paul croke - transport nsw - northwest metro – implementation and delivery of australia’s...
TRANSCRIPT
Australian Tunnelling ConferenceSydney Metro Northwest
Tunnels and Stations Civils Contract Director - Paul Croke
13 October 2015
Project Overview
Sydney Metro
66km, two stages
30 metro railway stations
Two optional stations
Sydney Metro
Open first half of 2019
8 new stations; 5 upgraded
4,000 car spaces
Stage 1 – 36km
• Tunnelling & Stations Civils (TSC)
• Surface Viaducts and Civils (SVC)
• Operations Trains and Systems (OTS)
Geology
Bella Vista 2013
Bella Vista 2015
Norwest 2013
Norwest 2015
Showground 2013
Showground 2015
Castle Hill 2013
Castle Hill 2015
Cherrybrook 2013
Cherrybrook 2015
Segment precast facility at Bella Vista
Acoustic shed; 24 hour operation
Segment production commenced June 2014
Segment manufacture
Batch plant managed by Holcim
Storage yards including gantry cranes
Gas steam curing chamber
Two carousels and central batch plant
Segments per ring - 6
Segment length 1.7 m
Weight per segment ~ 3.7 Tonne
Weight per ring~ 22 Tonne
Total segments ~ 99,000
Total rings ~ 16,500
Segment carriers and Menriders
Tunnelling (TSC)
91,000 of the 100,000 concrete segments
have been produced
Station boxes
Cherrybrook
Castle Hill
Showground
Norwest
Bella Vista
Castle Hill Station Box
NFM (designed in France, assembled in China)
Double gripper shield
TBM weight: 980 tonnes
Cutting diameter ~ 7.0m
First Launch 8th September 2014
TBM twin running tunnels
Approximate 15km each
TBM1 breakthrough into Showground Station, May 2015
23km of the 30km of tunnels excavated
Cross passage excavation ramps
Cross passage excavation
54 standard cross passages
Invert preparation
Cross passage opening
Completed cross passage
Cheltenham Services Facility shaft
Cheltenham Breakthrough
Mined tunnels - 3% of tunnelling
Permanent formwork- Periform system
TBM traverse
Epping Service Facility shaft
• Two running tunnels 298m and 334m
• One cross passage 55m long
• Breakthrough into ECRL Stub tunnels
(live rail environment)
• Two running tunnels 298m and 334m
• One cross passage 55m long
• Breakthrough into ECRL Stub tunnels
(live rail environment)
Epping mined tunnels lining form
Two running tunnels 298m and 334m
Lining form
One cross passage 55m long
Environmental Management
• 1.5 million tonnes of crushed rock removed
• Transported for reuse in various residential/commercial
developments
• Design Rating score of 83 awarded by Infrastructure
Sustainability Council of Australia
• Reused 29 beams from Sydney Monorail for temporary bridge
Safety & Workforce Development
• (TAFE certified) 5 day Tunnel Induction = 423
• One Day Tunnel Induction = 993
• Tunnel PPE/RPE Personal Fitting Inductions
• Tunnel Clean Shaven Policy for total workforce
• Behavioural safety “see the difference” programme
• TJHD live streaming TV into man riders and sites
Stakeholder and community engagement Stakeholder engagement through a variety of touchpoints using a number of
communications channels, both by the contractor and TfNSW:
– Door knocking residents along alignment (Contractor)
– Quarterly newsletters, regular updates and subscriptions to email updates
(weekly and monthly) (Contractor)
– Community and business forums (Contractor)
– Community Information Centre – permanent and pop up – and 1800
Community phone line (TfNSW)
– Community presentations – schools and community groups (TfNSW and
Contractor)
– Ongoing stakeholder engagement (TfNSW)
– Mobile booths at community events in the area (TfNSW)
– Social Media - Website and Facebook
Stakeholder and community engagement
Epping Breakthrough
Surface Viaducts & Civils (SVC)
4km skytrain between Bella Vista and Rouse
Hill
Landmark cable-stayed bridge
121 piers required for construction
1,200 concrete segments required to form
skytrain deck
State-of-the-art launch gantries from Dubai
Gantries to lift segments into place - enabling main
arterial roads to remain open during construction
Operations, Trains and Systems - OTS
$3.7 Billion Public Private Partnership – largest ever in NSW
Delivers Australia’s first ever fully automated metro network
First stage in the construction – earthworks at Cudgegong Road
Concept image of the rail services facility at Cudgegong Road
What’s next?
59
Expected to open 2024
5 new stations; plus 3 optional
Bankstown Line conversion
Stage 2 – 30km
Sydney Metro City & Southwest
Community consultation started
Start major construction 2017
Geotech drilling complete
Sydney Metro City & Southwest
Key milestones
No Description Planned Date
2015
01 Early Works (Site Survey and Investigation) - Commence Q1-2015
02 Community Consultation - Commence Q2-2015
03 Exhibition Northern Corridor Works EIS - Commence Q3-2015
04 Exhibition Sydney Harbour Crossing EIS - Commence Q4-2015
2016
05 Final Business Case to Government Q1-2016
06 Exhibition Western Extension REF - Commence Q2-2016
07 Expression of Interests (EOI) Release - TSC Q2-2016
08 Enabling Works (Major Demo on Site) - Commence Q4-2016
2017
09 Contract Award - TSC Q2-2017
2018
10 TBM Excavation - Commence Q4-2018
2024
11 Operations Commence Q4-2024