Passaic River Basin General Reevaluation David Rosenblatt NJDEP, Administrator, Office of E i i dC t ti Engineering and Construction Eugene Brickman, P.G. USACE Deputy Chief of Planning USACE, Deputy Chief of Planning Anthony Ciorra, P.E. USACE Chief Civil Works Branch USACE, Chief, Civil Works Branch Alicia Gould USACE, Project Manager 13 September 2012 Wayne, NJ US Army Corps of Engineers BUILDING STRONG ®

Upload: others

Post on 25-Sep-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin General Reevaluation

David RosenblattNJDEP, Administrator, Office of E i i d C t tiEngineering and Construction

Eugene Brickman, P.G.USACE Deputy Chief of PlanningUSACE, Deputy Chief of Planning

Anthony Ciorra, P.E.USACE Chief Civil Works BranchUSACE, Chief, Civil Works Branch

Alicia GouldUSACE, Project Manager, j g

13 September 2012Wayne, NJ

US Army Corps of EngineersBUILDING STRONG®

Page 2: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin Facts• 983 square mile basin

• ~2.5 million people (2000 census)

• 50 000 people are in floodplain• ~50,000 people are in floodplain

• 20,000 homes, businesses, & public buildings in over 100 municipalities

• Main Stem & major tributaries 100 year floodplain covers 40,000 acres (~60 mi2) of which half is fully developed

• One of the most densely developed floodplains on the eastern seaboard

• Extensive environmental degradation to river system coupled with significant repetitive flooding

• Nine Congressional Districts in basin

BUILDING STRONG®

Districts in basin

2

Page 3: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin - Flooding History

20101903

Floyd - 1999

$351M

19841968 1984

$878M

BUILDING STRONG®3

Page 4: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin - Flooding History

2010

Floyd - 1999

$261M in damagesApril 2007

$780M

March 2011

$700M

Irene 2011March 2010

$772M$1B

BUILDING STRONG®4

Page 5: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin Flood FactsPassaic River Basin Flood Facts

•15 Federal disaster declarations since 1968•6 of those since 20056 of those since 2005

•Since 1900 - 26 lives lost & over $6 billion in losses

•Since 1990 – over $3.5 billion in losses

BUILDING STRONG®5

Page 6: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin – Previous Studies1900 1940 8 State Studies• 1900 - 1940 ------- 8 State Studies

• 1936 - 1973 ------- 5 Federal Reports

• 1976 ---------------- New Basin Study Authorizedy150 alternatives studied including buy-outs, flood plain regulations, channels, levees, floodwalls, reservoirs, tunnels, and multiple combinationsConsider environmental impacts (NEPA) and Public Acceptance

•1987 Feasibility General Design Memorandum (GDM) and 1989 Chief’s Report

•1989 Beatties Dam Reconnaissance Report – No Federal Interest

•WRDA 1990 Project Authorization

•September 1995 – Passaic River draft GDM (authorized project)

•September 1995 – Passaic River Buyout Study Report BCR of 0.1 (100 year)September 1995 Passaic River Buyout Study Report BCR of 0.1 (100 year)

•October 1995 – Passaic River Floodway Buyout Study Report BCR of 0.2

•WRDA 2000, Section 327(i) Restriction on use of funds

BUILDING STRONG®

•February 2011 – Governor’s Flood Advisory Commission Report

6

Page 7: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

PERMANENT EVACUATION

1

2Permanent

3 PLAN 12Permanent

PLAN 5

BASIN – WIDE PLANS (BASED ON BUILDING BLOCKS)COMBINATION

MEASURE BUILDING BLOCKS

FLOODPROOF / RAISE

DAM AND BRIDGE

MODIFICATION

4

Evacuation, Floodproof /

Raise(Plans 1 & 2)

Permanent Evacuation, Levee /

Floodwall(Plans 1 & 11)

Evacuation , Floodproof / Raise,

Dam & Bridge Modification(Plan 3 & 4)

7 PLAN 8 Pl 15PLAN 10PLAN 9 PLAN 16

NG

BLO

CK

S

CHANNEL MODIFICATION

6

LEVEE /

11

Channel, Dam & Bridge

Modification(Plans 6 & 4)

7

Channel Modification, Permanent Evacuation

(Plans 7 & 1)

PLAN 8

Levee /

13

Channel Modification, Levee / Floodwall

(Plans 7 & 13)

Plan 15

Channel Modification, Floodproof / Raise

(Plan 7 & 3)

PLAN 10

Channel Modification, Floodproof / Raise

(Plans 7 & 2)

PLAN 9

Permanent Evacuation, PLAN 14

Channel Modification, Nonstructural, Levee /

Floodwall(Plans 7 & 14 , 3 & 15)

PLAN 16

ASU

RE

BU

ILD

IN LEVEE / FLOODWALL

EXISTING RESERVOIRS

17

18

Levee / Floodwall,

Dam & Bridge Modification

(Plans 11 & 4)

