pam and tmd

Upload: poojit-popli

Post on 02-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 pam and tmd

    1/13

    PAM

    PLANT AUXILIARY

    MAINTENANCE

    WATER CIRCULATION SYSTEM

    Theory of circulation

    Water must flow through the heat absorptionsurface of the boiler in order that it be evaporated into

    steam. Indrum type units (natural and controlled circulation) the water iscirculated from the drum

    through the generating circuits and then back to the drum where the steam is separated and directed to

  • 8/10/2019 pam and tmd

    2/13

    thesuper heater. The water leaves the drum through the down comersat a temperature slightly below

    the saturation temperature. Theflow through the furnace wall is at saturation temperature.

    Heatabsorbed in water wall is latent heat of vaporization creating amixture of steam and water.

    Types of boiler circulating system:

    Natural circulation system

    Controlled circulation system

    Combines circulation system

    Natural circulation system

    Water delivered to steam generator fromfeed heater is at a temperature well below the saturation

    valuecorresponding to that pressure. Entering first the economizer it isheated to about 30-

    40Cbelow saturation temperature. Fromeconomizer the water enters the drum and thus joins the

    circulationsystem. Water entering the drum flows through the down comer and enters ring heater at

    the bottom. In the water walls a part of thewater is converted to steam and the mixture flows back to

    thedrum. In the drum, the steam is separated, and sent to superheater for super heating and then sent to the high pressure turbine.Remaining water mixes with the inc

    oming water from theeconomizer and the cycle is repeated.The circulation in this case takes place onthe

    thermo-siphon principle. The dowm comers contain relativelycold water whereas the riser tubes contain

    a steam water mixture.Circulation takes place at such a rate that the driving force and thefrictional

    resistance in water walls are balanced

  • 8/10/2019 pam and tmd

    3/13

    As the pressure increases, the difference in density between water and steam reduces. Thus the

    hydrostatic head available will not beable to overcome the frictional resistance for a flow

    correspondingto the minimum requirement of cooling of water wall tubes.Therefore natural circulation

    is limited to the boiler with drumoperating pressure around 175 kg/cm.

    Controlled circulation system

    Beyond 80 kg/cm of pressure, circulationis to be assisted with mechanical pumps to overcome the

    frictionallosses. To regulate the flow through various tubes, orifice platesare used. This system is

    applicable in the high sub-critical regions(200 kg/cm)

    Combined circulation system

    Beyond the critical pressure, phasetransformation is absent, and hence once through system isadopted.

    However, it has been found that even at super critical pressure, it is advantageous to recirculate the

    water through thefurnace tubes and simplifies the start up procedure. A typicaloperating pressure for

    such a system is 260 kg/cm

    CHPH

    (CONTROL STRUCTURE PUMP HOUSE)

    The control system has following pumps:-

    Chlorine pump-2(for chlorination of water)

    HP pump-6(for boiling of water)

    LP pump-3(for EP pump house)

    Fire pump-(incase of fire breakdown)

    TWS pump-3(for screening of water)

    CRW pump-3(supply water for water treatment)

    This house is known as control house because amount of water to be supplied for treatment is

    controlled from this house with thehelp of these pumps. Generally 2 CRW pumps out of 3pumpsremains

    open.similarly,1 FS ,2 LP,4 HP,1 TWS pumps remainsopen. If more water is needed then others pumps

    are opened.

    WATER TREATMENT PLANT

    As the types of boiler are not alike their working pressure and operating conditions vary and so do the

    typesand methods of water treatment. Water treatment plants used inthermal power plants are

    designed to process the raw water towater with vary low in dissolved solids known as

  • 8/10/2019 pam and tmd

    4/13

    "dematerializedwater". No doubt, this plant has to be engineered very carefullykeeping in view the type

    of raw water to the thermal plant, itstreatment costs and overall economics

    Actually, the type of demineralization processchosen for a power station depends on three

    main factors:

    The quality of the rawwater.

    The degree of de-ionization i.e. treated water quality

    Selectivity of resins.

    Water treatment process which is generally made up of two sections:

    Pretreatment section

    Demineralizationsection

    Pretreatment section

    Pretreatment plant removes the suspendedsolids such as clay, silt, organic and inorganic matter, plants

    andother microscopic organism. The turbidity may be taken as of twotypes of suspended solids in water.

