![Page 1: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/1.jpg)
ATTACHMENT
G
![Page 2: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/2.jpg)
ADVISORY BOARD MEETING
COMMUNITY REDEVELOPMENT AGENCY
JULY 14 2009
RIVERSIDE PARK WEST DOCK REPAIR
SUMMARY
Approximately 2 months ago the dock located at Riverside Park West was demolished
by vandals Due to agenda deadlines we were unable to place the item on last months
agenda Mr Seger Deputy Director Public Works Parks Recreation and Public
Buildings has provided 3 quotes for work to be done to repair the dock Quotes and email
correspondence is attached for your review
Greene Marine 885000Custom Dock Davit 1029000Duncan Seawall Dock Boat Lift LLC 1354400
Mr Segersrecommendation is Greene Marine
Discussions had begun with Finance to determine the best budget line to take the money
This request appears to be a good allowable use of CRA funds Pursuant to our adopted
plan it improves the physical image within the CRA District strengthens downtown as a
multiusecenter and strengthens the citys contribution to the well being of the
community Please note that the doc has been temporarily secured with wooden
barricades to warn visitors ofthe potential danger
REQUIRED ACTION The Advisory Board should make a recommendation to the
CRA Board as to whether or not to approve expenditures for repair of the Riverside
Park West Dock Additional consideration should be given to recommend to the
CRA Board for a budget adjustment to move approved funds within the CRA
budget from one budget line to another if necessary
![Page 3: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/3.jpg)
Page 1 of 1
Beverly Minnix
From Tanya Lukowiak
Sent Monday June 08 2009 816AM
To Geoff SegerCc Beverly Minnix
Subject RE Riverside Park West
Yes I have been working with matt m to allocate that budgeted money thatsa good allowable use It
improves the physical image within the district strengthens downtown as a multiuse center and
strengthens the cityscontribution to the wellbeing of the community
Remember to give atimecertain for the quotes
t
From Geoff SegerSent Friday June 05 2009 235 PM
To Tanya Lukowiak
Cc Allen TusingSubject Riverside Park West
Tanya about a month ago the dock at Riverside Park was demolished by vandals the whole thing was in
the river and now the area is risk problem to the public
I am getting quotes from contractors for the needed repairs and to date the best quote is from Greene
Marine Construction for885000
Is this an area where we could utilize CRA funds for the repairs
Geoffrey T SegerDeputy Director Public Works
Parks Recreation and Public BuildingsCity of Palmetto Florida
Phone 7212138Fax 7212139
gseercrpahnettoflork
712009
![Page 4: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/4.jpg)
1a 27 09 0147p
ii
Trevor or Sharon Greene 9417228982 p1
GREETEMARINE CONSTRUCfiION INC
4sas 9TH sT E
ELLENTON FL 34222
941 7228982
May 3 2009
Attn Mrs Peggy MartinVia EmailFax
City of Palmetto pmartinpalrnettoflorg7212139Public Works Dept
Re Dock ReconstructionRegatta Point
Mrs Martin
We are pleased to submit this proposal for the dock work at the above referenced
location in accordance with our previous discussion
For a fee of 545000we propose to remove the existing decking and
framework and reconstruct it to the same dimensions All lumber will be 3x8
material 1 grade with a 25 CCA marine treatment and will be secured with 58
galy thru bolts The decking will be 2x6 1 grade and will be attached with 3
stainless steel deck screws The dock pilings will be left and reused A two rung
handrail wilt be constructed around the entire outer edge of the dock It will
consist of 2x6 material
Should you wish to upgrade to composite decking and railing material we can do
so for an additional 240000
![Page 5: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/5.jpg)
May 27 09 0147p Trevor or Sharon Greene 9417228982 p2
For an additional fee of 340000we can make the dock a full circle This will
require the installation of more pilings framework decking and labor
This price does not include any permitting fees Nor does it include any water or
electrical lines to the dock or any additional engineering surveying or permitting
which cannot be known at this time
We hope the above meets with your approval and look forward to working with
you on this project Your signature below will serve as our notice to proceed with
