Page 1: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Panel Discussion

Page 2: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Retrofit PJ Procedure

FS/Planning

Basic Design

Detail Design

Procurement

Construction

Commissioning

EPC Contractor

BID

M/C Hand Over

Owner

FEEDBenchmark

0 0

Page 3: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Typical Procedure of Retrofit

① Recognition

② Targeting

③ Feasibility Study

④ Basic Planning

⑤ FEED/EPC- Installing New Equip.- Retrofit(=Process Modification)

- Subsidy

STEP 1(BENCHIMARKING)

STEP 2(PLANNING)

STEP 3(DOING)

What Kind of Supports ?

Page 4: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Retrofit Procedure

FS/Planning

Basic Design

Detail Design

Procurement

Construction

Commissioning

EPC Contractor

BID

M/C Hand Over

Owner

FEEDBenchmark

0 0

Step-1 Step-2 Step-3 EPC

Page 5: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Singapore Specific Regulatory Challenge

Page 6: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Retrofit Procedure

FS/Planning

Basic Design

Detail Design

Procurement

Construction

Commissioning

EPC Contractor

BID

M/C Hand Over

Owner

FEEDBenchmark

0 0

Step-1

Page 7: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

STEP 1- BENCHIMARKING -

Monitoring / Visualization / Detection / Targeting / Recognition / Measuring / Awareness

Page 8: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

STEP 2- PLANNING -

Page 9: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

STEP 3- DOING -

Page 10: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Retrofit Procedure

FS/Planning

Basic Design

Detail Design

Procurement

Construction

Commissioning

EPC Contractor

BID

M/C Hand Over

Owner

FEEDBenchmark

0 0

Step-2

Page 11: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Singapore Specific Regulatory Challenge

Page 12: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Subsidy

Page 13: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

Retrofit Procedure

FS/Planning

Basic Design

Detail Design

Procurement

Construction

Commissioning

EPC Contractor

BID

M/C Hand Over

Owner

FEEDBenchmark

0 0

Step-3 EPC

Page 14: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

AssociationName

RING(Research Association of

Refinery Integration for Group-operation)

SII(Sustainable open Innovation

Initiative)

Relevant Government Office

METI(Petroleum Refining and

Reserve Division)

METI(Energy Efficiency Division)

Purpose • Strengthencompetitiveness of refineries and industrial complexes

• Promotion of energy saving

• Optimization of energy supply and demand

Target Company

Multiple operators including Refiners

All domestic businesses

Target Expenses

① Design cost② Equipment cost③ Construction cost

① Design cost② Equipment cost③ Construction cost

Subsidy Ratio 1/2 1/4~1/3

Maximum Amount

1 billion ¥ / year(Rules for 2018)

1 .5 billion ¥ / year

Subsidy Overview

Page 15: Panel Discussion - asiaeec-col.eccj.or.jp · Panel Discussion. Retrofit PJ Procedure FS/Planning Basic Design Detail Design Procurement Construction Commissioning EPC Contractor BID

AssociationName

RING(Research Association of

Refinery Integration for Group-operation)

SII(Sustainable open Innovation

Initiative)

Application Requirements

① Optimization of processed crude oil(Heavy, high acid value)

② Bottom-less measures (Heavy oil production reduction)

③ High value addedpetroleum products

④ Shift to chemicals⑤ Strengthening export

capacity⑥ Operational reliability

① Energy saving rate 1% or more

② Energy saving amount is over 1,000 KL(in a

crude oil equivalent)

③ Cost effectivenessMore than 200KL(in a

crude oil equivalent) / 10 million yen

④ Energy unit improvement rate 1% or more