    Firstly, the separable solids andsecondly the non separable solids (colloids). The coarsecomponents,

    such as sand, silt etc, can be removed from the water by simple sedimentation. Finer particles however,

    will not settle inany reasonable time and must be flocculated to produce the

    large particles which are settle able. Long term ability to remainsuspended in water is basically a

    function of both size and

    specificgravity. The settling rate of the colloidal and finely divided(approximately 001 to 1 micron)

    suspended matter is so slow thatremoving them from water by plain sedimentation is tank

    shavingordinary dimensions is impossible. Settling velocity of finelydivided and collide particles under

    gravity also are so small thatordinary sedimentation is not possible. It is necessary, therefore, touse

    procedures which agglomerate the small particles into

    larger aggregates, which have practical settling velocities. The term"Coagulation" and "flocculation"

    have been used indiscriminately to describe process of turbidity removal. "Coagulation" means to bring

    together the suspended particles. The process describes theeffect produced by the addition of

    a chemical Al (SP) g to acolloidal dispersion resulting in particle destabilization by areduction of force

    tending to keep particles apart. Rapid mixing

    isimportant at this stage to obtain. Uniform dispersion of thechemical and to increase opportunity for pa

    rticles to particlecontact. This operation is done by flash mixer in thec1ariflocculator. Second stage of

    formation of settle able particlesfrom destabilized colloidal sized particles is termed a"flocculation".

    Here coagulated particles grow in size by attachingto each other. In contrast to coagulation where the

    primary force iselectrostatic or intrinsic, "flocculation" occurs by chemical bridging. Flocculation is

    obtained by gentle and prolonged

    mixingwhich converts the submicroscopic coagulated particle intodiscrete, visible & suspended particles.

  • 8/10/2019 pam and tmd

    5/13

    At this stage particles arelarge enough to settle rapidly under the influence of gravityanomaly be

    removed.

    If pretreatment of the water is not done efficiently thenconsequences are as follows:

    Si02 may escape with water which will increase the anionloading.

    Organic matter may escape which may cause organic foulinginthe anion exchanger beds. In the 'pre-

    treatment plantchlorine addition provision is normally made to combatorganic contamination.

    Cation loading may unnecessary increase due to addition of Ca(OH)2 in excess of calculated amount for

    raising the pH of the water for maximum floe formation and also

    AKOrDgmay precipitate out. If less than calculated amount of Ca(OH)2 is added, proper pH flocculation

    will not beobtained and silica escape to demineralization section willoccur, thereby increasing load on

    anion bed.

    Demineralization

    This filter water is now used for demineralizing purpose and is fed to cation exchanger bed, butenroute

    being first dechlorinated, which is either done by passingthrough activated carbon filter or injecting

    along the flow of water,an equivalent amount of sodium sulphite through some stroke pumps. The

    residual chlorine which is- maintained in clarification plant to remove organic matter from raw water is

    now detrimentalto action resin and must be eliminated before its entry to this bed. Normally, the typical

    scheme of demineralization up to the .mark against an average surface water,is three bed system with a

    provision of removing gaseous carbondioxide from water before feeding to Anion Exchanger. Now, let

    us see, what happens actually in each bed when water is passedfrom one to another.Resins, which are

    built on synthetic matrixof a styrene divinely benzene copolymer, are manufactured in sucha way that

    these have the ability to, exchange one ion for another,hold it temporarily in chemical combination and

    give it to a strongelectrolytic solution. Suitable treatment is also given to them insuch a way that a

    particular resin absorbs only a particular group

    of ions. Resins, when absorbing and releasing cationic portion of dissolved salts, is called cation, exchang

    er resin and whenremoving anionic portion is called anion exchanger resin. presettrend is of employing

    'strongly acidic cation exchanger resin andstrongly basic anion exchanger resin in a DM Plant of

    modernthermal power station. We may see that the chemically activegroup in a cationic resin is SOx-H

    (normally represented by RH)and in an anionic resin the active group is either tertiary amine

    or quaternary ammonium group (normally the resin is represented byROH). The reaction of exchange

    may be further represented as below The water from the ex-cation containscarbonic acid also

    sufficiently, which is very weak acid difficult to be removed by strongly basic anion resin and causing

    hindrance toremove silicate ions from the bed. It is therefore a usual practice toremove carbonic acid

    before it is led to anion exchanger bed. Theex-cation water is trickled in fine streams from top of a tall

    tower packed with, rasching rings, and compressed air is passed from the bottom. Carbonic acid breaks

    into C03 and water

    mechanically(Henry's Law) with the carbon dioxide escaping into theatmosphere. The water is accumula

  • 8/10/2019 pam and tmd

    6/13

    ted in suitable storage tank below the tower, called degassed water dump from where the sameis led to

    anion exchanger bed, using acid resistant pump.The ex-anion water is fed to the mixed bedexchanger

    containing both cationic resin and anionic resin. This bed not only takes care of sodium slip from cation

    but also silicaslip from anion exchanger very effectively. The final output fromthe mixed bed is Exira-

    ordinarily pure water having less than0.2/Mho conductivity 7.0 and silica content less than 0.02 pm.