Levee / Floodwall, Dam & Br. Mod, Flood / Raise(Plans 1 & 13 , 3 & 13)

PLAN 24PLAN 19

SIN

GLE

MEA

NEW RESERVOIRS

18

PRESERVE NATURAL STORAGE

20

Existing & New Reservoirs, Tunnels

(Plans 19 & 23)

Existing & New Reservoirs

(Plans 17 & 18)

Pres Nat, Storage in Combination with other

Nonstructural and St t l MAREAS

AQUIFER RECHARGE

21

23

Aquifer Recharge, New & Existing Reservoirs,

Tunnels(Plans 22 & 25)

PLAN 26

Aquifer Recharge, Tunnels(Plans 21 & 23)

PLAN 25

Aquifer Recharge, New & Existing Reservoirs

(Plans 21 & 19)

PLAN 22

Structural Measures

** CHANNEL MODIFICATION

AND/OR LEVEES AND FLOODWALLS

BUILDING STRONG®TIDAL BARRIER

25

TUNNELS **Tunnels,

Floodproof / Raise,

Permanent Evacuation

(Plans 23 & 3)

PLAN 28

Tunnels, Channel

Modification(Plans 23 & 7)

PLAN 29

Tunnels, Levee / Floodwall

(Plans 23 & 13)

PLAN 30

Tunnels, Levee / Floodwall,

Nonstructural(Plans 23 & 14)

PLAN 33

Tunnels, Channel

Modification, Nonstructural

(Plans 23 & 10)

PLAN 32

Tunnels, Levee / Floodwall,

Channel Mod, Nonstructural

(Plans 23 & 16)

PLAN 34

Tunnels, Levee / Floodwall,

Channel Modification

(Plans 23 & 15)

PLAN 31FLOODWALLS REQUIRED IN PORTIONS OF

CENTRAL BASIN FOR MOST TUNNEL

BUILDING BLOCKS TO FUNCTION

Page 8: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin – Plans ComparedPlan Cost (Millions) StructuresPlan Cost (Millions) Structures

Protected/Acquired

100 Year Floodplain Buyout $7,350 ~13,300

50 Year Floodplain Buyout $5,880 ~11,100

25 Year Floodplain Buyout $4,704 ~9,500

10 Year Floodplain Buyout $3,381 ~7,400

Fl d B $294 800Floodway Buyout $294 ~800

100 Year Authorized Tunnel Diversion Plan $2,793 over 14,000

Levees, Floodwalls, Nonstructural Measures, some Bridge and Dam Modifications (14A)

$840 10 to 100 year level of protection

Levees, Floodwalls, Nonstructural Measures and $961 10 to 100 year

BUILDING STRONG®

Channel Modification, some Bridge and Dam Modifications (16A)

$96 0 to 00 yealevel of protection

October 2011 Price Levels

Page 9: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin N t StNext Steps

• Continue to Support New Jersey as they implement the recommendations made by the Governor’s Flood Advisory Commission (Jan 2011)

• Execute Feasibility Cost Sharing Agreement with NJDEP for a reevaluation for the Passaic River Basin (13 June 2012)2012)

• Conceptual Phase Draft Report (Jun/Jul 2013)

• Public Outreach (Jul – Oct 2013)

BUILDING STRONG®9

Page 10: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River General ReevaluationC t l Ph 6 Alt tiConceptual Phase – 6 Alternatives

• Comprehensive system of levees, floodwalls, p y , ,nonstructural measures, some bridge and dam modifications (alternative 14A from 1987) C h i t f l fl d ll• Comprehensive system of levees, floodwalls, nonstructural measures, channel modification, some bridge and dam modifications (alternative 16A from 1987)

• 1990 authorized plan (dual inlet tunnel, alternative 30E) • Improvements to Beatties Dam and Two Bridges• Nonstructural – 10 year• No Action

BUILDING STRONG®10

Page 11: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Plan 14A – Levee/Floodwall, Nonstructural, some Dam and Bridge Modification

BUILDING STRONG®

Current as of May 2010\

Page 12: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Plan 14A – Levee/Floodwall, Nonstructural, D d B id M difi tisome Dam and Bridge Modification

• Nonstructural measures (flood proofing, raising, buyout) for 6,000 structures

• No channel improvements• No channel improvements• 24 miles of levees

• Heights ranging from 3’ to 17’g g g

• 17 miles of flood walls• Heights ranging from 5’ to 22’

46 t ti• 46 pump stations

BUILDING STRONG®

Page 13: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Plan 16A – Levee/Floodwall, Nonstructural, Channel Modification,some Dam and Bridge Modification

BUILDING STRONG®

Current as of May 2010

Page 14: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Plan 16A – Levee/Floodwall, Nonstructural, Channel Modification,C a e od cat o ,

some Dam and Bridge Modification

N t t l (fl d fi i i b t)• Nonstructural measures (flood proofing, raising, buyout) for 6,000 structures

