pak: mff – power distribution enhancement investment program (tranche 3)€¦ · ·...
TRANSCRIPT
Environment Monitoring Report Bi-annual Environment Monitoring Report July 2015
PAK: MFF – Power Distribution Enhancement
Investment Program (Tranche 3)
Prepared by Islamabad Electric Supply Company, Federal for the Asian Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.
(ii) In this report “$” refer to US dollars. This environment monitoring report is a document of the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Page 1 of 1
L-2972 PDEIP: BAEMRs of FESCO, GEPCO, HESCO, IESCO approved for disclosure
Safia Shafiq
to: Liaqat Ali
27/07/2015 06:08 PM
Cc:
Adnan Tareen, Zehra Abbas, "Jeffrey Bowyer", Maria Ava Golda A. Destura, Jocelyn M. Cabrera Hide Details
From: Safia Shafiq/Consultants/ADB Sort List...
To: Liaqat Ali/PRM/ADB@ADB Cc: Adnan Tareen/CWRD/ADB@ADB, Zehra Abbas/CWRD/ADB@ADB, "Jeffrey Bowyer"
<[email protected]>, Maria Ava Golda A. Destura/CWRD/ADB@ADB, Jocelyn M.
CabreralConsultants/ADB @ADB
6 Attachments
L-2972 IESCO BAEMR (Jan-Jun 2015).pdf L-2972 HESCO BAEMR (Jan-Jun 2015).pdf
L-2972 GEPCO BAEMR (Jan-Jun 2015).pdf ATTMTORW.pdf L-2972 HESCO BAEMR (Jan-Jun 2015).pdf
L-2972 FESCO BAEMR (Jan-Jun 2015).pdf
Dear Liaqat Sb.,
The attached Bi-annual Environmental Monitoring Reports (Jan-Jun 2015) of FESCO, GEPCO, HESCO and IESCO under L-2972 PDEIP are approved for disclosure. Kindly have them uploaded on ADB website and share the weblinks with me.
Thanks and regards,
Safia Shafiq
Environment Specialist (Consultant)
Pakistan Resident Mission
Asian Development Bank
Level 8, North Wing, Serena Office Complex,
Khayaban-e-Suhrawardy G-5, Islamabad, Pakistan.
Tel: +92-51-2087300, Ext: 344
Fax: +92-51-2087397-8 & 2600365-6
Cell: +92-333-2154462
file:///C:/Users/alt/AppData/Local/Temp/notesBDE916/—web8004.htm 28/07/2015
This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and
the Government cannot be held liable for its contents.
BI – ANNUAL ENVIRONMENTAL
MONITORING REPORT (BAEMR)
Project Number: 2972 – PK, Tranche – III {January – July, 2015}
Islamic Republic of Pakistan Power Distribution Enhancement Investment Project (PDEIP) – Tranche – III Multi – Tranche Financing Facility (MFF) Financed by the ASIAN DEVELOPMENT BANK
Prepared By:
(Mr. Imran Malak / Mr. Mohammad Yasin)
Environment & Social Safeguards Section – Management Unit
Office of the Chief Engineer (Development)
ISLAMABAD ELECTRIC SUPPLY COMPANY (IESCO)
IESCO Head Office, Street 40, G – 7 / 4,
Islamabad, Pakistan.
Tel: + 92 – 51 – 9252036 / 9235001, Fax: + 92 – 51 – 9252978
E-mail: [email protected], Web: www.iesco.com.pk
For Islamabad Electric Supply Company (IESCO). Pakistan Electric Power Company (PEPCO).
