paper title - crc press and hudso… · web viewword file of the chapter 8 protocol sheets in...
TRANSCRIPT
![Page 1: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/1.jpg)
Word file of the Chapter 8 Protocol Sheets in“Rock Engineering Design” by Feng and Hudson
The Protocol Sheets have been provided in this Word file to allow users to be able
to complete the Sheets directly. The Sheets and an illustrative completed example
are explained in Chapters 8 & 9 of the book.
8 PROTOCOL SHEETS
The purpose of this Chapter is to explain and present the Protocol Sheets to be used for
recording the information relevant to the complete process of modelling and design and hence
support the technical auditing for a rock engineering project, the word ‘Protocol’ being used
here to indicate a pre-defined written procedural method. The Protocol Sheets follow the
philosophy outlined in the first five chapters of the book. Seven such sets of Protocol Sheets are
suitable to provide the necessary information recording the data and decisions leading to the
rock engineering design, including the during- and post-construction feedback for back analysis.
These seven sets of Protocol Sheets cover the following subjects.
- Objectives and overall approach to the project
- Geological setting and site investigation
- Modelling
- Design
- Technical auditing
- Feedback and back analysis
- Summary and conclusions
Currently, there is no international procedure for checking whether rock engineering
modelling and design are adequate for the purpose. In other areas of engineering constructions,
e.g., the manufacture of aeroplanes, there can be highly detailed checks on all aspects of the
construction process. It is not the intention here to reproduce such detailed quality assurance
1
![Page 2: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/2.jpg)
procedures but to provide an overview auditing method to ensure that the modelling and design
operations are suitable for the purpose. The term ‘technical auditing’ means the examination of
the technical content of a rock mechanics model or rock engineering design to establish if it is
adequate for the purpose—given the difficulties with some of the rock mechanics factors and
the idiosyncrasies of the different engineering projects. Key overview technical auditing
questions are:
- What is the work/project objective?
- Have the relevant variables and mechanisms been identified?
- Is the model/code adequate?
- Are the data adequate?
- Has the model been implemented properly?
- What are the prediction/back analysis protocols?
The technical auditing procedure ensures transparency of the methods used, traceability of
analysis methods and associated decisions, and confirms that investigation of the key factors has
been implemented. In particular, hazard scenarios can be investigated. Note that technical
auditing can be used concurrently with the work or subsequently when the work is completed.
Naturally, it is preferable if the Protocol Sheets are completed and the technical auditing applied
on a continuous basis during the operation of the modelling and design work. In rock mechanics
and rock engineering, there are still many unresolved issues, such as the most appropriate failure
criterion, the best way to characterise fractures, etc., so the technical auditing is conducted
within the current scientific framework with a consensus approach being the best way to deal
with such unresolved issues.
The sets of Protocol Sheets 1–5 can be used before construction. The set, Protocol Sheet 6, is
used as the construction starts with feedback information being received and back analysis
being possible. Finally, the result of completing and auditing the work as described in the
Protocol Sheets is summarised in Protocol Sheet 7.
2
![Page 3: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/3.jpg)
8.1 PROTOCOL SHEET 1: Objective and Overall Approach to the Project
It is necessary at the outset to establish the objective and overall approach to the project. This is
because there can be quite different philosophies and requirements for the different types of
project. For example, in civil engineering projects there is a requirement to avoid significant
rock failure. Conversely, in the block caving method of metal mining, the whole procedure
depends on successfully achieving progressive failure of a large rock mass.
PROTOCOL SHEET 1
Objectives and Overall Approach to the Project
(see Table 3.1, Item 1)Have the project, modelling and design objectives
been discussed?
List the main personnel (with their affiliation) who
have discussed the project
What were the dates of the discussions?
Have the objectives been clearly stated?
State the project objective
State the modelling objective
State the design objective
Are there any supplementary objectives?
Have any difficulties been encountered in
specifying the objectives?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.2 PROTOCOL SHEETS 2: Geological Setting and Site Investigation
3
![Page 4: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/4.jpg)
The purpose of this overview Protocol Sheet is to record the information concerning the details
of the geological setting and site investigation. There are then seven sub-sheets numbered as
follows.
2.1 Geological setting
2.2 In situ rock stress
2.3 Intact rock
2.4 Fractures and faults
2.5 Rock mass properties
2.6 Hydrogeological properties
2.7 Other special characteristics/parameters required, e.g. temperature
In each of these sub-sheets, overview data are requested, together with reference to the full
information contained in reports, electronic databases, photographs, etc. If necessary, the user
should provide an associated data sheet/document containing the detailed information.
