Line Item Description Unit Unit Price Total Price Quantity Total Price Unit Price Total Price Unit Price Contract S10CN02 Variance Bidder Engineer Massachusetts Bay Transportation Authority Capital Management System Comparison of Bids ORIENT HEIGHTS MAINTENANCE FACILITY, READVERTISEMENT -- PHASE II, EAST BOSTON Report ID: Date/Time: CMS-BM-003 Firm Name: Bidder: DMJM+HARRIS, INC (formerly DMJM) EN Bidder: Firm Name: Bid Date: A 11/27/2007 S&R CONSTRUCTION CO., INC.,dba S&R CONSTRUCTION ENTERPRISES FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00 CPM SCHEDULING 0110.002 LS 1 $210,178.08 $210,178.08 $300,000.00 $300,000.00 $89,821.92 $89,821.92 FIELD OFFICE - TRAILER 0130.100 LS 1 $183,908.55 $183,908.55 $75,000.00 $75,000.00 ($108,908.55) ($108,908.55) MAINTENANCE FACILITY 0130.174 AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00 ROADWAY MAINTENANCE 0130.300 AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00 TRAFFIC OFFICERS SERVICES 0130.430 AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00 LICENSED SITE PROFESSIONAL SERVICES 0160.091 LS 1 $13,554.15 $13,554.15 $176,691.03 $176,691.03 $163,136.88 $163,136.88 CLEARING OF SITE 0210.000 LS 1 $643,796.35 $643,796.35 $1,242,800.00 $1,242,800.00 $599,003.65 $599,003.65 DEMOLITION AND SITE PREPARATION 0210.150 SF 5,000 $5.84 $29,200.00 $1.00 $5,000.00 ($4.84) ($24,200.00) PATCHING AND REPAIRING 0211.003 Page 1 of 112

Upload: others

Post on 26-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $300,000.00 $300,000.00 $89,821.92 $89,821.92FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $75,000.00 $75,000.00 ($108,908.55) ($108,908.55)MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $176,691.03 $176,691.03 $163,136.88 $163,136.88CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $1,242,800.00 $1,242,800.00 $599,003.65 $599,003.65DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $1.00 $5,000.00 ($4.84) ($24,200.00)PATCHING AND REPAIRING0211.003

Page 1 of 112

Page 2: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LS 1 $1,148,821.95 $1,148,821.95 $1,500,000.00 $1,500,000.00 $351,178.05 $351,178.05CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $75,000.00 $75,000.00 ($17,238.34) ($17,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $42.00 $190,890.00 ($37.52) ($170,528.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $0.01 $16.94 ($133.56) ($226,250.64)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $0.01 $1.14 ($322.27) ($36,738.78)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $60.00 $210,000.00 $3.89 $13,615.00UNCLASSIFIED EXCAVATION0222.003

Page 2 of 112

Page 3: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

CY 440 $15.17 $6,674.80 $5.00 $2,200.00 ($10.17) ($4,474.80)TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $0.01 $2.28 ($269.19) ($61,375.32)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $0.01 $10.00 ($33.62) ($33,620.00)SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $50.00 $5,000.00 $21.95 $2,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $0.01 $100.00 ($0.71) ($7,100.00)DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $0.01 $3.00 ($23.63) ($7,089.00)ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $70.00 $53,410.00 $43.00 $32,809.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $400.00 $1,200.00 $52.73 $158.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $100.00 $32,300.00 $46.85 $15,132.55CRUSHED STONE FORDRAIN REVET

0222.603

Page 3 of 112

Page 4: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

TN 120 $31.67 $3,800.40 $150.00 $18,000.00 $118.33 $14,199.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $40.00 $7,160.00 ($17.31) ($3,098.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $85.00 $15,980.00 $68.00 $12,784.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $2.25 $5,539.50 ($4.51) ($11,103.62)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $0.01 $171.00 ($2.73) ($46,683.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $500.00 $3,000.00 ($65.99) ($395.94)BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $1,500.00 $1,272,000.00 ($343.87) ($291,601.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $50.00 $35,750.00 $32.60 $23,309.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $95.00 $1,900.00 $59.33 $1,186.608" PVC PIPE0251.591

Page 4 of 112

Page 5: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LF 20 $123.85 $2,477.00 $100.00 $2,000.00 ($23.85) ($477.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $30.00 $3,000.00 ($252.66) ($25,266.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $75.00 $14,100.00 $24.13 $4,536.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $50.00 $4,200.00 ($24.36) ($2,046.24)TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $50,000.00 $100,000.00 $10,719.83 $21,439.66OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $500.00 $1,000.00 $93.23 $186.46CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $192.50 $4,620.00 ($66.85) ($1,604.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $96.50 $24,125.00 $73.01 $18,252.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $85.00 $12,580.00 ($8.06) ($1,192.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 5 of 112

Page 6: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

TN 148 $101.52 $15,024.96 $85.00 $12,580.00 ($16.52) ($2,444.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $85.00 $28,220.00 $23.58 $7,828.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $120.00 $7,320.00 ($1,074.27) ($65,530.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $33.00 $12,870.00 ($5.32) ($2,074.80)72" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $1.85 $3,918.30 $0.73 $1,546.14SEEDING0282.150

LF 310 $5.31 $1,646.10 $6.00 $1,860.00 $0.69 $213.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $5.00 $1,550.00 ($0.73) ($226.30)SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $35.00 $3,500.00 $6.54 $654.00TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $16,200.00 $16,200.00 ($22,332.35) ($22,332.35)PLANTING0284.145

Page 6 of 112

Page 7: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

EA 3 $86,506.15 $259,518.45 $8,000.00 $24,000.00 ($78,506.15) ($235,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $225.00 $88,875.00 ($300.17) ($118,567.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $22.50 $4,050.00 ($29.29) ($5,272.20)RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $25.00 $9,875.00 ($26.79) ($10,582.05)SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $100.00 $118,100.00 $42.29 $49,944.49DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $99,776.00 $99,776.00 ($25,407.00) ($25,407.00)SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $166.00 $11,454.00 ($338.44) ($23,352.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $675.00 $2,700.00 $170.56 $682.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $245.00 $96,775.00 ($95.37) ($37,671.15)TRACK IN CONCRETE FLOOR0292.010

Page 7 of 112

Page 8: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LF 430 $504.44 $216,909.20 $169.00 $72,670.00 ($335.44) ($144,239.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $121.00 $12,100.00 ($18.59) ($1,859.00)CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $1,000.00 $1,339,000.00 ($496.73) ($665,121.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $180,000.00 $180,000.00 ($122,979.67) ($122,979.67)PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $15.00 $4,200.00 ($31.20) ($8,736.00)CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $145,000.00 $145,000.00 ($240,080.43) ($240,080.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $25.00 $11,700.00 ($25.03) ($11,714.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $1.00 $5,000.00 ($1.40) ($7,000.00)MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $700,000.00 $700,000.00 $32,102.44 $32,102.44STRUCTURAL METAL0510.000

Page 8 of 112

Page 9: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LS 1 $373,581.61 $373,581.61 $317,030.00 $317,030.00 ($56,551.61) ($56,551.61)METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $220,030.00 $220,030.00 ($203,416.86) ($203,416.86)MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $15.40 $13,228.60 ($61.29) ($52,648.11)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $29.00 $1,624.00 ($179.03) ($10,025.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,148,290.00 $1,148,290.00 ($51,710.00) ($51,710.00)BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $12,000.00 $12,000.00 ($93,475.83) ($93,475.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $5,000.00 $5,000.00 ($10,597.79) ($10,597.79)ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $500.00 $2,000.00 ($621.33) ($2,485.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $1,775.00 $24,850.00 ($6,119.04) ($85,666.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 9 of 112

Page 10: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LS 1 $8,526.26 $8,526.26 $6,380.00 $6,380.00 ($2,146.26) ($2,146.26)COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $45,000.00 $45,000.00 $22,909.97 $22,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $5,500.00 $5,500.00 $719.82 $719.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $2,500.00 $2,500.00 ($133.71) ($133.71)TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $7,000.00 $7,000.00 ($4,188.02) ($4,188.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $7,500.00 $7,500.00 ($7,556.79) ($7,556.79)RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $32,000.00 $32,000.00 ($13,102.61) ($13,102.61)PAINTING0990.000

EA 4 $95.75 $383.00 $250.00 $1,000.00 $154.25 $617.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.75 $1,210.00 $0.40 $176.004" REFLECTORIZED WHITE LINE1040.700

Page 10 of 112

Page 11: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

LS 1 $19,461.89 $19,461.89 $13,000.00 $13,000.00 ($6,461.89) ($6,461.89)SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $15,500.00 $15,500.00 $1,478.46 $1,478.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $15,000.00 $15,000.00 ($60,351.74) ($60,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $1,500.00 $1,500.00 ($2,769.56) ($2,769.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $150,000.00 $150,000.00 $77,555.40 $77,555.40MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $410,000.00 $410,000.00 ($47,535.55) ($47,535.55)MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $331,000.00 $331,000.00 $25,740.66 $25,740.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $130,000.00 $130,000.00 ($21,937.35) ($21,937.35)FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $3.00 $900.00 ($11.23) ($3,369.00)ACTIVATED CARBON1597.422

Page 11 of 112

Page 12: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

DY 60 $213.48 $12,808.80 $50.00 $3,000.00 ($163.48) ($9,808.80)GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $800,000.00 $800,000.00 ($724,304.16) ($724,304.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $10,000.00 $10,000.00 ($12,308.27) ($12,308.27)ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $715,000.00 $715,000.00 ($268,596.90) ($268,596.90)TRACTION POWER WORK1696.113

