paper 43 - opt 2015_bhi 9_2_15

22
OPT 2015 – February 25, 2015 John Grover 1 Deepwater Pipelines – the latest developments using coiled tubing down-lines for pre-commissioning and contingency dewatering

Upload: john-grover

Post on 16-Apr-2017

105 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

1

Deepwater Pipelines – the latest developments using coiled tubingdown-lines for pre-commissioning and contingency dewatering

Page 2: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

2

Presentation Contents

Recent advances using large bore coiled tubingas a down-line

What do we mean by pre-commissioning?

Why do we need a down-line?

Down-line types and comparison

Latest developments in coiled tubing down-lines

What governs down-line size and capacity?

Custom coiled tubing system design

Connecting to the pipeline

Blue-water marine challenges

Innovative WBC solution using coiled tubing

Why do we need wet buckle contingencysystems?

Using coiled tubing to partially dewater anddepressurise a deep water pipeline section

Summary and conclusions

Page 3: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

3

What do we mean by pre-commissioning?

CleaningFlooding Gauging System PressureTesting

Dewatering Conditioning Drying Inerting

Page 4: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

4

Why do we need a down-line?

Wet End to Wet End Pipeline Dry End to Dry End Pipeline

Dry End to Wet End Pipeline

Page 5: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

5

Down-line types and comparison?

3 ½” x 2,200m

2 3/8” x 2,200m

3 ½” x 2,000m

3 ½” x 1,800m

Coiled Tubing Composite Flexible Hose

Page 6: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

6

Down-line types and comparison?

Attribute Coiled Tubing Composite Down Line

Delivery Time Better – 8 to 9 months Worse – 12 to 18 months

Cost Better Worse – approx.. 2 x CT price

Deck Space Much Better Much Worse

Mobilisation Better – can move by roadMuch Worse – at 150 tonnes for reel

alone only by sea

ReliabilityBetter – over 100 subsea deployments

and millions of well deployments

Worse – some history of composite

down lines failing during test and

deployment

Contingency

Much Better – a spare coiled tubing

string and reel can be supplied quickly

and at low cost

Much Worse – cost of spare line and

reel approx.. 20 x that of CT with 12

month + delivery

Vessel Installation Better – heaviest lift approx. 41,000 KGWorse – heaviest lift approx.. 150

tonnes

Maximum Internal

Temperature

Better – can withstand 90°C typical of

air booster discharge

Worse – limited to 60°C hence

additional air cooling required

Size AvailabilityWorse – current design limited to 3 ½”

OD CT pipe

Better – we believe up to 6” ID

available

Page 7: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

7

What governs down-line size and capacity?

Page 8: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

8

What governs down-line size and capacity?

Line NPS 16”

Wall Thickness 20mm

Line Length 8KM

Water Depth at launcher 1500m

Water Depth at receiver 1500m

Water Temp at surface 28°C

Water Temp at Seabed 4°C

Average dewatering velocity required 0.3 m/sec Average

Free air delivery flow / pressure at

pipeline injection point to achieve

0.5m/sec

11,000 cfm @ 152 barg plus friction loss

through hose. See below

Down-line

Internal Diameter

Down-line

Length

Pressure Top of

Downline (barg)

Pressure Drop

(barg)

2” 2,200m 277barg 125barg

3” 2,200m 173barg 21barg

4” 2,200m 157barg 5barg

Page 9: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

9

Custom coiled tubing system design

1

2

3

4

Page 10: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

10

Custom coiled tubing system design

Capable of operating in water depths

up to 3000m

Designed for large diameter coiled

tubing of 2 7/8” or 3 ½”

DNV certified to allow offshore lifting

Road transportable in two loads

Standard basic components giving

easy access to spare parts and

trained mechanics / operators

Flexible frame to allow use on a wide

variety of vessels, either through a

moon pool or over the side

Subsea connection assembly installed

on deck then injector frame jacks out

overboard

Page 11: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

11

Connecting to the pipeline

Page 12: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

12

Blue-water deployment challenges

• The main issue is the impact of current onthe coiled tubing string and the vesselmovement, resulting from wave action,which can cause fatigue in the pipe string.

• Problem not present down-hole

• Each project modelled using softwarebased systems such as OrcaFlex™

• Custom bend stiffener deployed whererequired

Page 13: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

13

Why do we need wet buckle contingency systems?

• System to mitigate against the effects of a wet buckle

• A wet buckle is best defined as an unplanned event where thepipeline has been damaged and the integrity of the pipeline hasbeen lost

• The sea water enters the air filled pipeline and displaces the air

• Increased weight of the seawater in the pipeline may overloadthe tensioners on the lay vessel and cause the pipeline to bereleased to the seabed

• The lay vessel typically will not be able to recover the pipelineuntil the pipeline has been emptied of water and a suitableconnection point is installed on the pipeline.

• Significant project costs usually recovered through projectinsurance.

• Insurers are aware of such risks and often insist that a wetbuckle contingency system be available at short notice duringthe offshore pipe lay period.

Page 14: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

14

Wet buckle contingency for deep water pipelines

Page 15: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

15

Partial dewatering and depressurisation – step 1

Page 16: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

16

Partial dewatering and depressurisation – step 2

Page 17: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

17

Partial dewatering and depressurisation – step 3

Page 18: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

18

Partial dewatering and depressurisation – step 4

Page 19: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

19

Partial dewatering and depressurisation – step 5

Page 20: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

20

Partial dewatering and depressurisation – comparison

Key Issue Partial Dewatering Conventional Dewatering

Dewatering Time

Much Better – 2 days

including deployment &

recovery

Much Worse – 31days @ min

of 0.3m/sec

Deck Space

Much Better – a spread

designed for 0.1m/sec requires

approx. 880 m2 of deck space

Much Worse – a spread

designed for min 0.3m/sec

requires in excess of 3,300m2

Fuel UsageMuch Better – total of 25,600

litres

Much Worse – total of

7,300,000 litres

Equipment Cost

Significantly Better – even

excluding fuel 1/3 of the cost of

std. WBC.

Much Worse – excluding fuel

at least 3 x the cost of partial

dewatering.

Installation Vessel

Standby

Better – excluding flooding

vessel standby could be less

than 5 days

Worse – excluding flooding

standby could be 40 days

Page 21: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

21

Summary and conclusions

1. Down-lines play an important role in the pre-commissioning of deep waterpipelines

2. Coiled tubing should be considered as the preferred down-line system exceptwhere very large bore down-lines are required. Even then multiple coiledtubing down-lines can be considered as an alternative

3. Custom marine coiled tubing systems provide the flexibility for moon-pool orover-the-side deployment and are largely self-supporting once installed

4. Engineering and modelling is required prior to deploying coiled tubing in ablue-water environment

5. Coiled tubing down-lines today being deployed in Australia, Bulgaria, Norwayand Brazil

6. Deep, large bore gas pipelines require vast air compression systems todewater the line post any wet buckle event

7. A partial dewatering system offers a faster, lower cost alternative to a full wetbuckle contingency dewatering system, especially for pipelines not intendedfor hydrostatic pressure testing

Page 22: Paper 43 - OPT 2015_BHI 9_2_15

OPT 2015 – February 25, 2015

John Grover

22

Thank you and any questions?