PROTOCOL SHEET 2
Geological Setting and Site Investigation
(Overview sheet with example data contained in sub-sheets 2.1 to 2.7)Has a structural geologist visited the site and
provided a report on the geological setting?
Has the in situ rock stress been measured?
Is there information on the intact rock properties?
Have the fractures been characterised, including
large features such as brittle deformation zones?
Have the rock mass properties been estimated?
Have the hydrogeological properties been
estimated?
Are there any other key rock mass parameters
involved in the project?
Have any difficulties been encountered in
establishing the information above?
Give the name of the person completing this sheet
Give the name of the person checking the contents
4
![Page 5: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/5.jpg)
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
5
![Page 6: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/6.jpg)
8.2.1 PROTOCOL SHEET 2.1 :Information on the Geological Setting
In modelling and designing a project to be located on or in a rock mass, it is essential to have an
understanding of the geological setting. This provides crucial information on the configuration
of the rock masses and their likely content—which is required for model construction and
hazard analysis.
PROTOCOL SHEET 2.1
Information on the Geological Setting
How has the information on the geological setting
been established?
What are the ages of the rocks?
What rock units are present?
To what extent has the rock been tectonically
deformed?
Are there any faults (or more generally brittle
deformation zones) evident from the geological
setting?
Has the area been subject to glaciations in the past?
Is the rock susceptible to weathering?
Is there currently a Quaternary soil cover?
Are there any special features associated with the
geological setting?
Have any difficulties been encountered in
establishing the geological setting?
Where is the full information on the geological
setting currently held?
6
![Page 7: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/7.jpg)
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
7
![Page 8: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/8.jpg)
8.2.2 PROTOCOL SHEET 2.2: In Situ Stress
Knowledge of the in situ stress is required both for basic considerations of the possibility of
rock failure and as a required boundary condition input for numerical models.
PROTOCOL SHEET 2.2
In Situ Stress
Have the regional stress circumstances at the site
been established from stress maps or other sources?
Has the rock stress been measured at the site?
What type of method has been used for in situ
measurement?
How many locations were measured for in situ
stress?
Is the major principal stress orientated vertically,
horizontally, or at some other orientation?
In what azimuth direction is the major horizontal
stress?
What are the magnitudes and orientations of the
three principal stresses? Include a stereogram.
What are the principal stress ratios: 1/2 , 1/3 ,
2/3 ?
Does the rock overburden vary above the
anticipated project location?
Is there any reason to expect that the stress values
may vary across the site because of, e.g. varying
surface topography, effect of major faults, etc.?
Have the four ISRM Suggested Methods on rock
stress estimation been studied and used?
8
![Page 9: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/9.jpg)
Give the location of the report on the complete rock
stress estimation for the project site
Have any difficulties been encountered in
estimating the in situ stress?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completing this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.2.3 PROTOCOL SHEET 2.3: Intact Rock
The nature of the intact rock is crucial for many aspects of project modelling and design.
PROTOCOL SHEET 2.3
Intact Rock
Have the intact rock properties been considered
within the geological setting, Protocol Sheet 2.1?
How many distinct types of intact rock are present at
the site?
Has the rock been metamorphosed/altered in any
way by geological processes?
Have the intact rock properties been measured?
Which tests established the intact rock properties?
Which standards or suggested methods have been
employed in the determination of intact rock
properties?
9
![Page 10: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/10.jpg)
What are the mean Young’s moduli and Poisson’s
ratios of the intact rocks at the site?
What are the mean compressive strengths of the
intact rocks present at the site?
What are the mean tensile strengths of the intact
rocks present at the site?
Have complete stress–strain curves been obtained,
i.e., the post-peak characteristic in addition to the
pre-peak characteristic?
Any other intact rock data available, e.g., spalling
strength, fracture toughness, etc.?
Is the intact rock susceptible to weathering?
Are there any issues connected with intact rock
anisotropy, inhomogeneity or time dependence?
Have any difficulties been encountered in estimating
the intact rock properties?
Where is the borehole rock core located?
Where are the intact rock data located?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
10
![Page 11: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/11.jpg)
8.2.4 PROTOCOL SHEET 2.4: Fractures and Faults
Knowledge of the presence of fractures and faults is essential to avoid major problems and as
input to computer programs.
PROTOCOL SHEET 2.4
Fractures and Faults
What information can the knowledge of the geological
setting provide about the rock fracturing and faulting?