    Anydeviation from the above quality means that the resins in

    mixed bed are exhausted and need regeneration, regeneration of themixed bed first calls for suitable,

    back washing and settling, so thatthe two types of resins are seperated from each other. Lighter

    anionresin rises to the top and the heavier cation resin settles to the bottom. Both the resins are then

    regenerated separately with alkaliand acid, rinsed to the desired value and air mixed, to mix the

    resinagain thoroughly. It is then put to final rinsing till the desiredquality is obtained.It may be

    mentioned here that there are two types of strongly basic anion exchanger. Type II resins are slightly

    less basic than type I, but have higher regeneration efficiency than typeI. Again as type II resins are

    unable to remove silica effectively,type I resins also have to be used for the purpose. As such, thegeneral

    condition so far prevailing in India, is to employ type IIresin in anion exchangers bed and type I resin in

    mixed bed (for the anionic portion).It is also a general convention to regenerate theabove two resins

    under through fare system i.e. the caustic sodaentering into mixed bed for regeneration, of type I anion

    resin, isutilized to regenerate type II resin in anion exchanger bed. Thecontent of utilizing the above

    resin and mode of regeneration isnow days being switched over from the economy to a higher costso as

    to have more stringent quality control of the final D.M.Water.

    Internal Treatment

    This final D.M effluent is then either led tohot well of the condenser directly as make up to boilers, or

    beingstored in D.M. Water storage tanks first and then pumped for makeup purpose to boiler feed.As

    the D.M. Water has a good affinity toabsorb carbon dioxide and oxygen, and both are extremelyharmfulto metal surfaces for their destruction like corrosion, these have

    to be removed before it is fed to boiler. This is being done indesecrator. Still the residual oxygen which is

    remaining in thewater is neutralized by a suitable doze of hydrazine, at the pointafter desecrator. To

    have further minimum corrosion, the pH of feed water is to be maintained at around 9.0 for which

    purposeammonia in suitable doze is added to this make up water at a pointalong with hydrazine as

    stated above

  • 8/10/2019 pam and tmd

    7/13

    TMD

    TURBINE MAINTENANCE

    DEPARTMENT

    Operating Principles

    A steam turbine's two main parts are the cylinder andthe rotor.As the steam passes through

    the fixed blades or nozzles itexpands and its velocity increases. The high-velocity jet of

    steamstrikes the first set of moving blades. The kinetic energy of thesteam changes into

    mechanical energy, causing the shaft to rotate.The steam then enters the next set of fixed

    blades and strikes thenext row of moving blades.As the steam flows through the turbine, its

  • 8/10/2019 pam and tmd

    8/13

    pressure andtemperature decreases, while its volume increases. The decrease in pressure and

    temperature occurs as the steam transmits .energy tothe shaft and performs work. After

    passing through the last

    turbinestage, the steam exhausts into the condenser or process steamsystem.

    The kinetic energy of the steam changes intomechanical erringly through the impact (impulse)

    or reaction of thesteam against the blades.

    Main Turbine

    The 210MW turbine is a tandem compounded typemachine comprising of H.P. & I.P. cylinders.

    The H.P. turbinecomprises of 12 stages the I.P. turbine has 11 stages & the L.P. hasfour stages

    of double flow. The H.P. & I.P. turbine rotor are rigidlycompounded & the I.P. & the I.P. rotor by

    lens type semi flexiblecoupling. All the three rotors are aligned on five bearings of whichthe

    bearing no.2 is combined with thrust bearing.The main superheated steam branches off into

    twostreams from the boiler and passes through the emergency

    stopvalve and control valve before entering, the governing wheelchamber of the H.P. turbine.

    After expanding in the 12 stages inthe H.P. turbine the steam returned in the boiler for

    reheating.