$12,997,822.00 ($2,997,737.00)$15,995,559.00Total Estimate Contract Base Bid:

Page 12 of 112

Page 13: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $254,000.00 $254,000.00 ($143,957.35) ($143,957.35)ALTERNATE NO. 10001.100

$254,000.00 ($143,957.35)$397,957.35Subtotal Alternate # A01:

Page 13 of 112

Page 14: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $337,560.00 $337,560.00 ($165,672.63) ($165,672.63)ALTERNATE NO. 20001.200

$337,560.00 ($165,672.63)$503,232.63Subtotal Alternate # A02:

Page 14 of 112

Page 15: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

A

11/27/2007

S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $101,200.00 $101,200.00 $58,185.10 $58,185.10ALTERNATE NO. 30001.300

$101,200.00 $58,185.10$43,014.90Subtotal Alternate # A03:

$13,690,582.00 ($3,249,181.88)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 15 of 112

Page 16: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $120,000.00 $120,000.00 ($90,178.08) ($90,178.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $120,000.00 $120,000.00 ($63,908.55) ($63,908.55)MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $50,000.00 $50,000.00 $36,445.85 $36,445.85CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $200,000.00 $200,000.00 ($443,796.35) ($443,796.35)DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $1.00 $5,000.00 ($4.84) ($24,200.00)PATCHING AND REPAIRING0211.003

Page 16 of 112

Page 17: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LS 1 $1,148,821.95 $1,148,821.95 $1,200,000.00 $1,200,000.00 $51,178.05 $51,178.05CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $10,000.00 $10,000.00 ($82,238.34) ($82,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $35.00 $159,075.00 ($44.52) ($202,343.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $45.00 $76,230.00 ($88.57) ($150,037.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $100.00 $11,400.00 ($222.28) ($25,339.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $81.00 $283,500.00 $24.89 $87,115.00UNCLASSIFIED EXCAVATION0222.003

Page 17 of 112

Page 18: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

CY 440 $15.17 $6,674.80 $27.00 $11,880.00 $11.83 $5,205.20TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $220.00 $50,160.00 ($49.20) ($11,217.60)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $20.00 $20,000.00 ($13.63) ($13,630.00)SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $180.00 $18,000.00 $151.95 $15,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $2.00 $20,000.00 $1.28 $12,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $27.00 $8,100.00 $3.36 $1,008.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $54.00 $41,202.00 $27.00 $20,601.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $500.00 $1,500.00 $152.73 $458.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $54.00 $17,442.00 $0.85 $274.55CRUSHED STONE FORDRAIN REVET

0222.603

Page 18 of 112

Page 19: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

TN 120 $31.67 $3,800.40 $54.00 $6,480.00 $22.33 $2,679.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $54.00 $9,666.00 ($3.31) ($592.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $54.00 $10,152.00 $37.00 $6,956.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $3.00 $7,386.00 ($3.76) ($9,257.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $0.20 $3,420.00 ($2.54) ($43,434.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $1,000.00 $6,000.00 $434.01 $2,604.06BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $600.00 $508,800.00 ($1,243.87) ($1,054,801.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $40.00 $28,600.00 $22.60 $16,159.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $60.00 $1,200.00 $24.33 $486.608" PVC PIPE0251.591

Page 19 of 112

Page 20: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LF 20 $123.85 $2,477.00 $100.00 $2,000.00 ($23.85) ($477.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $120.00 $12,000.00 ($162.66) ($16,266.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $120.00 $22,560.00 $69.13 $12,996.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $300.00 $25,200.00 $225.64 $18,953.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $50,000.00 $100,000.00 $10,719.83 $21,439.66OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $800.00 $1,600.00 $393.23 $786.46CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $100.00 $2,400.00 ($159.35) ($3,824.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $100.00 $25,000.00 $76.51 $19,127.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $70.00 $10,360.00 ($23.06) ($3,412.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 20 of 112

Page 21: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

TN 148 $101.52 $15,024.96 $70.00 $10,360.00 ($31.52) ($4,664.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $70.00 $23,240.00 $8.58 $2,848.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $200.00 $12,200.00 ($994.27) ($60,650.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $35.00 $13,650.00 ($3.32) ($1,294.80)72" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $1.00 $2,118.00 ($0.12) ($254.16)SEEDING0282.150

LF 310 $5.31 $1,646.10 $10.00 $3,100.00 $4.69 $1,453.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $3.00 $930.00 ($2.73) ($846.30)SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $27.00 $2,700.00 ($1.46) ($146.00)TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $12,000.00 $12,000.00 ($26,532.35) ($26,532.35)PLANTING0284.145

Page 21 of 112

Page 22: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

EA 3 $86,506.15 $259,518.45 $50,000.00 $150,000.00 ($36,506.15) ($109,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $250.00 $98,750.00 ($275.17) ($108,692.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $50.00 $9,000.00 ($1.79) ($322.20)RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $50.00 $19,750.00 ($1.79) ($707.05)SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $50.00 $59,050.00 ($7.71) ($9,105.51)DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $100,000.00 $100,000.00 ($25,183.00) ($25,183.00)SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $100.00 $6,900.00 ($404.44) ($27,906.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $1,000.00 $4,000.00 $495.56 $1,982.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $250.00 $98,750.00 ($90.37) ($35,696.15)TRACK IN CONCRETE FLOOR0292.010

Page 22 of 112

Page 23: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LF 430 $504.44 $216,909.20 $250.00 $107,500.00 ($254.44) ($109,409.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $200.00 $20,000.00 $60.41 $6,041.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $1,200.00 $1,606,800.00 ($296.73) ($397,321.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $400,000.00 $400,000.00 $97,020.33 $97,020.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $10.00 $2,800.00 ($36.20) ($10,136.00)CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $200,000.00 $200,000.00 ($185,080.43) ($185,080.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $24.00 $11,232.00 ($26.03) ($12,182.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $1.00 $5,000.00 ($1.40) ($7,000.00)MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $1,700,000.00 $1,700,000.00 $1,032,102.44 $1,032,102.44STRUCTURAL METAL0510.000

Page 23 of 112

Page 24: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LS 1 $373,581.61 $373,581.61 $480,000.00 $480,000.00 $106,418.39 $106,418.39METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $430,000.00 $430,000.00 $6,553.14 $6,553.14MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $30.00 $25,770.00 ($46.69) ($40,106.71)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $130.00 $7,280.00 ($78.03) ($4,369.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $2,000,000.00 $2,000,000.00 $800,000.00 $800,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $10,000.00 $10,000.00 ($95,475.83) ($95,475.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $10,000.00 $10,000.00 ($5,597.79) ($5,597.79)ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $500.00 $2,000.00 ($621.33) ($2,485.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $2,500.00 $35,000.00 ($5,394.04) ($75,516.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 24 of 112

Page 25: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LS 1 $8,526.26 $8,526.26 $5,000.00 $5,000.00 ($3,526.26) ($3,526.26)COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $80,000.00 $80,000.00 $57,909.97 $57,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $20,000.00 $20,000.00 $15,219.82 $15,219.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $6,000.00 $6,000.00 $3,366.29 $3,366.29TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $10,000.00 $10,000.00 ($1,188.02) ($1,188.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $10,000.00 $10,000.00 ($5,056.79) ($5,056.79)RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $70,000.00 $70,000.00 $24,897.39 $24,897.39PAINTING0990.000

EA 4 $95.75 $383.00 $200.00 $800.00 $104.25 $417.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.00 $880.00 ($0.35) ($154.00)4" REFLECTORIZED WHITE LINE1040.700

Page 25 of 112

Page 26: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

LS 1 $19,461.89 $19,461.89 $30,000.00 $30,000.00 $10,538.11 $10,538.11SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $15,000.00 $15,000.00 $978.46 $978.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $10,000.00 $10,000.00 ($65,351.74) ($65,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $1,000.00 $1,000.00 ($3,269.56) ($3,269.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $100,000.00 $100,000.00 $27,555.40 $27,555.40MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $800,000.00 $800,000.00 $342,464.45 $342,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $800,000.00 $800,000.00 $494,740.66 $494,740.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $200,000.00 $200,000.00 $48,062.65 $48,062.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $5.00 $1,500.00 ($9.23) ($2,769.00)ACTIVATED CARBON1597.422

Page 26 of 112

Page 27: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

DY 60 $213.48 $12,808.80 $500.00 $30,000.00 $286.52 $17,191.20GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $900,000.00 $900,000.00 ($624,304.16) ($624,304.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $20,000.00 $20,000.00 ($2,308.27) ($2,308.27)ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $530,000.00 $530,000.00 ($453,596.90) ($453,596.90)TRACTION POWER WORK1696.113

$14,669,109.21 ($1,326,449.79)$15,995,559.00Total Estimate Contract Base Bid:

Page 27 of 112

Page 28: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $346,000.00 $346,000.00 ($51,957.35) ($51,957.35)ALTERNATE NO. 10001.100

$346,000.00 ($51,957.35)$397,957.35Subtotal Alternate # A01:

Page 28 of 112

Page 29: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $580,000.00 $580,000.00 $76,767.37 $76,767.37ALTERNATE NO. 20001.200

$580,000.00 $76,767.37$503,232.63Subtotal Alternate # A02:

Page 29 of 112

Page 30: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

B

11/27/2007

McCOURT CONSTRUCTION CO., INC.