Are any major faults (or brittle deformation zones)
present?
Have such faults been characterised in terms of their
location, geometry (dip/dip direction) and other features
such as zone thickness?
Have the faults been intersected by boreholes, or have
they been visible at outcrops or in underground
excavations?
Have the fractures been measured?
Which method has been utilised to determine rock mass
(discontinuity) characteristics (e.g., scanline survey,
window mapping, and measurements along the sidewalls
of an underground opening or geotechnical logging along
borehole cores)?
If borehole cores have been used, has a comparison been
carried out between the measurements obtained from
cores and surface techniques?
How many fracture sets are present?
What are the orientations of the fractures (supply one or
more stereograms)
11
![Page 12: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/12.jpg)
What other information concerning the fractures is
available, e.g., tracelength, roughness, aperture, etc.?
Do the fracture characteristics vary across the site, so that
structural fracture domains may be necessary?
Have any difficulties been encountered in estimating the
fracture properties?
Where is the fault and fracture information held?
Give the name of the person completing this sheet
Give the name of the person checking the contents of the
completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this Protocol
Sheet
8.2.5 PROTOCOL SHEET 2.5: Rock Mass Properties
The rock mass properties are a function of the combined effects of the intact rock and the
fractures, and possible external effects such as the applied stress.
PROTOCOL SHEET 2.5
Rock Mass Properties
What information can the knowledge of the
geological setting provide about the rock mass
properties?
Have the main mechanical properties of the rock
masses present been established?
Have the rock mass properties been measured
12
![Page 13: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/13.jpg)
directly?
Have empirical methods been used to estimate the
rock mass properties, e.g., via RMR, Q, GSI, BQ
ratings?
Have numerical methods been used to estimate the
rock mass properties, e.g., through the use of the
3DEC program with the intact rock and fracture
properties input to the model?
What are the rock mass deformation and strength
properties?
Have any difficulties been encountered in
estimating the rock mass properties?
Where is the rock mass information held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.2.6 PROTOCOL SHEET 2.6: Hydrogeological Properties
For many projects, knowledge of the rock mass permeability/hydraulic conductivity and other
characteristics of water flow through the rock mass is crucial for the success of the project and
for avoiding/mitigating water hazards.
13
![Page 14: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/14.jpg)
PROTOCOL SHEET 2.6
Hydrogeological Properties
What information can the knowledge of the
geological setting provide about the rock mass
hydrogeological properties?
Is water flow through the rock mass occurring
mainly through the intact rock or through the rock
fractures?
Have the rock mass hydraulic conductivity and/or
rock fracture transmissivities been estimated by any
means?
Have the rock mass hydraulic conductivity and/or
rock fracture transmissivities been measured
directly?
What are the likely water head pressures to be
encountered in the project?
What are the likely fracture transmissivity values?
Are high water pressures likely to be present when
faults are intersected by the rock excavation?
Have any difficulties been encountered in
specifying the rock mass hydrogeological
characteristics?
Where is the hydrogeological information held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
14
![Page 15: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/15.jpg)
Location of back-up electronic storage of this
Protocol Sheet
8.2.7 PROTOCOL SHEET 2.7: Other Special Parameters
Depending on the purpose and nature of the rock engineering project, information on a variety
of extra rock mass characteristics may be required, e.g., likely TBM excavation rates,
temperature of the rock, degree of foliation, etc.
PROTOCOL SHEET 2.7
Other Special Characteristics/Parameters Required
Is information on any ‘non-standard’ rock
characteristic required for modelling and designing
the project?
Which extra characteristics are required?
Have these been estimated?
Have these been measured?
Which methods (standard or suggested) have been
employed for the determination of extra
characteristics?
Have any difficulties been encountered in
establishing the values of these
characteristics/parameters?
Give the values of the these
characteristics/parameters
Where is the information on these extra parameters
held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
15
![Page 16: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/16.jpg)
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
16
![Page 17: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/17.jpg)
8.3 PROTOCOL SHEETS 3: Modelling
This Protocol Sheet and the associated sub-sheets follow the same pattern as for Protocol Sheet
2 but the subject is now modelling. In Chapter 2 we showed the Figure 2.1 diagram of the eight
main modelling methods; this diagram is reproduced below as Figure 8.1.
Protocol Sheet 1 covers the overall objectives and approach to the rock engineering project,
including the modelling objective. Protocol Sheets 2 cover the geological setting and the site
investigation aspects. Now Protocol Sheets 3 cover the eight main modelling aspects. The roles
of these three Protocol Sheets are indicated in Figure 8.1.