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 2 of 23
ABBREVIATIONS
ADB Asian Development Bank
AJ&K Azad Jammu & Kashmir
BPI British Power International
CED Chief Engineer Development
E&SS Environmental and Social Safeguard
EA Executing Agency
EIA Environmental Impact Assessment
EPA Environmental Protection Agency
EPD Environmental Protection Department
GOP Government of Pakistan
GS Grid Substation
IA Implementing Agency
IEE Initial Environmental Examination
IESCO Islamabad Electric Supply Company
kV Kilo – Volt
MOW&P Ministry of Water and Power
MFF Multi – Tranche Financing Facility
NEQs National Environmental Quality Standards
NOC No Objection Certificate
PDEIP Power Distribution Enhancement Investment Program / Project
PEPA Pakistan Environmental Protection Act
PEPCO Pakistan Electric Power Company
MU Management Unit
TL Transmission Line
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 3 of 23
TABLE OF CONTENTS
ABBREVIATIONS ................................................................................................................................................... 2 Part I INTRODUCTION ............................................................................................................................... 4
1.1 IESCO ............................................................................................................................................................ 4
1.2 Directorate of CE (Development) / Management Unit (MU) .................................................. 4
1.3 Environmental & Social Safeguard Section – Management Unit ........................................... 4
1.4 Power Distribution Enhancement Investment Program (PDEIP) – Tranche – III. ......... 5
1.5 Scope of the Work – Tranche-III Sub-projects .............................................................................. 6
1.6 Present Status of the Project: .............................................................................................................. 6
1.7 Relationships with Contractors .......................................................................................................... 6
Part II ENVIRONMENTAL MONITORING ........................................................................................... 8 2.1 Monitoring. ................................................................................................................................................. 8
2.2 Monitoring Status: ................................................................................................................................... 8
Part III ENVIRONMENTAL MANAGEMENT ........................................................................................ 9 3.1 Compliance Status with Statuary Requirements ......................................................................... 9
3.2 EMP as a part of Bid Documents. .................................................................................................... 10
3.3 Clauses in the Bid Documents. ......................................................................................................... 10
3.4 Other Monitoring Indicators............................................................................................................. 10
3.5 Compliance Status with Aid Memoire / Agreed Action. ......................................................... 12
Part IV PROJECT PICTURES ................................................................................................................... 15 Annex – A.
IESCO JURISDICTION MAP ......................................................................................................................... 16
Annex – B. ORGANIZATIONAL STRUCTURE OF MU – IESCO .............................................................................. 17
Annex – C. DETAIL SCOPE OF WORK OF TRANCHE - III SUBPROJECT .......................................................... 18
Annex – D. MONITORING STATUS / CHART .............................................................................................................. 19
Annex – E. CLAUSES IN THE BIDDING DOCUMENTS ............................................................................................. 21
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 4 of 23
Part I INTRODUCTION
1.1 IESCO
1. Islamabad Electric Supply Company Ltd. (IESCO) is a public utility company,
having more than 02 Million consumers and provides service to 04 Nos. Northern
Districts of the Punjab Province (Rawalpindi, Attock, Jhelum and Chakwal); Capital
Territory (Islamabad); and Southern parts of Azad Jammu & Kashmir (AJK). IESCO
jurisdiction map is placed at Annex – A.
1.2 Directorate of CE (Development) / Management Unit (MU)
2. To carry out and handle investment projects IESCO has established Management
Unit (MU) under the supervision of Chief Engineer (Development). The MU comprises of
four sections.
i) Planning Scheduling & Coordination
ii) Procurement
iii) Project Finance
iv) Environment & Social Safeguard
3. The organizational structure of MU – IESCO and main responsibilities of each
section are given in Annex – B.
1.3 Environmental & Social Safeguard Section – Management Unit
4. The Environmental & Social Safeguard (E&SS) Section of MU, IESCO provides an
overall supervision and advisory services during the Pre - Construction phase,
Construction phase & Post – Construction phase of the project. The unit also assists and
advises GSC Directorate, Construction Directorate and other IESCO departments on
environmental and social matters overall. Presently, the E&SS Section has one
Environmental and one Social Impact expert under the supervision of a Deputy Manager
Environmental and Social Safeguard (E&SS). Organizational structure of E&SS – MU
IESCO is attached as below.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 5 of 23
Figure 01: Management Structure of E&SS – MU – IESCO.
1.4 Power Distribution Enhancement Investment Program (PDEIP)
– Tranche – III.
5. Program basic information is provided in Table 1.
Table 1: Program Basic Information.
The Program:
Power Distribution Enhancement Investment Program (PDEIP). Multi – Tranche Financing Facility (MFF).