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $215,000.00 $215,000.00 $171,985.10 $171,985.10ALTERNATE NO. 30001.300

$215,000.00 $171,985.10$43,014.90Subtotal Alternate # A03:

$15,810,109.21 ($1,129,654.67)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 30 of 112

Page 31: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $190,685.00 $190,685.00 ($19,493.08) ($19,493.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $158,651.00 $158,651.00 ($25,257.55) ($25,257.55)MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $162,000.00 $162,000.00 $148,445.85 $148,445.85CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $402,800.00 $402,800.00 ($240,996.35) ($240,996.35)DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $17.00 $85,000.00 $11.16 $55,800.00PATCHING AND REPAIRING0211.003

Page 31 of 112

Page 32: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LS 1 $1,148,821.95 $1,148,821.95 $1,345,500.00 $1,345,500.00 $196,678.05 $196,678.05CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $55,000.00 $55,000.00 ($37,238.34) ($37,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $33.00 $149,985.00 ($46.52) ($211,433.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $39.00 $66,066.00 ($94.57) ($160,201.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $94.00 $10,716.00 ($228.28) ($26,023.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $65.00 $227,500.00 $8.89 $31,115.00UNCLASSIFIED EXCAVATION0222.003

Page 32 of 112

Page 33: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

CY 440 $15.17 $6,674.80 $43.00 $18,920.00 $27.83 $12,245.20TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $330.00 $75,240.00 $60.80 $13,862.40DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $88.00 $88,000.00 $54.37 $54,370.00SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $149.00 $14,900.00 $120.95 $12,095.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $1.00 $10,000.00 $0.28 $2,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $30.00 $9,000.00 $6.36 $1,908.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $42.00 $32,046.00 $15.00 $11,445.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $649.00 $1,947.00 $301.73 $905.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $27.00 $8,721.00 ($26.15) ($8,446.45)CRUSHED STONE FORDRAIN REVET

0222.603

Page 33 of 112

Page 34: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

TN 120 $31.67 $3,800.40 $66.00 $7,920.00 $34.33 $4,119.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $51.00 $9,129.00 ($6.31) ($1,129.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $20.00 $3,760.00 $3.00 $564.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $2.00 $4,924.00 ($4.76) ($11,719.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $1.00 $17,100.00 ($1.74) ($29,754.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $880.00 $5,280.00 $314.01 $1,884.06BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $1,115.00 $945,520.00 ($728.87) ($618,081.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $44.00 $31,460.00 $26.60 $19,019.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $62.00 $1,240.00 $26.33 $526.608" PVC PIPE0251.591

Page 34 of 112

Page 35: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LF 20 $123.85 $2,477.00 $79.00 $1,580.00 ($44.85) ($897.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $121.00 $12,100.00 ($161.66) ($16,166.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $106.00 $19,928.00 $55.13 $10,364.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $605.00 $50,820.00 $530.64 $44,573.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $19,800.00 $39,600.00 ($19,480.17) ($38,960.34)OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $396.00 $792.00 ($10.77) ($21.54)CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $149.00 $3,576.00 ($110.35) ($2,648.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $47.00 $11,750.00 $23.51 $5,877.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $88.00 $13,024.00 ($5.06) ($748.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 35 of 112

Page 36: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

TN 148 $101.52 $15,024.96 $88.00 $13,024.00 ($13.52) ($2,000.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $88.00 $29,216.00 $26.58 $8,824.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $587.00 $35,807.00 ($607.27) ($37,043.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $54.00 $21,060.00 $15.68 $6,115.2072" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $2.00 $4,236.00 $0.88 $1,863.84SEEDING0282.150

LF 310 $5.31 $1,646.10 $8.00 $2,480.00 $2.69 $833.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $10.00 $3,100.00 $4.27 $1,323.70SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $50.00 $5,000.00 $21.54 $2,154.00TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $23,100.00 $23,100.00 ($15,432.35) ($15,432.35)PLANTING0284.145

Page 36 of 112

Page 37: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

EA 3 $86,506.15 $259,518.45 $44,000.00 $132,000.00 ($42,506.15) ($127,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $374.00 $147,730.00 ($151.17) ($59,712.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $33.00 $5,940.00 ($18.79) ($3,382.20)RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $50.00 $19,750.00 ($1.79) ($707.05)SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $55.00 $64,955.00 ($2.71) ($3,200.51)DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $165,000.00 $165,000.00 $39,817.00 $39,817.00SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $440.00 $30,360.00 ($64.44) ($4,446.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $2,250.00 $9,000.00 $1,745.56 $6,982.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $495.00 $195,525.00 $154.63 $61,078.85TRACK IN CONCRETE FLOOR0292.010

Page 37 of 112

Page 38: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LF 430 $504.44 $216,909.20 $275.00 $118,250.00 ($229.44) ($98,659.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $495.00 $49,500.00 $355.41 $35,541.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $766.00 $1,025,674.00 ($730.73) ($978,447.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $634,700.00 $634,700.00 $331,720.33 $331,720.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $33.00 $9,240.00 ($13.20) ($3,696.00)CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $171,600.00 $171,600.00 ($213,480.43) ($213,480.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $29.00 $13,572.00 ($21.03) ($9,842.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $7.00 $35,000.00 $4.60 $23,000.00MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $1,278,366.00 $1,278,366.00 $610,468.44 $610,468.44STRUCTURAL METAL0510.000

Page 38 of 112

Page 39: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LS 1 $373,581.61 $373,581.61 $305,800.00 $305,800.00 ($67,781.61) ($67,781.61)METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $408,100.00 $408,100.00 ($15,346.86) ($15,346.86)MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $41.00 $35,219.00 ($35.69) ($30,657.71)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $172.00 $9,632.00 ($36.03) ($2,017.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,254,000.00 $1,254,000.00 $54,000.00 $54,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $41,358.00 $41,358.00 ($64,117.83) ($64,117.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $20,617.00 $20,617.00 $5,019.21 $5,019.21ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $550.00 $2,200.00 ($571.33) ($2,285.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $2,750.00 $38,500.00 ($5,144.04) ($72,016.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 39 of 112

Page 40: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LS 1 $8,526.26 $8,526.26 $9,350.00 $9,350.00 $823.74 $823.74COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $66,000.00 $66,000.00 $43,909.97 $43,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $16,500.00 $16,500.00 $11,719.82 $11,719.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $5,500.00 $5,500.00 $2,866.29 $2,866.29TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $2,420.00 $2,420.00 ($8,768.02) ($8,768.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $16,500.00 $16,500.00 $1,443.21 $1,443.21RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $123,464.00 $123,464.00 $78,361.39 $78,361.39PAINTING0990.000

EA 4 $95.75 $383.00 $330.00 $1,320.00 $234.25 $937.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $3.00 $1,320.00 $0.65 $286.004" REFLECTORIZED WHITE LINE1040.700

Page 40 of 112

Page 41: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

LS 1 $19,461.89 $19,461.89 $49,500.00 $49,500.00 $30,038.11 $30,038.11SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $20,625.00 $20,625.00 $6,603.46 $6,603.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $16,907.00 $16,907.00 ($58,444.74) ($58,444.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $1,650.00 $1,650.00 ($2,619.56) ($2,619.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $80,500.00 $80,500.00 $8,055.40 $8,055.40MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $855,000.00 $855,000.00 $397,464.45 $397,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $840,972.00 $840,972.00 $535,712.66 $535,712.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $226,600.00 $226,600.00 $74,662.65 $74,662.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $4.00 $1,200.00 ($10.23) ($3,069.00)ACTIVATED CARBON1597.422

Page 41 of 112

Page 42: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

DY 60 $213.48 $12,808.80 $660.00 $39,600.00 $446.52 $26,791.20GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $1,020,800.00 $1,020,800.00 ($503,504.16) ($503,504.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $27,500.00 $27,500.00 $5,191.73 $5,191.73ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $764,500.00 $764,500.00 ($219,096.90) ($219,096.90)TRACTION POWER WORK1696.113

$14,981,255.21 ($1,014,303.79)$15,995,559.00Total Estimate Contract Base Bid:

Page 42 of 112

Page 43: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $353,920.00 $353,920.00 ($44,037.35) ($44,037.35)ALTERNATE NO. 10001.100

$353,920.00 ($44,037.35)$397,957.35Subtotal Alternate # A01:

Page 43 of 112

Page 44: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $399,537.60 $399,537.60 ($103,695.03) ($103,695.03)ALTERNATE NO. 20001.200

$399,537.60 ($103,695.03)$503,232.63Subtotal Alternate # A02:

Page 44 of 112

Page 45: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

C

11/27/2007

W.T. RICH COMPANY, INC.

