Gulf Cooperation Council Interconnection Authority GCCIA TRANSMISSION & DISTRIBUTION Engineer GCC Interconnection Project - Phase I P921 Site Acceptance Test Report MiCOM P921 27/59 Bay Ref: Substation: SUMMARY REVISION PAGES 1 2 1 PURPOSE OF TESTS 2 X 2 REFERENCE DOCUMENT 2 X 3 SCOPE 2 X 4 RELAY TERMINLOGY 3 X 5 TEST EQUIPMENT 3 X 6 PRE-REQUISTES 3 X 7 PROCEDURES 4 X 8 RECORD TEST SHEET 6 X 8.1 RELAY INFORMATION 8.2 VT DATA: 8.3 PRODUCT CHECKS 8.4 MEASURMENT VALUE TEST: 8.5 OVER VOLTAGE PROTECTION X 8.6 UNDER VOLTAGE PROTECTION 8.7 BINARY INPUT TEST : 8.8 BINARY OUTPUT TEST: 8.9 FIXED LED INDICATIONS TEST: 8.10 LED INDICATIONS TEST: 8.11 FINAL CHECK AREVA T&D GCCIA / SNCL Signature Signature Name Name Date Date Doc. No. REV-2 Page 1 of 16

Upload: samiahmedmansour

Post on 19-Nov-2015

8 views

Category:

Documents


0 download

DESCRIPTION

PROTECTION

TRANSCRIPT

1

Gulf Cooperation Council

Interconnection Authority

GCCIATRANSMISSION & DISTRIBUTION

Engineer

GCC Interconnection Project - Phase I

P921Site Acceptance Test Report

MiCOM P921

27/59Bay Ref:Substation:

SUMMARYREVISION

PAGES12

1PURPOSE OF TESTS2X

2REFERENCE DOCUMENT2X

3SCOPE2X

4RELAY TERMINLOGY 3X

5TEST EQUIPMENT3X

6PRE-REQUISTES3X

7PROCEDURES4X

8RECORD TEST SHEET6X

8.1 RELAY INFORMATION

8.2 VT DATA:

8.3 PRODUCT CHECKS

8.4 MEASURMENT VALUE TEST:

8.5 OVER VOLTAGE PROTECTIONX

8.6 UNDER VOLTAGE PROTECTION

8.7 BINARY INPUT TEST :

8.8 BINARY OUTPUT TEST:

8.9 FIXED LED INDICATIONS TEST:

8.10 LED INDICATIONS TEST:

8.11 FINAL CHECK

1 PURPOSE OF TESTSThe purpose of the tests is to check the full functionality of the protection relay.This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning procedures.This procedure does not intend to check all tripping matrix and PSL logic tests, this, when applicable, is described into a separate document, dedicated to the specific substation and feeder type.

2 REFERENCE DOCUMENTSDOCUMENTDOCUMENT REFERENCEVERSION/ DATEREMARKS

Protection Line Diagram

Schematic Drawing

Service Manual

Operation Manual

Protection Relay Coordination Principles

Relay setting Calculation

LED Display Configuration

3 SCOPE

Substation Name :-

Diameter:

Bay :

Panel Number :

Relay Denomination in Scheme

Scheme to be Checked Relay Functionality Test.

4 TERMINOLOGYCode ( ANSI) Terminology

27/59Over/Under Voltage Relay

5 TEST EQUIPMENT USED

Sl NoDescriptionMakeEquipment

Sl No.Calibration dateCalibration due date

1.Secondary Injection Kit

2.Multimeter

3.LaptopNA

Setting software

Type : MICOM S1 Studio

Version : 2.14

6 PRE - REQUISITES

PRE-REQUISITESREMARKS

All Safety Condition Are Ok

All Competent Personnel Available For The Test

Ac & Dc Supply Availability And Security

PPE Safety Available.

All Other Relevant Safety Instructions Been Followed

Coordination With Other Parties ( GIS, Transformer, Etc..)

7 TEST PROCEDURESThe following procedures are written for demonstrating the main protection functions of the P921 relay using an Omicron test set or similar. The tests do not test the boundaries of all available function characteristics. They do test that the function is operating at a point on one chosen characteristic. This document is to be referred to when performing commissioning tests in association with the commissioning section of the service manual.

NOTE :

All the Test are performed in the Test Switch.

Omicron CMC156 Test Equipment or Any Equivalent To Be Used..

7.1 Testing Over/Under Voltage function

Values to be measured:

1. stage (V>) or (V) or (tV) check:

1. If time delay (tV>) is short, gradually inject the voltage into the 3 phases up to the Stage value: tripping should occur for a voltage equal to the stage (V>) to within 2%

2. If time delay (tV>) is long, inject a voltage equal to 0.98x(V>) into the 3 phases and check that tripping does not occur. Then inject 1.2x(V>) and check that tripping occurs.

3. Gradually reduce the voltage on one of the phases and measure the value of the dropoff stage (V>) : the function must reset for a voltage less than or equal to the programmed hysteresis.7.1.2 Stage (V