the permitting process
SincerelyGreene Marine Const lnc
Trevor Greene
President 941 8125288
Accepted By
Date
PS
Please indicate the options you choose
![Page 6: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/6.jpg)
s1y04 09 0735a Trevor or Sharon Greene 9417228982 p 1
GREENE MARINE CONSTRUCTION INC
4505 9TH ST E
ELLENTON FL 34222
941 7228982
May 3 2009
Attn Mrs Peggy Martin Via EmailJFax
City of Palmetto pmartin@palmettoflorg7212139Public Works Dept
Re Dock Reconstruction
Regatta Point
Mrs Martin
We are pleased to submit this proposal for the dock work at the above referenced
location in accordance with our previous discussion
For a fee of 545000we propose to remove the existing decking and
framework and reconstruct it to the same dimensions All lumber will be 3x8
material 1 grade with a 25 CCA marine treatment and will be secured with 58
galy thru bolts The decking will be 2x6 1 grade and will be attached with 3
stainless steel deck screws The dock pilings will be left and reused A two rung
handrail will be constructed around the entire outer edge of the dock It will
consist of 2x6 material
Should you wish to upgrade to composite decking and railing material we can do
so for an additional 240000
![Page 7: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/7.jpg)
Ma04 09 0736a Trevor or Sharon Greene 9417228982 p2
This price does not include any permitting fees Nor does it include any water or
electrical lines to the dock or any additional engineering surveying or permitting
which cannot be known at this time
We hope the above meets with your approval and look forward to working with
you on this project Your signature below will serve as our notice to proceed with
the permitting process
SincerelyGreene Marine Const Inc Accepted By
Trevor Greene
President 941 8125288Date
![Page 8: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/8.jpg)
06102009 1204 9419213702
S stomlnco1980 Hock
auit Inc
City ofPalmetto
G00 7 Street W
Palmetto FL 34221
Attn Peggy Martin
Re Riverside Parlc
CUSTOMDOCKDAVIT
Revised Proposaltune 9 2009
For the sum of1029000ten thousand two hundred ninety dollars we shall furnishlabor and materials to pErfonn the following
a mobilize to the site
PAGE 0209
b extract and haul ofisitc the existinglX12 dock platform and 112X2halfround upland deck platform and all piling
c reconstruct a new 12 roundhalfdcekhalfdock using 10 marine gradepiling and Premium 2X6No 1 grade pressurctreated MastEr Deck
with factory applied watcrrepellent and radiusmillededges attached withstainless steel screws
d construct 72linear feet of2X82X6pressttre treated top rail handrail
with2X4rrtidrail per attached HRI detail building code compliant
The following optionsupgrades shall be irtstallcd upon your request if you decide to add
any listed options to this contract please circle the option nwnber and initial beside it as
autltorizatiot
1 in lieu of the proposed pressure treated decking supply and install2X6
1Voisture Shield beveled edge cotnpositc attached with stainless steel screws
includes zmatching2X62X4cotmposite top rail handrail with2X4
midrailtlle additional cost will be295000
2 supply aad install 30X36 60 milhidensity polyethylene piling shields
using stainless steel ringsbank nails 3 oa center These shields preventwaterborne crustaceans from attaching to the piling which destroys the
stnictural integrity of the piling in as little as24yearsthe additional cost will be4000each
licensed Professional Marine Contractors
PO Box 21149 Sarasota Florida 34276 941 9231522
![Page 9: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/9.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0309
3 construct one pressure treated aluminumbracketedviewsaving benchthe additional cost will lie 4000per linear foot or for composite bench85000 per linear foot
All construction to be as per plans attached
T1tis proposal is contingent upon Customloek Davit Inc gaining sufficient access tothe job site for the aforcmettioned work
This proposal does not include the following1 the replacement ofsod ar landscape components2 the repair of subterranean utility lines or sprinkler systems
This proposal is contingent upon Custom Dock 8c Davit Inc obtaining all requiredpermits prior to the start ofconstruction If yvu are affected by bylaws or restrictions ofany local associations it will be your responsibility to inform us of such details prior tothe pcnxtitting process This proposal does not include permitengineeririg or surveyfees if required