Sub – Project: Tranche – III subproject.
Sponsoring Agency: Government of Pakistan, Ministry of Water & Power (MoW&P).
Executing Agency: Pakistan Electric Power Company (PEPCO).
Implement Agency: Islamabad Electric Supply Company (IESCO).
Type of Financing:
Loan amount US $ 24.55 Million. Loan No. 2972 – PK; Tranche – III Subproject.
Loan Signing Date: September 09, 2013.
Loan Effectiveness Date: December 10, 2013.
Closing Date: June 30, 2016.
Last ADB Review Mission Date: May 22 – June 03, 2015.
CE (Development)
Mr. Riaz Ali Shah
Dy. Manager (E&SS)
Mr. Mohammad Yasin
Asstt. Manager (Social Impact)
Mr. Sher Afzal
Asstt. Manager (Environment)
Mr. Imran Malak
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 6 of 23
1.5 Scope of the Work – Tranche-III Sub-projects
6. IESCO Tranche – III subproject includes 03 Nos. New Grid Station, Extensions /
Augmentations of power transformers at 13 No. Grid stations and 08 Nos.
Transmission Lines. The detail scope of work of Tranche – III subproject is
attached as Annex – C.
1.6 Present Status of the Project:
7. The civil works of following 132 KV T/lines sub-projects of Tr – III have been
awarded, but the physical execution is yet to get underway. The detail of works
awarded is provided below in table 2.
Table 2: Contract details
No.
Pa
cka
ge
Lot
No. Description of Work Awarded to
Contract
Award
Date
Civil work
status
1
ICB
-01
/T
R-I
II/
AD
B
II
a) F/F 132 KV Chakri Road G/Station
b) F/F 132 KV Sangjani-2 G/Station
c) F/F 132 KV Bara Kahu G/Station.
d) Replacement of Sangjani-Zero point 132 KV T/line.
e) 132 KV KTM – Chakri Road T/line
M/s ICC (Pvt),
Lahore. 19-03-2014
The contractor
(ICC) has
mobilized his
team at End
May, 2015, but
the civil work
is yet to start.
8. M/s ICC Pakistan has mobilized their construction staff and crew at the site in
end of May, 2015.
1.7 Relationships with Contractors
9. Orientation / pre – construction meeting was arranged by E&SS section for the
M/s ICC Private Limited , Pakistan ( the contractors) on 19 – 05 – 2015 and they have
been made aware of their responsibilities as per the EMP. The contractors were also
informed that monitoring will be an integral part of the project and will consist of;
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 7 of 23
Monitoring by contractor (Analysis of environmental parameters,
checklist filling) and reporting to GSC IESCO with a copy to MU.
Supervision / Monitoring by GSC and reporting to MU.
Random field visit by MU (E&SS staff) and reporting.
10. The meeting was attended by the following IESCO / Contractor Staff;
Name of Participants. Designation. Department.
Mr. Mohammad Yasin. DM (E&SS). E&SS – MU, IESCO.
Mr. Imran Malak. AM (Environment). E&SS – MU, IESCO.
Mr. Atique Niamet. Project Manager.
M/s ICC Private Limited, Lahore.
Sheikh Farhan Almaghazi (Mr.).
Principal Engineer.
Mr. Muhammad Afzal. Site Manager.
Mr. Sajid Mehmood. Principal Manager.
11. Contractor has been advised to nominate suitably qualified persons as i)
Environmentalist / HSE Officer & ii) Social / Resettlement Officer as per bid document of the subject contract Para . Personnel to handle the environmental & social issues and ensure effective implementation of EMP & Monitoring Plan under the contract.
12. On the request of M/s SMEC, Lahore (Project Facility Consultant), a facilitation /
Pre-work meeting was arranged with M/s ICC Private Limited, Pakistan (the
contractors) on 05 – 06 – 2015 at the Camp office of contractor at Rawalpindi.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 8 of 23
Part II ENVIRONMENTAL MONITORING
2.1 Monitoring.
13. Environmental Monitoring of the projects will be carried out by the contractors
under the supervision of Environmental and Social Safeguard (E&SS) section PMU,
IESCO during the execution phase. For this, field visit will also be carried out by E&SS
Section, PMU IESCO for the smooth and effective implantation of EMMP & Monitoring
plan as prescribed in approved Environmental Assessment Report.