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $76,160.00 $76,160.00 $33,145.10 $33,145.10ALTERNATE NO. 30001.300

$76,160.00 $33,145.10$43,014.90Subtotal Alternate # A03:

$15,810,872.81 ($1,128,891.07)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 45 of 112

Page 46: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $150,000.00 $150,000.00 ($60,178.08) ($60,178.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $215,000.00 $215,000.00 $31,091.45 $31,091.45MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $75,000.00 $75,000.00 $61,445.85 $61,445.85CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $384,699.79 $384,699.79 ($259,096.56) ($259,096.56)DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $3.00 $15,000.00 ($2.84) ($14,200.00)PATCHING AND REPAIRING0211.003

Page 46 of 112

Page 47: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LS 1 $1,148,821.95 $1,148,821.95 $1,000,000.00 $1,000,000.00 ($148,821.95) ($148,821.95)CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $50,000.00 $50,000.00 ($42,238.34) ($42,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $40.00 $181,800.00 ($39.52) ($179,618.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $65.00 $110,110.00 ($68.57) ($116,157.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $125.00 $14,250.00 ($197.28) ($22,489.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $30.00 $105,000.00 ($26.11) ($91,385.00)UNCLASSIFIED EXCAVATION0222.003

Page 47 of 112

Page 48: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

CY 440 $15.17 $6,674.80 $25.00 $11,000.00 $9.83 $4,325.20TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $265.00 $60,420.00 ($4.20) ($957.60)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $65.00 $65,000.00 $31.37 $31,370.00SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $60.00 $6,000.00 $31.95 $3,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $1.00 $10,000.00 $0.28 $2,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $30.00 $9,000.00 $6.36 $1,908.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $40.00 $30,520.00 $13.00 $9,919.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $500.00 $1,500.00 $152.73 $458.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $50.00 $16,150.00 ($3.15) ($1,017.45)CRUSHED STONE FORDRAIN REVET

0222.603

Page 48 of 112

Page 49: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

TN 120 $31.67 $3,800.40 $45.00 $5,400.00 $13.33 $1,599.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $50.00 $8,950.00 ($7.31) ($1,308.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $30.00 $5,640.00 $13.00 $2,444.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $2.50 $6,155.00 ($4.26) ($10,488.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $1.00 $17,100.00 ($1.74) ($29,754.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $1,200.00 $7,200.00 $634.01 $3,804.06BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $1,200.00 $1,017,600.00 ($643.87) ($546,001.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $35.00 $25,025.00 $17.60 $12,584.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $60.00 $1,200.00 $24.33 $486.608" PVC PIPE0251.591

Page 49 of 112

Page 50: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LF 20 $123.85 $2,477.00 $60.00 $1,200.00 ($63.85) ($1,277.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $90.00 $9,000.00 ($192.66) ($19,266.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $95.00 $17,860.00 $44.13 $8,296.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $350.00 $29,400.00 $275.64 $23,153.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $40,000.00 $80,000.00 $719.83 $1,439.66OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $1,900.00 $3,800.00 $1,493.23 $2,986.46CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $120.00 $2,880.00 ($139.35) ($3,344.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $65.00 $16,250.00 $41.51 $10,377.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $75.00 $11,100.00 ($18.06) ($2,672.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 50 of 112

Page 51: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

TN 148 $101.52 $15,024.96 $75.00 $11,100.00 ($26.52) ($3,924.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $75.00 $24,900.00 $13.58 $4,508.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $300.00 $18,300.00 ($894.27) ($54,550.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $50.00 $19,500.00 $11.68 $4,555.2072" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $3.00 $6,354.00 $1.88 $3,981.84SEEDING0282.150

LF 310 $5.31 $1,646.10 $6.00 $1,860.00 $0.69 $213.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $10.00 $3,100.00 $4.27 $1,323.70SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $60.00 $6,000.00 $31.54 $3,154.00TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $35,000.00 $35,000.00 ($3,532.35) ($3,532.35)PLANTING0284.145

Page 51 of 112

Page 52: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

EA 3 $86,506.15 $259,518.45 $50,000.00 $150,000.00 ($36,506.15) ($109,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $500.00 $197,500.00 ($25.17) ($9,942.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $60.00 $10,800.00 $8.21 $1,477.80RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $60.00 $23,700.00 $8.21 $3,242.95SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $60.00 $70,860.00 $2.29 $2,704.49DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $165,000.00 $165,000.00 $39,817.00 $39,817.00SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $500.00 $34,500.00 ($4.44) ($306.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $600.00 $2,400.00 $95.56 $382.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $400.00 $158,000.00 $59.63 $23,553.85TRACK IN CONCRETE FLOOR0292.010

Page 52 of 112

Page 53: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LF 430 $504.44 $216,909.20 $250.00 $107,500.00 ($254.44) ($109,409.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $250.00 $25,000.00 $110.41 $11,041.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $1,125.00 $1,506,375.00 ($371.73) ($497,746.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $500,000.00 $500,000.00 $197,020.33 $197,020.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $45.00 $12,600.00 ($1.20) ($336.00)CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $130,000.00 $130,000.00 ($255,080.43) ($255,080.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $50.00 $23,400.00 ($0.03) ($14.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $5.00 $25,000.00 $2.60 $13,000.00MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $1,500,000.00 $1,500,000.00 $832,102.44 $832,102.44STRUCTURAL METAL0510.000

Page 53 of 112

Page 54: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LS 1 $373,581.61 $373,581.61 $300,000.00 $300,000.00 ($73,581.61) ($73,581.61)METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $500,000.00 $500,000.00 $76,553.14 $76,553.14MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $75.00 $64,425.00 ($1.69) ($1,451.71)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $125.00 $7,000.00 ($83.03) ($4,649.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,500,000.00 $1,500,000.00 $300,000.00 $300,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $40,000.00 $40,000.00 ($65,475.83) ($65,475.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $20,000.00 $20,000.00 $4,402.21 $4,402.21ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $1,000.00 $4,000.00 ($121.33) ($485.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $2,500.00 $35,000.00 ($5,394.04) ($75,516.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 54 of 112

Page 55: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LS 1 $8,526.26 $8,526.26 $25,000.00 $25,000.00 $16,473.74 $16,473.74COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $75,000.00 $75,000.00 $52,909.97 $52,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $15,000.00 $15,000.00 $10,219.82 $10,219.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $2,500.00 $2,500.00 ($133.71) ($133.71)TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $6,500.00 $6,500.00 ($4,688.02) ($4,688.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $16,000.00 $16,000.00 $943.21 $943.21RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $125,000.00 $125,000.00 $79,897.39 $79,897.39PAINTING0990.000

EA 4 $95.75 $383.00 $250.00 $1,000.00 $154.25 $617.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.00 $880.00 ($0.35) ($154.00)4" REFLECTORIZED WHITE LINE1040.700

Page 55 of 112

Page 56: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

LS 1 $19,461.89 $19,461.89 $15,000.00 $15,000.00 ($4,461.89) ($4,461.89)SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $20,000.00 $20,000.00 $5,978.46 $5,978.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $25,000.00 $25,000.00 ($50,351.74) ($50,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $4,000.00 $4,000.00 ($269.56) ($269.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $25,000.00 $25,000.00 ($47,444.60) ($47,444.60)MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $1,000,000.00 $1,000,000.00 $542,464.45 $542,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $600,000.00 $600,000.00 $294,740.66 $294,740.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $210,000.00 $210,000.00 $58,062.65 $58,062.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $10.00 $3,000.00 ($4.23) ($1,269.00)ACTIVATED CARBON1597.422

Page 56 of 112

Page 57: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

DY 60 $213.48 $12,808.80 $375.00 $22,500.00 $161.52 $9,691.20GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $1,000,000.00 $1,000,000.00 ($524,304.16) ($524,304.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $50,000.00 $50,000.00 $27,691.73 $27,691.73ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $750,000.00 $750,000.00 ($233,596.90) ($233,596.90)TRACTION POWER WORK1696.113

$15,149,500.00 ($846,059.00)$15,995,559.00Total Estimate Contract Base Bid:

Page 57 of 112

Page 58: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $320,000.00 $320,000.00 ($77,957.35) ($77,957.35)ALTERNATE NO. 10001.100

$320,000.00 ($77,957.35)$397,957.35Subtotal Alternate # A01:

Page 58 of 112

Page 59: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $630,000.00 $630,000.00 $126,767.37 $126,767.37ALTERNATE NO. 20001.200

$630,000.00 $126,767.37$503,232.63Subtotal Alternate # A02:

Page 59 of 112

Page 60: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

D

11/27/2007

BARLETTA HEAVY DIVISION, INC.

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $75,000.00 $75,000.00 $31,985.10 $31,985.10ALTERNATE NO. 30001.300

$75,000.00 $31,985.10$43,014.90Subtotal Alternate # A03:

$16,174,500.00 ($765,263.88)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 60 of 112

Page 61: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $30,000.00 $30,000.00 ($180,178.08) ($180,178.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $2,950,436.00 $2,950,436.00 $2,766,527.45 $2,766,527.45MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $13,344.00 $13,344.00 ($210.15) ($210.15)CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $598,796.00 $598,796.00 ($45,000.35) ($45,000.35)DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $3.00 $15,000.00 ($2.84) ($14,200.00)PATCHING AND REPAIRING0211.003

Page 61 of 112

Page 62: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LS 1 $1,148,821.95 $1,148,821.95 $1,078,800.00 $1,078,800.00 ($70,021.95) ($70,021.95)CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $90,812.00 $90,812.00 ($1,426.34) ($1,426.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $31.00 $140,895.00 ($48.52) ($220,523.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $50.00 $84,700.00 ($83.57) ($141,567.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $80.00 $9,120.00 ($242.28) ($27,619.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $22.50 $78,750.00 ($33.61) ($117,635.00)UNCLASSIFIED EXCAVATION0222.003

Page 62 of 112

Page 63: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

CY 440 $15.17 $6,674.80 $20.00 $8,800.00 $4.83 $2,125.20TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $210.00 $47,880.00 ($59.20) ($13,497.60)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $35.00 $35,000.00 $1.37 $1,370.00SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $40.00 $4,000.00 $11.95 $1,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $0.90 $9,000.00 $0.18 $1,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $30.00 $9,000.00 $6.36 $1,908.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $35.00 $26,705.00 $8.00 $6,104.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $400.00 $1,200.00 $52.73 $158.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $30.00 $9,690.00 ($23.15) ($7,477.45)CRUSHED STONE FORDRAIN REVET