All dock piles shall be installed to minimum penetration of6 feet and boatlift and mooringpiles to S feet or to impassable rock In the Event impassable rock is found at shallowerlevels rock punching ofthe piliaag shall be performed at the rate of25000 each
For your protection we meet all State and local licensing requirements We are insuredagainst liability property damage and all workers injury claims by both tlac State of Floridaand the Federal Government See attachment for additional policy information
Al worktnanshipand materials will be guaranteed to equal yr exceed industry standards
Upon completion all excess materials acid debris will be removed and the site will be leftin a clean condition It is ow sincere intention to perform this work its a manner thatcauses the least inconvenience to you and your guests
A partial paynitent of 20 oft11e contract price is to be paid upon the signing and
submitting of this proposal laytnent in full is to be received upon cvmlelivn ofcazstrrction We will honor this proposal for a period ofthirty days and it will becomeabinding contract with your signature Your signature will authonizc Custottt bock
Davit lnc to serve as your representative in any required permitting procedures
![Page 10: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/10.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0409
This work will commence within 10 to 30 working days aver our receipt of a signedcontract and authorized permit if required unless a different date has been discussed
ames H Smith nSenior Sales Representa iv
Custom Dock Davit Inc
Ticense A1087
Authorized Agcnt or
Property OwtaerDate of Execution
JHSmtn
![Page 11: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/11.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0509
Cstomilnco98
Dockavit Inc
Thank you for allowing Custorra Dock Davit Inc the opportunity to offer you abid for
your waterfront property project
We are a family owned and operated full service marine construction company operatingon the west coast of rlorida since 1980 With twentynineyears ofquality service andworkmanship we have developed an outstanding reputation for our professionalism In
addition we abide by all State and Federal laws providing all required insurance
coverage for our staff and customers
Custom Dock Davit Inc provides State Workers Compensation Fedora UnitedStates Longshoreman and Harbor Workers Insurance USLHanal Federal Jones Act
coverage Maritime work requires additiolal coverage wlxen performing work at on or
near the water and in navigable watezways State of Florida workersconpcnsationinsurance does not providetNX coverage in these areas These coverages are not onlyrequired by law but they protect XOU the homeowner from potential responsibility ifa
worker is injured on your property
To complete maritime coverage the Federal govenutentrequires Jones Act Insurance for
the crew of a vessel in anavigablc waterway Typically the need for this coverage is
when woxk is being performed on abarge in navigable water
Protect yourselfl Ask to sec a Certificate ofInsurance with USLBiH and Jones Act
coverage before you allowANX work on your waterfront property Without this
coverage you may be held pezsonally responsible Having a building permit does not
guarantee proper insurance coverage
T11is information is very important for you to know and understand A proof of insurance
certif rate is available upon request Should you have any questions or concerns pleosecall our office and we would be happy to discuss them with you
r
5
Licensed Professional Marine Contractors
P0 Box 21149 Sarasota Florida 34276 941 9231522
![Page 12: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/12.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0609
Is a
cz
Q wJa J
w
q
P p
wc w w
4 a O
4 rLQ d E 7
q
J
I I GJ
1 7
1 p
i
U U
fV
N Q
Jo j K
NN
r
yJ
N
uQ
it
oa
![Page 13: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/13.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0709
w z U
lj l7 oJOY a w vOZ QJ
n H D oC Qn
c a s rx Q a WQ
v pv OZ w wQinZZ ocL
c7 QI vi w x w d a OJ
a p N ate aoLL
o
i I iflilil IiII
W
wII aQWII
z Ez
z
o z
Q tj Zg w IIIVIOuI
z L V I I w
w
ww w
J 1
U pN
J Q N J W UIr Q U
Q G kpU
V
i V1 t Q W Nw w
aa Q i
d W w
Nw
wW 1 1T A I 4i VyO yyl I
w
w ww 1
1 W
VV N