Figure 8 1. The eight main types of modelling to support rock engineering design (following Figure 2.1).
Accordingly, there are ten Protocol Sheet 3 sub-sheets as listed below. These follow the eight
main modelling methods in the order of Method A through to Method D in Figure 8.1 with, in
each case, the Level 1 procedure taken firstly and the Level 2 procedure taken secondly. The
Protocol Sheet 2
Protocol Sheet 1 Protocol Sheet 3Objective
Method A Method B Method C Method D
Lab
and
field
test
s
Use ofpre-existing
standard methods
Design based on forward analysis Design based on back analysis
Level 2Not 1:1 mapping
Level 11:1 mapping
Precedent type
analyses and
modifications
Analytical methods,
stress-based
Rock massclassification,
RMR, Q,GSI, BQ
Basic numerical methods,
FEM, BEM, DEM, hybrid
Databaseexpert
systems, & other
systemsapproaches
Extended numerical methods,
fully-coupled models
Integratedsystems
approaches, internet-based
Site
inve
stig
atio
n
Construction and monitoring
17
![Page 18: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/18.jpg)
ninth Protocol Sheet 3 sub-sheet covers the eventuality that another type of modelling is
additionally being conducted, e.g., physical modelling. The tenth Protocol Sheet 3 sub-sheet
covers the use of the different methods in combination or sequence—because more than one
method is usually used.
3.1 Pre-existing standard methods
3.2 Precedent type analyses
3.3 Analytical methods
3.4 Rock mass classification
3.5 Basic numerical models
3.6 Database and systems approaches
3.7 Extended numerical models
3.8 Advanced systems approaches
3.9 Alternative type(s) of modelling
3.10 Use of the different methods in combination or sequence
18
![Page 19: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/19.jpg)
PROTOCOL SHEET 3
Modelling
(Overview sheet with associated sub-sheets 3.1 to 3.10 following)
What is the purpose of the completed or anticipated
modelling?
Is the type of modelling being used covered by one
or more of the eight methods shown in Figure 8.1?
If so, state which of the eight main modelling
methods is/are being used?
If the modelling method being used is not one of the
eight methods shown in Figure 2.1 or 8.1 (Feng and
Hudson, 2011), specify the type(s) of modelling
being used.
Is the modelling being conducted as one exercise or
is the modelling sequential in some way?
Have all the input parameters for the modelling
method(s) been satisfactorily obtained?
Has it been possible to verify the modelling in any
way, i.e., has there been any check of the results
obtained by two or more modelling methods?
Has it been possible to validate the model in any
way, i.e., check that the modelling results
correspond with the rock reality?
Has the modelling method raised any unforeseen
difficulties?
Give the name of the person completing this sheet
19
![Page 20: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/20.jpg)
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
20
![Page 21: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/21.jpg)
8.3.1 PROTOCOL SHEET 3.1: Pre-existing Standard Methods
The simplest design approach is to use a pre-existing standard method, e.g. a standard type of
tunnel lining, without any further consideration. Although most projects now require more
design than the direct application of a pre-existing method, it is possible that some
circumstances will allow this, particularly if there is specific experience of the method at an
adjacent location in the same rock mass.
PROTOCOL SHEET 3.1
Pre-existing Standard Methods
Why is it possible to use a pre-existing standard
method?
What is the pre-existing standard method that is to
be used?
Have any supporting modelling methods been used
to confirm the applicability of the standard method?
Is the rock mass consistent over the area/volume of
the rock mass involved?
Is it anticipated that in places the ground conditions
may locally not be suitable for the pre-existing
standard method?
Have any difficulties been encountered in ensuring
that the pre-existing method is suitable?
Where is the full information on the pre-existing
method being applied for the project currently held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
21
![Page 22: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/22.jpg)
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
22
![Page 23: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/23.jpg)
8.3.2 PROTOCOL SHEET 3.2: Precedent Type Analysis (PTA)
A sophisticated extension of the pre-existing standard method is to use the Precedent Type
Analysis method pioneered in China which allows tailoring precedent construction to the
ground conditions for assessing rock stability in tunnels. It is a ‘semi-analytic’ method that
applies the geological conditions and relevant construction conditions of a so-called ‘typical’
project to a new tunnelling project for stability analysis (Li et al., 1998). Briefly, the method
uses rock mass classification and numerical analysis to compare the new site with the data for
past ‘typical’ projects. It is an analogue reasoning method.
