPING INSULATION : 30,000 ml
21/15
21/16
21/17
21/18
21/19
PROJECT NAME : Foundation of Ethylene tank ILAM Petrochemical –
Olephine No.13 (joint with Radira)
CLIENT : STEEM Co.
PROJECT DESCRIPTION : Construction of Dobell wall Foundation
PROJECT DURATION : 6 MONTH
PROGRESS : Temporary handover
DATE OF COMPLETION : 2008
MAJOR QUANTITIES OF THE WORK:
CONCRETE : 1,700 m3
FORMWORK : 530 m2
REBAR : 230 ton
21/20
21/21
PROJECT NAME : phase12. south Pars – EPC1 - PPl Camp
(joint with Radira)
CLIENT : NASR Consortium
PROJECT DESCRIPTION : Construction of PetroPars Engineering Camp
Consist of ( Bedrooms Camp, Restaurant, Clinic, Mosque, Shop, … )
PROJECT DURATION : 8 MONTH
PROGRESS : Permanent handover
MAJOR QUANTITIES OF THE WORK:
CONCRETE : 5,000 m3
FORMWORK : 9,000 m2
REBAR : 400 ton
STEEL STRUCTURE ERECTION : 280 ton
21/22
21/23
PROJECT NAME : BANDAR ABBAS GAS CONDENSATE
REFINARY – RENOVATION OF PIONEER
CAMP / BOSTANOO CAMP
CLIENT : PERSIAN GULF STAR OIL COMPANY
(PGSOC – GGIL )
PROJECT DESCRIPTION : REFURBISHMENT OF 25000 SM OF BUILDINGS
PROJECT DURATION : 12 MONTHS
DATE OF COMPLETION : 2008, JUNE
MAJOR QUANTITIES OF THE WORK:
SITE WORKS : 10,000 M2
PLASTER WORKS : 60,000 M2
HVAC : 700 SET
CERAMIC TILE : 20,000 M2
WATER PROOFING WORKS : 10,000 M2
PAINTING : 100,000 M2
21/24
PROJECT NAME : SEGREGATE , PROCESS AND STORAGE
OF LPG IN LAVAN ISLAND (joint with Radira)
CLIENT : CHAGALESH CONSULTING ENGINEERS
PROJECT DESCRIPTION : EXECUTING OF MECHANICAL ,ELECTRICAL
& INSTRUMENT WORKS.
PROJECT DURATION :18 MONTHS
MAJOR QUANTITIES OF THE WORK:
C.S PIPING : 25,000 IN.DIA
EQUIPMENT ERECTION : 250 TON
ST. STRACTURAL ERECTION : 120 TON
ELECTRICAL INSTRUMENT CABLING : 65 KM
INSTRUMENT CALIBRATION & ERECTION : 215 SET
SAND BLAST & PAINTING : 7,000 M2
PIPING INSULATION : 7,500 M2
EQUIPMENT INSULATION : 300 M2
21/25
21/26
PROJECT NAME : SEGREGATE , PROCESS AND STORAGE OF
LPG IN LAVAN ISLAND ( joint with Radira )
CLIENT : CHAGALESH CONSULTING ENGINEERS
PROJECT DESCRIPTION : EXECUTING OF EQUIPMENT FOUNDATION ,
CONTROL ROOM,SUBSTATION & SITE CIVIL
WORKS.
PROJECT DURATION : 12 MONTHS
MAJOR QUANTITIES OF THE WORK:
EARTHWORKS : 7,500 M3
CONCRETE : 1,800 M3
FORMWORKS : 2,500 M2
REBAR WORKS : 350 TONS
BUILDING : 250 M2
21/27
PROJECT NAME : KERMANSHAH CITRIC ACID PLANT
CLIENT : KIMIA GHARB GOSTAR COMPANY
PROJECT DESCRIPTION : MECHANICAL, ELECTRICAL AND
INSTRUMENTATION WORKS OF
KERMANSHAH CITRIC ACID PLANT
PROJECT DURATION : 14 MONTHS
DATE OF COMPLETION : 2006
MAJOR QUANTITIES OF THE WORK:
C.S. PIPING : 15,000 INCH- DIA
S.S. PIPING : 50,000 INCH- DIA
EQUIPMENT ERECTION : 700 TONS
CABLING : 35 KM
ELEC./INSTR. EQUIPMENT : 1100 SET
SAND BLASTING / PAINTING :10,000 m2
INSULLATION :7,500 m2
21/28
21/29
21/30
• PROJECT NAME : KERMANSHAH CITRIC ACID PLANT
• CLIENT : KIMIA GHARB GOSTAR COMPNY
• PROJECT DESCRIPTION : CONSTRUCTION OF KERMANSHAH
CITRIC ACID INDUSTRIAL WASTE
WATER TREATMENT PLANT AND ADMIN.
BUILDING
• PROJECT DURATION : 12 MONTHS
• DATE OF COMPLETION : 2006
• MAJOR QUANTITIES OF THE WORK:
• EARTHWORKS : 15,000 M3
• FORMWORKS : 4,000 M2
• REBAR WORKS : 350 TONS
• CONCRETE : 4,000 M3
21/31
PROJECT NAME : TABRIZ PETROCHEMICAL PLANT
CLIENT : TABRIZ PETROCHEMICAL COMPLEX
PROJECT DESCRIPTION : ERECTION OF STORAGE TANKS
OF T.P.C
PROJECT DURATION : 12 MONTHS
DATE OF COMPLETION : 1997
MAJOR QUANTITIES OF THE WORK:
TANK ERRECTION : 1,200 TON
C.S. PIPING : 24, 200 INCH- DIA
CABLING : 10 KM
SAND BLASTING / PAINTING :36,000 m2
HOT INSULLATION :16,000 m2
21/32
21/33
5- QUALITY MANAGEMENT
22
5 – QUALITY MANAGEMENT:
THE AIM OF COPMANY IS PROVIDING SERVICES ACCORDING TO
THE CONTRACT, WITH CONSIDERATION OF UPDATED LOCAL AS
WELL AS INTERNATIONAL CODES AND STANDARDS IN PROJECTS.