• 16 5 miles of channel improvements16.5 miles of channel improvements• 20 miles of levees

• Heights ranging from 4’ to 17’

• 9 miles of flood walls• Heights ranging from 7’ to 14’

• 22 pump stations• 22 pump stations

BUILDING STRONG®

Page 15: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin WRDA 1990 Authorized Plan (30E)as designed in September 1995g p

BUILDING STRONG®

Page 16: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River Basin WRDA 1990 Authorized Plan (30E)990 ut o ed a (30 )

as designed in September 1995

• 20 mile, 42 ft. dia. main diversion tunnel• 1.2 mile, 23 ft. dia. spur tunnel• 7 miles of channel improvements• 7 miles of levees

13 il f fl d ll• 13 miles of flood walls• 15 pump stations

BUILDING STRONG®

Page 17: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Modification of Beatties Dam d T B idand Two Bridges

• The following will be considered:

R i ti ll f B tti D• Removing a portion or all of Beatties Dam• Placing gates on Beatties Dam• A weir or structure near the confluence of the• A weir or structure near the confluence of the

Pompton and Passaic Rivers to regulate the flow• Channel modification

BUILDING STRONG®

Page 18: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River General ReevaluationConceptual Phase

• NJDEP will have the opportunity to determine alternative(s) on which to proceed on the basis of conceptual costs and economics, environmental requirements and public inputrequirements and public input

• Public Outreach with NJDEP:• Two Public Study Kick off Meetings:• Two Public Study Kick-off Meetings:

• July 11, 2012• September 13, 2012

• Ten Public Outreach Meetings (Jul-Oct 2013)• Ten Public Outreach Meetings (Jul Oct 2013)• Plan Sheets and Posters geared towards different areas of the

BasinVisual Renderings

BUILDING STRONG®

• Visual Renderings

18

Page 19: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

1987 Alternatives

BUILDING STRONG®19

Page 20: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River General ReevaluationConceptual Phase Major TasksConceptual Phase Major Tasks

• Update floodplain based on 1990s UNET model and current FEMA HEC-RAS models

• Model each alternative for reduction in water surface levels (level of protection may have changed)

• Comparative cost estimatesp• Economic screening of alternatives

• Damages prevented (benefits) vs project cost• Identify threatened or endangered species known historic• Identify threatened or endangered species, known historic

resources and potential wetland and riverine habitats. • Review existing literature

C di t ith NJDEP USFWS th NGO t• Coordinate with NJDEP, USFWS, other NGOs, etc• Architectural renderings, photographs and cross-section

posters of typical project features

BUILDING STRONG®

• Public Outreach

20

Page 21: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Passaic River General ReevaluationConceptual Phase Recent TasksConceptual Phase Recent Tasks

• 11 July 2012 Public Information Session• Passaic River Website

• Technical Tasks:Technical Tasks:• Hydrology:• Received FEMA HMS models from NJDEP• Rainfall data was collected from IreneRainfall data was collected from Irene• Developing calibrated runs for Irene• Coordination with the NJ Silver Jackets Team

• Hydraulics:y• 1990s UNET model converted to HEC-RAS• Received FEMA HEC-RAS models for the Central/Lower Basin,

Pompton and Ramapo Rivers

BUILDING STRONG®21

Page 22: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

• Passaic River Resources• www.nj.gov/dep/passaicriver• http://bit.ly/passaicstudyp y p y

• Information about the poster boardsp

• Introduction of the Team Members

• Comment period

BUILDING STRONG®22

Page 23: Passaic River Basin General Reevaluation€¦ · Passaic River Basin - Flooding History 2010 1903 Floyd - 1999 $351M 1968 1984 $878M 3 BUILDING STRONG

Dave Rosenblatt, NJDEP, Administrator, Office of Engineering and ConstructionJohn Moyle, P.E., NJDEP, Manager, Bureau of Dam Safety and Flood ControlEugene Brickman, P.G., USACE, Deputy Chief, PlanningAnthony Ciorra P E USACE Chief Civil Works BranchAnthony Ciorra, P.E., USACE, Chief Civil Works BranchAlicia Gould, USACE, Project ManagerThomas Hodson, USACE, Chief, Plan FormulationJ Sh USACE Pl Ci il E iJason Shea, USACE, Planner, Civil EngineerKaren Ashton, P.E., USACE, Planner, Civil EngineerFrank Santangelo, P.E., USACE, Chief, Hydraulics and HydrologyRaymond Schembri, P.E., USACE, Hydraulic EngineerNancy Brighton, USACE, Chief, Watershed Section Matthew Voisine USACE BiologistMatthew Voisine, USACE, BiologistKenneth Wells, USACE, Chief, Public AffairsChristopher Gardner, USACE, Public Affairs

BUILDING STRONG®23