Note: In Figure 8.1, Methods A to D represent an increase in complexity, so the PTA method
should really be further to the right—because it incorporates both rock mass classification and
numerical analyses; however, it is convenient to retain PTA’s position in Figure 8.1 because its
basis is the use of site data from previous typical projects.
PROTOCOL SHEET 3.2
Precedent Type Analysis (PTA)
Why is the PTA approach being used?
Has the exact Li Shihui et al. (1998, IJRMMS, 35,
6, 787-795) PTA been used?
(Li, S.H., Wu, X.Y. & Ma, F.S.: Application of Precedent Type
Analysis (PTA) in the Construction of the Ertan Hydro-Electric
Station, China. Int. J. Rock Mech. Min. Sci. 35 (1998), pp.787–
795.)
If not, what modifications have been introduced?
What type of rock mass classification was used in
the approach?
Which data from previous typical projects were
used?
What type of numerical analysis was used?
Was the flowchart in Figure 3 of Li Shihui et al.
(1998), used to guide the modelling work?
23
![Page 24: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/24.jpg)
Did the use of PTA essentially follow the same
procedure as that used for the construction of the
Ertan hydroelectric station ( see Li Shihui et al.,
1998, IJRMMS, 35, 6, 787-795)?
Were any difficulties encountered in the application
of PTA?
Give the location of the report on the use of PTA
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completing this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.3 PROTOCOL SHEET 3.3: Analytical Methods
The term ‘analytical methods’ here refers mainly to elastic solutions which provide the
distributions of stresses and strains for relatively simple geometries, with the assumptions of
continuity, homogeneity, isotropy and linear elasticity. An example is the Kirsch solution which
provides the stresses around a circular hole given the applied boundary stresses. Although these
solutions are for a highly idealised material, they can provide helpful guidance.
PROTOCOL SHEET 3.3
Analytical Methods
Why was an analytical method approach used?
Was the use of the analytical method supported by
24
![Page 25: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/25.jpg)
any other methods?
Which particular analytical solution was used?
Are the strict CHILE conditions (continuity,
homogeneity, isotropy, linear elasticity) for an
elastic solution applicable for the rock mass being
considered?
Was the solution in 2-D or 3-D?
If rock mass parameters were used (e.g., not
required for stresses in the Kirsch solution but are
required for displacement), where did the parameter
values come from?
Were any difficulties encountered in finding and
applying the appropriate analytical solution?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.4 PROTOCOL SHEET 3.4: Rock Mass Classification
The analytical methods considered in Protocol Sheet 3.3 are in the top row in Figure 8.1, i.e.,
1:1 mapping, because there is an attempt to model the exact geometry in question—a circular
opening in the case of the Kirsch solution. However, in the case of rock mass classification, the
values of several rock mass parameters are reduced to index values from which an overall rock
mass classification value is established. This value then indicates the quality of the rock from
25
![Page 26: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/26.jpg)
which decisions can be made regarding excavation and support. Thus, rock mass classification
is a non 1:1 mapping method because there is no direct attempt to incorporate the engineering
geometry into the rock mass classification value.
PROTOCOL SHEET 3.4
Rock Mass Classification
Why was the rock mass classification approach used?
Which type of rock mass classification method is being used?
Is the method(s) a standard one or is it a new one specially
developed for the project, or a modification of a standard
method?
If it is not a standard rock mass classification method, explain
the motivation for its use and its content
How is/are the rock mass classification value(s) to be used?
Have the engineers been trained in obtaining the rock mass
classification values? If so, how?
Has there been any check on the variability of the rock mass
classification values, e.g., the standard deviation of values?
Is there any check on the rock mass classification results and
implications using another modelling method, e.g. numerical
modelling?
Since the rock mass classification method is not 1:1 mapping,
how have you incorporated other factors, e.g., the presence of
a nearby fault?
Have any difficulties been encountered in using the rock mass
classification method?
Where is the rock mass classification information held?
Give the name of the person completing this sheet
26
![Page 27: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/27.jpg)
Give the name of the person checking the contents of the
completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this Protocol Sheet
8.3.5 PROTOCOL SHEET 3.5: Basic Numerical Models
The basic numerical methods include the Finite Element Method, Boundary Element Method,
and Discrete/Distinct Element Method. These are classed as 1:1 methods because there is an
attempt to simulate the engineering geometry. Usually, the known larger fractures, e.g., faults
can be input into the mesh geometry as deterministic features but the smaller fractures are
simulated statistically via probability distribution functions. This Protocol Sheet 3.5 covers the
general use of numerical models; those with more advanced features, such as thermo-hydro-
mechanical couplings, are dealt with in Protocol Sheet 3.7.