0222.603

Page 63 of 112

Page 64: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

TN 120 $31.67 $3,800.40 $30.00 $3,600.00 ($1.67) ($200.40)STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $30.00 $5,370.00 ($27.31) ($4,888.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $30.00 $5,640.00 $13.00 $2,444.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $1.00 $2,462.00 ($5.76) ($14,181.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $0.60 $10,260.00 ($2.14) ($36,594.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $600.00 $3,600.00 $34.01 $204.06BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $662.00 $561,376.00 ($1,181.87) ($1,002,225.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $60.00 $42,900.00 $42.60 $30,459.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $50.00 $1,000.00 $14.33 $286.608" PVC PIPE0251.591

Page 64 of 112

Page 65: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LF 20 $123.85 $2,477.00 $50.00 $1,000.00 ($73.85) ($1,477.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $50.00 $5,000.00 ($232.66) ($23,266.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $50.00 $9,400.00 ($0.87) ($163.56)8" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $400.00 $33,600.00 $325.64 $27,353.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $20,000.00 $40,000.00 ($19,280.17) ($38,560.34)OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $1,500.00 $3,000.00 $1,093.23 $2,186.46CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $120.00 $2,880.00 ($139.35) ($3,344.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $25.00 $6,250.00 $1.51 $377.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $70.00 $10,360.00 ($23.06) ($3,412.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 65 of 112

Page 66: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

TN 148 $101.52 $15,024.96 $70.00 $10,360.00 ($31.52) ($4,664.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $80.00 $26,560.00 $18.58 $6,168.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $500.00 $30,500.00 ($694.27) ($42,350.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $50.00 $19,500.00 $11.68 $4,555.2072" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $3.00 $6,354.00 $1.88 $3,981.84SEEDING0282.150

LF 310 $5.31 $1,646.10 $8.00 $2,480.00 $2.69 $833.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $7.00 $2,170.00 $1.27 $393.70SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $25.00 $2,500.00 ($3.46) ($346.00)TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $21,000.00 $21,000.00 ($17,532.35) ($17,532.35)PLANTING0284.145

Page 66 of 112

Page 67: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

EA 3 $86,506.15 $259,518.45 $18,000.00 $54,000.00 ($68,506.15) ($205,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $270.00 $106,650.00 ($255.17) ($100,792.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $120.00 $21,600.00 $68.21 $12,277.80RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $270.00 $106,650.00 $218.21 $86,192.95SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $50.00 $59,050.00 ($7.71) ($9,105.51)DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $103,000.00 $103,000.00 ($22,183.00) ($22,183.00)SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $180.00 $12,420.00 ($324.44) ($22,386.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $1,800.00 $7,200.00 $1,295.56 $5,182.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $270.00 $106,650.00 ($70.37) ($27,796.15)TRACK IN CONCRETE FLOOR0292.010

Page 67 of 112

Page 68: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LF 430 $504.44 $216,909.20 $270.00 $116,100.00 ($234.44) ($100,809.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $300.00 $30,000.00 $160.41 $16,041.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $672.00 $899,808.00 ($824.73) ($1,104,313.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $577,000.00 $577,000.00 $274,020.33 $274,020.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $50.00 $14,000.00 $3.80 $1,064.00CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $156,000.00 $156,000.00 ($229,080.43) ($229,080.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $26.00 $12,168.00 ($24.03) ($11,246.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $5.50 $27,500.00 $3.10 $15,500.00MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $1,025,000.00 $1,025,000.00 $357,102.44 $357,102.44STRUCTURAL METAL0510.000

Page 68 of 112

Page 69: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LS 1 $373,581.61 $373,581.61 $188,000.00 $188,000.00 ($185,581.61) ($185,581.61)METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $430,634.00 $430,634.00 $7,187.14 $7,187.14MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $30.00 $25,770.00 ($46.69) ($40,106.71)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $40.00 $2,240.00 ($168.03) ($9,409.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,340,000.00 $1,340,000.00 $140,000.00 $140,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $20,000.00 $20,000.00 ($85,475.83) ($85,475.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $5,000.00 $5,000.00 ($10,597.79) ($10,597.79)ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $1,000.00 $4,000.00 ($121.33) ($485.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $1,000.00 $14,000.00 ($6,894.04) ($96,516.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 69 of 112

Page 70: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LS 1 $8,526.26 $8,526.26 $10,000.00 $10,000.00 $1,473.74 $1,473.74COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $56,700.00 $56,700.00 $34,609.97 $34,609.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $10,000.00 $10,000.00 $5,219.82 $5,219.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $2,000.00 $2,000.00 ($633.71) ($633.71)TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $2,200.00 $2,200.00 ($8,988.02) ($8,988.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $12,000.00 $12,000.00 ($3,056.79) ($3,056.79)RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $44,405.00 $44,405.00 ($697.61) ($697.61)PAINTING0990.000

EA 4 $95.75 $383.00 $200.00 $800.00 $104.25 $417.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.00 $880.00 ($0.35) ($154.00)4" REFLECTORIZED WHITE LINE1040.700

Page 70 of 112

Page 71: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

LS 1 $19,461.89 $19,461.89 $11,000.00 $11,000.00 ($8,461.89) ($8,461.89)SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $18,750.00 $18,750.00 $4,728.46 $4,728.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $28,000.00 $28,000.00 ($47,351.74) ($47,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $2,000.00 $2,000.00 ($2,269.56) ($2,269.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $65,324.00 $65,324.00 ($7,120.60) ($7,120.60)MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $750,000.00 $750,000.00 $292,464.45 $292,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $531,000.00 $531,000.00 $225,740.66 $225,740.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $224,000.00 $224,000.00 $72,062.65 $72,062.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $2.50 $750.00 ($11.73) ($3,519.00)ACTIVATED CARBON1597.422

Page 71 of 112

Page 72: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

DY 60 $213.48 $12,808.80 $1,000.00 $60,000.00 $786.52 $47,191.20GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $1,200,478.00 $1,200,478.00 ($323,826.16) ($323,826.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $10,246.00 $10,246.00 ($12,062.27) ($12,062.27)ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $922,840.00 $922,840.00 ($60,756.90) ($60,756.90)TRACTION POWER WORK1696.113

$15,681,599.21 ($313,959.79)$15,995,559.00Total Estimate Contract Base Bid:

Page 72 of 112

Page 73: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $410,000.00 $410,000.00 $12,042.65 $12,042.65ALTERNATE NO. 10001.100

$410,000.00 $12,042.65$397,957.35Subtotal Alternate # A01:

Page 73 of 112

Page 74: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $450,000.00 $450,000.00 ($53,232.63) ($53,232.63)ALTERNATE NO. 20001.200

$450,000.00 ($53,232.63)$503,232.63Subtotal Alternate # A02:

Page 74 of 112

Page 75: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

E

11/27/2007

J & J CONTRACTORS, INC.

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $220,000.00 $220,000.00 $176,985.10 $176,985.10ALTERNATE NO. 30001.300

$220,000.00 $176,985.10$43,014.90Subtotal Alternate # A03:

$16,761,599.21 ($178,164.67)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 75 of 112

Page 76: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $80,000.00 $80,000.00 ($130,178.08) ($130,178.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $350,000.00 $350,000.00 $166,091.45 $166,091.45MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $125,000.00 $125,000.00 $111,445.85 $111,445.85CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $1,250,000.00 $1,250,000.00 $606,203.65 $606,203.65DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $40.00 $200,000.00 $34.16 $170,800.00PATCHING AND REPAIRING0211.003

Page 76 of 112

Page 77: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LS 1 $1,148,821.95 $1,148,821.95 $1,000,000.00 $1,000,000.00 ($148,821.95) ($148,821.95)CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $50,000.00 $50,000.00 ($42,238.34) ($42,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $25.00 $113,625.00 ($54.52) ($247,793.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $50.00 $84,700.00 ($83.57) ($141,567.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $50.00 $5,700.00 ($272.28) ($31,039.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $45.00 $157,500.00 ($11.11) ($38,885.00)UNCLASSIFIED EXCAVATION0222.003

Page 77 of 112

Page 78: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

CY 440 $15.17 $6,674.80 $15.00 $6,600.00 ($0.17) ($74.80)TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $210.00 $47,880.00 ($59.20) ($13,497.60)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $30.00 $30,000.00 ($3.63) ($3,630.00)SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $100.00 $10,000.00 $71.95 $7,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $1.00 $10,000.00 $0.28 $2,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $35.00 $10,500.00 $11.36 $3,408.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $45.00 $34,335.00 $18.00 $13,734.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $250.00 $750.00 ($97.27) ($291.81)FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $30.00 $9,690.00 ($23.15) ($7,477.45)CRUSHED STONE FORDRAIN REVET

0222.603

Page 78 of 112

Page 79: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

TN 120 $31.67 $3,800.40 $100.00 $12,000.00 $68.33 $8,199.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $50.00 $8,950.00 ($7.31) ($1,308.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $40.00 $7,520.00 $23.00 $4,324.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $2.00 $4,924.00 ($4.76) ($11,719.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $0.50 $8,550.00 ($2.24) ($38,304.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $500.00 $3,000.00 ($65.99) ($395.94)BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $1,000.00 $848,000.00 ($843.87) ($715,601.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $30.00 $21,450.00 $12.60 $9,009.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $120.00 $2,400.00 $84.33 $1,686.608" PVC PIPE0251.591