    The reheated steam from the boiler enter I.P. turbine viainterceptor valves and control valves

    and after expanding entersthe L.P. turbine stage via 2 numbers of cross over pipes.In the L.P.

    stage the steam expands in axially oppositedirection to counteract the trust and enters the

    condenser

    placeddirectly below the L.P. turbine. The cooling water flowingthroughout the condenser tube

    s condenses the steam and thecondensate collected in the hot well of the condenser.The

    condensate collected is pumped by means of 3*50% duty condensate pumps through L.P.

    heaters to

    deaerator from where the boiler feed pump delivers the water to boiler through H.P. heaters th

    us forming a closed cycle.

    TURBINE CYCLE

    Fresh steam from boiler is supplied to the turbinethrough the emergency stop valve. From the

    stop valves steam issupplied to control valves situated on H.P. cylinders on the front bearing

    end. After expansion through 12 stages at the H.P. cylinder steam flows back to boiler for

    reheating and reheated steam from

    he boiler cover to the intermediate pressure turbine trough twointerceptor valves and four

    control valves mounted on the I.P.turbine.After flowing trough I.P. turbine steam enters the

    middle part of the L.P. turbine through cross over pipes. In L.P. turbine theexhaust steam

    condenses in the surface condensers welded directlyto the exhaust part of L.P. turbine. The

  • 8/10/2019 pam and tmd

    9/13

    selection of extraction points and cold reheat pressurehas been done with a view to achieve

    the highest efficiency. Theseare two extractions from H.P. turbine, four from I.P. turbine

    andone from L.P. turbine. Steam at 1.10 to 1.03 g/sq cm Abs issupplied for the gland sealing.

    Steam for this purpose is obtainedfrom deaerator through a collection where pressure of steam

    isregulated.From the condenser condensate is pumped with the helpof 3*50% capacitycondensate pumps to deaerator through the low pressure regenerative equipments.

    Feed water is pumped from deaerator to the boiler through the H.P. heaters by means of

    3*50% capacity feed pumpsconnected before the H.P. heaters.

    DESCRIPTION OF MAIN TURBINE

    Main Components of Turbine:

    Emergency Stop Valve

    Steam from the boiler is supplied to the turbine throughtwo emergency stop valves. The

    emergency stop valve operated byhydraulic servomotor shuts off steam supply to the turbine

    whenthe turbo set is tripped. The emergency stop valves connected

    tothe four control valves through four flexible loop pipes of Chromium-Molybdenum-Vanadium

    steel.

    H.P. Cylinder

    It is made of creep resisting Cr-Mo-V steel castingmade of two halves joined at the horizontal

    planeThe horizontal joint is secured with the help of studsand nuts made of high creep resisting Cr-

    Mo-V steel forgings.

    Toensure H.P. tightness the studs are tightened by heat to a predetermined temperature with

    the help of electric heater.

    H.P. Rotor

    The H.P. rotor has discs integrally forged with the shaftsand is mechanical forming single Cr-

    Mo-V steel forging. A special process to prevent abnormal rotor deflection thermally

    stabilizesthe rotor forging.

    L.P. Rotor

    It consists of shrunk fit discs on a shaft. The shaft is aforging of Cr-Mo-V steel while the discs are

    of high strength Nisteel forging.The H.P. rotor is connected by rigid couplings whole theI.P.

    rotor and L.P. rotor are connected by semi-flexible lens typecoupling. The rotors are

    dynamically balanced to a very precisedegree.

  • 8/10/2019 pam and tmd

    10/13

  • 8/10/2019 pam and tmd

    11/13

    Boiler Feed Pump

    : Three per unit of 50% capaCity eachlocated in the '0' meter level in the TG bay.

    High Pressure Heaters

    : Normally three in number and aresituated in the TG bay.

    Drip Pumps

    : Generally two in number of 100% capacity eachsituated beneath the LP heaters.

    Turbine Lubricating Oil System

    : This consists of Main OilPump (MOP) Starting Oil Pump (SOP), AC standby oil pumpsand

    emergency DC' oil pump and Jacking Oil Pump (JOP) (oneeach per unit).