PROTOCOL SHEET 3.5
Basic Numerical Models
Why was a numerical model used?
Which type of numerical model was used?
Why was that type of numerical model chosen?
How were the values of input parameters chosen?
Were the results from two different codes compared
to check if similar results were obtained?
Was a sensitivity study conducted, i.e., how
variations in the input parameters affected the
output parameters?
How were the factors of rock discontinuities,
27
![Page 28: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/28.jpg)
inhomogeneity, anisotropy and time dependency
taken into account?
Have any difficulties been encountered in
estimating the rock mass properties?
How was the presence of faults taken into account?
Has there been any way of validating the numerical
output, i.e., being able to check that the model
correctly represents the behaviour of the real rock?
Location of the numerical modelling information?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.6 PROTOCOL SHEET 3.6: Database and Systems Approaches
This approach is a more extensive version of the Precedent Type Analysis and Rock Mass
Classification, but is still a non 1:1 mapping method because the exact geometry of the project
is not mapped directly. The many variables in the system are studied, together with their
interactions, so that the most important components can then be identified, both with regard to
their importance and their hazard significance. Decisions on design can then be made on the
basis of this information, often supported by database information on rock engineering projects.
PROTOCOL SHEET 3.6
Database and Systems Approaches
28
![Page 29: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/29.jpg)
Why was a database/systems approach used?
Which type of database/systems approach was
used?
How were the key project components identified?
Were these components ranked in terms of their
importance for the project?
Was a hazard analysis conducted based on the
identification of the most important parameters?
Was the significance of changes in parameters
studied, i.e., parameter A affects parameter B which
affects Parameter C, etc.?
Which specific database was used?
Have any difficulties been encountered in using the
database/systems approach?
Where is the database/systems information held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
29
![Page 30: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/30.jpg)
8.3.7 PROTOCOL SHEET 3.7: Extended Numerical Models
This subject covers extensions to the ‘conventional’ numerical methods, especially the use of
coupling algorithms to incorporate interactions between the primary variables, e.g., thermo-
mechanical coupling and hydro-mechanical coupling. More advanced extensions, such as full
thermo-hydro-mechanico-chemical (THMC) coupling are included and other features that make
the method advanced or specialised in some way.
PROTOCOL SHEET 3.7
Extended Numerical Models
Which type of extended numerical model has been
used?
Has this extended model been obtained ‘off the
shelf’, or has it been developed ‘in house’?
What are the special features of the extended model
being used?
How have the necessary input parameters been
obtained?
Have any difficulties been encountered in
establishing the values of these
characteristics/parameters?
Has it been possible to check the output with another
modelling method, numerical or otherwise?
Has it been possible to validate the output of the
model, i.e., check that it correctly represents the real
rock behaviour?
Where is the information on the modelling
parameters and use of the extended numerical model
held?
Give the name of the person completing this sheet
30
![Page 31: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/31.jpg)
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.8 PROTOCOL SHEET 3.8: Advanced Systems Approaches
This Protocol Sheet covers methods more advanced than those covered in Protocol Sheet 3.6
and includes advanced systems approaches, internet-based systems approaches, virtual
computing platforms, use of real-time site data from instruments, TV images, etc.
PROTOCOL SHEET 3.8
Advanced Systems Approaches
Why is an advanced systems approach being used?
What type of advanced systems approach is being
used?
Explain how the data are being obtained
Explain how the data are being processed
Explain how the modelling output is being generated
Has it been possible to compare the results of the
advanced systems approach with any other
modelling method?
Have any difficulties been encountered in
establishing the values of these
characteristics/parameters and processing the data?
31
![Page 32: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/32.jpg)
Where is the information on the use of the advanced
systems approach being held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.9 PROTOCOL SHEET 3.9: Alternative Type(s) of Modelling
The previous eight Protocol Sheets have covered the eight basic modelling methods shown
within the Protocol Sheet 3 rectangle in Figure 8.1. It is possible that some other type of
modelling method may be considered or have been used, e.g., physical modelling. This Protocol
Sheet 3.9 covers that eventuality.
PROTOCOL SHEET 3.9
Alternative Type(s) of Modelling
Why was an alternative modelling method used?
What type of alternative modelling method was
used?
Was it a 1:1 mapping or non-1:1 mapping model?
If it was a physical model, what type of physical
model was used?
Has total dimensional similarity been achieved?