2.2 Monitoring Status:
Description of Indicator. Remarks.
Summarizes the previous six months
monitoring data and provide explanations
of any instances where environmental
standards or guidelines are exceeded. Not Applicable at this stage. Monitoring
Status / Chart is attached at Annex – D. Noise and Vibration.
Water Quality.
Air Quality.
Flora and Fauna Monitoring.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 9 of 23
Part III ENVIRONMENTAL MANAGEMENT
3.1 Compliance Status with Statuary Requirements
14. The loan agreement of the project requires the Implementing Agency (IA) to
implement the project in compliance with statuary / regulatory requirements of the
country and requirements of ADB Guidelines (May 2003). The detail of environmental &
social compliance regarding statuary / regulatory requirements in accordance to ADB &
National Law is tabulated below.
No. Regulatory Requirements. Status of Compliance.
01. Preparation of Environmental
Assessment Reports. EIA Prepared.
02. Clearance from ADB. Clearance given by ADB.
03.
Clearance / Obtaining of No
Objection Certificate (NOC) from
the Environmental Protection
Agency (EPA).
No Objection Certificate (NOC) / Clearance for
execution of the project has been issued by
Punjab Environmental Protection Agency
(Punjab – EPA) on 30th June, 2014.
NOC from Pakistan Environmental Protection
Agency (PAK – EPA), Islamabad is pending for
the re-located site of 132 kv Bara-Kahu Grid
Station.
3.2 Re-location of 132 KV Bara-Kahu Grid Station Site / Feeding
Transmission Line
15. The Bhara Kahu grid station subproject was to be constructed on )ESCO s owned land at 220 KV Grid Station Bhara Kahu, covering an area of approximately 20 Kanals of
land. However, due to technical reasons the site for the said grid station has now been
relocated. The new 32 kanal site is located near Barakahu at Village Phulgaran, Tehsil
and District Islamabad. The project site is accessible from Simly Dam road, about 25
km from the Kashmir Chowk. It is at about 10 minutes drive from the Bara Kahu
town. Presently, the land is owned by M/s Bharia Town Ltd. and they have offered
and committed to provided 32 Kanal (04 Acres) of land to IESCO on willing buyer
willing seller basis for construction of the said grid station. For this purpose, IESCO
constituted a Committee to finalize the site, and mutually negotiate price with M/s
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 10 of 23
Bharia Town Ltd. Consequently, the grid station site is being purchased by IESCO from
M/s Bharia Town Ltd on mutually agreed rate of Pak Rs. 0.6 million per Kanal i.e a total
cost of 19.2 million for the construction of 132 kV Bara Kahu grid station. The land will
be transferred to IESCO once the purchase agreement/ procedural formalities are
finalized.
16. The proposed 132 kv feeding line (about 09 km having approx. 14 poles and 35
towers) will pass along the existing road i.e Nimra Abbasi road and hilly area and some
forest land with shrub and sparse tree cover. The Transmission line will be constructed in
the barren areas of the foot hills excluding the houses or any other public infrastructure or
the private land. The proposed feeding will be connected to existing 132 kV Transmission
line University – Nilor.
3.3 EMP as a part of Bid Documents.
17. Environmental Management & Mitigation Plan (EMMP) & Monitoring Plan of the
approved EIA Reports have been made part of all the bidding documents of civil works
of Tranche – III sub projects.
3.4 Clauses in the Bid Documents.
18. Sufficient clauses have been included in the bid documents and the Contractor is
bound to comply with and carry out all the monitoring and mitigation measures as set
in the Environmental and Social Assessment reports and EMP. Detail of all the clauses
included in the bid documents are given at Annex – E.
3.5 Other Monitoring Indicators.
Description of Indicator. Remarks.
EMS, SSEMP and work plans. Report on
delivery of documents, required
amendments etc.
EMP prepared.