N j rw Q
X wQ
Z
J N
Ia Q
iii
liN illi il0
m Illli IIliii
![Page 14: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/14.jpg)
06102009 1204 9419213702 CUSTOMDOCKDAVIT PAGE 0809
Na O Na
Paz NNz aZ b Ww
z
x4 N I W
W tn Q
a Q q0 u
a
Q OLr
U I
UZ W
NJ Jo0d QOW
ZQUh
a o OQU
x Zz o a z o Z
Q Qp vir o OQ Q p
00z 0 z w U
x Z u Z w JU1
Jv v N
lAx
Z J Z Q W WJQ
I n o O QU
Z in a wZ
X N h Or WV1 Q n a
QL
Qm N f N
Q ao W
Ox
0 rV v pQ
F Z
U
![Page 15: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/15.jpg)
i102009 1204 9419213702 CUSTOMDOCKDAUIT PAGE 0909
R 1
1
q a1Q Q kEVV w
z f
b q o
N c
i r
trys
mil
M1
N
![Page 16: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/16.jpg)
June 10 2009
The City of Palmetto
Ms Peggy Martin
910 16 Street West
Palmetto FL 34221
Ph 7212138Fx 7212139
Email pmartin@palmettoflorggseger cr palmettoflorg
Re Park Project at US 41 Bridge New Decking Arch Extension
Dear Ms Martin
Thank you for considering Duncan Seawall Dock and Boat Lift for the proposed new decking projectDuncan Seawall has been in business since 1979 and has maintained an excellent reputation fot qualityworkmanship Our proposal is as follows
Duncan Seawall Dock and Boat Lift will extract andtemove from site the existing pilings substructure
and decking Duncan Seawall will then construct a new pressure treated dock in the shape of an arch to
match the arch on the existing landward side approximately 22 wide and 11 out into the water The
dock will be supported by 6 new pilings and the existing concrete base The stringers and headers will
be constructed of2x 8 pressure treated timbers and will be bolted to each piling with 58diameter
stainless steel bolts The decking will consist of2x 6 1 grade 40ACQhand select Master Deck
timbers and will be attached with stainless steel screws two per connection All exposed edges ofcut
timbers including pilings headers and deck boards will be beveled to prevent splintering as well as for
appearance The hand rail which is included in this price will consist of a long lasting and aestheticallypleasing marine grade wood top plate and 2x 4pressure treated side and midrails The hand rail will
be segmented in 8 sections and supported by4x 4pressure treated posts
Fot the cost of 1354400
Price quoted does not include any permitting costs Duncan Seawall will help in obtaining the Manatee
County permit and theDEPandor Army Corps of Engineetsapprovals Manatee County will require a
copy of asurvey All costs including surveys andor engineering fees required by any ofthese agencieswill be the owners responsibility and added to the project total
All materials and workmanship are guaranteed to be as specified and the above work performed in a
professional mannerwith a 10down payment and 90Itre upon cottrpletiott ofthe above stated work
Fully Licensed Insured and Bonded
UNCANSEAWVALL DOCK BOAT LIFT LLC
![Page 17: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/17.jpg)
City ofPalmetto Page 2 of2 June 10 2009
Duncan Seawall Dock and Boat Lift is licensed A1346 and insured by Marine Underwriters for
General Liability Duncan Seawall carries the federally mandated USLHand Jones Act endorsement
6006F to insure customer protection in the unlikely event ofan injury Duncan Seawall is also an
Anchor Member in the Florida Marine Contractors Association
This contract incorporates Florida Statute 713015 relating to Florida construction lien laws as attached
In the event ofdefault ofcontract the prevailing party is entitled to receive reasonable and customary
court costs attorney fees and appellate fees if any in relation to the enforcement of contract Interest
will accrue at 18per annum on all accounts not paid within 10 days of project completion
Respectfiilly submitted
Mark Moore
NOTE Duncan Seawall may withdraw this proposal if not accepted within 30 days
ACCEPTANCE OF PROPOSAL
The above prices specifications and conditions are satisfactory and are hereby accepted Duncan Seawall
Dock and Boat Lift is authorized to do the work as specified above
Signature
Fully Licensed Insured and Bonded
Date
IUNCANSEAWALL DOCK BOAT LIFT LLC
![Page 18: ATTACHMENTdocsonline.palmettofl.org/palmetto/Agendas/cab/2009/071409/Tabg.… · Page 1 of 1 Beverly Minnix From Tanya Lukowiak Sent Monday June 08 2009 816AM To Geoff Seger Cc Beverly](https://reader033.vdocuments.site/reader033/viewer/2022042322/5f0bddcd7e708231d43299e4/html5/thumbnails/18.jpg)