32
![Page 33: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/33.jpg)
If it was not a physical model, what type of
alternative model was used?
Explain the mode of operation of this alternative
model
Has it been possible to check the results of the
alternative model with any of the other methods
outlined in the Protocol Sheet 3 rectangle in Figure
8.1 in this book (Feng and Hudson, 2011)?
Were any difficulties encountered in the use of the
alternative model?
Where is the information on the use of the
alternative model held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.3.10 PROTOCOL SHEET 3.10: Use of Different Modelling Methods in Combination or
Sequence
Often more than one modelling method is used to support the design of a rock engineering
project, i.e., two or more of the eight methods shown within the Protocol Sheet 3 rectangle in
Figure 8.1 may be used. These methods could be used in combination, e.g., the analytical and
rock mass classification approaches used together so that the results can be compared.
Alternatively, the methods could be used in sequence, e.g., an analytical method solution is used
33
![Page 34: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/34.jpg)
to calibrate a basic numerical method, which is then extended to account for a particular feature
of the rock engineering project, such as the elevated temperature.
PROTOCOL SHEET 3.10
Use of Different Methods in Combination or Sequence
Why was it necessary to use more than one of the
modelling methods?
Which modelling methods were used?
Were these methods used in combination for
comparison of results or were they used in sequence
for a particular purpose?
Explain the overall results of using more than two
methods
Were any difficulties encountered in using two or
more or the modelling approaches?
Where is the information on the multiple use of
modelling methods held?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
34
![Page 35: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/35.jpg)
8.4 PROTOCOL SHEETS 4: Design
Figure 8.2 below is the flowchart for design which was presented in Chapter 3, Figure 3.12,
(and is the companion to Figure 8.1 for modelling already included in Chapter 2, Figure 2.1).
The location in the Figure of Protocol Sheets 1-4 is indicated. Now we consider the Protocol
Sheets 4.1 and 4.2 dealing with the initial design and the final design, respectively. Note that
Protocol Sheet 4.2 also includes integration of all the modelling results, feedback obtained
during the construction process and the associated back-analysis.
Figure 8.2. The seven steps in the design process and the related Protocol Sheets.
It is possible to go directly from Step 5 to Step 7 in Figure 8.2, i.e., taking the initial design
(Protocol Sheet 4.1) as being the final design, but the inclusion of Protocol Sheet 4.2 allows for
the feedback loop accounting for information from construction—which may be traversed
Protocol Sheet 1
Protocol Sheets 2
Protocol Sheets 3
Protocol Sheets 4
7. Final design and verification
6. Integrated modelling and
feedback information
5. Establish initial design
4. Choose modelling method and appropriate
code
3. Design approach strategy
2. Key features of the site, rock
mass and project
1. Project purpose
Establish the objective and sub-objectives of the project
Identify the features and constraints of the site
rock mass and projectDevelop the overall design approach strategy based on the options in the
Methods A to D in the Figure 2.1 flowchart
Utilise the principles of modelling,
choose method(s)
Utilise the principles of code
implementation, choose method(s)
Establish initial design, conduct hazard assessment, and initiate construction, with
monitoring
Consider the integration of the
modelling methods in Figure 2.1
Consider feedback information from
construction, as in Fig.2.1, leading to closed-loop design
INITIAL DESIGN
FINAL DESIGN
DESIGN STEP CONTENTS OF THE DESIGN STEP
Establish final design and verify by monitoring
35
![Page 36: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/36.jpg)
several times as successively more and more construction related information becomes
available.
8.4.1 PROTOCOL SHEET 4.1: Initial Design
This Protocol Sheet covers Step 5 in Figure 8.2: the initial design. The decision may be taken
that the initial design is the final design; alternatively, Steps 6 and 7 may also be implemented,
leading to the final design which means that Protocol Sheet 4.2 is also required.
PROTOCOL SHEET 4.1
Initial Design
Has an initial design been established?
If so, what has been the main information leading to
the initial design?
Has there been appropriate integration of the
objective, the geological and site information and
the modelling?
What have been the key project factors affecting the
initial design?
What have been the key features of the site
affecting the initial design?
What have been the key modelling conclusions
affecting the initial design?
Has a hazard assessment been conducted and, if so,
what type?
Has monitoring been installed so that feedback
information will be available and back analysis then
possible?
Is the initial design flexible in the sense that
36
![Page 37: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/37.jpg)
changes can be made?
Were any problems encountered in establishing the
initial design?