Page 79 of 112

Page 80: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LF 20 $123.85 $2,477.00 $95.00 $1,900.00 ($28.85) ($577.00)6" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $110.00 $11,000.00 ($172.66) ($17,266.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $55.00 $10,340.00 $4.13 $776.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $500.00 $42,000.00 $425.64 $35,753.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $5,500.00 $11,000.00 ($33,780.17) ($67,560.34)OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $100.00 $200.00 ($306.77) ($613.54)CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $150.00 $3,600.00 ($109.35) ($2,624.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $120.00 $30,000.00 $96.51 $24,127.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $75.00 $11,100.00 ($18.06) ($2,672.88)CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 80 of 112

Page 81: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

TN 148 $101.52 $15,024.96 $80.00 $11,840.00 ($21.52) ($3,184.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $80.00 $26,560.00 $18.58 $6,168.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $500.00 $30,500.00 ($694.27) ($42,350.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $50.00 $19,500.00 $11.68 $4,555.2072" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $2.00 $4,236.00 $0.88 $1,863.84SEEDING0282.150

LF 310 $5.31 $1,646.10 $6.00 $1,860.00 $0.69 $213.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $9.00 $2,790.00 $3.27 $1,013.70SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $40.00 $4,000.00 $11.54 $1,154.00TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $10,000.00 $10,000.00 ($28,532.35) ($28,532.35)PLANTING0284.145

Page 81 of 112

Page 82: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

EA 3 $86,506.15 $259,518.45 $35,000.00 $105,000.00 ($51,506.15) ($154,518.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $200.00 $79,000.00 ($325.17) ($128,442.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $175.00 $31,500.00 $123.21 $22,177.80RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $75.00 $29,625.00 $23.21 $9,167.95SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $30.00 $35,430.00 ($27.71) ($32,725.51)DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $80,000.00 $80,000.00 ($45,183.00) ($45,183.00)SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $750.00 $51,750.00 $245.56 $16,943.64RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $3,000.00 $12,000.00 $2,495.56 $9,982.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $550.00 $217,250.00 $209.63 $82,803.85TRACK IN CONCRETE FLOOR0292.010

Page 82 of 112

Page 83: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LF 430 $504.44 $216,909.20 $200.00 $86,000.00 ($304.44) ($130,909.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $250.00 $25,000.00 $110.41 $11,041.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $950.00 $1,272,050.00 ($546.73) ($732,071.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $800,000.00 $800,000.00 $497,020.33 $497,020.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $80.00 $22,400.00 $33.80 $9,464.00CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $450,000.00 $450,000.00 $64,919.57 $64,919.57UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $50.00 $23,400.00 ($0.03) ($14.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $1.50 $7,500.00 ($0.90) ($4,500.00)MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $1,600,000.00 $1,600,000.00 $932,102.44 $932,102.44STRUCTURAL METAL0510.000

Page 83 of 112

Page 84: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LS 1 $373,581.61 $373,581.61 $400,000.00 $400,000.00 $26,418.39 $26,418.39METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $430,000.00 $430,000.00 $6,553.14 $6,553.14MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $36.50 $31,353.50 ($40.19) ($34,523.21)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $156.00 $8,736.00 ($52.03) ($2,913.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,500,000.00 $1,500,000.00 $300,000.00 $300,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $80,000.00 $80,000.00 ($25,475.83) ($25,475.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $5,000.00 $5,000.00 ($10,597.79) ($10,597.79)ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $950.00 $3,800.00 ($171.33) ($685.32)METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $1,200.00 $16,800.00 ($6,694.04) ($93,716.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 84 of 112

Page 85: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LS 1 $8,526.26 $8,526.26 $20,000.00 $20,000.00 $11,473.74 $11,473.74COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $75,000.00 $75,000.00 $52,909.97 $52,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $20,000.00 $20,000.00 $15,219.82 $15,219.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $3,000.00 $3,000.00 $366.29 $366.29TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $2,200.00 $2,200.00 ($8,988.02) ($8,988.02)ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $4,500.00 $4,500.00 ($10,556.79) ($10,556.79)RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $100,000.00 $100,000.00 $54,897.39 $54,897.39PAINTING0990.000

EA 4 $95.75 $383.00 $150.00 $600.00 $54.25 $217.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.00 $880.00 ($0.35) ($154.00)4" REFLECTORIZED WHITE LINE1040.700

Page 85 of 112

Page 86: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

LS 1 $19,461.89 $19,461.89 $12,000.00 $12,000.00 ($7,461.89) ($7,461.89)SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $6,000.00 $6,000.00 ($8,021.54) ($8,021.54)LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $25,000.00 $25,000.00 ($50,351.74) ($50,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $7,500.00 $7,500.00 $3,230.44 $3,230.44TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $125,000.00 $125,000.00 $52,555.40 $52,555.40MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $500,000.00 $500,000.00 $42,464.45 $42,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $250,000.00 $250,000.00 ($55,259.34) ($55,259.34)PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $250,000.00 $250,000.00 $98,062.65 $98,062.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $2.00 $600.00 ($12.23) ($3,669.00)ACTIVATED CARBON1597.422

Page 86 of 112

Page 87: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

DY 60 $213.48 $12,808.80 $500.00 $30,000.00 $286.52 $17,191.20GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $1,000,000.00 $1,000,000.00 ($524,304.16) ($524,304.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $25,000.00 $25,000.00 $2,691.73 $2,691.73ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $700,000.00 $700,000.00 ($283,596.90) ($283,596.90)TRACTION POWER WORK1696.113

$15,429,110.71 ($566,448.29)$15,995,559.00Total Estimate Contract Base Bid:

Page 87 of 112

Page 88: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $500,000.00 $500,000.00 $102,042.65 $102,042.65ALTERNATE NO. 10001.100

$500,000.00 $102,042.65$397,957.35Subtotal Alternate # A01:

Page 88 of 112

Page 89: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $750,000.00 $750,000.00 $246,767.37 $246,767.37ALTERNATE NO. 20001.200

$750,000.00 $246,767.37$503,232.63Subtotal Alternate # A02:

Page 89 of 112

Page 90: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

F

11/27/2007

WALSH CONSTRUCTION CO. OF ILLINOIS

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $100,000.00 $100,000.00 $56,985.10 $56,985.10ALTERNATE NO. 30001.300

$100,000.00 $56,985.10$43,014.90Subtotal Alternate # A03:

$16,779,110.71 ($160,653.17)$16,939,763.88Contract Total - Base Bid and Alternates:

Page 90 of 112

Page 91: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

FP 1 $42,736.21 $42,736.21 $42,736.21 $42,736.21 $0.00 $0.00CPM SCHEDULING0110.002

LS 1 $210,178.08 $210,178.08 $50,000.00 $50,000.00 ($160,178.08) ($160,178.08)FIELD OFFICE - TRAILER0130.100

LS 1 $183,908.55 $183,908.55 $240,000.00 $240,000.00 $56,091.45 $56,091.45MAINTENANCE FACILITY0130.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00ROADWAY MAINTENANCE0130.300

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00TRAFFIC OFFICERS SERVICES0130.430

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00LICENSED SITE PROFESSIONALSERVICES

0160.091

LS 1 $13,554.15 $13,554.15 $200,000.00 $200,000.00 $186,445.85 $186,445.85CLEARING OF SITE0210.000

LS 1 $643,796.35 $643,796.35 $300,000.00 $300,000.00 ($343,796.35) ($343,796.35)DEMOLITION AND SITEPREPARATION

0210.150

SF 5,000 $5.84 $29,200.00 $20.00 $100,000.00 $14.16 $70,800.00PATCHING AND REPAIRING0211.003

Page 91 of 112

Page 92: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LS 1 $1,148,821.95 $1,148,821.95 $2,925,000.00 $2,925,000.00 $1,776,178.05 $1,776,178.05CONTROLLED DEMOLITION0211.005

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00SITE UTILITIES0211.491

LS 1 $92,238.34 $92,238.34 $71,000.00 $71,000.00 ($21,238.34) ($21,238.34)REMOVE LEAD PAINT0212.153

AL 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $0.00 $0.00ASBESTOS REMOVAL0212.174

AL 1 $10,000.00 $10,000.00 $10,000.00 $10,000.00 $0.00 $0.00RODENT CONTROL0213.201

TN 4,545 $79.52 $361,418.40 $30.00 $136,350.00 ($49.52) ($225,068.40)DISPOSE OF CONTAMINATED SOILAT IN-STATE LINED LANDFILL

0221.345

TN 1,694 $133.57 $226,267.58 $50.00 $84,700.00 ($83.57) ($141,567.58)DISPOSE OF CONTAMINATED SOILIN-STATE RECYCLING FACILITY

0221.347

TN 114 $322.28 $36,739.92 $80.00 $9,120.00 ($242.28) ($27,619.92)CONTAMINATED SOIL DISPOSAL ATNON-RCRA OUT-OF-STATE LANDFILL