Amendments will be made as per
requirements.
Internal monitoring will be carried out on
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 11 of 23
regular basis to check the
Implementation of EMP.
Non-compliance notices – summarizes the
details on the number of notices given out
and the issues covered.
Summaries the ranking of issues.
Nil.
Corrective action plans - report on
timeliness of preparation and completion Nil.
Consultation and complaints – report on
any consultation undertaken and list any
complaints received.
Consultation carried out during
preparation of Environmental
Assessment reports.
Complaint Registers will be placed at
all work sites / camp sites, PMU &
SDO offices concerned.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 12 of 23
3.6 Compliance Status with Aid Memoire / Agreed Action.
19. The compliance status with ADB Aid Memoire / agreed action during the review mission are as under;
No. Agreed Action. Status of Compliance.
01.
The site of one IESCO subproject is to be changed and the
application for EPA NOC will be filed after the new site is
confirmed.
An addendum to EIA for Bara Kahu grid station site has been
prepared and submitted to Pakistan Environmental Protection
Agency (PAK – EPA), Islamabad for Clearance / NOC on 26-06-
2015.
02.
BIDDING DOCUMENTS.
All DISCOs have included environmental clauses in bidding
documents and subproject EMPs have also been attached.
Complied.
03.
DISCLOSURE:
Similar to tranche-2 subprojects, the EMPs of tranche-3
subprojects are to be translated into urdu and disclosed on
the project website and are also to be placed at the
subproject sites,
EMP has already been translated into Urdu and uploaded at
IESCO website; the same will be disclosed at PMU, office of
concerned XEN / SDO and project site.
04.
At least one environment staff has been appointed in the
Environment and Social Cells (ESC) established under the
various PMUs.
Complied.
05.
ENVIRONMENT STAFF OF CONTRACTORS:
It must be ensured by the DISCOs that all contractors hire
qualified and experienced environment staff. The CVs of
the applicants for the position should be shared with the
Environment Officer of the DISCO and the appointment
Contractor has been advised to nominate suitably qualified
persons as i) Environmentalist / HSE Officer & ii) Social /
Resettlement Officer under the contract. In this regard, contactor
is advised to furnish the following documents to E&SS Section of
the IESCO for approval;
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 13 of 23
No. Agreed Action. Status of Compliance.
should only be confirmed after the relevant DISCOs ESC staff s approval. )t is also recommended that the bidding documents be shared with the environment staff of SMEC
to further ensure that clauses for hiring of qualified
environment staff by the contractor have been adequately
included.
Nomination Letter from ICC (Original),
CV of the nominated Persons (Copy), and;
CNIC (Copy).
06.
SITE SPECIFIC ENVIRONMENTAL MANAGEMENT PLANS:
The Environmental Assessment and Review Framework EARF of PDE)P Tranche further requires that Package was site specific Environmental Management Plan (SSEMP)
will be prepared by the contractor under the supervision of
Environment Specialist (ES) of SMEC. The SSEMP would be approved by these D)SCOs and ADB paragraph of EARF for Power Distribution Enhancement Investment
Program – Tranche-3, September 2012). In view of the
large number of subprojects under Tranche-3 ADB will
only required SSECPs of new grid stations and
transmission lines passing through ecologically sensitive
areas (if any) to be prepared. The subprojects for which the
SSEMPs are to be prepared will be decided in consultation with ADB s environment specialist based at PRM. For
subprojects that have already been awarded (e.g. new grid
stations under MEPCO) SSEMPs are to be prepared and
submitted to MEPCO and then ADB for approval by 30 June
2015.
Will be complied.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 14 of 23
No. Agreed Action. Status of Compliance.
07.
Grievance Redress Mechanism: As was done for tranche-2,
the Grievance Redress Mechanism is to be instituted as
described in tranche-3 EARF (page 10) and the Grievance
Redress Committee for tranche-3 is to be notified by all
DISCOs.
Complied.
08.