If it is decided that the initial design is the final
design, for what reasons was that decision made?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.4.2 PROTOCOL SHEET 4.2: Final Design
This Protocol Sheet 4.2 is used if modifications to the initial design lead to the final design.
PROTOCOL SHEET 4.2
Final Design
Why was the initial design modified to the final
design?
What has been the main type of information causing
the change to the final design?
If monitoring information during construction has
caused alteration to the initial design, which specific
data caused the change?
Has new modelling (via a back analysis) been
37
![Page 38: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/38.jpg)
conducted as a result of the information obtained
during construction?
How many iterations of the loop indicated in Figure
8.2 (i.e., Steps 6 to 7 and 7 to 6 forming a feedback
loop) have been carried out?
How did you know when to stop the Steps 6 to 7
and 7 to 6 feedback loop and establish the final
design?
Has a new hazard assessment been conducted as a
result of the monitored information and, if so, of
what type?
Were any problems encountered in establishing the
final design?
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
8.5 PROTOCOL SHEET 5: Auditing Evaluation
As mentioned earlier, the technical auditing requirement is
- to evaluate the logic of the work based on the stated objective,
- to establish whether all the necessary physical mechanisms, variables, and parameters
have been included in the relevant analyses,
38
![Page 39: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/39.jpg)
- to show that the supporting analyses are technically correct,
- to consider whether conclusions are justified in terms of the project objectives and the
work conducted, and
- to provide an information, analysis and decision audit trail.
The purpose of the Protocol Sheets 1–4, together with their sub-sheets, now becomes
apparent: there is an audit trail explaining how and why all the major activities have been
conducted. From this, all the required items 1–5 in the list above have been satisfied.
Additionally, in Chapter 5 it was explained that the auditing can be ‘soft’, ‘semi-hard’ or
‘hard’, as indicated in Figure 8.3. The Protocol Sheets included so far certainly provide the basic
information necessary for establishing the essence of the problem in the ‘soft’ audit and, if the
necessary supporting information is included or referenced with the completed Protocol Sheets,
also satisfy the requirement for the ‘hard’ audit.
Protocol Sheets 5
Soft Audit Semi-Hard Audit Hard Audit
Checking that the basic approach to the design problem and
the associated modelling follow
appropriate principles
Checking that the basic approach to the design
problem and the associated modelling,plus the key details,
follow appropriate principles
Checking that all aspects with all the
relevant details have been appropriately
implemented
AUDIT EVALUATIONThe evaluation will depend on the type of auditing used,
‘soft’, ‘semi-hard’, or ’hard’, and whether a single audit has been usedor a progression through the three auditing types
39
![Page 40: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/40.jpg)
Figure 8.3. The ‘soft’, ‘semi-hard’ and ‘hard’ audits, and the audit evaluation.
What remains now is to evaluate this audit information to ensure that the information
gathered, the modelling work and the initial/final rock design are adequate for the purpose, see
the final box in Figure 8.3.
PROTOCOL SHEET 5
Auditing Evaluation
Is this auditing evaluation being made as a ‘soft’,
‘semi-soft’ or ‘hard’ audit (see Figure 8.3)
Has it been assured that all the information in all the
completed Protocol Sheets is correct?
Is the quantity of information in all the Protocol
Sheets acceptable* — in the sense that there is
sufficient information (either directly or through the
referenced material) for the audit evaluation to be
completed? If not, specify where there is
insufficient information.
*This refers to the information itself, not to the evaluation
of the information
Can you recommend how this lack of sufficient
information can be overcome?
Does this auditing evaluation indicate that all
aspects of the work (as described in the Protocol
Sheets) are acceptable? If not, indicate where there
are problems
Can you recommend how these problems should be
overcome?
40
![Page 41: Paper title - CRC Press and Hudso… · Web viewWord file of the Chapter 8 Protocol Sheets in “Rock Engineering Design” by Feng and Hudson The Protocol Sheets have been provided](https://reader036.vdocuments.site/reader036/viewer/2022070622/5e42600526d1ca0b3043b3f0/html5/thumbnails/41.jpg)
Were any difficulties encountered in undertaking
this auditing evaluation?
Is this Auditing Evaluation Protocol Sheet being
completed by a person who has an independent
status, and is free of investigatory and reporting
constraints? If not, explain where there could be a
conflict of interest
Give the name of the person completing this sheet
Give the name of the person checking the contents
of the completed sheet
Date of completion of this sheet
Location of electronic storage of this Protocol Sheet
Location of back-up electronic storage of this
Protocol Sheet
41