0221.349

CY 3,500 $56.11 $196,385.00 $70.00 $245,000.00 $13.89 $48,615.00UNCLASSIFIED EXCAVATION0222.003

Page 92 of 112

Page 93: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

CY 440 $15.17 $6,674.80 $39.00 $17,160.00 $23.83 $10,485.20TRENCH EXCAVATION - CLASS B0222.151

TN 228 $269.20 $61,377.60 $200.00 $45,600.00 ($69.20) ($15,777.60)DISPOSE OF RCRA HAZARDOUSWASTE

0222.365

SF 1,000 $33.63 $33,630.00 $20.00 $20,000.00 ($13.63) ($13,630.00)SUPPORT OF EXCAVATION0222.416

CY 100 $28.05 $2,805.00 $310.00 $31,000.00 $281.95 $28,195.00TEST PITS0222.442

GL 10,000 $0.72 $7,200.00 $3.00 $30,000.00 $2.28 $22,800.00DISPOSE OF CONTAMINATEDGROUNDWATER

0222.460

CY 300 $23.64 $7,092.00 $40.00 $12,000.00 $16.36 $4,908.00ORDINARY BORROW0222.501

CY 763 $27.00 $20,601.00 $50.00 $38,150.00 $23.00 $17,549.00GRAVEL BORROW0222.504

EA 3 $347.27 $1,041.81 $600.00 $1,800.00 $252.73 $758.19FRAMES AND GRATES OR COVERSREMOVE AND RESET

0222.542

TN 323 $53.15 $17,167.45 $38.00 $12,274.00 ($15.15) ($4,893.45)CRUSHED STONE FORDRAIN REVET

0222.603

Page 93 of 112

Page 94: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

TN 120 $31.67 $3,800.40 $56.00 $6,720.00 $24.33 $2,919.60STONE BALLAST0222.614

TN 179 $57.31 $10,258.49 $40.00 $7,160.00 ($17.31) ($3,098.49)DENSE GRADED CRUSHED STONE0222.619

TN 188 $17.00 $3,196.00 $50.00 $9,400.00 $33.00 $6,204.00CRUSHED STONE - BACKFILL0222.629

SY 2,462 $6.76 $16,643.12 $2.50 $6,155.00 ($4.26) ($10,488.12)FILTER FABRIC0227.007

LB 17,100 $2.74 $46,854.00 $0.50 $8,550.00 ($2.24) ($38,304.00)CALCIUM CHLORIDE FORDUST CONTROL

0227.100

EA 6 $565.99 $3,395.94 $1,100.00 $6,600.00 $534.01 $3,204.06BOLLARDS0234.195

CY 848 $1,843.87 $1,563,601.76 $600.00 $508,800.00 ($1,243.87) ($1,054,801.76)CAISSONS0235.102

LF 715 $17.40 $12,441.00 $105.00 $75,075.00 $87.60 $62,634.0012" CORRUGATED POLYETHYLENEPIPE

0251.093

LF 20 $35.67 $713.40 $780.00 $15,600.00 $744.33 $14,886.608" PVC PIPE0251.591

Page 94 of 112

Page 95: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LF 20 $123.85 $2,477.00 $135.00 $2,700.00 $11.15 $223.006" CAST-IRON PIPE0251.640

LF 100 $282.66 $28,266.00 $135.00 $13,500.00 ($147.66) ($14,766.00)8" CAST IRON PIPE - CLASS 500251.708

LF 188 $50.87 $9,563.56 $137.00 $25,756.00 $86.13 $16,192.448" DUCTILE IRON PIPE0251.770

LF 84 $74.36 $6,246.24 $512.00 $43,008.00 $437.64 $36,761.76TRENCH DRAIN0253.948

EA 2 $39,280.17 $78,560.34 $48,250.00 $96,500.00 $8,969.83 $17,939.66OIL/WATER SEPARATOR0255.070

EA 2 $406.77 $813.54 $460.00 $920.00 $53.23 $106.46CLEANOUTS0255.129

TN 24 $259.35 $6,224.40 $200.00 $4,800.00 ($59.35) ($1,424.40)BITUMINOUS CONCRETE BERM0261.140

SY 250 $23.49 $5,872.50 $60.00 $15,000.00 $36.51 $9,127.50REPAIR EXISTING BITUMINOUSCONCRETE PAVEMENT

0261.146

TN 148 $93.06 $13,772.88 $100.00 $14,800.00 $6.94 $1,027.12CLASS I, BITUMINOUS CONCRETEPAVEMENT, TYPE I-1 BINDERCOURSE

0261.197

Page 95 of 112

Page 96: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

TN 148 $101.52 $15,024.96 $100.00 $14,800.00 ($1.52) ($224.96)CLASS I, BITUMINOUS CONCRETEPAVEMENT TYPE I-1,TOP COURSE

0261.200

TN 332 $61.42 $20,391.44 $100.00 $33,200.00 $38.58 $12,808.56CLASS I BITUMINOUS CONCRETEPAVEMENT TYPE I-1BASE COURSE

0261.201

CY 61 $1,194.27 $72,850.47 $450.00 $27,450.00 ($744.27) ($45,400.47)CONCRETE SIDEWALKS0263.160

LF 390 $38.32 $14,944.80 $54.00 $21,060.00 $15.68 $6,115.2072" CHAIN LINK FENCE0271.700

SY 2,118 $1.12 $2,372.16 $1.75 $3,706.50 $0.63 $1,334.34SEEDING0282.150

LF 310 $5.31 $1,646.10 $8.50 $2,635.00 $3.19 $988.90BALES OF HAYFOR EROSION CONTROL

0282.211

LF 310 $5.73 $1,776.30 $6.00 $1,860.00 $0.27 $83.70SILT FENCE FOR EROSION CONTROL0282.220

CY 100 $28.46 $2,846.00 $58.00 $5,800.00 $29.54 $2,954.00TOPSOIL0282.256

LS 1 $38,532.35 $38,532.35 $25,500.00 $25,500.00 ($13,032.35) ($13,032.35)PLANTING0284.145

Page 96 of 112

Page 97: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

EA 3 $86,506.15 $259,518.45 $65,500.00 $196,500.00 ($21,006.15) ($63,018.45)RUBBER GRADE CROSSING0290.022

LF 395 $525.17 $207,442.15 $350.00 $138,250.00 ($175.17) ($69,192.15)RAILROAD TRACK CONSTRUCTION0290.100

LF 180 $51.79 $9,322.20 $18.00 $3,240.00 ($33.79) ($6,082.20)RESURFACING AND ALIGNMENT0290.108

LF 395 $51.79 $20,457.05 $33.00 $13,035.00 ($18.79) ($7,422.05)SURFACE AND ALIGN TRACK0290.260

LF 1,181 $57.71 $68,155.51 $75.00 $88,575.00 $17.29 $20,419.49DISMANTLE AND REMOVE TRACK0290.904

EA 1 $125,183.00 $125,183.00 $145,000.00 $145,000.00 $19,817.00 $19,817.00SPECIAL TRACKWORK -200' RADIUS TURNOUTFURNISH AND INSTALL

0291.269

LF 69 $504.44 $34,806.36 $230.00 $15,870.00 ($274.44) ($18,936.36)RESTRAINING RAIL0291.400

EA 4 $504.44 $2,017.76 $1,000.00 $4,000.00 $495.56 $1,982.24INSULATED JOINTS0291.800

LF 395 $340.37 $134,446.15 $800.00 $316,000.00 $459.63 $181,553.85TRACK IN CONCRETE FLOOR0292.010

Page 97 of 112

Page 98: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LF 430 $504.44 $216,909.20 $210.00 $90,300.00 ($294.44) ($126,609.20)PIT TRACK0292.020

CY 100 $139.59 $13,959.00 $215.00 $21,500.00 $75.41 $7,541.00CAST-IN-PLACE PIPE ENCASEMENT0329.908

CY 1,339 $1,496.73 $2,004,121.47 $950.00 $1,272,050.00 ($546.73) ($732,071.47)4000 PSI CONCRETE0330.057

LS 1 $302,979.67 $302,979.67 $475,000.00 $475,000.00 $172,020.33 $172,020.33PRECAST CONCRETE PANELS0341.000

SY 280 $46.20 $12,936.00 $48.00 $13,440.00 $1.80 $504.00CLEAN AND RESTORE CONCRETE0370.100

LS 1 $385,080.43 $385,080.43 $220,000.00 $220,000.00 ($165,080.43) ($165,080.43)UNIT MASONRY0420.000

SF 468 $50.03 $23,414.04 $50.00 $23,400.00 ($0.03) ($14.04)MASONRY RESTORATION0420.102

SF 5,000 $2.40 $12,000.00 $7.00 $35,000.00 $4.60 $23,000.00MASONRY ACID CLEANING,AS REQUIRED

0420.122

LS 1 $667,897.56 $667,897.56 $950,000.00 $950,000.00 $282,102.44 $282,102.44STRUCTURAL METAL0510.000

Page 98 of 112

Page 99: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LS 1 $373,581.61 $373,581.61 $325,000.00 $325,000.00 ($48,581.61) ($48,581.61)METAL DECKING0530.000

LS 1 $423,446.86 $423,446.86 $625,000.00 $625,000.00 $201,553.14 $201,553.14MISCELLANEOUS METALS0550.000

SY 859 $76.69 $65,876.71 $40.00 $34,360.00 ($36.69) ($31,516.71)WATERPROOFING0710.050

SY 56 $208.03 $11,649.68 $160.00 $8,960.00 ($48.03) ($2,689.68)CEMENTITIOUS WATERPROOFING0718.004

LS 1 $1,200,000.00 $1,200,000.00 $1,600,000.00 $1,600,000.00 $400,000.00 $400,000.00BUILT-UP BITUMINOUS ROOFING- CARHOUSE

0751.010

LS 1 $105,475.83 $105,475.83 $42,500.00 $42,500.00 ($62,975.83) ($62,975.83)CAULKING AND SEALANTS- R.T. SHOP

0790.001

LS 1 $15,597.79 $15,597.79 $33,000.00 $33,000.00 $17,402.21 $17,402.21ELASTOMERIC EXPANSION JOINT0790.101

EA 4 $1,121.33 $4,485.32 $2,600.00 $10,400.00 $1,478.67 $5,914.68METAL DOORS AND FRAMES0810.002

EA 14 $7,894.04 $110,516.56 $2,700.00 $37,800.00 ($5,194.04) ($72,716.56)HOLLOW METAL DOORS ANDFRAMES

0811.002

Page 99 of 112

Page 100: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LS 1 $8,526.26 $8,526.26 $22,500.00 $22,500.00 $13,973.74 $13,973.74COILING DOORS AND GRILLES0833.000