Bi-annual Environmental Monitoring Report: The Bi-
annual Environmental Monitoring Reports (BAEMRs) for
the period of July to December 2014 were submitted timely by all D)SCOs except (ESCO, and were disclosed in ADB s website. The BAEMRs for the period of January to June
2015 is to be prepared by all DESCOs for tranche-3
subprojects and submitted to ADB by 15 July 2015.
Compliance being made.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 15 of 23
Part IV PROJECT PICTURES
20. Project pictures will be made part of report after the start of physical work.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 16 of 23
Annex – A.
IESCO JURISDICTION MAP
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 17 of 23
Annex – B.
ORGANIZATIONAL STRUCTURE OF MU – IESCO
Chief Engineer (Development)
Manager
(Planning, Scheduling
& Co-ordination)
Dy Manager
(Monitoring Control
& Coordination)
Assistant Manager
(MC&C)
Dy manager
(Planning & Scheduling)
Assistant Manager
(P&S)
Manger (Procurement)
DM
(Procurement)
Assistant Manager
DM
(Procurement)
Assistant Manager
Dy. Manager
(Environment and Safeguards)
AM
(Social Impact)
AM
(Environment)
Manager
(Project Financing)
DM
(Project Financing)
Assistant Manager Assistant Manager
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 18 of 23
Annex – C.
DETAIL SCOPE OF WORK OF TRANCHE - III SUBPROJECT
No. Project Component
01.
New Grid Station. 03 Nos.
i. 132 kV Bara Kahu Grid Station.
ii. 132 kV Chakri Road Grid Station.
iii. 132 kV Sangani – II Grid Station.
02.
Extension of Power Transformers 04Nos.
i. 132 kV Rajjar Grid Station.
ii. 132 kV Fateh Jang Grid Station.
iii. 132 kV F – 11 Grid Station.
iv. 132 kV Sowan Grid Station.
03.
Augmentation of Power Transformers 09 Nos.
i. 132 kV Kamalabad Grid Station.
ii. 132 kV KTM Grid Station.
iii. 132 kV New Wah Grid Station.
iv. 132 kV Jhelum Grid Station.
v. 132 kV Rawalpindi Cantt (REPCO) Grid Station.
vi. 132 kV Zero Point Grid Station.
vii. 132 kV I – 10 Grid Station.
viii. 132 kV I – 8 Grid Station.
ix. 132 kV Chaklala Grid Station.
04.
Transmission Lines (New) 04 Nos.
i. 132 kV Feed for Bara Kahu Grid Station Transmission Line.
ii. 132 kV Feed for Chakri Road Grid Station Transmission Line.
iii. 132 kV Feed for Sangjani –II Grid Station Transmission Line.
iv. 132 kV KTM – Chakri Road Transmission Line.
05.
Transmission Lines (Remodelling / Replacement) 04 No.
i. 132 kV Sangjani – Zero Point Transmission Line.
ii. 132 kV Burhan – New Wah Transmission Line.
iii. 132 kV New Rewat – Sowan Transmission Line.
iv. 132 kV in – out Construction at Chakri Grid Station Transmission Line.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 19 of 23
Annex – D.
MONITORING STATUS / CHART
No. Description. Status of Compliance
01. Establishment of PMU in IESCO. Yes.
02. Induction of E&SS Section and Staff in
PMU. Yes.
03. Preparation of Environmental Assessment
Reports (EIA Reports). Yes.
04. Clearance & approval of IEE / EIA Reports
from ADB. Yes.
05. Approval of IEE / EIA Reports from CEO,
IESCO. Yes.
06. Uploading of EIA Reports on IESCO
website. Yes.
07. Submission to Concerned EPA / EPD. Yes.
08. Public Hearing Sessions / Events. Public Hearing Event for Punjab – EPA was
held on 26th March, 2014 in Rawalpindi.
09. Clearance / Obtaining No Objection
Certificate (NOC) from the EPA / EPD.
No Objection Certificate (NOC) / Clearance for execution of the project issued by Punjab – EPA on 30th June, 2014.
NOC which was pending due to re-location of Barakha Grid Station is requested from Pakistan Environmental Protection Agency (PAK – EPA), Islamabad.
