PA Chemical FacilityDesign and Construction of Heavy Haul Bridge
November 17, 2016
Presented by: David J. Phelan, PEDaniel Noecker, PE
![Page 2: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/2.jpg)
Agenda
2
1. Project Overview2. Design Phase3. Construction Phase4. Lessons Learned5. Question and Answer
![Page 3: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/3.jpg)
Project Overview
3
![Page 4: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/4.jpg)
Project Overview
4
I-376PROPOSED
PA CHEMICAL FACILITY
![Page 5: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/5.jpg)
Project Overview• Relocate portion of SR 0018 south by 950 feet• New alignment cuts through mountainous terrain• Move 7M CY of excavated material to cap site• Aggressive design & construction schedule
5
![Page 6: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/6.jpg)
Project Overview (con’t)• Road/bridge necessary across existing SR 0018,
relocated CSX Railroad, and future Rail Lines– Coordination with PennDOT 11-0 (HOP) and CSX– Temporary condition – hauling operation– Permanent condition – site access road
6
![Page 7: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/7.jpg)
Project Overview
7
West Haul Bridge East Bridge
PROPOSED PA CHEMICAL FACILITY
Ohio River
![Page 8: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/8.jpg)
Project Overview
8
``
West Haul Bridge
![Page 9: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/9.jpg)
Design Phase
9
![Page 10: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/10.jpg)
Design Phase• Challenges
– Compressed design schedule– Short construction duration over Western PA winter– Heavy vehicular load– Impact load
10
![Page 11: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/11.jpg)
Design Phase• Design Criteria
– 75 year permanent design life– 2 year temporary design life (Hauling Operation)– Heavy Haul Considerations Alternatives
• Prefabricated temporary haul bridge• Permanent bridge• At-grade crossing• Conveyor belts
11
![Page 12: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/12.jpg)
Design Phase
12
• Design Criteria (con’t)– Bridge Geometry
• No skew• Three (3) – 115 ft Spans
• Two (2) – 30 ft Lanes• 66 ft Overall Width
![Page 13: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/13.jpg)
Design Phase• Design Criteria (con’t)
– Design Loads• Standard PennDOT/AASHTO Highway Loads• Caterpillar 777G (360 k GVW)
– Use of Standard PennDOT Details to the extent possible
13
![Page 14: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/14.jpg)
Design Phase
14
CAT 777G (360,000 lbs GVW) PHL-93 (72,000 lbs GVW)
![Page 15: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/15.jpg)
Design Phase• Proposed Bridge Superstructure
– P/S Concrete PA Bulb-Tee Beams 33x71.5• Simple Spans made Continuous for Live Load• Cost effective• Low future maintenance• Common bridge beam type in PA for these spans• Quicker fabrication turn-around time compared to steel
beams
15
![Page 16: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/16.jpg)
Design Phase• Proposed Bridge Superstructure (con’t)
– 10 Beams– 6.5’ Spacing– 10,000 psi concrete– 0.6” diameter strands
16
![Page 17: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/17.jpg)
Design Phase• Proposed Bridge Superstructure (con’t)
– Reinforced Concrete Deck & Approach Slabs• Special designs for heavier loads• 12” thick concrete deck with future LMC overlay• 30” thick approach slabs• Steel plate over neoprene strip seal
17
![Page 18: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/18.jpg)
Design Phase
18
![Page 19: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/19.jpg)
Design Phase• Proposed Bridge Superstructure (con’t)
19
– Enhanced AASHTO yield line analysis using assumed impact loads from design haul vehicle.• 8’-8” barrier and rail
combination• 14’-0” debris shield
![Page 20: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/20.jpg)
Design Phase• Proposed Bridge Superstructure (con’t)
20
– 3D Finite Element Analysis for Deck and Approach Slab Design• 12” Class AAAP
Concrete Deck• 30” Class AAAP
Concrete Approach Slab
![Page 21: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/21.jpg)
Design Phase• STAAD – Concrete Stress Output
21
![Page 22: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/22.jpg)
Design Phase• Proposed Bridge Substructure
– Pile Stub Abutments behind MSE Walls (BC-799M)• Cost effective• Quick construction• Minimize concrete pours in winter• Integral CIP concrete crash wall for adjacent railroad• Predrilling to eliminate pile downdrag
22
![Page 23: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/23.jpg)
Design Phase• Proposed Bridge Substructure (con’t)
– Wall Piers• Simple construction• Integral crash wall for adjacent railroad
23
![Page 24: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/24.jpg)
Design Phase• Structural Design Considerations
– Two 30-0” bi-directional loaded lanes, limiting only one CAT 777G in each lane.
– Pile design (S.O.L. 483-13-12) • 50 ksi pile capacity• Temporary haul condition – Full pile section• Permanent condition – Reduced section accounting for
1/16” loss due to corrosive soils
24
![Page 25: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/25.jpg)
Construction Phase
25
![Page 26: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/26.jpg)
Construction Phase• MSE Wall Embankment Fill
– Contract drawings specified AASHTO NO. 57– Standard PennDOT Special Provisions allow for varying
types of fill materials with up to 15% fines– Special provisions take precedence in hierarchy of
contract documents in case of a discrepancy– Contractor’s bid based on sand
26
![Page 27: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/27.jpg)
Construction Phase
27
![Page 28: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/28.jpg)
Construction Phase• Request to run larger equipment across bridge
– CAT 785C• 550 k GVW (compared to 360 k GVW for CAT 777G)• 50% heavier than CAT 777G design• Bridge did not rate
– Various additional equipment loads evaluated– Signs installed at bridge approaches
• One vehicle in each direction at a time (200’ spacing)• Limit equipment on bridge & speed to 15 MPH
28
![Page 29: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/29.jpg)
Construction Phase• Future Pipe Rack
– Additional 1.5 k/ft– Evaluate for final condition– Design modifications to accommodate
29
![Page 30: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/30.jpg)
Construction Phase
30
January 2016 Field Visit
West Haul BridgeOhio River I-376
![Page 31: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/31.jpg)
Construction Phase
31
January 2016 Field Visit
![Page 32: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/32.jpg)
Construction Phase
32
January 2016 Field Visit
![Page 33: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/33.jpg)
Construction Phase
33
March 2016 West Haul Bridge in Use
![Page 34: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/34.jpg)
Lessons Learned
34
![Page 35: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/35.jpg)
Lessons Learned• Review special requirements closely against
contract documents (MSE Fill)• Ensure design limitations are clear on plans• Consider modifying design criteria for temporary
conditions• Consider future potential uses and loadings
35
![Page 36: PA Chemical Facility - APC/PennDOT Fall Seminarapcfallseminar.com/wp-content/uploads/2016/11/STRUCTURES1_Phela… · Construction Phase • Request to run larger equipment across](https://reader030.vdocuments.site/reader030/viewer/2022021510/5aad9a3c7f8b9a693f8e9c89/html5/thumbnails/36.jpg)
www.jacobs.com | worldwideNovember 21, 2016© Copyright Jacobs
Questions and Answer