PAYBAST ENDEVOURS TO ACHIEVE FOLOWING GOALS WITH
APPLAYING QUALITY MANAGEMENT SYSTEMS:
• SAFE PERFORMANCE OF THE WORK.
• SATISFACTION OF THE CLIENTS
• IMPROVEMENT OF WORKMANSHIP QUALITY
• DOCUMENTATION OF EXECUTED WORKS
• INCREASING THE EFFICIENCY
“PAYBAST IS TRYING TO ADAPT ITS QUALITY MANEGMENT
SYSTEM ON THE BASIS OF THE QUALITY MANAGEMENT OF ISO”
23
6 – COMPANY RESOURCES
6-1- MANPOWER
6-2- CONSTRUCTION EQUIPMENT AND MACHINERY
24
6-1- MANPOWER
25
ITEM. DESCRIPTION NO.
1 MANAGEMENT , TECHNICIAN & CELERC 9
2 FORM WORKER 40
3 REBAR WORKER 30
4 MASON 10
5 CONCRETE WORKER 20
6 STEEL WORKER 15
7 ERECTOR 8
8 EQUIPMENT ERECTOR 10
9 MILWRAIGHT 4
10 FITTER 20
11 WELDER 30
12 SCAFFOLDER 20
e - PIPING WORKS :
d - MECHANICAL WORKS :
6 - 1 - MAN POWER
a - HOM OFFICE
b - CIVIL & BUILDING WORKS :
c - STEEL STRUCTURE WORKS :
ITEM. DESCRIPTION NO.
13 ELECTRICIAN 20
14 INSTRUMENT TECHNICIAN 15
15 SAND BLASTER 10
16 PAINTER 4
17 INSULATER 20
285
6 - 1 - MAN POWER
f - ELECTRICAL & INSTRUMENTATION WORKS :
g - PAINTING , SAND BLAST & INSULATION WORKS :
TOTAL
6-2- CONSTRUCTION EQUIPMENT AND MACHINERY
26
NO. DESCRIPTION UNIT CAPACITY MODEL QTY1 Rough Terrain Crane No. 45 ton KATO 1
2 Rough Terrain Crane No. 25 ton KATO 3
3 Truck Crane No. 10 ton M.S.A 1
4 Truck Crane No. 3 ton KHAVAR 2
5 Fork Lift No. 10 ton Clark 1
6 Louder No. 625 HEPCO 1
7 Dump Truck No. 16 ton DANG FONG 1
8 Truck Mixer No. 8 - 9 m3 BENZ-MACK 2
9 Truck Mixer No. 7 m3 HOWO - DANG FONG 2
10 Tractor With Trailer No. TABRIZ CO. 3
11 Batching Plant No. 35 m3 in hour BEHNAM SAANAT 1
12 Mobile Concrete Pump No. 36 meter h POITZ MASTER 1
13 Cement Silo No. 80 ton JAHAN SAMT 4
14 Air Compressor No. 250 CFM TABRIZ CO. 2
15 Air Compressor No. 800 CMF Ingersoll-Rand 1
16 Compactor No. 3 ton HEPKO DOBELL 2
17 Diesel generator No. 250 KVA VOLVO 8
18 Diesel generator No. 160 KVA VOLVO 9
19 Diesel generator No. 60 KVA PERKINZ 9
20Welding Machine (
Rectifier )No. 500/600 Amp.
KARA/KHAZAR TRANSFO
110
21Plasma Cutting
MachineNo. 2
22Auto-Welding Machine for
bottom plate of Tank No. GAM ELECTRIK 3
23Auto-Welding Machine for
Tank horizontal shell No. LINKOLN 2
24 Sand blast Equipment No. 3
25 Airless No. 2
26Pipe Bender up to 2
InchNo. 2
27 Threading Machine No. 2
6-2 - CONSTRUCTION EQUIPMENT AND MACHINERY
NO. DESCRIPTION UNIT CAPACITY MODEL QTY6-2 - CONSTRUCTION EQUIPMENT AND MACHINERY
28 4" Filling Pump No. 1
29 2" Submerge Pump No. 4
30 Test Pump No. 50 - 200 bar 6
31 Bar Cutting Maching No. FARS GALEB 1
32 Bar Cutting Maching No. FARS GALEB 2
33 Betonier No. PARS ARIAN 2
34 Vibrator No. 8
35 Container No. 20/40 foot 6
36 Protocabin No. 20/40 foot 14
37 Steel form work ton 300
38 Scaffolding Material ton 200
39Total Station ( survey
instrument )No. 3
40Nivoo. ( survey
instrument )No. 6
41 Grinding Machine No. 45
42 Magnetic Drill No. 4
43 Shop Drill No. 2
44 Oxygen Cylinder No. 60
45 Argon Cylinder No. 50
46 Pickup No. 5
47 Car No. 6