10. Training on Environment Issues. Yes.
11. Internal Monitoring & Field Visit. -
12. External Monitoring & Field Visit. -
13. EMMP is made part of Bidding Documents Yes.
14.
Provision made in BOQ of Bidding
Documents for Environmental & Social
Issues.
Yes.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 20 of 23
No. Description. Status of Compliance
15. Status of implementation of EMMP &
Monitoring Parameters. -
15. Environmental Audit. -
16. Project Present Status. -
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 21 of 23
Annex – E.
CLAUSES IN THE BIDDING DOCUMENTS
The Clauses included in the bidding documents are;
i. Required Personnel: The Bidder shall provide details of the proposed
personnel and their experience records in the relevant Information Forms
included in Section 4 (Bidding Forms).
ii. The Bidder must demonstrate that it has the personnel for the key positions
that meet the following requirements:
No. Position.
Total Work
Experience
(Year).
Experience in
Similar Work
(Years).
01. Project Manager. 15 10
02. Lead Design Engineer (Civil). 10 05
03. Lead Design Engineer (Electrical). 10 05
04. Construction Manager 10 05
05. Environmentalist / HSE Officer. 05 03
06. Social / Resettlement Officer. 05 03
iii. Employer’s Requirement / Supplementary Information:
SI-03. Environmental Issues:
The Contractor shall comply and carry out all the monitoring and mitigation
measures as set forth in the Environmental & Social Management Plan
(EMP). The EMP & Environmental Monitoring Plan are attached as
Annexure with bidding document.
iv. General Condition of Contract:
Protection of Environment
46. Protection of
Environment
46.1 The Contractor shall observe the environment mitigation
measures that are set out in the Environmental Management
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 22 of 23
Plan (EMP) that has been prepared for the Project.
46.2 The Contractor shall take all reasonable steps to protect the
environment (both on and off the Site) and to limit damage
and nuisance to people and property resulting from
pollution, noise and other results of operations as set forth in
the EMP.
46.3 The Contractor shall ensure that emissions, surface
discharges and effluent from its activities shall not exceed the
values stated in the Specifications, or as prescribed by the
applicable laws.
46.4 The contractor shall Comply with all applicable
environmental laws and regulations of Pakistan.
46.5 The contractor shall
a) Establish an operational system for managing
environmental impacts.
b) Carry out all of the monitoring and mitigating measures set
forth in the EIA and the EMP.
c) Allocate the budget required to ensure that such measures
are carried out, and the actual costs for the implementation
of such measures shall be reimbursed by the employer to
the contractor from provisional sums. The contractor shall
submit to the employer quarterly reports on the carrying
out of such measures.
46.6 The Contractor shall submit monthly & quarterly reports on
carrying out such measures to the Employer.
v. Special Condition of Contract:
9. Contractor’s Responsibilities.
9.8. The Contractor shall comply with all applicable national,
provincial, and local Environmental laws and regulations.
Bi Annual Environmental Monitoring Report ADB (Jan – June 2015)
E&SS – MU – IESCO
Page 23 of 23
The Contractor shall;
a) Establish an operational system for managing
environmental impacts.
b) Carry out all of the monitoring and mitigation measures set forth in the )nitial Environmental Examination )EE and the Environmental Management Plan (EMP) attached
hereto as Appendix 8 / Annexure – C
c) Allocate the budget required to ensure that such
measures are carried out.
d) The Contractor shall submit to the Employer quarterly
report on the carrying out of such measures and the actual
costs for the implementation of such measures shall be
reimbursed by the Employer to the Contractor from Provisional Sums .
vi. Contract Forms / Contract Agreement:
The following documents shall constitute the Contract between the Employer
and the Contractor, and each shall be read and construed as an integral part
of the Contract (Reference GCC Clause 2):
a) This Contract Agreement and the Appendices hereto
b) Letter of Bid and Price Schedules submitted by the Contractor,
c) Special Conditions,
d) General Conditions,
e) Specification,
f) Drawings,
g) Environmental & Social Mitigation Plan,
h) Environmental Monitoring Plan,
i) Other completed Bidding Forms submitted with the Letter of Bid,
j) Any other documents part of the Employer s Requirements.