LS 1 $22,090.03 $22,090.03 $64,000.00 $64,000.00 $41,909.97 $41,909.97OVERHEAD DOORS0836.000

LS 1 $4,780.18 $4,780.18 $23,000.00 $23,000.00 $18,219.82 $18,219.82GYPSUM DRYWALL0925.000

LS 1 $2,633.71 $2,633.71 $5,200.00 $5,200.00 $2,566.29 $2,566.29TILE WORK0930.000

LS 1 $11,188.02 $11,188.02 $14,000.00 $14,000.00 $2,811.98 $2,811.98ACOUSTICAL PANELS0950.005

LS 1 $15,056.79 $15,056.79 $16,500.00 $16,500.00 $1,443.21 $1,443.21RESILIENT FLOOR AND BASE0964.990

LS 1 $45,102.61 $45,102.61 $140,000.00 $140,000.00 $94,897.39 $94,897.39PAINTING0990.000

EA 4 $95.75 $383.00 $300.00 $1,200.00 $204.25 $817.00FIRE EXTINGUISHERS1025.100

LF 440 $2.35 $1,034.00 $2.50 $1,100.00 $0.15 $66.004" REFLECTORIZED WHITE LINE1040.700

Page 100 of 112

Page 101: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

LS 1 $19,461.89 $19,461.89 $39,000.00 $39,000.00 $19,538.11 $19,538.11SIGNAGE1042.012

LS 1 $14,021.54 $14,021.54 $24,000.00 $24,000.00 $9,978.46 $9,978.46LOCKERS AND BENCHES1050.151

LS 1 $75,351.74 $75,351.74 $32,000.00 $32,000.00 ($43,351.74) ($43,351.74)MESH PARTITIONS1053.000

LS 1 $4,269.56 $4,269.56 $1,500.00 $1,500.00 ($2,769.56) ($2,769.56)TOILET ACCESSORIES1080.000

LS 1 $72,444.60 $72,444.60 $90,000.00 $90,000.00 $17,555.40 $17,555.40MECHANICAL DEMOLITION1500.440

LS 1 $457,535.55 $457,535.55 $625,000.00 $625,000.00 $167,464.45 $167,464.45MECHANICAL WORK1500.500

LS 1 $305,259.34 $305,259.34 $1,100,000.00 $1,100,000.00 $794,740.66 $794,740.66PLUMBING1501.000

LS 1 $151,937.35 $151,937.35 $250,000.00 $250,000.00 $98,062.65 $98,062.65FIRE PROTECTION1502.000

LB 300 $14.23 $4,269.00 $3.00 $900.00 ($11.23) ($3,369.00)ACTIVATED CARBON1597.422

Page 101 of 112

Page 102: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

DY 60 $213.48 $12,808.80 $100.00 $6,000.00 ($113.48) ($6,808.80)GROUNDWATER TREATMENTSYSTEM OPERATION

1597.525

LS 1 $1,524,304.16 $1,524,304.16 $1,200,000.00 $1,200,000.00 ($324,304.16) ($324,304.16)ELECTRICAL WORK1600.500

LS 1 $22,308.27 $22,308.27 $6,000.00 $6,000.00 ($16,308.27) ($16,308.27)ELECTRICAL SNOW MELTINGSYSTEM

1683.000

LS 1 $983,596.90 $983,596.90 $1,065,000.00 $1,065,000.00 $81,403.10 $81,403.10TRACTION POWER WORK1696.113

$17,174,025.71 $1,178,466.71$15,995,559.00Total Estimate Contract Base Bid:

Page 102 of 112

Page 103: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

Alternate #A01 Line Items

LS 1 $397,957.35 $397,957.35 $660,000.00 $660,000.00 $262,042.65 $262,042.65ALTERNATE NO. 10001.100

$660,000.00 $262,042.65$397,957.35Subtotal Alternate # A01:

Page 103 of 112

Page 104: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

Alternate #A02 Line Items

LS 1 $503,232.63 $503,232.63 $650,000.00 $650,000.00 $146,767.37 $146,767.37ALTERNATE NO. 20001.200

$650,000.00 $146,767.37$503,232.63Subtotal Alternate # A02:

Page 104 of 112

Page 105: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

Line Item Description Unit Unit Price Total PriceQuantity Total PriceUnit PriceTotal PriceUnit Price

Contract S10CN02

VarianceBidderEngineer

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder:

DMJM+HARRIS, INC(formerly DMJM)

EN Bidder:

Firm Name:

Bid Date:

G

11/27/2007

J.F. WHITE CONTRACTING CO.

Alternate #A03 Line Items

LS 1 $43,014.90 $43,014.90 $400,000.00 $400,000.00 $356,985.10 $356,985.10ALTERNATE NO. 30001.300

$400,000.00 $356,985.10$43,014.90Subtotal Alternate # A03:

$18,884,025.71 $1,944,261.83$16,939,763.88Contract Total - Base Bid and Alternates:

Page 105 of 112

Page 106: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

G

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: J.F. WHITE CONTRACTING CO.

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $17,174,025.71 ($1,178,466.71)

Total Type Alternate group 01 - not in bid total = $397,957.35 $660,000.00 ($262,042.65)

Total Type Alternate group 02 - not in bid total = $503,232.63 $650,000.00 ($146,767.37)

Total Type Alternate group 03 - not in bid total = $43,014.90 $400,000.00 ($356,985.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $18,884,025.71 ($1,944,261.83)

Page 106 of 112

Page 107: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

F

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: WALSH CONSTRUCTION CO. OF ILLINOIS

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $15,429,110.71 $566,448.29

Total Type Alternate group 01 - not in bid total = $397,957.35 $500,000.00 ($102,042.65)

Total Type Alternate group 02 - not in bid total = $503,232.63 $750,000.00 ($246,767.37)

Total Type Alternate group 03 - not in bid total = $43,014.90 $100,000.00 ($56,985.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $16,779,110.71 $160,653.17

Page 107 of 112

Page 108: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

E

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: J & J CONTRACTORS, INC.

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $15,681,599.21 $313,959.79

Total Type Alternate group 01 - not in bid total = $397,957.35 $410,000.00 ($12,042.65)

Total Type Alternate group 02 - not in bid total = $503,232.63 $450,000.00 $53,232.63

Total Type Alternate group 03 - not in bid total = $43,014.90 $220,000.00 ($176,985.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $16,761,599.21 $178,164.67

Page 108 of 112

Page 109: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

D

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: BARLETTA HEAVY DIVISION, INC.

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $15,149,500.00 $846,059.00

Total Type Alternate group 01 - not in bid total = $397,957.35 $320,000.00 $77,957.35

Total Type Alternate group 02 - not in bid total = $503,232.63 $630,000.00 ($126,767.37)

Total Type Alternate group 03 - not in bid total = $43,014.90 $75,000.00 ($31,985.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $16,174,500.00 $765,263.88

Page 109 of 112

Page 110: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

C

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: W.T. RICH COMPANY, INC.

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $14,981,255.21 $1,014,303.79

Total Type Alternate group 01 - not in bid total = $397,957.35 $353,920.00 $44,037.35

Total Type Alternate group 02 - not in bid total = $503,232.63 $399,537.60 $103,695.03

Total Type Alternate group 03 - not in bid total = $43,014.90 $76,160.00 ($33,145.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $15,810,872.81 $1,128,891.07

Page 110 of 112

Page 111: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

B

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: McCOURT CONSTRUCTION CO., INC.

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $14,669,109.21 $1,326,449.79

Total Type Alternate group 01 - not in bid total = $397,957.35 $346,000.00 $51,957.35

Total Type Alternate group 02 - not in bid total = $503,232.63 $580,000.00 ($76,767.37)

Total Type Alternate group 03 - not in bid total = $43,014.90 $215,000.00 ($171,985.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $15,810,109.21 $1,129,654.67

Page 111 of 112

Page 112: Page 1 of 112 - Massachusetts Bay Transportation Authority · 2019. 7. 2. · Engineer Bidder Variance Massachusetts Bay Transportation Authority Capital Management System Comparison

S10CN02

Massachusetts Bay Transportation Authority

Capital Management System

Comparison of Bids

Report ID:

Date/Time:

CMS-BM-003

Firm Name:

Bidder: EN Bidder:

Bid Date:

A

11/27/2007

DMJM+HARRIS, INC(formerly DMJM)

ORIENT HEIGHTS MAINTENANCE FACILITY,READVERTISEMENT -- PHASE II, EAST BOSTON

Contract

Firm Name: S&R CONSTRUCTION CO., INC.,dba S&RCONSTRUCTION ENTERPRISES

Engineer Bidder Variance

Total Type Basic = $15,995,559.00 $12,997,822.00 $2,997,737.00

Total Type Alternate group 01 - not in bid total = $397,957.35 $254,000.00 $143,957.35

Total Type Alternate group 02 - not in bid total = $503,232.63 $337,560.00 $165,672.63

Total Type Alternate group 03 - not in bid total = $43,014.90 $101,200.00 ($58,185.10)

Contract Total - Base Bid and Alternates: $16,939,763.88 $13,690,582.00 $3,249,181.88

Page 112 of 112