    Boiler Feed Pumps

    This pump is horizontal and of barrel design driven byan Electric motor through a hydraulic

    coupling. All the bearings of pump and motor are forced lubricated by a suitable oil

    lubricatingsystem with adequate protection to trip the pump if the lubricationoil pressure falls

    below a preset value.The high-pressure boiler feed pump is very

    expensivemachine which calls for a very careful operation and skilledmaintenance. The safety

    in operation and efficiency of the feed pump depends largely on the reliable operation and

    maintenance.Operating staff must be able to find out the causes of defect at thevery beginning

    which can be easily removed without endangeringthe operator of the power plant and alsowithout the expensivedismantling of the high pressure feed pump.The feed pump consists of

    pump barrel, into which ismounted the inside stator together with rotor. The hydraulic part is

    enclosed by the high pressure cover along with the balancingdevice. The suction side of the

    barrel and the space in the high pressure cover behind the balancing device are enclosed by the

    low pressure covers along with the stuffing box casings. The

    bracketsof the radial bearing of the suction side and radial and thrust bearing of the discharge

    side are fixed to the low pressure

    covers.The entire pumps are mounted on a foundation frame. Thehydraulic coupling and two

    claws coupling with coupling guardsare also delivered along with the pump. Water cooling andoillubricating are provided with their accessories.

    Turbine Driven Boiler Feed Pump

    The single cylinder turbine is of the axial flow type.The live steam flows through the emergency

    stop valve and thenthrough the main Control Valves 5 nos. (Nozzle governing). Thesevalves

    regulate the steam supply through the turbine in accordancewith load requirements. The

  • 8/10/2019 pam and tmd

    12/13

    control valves are actuated by a lift bar which is raised or lowered via a lever system by the

    relaycylinder mounted on the turbine casing axial thrust to the maximum extent. Since the axial

    thrust varieswith the load, the residual thrust is taken up by the thrust bearing.The leak off

    from the balancing piston is connected back to theturbine after 9th stage.The turbine is

    provided with hydraulic andelectro-hydraulic governing system. A primary oil pump is used asaspeed sensor for hydraulic governing and shall Probes are used asa speed sensor for electro

    hydraulic governing.Whenever steam is drawn from the cold reheat line

    or auxiliary supply, steam flow is controlled by auxiliary controlvalve. During this period the

    main control valves (4 nos.) willremain fully opened and the bypass valve across it will

    remainclosed. (Bypass remains closed for a short period when change,over from IP steam to

    CRH takes place).The steam exhaust for the BFP- Turbine is connected tothe main condenser

    and the turbine glands are sealed by glandsteam axial thrust to the maximum extent. Since the

    axial thrust varieswith the load, the residual thrust is taken up by the thrust bearing.The leak off

    from the balancing piston is connected back to theturbine after 9th stage.The turbine is

    provided with hydraulic andelectro-hydraulic governing system. A primary oil pump is used asa

    speed sensor for hydraulic governing and shall Probes are used asa speed sensor for electro

    hydraulic governing.Whenever steam is drawn from the cold reheat line

    or auxiliary supply, steam flow is controlled by auxiliary controlvalve. During this period the

    main control valves (4 nos.) willremain fully opened and the bypass valve across it will

    remainclosed. (Bypass remains closed for a short period when change,over from IP steam to

    CRH takes place).The steam exhaust for the BFP- Turbine is connected tothe main condenser

    and the turbine glands are sealed by glandsteam.

    High Pressure Heaters

    These are regenerative feed water heaters operating

    athigh pressure and located by the side of turbine. These aregenerally vertical type and turbine

    bleed steam pipes are connectedto them.HP heaters are connected in series on feed

    watersideand by such arrangement, the feed water, after feed pump entersthe HP heaters. The

    steam is supplied to these heaters form the bleed point of the turbine through motor operated

    valves. Theseheaters have a group bypass protection on the feed waterside.In the event f tube

    rupture in any of the HPH and the level of thecondensate rising to dangerous level, the group

    protection devicediverts automatically the feed water directly to boiler, thus bypassing all the

    3 H.P. heaters

    Following fittings are generally provided on the HP heaters

    Gauge glass for indicating the drainlevel.

    Pressure gauge with three way cock.

  • 8/10/2019 pam and tmd

    13/13

    Air Vent cock.

    Safety valve shell side.

    Seal pot.

    Isolating valves.

    High level alarm switch.

    Speed Governor

    It is directly coupled to the turbine rotor

    throughcoupling and has been designed to maintain automatically thespeed of the turbo set. It

    is located with the front pedestals

    Turbine Oil Lubricating System

    This consists of main oil pump, starting oil pump emergencyD.C. oil pump and each per unit.

    TYPES OF VALVES USED AND MAINTAINED IN TMD

    Gate Valve

    Regulating Valve

    Non-Return Valve

    Safety Valve